Tuto Hec Ras

Embed Size (px)

Citation preview

  • 8/20/2019 Tuto Hec Ras

    1/10

    HEC-RAS LAB #1 Page 1 of 10TRIANGULAR OPEN CHANNEL

    Project F il e: LAB _1.PRJ

    HEC-RAS input files for example problem with single triangular open channel.Input data for open channel, copy cross sections, and interpolate cross sections..Generate program files, perform analysis and review output. Discussion of outputformats available from HEC-RAS (e.g., charts, tables, figures ).

    Problem Statement: One river reach (River TREEO , Reach Main ) dischargesinto a downstream basin outlet. The peak discharge has been calculated at 50 cfs,using other methodology for input into HEC-RAS. The reach is 800 feet long.

    To Do: Prepare a backwater profile analysis along the creek.

    NOTE:

    Projects consist of multiple files with multiple file extensions.

    Extension: File Description

    PRJ Main Project FileG** Geometry FileF** Steady Flow FileP** Plan FileR** Run File (contains results)O** Output File (used to create graphs and tables)

  • 8/20/2019 Tuto Hec Ras

    2/10

    HEC-RAS LAB #1 Page 2 of 10TRIANGULAR OPEN CHANNEL

    Lab #1 Steps to Develop the HEC-RAS Model:

    1. Open HEC-RAS

    Go to Windows Start , Programs , HEC , and click on the HEC-RAS icon.

    2. Enter Project InformationSelect File , New Project

    Create Directory : Problems (enter)Enter Short Project ID and Project Filename (extension is added automatically)Short Project ID: RAS LAB 1 Project Filename: RASLAB1 (extension is added automatically)

    Add Project Description: RAS LAB # 1 (optional information)

  • 8/20/2019 Tuto Hec Ras

    3/10

    HEC-RAS LAB #1 Page 3 of 10TRIANGULAR OPEN CHANNEL

    3. Begin building model.Start Geometric Data

    Select Edit , Geometric Data

    4. Add Reaches and Cross SectionsDraw Reach by Selecting the Reach Button (Click Once)

    Move over screen to draw reachDefine Reach proceeding from upstream to downstream

    With cursor in draw screen, click mouse button once to start Move cursor, click mouse button once to add point, change directionAt downsteam point, doubleclick mouse button to end

    Reaches

    CrossSections

  • 8/20/2019 Tuto Hec Ras

    4/10

    HEC-RAS LAB #1 Page 4 of 10TRIANGULAR OPEN CHANNEL

    4. continued

    Enter River Name (TREEO) and Reach Name (MAIN)

    5. Add Cross Sections to Reach

    Select Cross Section Button (click once)

    Select Options, Add a new Cross Section Enter Station Location ( 1.0 )and Cross Section Description

    (optional) Station must be numerical value and are defined asfollows:

    lower station downstream, higher stations upstream

  • 8/20/2019 Tuto Hec Ras

    5/10

    HEC-RAS LAB #1 Page 5 of 10TRIANGULAR OPEN CHANNEL

    Cross Section DataCross Sections typically enter left to right looking downstream

    Cross Section Stationing in left columnElevation Data in right column

    Triangular ChannelStation Elevation0 730 6 THIS IS A TRIANGULAR50 4 CHANNEL,10:1 SIDE SLOPE70 690 7

    Enter downstream reach lengths for main channel and overbanksNo downstream reach lengths for most downstream sectionFurthest downstream section defined by boundary conditions

    Add Manning’s n value for main channel and overbanks .04 .035 .04

    Outer Banks are outside Main Channel.Must correspond to a cross section station.Left Main Channel Bank at 30 Right Main Channel Bank at 70

    Repeat for additional Cross SectionsUse Add, Copy, Interpolate

    Copy - Define New Cross Section Name: 9.0Adjust Elevation: +4 feet (1/2 percent slope)Revise Downstream Reach Lengths: 800 feetExit Cross Section Data Editor

    Interpolate - On main geometry screenTools, XS Interpolation, Within a Reach

    Maximum distance: 100 feetInterpolate XSs, Close

    Interpolated Cross Sections have “*” by station name Interpolated Cross Sections can be made permanent byediting the name in the cross section editor andremoving the asterisk

  • 8/20/2019 Tuto Hec Ras

    6/10

    HEC-RAS LAB #1 Page 6 of 10TRIANGULAR OPEN CHANNEL

    SAVE GEOMETRIC DATA , file name automatically assigned

    6. Start Steady Flow Data

    Select Edit, Steady Flow Data

  • 8/20/2019 Tuto Hec Ras

    7/10

    HEC-RAS LAB #1 Page 7 of 10TRIANGULAR OPEN CHANNEL

    Enter the Flow for the River TREEO and Reach Main : 50 cfs(this is the flow at the upstream cross section of each)

    Enter Boundary ConditionsMost Downstream Channel

    - use Known Water Surface Elevation- Critical Depth, determined by size of channel- Normal Depth defined by channel shape, slope, and flow- Rating Curve (user defined)- HEC-RAS will normally set these automatically

    SAVE STEADY FLOW DATA , file name automatically assigned

    Normal Depth,slope = 0.005

  • 8/20/2019 Tuto Hec Ras

    8/10

    HEC-RAS LAB #1 Page 8 of 10TRIANGULAR OPEN CHANNEL

    7. Simulate Backwater Analysis

    Select Run , Simulate

    Select Geometry File: TREEO LAB 1Select Steady Flow File

    Save Steady Flow Analysis FileDescription: TREEO LAB 1 Short Form: LAB 1

    8. COMPUTEOptions within this segment allow for error checking, precision, etc.

    See FINISHED COMPUTATION screen for errors and warnings.Close Window

    EXIT STEADY FLOW ANALYSIS

  • 8/20/2019 Tuto Hec Ras

    9/10

    HEC-RAS LAB #1 Page 9 of 10TRIANGULAR OPEN CHANNEL

    9. View Results

    View GraphicsCross SectionsProfilesRating Curves (multiple profiles)X-Y-Z Perspective (3-D)

    View, X-Y-Z Perspective Plot

    View, Water Surface Profile

    print using File, Print from screen or copy to Windows clipboard

  • 8/20/2019 Tuto Hec Ras

    10/10

    HEC-RAS LAB #1 Page 10 of 10TRIANGULAR OPEN CHANNEL

    View TablesCross Sections/Culverts/BridgesProfile TableSummary Errors/Warnings

    print using File, Print from screen or copy to Windows clipboard

    Cross Section 2.0: Water Surface Elevation = 5.94 feet

    10. Generate Report - File, Generate - Select Filename

    SAVE PROJECT , file name assigned in step 1.