UCSD Final Report Isa

Embed Size (px)

Citation preview

  • 8/12/2019 UCSD Final Report Isa

    1/105

    STRUCTURAL SYSTEMS

    RESEARCH PROJECT

    Report No.

    SSRP- 11/07 FATIGUE TESTS OF WELDED CONNECTIONS

    IN CANTILEVERED STEEL SIGN STRUCTURES

    by

    HYOUNG-BO SIM

    CHIA-MING UANG

    Final Report Submitted to International Sign Association

    October 2011Department of Structural Engineering

    University of California, San Diego

    La Jolla, California 92093-0085

  • 8/12/2019 UCSD Final Report Isa

    2/105

    University of California, San Diego

    Department of Structural Engineering

    Structural Systems Research Project

    Report No. SSRP-11/07

    Fatigue Tests of Welded Connections in Cantilevered

    Steel Sign Structures

    by

    Hyoung-Bo Sim

    Postdoctoral Researcher

    Chia-Ming Uang

    Professor of Structural Engineering

    Final Report Submitted to International Sign Association

    Department of Structural EngineeringUniversity of California, San Diego

    La Jolla, California 92093-0085

    October 2011

  • 8/12/2019 UCSD Final Report Isa

    3/105

    i

    ACKNOWLEDGEMENTS

    Funding for this research was provided by the International Sign Association

    (ISA). We would like to thank Mr. Bill Dundas, ISA Director of Technical andRegulatory Affairs, and the ISA Mechanical and Structural Subcommittee, chaired by

    Mr. Wes Wilkens, for providing guidance in this research. We would also like to thank

    Mr. Jack Lester for preparing the specimen drawings and arranging the fabrication and

    shipping of most of the specimens. Additionally, we would like to thank Mr. Roy Flahive

    for coordinating efforts at the laboratory on test specimen preparation, repairs and

    inspections. Union Metal (Canton, OH) donated the tapered-pole specimen (A7) and Fyfe

    Company LLC (San Diego, CA) donated materials and services for the Fiber Reinforced

    Polymer (FRP) repair.

    The testing was conducted in the Charles Lee Powell Structural Components

    Laboratory at the University of California, San Diego. Assistance from the laboratory

    staff is much appreciated.

  • 8/12/2019 UCSD Final Report Isa

    4/105

    ii

    ABSTRACT

    Freestanding (cantilevered) steel sign structures have been widely used by

    commercial and retail business for many years. The actual probability of failure forcantilevered sign structures due to wind-induced vibration is relatively small. In this case,

    failure is defined as fatigue cracking which causes collapse or loss of a structures

    serviceability. While the majority of these structures have performed well in long-term

    use, however, some structures have been damaged or destroyed.

    This type of structure is flexible, has a low damping and, under certain

    circumstances, can be prone to fatigue-type cracking due to wind-induced vibration.

    Cracks at the sleeve connections, some resulting in sign failures, have been reported

    when the wind speed was significantly below that used in design. In connection with its

    ongoing efforts to support the safety and acceptability of signage products, the

    International Sign Association (ISA) made a decision to investigate potential remedies by

    sponsoring the tests described in this report.

    Fatigue tests of seventeen full-scale connection details were conducted to evaluate

    their relative fatigue resistance. Test specimens included four conventional (with or

    without a guide ring), five repaired (with various combinations of welded gussets, grout,

    steel cones or jackets and Fiber Reinforced Polymer composites), and eight alternative

    connection details for new construction.

    Testing demonstrated that conventional welded sleeve connections had a

    relatively low fatigue resistance. All four specimens showed the same cracking pattern as

    commonly observed in the field on damaged or failed structures. The use of a guide ring

    had a minimal effect on the fatigue resistance. After testing, the damaged conventional

    specimens were repaired with various schemes to evaluate their effectiveness.

    A gusset-repaired specimen also showed relatively low fatigue resistance. Steel-

    jacketed cement grouting, or the use of a welded steel cone above the upper ring,

    significantly improved the fatigue resistance at the most commonly observed failure

    location, although fatigue cracking later occurred at the next weak locations (i.e., the

    lower pipe-to-upper ring fillet weld and the slot welds, which also are prone to fatigue).

    Grouting the sleeve region or using welded patch plates did not improve the fatigue

  • 8/12/2019 UCSD Final Report Isa

    5/105

    iii

    resistance of the slot welds. An FRP-repair scheme for cracked slot welds effectively

    prevented further crack growth.

    Some promising alternative connections that can potentially be used for new

    construction were experimentally evaluated. A bolted match-plate connection performed

    relatively poorly. But a revised sleeve connection incorporating a one-sided, bottom-only

    fillet weld detail at the upper pipe-to-upper ring joint was effective in enhancing the

    fatigue performance compared to the conventional sleeve connections. To avoid cracking

    at slot welds, the use of grout between the pipes in the sleeve region significantly

    increased the fatigue resistance. Using a welded cone to provide a smooth transition

    between the pipes also showed improved performance. A tapered slip-joint connection,

    which requires no welded joints between the pipe sections, substantially outperformed all

    of the other specimens tested.

  • 8/12/2019 UCSD Final Report Isa

    6/105

    iv

    TABLE OF CONTENTS

    ACKNOWLEDGEMENTS....................................................................................................... i

    ABSTRACT ........................................................................................................................ ii

    TABLE OF CONTENTS......................................................................................................... iv

    LIST OF TABLES................................................................................................................... vi

    LIST OF FIGURES ................................................................................................................ vii

    1. INTRODUCTION........................................................................................................... 10

    1.1 Problem Statements ................................................................................................ 10

    1.2 Past Research .......................................................................................................... 10

    1.3 Objectives and Scope.............................................................................................. 13

    2. TEST PROGRAM........................................................................................................... 14

    2.1 Test Setup................................................................................................................ 14

    2.2 Test Matrix.............................................................................................................. 15

    2.3 Connection Details.................................................................................................. 16

    2.3.1 Conventional Welded Sleeve Connection Details ....................................... 16

    2.3.2 Repaired Connection Details ....................................................................... 19

    2.3.3 Alternative Connection Details.................................................................... 24

    2.4 Loading Scheme...................................................................................................... 27

    2.5 Instrumentation and Crack Inspections................................................................... 273. TEST RESULTS OF CONVENTIONAL CONNECTIONS ......................................... 29

    3.1 Introduction............................................................................................................. 29

    3.2 Conventional Connection Details without Guide Ring .......................................... 29

    3.2.1 Specimen C1 ................................................................................................ 29

    3.2.2 Specimen C2 ................................................................................................ 31

    3.3 Conventional Connection Details with Guide Ring................................................ 33

    3.3.1 Specimen C3 ................................................................................................ 33

    3.3.2 Specimen C4 ................................................................................................ 34

    3.4 Comparison of Test Results.................................................................................... 35

    4. TEST RESULTS OF REPAIRED CONNECTIONS ..................................................... 36

    4.1 Introduction............................................................................................................. 36

    4.2 Gusset Repair: Specimen R1 .................................................................................. 36

    4.3 Steel-Jacketed and Cement-Grouted Repair ........................................................... 38

  • 8/12/2019 UCSD Final Report Isa

    7/105

    v

    4.3.1 Introduction.................................................................................................. 38

    4.3.2 Specimen R2 ................................................................................................ 38

    4.3.3 Specimen R3 ................................................................................................ 44

    4.4 Steel Cone and Cement Grout Repair: Specimen R4 ............................................. 45

    4.5 FRP Repair: Specimen R5 ...................................................................................... 52

    4.6 Comparison of Test Results.................................................................................... 56

    5. TEST RESULTS OF ALTERNATIVE CONNECTIONS FOR NEW

    CONSTRUCTION .......................................................................................................... 58

    5.1 Modified Sleeve Connection Details ...................................................................... 58

    5.1.1 Specimen A1................................................................................................ 58

    5.1.2 Specimen A2................................................................................................ 64

    5.1.3 Specimen A3................................................................................................ 69

    5.1.4 Specimen A4................................................................................................ 75

    5.2 Cone Transition Connection Details....................................................................... 79

    5.2.1 Introduction.................................................................................................. 79

    5.2.2 Specimen A5................................................................................................ 79

    5.2.3 Specimen A6................................................................................................ 81

    5.3 Tapered Slip Joint: Specimen A7 ........................................................................... 82

    5.4 Bolted Match-Plate Connection: Specimen A8 ...................................................... 83

    6. ANALYSIS OF TEST RESULTS .................................................................................. 87

    6.1 Introduction............................................................................................................. 87

    6.2 Comparison of Fatigue Resistance.......................................................................... 88

    6.2.1 Specimens C1 to C4..................................................................................... 88

    6.2.2 Specimen R1 (Gusset-Repair)...................................................................... 91

    6.2.3 Specimens R2 and R4 (Grout- or Cone-Repair) .......................................... 91

    6.2.4 Specimens R5 (FRP-Repair)........................................................................ 92

    6.2.5 Specimens A1 and A2 (Modified Sleeve Connection) ................................ 92

    6.2.6 Specimens A3 and A4 (Modified Sleeve Connection) ................................ 93

    6.2.7 Specimens A5 and A6 (Cone Transition) .................................................... 93

    6.2.8 Specimen A7 (Tapered Slip-Joint)............................................................... 93

    6.2.9 Specimen A8 (Bolted Match-Plate Connection).......................................... 93

    7. SUMMARY AND CONCLUSIONS.............................................................................. 94

    REFERENCES ...................................................................................................................... 97

    APPENDIX A. APPLIED LOAD TIME HISTORY ............................................................. 98

  • 8/12/2019 UCSD Final Report Isa

    8/105

    vi

    LIST OF TABLES

    Table 2.1 Test matrix ........................................................................................................ 15

    Table 6.1 Detail category constant and threshold (AASHTO 2010) ................................ 90

  • 8/12/2019 UCSD Final Report Isa

    9/105

    vii

    LIST OF FIGURES

    Figure 1.1 Typical configuration of a sign structure......................................................... 12

    Figure 1.2 Assumed force transfer mechanism at sleeve connection (Jones 1998).......... 12

    Figure 1.3 Typical failure locations of sign structures ..................................................... 12Figure 1.4 Proposed connection details (Sim and Uang 2008)......................................... 13

    Figure 2.1 Test setup......................................................................................................... 14

    Figure 2.2 Overall configuration of test specimens.......................................................... 17

    Figure 2.3 Connection details of Specimens C1 to C4 ..................................................... 18

    Figure 2.4 Connection details of Specimen R1 ................................................................ 20

    Figure 2.5 Grout-repaired region of Specimens R2 to R4................................................ 20

    Figure 2.6 Connection details of Specimens R2 and R3 .................................................. 21

    Figure 2.7 Connection details of Specimen R4 ................................................................ 22

    Figure 2.8 Connection details of Specimen R5 ................................................................ 23

    Figure 2.9 Connection details of Specimens A1 and A2.................................................. 25

    Figure 2.10 Connection details of Specimens A3 and A4................................................ 25

    Figure 2.11 Connection details of Specimens A5 and A6................................................ 26

    Figure 2.12 Connection details of Specimen A7 .............................................................. 26

    Figure 2.13 Connection details of Specimen A8 .............................................................. 27

    Figure 2.14 Loading scheme............................................................................................. 28

    Figure 2.15 Sample instrumentation layout (Specimen A1)............................................. 28

    Figure 3.1 Specimen C1: observed crack ......................................................................... 30

    Figure 3.2 Specimen C1: measured strains near crack location ....................................... 31

    Figure 3.3 Specimen C1: strain profiles near fillet weld toe (at 1500 cycles).................. 31

    Figure 3.4 Specimen C2: observed crack ......................................................................... 32

    Figure 3.5 Specimen C2: measured strains near crack location ....................................... 32

    Figure 3.6 Specimen C3: observed crack ......................................................................... 33

    Figure 3.7 Specimen C3: measured strains near crack location ....................................... 34

    Figure 3.8 Specimen C4: observed crack ......................................................................... 34

    Figure 3.9 Specimen C4: measured strains near crack location ....................................... 35

    Figure 3.10 Comparison of fatigue resistance of conventional connections .................... 35

    Figure 4.1 Specimen R1: gusset connection before testing .............................................. 37

  • 8/12/2019 UCSD Final Report Isa

    10/105

    viii

    Figure 4.2 Specimen R1: crack at fillet weld of Gusset No. 4.......................................... 38

    Figure 4.3 Specimen R2: repair procedure ....................................................................... 40

    Figure 4.4 Specimen R2: crack locations ......................................................................... 41

    Figure 4.5 Specimen R2: cracks at lower pipe-to-upper ring fillet weld.......................... 41

    Figure 4.6 Specimen R2: crack on lower pipe at slot weld location................................. 42

    Figure 4.7 Specimen R2: measured strains near lower pipe-to-upper ring welded joint.. 42

    Figure 4.8 Specimen R2: grout condition after testing..................................................... 43

    Figure 4.9 Specimen R2: fracture surface at slot weld location ....................................... 43

    Figure 4.10 Specimen R2: measured flexural strain distribution in grout region............. 44

    Figure 4.11 Specimen R3: observed crack on slot weld................................................... 45

    Figure 4.12 Specimen R3: measured strains near crack location ..................................... 45

    Figure 4.13 Specimen R4: repair procedure ..................................................................... 47

    Figure 4.14 Specimen R4: connection after repair ........................................................... 48

    Figure 4.15 Specimen R4: crack locations ....................................................................... 48

    Figure 4.16 Specimen R4: crack at lower pipe-to-upper ring fillet weld ......................... 49

    Figure 4.17 Specimen R4: crack on lower pipe at the slot weld location......................... 50

    Figure 4.18 Specimen R4: view of inside after cut........................................................... 51

    Figure 4.19 Specimen R4: fracture surface (Detail 1) ...................................................... 51

    Figure 4.20 Specimen R4: fracture surface (Detail 2) ...................................................... 52

    Figure 4.21 Specimen R5: crack at lower pipe-to-upper ring fillet weld ......................... 53

    Figure 4.22 Specimen R5: measured strains on FRP........................................................ 54

    Figure 4.23 Specimen R5: slot weld crack examination after FRP removal.................... 55

    Figure 4.24 Comparison of fatigue resistance of repair connections................................ 57

    Figure 5.1 Specimen A1: connection................................................................................ 59

    Figure 5.2 Specimen A1: cracks on slot welds at lower ring (at 45,000 cycles) .............. 60

    Figure 5.3 Specimen A1: repair procedure of damaged slot welds .................................. 60

    Figure 5.4 Specimen A1: needle peening of patch plate weld.......................................... 61

    Figure 5.5 Specimen A1: crack at patch plate location .................................................... 61

    Figure 5.6 Specimen A1: crack on slot weld location at guide ring level ........................ 62

    Figure 5.7 Specimen A1: measured strains....................................................................... 63

    Figure 5.8 Specimen A1: examination of inside after testing........................................... 63

  • 8/12/2019 UCSD Final Report Isa

    11/105

    ix

    Figure 5.9 Specimen A2: assembly procedure ................................................................. 65

    Figure 5.10 Specimen A2: measured strains near upper pipe-to-upper ring .................... 66

    Figure 5.11 Specimen A2: disassembly after testing........................................................ 67

    Figure 5.12 Specimen A2: crack at upper pipe-to-upper ring welded joint...................... 68

    Figure 5.13 Specimen A3: crack locations on slot welds ................................................. 70

    Figure 5.14 Specimen A3: typical crack pattern at slot weld location ............................. 70

    Figure 5.15 Specimen A3: measured strains near crack locations.................................... 71

    Figure 5.16 Specimen A3: specimen cut after testing ...................................................... 71

    Figure 5.17 Specimen A3: crack at Detail 1..................................................................... 72

    Figure 5.18 Specimen A3: crack at Detail 2 (guide ring level) ........................................ 73

    Figure 5.19 Specimen A3: fracture surface at Detail 2 (guide ring level)........................ 73

    Figure 5.20 Specimen A3: crack at Detail 3 (lower ring level)........................................ 74

    Figure 5.21 Specimen A3: crack at Detail 4 (lower ring level)........................................ 74

    Figure 5.22 Specimen A4: crack locations ....................................................................... 75

    Figure 5.23 Specimen A4: crack pattern at gusset-to-upper ring fillet weld.................... 76

    Figure 5.24 Specimen A4: crack pattern at slot weld location ......................................... 77

    Figure 5.25 Specimen A4: crack pattern at gusset-to-upper pipe welded joint................ 78

    Figure 5.26 Specimen A5: observed crack ....................................................................... 79

    Figure 5.27 Specimen A5: crack view from inside........................................................... 80

    Figure 5.28 Specimen A6: observed cracks...................................................................... 81

    Figure 5.29 Specimen A7: assembly using come-along hoists......................................... 82

    Figure 5.30 Specimen A7: examination of inside after testing......................................... 83

    Figure 5.31 Specimen A8: observed crack ....................................................................... 84

    Figure 5.32 Specimen A8: examination of inside after testing......................................... 85

    igure 5.33 Specimen A8: fracture surface......................................................................... 86

    Figure 6.1 Summary of fatigue resistance ........................................................................ 88

    Figure 6.2 S-N curves (AASHTO 2010) .......................................................................... 91

    Figure A.1 Specimen C1: Applied load time history........................................................ 98

    Figure A.1 Specimen C2: Applied load time history........................................................ 98

    Figure A.1 Specimen C3: Applied load time history........................................................ 98

    Figure A.1 Specimen C4: Applied load time history........................................................ 99

  • 8/12/2019 UCSD Final Report Isa

    12/105

    10

    1. INTRODUCTION1.1 Problem Statements

    Freestanding (cantilevered) steel sign structures have been widely used for

    commercial and retail signs. A common configuration for this type of structure is shown

    schematically in Figure 1.1(a). The pole supporting the sign cabinet consists of

    progressively smaller diameter pipes, with the smaller pipes inserted into larger pipes as

    per a commonly used welded sleeve connection shown in Figure 1.1(b). Both the lower

    and upper rings, as well as an optional guide ring which aids in alignment of the pipe

    sections during erection, are first shop-welded to the upper pipe. In the field, the upper

    ring is then fillet-welded to the top of the lower (outer) pipe. The lower and guide rings

    are also slot- or plug-welded to the lower pipe in the field.

    It is a common practice in design that the moment at the splice location is resisted

    by a force couple as shown in Figure 1.2 (Jones 1998). This simplified static design

    procedure has been used for decades and has served well for the majority of sign

    structures. But this type of structure is flexible, has a low damping, and can be prone to

    fatigue-type cracking due to wind-induced vortex shedding. Damage and collapses of

    sign structures due to fracture at the sleeve connections, even with no apparent defects in

    the construction, have been reported when the wind speed was far below that used in

    design. Figure 1.3 shows the typical crack locations of sign structures. As shown in

    Figure 1.3(a) and (b), the fatigue-type failure occurs most often in the upper pipes at the

    toe of the fillet-weld between the upper pipe and the upper ring. Although the sleeve

    connections have sometimes been strengthened or repaired by vertical gussets or C-

    channel gussets, fatigue cracks at the gusset-to-upper pipe (or upper ring) welded joint

    have been observed; see Figure 1.3(c) and (d) for the typical crack locations.

    1.2 Past ResearchCase studies on ten failed sign structures and the associated finite element analyses

    have been performed in an attempt to identify the cause of failure at the welded sleeve

    connection (Sim and Uang 2008). It was concluded that the fatigue-type cracks in the

  • 8/12/2019 UCSD Final Report Isa

    13/105

    11

    upper pipe initiated at the toe of the fillet weld connecting the upper pipe to the upper

    ring. The crack then propagated into the pipe section and caused failure.

    Finite element analysis of a typical sign structure showed a very high, geometry-

    induced stress concentration at this location. The following observations were also made

    from the finite element analysis. Within the practical range of the ring plate thickness,

    only 60% to 80% of the moment was transferred through the horizontal force couple. The

    remaining portion was transferred by the bending of the ring plates, which is a

    mechanism not reflected in a simplified, conventional design procedure. The stress

    concentration at the top fillet weld became more severe if the upper pipe was allowed to

    move due to defective or damaged slot welds. Based on case studies of damaged

    structures and other available evidence, it was determined that a common practice of

    strengthening or repairing the upper ring welded joint by installing welded gusset plates

    is not effective in mitigating fatigue cracking. Adding these gussets simply moves the

    critical stress concentration location to the top end of the gussets where fatigue-type

    cracking also has been observed. The use of a guide ring had a minimal effect on the

    stress distribution.

    Based on the observations from case studies and finite element analysis results,

    two alternative connection details were proposed (Sim and Uang 2008). Figure 1.4(a)

    shows the first proposed connection detail. The detail and fabrication of this connection

    are very similar to those of the conventional sleeve connection. However, no weld is

    specified on the top side of the fillet-weld joint between the upper ring and upper pipe;

    only the bottom side is welded. The second proposed connection detail is shown in

    Figure 1.4(b). Instead of using a pair of rings to transfer the moment through a horizontal

    force couple, a structural filler material (e.g., concrete or mortar) is used to fill the gap

    between the two pipes. The lateral moment is transferred through the bearing action of

    the filler material between the pipes.

  • 8/12/2019 UCSD Final Report Isa

    14/105

    12

    Sign

    Cabinet

    Steel Pipe

    Sleeve

    Connection

    Sign

    Cabinet

    Steel Pipe

    Sleeve

    Connection

    Upper Ring

    Lower Ring

    Upper Pipe

    Lower Pipe

    Guide Ring

    (Optional)

    (a) Elevation (b) Sleeve connection

    Figure 1.1 Typical configuration of a sign structure

    M

    H = M/d

    d

    H+V

    V

    M

    H = M/d

    d

    H+V

    V

    Figure 1.2 Assumed force transfer mechanism at sleeve connection (Jones 1998)

    Upper Pipe

    Upper

    Ring

    Crack Upper Pipe

    Upper

    Ring

    Crack

    Upper RingUpper Ring

    (a) Conventional sleeve connection (b) View of lower pipe after failure

    Lower

    Pipe

    Crack

    Upper Pipe

    Lower

    Pipe

    Crack

    Upper Pipe

    C-Channel

    Crack

    Upper

    Ring

    C-Channel

    Crack

    Upper

    Ring

    (c) Stiffened gusset plate connection (d) Stiffened C-channel gusset connection

    Figure 1.3 Typical failure locations of sign structures

  • 8/12/2019 UCSD Final Report Isa

    15/105

    13

    UpperRing

    UpperPipe

    LowerPipe

    Typ.

    Lower

    Ring

    Filler (Mortar

    or Concrete)

    Lower Ring

    Upper Pipe

    Lower Pipe

    Optional

    Guide Fins

    Typ.

    (a) Connection detail 1 (b) Connection detail 2

    Figure 1.4 Proposed connection details (Sim and Uang 2008)

    1.3 Objectives and ScopeThe objective of this research was to evaluate the performance of various

    alternative connection details for new construction and retrofit or repair of sign

    structures, and to compare the results to those derived from similar tests of conventional-

    type sleeve connections. Fatigue tests of seventeen different connection details were

    conducted to evaluate the relative fatigue resistance of these connection details.

  • 8/12/2019 UCSD Final Report Isa

    16/105

    14

    2. TEST PROGRAM2.1 Test Setup

    Figure 2.1 shows the test setup. The specimens were tested in the horizontal

    position using a hydraulic actuator acting at the free end to simulate wind-induced

    bending stresses at the connections. The lower pipe end was welded to a base plate and

    was anchored to a reaction wall. Such base boundary was not intended to simulate the

    actual base details of sign structures under study. To rule out any potential fatigue failure

    at this location, it was decided to clamp the specimen 22 in. away from the specimen base

    by a pair of concrete collars such that the bending stresses at the base plate weld was

    greatly reduced.

    ReactionWall Upper PipeLower Pipe

    North

    8'-6" 12'-6"

    21'

    3'

    22"

    Concre Blocks for

    Fixed Boundary ConditionMo

    untingPL.

    Strong Floor

    Hydraulic Actuator

    Actuator Corbel

    (a) Elevation

    (b) Photo view

    Figure 2.1 Test setup

  • 8/12/2019 UCSD Final Report Isa

    17/105

    15

    2.2 Test Matr ixA total of seventeen, 21-ft-long full-scale specimens were tested. Table 2.1shows

    the test matrix. Specimens included four conventional (with or without a guide ring), five

    repaired (by welded gussets, grout, or Fiber Reinforced Polymer (FRP) composites), and

    eight alternative connection details. ASTM A53 Grade B steel for the pipes and A36 steel

    for the plates were used for the specimens.

    Table 2.1 Test matrix

    Connection TypeSpecimen

    DesignationConnection Details

    C1 No guide ring usedNo Guide Ring

    C2 Specimen C1 + peeningC3 Guide ring usedConventional

    Guide RingC4

    Specimen C3 + gussets

    (gussets not connected to upper ring)

    Gusset Repair R1 Gusset repair of Specimen C1

    R2 Grout repair of Specimen C3

    R3 Grout repair of Specimen C2Grout Repair

    R4Steel cone & grout repair of

    Specimen C4

    Repair

    FRP Repair R5 FRP repair of Specimen R3

    A1

    Conventional weld details, but without

    top fillet weld at upper pipe-to-upper

    ring

    A2 Grout + no field welds and slot welds

    A3No fillet weld at lower pipe-to-upper

    ring + gussets + peening

    ModifiedSleeve Connection

    A4No fillet weld at upper pipe-to-upper

    ring + gussets

    A5Conical transition connection betweenupper and lower pipes

    Cone A6 Specimen A5 + peening

    Tapered A7 Tapered slip joint

    Alternative

    Bolted A8 Bolted match-plate connection

  • 8/12/2019 UCSD Final Report Isa

    18/105

    16

    2.3 Connection Details2.3.1 Conventional Welded Sleeve Connection Details

    A total of four conventional sleeve connections were tested. The objectives of

    testing were to (1) evaluate the failure mode as compared to field observations, (2)establish a baseline fatigue resistance for comparison with those of improved connection

    details, (3) assess the significance of guide ring in improving structural performance, and

    (4) assess the effect of post-weld peening treatment. After testing, these specimens were

    also repaired and re-tested to evaluate the effectiveness of several repair schemes.

    The overall configuration of the test specimens is shown in Figure 2.2. The

    diameters of the upper and lower pipes were 18 in and 22 in, respectively. The specified

    thickness of the pipes was 3/8 in (0.375 in); the measured thickness was approximately

    0.35 in. The sleeve length between the upper and lower ring plate levels was 35 in.

    Figure 2.3 shows the connection details of each specimen; the slot-weld details

    are also provided in Figure 2.3(c). Specimens C1 and C2 did not incorporate guide rings

    and were nominally identical, except that Specimen C2 received a post-weld peening

    treatment at the upper pipe-to-upper ring fillet weld. Both Specimens C3 and C4 had a

    guide ring, but the latter had a total of 12 gusset plates welded to the upper pipe and the

    upper ring. Specimen C4 had no weld specified on the lower pipe-to-upper ring joint per

    design, but this joint was welded in error during fabrication. Therefore, it was decided to

    modify the details of Specimen C4 such that the lower ends of the gussets near the upper

    ring were removed. Since the structural detail of the modified specimen was similar to

    that of the conventional sleeve connection, Specimen C4 was grouped with the

    conventional connections, assuming that the effect of the partially connected gussets on

    the fatigue performance of the specimen was insignificant.

  • 8/12/2019 UCSD Final Report Isa

    19/105

    17

    12'-6"

    8'-6"

    21'

    Upper Pipe

    (O.D. 18" x 3/8" )

    Lower Pipe

    (O.D. 22" x 3/8" )

    3'

    Figure 2.2 Overall configuration of test specimens

  • 8/12/2019 UCSD Final Report Isa

    20/105

    18

    Peening

    (Specimen C2 Only)

    Slot Weld

    6-1/2

    1" Thk Guide Ring

    (Specimen C3 Only)

    1" Thk Lower Ring

    3/16

    3/8

    3/16

    1/41/4

    1/2

    5/8" Thk Upper Ring

    36

    (a) Specimens C1 to C3

    Slot Weld

    6-1/21" Thk Guide Ring

    1" Thk Lower Ring

    3/16

    3/8

    3/16

    1/41/4

    5/8" Thk Upper Ring

    36

    10

    3/8" Thk Gusset, Typ

    1/41/4

    Typ

    (b) Specimen C4

    30

    Lower Pipe

    3

    11/16

    Lower or Guide

    Ring PL.

    (c) Slot weld details

    Figure 2.3 Connection details of Specimens C1 to C4

  • 8/12/2019 UCSD Final Report Isa

    21/105

    19

    2.3.2 Repair ed Connection DetailsThe investigated repair scheme included (1) welded gusset plates, a procedure

    commonly used in practice, (2) cement grout with steel jacketing, and (3) Fiber

    Reinforced Polymer strengthening. The objective was to develop effective and

    economical procedures for not only repairing damaged sign structures but also for retrofit

    or new construction.

    The details of the repair procedure investigated in this study are presented below.

    Gusset-Repaired Connection (Specimen R1)

    Specimen R1 is the repaired Specimen C1. After testing of Specimen C1, the

    damaged fillet weld between the upper pipe and upper ring was repaired, and gusset

    plates (A36 steel) were then added to strength the connection. Specimen R1 represents a

    common practice of attempting to strengthen or repair sleeve connections by installing

    gussets. Figure 2.4 shows the gusset connection details. Six 3/8-in.-thick gussets were

    fillet-welded to the upper pipe and the upper ring. A slight modification on the gusset

    weld was made such that the fillet weld at the tip of the gusset was not wrapped around

    for three of the gussets (located on the top side in the test setup), while welds on the other

    three gussets were wrapped around (located on the bottom side in the test setup).

    Cement Grout-Repaired Connection (Specimens R2 to R4)

    Figure 2.5shows the region where the connection was strengthened by grouting.

    Specimens R2 and R3 had a steel collar installed above the upper ring, and Specimen R4

    used a steel cone. Specimens R2 and R3 were grouted between the steel collar and the

    upper pipe. Compared to Specimen R2, Specimen R3 was also grouted between the two

    pipes in the sleeve region. Specimen R4 was grouted only in the sleeve region. The

    connection details of the repair specimens are shown in Figure 2.6and Figure 2.7. The

    repair procedures are described in Section 4.3.

    FRP-Repaired Connection (Specimen R5)

    Specimen R5 was the repaired Specimen R3. After testing of Specimen R3, Fiber

    Reinforced Polymer (FRP) composites were used to strengthen the cracked lower pipe at

    the slot weld. Figure 2.8 shows the connection details. The repair was performed by

    FYFE CO. LLC. The FRP was applied symmetrically with respect to the crack location

  • 8/12/2019 UCSD Final Report Isa

    22/105

    20

    in the longitudinal direction. Five layers of FRP (oriented longitudinally) and three layers

    of FRP (oriented transversely) were applied, as shown in Figure 2.8. For surface

    preparation, a 4-in grinder with a rough wire wheel was first used to remove the mill

    scale of the steel, and then an 80-grit flapper disk was used for a clean finish. Two

    separate epoxy resins were used. Epoxy resin (Tyfo MB-3) was used for improved

    adhesion to the metal and between layers of the fabric, and epoxy resin (Tyfo S) was used

    to saturate the fabric.

    1/41/4

    Typ

    3/8" Thk Gusset PL (6 Total)

    10

    1/2

    Figure 2.4 Connection details of Specimen R1

    6'

    3'

    3'

    (a) Specimen R2 (b) Specimen R3 (c) Specimen R4

    Figure 2.5 Grout-repaired region of Specimens R2 to R4

  • 8/12/2019 UCSD Final Report Isa

    23/105

    21

    3"

    6"

    6"

    6"

    6"

    6"

    3"

    3'-0"

    3 8"

    2'-11"

    No Weld

    No Weld

    1 / 4

    Non-Shrink Grout

    See Detail

    R = 0 to 1/4

    f = 0 to 1/8

    = 45

    R = 0 to 1/4

    f = 0 to 1/8

    = 45

    (a) Elevation (b) CJP weld details

    5/16PJP

    Same size Pipe

    Tack Weld

    Nuts in Place

    1/2" x 1.5" Bolts

    1/4" x 3" Flat Bar

    (Yellow Zinc Grade 8, Snug-Tight)

    Tack Weld

    Nuts in Place

    1/2" x 1.5" Bolts

    1/4" x 3" Flat Bar

    (Yellow Zinc Grade 8, Snug-Tight)

    (c) Exploded view (d) Plan view of splice sleeve

    Figure 2.6 Connection details of Specimens R2 and R3

  • 8/12/2019 UCSD Final Report Isa

    24/105

    22

    3 ft3 ft

    (a) Elevation (b) Exploded view

    (c) Detail A

    (d) Detail B (e) Detail C

    Figure 2.7 Connection details of Specimen R4

  • 8/12/2019 UCSD Final Report Isa

    25/105

    23

    32"

    40"

    24"

    24"

    Apply 5 Layers of FRP,

    Oriented Longitudinally

    Taper 2 LayersEvery 4 inches

    Apply 2 Layers of FRP,Oriented Transversely Overtop

    the Longitudinal Fiber

    Section A-A

    32"

    40"

    24"

    24"

    Apply 5 Layers of FRP,

    Oriented Longitudinally

    Taper 2 LayersEvery 4 inches

    Apply 2 Layers of FRP,Oriented Transversely Overtop

    the Longitudinal Fiber

    Section A-A

    (a) Elevation

    APPLY 5 LAYERS OF THE

    SCH-41-2X SYSTEM (SECOND),

    ORIENTED LONGITUDINALLY

    APPLY 2 LAYERS OF THE

    SCH-41-2X SYSTEM (LAST),

    ORIENTED TRANSVERSELY

    0-1/2" GAP, TYP.

    22"

    21.25"

    APPLY 1 LAYER OF THE TYFO

    WEB SYSTEM (FIRST) TO ACT AS A

    DIELECTRIC BARRIER TO THE STEEL

    6" OVERLAP, TYP.

    (b) Cross section (Section A-A)

    Figure 2.8 Connection details of Specimen R5

  • 8/12/2019 UCSD Final Report Isa

    26/105

    24

    2.3.3 Alternat ive Connection DetailsModified Sleeve Connection Details (Specimens A1 to A4)

    Specimen A1, shown in Figure 2.9(a), used the same connection details as

    Specimen C3, except that no weld was specified on the top of the fillet-welded jointbetween the upper pipe and the upper ring; only the bottom side was welded. Specimen

    A2, shown in Figure 2.9(b), also eliminated the top-side fillet weld like Specimen A1.

    But slot welds were not used to avoid potential cracking at these locations. Instead, the

    gap between the two pipes in the sleeve region was filled by grout after the upper pipe

    was inserted into the lower pipe. Furthermore, the lower pipe-to-upper ring field fillet

    weld was eliminated.

    The connection details of Specimens A3 and A4 are shown in Figure 2.10. Each

    specimen used a total of twelve gusset plates; see Figure 2.10(b) for the gusset details.

    Both specimens had similar connection details, but the weld detail in the sleeve region of

    each specimen was slightly different. While Specimen A3 used no weld at the lower

    pipe-to-upper ring joint, Specimen A4 used no weld at the upper pipe-to-upper ring joint.

    Cone Transition Connection Details (Specimens A5 to A6)

    Specimens A5 and A6 incorporated a steel conical section between the upper and

    lower pipes. Both specimens were identical, except that Specimen A6 received a post-

    weld peening treatment. The connection details are provided in Figure 2.11. Complete-

    joint-penetration (CJP) welds were used to connect the cone to the pipes.

    Tapered Slip-Joint (Specimen A7)

    Specimen A7, shown in Figure 2.12, incorporated a tapered slip-joint between the

    two pipes. The upper pipe was slipped into the lower pipe until a target slip engagement

    length (= 38 in) was achieved. No welds were needed to connect the two pipes.

    Bolted Match-Plate Connection Details (Specimen A8)

    Specimen A8 incorporated a bolted match-plate connection between the upper

    and lower pipes. The connection details are shown in Figure 2.13. Each pipe was CJP-

    welded to a circular match plate in the shop. Two pipe sections were then connected by

  • 8/12/2019 UCSD Final Report Isa

    27/105

    25

    pretension bolting of two match plates in the field. No field welding is required for this

    type of connection.

    Slot Weld

    6-1/2

    1" Thk Guide Ring

    1" Thk Lower Ring

    3/16

    3/8

    1/41/4

    1/2

    5/8" Thk Upper Ring

    36

    No Weld at Top

    No Weld

    No Weld at Top

    3/8

    1/4

    1/4

    Grout

    No Slot Weld

    (a) Specimen A1 (b) Specimen A2

    Figure 2.9 Connection details of Specimens A1 and A2

    1" Thk Lower Ring

    1/41/4

    5/8" Thk Upper Ring

    Gusset, Typ

    3/83/8

    3/163/16Peening

    Specimen A4

    Only

    Specimen A3 Only

    Slot Weld

    1" Thk Guide Ring

    (12 Total)

    1" Thk Lower Ring

    1/41/4

    5/8" Thk Upper Ring

    Gusset, Typ

    3/83/8

    3/163/16Peening

    Specimen A4

    Only

    Specimen A3 Only

    Slot Weld

    1" Thk Guide Ring

    (12 Total)

    (a) Specimens A3 and A4 (b) Gusset details

    Figure 2.10 Connection details of Specimens A3 and A4

  • 8/12/2019 UCSD Final Report Isa

    28/105

    26

    Figure 2.11 Connection details of Specimens A5 and A6

    15'-8"

    1'-758

    "

    1'-212

    "

    12'-6"

    8'-6"

    SECTION

    BASE SECTION

    3/8" FORMED PLATE

    TOP SECTION

    3/8" FORMED PLATE

    O.D. UPPER OUTER PIPE 18"

    O.D. LOWER INNER PIPE 17.25"

    O.D. UPPER OUTER PIPE 18.89"

    O.D. LOWER INNER PIPE 18.14"

    SECTION

    (a) Elevation (b) Slip-joint

    Figure 2.12 Connection details of Specimen A7

  • 8/12/2019 UCSD Final Report Isa

    29/105

    27

    R1'-1" 1" BOLT ASTM A325

    1" PLATE

    118"

    R1'-3"

    (Pretensioned)

    R1'-1" 1" BOLT ASTM A325

    1" PLATE

    118"

    R1'-3"

    (Pretensioned)

    (a) Plan view (b) Weld details

    Figure 2.13 Connection details of Specimen A8

    2.4 Loading SchemeThe cyclic testing was conducted in a displacement-controlled mode. Since it was

    not possible to measure the nominal strain on the upper pipe section at the upper ring

    level of the sleeve connection due to stress concentration, a free-end displacement target

    for each specimen was determined based on the recorded strains on an upper pipe section

    away from the connection such that a nominal stress range of 30 ksi ( 15 ksi) was

    applied to the critical upper pipe section (see Figure 2.14). (The instrumented section was

    selected to be sufficiently away from the critical section such that it would remain in the

    elastic range.) The measured actuator forces applied to the specimens are provided in

    Appendix A. Testing was conducted with a loading frequency ranging from 1.0 to 1.3 Hz.

    2.5 Instrumentation and Cr ack InspectionsThe specimens were instrumented with uni-axial and rosette strain gages to

    measure local strains. Figure 2.15 shows a sample instrumentation layout. Strain gage

    locations varied for each test specimen. During testing, strains were recorded at interval

    (e.g., every 5,000 loading cycles) and strain variations at critical welded joints were

    monitored to identify any cracking. Dye penetrant, magnetic particle, and ultrasonic

    testing inspections were also conducted by a local inspection company.

  • 8/12/2019 UCSD Final Report Isa

    30/105

    28

    L2 L1

    L1L2

    Nominal Flexural Strain Profile

    Strain Gages

    top

    bot

    )10(103429000ksi)(E

    30ksi)(

    6

    target

    target

    21

    1bottop

    0 LL

    L

    2

    0

    L1L2

    L1L2L2 L1

    L1L2

    Nominal Flexural Strain Profile

    Strain Gages

    top

    bot

    )10(103429000ksi)(E

    30ksi)(

    6

    target

    target

    21

    1bottop

    0 LL

    L

    2

    0

    L1L2

    L1L2

    Figure 2.14 Loading scheme

    ReactionWall

    18"x0.375" Pipe22"x0.375"

    Pipe

    3'-112

    "6"

    Section1

    Section4

    Section 4Section 1

    North

    8'-6" 12'-6"

    21'

    1'-3"

    Section3

    Section 3Section 2S10

    Section2

    1'-3"

    0.375" (Typ.)

    Figure 2.15 Sample instrumentation layout (Specimen A1)

  • 8/12/2019 UCSD Final Report Isa

    31/105

    29

    3. TEST RESULTS OF CONVENTIONAL CONNECTIONS3.1 Introduction

    Figure 2.3 shows the details of the four conventional welded sleeve connection

    specimens. The testing had the following objectives:

    to evaluate the fatigue resistance and the associated failure mode for comparison

    with field observations,

    to provide a baseline for comparison with alternative connection details,

    to evaluate the effectiveness of using a guide ring,

    to evaluate the effectiveness of peening as a post-weld treatment.

    3.2 Conventional Connection Details without Guide Ring3.2.1 Specimen C1

    Testing of Specimen C1 was completed at 22,000 cycles when the crack length

    was about 14 in long (or 25% of the circumference). The specimen cracked at the upper

    pipe-to-upper ring fillet welded joint. The observed crack on the top side of the specimen

    is shown in Figure 3.1. No cracks were observed on the bottom side. The crack initiated

    at the toe of the fillet weld between the upper pipe and the upper ring, and then

    propagated into the upper pipe wall thickness along the weld toe circumference.

    Strain range variations measured near the crack location are shown in Figure 3.2;

    the strain gage locations are provided in Figure 3.1. The strain range began to decrease at

    early stage, which indicates that the crack may have initiated very early. The strain range

    gradually decreased as the crack propagated. To monitor the strain concentration at the

    weld toe, Specimen C1 was instrumented with a strip gage, which was a series of five

    closely spaced gages. As shown in Figure 3.1(a), one strip gage (S1 to S5) was placed on

    the upper pipe right above the upper ring, and another strip gage (S6 to S10) was placed

    on the lower pipe right below the upper ring. The centerline of each strip gage was

    located 3/8 in away from the weld toe. The strain profiles measured by the strip gages are

    shown in Figure 3.3. For comparison purposes, the nominal strain range (= 1034 )

    based on beam theory was also shown. High strain readings (with large strain gradient)

  • 8/12/2019 UCSD Final Report Isa

    32/105

    30

    on the upper pipe near the weld toe are clearly shown, while the lower pipe had low

    strains. This experimental evidence on stress concentration is consistent with that

    reported in a finite element analysis (Sim and Uang 2008).

    Lower Pipe

    Upper Pipe

    Upper

    Ring

    Crack Location

    (Fillet Weld Toe)

    S1 to S5

    S6 to S10

    Lower Pipe

    Upper Pipe

    Upper

    Ring

    Crack Location

    (Fillet Weld Toe)

    S1 to S5

    S6 to S10

    (a) Crack location

    0.375

    S1 to S5

    Upper Ring

    Upper Pipe

    0.375

    S1 to S5

    Upper Ring

    Upper Pipe

    (b) Close-up view of crack

    Figure 3.1 Specimen C1: observed crack

  • 8/12/2019 UCSD Final Report Isa

    33/105

    31

    0 10 20 300

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    S1

    S2

    S4

    S5

    Strain

    Range(x10-6)

    S3 Malfunctioned

    Nominal Strain Range

    at Sleeve Connection

    0 10 20 300

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    S1

    S2

    S4

    S5

    Strain

    Range(x10-6)

    S3 Malfunctioned

    Nominal Strain Range

    at Sleeve Connection

    Figure 3.2 Specimen C1: measured strains near crack location

    0.0 0.2 0.4 0.60

    500

    1000

    1500

    2000

    2500

    3000

    Distance from Fillet Weld Toe (in.)

    StrainRange(x

    10-6) S1

    S2

    S4 S5

    0.0 0.2 0.4 0.60

    500

    1000

    1500

    2000

    2500

    3000

    Distance from Fillet Weld Toe (in.)

    StrainRange(x

    10-6) S1

    S2

    S4 S5

    0.0 0.2 0.4 0.60

    500

    1000

    1500

    2000

    2500

    3000

    Distance from Fillet Weld Toe (in.)

    StrainRange(x

    10-6)

    S6 S7 S8 S9 S10

    0.0 0.2 0.4 0.60

    500

    1000

    1500

    2000

    2500

    3000

    Distance from Fillet Weld Toe (in.)

    StrainRange(x

    10-6)

    S6 S7 S8 S9 S10

    (a) on upper pipe (b) on lower pipe

    Figure 3.3 Specimen C1: strain profiles near fillet weld toe (at 1500 cycles)

    3.2.2 Specimen C2Specimen C2 was nominally identical to Specimen C1, except that Specimen C2

    received a post-weld peening treatment at the upper pipe-to-upper ring fillet-welded joint.

    If properly applied, peening the toe of a weld termination can effectively increases the

    fatigue resistance by producing beneficial compressive residual stresses (Fisher et. al

    1998). However, it was realized after testing that peening had not been performed

    according to specifications in AWS D.1.1, Section 5.27 (AWS 2006). Therefore, the

    effect of peening on this specimen might be minimal.

    Testing of Specimen C2 was completed at 17,000 cycles when the maximum

    crack length was about 15 in. Specimen C2 showed the same crack pattern as that

    observed in Specimen C1. Figure 3.4 shows the crack at the upper pipe-to-upper ring

    fillet welded joint. While Specimen C1 cracked on the top side only, Specimen C2

  • 8/12/2019 UCSD Final Report Isa

    34/105

    32

    cracked on both the top and bottom sides of the pipe. Strain range variations measured

    near the crack locations on both the top and bottom sides are shown in Figure 3.5. The

    strain ranges began to decrease between 10,000 and 15,000 cycles, which indicates that

    the cracks initiated during this period.

    Crack

    Lower Pipe

    Upper Pipe

    Upper Ring

    S5 (on Top Side)

    S6 (on Bottom Side)

    0.375

    Crack

    Lower Pipe

    Upper Pipe

    Upper Ring

    S5 (on Top Side)

    S6 (on Bottom Side)

    0.375

    Figure 3.4 Specimen C2: observed crack

    0 10 20 300

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    StrainRange(x10-6)

    S6

    S5

    0 10 20 300

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    StrainRange(x10-6)

    S6

    S5

    Figure 3.5 Specimen C2: measured strains near crack location

  • 8/12/2019 UCSD Final Report Isa

    35/105

    33

    3.3 Conventional Connection Details with Guide Ring3.3.1 Specimen C3

    Specimen C3 was nominally identical to Specimen C1, except that Specimen C3

    had a guide ring. Testing of Specimen C3 was completed at 17,000 cycles when the cracklength was about 10 in. Specimen C3 had the same crack pattern as that observed in both

    Specimens C1 and C2. Figure 3.6shows the crack observed at the upper pipe-to-upper

    ring fillet welded joint on the top side of the specimen. Strain range variations measured

    near the crack location, shown in Figure 3.7, showed the similar trend as that observed in

    Specimen C2.

    Crack Location(Fillet Weld Toe)

    Lower Pipe

    Upper Pipe

    Upper Ring

    S2

    0.375

    Crack Location(Fillet Weld Toe)

    Lower Pipe

    Upper Pipe

    Upper Ring

    S2

    0.375

    (a) Crack location

    Upper PipeCrack at Weld Toe

    Upper Ring

    Fillet Weld

    Upper PipeCrack at Weld Toe

    Upper Ring

    Fillet Weld

    (b) Close-up view of crack

    Figure 3.6 Specimen C3: observed crack

  • 8/12/2019 UCSD Final Report Isa

    36/105

    34

    0 10 20 300

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    S2

    Strain

    Range(x10-6)

    0 10 20 300

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    S2

    Strain

    Range(x10-6)

    Figure 3.7 Specimen C3: measured strains near crack location

    3.3.2 Specimen C4As described in Section 2.3.1, inspections of this specimen detected a misplaced

    weld due to a fabrication error, so it was decided to detach the gusset plates from the

    upper ring. This modified connection is similar to, but not exactly the same as that of

    Specimen C3.

    Testing of Specimen C4 was completed at 25,000 cycles when the maximum

    crack length was about 14 in. Specimen C4 also showed the similar crack pattern as that

    observed in the previous specimens. Figure 3.8 shows the crack location. Both the top

    and bottom sides cracked, but the crack length on the bottom side (3 in at 25,000 cycles)

    was shorter when compared with the top side crack (14 in long at 25,000 cycles). Strain

    range variations measured near the crack location on the top side are shown in Figure 3.9.

    1

    S11

    S13

    Crack Location

    (Fillet Weld Toe)

    LowerPipe

    UpperRing

    Top Edge Line

    1

    S11

    S13

    Crack Location

    (Fillet Weld Toe)

    LowerPipe

    UpperRing

    Top Edge Line

    Figure 3.8 Specimen C4: observed crack

  • 8/12/2019 UCSD Final Report Isa

    37/105

    35

    0 10 20 300

    5001000

    1500

    000

    500

    3000

    Number of Cycles (x 1000)

    Strain

    Range(x10-6)

    S11

    S13

    0 10 20 300

    5001000

    1500

    000

    500

    3000

    Number of Cycles (x 1000)

    Strain

    Range(x10-6)

    S11

    S13

    Figure 3.9 Specimen C4: measured strains near crack location

    3.4 Compar ison of Test ResultsAll four conventional welded sleeve connection specimens showed the same crack

    pattern in which the crack initiated at the toe of the fillet weld between the upper pipe andthe upper ring due to high strain concentration. The cracks then propagated into the upper

    pipe section and along the weld toe circumference. The crack pattern from testing was

    similar to that observed in the failed sign structures like that shown in Figure 1.3(a). The

    use of a guide ring had an insignificant effect on the fatigue resistance of the critical joint.

    This experimental evidence is consistent with the finding from a finite element analysis

    (Sim and Uang 2008).

    0

    50

    100

    150

    200

    FailureCycles(x103)

    C1

    Specimen No.

    C2 C3 C40

    50

    100

    150

    200

    FailureCycles(x103)

    C1

    Specimen No.

    C2 C3 C4

    Figure 3.10 Comparison of fatigue resistance of conventional connections

  • 8/12/2019 UCSD Final Report Isa

    38/105

    36

    4. TEST RESULTS OF REPAIRED CONNECTIONS4.1 Introduction

    Each of the four tested conventional sleeve connection specimens was repaired by

    various methods to evaluate their effectiveness. One specimen was repaired twice,

    resulting in a total of five repaired specimens (R1 to R5, see Table 2.1). Figures 2.4 to 2.8

    depict the design of these repaired specimens.

    4.2 Gusset Repair : Specimen R1After repair, the tested specimen C1 is designated as R1 (see Figure 2.4). The

    damaged fillet weld between the upper pipe and upper ring was repaired first, and then

    gusset plates were added to strength the connection. Specimen R1 represents a common

    means of attempting to strengthen or repair sleeve connections by installing gussets in the

    field. Figure 4.1shows the connection with the designation of six gussets. Along the long

    side of the gusset plate, the fillet weld at the tip was not wrapped around for three gussets

    (Gussets 1, 2, and 6), while the other three gussets (Gussets 3, 4, and 5) were wrapped

    around. On the short side, fillet weld was wrapped around for all specimens.

    Specimen R1 cracked early during testing at the short side (i.e., horizontal side

    when the specimen is in an upright position) of the gusset weld. Figure 4.2 shows thecrack observed at the bottom gusset (Gusset 4) fillet weld at 4,200 cycles. The top gusset

    (Gusset 1) fillet weld also showed a similar crack pattern. The crack first initiated at the

    wrap-around location, and propagated along the gusset weld length. After the welds along

    the short side of the gusset failed, the connection behaved like a conventional sleeve

    connection, and additional cracks similar to those observed in Specimens C1 to C4

    occurred at the toe of the fillet weld between the upper pipe and the upper ring. Testing of

    Specimen R1 was completed at 13,000 cycles when the crack length of the upper pipe-to-

    upper ring fillet weld reached about 20% of the upper pipe circumference.

    Note that the location of the weld fracture is different from that commonly

    observed in the field, as shown in Figure 1.3(c). This is mainly due to the very short

    horizontal weld length for connecting the gussets to the upper ring.

  • 8/12/2019 UCSD Final Report Isa

    39/105

    37

    West

    2

    1

    6

    Upper Pipe

    Lower Pipe

    Upper Ring

    Gusset

    Designation

    Fillet WeldNot Wrapped Aroundfor Gussets 1, 2, and 6

    West

    2

    1

    6

    Upper Pipe

    Lower Pipe

    Upper Ring

    Gusset

    Designation

    Fillet WeldNot Wrapped Aroundfor Gussets 1, 2, and 6

    (a) Top side

    Lower Pipe

    Upper Ring

    Upper Pipe

    3

    West

    4

    5

    Fillet Weld

    Wrapped Around

    for Gussets 3, 4, and 5

    Lower Pipe

    Upper Ring

    Upper Pipe

    3

    West

    4

    5

    Fillet Weld

    Wrapped Around

    for Gussets 3, 4, and 5

    (b) Bottom side

    Figure 4.1 Specimen R1: gusset connection before testing

  • 8/12/2019 UCSD Final Report Isa

    40/105

    38

    Upper Ring

    Gusset

    Upper Ring

    Gusset

    Upper RingUpper Ring

    (a) View from East (b) View from West

    Figure 4.2 Specimen R1: crack at fillet weld of Gusset No. 4

    4.3 Steel-Jacketed and Cement-Grouted Repair4.3.1 Introduction

    Two tested conventional sleeve connections (Specimens C2 and C3) were repaired

    by a steel jacketed grouting scheme. It has been shown in an analytical study (Sim and

    Uang 2008) that the bending moment from the upper pipe is not completely transferred as

    a force couple (see Figure 1.2) to the lower pipe. As well as aiming to reduce the stressconcentration at the upper ring welded joint, the intent of this strengthening scheme was

    to transfer the moment through bearing action of the filler material between the pipes.

    After the testing of Specimens R2 and R3, another weakness in the existing slot-

    welded location surfaced. Therefore, Specimen R3 was again repaired using Fiber

    Reinforced Polymer (FRP) material, and the twice-repaired specimen is designated as R5.

    4.3.2 Specimen R2Specimen R2 was the repaired Specimen C3 [see Figure 2.5(a) and Figure 2.6].

    After testing of Specimen C3, the damaged fillet weld between the upper pipe and the

    upper ring was first repaired, and the specimen was strengthened by steel jacketing and

    grouting using cement (Rapid Set Cement All Grout), a non-shrinking, multipurpose

    grout which can attain a 2,000 psi compressive strength in one hour.

  • 8/12/2019 UCSD Final Report Isa

    41/105

    39

    Figure 4.3 shows the repair procedure. After the weld repair, a steel collar was

    first installed and welded to the upper ring. The steel collar consisted of two separate

    halves, and these were connected by snug-tight bolts. The gap between the steel collar

    and the upper pipe was then filled with grout. After grouting, a cap ring consisting of two

    separate half pieces was welded to the collars to seal the grout. The cap ring pieces were

    first fillet-welded to the steel collars but not to the upper pipe, and then they were

    connected together by partial-joint-penetration groove welds.

    Although cracks did not occur at the upper pipe-to-upper ring welded joint with

    the grout-repair scheme, fatigue cracks occurred at the next weak locations as the number

    of cycles imposed on the specimen increased. Figure 4.4 shows the crack locations

    observed during testing. As shown in Figure 4.5(a), the crack first occurred at the existing

    fillet weld between the lower pipe and the upper ring on the bottom side. As the testing

    continued, another crack on the lower pipe at the slot weld location of the lower ring was

    observed as shown in Figure 4.6. Near the end of the testing, a small crack at the lower

    pipe-to-upper ring fillet weld on the top side was observed, as shown in Figure 4.5(b).

    Strain range variations measured near the cracked fillet welds are shown in Figure 4.7;

    see Figure 4.5for the strain gage locations.

    Testing of Specimen R2 was completed at 155,000 cycles when the length of the

    crack in Figure 4.6propagated to 16 in. After testing, the steel jackets were removed to

    examine the condition of the grout (see Figure 4.8). A visual inspection showed that the

    quality of grout remained sound with no crushing observed. A steel piece at the slot weld

    location was also cut out for examination (see Figure 4.9). The fractured surface showed

    that the crack may have initiated at the ends of the slot weld and propagated outward

    through the lower pipe wall thickness.

    Figure 4.10shows the measured flexural strain profiles on the upper pipe and the

    steel collar, respectively. As shown in the plots, the strains on the upper pipe gradually

    decreased from the grout cap level to the upper ring level, while the strain on the steel

    collar gradually increased. Figure 4.10(a) shows that the jacketed grout was effective in

    reducing the stresses transferred to the existing upper ring weld. Therefore, the crack

    potential at this welded joint was significantly reduced.

  • 8/12/2019 UCSD Final Report Isa

    42/105

    40

    (a) Weld Repair (b) Install steel collars and

    bolt together

    (c) Groove weld of steel

    collar to upper ring

    (d) Grouting (e) Install cap cover ring

    Figure 4.3 Specimen R2: repair procedure

  • 8/12/2019 UCSD Final Report Isa

    43/105

    41

    (3) Last location where crack was observed

    (crack at lower pipe-to-upper ring fillet weld)

    (1) Location where crack was first observed

    (crack at lower pipe-to-upper ring fillet weld)

    (2) Location where crack was next observed

    (crack at slot weld at lower ring level)

    Top Edge Line

    Slot Weld Orientation

    (at Lower Ring Level)

    45, Typ.

    South

    Lower Pipe

    Steel

    Collar

    axis of bending(3) Last location where crack was observed

    (crack at lower pipe-to-upper ring fillet weld)

    (1) Location where crack was first observed

    (crack at lower pipe-to-upper ring fillet weld)

    (2) Location where crack was next observed

    (crack at slot weld at lower ring level)

    Top Edge Line

    Slot Weld Orientation

    (at Lower Ring Level)

    45, Typ.

    South

    Lower Pipe

    Steel

    Collar

    axis of bending

    Figure 4.4 Specimen R2: crack locations

    Lower Pipe

    Crack Length = 17

    at 150,000 Cycles

    Steel Collar

    UpperR

    ing0.375

    S24

    Lower Pipe

    Crack Length = 17

    at 150,000 Cycles

    Steel Collar

    UpperR

    ing0.375

    S24

    (a) Bottom side

    Lower PipeCrack Length = 3at 155,000 Cycles

    Steel Collar

    UpperRing

    0.375

    S16

    Lower PipeCrack Length = 3at 155,000 Cycles

    Steel Collar

    UpperRing

    0.375

    S16

    (b) Top side

    Figure 4.5 Specimen R2: cracks at lower pipe-to-upper ring fillet weld

  • 8/12/2019 UCSD Final Report Isa

    44/105

    42

    CrackLength

    16in.

    at155,000Cycles

    Crack

    CrackLength

    9in.

    at132,000Cycles

    Slot Weld Location

    CrackLength

    16in.

    at155,000Cycles

    Crack

    CrackLength

    9in.

    at132,000Cycles

    Slot Weld Location

    Figure 4.6 Specimen R2: crack on lower pipe at slot weld location

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    S24StrainRa

    nge(x10-6)

    S16

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    S24StrainRa

    nge(x10-6)

    S16

    Figure 4.7 Specimen R2: measured strains near lower pipe-to-upper ring welded joint

  • 8/12/2019 UCSD Final Report Isa

    45/105

    43

    Cut-Out Location

    Grout

    Cut-Out Location

    Grout

    Figure 4.8 Specimen R2: grout condition after testing

    LowerRing

    Upper Pipe

    Lower Pipe

    Slot Weld

    LowerRing

    Upper Pipe

    Lower Pipe

    Slot Weld

    (a) Cut-out piece

    Slot WeldSlot Weld

    (b) Fracture surface

    Figure 4.9 Specimen R2: fracture surface at slot weld location

  • 8/12/2019 UCSD Final Report Isa

    46/105

    44

    0 10 20 300

    200

    400

    600

    800

    1000

    5

    10

    15

    20

    25Top SurfaceBottom Surface

    StrainRange(x10-6)

    x, Distance from Upper Ring (in.)

    x

    UpperRing

    Level

    GroutCap

    Level

    Location for Plots

    Top Surface

    Bottom Surface

    StressRange(ksi)

    Lower

    Pipe

    Upper

    Pipe

    0 10 20 300

    200

    400

    600

    800

    1000

    5

    10

    15

    20

    25Top SurfaceBottom Surface

    StrainRange(x10-6)

    x, Distance from Upper Ring (in.)

    x

    UpperRing

    Level

    GroutCap

    Level

    Location for Plots

    Top Surface

    Bottom Surface

    StressRange(ksi)

    Lower

    Pipe

    Upper

    Pipe

    0 10 20 300

    200

    400

    600

    800

    1000

    5

    10

    15

    20

    25Top SurfaceBottom Surface

    StrainRange(x10-6)

    x, Distance from Upper Ring (in.)

    Location for Plots

    Top Surface

    Bottom Surface

    x

    UpperRing

    Level

    GroutCap

    Level

    StressRange(ksi)

    LowerPipe

    Upper

    Pipe

    0 10 20 300

    200

    400

    600

    800

    1000

    5

    10

    15

    20

    25Top SurfaceBottom Surface

    StrainRange(x10-6)

    x, Distance from Upper Ring (in.)

    Location for Plots

    Top Surface

    Bottom Surface

    x

    UpperRing

    Level

    GroutCap

    Level

    StressRange(ksi)

    LowerPipe

    Upper

    Pipe

    (a) Strain profiles on upper pipe (b) Stain profiles on steel collar

    Figure 4.10 Specimen R2: measured flexural strain distribution in grout region

    4.3.3 Specimen R3Specimen R3 was the repaired Specimen C2 [see Figure 2.5(b) and Figure 2.6].

    After testing of Specimen C2, the damaged fillet weld between the upper pipe and the

    upper ring was first repaired. The slot weld was ground flush for an UT inspection; the

    inspection revealed no rejectable weld cracks. Then the specimen was strengthened by

    steel jacketing and grouting. The same repair procedure as used in Specimen R2 was

    applied, except that Specimen R2 was grouted above the upper ring only while Specimen

    R3 was grouted in the sleeve region as well. Two holes (2 in diameter) on the upper

    ring were drilled to accommodate the grouting in the sleeve region.

    Figure 4.11shows the crack location. The crack occurred on the lower pipe at the

    slot weld location of the lower ring. Strain range variations near the cracked slot weld are

    shown in Figure 4.12. Specimen R2 was subjected to a large number of cycles (155,000

    cycles), however the slot-weld crack had extended to a length of 5 in. at only 40,000

    cycles. To better utilize this specimen, it was decided to stop the testing of R3 at that

    point such that the potential of using fiber reinforced polymer composites to repair the

    cracked slot welds could be evaluated in Specimen R5.

  • 8/12/2019 UCSD Final Report Isa

    47/105

    45

    Steel Collar

    Lower

    Pipe

    Crack at SlotWeld Location

    Top

    Edge

    Lin

    e

    4 in

    Slot Weld Orientation

    (at Lower Ring Level)

    axis of

    bending

    Steel Collar

    Lower

    Pipe

    Crack at SlotWeld Location

    Top

    Edge

    Lin

    e

    4 in

    Slot Weld Orientation

    (at Lower Ring Level)

    axis of

    bending

    Crack

    S15

    S13

    1 (Typ)

    Crack

    S15

    S13

    1 (Typ)

    (a) Crack location (b) Close-up view of crack

    Figure 4.11 Specimen R3: observed crack on slot weld

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    S15S13S

    trainRange(x10-6)

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    S15S13S

    trainRange(x10-6)

    Figure 4.12 Specimen R3: measured strains near crack location

    4.4 Steel Cone and Cement Gr out Repair : Specimen R4Specimen R4 was the repaired Specimen C4 [see Figure 2.5(c) and Figure 2.6].

    After testing of Specimen C4, the damaged fillet weld between the upper pipe and upper

    ring was first repaired, and the specimen was strengthened by a steel cone and cement

    grouting above and below the upper ring, respectively. Figure 4.13 shows the repair

    procedure. The gap between the pipes above the guide ring in the sleeve region was first

    filled by grout; small holes on the upper ring were drilled to accommodate the grouting.

    The gap between the pipes below the guide ring was also filled by grout; small holes on

    the lower pipe right below the guide ring were also drilled to accommodate the grouting.

  • 8/12/2019 UCSD Final Report Isa

    48/105

    46

    A steel cone (A36 steel) was then installed and welded to the upper ring and the upper

    pipe. The steel cone consisted of two separate half pieces, and they were connected by

    welding (see Figure 2.5). Figure 4.14shows the connection after repair.

    Figure 4.15 shows the crack locations observed during testing. As shown in

    Figure 4.16(a), the crack (on the bottom side) first occurred at the existing fillet weld

    between the upper ring and the lower pipe. As the testing continued, another crack on the

    lower pipe at the slot weld location was observed, as shown in Figure 4.17(a). Testing of

    Specimen R4 was completed at 105,000 cycles. At the end of testing, the length of the

    crack in Figure 4.16(a) propagated to 30 in and the length of the crack in Figure 4.17(b)

    was 11 in.

    After testing, the specimen was cut to examine the inside, as shown in Figure

    4.18. The grout remained intact and its condition was good. The fracture surfaces on the

    slot weld are shown in Figures 4.19 and 4.20. A visual inspection on the fracture surface

    indicated that the crack initiated at both ends of the slot weld and propagated outward

    through the lower pipe wall thickness. This slot-weld failure appeared to be caused by

    high bending stresses on the lower pipe together with a geometric imperfection resulting

    from the slot weld itself.

  • 8/12/2019 UCSD Final Report Isa

    49/105

    47

    (a) Weld repair (b) Grouting between upper and guide rings

    (c) Grouting between guide and lower rings (d) Installation of steel cone

    Figure 4.13 Specimen R4: repair procedure

  • 8/12/2019 UCSD Final Report Isa

    50/105

    48

    PJP Weld

    Upper Pipe

    Cone

    Cone

    Lower Pipe

    Upper Pipe

    Cone

    Lower Pipe

    PJP Weld

    Upper Pipe

    Cone

    Cone

    Lower Pipe

    Upper Pipe

    Cone

    Lower Pipe

    Figure 4.14 Specimen R4: connection after repair

    (2) Crack at Slot

    Weld Location

    Cone

    Lower

    Pipe

    (1) Crack at Lower Pipe-

    to-Upper Ring Fillet Weld

    (Bottom Side Only)

    5 in

    Slot Weld Orientation

    (at Lower Ring Level)

    axis ofbending

    (2) Crack at Slot

    Weld Location

    Cone

    Lower

    Pipe

    (1) Crack at Lower Pipe-

    to-Upper Ring Fillet Weld

    (Bottom Side Only)

    5 in

    Slot Weld Orientation

    (at Lower Ring Level)

    axis ofbending

    5 in

    Slot Weld Orientation

    (at Lower Ring Level)

    axis ofbending

    Figure 4.15 Specimen R4: crack locations

  • 8/12/2019 UCSD Final Report Isa

    51/105

    49

    CrackS18

    Ring

    LowerPipe

    Cone

    0.375

    CrackS18

    Ring

    LowerPipe

    Cone

    0.375

    (a) Crack location

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    Strain

    Range(x10-6)

    S18

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    Strain

    Range(x10-6)

    S18

    (b) Measured strains

    Figure 4.16 Specimen R4: crack at lower pipe-to-upper ring fillet weld

  • 8/12/2019 UCSD Final Report Isa

    52/105

    50

    Crack

    S29

    1 in

    1 in

    South

    S25

    Crack

    S29

    1 in

    1 in

    South

    S25

    (a) Crack location

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    StrainRange(x10-6)

    S29

    S25

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    StrainRange(x10-6)

    S29

    S25

    (b) Measured strains

    Figure 4.17 Specimen R4: crack on lower pipe at the slot weld location

  • 8/12/2019 UCSD Final Report Isa

    53/105

    51

    Cone

    Top Side

    during Testing

    Lower

    Pipe

    Guide Ring LevelLower Ring Level

    Detail 1 Grout

    Detail 2

    Cut-out

    Piece

    Cone

    Top Side

    during Testing

    Lower

    Pipe

    Guide Ring LevelLower Ring Level

    Detail 1 Grout

    Detail 2

    Cut-out

    Piece

    Figure 4.18 Specimen R4: view of inside after cut

    Ring

    Slot Weld

    Upper Pipe

    Grout

    Ring

    Slot Weld

    Upper Pipe

    Grout

    Figure 4.19 Specimen R4: fracture surface (Detail 1)

  • 8/12/2019 UCSD Final Report Isa

    54/105

    52

    Outer Surface of Lower Pipe Slot WeldOuter Surface of Lower Pipe Slot Weld

    Figure 4.20 Specimen R4: fracture surface (Detail 2)

    4.5 FRP Repair: Specimen R5Observations made from testing of Specimens R2 and R3 revealed two additional

    weaknesses in existing welds: the slot welds connecting the lower ring to the lower pipe

    and the fillet weld connecting the upper ring to the lower pipe, both made in the field. For

    Specimen R2, cracking first occurred in the fillet weld, followed by cracking in the slot

    weld. Specimen R3 first experienced cracking in one slot weld in the early stage of

    testing. It was then decided to stop the testing at 40,000 cycles and repair the specimen

    with Fiber Reinforced Polymer (FRP) composites to prevent further cracking in the slot

    weld. The repaired specimen is designated as R5. See Figure 2.8 for the strengthening

    scheme and location.

    Figure 4.21shows the crack location and measured strain. The crack (on the top

    side) occurred at the lower pipe-to-upper ring fillet weld. Strains on the FRP material

    were also monitored during testing to identify any failure. Figure 4.22(a) shows the

    rosette strain gage locations; the gages in parentheses were located on the bottom side.

    The measured strains are provided in Figure 4.22(b). As shown, the strain ranges on the

    FRP remained constant during testing, which indicates no failure of the FRP.

  • 8/12/2019 UCSD Final Report Isa

    55/105

    53

    Testing of Specimen R5 was completed at 120,000 cycles when the length of the

    crack shown in Figure 4.21(a) was about 20 in. After testing, the FRP was removed [see

    Figure 4.23(a)] to examine the pre-existing crack. As shown in Figure 4.23(b), the

    Magnetic Particle (MT) test showed that the pre-existing crack length remained at 5 in.,

    indicating no further crack growth after the FRP composites were applied to the

    specimen. The bottom slot weld was also examined and no cracks were observed.

    Crack

    Upper Pipe

    Lower Pipe

    Upper Ring

    S11

    0.375

    Crack

    Upper Pipe

    Lower Pipe

    Upper Ring

    S11

    0.375

    (a) Crack location

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    StrainRange(x10-6

    )

    S11

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    StrainRange(x10-6

    )

    S11

    (b) Measured strains

    Figure 4.21 Specimen R5: crack at lower pipe-to-upper ring fillet weld

  • 8/12/2019 UCSD Final Report Isa

    56/105

    54

    3 ft

    R1b

    (R2b) R1y(R2y)

    R1r(R2r)

    3 ft

    R1b

    (R2b) R1y(R2y)

    R1r(R2r)

    (a) Strain gage locations

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    Strain

    Range(x10-6)

    R1bR2bR2r, R1rR2y, R1y

    0 50 100 150 2000

    500

    1000

    1500

    2000

    2500

    3000

    Number of Cycles (x 1000)

    Strain

    Range(x10-6)

    R1bR2bR2r, R1rR2y, R1y

    (b) Measured strains

    Figure 4.22 Specimen R5: measured strains on FRP

  • 8/12/2019 UCSD Final Report Isa

    57/105

    55

    FRP

    Upper

    Pipe Upper Ring

    Cut-out Location

    FRP

    Upper

    Pipe Upper Ring

    Cut-out Location

    (a) Specimen cut

    FRP

    Crack Indication by

    Magnetic Particle Test

    FRP

    Crack Indication by

    Magnetic Particle Test

    (b) Crack inspection

    Figure 4.23 Specimen R5: slot weld crack examination after FRP removal

  • 8/12/2019 UCSD Final Report Isa

    58/105

    56

    4.6 Compar ison of Test ResultsFigure 4.24 compares the fatigue resistance of the repaired specimens. For

    comparison purposes, the mean failure cycle from the conventional sleeve connection

    specimens is also shown. The failure cycles were 13,000 (Specimen R1: gusset repair),

    155,000 (Specimen R2: grout repair), 40,000 (Specimen R3: grout repair), 105,000

    (Specimen R4: cone and grout repair), and 160,000 (Specimen R5: FRP repair). Since the

    testing of Specimen R3 was completed early for the FRP repair, this specimen is

    excluded in the comparison of fatigue resistance.

    Specimen R1 showed early cracking at the gusset-to-upper ring welded joint. After

    the gusset welds failed, the specimen experienced the same crack pattern as that observed

    in the conventional connection specimens. The fatigue resistance of this specimen is

    similar to that of the conventional connection (see Figure 3.10).

    Specimens R2 and R4 performed better, showing significant improvements in

    fatigue resistance. Cement grouting (above the upper ring) with steel jackets in Specimen

    R2, and the use of a steel cone (above the upper ring) in Specimen R4 effectively

    prevented cracks at the upper pipe-to-upper ring fillet welded joint. However, cracks

    occurred at the next weak locations (i.e., the lower pipe-to-upper ring fillet weld and the

    slot welds). As demonstrated in the testing of Specimens R3 and R4, grouting below the

    upper ring was not effective in preventing cracks at the next weak locations, although thefatigue life of the entire connection was significantly improved.

    Based on visual inspections of the fractured surface of the lower pipe at the slot-

    weld locations, the cracks appeared to be caused by high bending stresses on the lower

    pipe with cracking initiated from the inner surface of the pipe (likely at the slot-weld

    terminations of stress concentration). This observation indicates that the slot welds, when

    used, should be oriented such that the bending stresses at the slot-weld locations are

    minimized. As shown in Figure 4.4, the slot welds of Specimen R2 were located away

    from the top and bottom sides, where the highest bending stresses on the pipe section

    were developed in testing. The slot-weld crack length at 132,000 cycles was 9 in (see

    Figure 4.6). On the other hand, Specimen R3 experienced cracking at the slot weld in the

    early stage of testing (the crack length was 5 in at 40,000 cycles), possibly due to a

    different slot-weld orientation. As shown in Figure 4.11(a), the slot weld of Specimen R3

  • 8/12/2019 UCSD Final Report Isa

    59/105

    57

    was located near the top side, where the bending stress was higher. In actual applications,

    the optimal slot weld locations are 45 degrees from the design longitudinal and transverse

    axis of the cross section.

    The cracks on the lower pipe-to-upper ring joint occurred at the fillet weld, not in

    the base metal. The failure of this fillet weld also did not significantly contribute to the

    reduction of the specimen global stiffness during testing. Since the failure was in the fillet

    weld, the fatigue resistance of this detail can be increased with a larger size of fillet weld

    in repair.

    Specimen R5, which used FRP as a repair scheme for the slot welds, was effective

    in enhancing the fatigue resistance. An inspection after the FRP removal indicated no

    further growth of the pre-existing crack.

    0

    50

    100

    150

    200

    FailureCycles(x103)

    R1

    Specimen No.

    R2 R3 R4R5

    GussetRepair

    GroutRepair

    (TestingStoppedEarly

    forFRP

    Repair)

    Grout

    Repair

    Cone&

    Grout

    Repair

    FRP

    Repair

    mean failure cycleof conventional

    sleeve connections0

    50

    100

    150

    200

    FailureCycles(x103)

    R1

    Specimen No.

    R2 R3 R4R5

    GussetRepair

    GroutRepair

    (TestingStoppedEarly

    forFRP

    Repair)

    Grout

    Repair

    Cone&

    Grout

    Repair

    FRP

    Repair

    mean failure cycleof conventional

    sleeve connections

    Figure 4.24 Comparison of fatigue resistance of repair connections

  • 8/12/2019 UCSD Final Report Isa

    60/105

    58

    5. TEST RESULTS OF ALTERNATIVE CONNECTIONS FOR NEWCONSTRUCTION

    5.1 Modified Sleeve Connection Details5.1.1 Specimen A1

    The connection details of Specimen A1 were the same as those of Specimen C3,

    except that no weld was specified on the top of the fillet-welded joint between the upper

    pipe and the upper ring; only the bottom side is welded. See Figure 2.9(a) for the

    connection details. The intent of this detail was to eliminate the high stress conce