Upload
jorgevelso
View
219
Download
0
Embed Size (px)
Citation preview
8/12/2019 UCSD Final Report Isa
1/105
STRUCTURAL SYSTEMS
RESEARCH PROJECT
Report No.
SSRP- 11/07 FATIGUE TESTS OF WELDED CONNECTIONS
IN CANTILEVERED STEEL SIGN STRUCTURES
by
HYOUNG-BO SIM
CHIA-MING UANG
Final Report Submitted to International Sign Association
October 2011Department of Structural Engineering
University of California, San Diego
La Jolla, California 92093-0085
8/12/2019 UCSD Final Report Isa
2/105
University of California, San Diego
Department of Structural Engineering
Structural Systems Research Project
Report No. SSRP-11/07
Fatigue Tests of Welded Connections in Cantilevered
Steel Sign Structures
by
Hyoung-Bo Sim
Postdoctoral Researcher
Chia-Ming Uang
Professor of Structural Engineering
Final Report Submitted to International Sign Association
Department of Structural EngineeringUniversity of California, San Diego
La Jolla, California 92093-0085
October 2011
8/12/2019 UCSD Final Report Isa
3/105
i
ACKNOWLEDGEMENTS
Funding for this research was provided by the International Sign Association
(ISA). We would like to thank Mr. Bill Dundas, ISA Director of Technical andRegulatory Affairs, and the ISA Mechanical and Structural Subcommittee, chaired by
Mr. Wes Wilkens, for providing guidance in this research. We would also like to thank
Mr. Jack Lester for preparing the specimen drawings and arranging the fabrication and
shipping of most of the specimens. Additionally, we would like to thank Mr. Roy Flahive
for coordinating efforts at the laboratory on test specimen preparation, repairs and
inspections. Union Metal (Canton, OH) donated the tapered-pole specimen (A7) and Fyfe
Company LLC (San Diego, CA) donated materials and services for the Fiber Reinforced
Polymer (FRP) repair.
The testing was conducted in the Charles Lee Powell Structural Components
Laboratory at the University of California, San Diego. Assistance from the laboratory
staff is much appreciated.
8/12/2019 UCSD Final Report Isa
4/105
ii
ABSTRACT
Freestanding (cantilevered) steel sign structures have been widely used by
commercial and retail business for many years. The actual probability of failure forcantilevered sign structures due to wind-induced vibration is relatively small. In this case,
failure is defined as fatigue cracking which causes collapse or loss of a structures
serviceability. While the majority of these structures have performed well in long-term
use, however, some structures have been damaged or destroyed.
This type of structure is flexible, has a low damping and, under certain
circumstances, can be prone to fatigue-type cracking due to wind-induced vibration.
Cracks at the sleeve connections, some resulting in sign failures, have been reported
when the wind speed was significantly below that used in design. In connection with its
ongoing efforts to support the safety and acceptability of signage products, the
International Sign Association (ISA) made a decision to investigate potential remedies by
sponsoring the tests described in this report.
Fatigue tests of seventeen full-scale connection details were conducted to evaluate
their relative fatigue resistance. Test specimens included four conventional (with or
without a guide ring), five repaired (with various combinations of welded gussets, grout,
steel cones or jackets and Fiber Reinforced Polymer composites), and eight alternative
connection details for new construction.
Testing demonstrated that conventional welded sleeve connections had a
relatively low fatigue resistance. All four specimens showed the same cracking pattern as
commonly observed in the field on damaged or failed structures. The use of a guide ring
had a minimal effect on the fatigue resistance. After testing, the damaged conventional
specimens were repaired with various schemes to evaluate their effectiveness.
A gusset-repaired specimen also showed relatively low fatigue resistance. Steel-
jacketed cement grouting, or the use of a welded steel cone above the upper ring,
significantly improved the fatigue resistance at the most commonly observed failure
location, although fatigue cracking later occurred at the next weak locations (i.e., the
lower pipe-to-upper ring fillet weld and the slot welds, which also are prone to fatigue).
Grouting the sleeve region or using welded patch plates did not improve the fatigue
8/12/2019 UCSD Final Report Isa
5/105
iii
resistance of the slot welds. An FRP-repair scheme for cracked slot welds effectively
prevented further crack growth.
Some promising alternative connections that can potentially be used for new
construction were experimentally evaluated. A bolted match-plate connection performed
relatively poorly. But a revised sleeve connection incorporating a one-sided, bottom-only
fillet weld detail at the upper pipe-to-upper ring joint was effective in enhancing the
fatigue performance compared to the conventional sleeve connections. To avoid cracking
at slot welds, the use of grout between the pipes in the sleeve region significantly
increased the fatigue resistance. Using a welded cone to provide a smooth transition
between the pipes also showed improved performance. A tapered slip-joint connection,
which requires no welded joints between the pipe sections, substantially outperformed all
of the other specimens tested.
8/12/2019 UCSD Final Report Isa
6/105
iv
TABLE OF CONTENTS
ACKNOWLEDGEMENTS....................................................................................................... i
ABSTRACT ........................................................................................................................ ii
TABLE OF CONTENTS......................................................................................................... iv
LIST OF TABLES................................................................................................................... vi
LIST OF FIGURES ................................................................................................................ vii
1. INTRODUCTION........................................................................................................... 10
1.1 Problem Statements ................................................................................................ 10
1.2 Past Research .......................................................................................................... 10
1.3 Objectives and Scope.............................................................................................. 13
2. TEST PROGRAM........................................................................................................... 14
2.1 Test Setup................................................................................................................ 14
2.2 Test Matrix.............................................................................................................. 15
2.3 Connection Details.................................................................................................. 16
2.3.1 Conventional Welded Sleeve Connection Details ....................................... 16
2.3.2 Repaired Connection Details ....................................................................... 19
2.3.3 Alternative Connection Details.................................................................... 24
2.4 Loading Scheme...................................................................................................... 27
2.5 Instrumentation and Crack Inspections................................................................... 273. TEST RESULTS OF CONVENTIONAL CONNECTIONS ......................................... 29
3.1 Introduction............................................................................................................. 29
3.2 Conventional Connection Details without Guide Ring .......................................... 29
3.2.1 Specimen C1 ................................................................................................ 29
3.2.2 Specimen C2 ................................................................................................ 31
3.3 Conventional Connection Details with Guide Ring................................................ 33
3.3.1 Specimen C3 ................................................................................................ 33
3.3.2 Specimen C4 ................................................................................................ 34
3.4 Comparison of Test Results.................................................................................... 35
4. TEST RESULTS OF REPAIRED CONNECTIONS ..................................................... 36
4.1 Introduction............................................................................................................. 36
4.2 Gusset Repair: Specimen R1 .................................................................................. 36
4.3 Steel-Jacketed and Cement-Grouted Repair ........................................................... 38
8/12/2019 UCSD Final Report Isa
7/105
v
4.3.1 Introduction.................................................................................................. 38
4.3.2 Specimen R2 ................................................................................................ 38
4.3.3 Specimen R3 ................................................................................................ 44
4.4 Steel Cone and Cement Grout Repair: Specimen R4 ............................................. 45
4.5 FRP Repair: Specimen R5 ...................................................................................... 52
4.6 Comparison of Test Results.................................................................................... 56
5. TEST RESULTS OF ALTERNATIVE CONNECTIONS FOR NEW
CONSTRUCTION .......................................................................................................... 58
5.1 Modified Sleeve Connection Details ...................................................................... 58
5.1.1 Specimen A1................................................................................................ 58
5.1.2 Specimen A2................................................................................................ 64
5.1.3 Specimen A3................................................................................................ 69
5.1.4 Specimen A4................................................................................................ 75
5.2 Cone Transition Connection Details....................................................................... 79
5.2.1 Introduction.................................................................................................. 79
5.2.2 Specimen A5................................................................................................ 79
5.2.3 Specimen A6................................................................................................ 81
5.3 Tapered Slip Joint: Specimen A7 ........................................................................... 82
5.4 Bolted Match-Plate Connection: Specimen A8 ...................................................... 83
6. ANALYSIS OF TEST RESULTS .................................................................................. 87
6.1 Introduction............................................................................................................. 87
6.2 Comparison of Fatigue Resistance.......................................................................... 88
6.2.1 Specimens C1 to C4..................................................................................... 88
6.2.2 Specimen R1 (Gusset-Repair)...................................................................... 91
6.2.3 Specimens R2 and R4 (Grout- or Cone-Repair) .......................................... 91
6.2.4 Specimens R5 (FRP-Repair)........................................................................ 92
6.2.5 Specimens A1 and A2 (Modified Sleeve Connection) ................................ 92
6.2.6 Specimens A3 and A4 (Modified Sleeve Connection) ................................ 93
6.2.7 Specimens A5 and A6 (Cone Transition) .................................................... 93
6.2.8 Specimen A7 (Tapered Slip-Joint)............................................................... 93
6.2.9 Specimen A8 (Bolted Match-Plate Connection).......................................... 93
7. SUMMARY AND CONCLUSIONS.............................................................................. 94
REFERENCES ...................................................................................................................... 97
APPENDIX A. APPLIED LOAD TIME HISTORY ............................................................. 98
8/12/2019 UCSD Final Report Isa
8/105
vi
LIST OF TABLES
Table 2.1 Test matrix ........................................................................................................ 15
Table 6.1 Detail category constant and threshold (AASHTO 2010) ................................ 90
8/12/2019 UCSD Final Report Isa
9/105
vii
LIST OF FIGURES
Figure 1.1 Typical configuration of a sign structure......................................................... 12
Figure 1.2 Assumed force transfer mechanism at sleeve connection (Jones 1998).......... 12
Figure 1.3 Typical failure locations of sign structures ..................................................... 12Figure 1.4 Proposed connection details (Sim and Uang 2008)......................................... 13
Figure 2.1 Test setup......................................................................................................... 14
Figure 2.2 Overall configuration of test specimens.......................................................... 17
Figure 2.3 Connection details of Specimens C1 to C4 ..................................................... 18
Figure 2.4 Connection details of Specimen R1 ................................................................ 20
Figure 2.5 Grout-repaired region of Specimens R2 to R4................................................ 20
Figure 2.6 Connection details of Specimens R2 and R3 .................................................. 21
Figure 2.7 Connection details of Specimen R4 ................................................................ 22
Figure 2.8 Connection details of Specimen R5 ................................................................ 23
Figure 2.9 Connection details of Specimens A1 and A2.................................................. 25
Figure 2.10 Connection details of Specimens A3 and A4................................................ 25
Figure 2.11 Connection details of Specimens A5 and A6................................................ 26
Figure 2.12 Connection details of Specimen A7 .............................................................. 26
Figure 2.13 Connection details of Specimen A8 .............................................................. 27
Figure 2.14 Loading scheme............................................................................................. 28
Figure 2.15 Sample instrumentation layout (Specimen A1)............................................. 28
Figure 3.1 Specimen C1: observed crack ......................................................................... 30
Figure 3.2 Specimen C1: measured strains near crack location ....................................... 31
Figure 3.3 Specimen C1: strain profiles near fillet weld toe (at 1500 cycles).................. 31
Figure 3.4 Specimen C2: observed crack ......................................................................... 32
Figure 3.5 Specimen C2: measured strains near crack location ....................................... 32
Figure 3.6 Specimen C3: observed crack ......................................................................... 33
Figure 3.7 Specimen C3: measured strains near crack location ....................................... 34
Figure 3.8 Specimen C4: observed crack ......................................................................... 34
Figure 3.9 Specimen C4: measured strains near crack location ....................................... 35
Figure 3.10 Comparison of fatigue resistance of conventional connections .................... 35
Figure 4.1 Specimen R1: gusset connection before testing .............................................. 37
8/12/2019 UCSD Final Report Isa
10/105
viii
Figure 4.2 Specimen R1: crack at fillet weld of Gusset No. 4.......................................... 38
Figure 4.3 Specimen R2: repair procedure ....................................................................... 40
Figure 4.4 Specimen R2: crack locations ......................................................................... 41
Figure 4.5 Specimen R2: cracks at lower pipe-to-upper ring fillet weld.......................... 41
Figure 4.6 Specimen R2: crack on lower pipe at slot weld location................................. 42
Figure 4.7 Specimen R2: measured strains near lower pipe-to-upper ring welded joint.. 42
Figure 4.8 Specimen R2: grout condition after testing..................................................... 43
Figure 4.9 Specimen R2: fracture surface at slot weld location ....................................... 43
Figure 4.10 Specimen R2: measured flexural strain distribution in grout region............. 44
Figure 4.11 Specimen R3: observed crack on slot weld................................................... 45
Figure 4.12 Specimen R3: measured strains near crack location ..................................... 45
Figure 4.13 Specimen R4: repair procedure ..................................................................... 47
Figure 4.14 Specimen R4: connection after repair ........................................................... 48
Figure 4.15 Specimen R4: crack locations ....................................................................... 48
Figure 4.16 Specimen R4: crack at lower pipe-to-upper ring fillet weld ......................... 49
Figure 4.17 Specimen R4: crack on lower pipe at the slot weld location......................... 50
Figure 4.18 Specimen R4: view of inside after cut........................................................... 51
Figure 4.19 Specimen R4: fracture surface (Detail 1) ...................................................... 51
Figure 4.20 Specimen R4: fracture surface (Detail 2) ...................................................... 52
Figure 4.21 Specimen R5: crack at lower pipe-to-upper ring fillet weld ......................... 53
Figure 4.22 Specimen R5: measured strains on FRP........................................................ 54
Figure 4.23 Specimen R5: slot weld crack examination after FRP removal.................... 55
Figure 4.24 Comparison of fatigue resistance of repair connections................................ 57
Figure 5.1 Specimen A1: connection................................................................................ 59
Figure 5.2 Specimen A1: cracks on slot welds at lower ring (at 45,000 cycles) .............. 60
Figure 5.3 Specimen A1: repair procedure of damaged slot welds .................................. 60
Figure 5.4 Specimen A1: needle peening of patch plate weld.......................................... 61
Figure 5.5 Specimen A1: crack at patch plate location .................................................... 61
Figure 5.6 Specimen A1: crack on slot weld location at guide ring level ........................ 62
Figure 5.7 Specimen A1: measured strains....................................................................... 63
Figure 5.8 Specimen A1: examination of inside after testing........................................... 63
8/12/2019 UCSD Final Report Isa
11/105
ix
Figure 5.9 Specimen A2: assembly procedure ................................................................. 65
Figure 5.10 Specimen A2: measured strains near upper pipe-to-upper ring .................... 66
Figure 5.11 Specimen A2: disassembly after testing........................................................ 67
Figure 5.12 Specimen A2: crack at upper pipe-to-upper ring welded joint...................... 68
Figure 5.13 Specimen A3: crack locations on slot welds ................................................. 70
Figure 5.14 Specimen A3: typical crack pattern at slot weld location ............................. 70
Figure 5.15 Specimen A3: measured strains near crack locations.................................... 71
Figure 5.16 Specimen A3: specimen cut after testing ...................................................... 71
Figure 5.17 Specimen A3: crack at Detail 1..................................................................... 72
Figure 5.18 Specimen A3: crack at Detail 2 (guide ring level) ........................................ 73
Figure 5.19 Specimen A3: fracture surface at Detail 2 (guide ring level)........................ 73
Figure 5.20 Specimen A3: crack at Detail 3 (lower ring level)........................................ 74
Figure 5.21 Specimen A3: crack at Detail 4 (lower ring level)........................................ 74
Figure 5.22 Specimen A4: crack locations ....................................................................... 75
Figure 5.23 Specimen A4: crack pattern at gusset-to-upper ring fillet weld.................... 76
Figure 5.24 Specimen A4: crack pattern at slot weld location ......................................... 77
Figure 5.25 Specimen A4: crack pattern at gusset-to-upper pipe welded joint................ 78
Figure 5.26 Specimen A5: observed crack ....................................................................... 79
Figure 5.27 Specimen A5: crack view from inside........................................................... 80
Figure 5.28 Specimen A6: observed cracks...................................................................... 81
Figure 5.29 Specimen A7: assembly using come-along hoists......................................... 82
Figure 5.30 Specimen A7: examination of inside after testing......................................... 83
Figure 5.31 Specimen A8: observed crack ....................................................................... 84
Figure 5.32 Specimen A8: examination of inside after testing......................................... 85
igure 5.33 Specimen A8: fracture surface......................................................................... 86
Figure 6.1 Summary of fatigue resistance ........................................................................ 88
Figure 6.2 S-N curves (AASHTO 2010) .......................................................................... 91
Figure A.1 Specimen C1: Applied load time history........................................................ 98
Figure A.1 Specimen C2: Applied load time history........................................................ 98
Figure A.1 Specimen C3: Applied load time history........................................................ 98
Figure A.1 Specimen C4: Applied load time history........................................................ 99
8/12/2019 UCSD Final Report Isa
12/105
10
1. INTRODUCTION1.1 Problem Statements
Freestanding (cantilevered) steel sign structures have been widely used for
commercial and retail signs. A common configuration for this type of structure is shown
schematically in Figure 1.1(a). The pole supporting the sign cabinet consists of
progressively smaller diameter pipes, with the smaller pipes inserted into larger pipes as
per a commonly used welded sleeve connection shown in Figure 1.1(b). Both the lower
and upper rings, as well as an optional guide ring which aids in alignment of the pipe
sections during erection, are first shop-welded to the upper pipe. In the field, the upper
ring is then fillet-welded to the top of the lower (outer) pipe. The lower and guide rings
are also slot- or plug-welded to the lower pipe in the field.
It is a common practice in design that the moment at the splice location is resisted
by a force couple as shown in Figure 1.2 (Jones 1998). This simplified static design
procedure has been used for decades and has served well for the majority of sign
structures. But this type of structure is flexible, has a low damping, and can be prone to
fatigue-type cracking due to wind-induced vortex shedding. Damage and collapses of
sign structures due to fracture at the sleeve connections, even with no apparent defects in
the construction, have been reported when the wind speed was far below that used in
design. Figure 1.3 shows the typical crack locations of sign structures. As shown in
Figure 1.3(a) and (b), the fatigue-type failure occurs most often in the upper pipes at the
toe of the fillet-weld between the upper pipe and the upper ring. Although the sleeve
connections have sometimes been strengthened or repaired by vertical gussets or C-
channel gussets, fatigue cracks at the gusset-to-upper pipe (or upper ring) welded joint
have been observed; see Figure 1.3(c) and (d) for the typical crack locations.
1.2 Past ResearchCase studies on ten failed sign structures and the associated finite element analyses
have been performed in an attempt to identify the cause of failure at the welded sleeve
connection (Sim and Uang 2008). It was concluded that the fatigue-type cracks in the
8/12/2019 UCSD Final Report Isa
13/105
11
upper pipe initiated at the toe of the fillet weld connecting the upper pipe to the upper
ring. The crack then propagated into the pipe section and caused failure.
Finite element analysis of a typical sign structure showed a very high, geometry-
induced stress concentration at this location. The following observations were also made
from the finite element analysis. Within the practical range of the ring plate thickness,
only 60% to 80% of the moment was transferred through the horizontal force couple. The
remaining portion was transferred by the bending of the ring plates, which is a
mechanism not reflected in a simplified, conventional design procedure. The stress
concentration at the top fillet weld became more severe if the upper pipe was allowed to
move due to defective or damaged slot welds. Based on case studies of damaged
structures and other available evidence, it was determined that a common practice of
strengthening or repairing the upper ring welded joint by installing welded gusset plates
is not effective in mitigating fatigue cracking. Adding these gussets simply moves the
critical stress concentration location to the top end of the gussets where fatigue-type
cracking also has been observed. The use of a guide ring had a minimal effect on the
stress distribution.
Based on the observations from case studies and finite element analysis results,
two alternative connection details were proposed (Sim and Uang 2008). Figure 1.4(a)
shows the first proposed connection detail. The detail and fabrication of this connection
are very similar to those of the conventional sleeve connection. However, no weld is
specified on the top side of the fillet-weld joint between the upper ring and upper pipe;
only the bottom side is welded. The second proposed connection detail is shown in
Figure 1.4(b). Instead of using a pair of rings to transfer the moment through a horizontal
force couple, a structural filler material (e.g., concrete or mortar) is used to fill the gap
between the two pipes. The lateral moment is transferred through the bearing action of
the filler material between the pipes.
8/12/2019 UCSD Final Report Isa
14/105
12
Sign
Cabinet
Steel Pipe
Sleeve
Connection
Sign
Cabinet
Steel Pipe
Sleeve
Connection
Upper Ring
Lower Ring
Upper Pipe
Lower Pipe
Guide Ring
(Optional)
(a) Elevation (b) Sleeve connection
Figure 1.1 Typical configuration of a sign structure
M
H = M/d
d
H+V
V
M
H = M/d
d
H+V
V
Figure 1.2 Assumed force transfer mechanism at sleeve connection (Jones 1998)
Upper Pipe
Upper
Ring
Crack Upper Pipe
Upper
Ring
Crack
Upper RingUpper Ring
(a) Conventional sleeve connection (b) View of lower pipe after failure
Lower
Pipe
Crack
Upper Pipe
Lower
Pipe
Crack
Upper Pipe
C-Channel
Crack
Upper
Ring
C-Channel
Crack
Upper
Ring
(c) Stiffened gusset plate connection (d) Stiffened C-channel gusset connection
Figure 1.3 Typical failure locations of sign structures
8/12/2019 UCSD Final Report Isa
15/105
13
UpperRing
UpperPipe
LowerPipe
Typ.
Lower
Ring
Filler (Mortar
or Concrete)
Lower Ring
Upper Pipe
Lower Pipe
Optional
Guide Fins
Typ.
(a) Connection detail 1 (b) Connection detail 2
Figure 1.4 Proposed connection details (Sim and Uang 2008)
1.3 Objectives and ScopeThe objective of this research was to evaluate the performance of various
alternative connection details for new construction and retrofit or repair of sign
structures, and to compare the results to those derived from similar tests of conventional-
type sleeve connections. Fatigue tests of seventeen different connection details were
conducted to evaluate the relative fatigue resistance of these connection details.
8/12/2019 UCSD Final Report Isa
16/105
14
2. TEST PROGRAM2.1 Test Setup
Figure 2.1 shows the test setup. The specimens were tested in the horizontal
position using a hydraulic actuator acting at the free end to simulate wind-induced
bending stresses at the connections. The lower pipe end was welded to a base plate and
was anchored to a reaction wall. Such base boundary was not intended to simulate the
actual base details of sign structures under study. To rule out any potential fatigue failure
at this location, it was decided to clamp the specimen 22 in. away from the specimen base
by a pair of concrete collars such that the bending stresses at the base plate weld was
greatly reduced.
ReactionWall Upper PipeLower Pipe
North
8'-6" 12'-6"
21'
3'
22"
Concre Blocks for
Fixed Boundary ConditionMo
untingPL.
Strong Floor
Hydraulic Actuator
Actuator Corbel
(a) Elevation
(b) Photo view
Figure 2.1 Test setup
8/12/2019 UCSD Final Report Isa
17/105
15
2.2 Test Matr ixA total of seventeen, 21-ft-long full-scale specimens were tested. Table 2.1shows
the test matrix. Specimens included four conventional (with or without a guide ring), five
repaired (by welded gussets, grout, or Fiber Reinforced Polymer (FRP) composites), and
eight alternative connection details. ASTM A53 Grade B steel for the pipes and A36 steel
for the plates were used for the specimens.
Table 2.1 Test matrix
Connection TypeSpecimen
DesignationConnection Details
C1 No guide ring usedNo Guide Ring
C2 Specimen C1 + peeningC3 Guide ring usedConventional
Guide RingC4
Specimen C3 + gussets
(gussets not connected to upper ring)
Gusset Repair R1 Gusset repair of Specimen C1
R2 Grout repair of Specimen C3
R3 Grout repair of Specimen C2Grout Repair
R4Steel cone & grout repair of
Specimen C4
Repair
FRP Repair R5 FRP repair of Specimen R3
A1
Conventional weld details, but without
top fillet weld at upper pipe-to-upper
ring
A2 Grout + no field welds and slot welds
A3No fillet weld at lower pipe-to-upper
ring + gussets + peening
ModifiedSleeve Connection
A4No fillet weld at upper pipe-to-upper
ring + gussets
A5Conical transition connection betweenupper and lower pipes
Cone A6 Specimen A5 + peening
Tapered A7 Tapered slip joint
Alternative
Bolted A8 Bolted match-plate connection
8/12/2019 UCSD Final Report Isa
18/105
16
2.3 Connection Details2.3.1 Conventional Welded Sleeve Connection Details
A total of four conventional sleeve connections were tested. The objectives of
testing were to (1) evaluate the failure mode as compared to field observations, (2)establish a baseline fatigue resistance for comparison with those of improved connection
details, (3) assess the significance of guide ring in improving structural performance, and
(4) assess the effect of post-weld peening treatment. After testing, these specimens were
also repaired and re-tested to evaluate the effectiveness of several repair schemes.
The overall configuration of the test specimens is shown in Figure 2.2. The
diameters of the upper and lower pipes were 18 in and 22 in, respectively. The specified
thickness of the pipes was 3/8 in (0.375 in); the measured thickness was approximately
0.35 in. The sleeve length between the upper and lower ring plate levels was 35 in.
Figure 2.3 shows the connection details of each specimen; the slot-weld details
are also provided in Figure 2.3(c). Specimens C1 and C2 did not incorporate guide rings
and were nominally identical, except that Specimen C2 received a post-weld peening
treatment at the upper pipe-to-upper ring fillet weld. Both Specimens C3 and C4 had a
guide ring, but the latter had a total of 12 gusset plates welded to the upper pipe and the
upper ring. Specimen C4 had no weld specified on the lower pipe-to-upper ring joint per
design, but this joint was welded in error during fabrication. Therefore, it was decided to
modify the details of Specimen C4 such that the lower ends of the gussets near the upper
ring were removed. Since the structural detail of the modified specimen was similar to
that of the conventional sleeve connection, Specimen C4 was grouped with the
conventional connections, assuming that the effect of the partially connected gussets on
the fatigue performance of the specimen was insignificant.
8/12/2019 UCSD Final Report Isa
19/105
17
12'-6"
8'-6"
21'
Upper Pipe
(O.D. 18" x 3/8" )
Lower Pipe
(O.D. 22" x 3/8" )
3'
Figure 2.2 Overall configuration of test specimens
8/12/2019 UCSD Final Report Isa
20/105
18
Peening
(Specimen C2 Only)
Slot Weld
6-1/2
1" Thk Guide Ring
(Specimen C3 Only)
1" Thk Lower Ring
3/16
3/8
3/16
1/41/4
1/2
5/8" Thk Upper Ring
36
(a) Specimens C1 to C3
Slot Weld
6-1/21" Thk Guide Ring
1" Thk Lower Ring
3/16
3/8
3/16
1/41/4
5/8" Thk Upper Ring
36
10
3/8" Thk Gusset, Typ
1/41/4
Typ
(b) Specimen C4
30
Lower Pipe
3
11/16
Lower or Guide
Ring PL.
(c) Slot weld details
Figure 2.3 Connection details of Specimens C1 to C4
8/12/2019 UCSD Final Report Isa
21/105
19
2.3.2 Repair ed Connection DetailsThe investigated repair scheme included (1) welded gusset plates, a procedure
commonly used in practice, (2) cement grout with steel jacketing, and (3) Fiber
Reinforced Polymer strengthening. The objective was to develop effective and
economical procedures for not only repairing damaged sign structures but also for retrofit
or new construction.
The details of the repair procedure investigated in this study are presented below.
Gusset-Repaired Connection (Specimen R1)
Specimen R1 is the repaired Specimen C1. After testing of Specimen C1, the
damaged fillet weld between the upper pipe and upper ring was repaired, and gusset
plates (A36 steel) were then added to strength the connection. Specimen R1 represents a
common practice of attempting to strengthen or repair sleeve connections by installing
gussets. Figure 2.4 shows the gusset connection details. Six 3/8-in.-thick gussets were
fillet-welded to the upper pipe and the upper ring. A slight modification on the gusset
weld was made such that the fillet weld at the tip of the gusset was not wrapped around
for three of the gussets (located on the top side in the test setup), while welds on the other
three gussets were wrapped around (located on the bottom side in the test setup).
Cement Grout-Repaired Connection (Specimens R2 to R4)
Figure 2.5shows the region where the connection was strengthened by grouting.
Specimens R2 and R3 had a steel collar installed above the upper ring, and Specimen R4
used a steel cone. Specimens R2 and R3 were grouted between the steel collar and the
upper pipe. Compared to Specimen R2, Specimen R3 was also grouted between the two
pipes in the sleeve region. Specimen R4 was grouted only in the sleeve region. The
connection details of the repair specimens are shown in Figure 2.6and Figure 2.7. The
repair procedures are described in Section 4.3.
FRP-Repaired Connection (Specimen R5)
Specimen R5 was the repaired Specimen R3. After testing of Specimen R3, Fiber
Reinforced Polymer (FRP) composites were used to strengthen the cracked lower pipe at
the slot weld. Figure 2.8 shows the connection details. The repair was performed by
FYFE CO. LLC. The FRP was applied symmetrically with respect to the crack location
8/12/2019 UCSD Final Report Isa
22/105
20
in the longitudinal direction. Five layers of FRP (oriented longitudinally) and three layers
of FRP (oriented transversely) were applied, as shown in Figure 2.8. For surface
preparation, a 4-in grinder with a rough wire wheel was first used to remove the mill
scale of the steel, and then an 80-grit flapper disk was used for a clean finish. Two
separate epoxy resins were used. Epoxy resin (Tyfo MB-3) was used for improved
adhesion to the metal and between layers of the fabric, and epoxy resin (Tyfo S) was used
to saturate the fabric.
1/41/4
Typ
3/8" Thk Gusset PL (6 Total)
10
1/2
Figure 2.4 Connection details of Specimen R1
6'
3'
3'
(a) Specimen R2 (b) Specimen R3 (c) Specimen R4
Figure 2.5 Grout-repaired region of Specimens R2 to R4
8/12/2019 UCSD Final Report Isa
23/105
21
3"
6"
6"
6"
6"
6"
3"
3'-0"
3 8"
2'-11"
No Weld
No Weld
1 / 4
Non-Shrink Grout
See Detail
R = 0 to 1/4
f = 0 to 1/8
= 45
R = 0 to 1/4
f = 0 to 1/8
= 45
(a) Elevation (b) CJP weld details
5/16PJP
Same size Pipe
Tack Weld
Nuts in Place
1/2" x 1.5" Bolts
1/4" x 3" Flat Bar
(Yellow Zinc Grade 8, Snug-Tight)
Tack Weld
Nuts in Place
1/2" x 1.5" Bolts
1/4" x 3" Flat Bar
(Yellow Zinc Grade 8, Snug-Tight)
(c) Exploded view (d) Plan view of splice sleeve
Figure 2.6 Connection details of Specimens R2 and R3
8/12/2019 UCSD Final Report Isa
24/105
22
3 ft3 ft
(a) Elevation (b) Exploded view
(c) Detail A
(d) Detail B (e) Detail C
Figure 2.7 Connection details of Specimen R4
8/12/2019 UCSD Final Report Isa
25/105
23
32"
40"
24"
24"
Apply 5 Layers of FRP,
Oriented Longitudinally
Taper 2 LayersEvery 4 inches
Apply 2 Layers of FRP,Oriented Transversely Overtop
the Longitudinal Fiber
Section A-A
32"
40"
24"
24"
Apply 5 Layers of FRP,
Oriented Longitudinally
Taper 2 LayersEvery 4 inches
Apply 2 Layers of FRP,Oriented Transversely Overtop
the Longitudinal Fiber
Section A-A
(a) Elevation
APPLY 5 LAYERS OF THE
SCH-41-2X SYSTEM (SECOND),
ORIENTED LONGITUDINALLY
APPLY 2 LAYERS OF THE
SCH-41-2X SYSTEM (LAST),
ORIENTED TRANSVERSELY
0-1/2" GAP, TYP.
22"
21.25"
APPLY 1 LAYER OF THE TYFO
WEB SYSTEM (FIRST) TO ACT AS A
DIELECTRIC BARRIER TO THE STEEL
6" OVERLAP, TYP.
(b) Cross section (Section A-A)
Figure 2.8 Connection details of Specimen R5
8/12/2019 UCSD Final Report Isa
26/105
24
2.3.3 Alternat ive Connection DetailsModified Sleeve Connection Details (Specimens A1 to A4)
Specimen A1, shown in Figure 2.9(a), used the same connection details as
Specimen C3, except that no weld was specified on the top of the fillet-welded jointbetween the upper pipe and the upper ring; only the bottom side was welded. Specimen
A2, shown in Figure 2.9(b), also eliminated the top-side fillet weld like Specimen A1.
But slot welds were not used to avoid potential cracking at these locations. Instead, the
gap between the two pipes in the sleeve region was filled by grout after the upper pipe
was inserted into the lower pipe. Furthermore, the lower pipe-to-upper ring field fillet
weld was eliminated.
The connection details of Specimens A3 and A4 are shown in Figure 2.10. Each
specimen used a total of twelve gusset plates; see Figure 2.10(b) for the gusset details.
Both specimens had similar connection details, but the weld detail in the sleeve region of
each specimen was slightly different. While Specimen A3 used no weld at the lower
pipe-to-upper ring joint, Specimen A4 used no weld at the upper pipe-to-upper ring joint.
Cone Transition Connection Details (Specimens A5 to A6)
Specimens A5 and A6 incorporated a steel conical section between the upper and
lower pipes. Both specimens were identical, except that Specimen A6 received a post-
weld peening treatment. The connection details are provided in Figure 2.11. Complete-
joint-penetration (CJP) welds were used to connect the cone to the pipes.
Tapered Slip-Joint (Specimen A7)
Specimen A7, shown in Figure 2.12, incorporated a tapered slip-joint between the
two pipes. The upper pipe was slipped into the lower pipe until a target slip engagement
length (= 38 in) was achieved. No welds were needed to connect the two pipes.
Bolted Match-Plate Connection Details (Specimen A8)
Specimen A8 incorporated a bolted match-plate connection between the upper
and lower pipes. The connection details are shown in Figure 2.13. Each pipe was CJP-
welded to a circular match plate in the shop. Two pipe sections were then connected by
8/12/2019 UCSD Final Report Isa
27/105
25
pretension bolting of two match plates in the field. No field welding is required for this
type of connection.
Slot Weld
6-1/2
1" Thk Guide Ring
1" Thk Lower Ring
3/16
3/8
1/41/4
1/2
5/8" Thk Upper Ring
36
No Weld at Top
No Weld
No Weld at Top
3/8
1/4
1/4
Grout
No Slot Weld
(a) Specimen A1 (b) Specimen A2
Figure 2.9 Connection details of Specimens A1 and A2
1" Thk Lower Ring
1/41/4
5/8" Thk Upper Ring
Gusset, Typ
3/83/8
3/163/16Peening
Specimen A4
Only
Specimen A3 Only
Slot Weld
1" Thk Guide Ring
(12 Total)
1" Thk Lower Ring
1/41/4
5/8" Thk Upper Ring
Gusset, Typ
3/83/8
3/163/16Peening
Specimen A4
Only
Specimen A3 Only
Slot Weld
1" Thk Guide Ring
(12 Total)
(a) Specimens A3 and A4 (b) Gusset details
Figure 2.10 Connection details of Specimens A3 and A4
8/12/2019 UCSD Final Report Isa
28/105
26
Figure 2.11 Connection details of Specimens A5 and A6
15'-8"
1'-758
"
1'-212
"
12'-6"
8'-6"
SECTION
BASE SECTION
3/8" FORMED PLATE
TOP SECTION
3/8" FORMED PLATE
O.D. UPPER OUTER PIPE 18"
O.D. LOWER INNER PIPE 17.25"
O.D. UPPER OUTER PIPE 18.89"
O.D. LOWER INNER PIPE 18.14"
SECTION
(a) Elevation (b) Slip-joint
Figure 2.12 Connection details of Specimen A7
8/12/2019 UCSD Final Report Isa
29/105
27
R1'-1" 1" BOLT ASTM A325
1" PLATE
118"
R1'-3"
(Pretensioned)
R1'-1" 1" BOLT ASTM A325
1" PLATE
118"
R1'-3"
(Pretensioned)
(a) Plan view (b) Weld details
Figure 2.13 Connection details of Specimen A8
2.4 Loading SchemeThe cyclic testing was conducted in a displacement-controlled mode. Since it was
not possible to measure the nominal strain on the upper pipe section at the upper ring
level of the sleeve connection due to stress concentration, a free-end displacement target
for each specimen was determined based on the recorded strains on an upper pipe section
away from the connection such that a nominal stress range of 30 ksi ( 15 ksi) was
applied to the critical upper pipe section (see Figure 2.14). (The instrumented section was
selected to be sufficiently away from the critical section such that it would remain in the
elastic range.) The measured actuator forces applied to the specimens are provided in
Appendix A. Testing was conducted with a loading frequency ranging from 1.0 to 1.3 Hz.
2.5 Instrumentation and Cr ack InspectionsThe specimens were instrumented with uni-axial and rosette strain gages to
measure local strains. Figure 2.15 shows a sample instrumentation layout. Strain gage
locations varied for each test specimen. During testing, strains were recorded at interval
(e.g., every 5,000 loading cycles) and strain variations at critical welded joints were
monitored to identify any cracking. Dye penetrant, magnetic particle, and ultrasonic
testing inspections were also conducted by a local inspection company.
8/12/2019 UCSD Final Report Isa
30/105
28
L2 L1
L1L2
Nominal Flexural Strain Profile
Strain Gages
top
bot
)10(103429000ksi)(E
30ksi)(
6
target
target
21
1bottop
0 LL
L
2
0
L1L2
L1L2L2 L1
L1L2
Nominal Flexural Strain Profile
Strain Gages
top
bot
)10(103429000ksi)(E
30ksi)(
6
target
target
21
1bottop
0 LL
L
2
0
L1L2
L1L2
Figure 2.14 Loading scheme
ReactionWall
18"x0.375" Pipe22"x0.375"
Pipe
3'-112
"6"
Section1
Section4
Section 4Section 1
North
8'-6" 12'-6"
21'
1'-3"
Section3
Section 3Section 2S10
Section2
1'-3"
0.375" (Typ.)
Figure 2.15 Sample instrumentation layout (Specimen A1)
8/12/2019 UCSD Final Report Isa
31/105
29
3. TEST RESULTS OF CONVENTIONAL CONNECTIONS3.1 Introduction
Figure 2.3 shows the details of the four conventional welded sleeve connection
specimens. The testing had the following objectives:
to evaluate the fatigue resistance and the associated failure mode for comparison
with field observations,
to provide a baseline for comparison with alternative connection details,
to evaluate the effectiveness of using a guide ring,
to evaluate the effectiveness of peening as a post-weld treatment.
3.2 Conventional Connection Details without Guide Ring3.2.1 Specimen C1
Testing of Specimen C1 was completed at 22,000 cycles when the crack length
was about 14 in long (or 25% of the circumference). The specimen cracked at the upper
pipe-to-upper ring fillet welded joint. The observed crack on the top side of the specimen
is shown in Figure 3.1. No cracks were observed on the bottom side. The crack initiated
at the toe of the fillet weld between the upper pipe and the upper ring, and then
propagated into the upper pipe wall thickness along the weld toe circumference.
Strain range variations measured near the crack location are shown in Figure 3.2;
the strain gage locations are provided in Figure 3.1. The strain range began to decrease at
early stage, which indicates that the crack may have initiated very early. The strain range
gradually decreased as the crack propagated. To monitor the strain concentration at the
weld toe, Specimen C1 was instrumented with a strip gage, which was a series of five
closely spaced gages. As shown in Figure 3.1(a), one strip gage (S1 to S5) was placed on
the upper pipe right above the upper ring, and another strip gage (S6 to S10) was placed
on the lower pipe right below the upper ring. The centerline of each strip gage was
located 3/8 in away from the weld toe. The strain profiles measured by the strip gages are
shown in Figure 3.3. For comparison purposes, the nominal strain range (= 1034 )
based on beam theory was also shown. High strain readings (with large strain gradient)
8/12/2019 UCSD Final Report Isa
32/105
30
on the upper pipe near the weld toe are clearly shown, while the lower pipe had low
strains. This experimental evidence on stress concentration is consistent with that
reported in a finite element analysis (Sim and Uang 2008).
Lower Pipe
Upper Pipe
Upper
Ring
Crack Location
(Fillet Weld Toe)
S1 to S5
S6 to S10
Lower Pipe
Upper Pipe
Upper
Ring
Crack Location
(Fillet Weld Toe)
S1 to S5
S6 to S10
(a) Crack location
0.375
S1 to S5
Upper Ring
Upper Pipe
0.375
S1 to S5
Upper Ring
Upper Pipe
(b) Close-up view of crack
Figure 3.1 Specimen C1: observed crack
8/12/2019 UCSD Final Report Isa
33/105
31
0 10 20 300
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
S1
S2
S4
S5
Strain
Range(x10-6)
S3 Malfunctioned
Nominal Strain Range
at Sleeve Connection
0 10 20 300
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
S1
S2
S4
S5
Strain
Range(x10-6)
S3 Malfunctioned
Nominal Strain Range
at Sleeve Connection
Figure 3.2 Specimen C1: measured strains near crack location
0.0 0.2 0.4 0.60
500
1000
1500
2000
2500
3000
Distance from Fillet Weld Toe (in.)
StrainRange(x
10-6) S1
S2
S4 S5
0.0 0.2 0.4 0.60
500
1000
1500
2000
2500
3000
Distance from Fillet Weld Toe (in.)
StrainRange(x
10-6) S1
S2
S4 S5
0.0 0.2 0.4 0.60
500
1000
1500
2000
2500
3000
Distance from Fillet Weld Toe (in.)
StrainRange(x
10-6)
S6 S7 S8 S9 S10
0.0 0.2 0.4 0.60
500
1000
1500
2000
2500
3000
Distance from Fillet Weld Toe (in.)
StrainRange(x
10-6)
S6 S7 S8 S9 S10
(a) on upper pipe (b) on lower pipe
Figure 3.3 Specimen C1: strain profiles near fillet weld toe (at 1500 cycles)
3.2.2 Specimen C2Specimen C2 was nominally identical to Specimen C1, except that Specimen C2
received a post-weld peening treatment at the upper pipe-to-upper ring fillet-welded joint.
If properly applied, peening the toe of a weld termination can effectively increases the
fatigue resistance by producing beneficial compressive residual stresses (Fisher et. al
1998). However, it was realized after testing that peening had not been performed
according to specifications in AWS D.1.1, Section 5.27 (AWS 2006). Therefore, the
effect of peening on this specimen might be minimal.
Testing of Specimen C2 was completed at 17,000 cycles when the maximum
crack length was about 15 in. Specimen C2 showed the same crack pattern as that
observed in Specimen C1. Figure 3.4 shows the crack at the upper pipe-to-upper ring
fillet welded joint. While Specimen C1 cracked on the top side only, Specimen C2
8/12/2019 UCSD Final Report Isa
34/105
32
cracked on both the top and bottom sides of the pipe. Strain range variations measured
near the crack locations on both the top and bottom sides are shown in Figure 3.5. The
strain ranges began to decrease between 10,000 and 15,000 cycles, which indicates that
the cracks initiated during this period.
Crack
Lower Pipe
Upper Pipe
Upper Ring
S5 (on Top Side)
S6 (on Bottom Side)
0.375
Crack
Lower Pipe
Upper Pipe
Upper Ring
S5 (on Top Side)
S6 (on Bottom Side)
0.375
Figure 3.4 Specimen C2: observed crack
0 10 20 300
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
StrainRange(x10-6)
S6
S5
0 10 20 300
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
StrainRange(x10-6)
S6
S5
Figure 3.5 Specimen C2: measured strains near crack location
8/12/2019 UCSD Final Report Isa
35/105
33
3.3 Conventional Connection Details with Guide Ring3.3.1 Specimen C3
Specimen C3 was nominally identical to Specimen C1, except that Specimen C3
had a guide ring. Testing of Specimen C3 was completed at 17,000 cycles when the cracklength was about 10 in. Specimen C3 had the same crack pattern as that observed in both
Specimens C1 and C2. Figure 3.6shows the crack observed at the upper pipe-to-upper
ring fillet welded joint on the top side of the specimen. Strain range variations measured
near the crack location, shown in Figure 3.7, showed the similar trend as that observed in
Specimen C2.
Crack Location(Fillet Weld Toe)
Lower Pipe
Upper Pipe
Upper Ring
S2
0.375
Crack Location(Fillet Weld Toe)
Lower Pipe
Upper Pipe
Upper Ring
S2
0.375
(a) Crack location
Upper PipeCrack at Weld Toe
Upper Ring
Fillet Weld
Upper PipeCrack at Weld Toe
Upper Ring
Fillet Weld
(b) Close-up view of crack
Figure 3.6 Specimen C3: observed crack
8/12/2019 UCSD Final Report Isa
36/105
34
0 10 20 300
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
S2
Strain
Range(x10-6)
0 10 20 300
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
S2
Strain
Range(x10-6)
Figure 3.7 Specimen C3: measured strains near crack location
3.3.2 Specimen C4As described in Section 2.3.1, inspections of this specimen detected a misplaced
weld due to a fabrication error, so it was decided to detach the gusset plates from the
upper ring. This modified connection is similar to, but not exactly the same as that of
Specimen C3.
Testing of Specimen C4 was completed at 25,000 cycles when the maximum
crack length was about 14 in. Specimen C4 also showed the similar crack pattern as that
observed in the previous specimens. Figure 3.8 shows the crack location. Both the top
and bottom sides cracked, but the crack length on the bottom side (3 in at 25,000 cycles)
was shorter when compared with the top side crack (14 in long at 25,000 cycles). Strain
range variations measured near the crack location on the top side are shown in Figure 3.9.
1
S11
S13
Crack Location
(Fillet Weld Toe)
LowerPipe
UpperRing
Top Edge Line
1
S11
S13
Crack Location
(Fillet Weld Toe)
LowerPipe
UpperRing
Top Edge Line
Figure 3.8 Specimen C4: observed crack
8/12/2019 UCSD Final Report Isa
37/105
35
0 10 20 300
5001000
1500
000
500
3000
Number of Cycles (x 1000)
Strain
Range(x10-6)
S11
S13
0 10 20 300
5001000
1500
000
500
3000
Number of Cycles (x 1000)
Strain
Range(x10-6)
S11
S13
Figure 3.9 Specimen C4: measured strains near crack location
3.4 Compar ison of Test ResultsAll four conventional welded sleeve connection specimens showed the same crack
pattern in which the crack initiated at the toe of the fillet weld between the upper pipe andthe upper ring due to high strain concentration. The cracks then propagated into the upper
pipe section and along the weld toe circumference. The crack pattern from testing was
similar to that observed in the failed sign structures like that shown in Figure 1.3(a). The
use of a guide ring had an insignificant effect on the fatigue resistance of the critical joint.
This experimental evidence is consistent with the finding from a finite element analysis
(Sim and Uang 2008).
0
50
100
150
200
FailureCycles(x103)
C1
Specimen No.
C2 C3 C40
50
100
150
200
FailureCycles(x103)
C1
Specimen No.
C2 C3 C4
Figure 3.10 Comparison of fatigue resistance of conventional connections
8/12/2019 UCSD Final Report Isa
38/105
36
4. TEST RESULTS OF REPAIRED CONNECTIONS4.1 Introduction
Each of the four tested conventional sleeve connection specimens was repaired by
various methods to evaluate their effectiveness. One specimen was repaired twice,
resulting in a total of five repaired specimens (R1 to R5, see Table 2.1). Figures 2.4 to 2.8
depict the design of these repaired specimens.
4.2 Gusset Repair : Specimen R1After repair, the tested specimen C1 is designated as R1 (see Figure 2.4). The
damaged fillet weld between the upper pipe and upper ring was repaired first, and then
gusset plates were added to strength the connection. Specimen R1 represents a common
means of attempting to strengthen or repair sleeve connections by installing gussets in the
field. Figure 4.1shows the connection with the designation of six gussets. Along the long
side of the gusset plate, the fillet weld at the tip was not wrapped around for three gussets
(Gussets 1, 2, and 6), while the other three gussets (Gussets 3, 4, and 5) were wrapped
around. On the short side, fillet weld was wrapped around for all specimens.
Specimen R1 cracked early during testing at the short side (i.e., horizontal side
when the specimen is in an upright position) of the gusset weld. Figure 4.2 shows thecrack observed at the bottom gusset (Gusset 4) fillet weld at 4,200 cycles. The top gusset
(Gusset 1) fillet weld also showed a similar crack pattern. The crack first initiated at the
wrap-around location, and propagated along the gusset weld length. After the welds along
the short side of the gusset failed, the connection behaved like a conventional sleeve
connection, and additional cracks similar to those observed in Specimens C1 to C4
occurred at the toe of the fillet weld between the upper pipe and the upper ring. Testing of
Specimen R1 was completed at 13,000 cycles when the crack length of the upper pipe-to-
upper ring fillet weld reached about 20% of the upper pipe circumference.
Note that the location of the weld fracture is different from that commonly
observed in the field, as shown in Figure 1.3(c). This is mainly due to the very short
horizontal weld length for connecting the gussets to the upper ring.
8/12/2019 UCSD Final Report Isa
39/105
37
West
2
1
6
Upper Pipe
Lower Pipe
Upper Ring
Gusset
Designation
Fillet WeldNot Wrapped Aroundfor Gussets 1, 2, and 6
West
2
1
6
Upper Pipe
Lower Pipe
Upper Ring
Gusset
Designation
Fillet WeldNot Wrapped Aroundfor Gussets 1, 2, and 6
(a) Top side
Lower Pipe
Upper Ring
Upper Pipe
3
West
4
5
Fillet Weld
Wrapped Around
for Gussets 3, 4, and 5
Lower Pipe
Upper Ring
Upper Pipe
3
West
4
5
Fillet Weld
Wrapped Around
for Gussets 3, 4, and 5
(b) Bottom side
Figure 4.1 Specimen R1: gusset connection before testing
8/12/2019 UCSD Final Report Isa
40/105
38
Upper Ring
Gusset
Upper Ring
Gusset
Upper RingUpper Ring
(a) View from East (b) View from West
Figure 4.2 Specimen R1: crack at fillet weld of Gusset No. 4
4.3 Steel-Jacketed and Cement-Grouted Repair4.3.1 Introduction
Two tested conventional sleeve connections (Specimens C2 and C3) were repaired
by a steel jacketed grouting scheme. It has been shown in an analytical study (Sim and
Uang 2008) that the bending moment from the upper pipe is not completely transferred as
a force couple (see Figure 1.2) to the lower pipe. As well as aiming to reduce the stressconcentration at the upper ring welded joint, the intent of this strengthening scheme was
to transfer the moment through bearing action of the filler material between the pipes.
After the testing of Specimens R2 and R3, another weakness in the existing slot-
welded location surfaced. Therefore, Specimen R3 was again repaired using Fiber
Reinforced Polymer (FRP) material, and the twice-repaired specimen is designated as R5.
4.3.2 Specimen R2Specimen R2 was the repaired Specimen C3 [see Figure 2.5(a) and Figure 2.6].
After testing of Specimen C3, the damaged fillet weld between the upper pipe and the
upper ring was first repaired, and the specimen was strengthened by steel jacketing and
grouting using cement (Rapid Set Cement All Grout), a non-shrinking, multipurpose
grout which can attain a 2,000 psi compressive strength in one hour.
8/12/2019 UCSD Final Report Isa
41/105
39
Figure 4.3 shows the repair procedure. After the weld repair, a steel collar was
first installed and welded to the upper ring. The steel collar consisted of two separate
halves, and these were connected by snug-tight bolts. The gap between the steel collar
and the upper pipe was then filled with grout. After grouting, a cap ring consisting of two
separate half pieces was welded to the collars to seal the grout. The cap ring pieces were
first fillet-welded to the steel collars but not to the upper pipe, and then they were
connected together by partial-joint-penetration groove welds.
Although cracks did not occur at the upper pipe-to-upper ring welded joint with
the grout-repair scheme, fatigue cracks occurred at the next weak locations as the number
of cycles imposed on the specimen increased. Figure 4.4 shows the crack locations
observed during testing. As shown in Figure 4.5(a), the crack first occurred at the existing
fillet weld between the lower pipe and the upper ring on the bottom side. As the testing
continued, another crack on the lower pipe at the slot weld location of the lower ring was
observed as shown in Figure 4.6. Near the end of the testing, a small crack at the lower
pipe-to-upper ring fillet weld on the top side was observed, as shown in Figure 4.5(b).
Strain range variations measured near the cracked fillet welds are shown in Figure 4.7;
see Figure 4.5for the strain gage locations.
Testing of Specimen R2 was completed at 155,000 cycles when the length of the
crack in Figure 4.6propagated to 16 in. After testing, the steel jackets were removed to
examine the condition of the grout (see Figure 4.8). A visual inspection showed that the
quality of grout remained sound with no crushing observed. A steel piece at the slot weld
location was also cut out for examination (see Figure 4.9). The fractured surface showed
that the crack may have initiated at the ends of the slot weld and propagated outward
through the lower pipe wall thickness.
Figure 4.10shows the measured flexural strain profiles on the upper pipe and the
steel collar, respectively. As shown in the plots, the strains on the upper pipe gradually
decreased from the grout cap level to the upper ring level, while the strain on the steel
collar gradually increased. Figure 4.10(a) shows that the jacketed grout was effective in
reducing the stresses transferred to the existing upper ring weld. Therefore, the crack
potential at this welded joint was significantly reduced.
8/12/2019 UCSD Final Report Isa
42/105
40
(a) Weld Repair (b) Install steel collars and
bolt together
(c) Groove weld of steel
collar to upper ring
(d) Grouting (e) Install cap cover ring
Figure 4.3 Specimen R2: repair procedure
8/12/2019 UCSD Final Report Isa
43/105
41
(3) Last location where crack was observed
(crack at lower pipe-to-upper ring fillet weld)
(1) Location where crack was first observed
(crack at lower pipe-to-upper ring fillet weld)
(2) Location where crack was next observed
(crack at slot weld at lower ring level)
Top Edge Line
Slot Weld Orientation
(at Lower Ring Level)
45, Typ.
South
Lower Pipe
Steel
Collar
axis of bending(3) Last location where crack was observed
(crack at lower pipe-to-upper ring fillet weld)
(1) Location where crack was first observed
(crack at lower pipe-to-upper ring fillet weld)
(2) Location where crack was next observed
(crack at slot weld at lower ring level)
Top Edge Line
Slot Weld Orientation
(at Lower Ring Level)
45, Typ.
South
Lower Pipe
Steel
Collar
axis of bending
Figure 4.4 Specimen R2: crack locations
Lower Pipe
Crack Length = 17
at 150,000 Cycles
Steel Collar
UpperR
ing0.375
S24
Lower Pipe
Crack Length = 17
at 150,000 Cycles
Steel Collar
UpperR
ing0.375
S24
(a) Bottom side
Lower PipeCrack Length = 3at 155,000 Cycles
Steel Collar
UpperRing
0.375
S16
Lower PipeCrack Length = 3at 155,000 Cycles
Steel Collar
UpperRing
0.375
S16
(b) Top side
Figure 4.5 Specimen R2: cracks at lower pipe-to-upper ring fillet weld
8/12/2019 UCSD Final Report Isa
44/105
42
CrackLength
16in.
at155,000Cycles
Crack
CrackLength
9in.
at132,000Cycles
Slot Weld Location
CrackLength
16in.
at155,000Cycles
Crack
CrackLength
9in.
at132,000Cycles
Slot Weld Location
Figure 4.6 Specimen R2: crack on lower pipe at slot weld location
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
S24StrainRa
nge(x10-6)
S16
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
S24StrainRa
nge(x10-6)
S16
Figure 4.7 Specimen R2: measured strains near lower pipe-to-upper ring welded joint
8/12/2019 UCSD Final Report Isa
45/105
43
Cut-Out Location
Grout
Cut-Out Location
Grout
Figure 4.8 Specimen R2: grout condition after testing
LowerRing
Upper Pipe
Lower Pipe
Slot Weld
LowerRing
Upper Pipe
Lower Pipe
Slot Weld
(a) Cut-out piece
Slot WeldSlot Weld
(b) Fracture surface
Figure 4.9 Specimen R2: fracture surface at slot weld location
8/12/2019 UCSD Final Report Isa
46/105
44
0 10 20 300
200
400
600
800
1000
5
10
15
20
25Top SurfaceBottom Surface
StrainRange(x10-6)
x, Distance from Upper Ring (in.)
x
UpperRing
Level
GroutCap
Level
Location for Plots
Top Surface
Bottom Surface
StressRange(ksi)
Lower
Pipe
Upper
Pipe
0 10 20 300
200
400
600
800
1000
5
10
15
20
25Top SurfaceBottom Surface
StrainRange(x10-6)
x, Distance from Upper Ring (in.)
x
UpperRing
Level
GroutCap
Level
Location for Plots
Top Surface
Bottom Surface
StressRange(ksi)
Lower
Pipe
Upper
Pipe
0 10 20 300
200
400
600
800
1000
5
10
15
20
25Top SurfaceBottom Surface
StrainRange(x10-6)
x, Distance from Upper Ring (in.)
Location for Plots
Top Surface
Bottom Surface
x
UpperRing
Level
GroutCap
Level
StressRange(ksi)
LowerPipe
Upper
Pipe
0 10 20 300
200
400
600
800
1000
5
10
15
20
25Top SurfaceBottom Surface
StrainRange(x10-6)
x, Distance from Upper Ring (in.)
Location for Plots
Top Surface
Bottom Surface
x
UpperRing
Level
GroutCap
Level
StressRange(ksi)
LowerPipe
Upper
Pipe
(a) Strain profiles on upper pipe (b) Stain profiles on steel collar
Figure 4.10 Specimen R2: measured flexural strain distribution in grout region
4.3.3 Specimen R3Specimen R3 was the repaired Specimen C2 [see Figure 2.5(b) and Figure 2.6].
After testing of Specimen C2, the damaged fillet weld between the upper pipe and the
upper ring was first repaired. The slot weld was ground flush for an UT inspection; the
inspection revealed no rejectable weld cracks. Then the specimen was strengthened by
steel jacketing and grouting. The same repair procedure as used in Specimen R2 was
applied, except that Specimen R2 was grouted above the upper ring only while Specimen
R3 was grouted in the sleeve region as well. Two holes (2 in diameter) on the upper
ring were drilled to accommodate the grouting in the sleeve region.
Figure 4.11shows the crack location. The crack occurred on the lower pipe at the
slot weld location of the lower ring. Strain range variations near the cracked slot weld are
shown in Figure 4.12. Specimen R2 was subjected to a large number of cycles (155,000
cycles), however the slot-weld crack had extended to a length of 5 in. at only 40,000
cycles. To better utilize this specimen, it was decided to stop the testing of R3 at that
point such that the potential of using fiber reinforced polymer composites to repair the
cracked slot welds could be evaluated in Specimen R5.
8/12/2019 UCSD Final Report Isa
47/105
45
Steel Collar
Lower
Pipe
Crack at SlotWeld Location
Top
Edge
Lin
e
4 in
Slot Weld Orientation
(at Lower Ring Level)
axis of
bending
Steel Collar
Lower
Pipe
Crack at SlotWeld Location
Top
Edge
Lin
e
4 in
Slot Weld Orientation
(at Lower Ring Level)
axis of
bending
Crack
S15
S13
1 (Typ)
Crack
S15
S13
1 (Typ)
(a) Crack location (b) Close-up view of crack
Figure 4.11 Specimen R3: observed crack on slot weld
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
S15S13S
trainRange(x10-6)
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
S15S13S
trainRange(x10-6)
Figure 4.12 Specimen R3: measured strains near crack location
4.4 Steel Cone and Cement Gr out Repair : Specimen R4Specimen R4 was the repaired Specimen C4 [see Figure 2.5(c) and Figure 2.6].
After testing of Specimen C4, the damaged fillet weld between the upper pipe and upper
ring was first repaired, and the specimen was strengthened by a steel cone and cement
grouting above and below the upper ring, respectively. Figure 4.13 shows the repair
procedure. The gap between the pipes above the guide ring in the sleeve region was first
filled by grout; small holes on the upper ring were drilled to accommodate the grouting.
The gap between the pipes below the guide ring was also filled by grout; small holes on
the lower pipe right below the guide ring were also drilled to accommodate the grouting.
8/12/2019 UCSD Final Report Isa
48/105
46
A steel cone (A36 steel) was then installed and welded to the upper ring and the upper
pipe. The steel cone consisted of two separate half pieces, and they were connected by
welding (see Figure 2.5). Figure 4.14shows the connection after repair.
Figure 4.15 shows the crack locations observed during testing. As shown in
Figure 4.16(a), the crack (on the bottom side) first occurred at the existing fillet weld
between the upper ring and the lower pipe. As the testing continued, another crack on the
lower pipe at the slot weld location was observed, as shown in Figure 4.17(a). Testing of
Specimen R4 was completed at 105,000 cycles. At the end of testing, the length of the
crack in Figure 4.16(a) propagated to 30 in and the length of the crack in Figure 4.17(b)
was 11 in.
After testing, the specimen was cut to examine the inside, as shown in Figure
4.18. The grout remained intact and its condition was good. The fracture surfaces on the
slot weld are shown in Figures 4.19 and 4.20. A visual inspection on the fracture surface
indicated that the crack initiated at both ends of the slot weld and propagated outward
through the lower pipe wall thickness. This slot-weld failure appeared to be caused by
high bending stresses on the lower pipe together with a geometric imperfection resulting
from the slot weld itself.
8/12/2019 UCSD Final Report Isa
49/105
47
(a) Weld repair (b) Grouting between upper and guide rings
(c) Grouting between guide and lower rings (d) Installation of steel cone
Figure 4.13 Specimen R4: repair procedure
8/12/2019 UCSD Final Report Isa
50/105
48
PJP Weld
Upper Pipe
Cone
Cone
Lower Pipe
Upper Pipe
Cone
Lower Pipe
PJP Weld
Upper Pipe
Cone
Cone
Lower Pipe
Upper Pipe
Cone
Lower Pipe
Figure 4.14 Specimen R4: connection after repair
(2) Crack at Slot
Weld Location
Cone
Lower
Pipe
(1) Crack at Lower Pipe-
to-Upper Ring Fillet Weld
(Bottom Side Only)
5 in
Slot Weld Orientation
(at Lower Ring Level)
axis ofbending
(2) Crack at Slot
Weld Location
Cone
Lower
Pipe
(1) Crack at Lower Pipe-
to-Upper Ring Fillet Weld
(Bottom Side Only)
5 in
Slot Weld Orientation
(at Lower Ring Level)
axis ofbending
5 in
Slot Weld Orientation
(at Lower Ring Level)
axis ofbending
Figure 4.15 Specimen R4: crack locations
8/12/2019 UCSD Final Report Isa
51/105
49
CrackS18
Ring
LowerPipe
Cone
0.375
CrackS18
Ring
LowerPipe
Cone
0.375
(a) Crack location
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
Strain
Range(x10-6)
S18
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
Strain
Range(x10-6)
S18
(b) Measured strains
Figure 4.16 Specimen R4: crack at lower pipe-to-upper ring fillet weld
8/12/2019 UCSD Final Report Isa
52/105
50
Crack
S29
1 in
1 in
South
S25
Crack
S29
1 in
1 in
South
S25
(a) Crack location
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
StrainRange(x10-6)
S29
S25
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
StrainRange(x10-6)
S29
S25
(b) Measured strains
Figure 4.17 Specimen R4: crack on lower pipe at the slot weld location
8/12/2019 UCSD Final Report Isa
53/105
51
Cone
Top Side
during Testing
Lower
Pipe
Guide Ring LevelLower Ring Level
Detail 1 Grout
Detail 2
Cut-out
Piece
Cone
Top Side
during Testing
Lower
Pipe
Guide Ring LevelLower Ring Level
Detail 1 Grout
Detail 2
Cut-out
Piece
Figure 4.18 Specimen R4: view of inside after cut
Ring
Slot Weld
Upper Pipe
Grout
Ring
Slot Weld
Upper Pipe
Grout
Figure 4.19 Specimen R4: fracture surface (Detail 1)
8/12/2019 UCSD Final Report Isa
54/105
52
Outer Surface of Lower Pipe Slot WeldOuter Surface of Lower Pipe Slot Weld
Figure 4.20 Specimen R4: fracture surface (Detail 2)
4.5 FRP Repair: Specimen R5Observations made from testing of Specimens R2 and R3 revealed two additional
weaknesses in existing welds: the slot welds connecting the lower ring to the lower pipe
and the fillet weld connecting the upper ring to the lower pipe, both made in the field. For
Specimen R2, cracking first occurred in the fillet weld, followed by cracking in the slot
weld. Specimen R3 first experienced cracking in one slot weld in the early stage of
testing. It was then decided to stop the testing at 40,000 cycles and repair the specimen
with Fiber Reinforced Polymer (FRP) composites to prevent further cracking in the slot
weld. The repaired specimen is designated as R5. See Figure 2.8 for the strengthening
scheme and location.
Figure 4.21shows the crack location and measured strain. The crack (on the top
side) occurred at the lower pipe-to-upper ring fillet weld. Strains on the FRP material
were also monitored during testing to identify any failure. Figure 4.22(a) shows the
rosette strain gage locations; the gages in parentheses were located on the bottom side.
The measured strains are provided in Figure 4.22(b). As shown, the strain ranges on the
FRP remained constant during testing, which indicates no failure of the FRP.
8/12/2019 UCSD Final Report Isa
55/105
53
Testing of Specimen R5 was completed at 120,000 cycles when the length of the
crack shown in Figure 4.21(a) was about 20 in. After testing, the FRP was removed [see
Figure 4.23(a)] to examine the pre-existing crack. As shown in Figure 4.23(b), the
Magnetic Particle (MT) test showed that the pre-existing crack length remained at 5 in.,
indicating no further crack growth after the FRP composites were applied to the
specimen. The bottom slot weld was also examined and no cracks were observed.
Crack
Upper Pipe
Lower Pipe
Upper Ring
S11
0.375
Crack
Upper Pipe
Lower Pipe
Upper Ring
S11
0.375
(a) Crack location
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
StrainRange(x10-6
)
S11
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
StrainRange(x10-6
)
S11
(b) Measured strains
Figure 4.21 Specimen R5: crack at lower pipe-to-upper ring fillet weld
8/12/2019 UCSD Final Report Isa
56/105
54
3 ft
R1b
(R2b) R1y(R2y)
R1r(R2r)
3 ft
R1b
(R2b) R1y(R2y)
R1r(R2r)
(a) Strain gage locations
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
Strain
Range(x10-6)
R1bR2bR2r, R1rR2y, R1y
0 50 100 150 2000
500
1000
1500
2000
2500
3000
Number of Cycles (x 1000)
Strain
Range(x10-6)
R1bR2bR2r, R1rR2y, R1y
(b) Measured strains
Figure 4.22 Specimen R5: measured strains on FRP
8/12/2019 UCSD Final Report Isa
57/105
55
FRP
Upper
Pipe Upper Ring
Cut-out Location
FRP
Upper
Pipe Upper Ring
Cut-out Location
(a) Specimen cut
FRP
Crack Indication by
Magnetic Particle Test
FRP
Crack Indication by
Magnetic Particle Test
(b) Crack inspection
Figure 4.23 Specimen R5: slot weld crack examination after FRP removal
8/12/2019 UCSD Final Report Isa
58/105
56
4.6 Compar ison of Test ResultsFigure 4.24 compares the fatigue resistance of the repaired specimens. For
comparison purposes, the mean failure cycle from the conventional sleeve connection
specimens is also shown. The failure cycles were 13,000 (Specimen R1: gusset repair),
155,000 (Specimen R2: grout repair), 40,000 (Specimen R3: grout repair), 105,000
(Specimen R4: cone and grout repair), and 160,000 (Specimen R5: FRP repair). Since the
testing of Specimen R3 was completed early for the FRP repair, this specimen is
excluded in the comparison of fatigue resistance.
Specimen R1 showed early cracking at the gusset-to-upper ring welded joint. After
the gusset welds failed, the specimen experienced the same crack pattern as that observed
in the conventional connection specimens. The fatigue resistance of this specimen is
similar to that of the conventional connection (see Figure 3.10).
Specimens R2 and R4 performed better, showing significant improvements in
fatigue resistance. Cement grouting (above the upper ring) with steel jackets in Specimen
R2, and the use of a steel cone (above the upper ring) in Specimen R4 effectively
prevented cracks at the upper pipe-to-upper ring fillet welded joint. However, cracks
occurred at the next weak locations (i.e., the lower pipe-to-upper ring fillet weld and the
slot welds). As demonstrated in the testing of Specimens R3 and R4, grouting below the
upper ring was not effective in preventing cracks at the next weak locations, although thefatigue life of the entire connection was significantly improved.
Based on visual inspections of the fractured surface of the lower pipe at the slot-
weld locations, the cracks appeared to be caused by high bending stresses on the lower
pipe with cracking initiated from the inner surface of the pipe (likely at the slot-weld
terminations of stress concentration). This observation indicates that the slot welds, when
used, should be oriented such that the bending stresses at the slot-weld locations are
minimized. As shown in Figure 4.4, the slot welds of Specimen R2 were located away
from the top and bottom sides, where the highest bending stresses on the pipe section
were developed in testing. The slot-weld crack length at 132,000 cycles was 9 in (see
Figure 4.6). On the other hand, Specimen R3 experienced cracking at the slot weld in the
early stage of testing (the crack length was 5 in at 40,000 cycles), possibly due to a
different slot-weld orientation. As shown in Figure 4.11(a), the slot weld of Specimen R3
8/12/2019 UCSD Final Report Isa
59/105
57
was located near the top side, where the bending stress was higher. In actual applications,
the optimal slot weld locations are 45 degrees from the design longitudinal and transverse
axis of the cross section.
The cracks on the lower pipe-to-upper ring joint occurred at the fillet weld, not in
the base metal. The failure of this fillet weld also did not significantly contribute to the
reduction of the specimen global stiffness during testing. Since the failure was in the fillet
weld, the fatigue resistance of this detail can be increased with a larger size of fillet weld
in repair.
Specimen R5, which used FRP as a repair scheme for the slot welds, was effective
in enhancing the fatigue resistance. An inspection after the FRP removal indicated no
further growth of the pre-existing crack.
0
50
100
150
200
FailureCycles(x103)
R1
Specimen No.
R2 R3 R4R5
GussetRepair
GroutRepair
(TestingStoppedEarly
forFRP
Repair)
Grout
Repair
Cone&
Grout
Repair
FRP
Repair
mean failure cycleof conventional
sleeve connections0
50
100
150
200
FailureCycles(x103)
R1
Specimen No.
R2 R3 R4R5
GussetRepair
GroutRepair
(TestingStoppedEarly
forFRP
Repair)
Grout
Repair
Cone&
Grout
Repair
FRP
Repair
mean failure cycleof conventional
sleeve connections
Figure 4.24 Comparison of fatigue resistance of repair connections
8/12/2019 UCSD Final Report Isa
60/105
58
5. TEST RESULTS OF ALTERNATIVE CONNECTIONS FOR NEWCONSTRUCTION
5.1 Modified Sleeve Connection Details5.1.1 Specimen A1
The connection details of Specimen A1 were the same as those of Specimen C3,
except that no weld was specified on the top of the fillet-welded joint between the upper
pipe and the upper ring; only the bottom side is welded. See Figure 2.9(a) for the
connection details. The intent of this detail was to eliminate the high stress conce