Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
UK Power Networks Street Works Forum June 2014
Welcome
2
Safety and housekeeping
• No planned fire alarms
• Emergency exits
• Fire assembly points
• Toilets
• Mobile phones
• Data Protection - we record our findings and publish a
report of the proceedings and our follow-up actions
3
Today’s Agenda
4
10:55 – 11:25 Feedback session
• What you think UK Power Networks does well and areas for improvement?
• How UK Power Networks rates against other utilities?
11:25 – 11:45 Working with Local Authorities
11:45 – 12:05 Our future plans for Street Works
08:45 – 09:30 REGISTRATION AND COFFEE
10:40 – 10:55 COFFEE
12:05 – 12:40 QUESTIONS
12:40 ONWARDS – LUNCH
09:30 – 09:50 Update on actions resulting from our April 2013 Street Works forum
09:50 – 10:00 Health & Safety video
10:00 – 10:40 Engineering elements of electricity work – technical and safety issues of underground electrical work
UK Power Networks
5
One of UK’s largest electricity
distribution businesses
Eight million end customers in
London, South East & East of
England
Operates in 52 local authority
areas
Our 3 networks distribute
electricity using more than
160,000km of underground
cables and overhead lines, and
more than 135,600 substations
April 2013 forum outcomes
Chris Perkins – Strategy Manager Street Works
April 2013 Street Works Forum
The last Street Works Forum provided UK Power Networks
with:
A guide to future requirements
An understanding of the
requirements of stakeholders
An opportunity to meet those who
are affected by our works
An opportunity to present the UK
Power Networks’ Street Works vision
Actions from April 2013 Street Works Forum
You said The performance target for resolving reported defects was too long
at 1 month. We did
Tightened up the measure by halving the acceptable duration to 2 weeks and reducing the performance target from 5 to 2.
You said Provide more information on site to say what is going on. We did Introduced a new customer information sign at all our work site saying what we are doing and when we will be finished.
Actions from April 2013 Street Works Forum
You said Can we report on number of days work overrun.
We did
We report the percentage of works completed on time as it reflects all work undertaken.
In the last 12 months with a 16% increase in work volume we have
reduced the number of overrun works from 7% to 2% – 71% improvement
Since our last forum we have:
New London UK Power Networks team to deal with the issues of traveling, responding
and working in Central London
Brought in house the delivery of ground works for faults, connections and small projects in London and the South East
Fully imbedded our integrated Street Works management system
Introduced the use of Electronic Transfer of Noticing system version 6 on 1st April 2014
Provide the CEO and Executive Management with a monthly performance report against
our Best in Class targets
Since our last forum we have:
Tighten up our Best in Class Street Works performance targets and introduced weekly
conference calls and meetings to target improvements
Focused ownership of Street Works failures and cost at local management level
Employed the company ‘SQS’ to support our in house ground works team for
reinstatement
Employed a company on a trail basis to respond quickly and investigate reported
apparatus defects
Pictorial representation of performance
Stay Safe video
Engineering elements of electricity work –
technical and safety issues of underground
electrical work
Paul Fidler – Director of Operations, ENA
Energy
Networks
Association Engineering elements of electricity work ‒ technical and safety issues of underground electrical work Paul Fidler Director of Operations 24 June 2014 UK Power Networks Street Works Forum
The Voice of the Networks
16 The Voice of the Networks
Introduction
• Procedures and Competency
• Existing Structures
• Guidance
• Industry Initiative
• HSE
17 The Voice of the Networks
Competency
The industry Safety Strategy for 2010-2015, Asset Management and Maintenance, was the Overarching Theme for 2012.
HSE Strategy ‘Be Part of the Solution’
"We believe this strategy represents a clear statement of core principles and a sensible approach to health and safety in Great Britain. Whilst the economic climate is difficult and the temptation for some may be to cut corners, HSE, its partners and businesses must resolve to continue to strive to improve health and safety performance. Good health and safety is good business.” Judith Hackett (Chair HSE)
Vision: The UK Electricity Industry will be a world leader in health and safety performance by 2015
18 The Voice of the Networks
• 2012 saw the industry strategy focus upon
Asset Management and Maintenance; this included
some extensive work on cables.
• Cables assumed to be dead, cables in concrete
and excavations around cables.
2012 – Asset Management
Never assume any HV or LV cable is dead unless proved by an approved method.
Follow your company LV fault finding procedures.
ASSET MANAGMENT AND MAINTENACE
REVIEW OF PAST INCIDENTS
19 The Voice of the Networks
A Powering Improvement Asset Management Workshop was held on the 1 April 2014,
hosted by UK Power Networks.
UK Power Networks Workshop
20 The Voice of the Networks
• The focus in 2013 was on Human and Organisational Factors:
Behavioural Safety and Personal Responsibility
• Outcomes for 2013 were that:
“Workers will be more aware of how their behaviour can impact
on health and safety performance and for companies and
trade unions to have worked together to ensure employees are
comfortable and supported in challenging unsafe acts
and conditions”.
Supported by the publication of case studies on the range of
behavioural safety initiatives and programmes in the industry,
the collation of best practice from high-hazard industries and
a high level principles and guidance document.
2013 – Human & Organisational
Factors
ASSET MANAGMENT AND MAINTENACE
REVIEW OF PAST INCIDENTS
HUMAN AND ORGANISATIONAL FACTORS: BEHAVIOURAL SAFETY AND PERSONAL RESPONSIBILITY
SHE REVIEW: CASE STUDIES
21 The Voice of the Networks
Existing Structures
Bob Gallienne was appointed as the new CEO of NJUG on the 1 August 2013.
Vision "To create in partnership with government, authorities and stakeholders, a self-regulated environment which motivates our members to deliver the highest standards of street works at minimum cost and disruption to their customers and to the overall benefit of UK Plc". Bob Gallienne, CEO, NJUG
Key Objectives • To promote best practice among members • To foster the industry’s image in Government and Parliament • To positively influence the development of legislation and regulations affecting the
industry • To provide a forum for discussion on the issues • To produce NJUG policy and act collectively on issues of importance
22 The Voice of the Networks
ENA Street Works Forum
• As a result of NJUG’s new vision, objectives and structure, ENA’s Street Works Forum
work closely with NJUG and continue to provide input into the review of their vision
and objectives.
• ENA manages street works and Traffic Management Act issues while promoting
external awareness of street works issues in support of ENA member companies.
• The Street Works Forum provides a opportunity for all the member companies to
discuss issues relating to legislation on street works activities.
Existing Structures
23 The Voice of the Networks
Utility Strike Avoidance Group
The Utility Strike Avoidance Group (USAG) is a collaborative group of over 60 utilities asset owners, industry groups and contractors that seek to ensure the highest standards of safety and best practice when carrying out work on the vital services for our homes and businesses. In particular it will help those carrying out work avoid disrupting supplies through accidental strikes on utilities in the ground.
24 The Voice of the Networks
Utility Strike Avoidance Group
25 The Voice of the Networks
Utility Strike Avoidance Group Charter
26 The Voice of the Networks
2012 Charter Launch
Transport Minister Norman Baker MP launched the industry-led charter to improve the safety of street works. The Safe Dig Charter has been compiled by the utilities sectors and contractors to ensure the highest standards of safety and best practice when carrying out maintenance work on the vital services for our homes and businesses.
Latest USAG
Members
27 The Voice of the Networks
Institution of Occupational Safety and Health
IOSH fully supports this proactive industry-led initiative and wholeheartedly agrees that risk assessment, planning, safe systems of work and competence are all essential for ensuring that digging and excavating are safe. The latest HSE guidance ‘Avoiding danger from underground services’ highlights the devastating consequences of failing to manage such work properly, with workers being killed or seriously injured from striking live underground cables. These tragedies are preventable and IOSH believes we must act to ensure every worker goes home safely at the end of the working day. The Institution would urge all organisations involved in commissioning or conducting any ground or excavation work to renew their efforts to raise health and safety standards and to sign up to this Charter. We all need to work together to make sure accidental contact with underground services is a tragedy of the past. Jan Chmiel, Chief Executive, Institution of Occupational Safety and Health
28 The Voice of the Networks
We Will:
1. Ensure that all work carried out by us or on our behalf is properly planned and that
those responsible are aware of their responsibilities and how to carry them out.
2. Ensure that all people working on our behalf are assessed to ensure they are competent
and capable of carrying out the task given to them and that at least one person in each work team
is competent in the use of cable detection equipment to its full potential.
3. Ensure that excavations, including those undertaken by anyone excavating on our behalf, are
carried out in accordance with safe systems of work, company or USAG procedures.
4. Ensure that the equipment provided for the detection and avoidance of services is inspected,
calibrated and tested in accordance with the manufacturer’s requirements and that records are
kept, including a daily check to ensure that the equipment continues to operate as expected.
5. Ensure that all those working, including those on our behalf use the correct protective equipment
and are trained in its use.
6. Ensure that relevant latest utility asset drawings are available to people excavating, that our work
is inspected and audited and that failure to achieve the expected standards is recorded.
7. Ensure that where damage to utility assets occur, a suitable and sufficient investigation takes
place, that learning is shared and that action is taken to reduce the risks to those carrying out the
work.
Utility Strike Avoidance Group Charter
29 The Voice of the Networks
• Designed to support existing systems, or
• Provide simple systems for SME’s with
limited in-company H&S support.
• Allow a full self check to take place.
• Corporate responsibility.
Toolkit
30 The Voice of the Networks
USAG Charter Wins Award
Industry Charter wins award recognition The Safe Dig Charter won an award for avoidance of damage to supplies. The Charter was facilitated by Energy Networks Association (ENA) through the Utility Strike Avoidance Group and was recognised at the National Joint Utilities Group (NJUG) Annual Awards in the House of Commons by Transport Minister Norman Baker MP.
Winners of the NJUG ‘Avoiding Damages’ Award 2012, for the
Utility Strikes Avoidance Group Safe Dig Charter
31 The Voice of the Networks
Steering Group
• ENA Chair
Membership: Asset Owners, Contractors, Construction companies,
Service Providers, HSE.
Working Groups
• Membership Scottish Water Chair
• Toolkit Development Northern Gas Networks Chair
• Training & Education Construction Chair
• Data and Reporting Service Provider Chair
• Web site Development Civil Engineering Chair
New USAG Structure
32 The Voice of the Networks
HSE Developments
Revised Guidance document HSG47 ‘Avoiding Underground Services’ This guidance is aimed at all those involved in commissioning, planning, managing and carrying out work on or near underground services. It will also be of use to the owners and operators of such services.
It outlines the potential dangers of working near underground services and gives advice on how to reduce any direct risks to people’s health and safety, as well as the indirect risks arising through damage to services. Best Practice in Avoiding Underground Services (BPAUS) “Safe Digging is Not Enough” toolkit. The Launch of HSG47 and BPAUS industry Best Practice will be on the 24th June which will be supported by Mike Penning MP (Minister for Health and Safety).
33 The Voice of the Networks
Common Ground Alliance (CGA)
The organisation was formed in 2000 in USA with the objective of reducing
damages to all underground utilities. The work of the group builds on the
Common Ground Study in 1999 and the Alliance currently has 2,000
corporate members and 58 sponsors.
• In 2007 CGA launched a national 811 ‘Call Before You Dig’ number and web
site to aid third party excavations.
• A Damage Information Reporting Tool (DIRT) report is issued annually
outlining the number of incidents; the latest report in 2012 lists 230,000
events and identifies the root causes by geographical area.
• CGA issues guidance and videos, and conferences are arranged to share
best practice procedures. A UK conference was held in February 2014 at
the University of Birmingham.
Common Ground Alliance (USA)
34 The Voice of the Networks
Thank You
Any Questions
35 The Voice of the Networks
Paul Fidler
Director of Operations
T: +44 (0) 20 7706 5151
M: +44 (0) 7793 957 256
6th Floor, Dean Bradley House,
52 Horseferry Road, London SW1P 2AF
www.energynetworks.org
@EnergyNetworks
Thank You
Feedback session
What you think UK Power Networks
does well?
How UK Power Networks rates against
other utilities?
What are the areas where UK Power
Networks can improve?
Working with Local Authorities
Richard Boissieux – Street Works Manager
UK Power Networks
• Safety and Customer
Service are our top
priorities. These are at the
heart of everything we do.
• Electricity kills - we have
a duty to maintain a safe
and reliable electricity
network for everyone.
Facts behind UK Power Networks’ Street
Works
• Operates in 52 authority
areas
- 43 operate permit schemes
- Two operate lane rental
schemes
• 49% maintenance and faults
• 47% connections work
• 4% network upgrade
• Of all the work undertaken on the highway approximately
30% is on the carriageway or cycleway
Challenges of working across different
Authorities
Consistency of
approach
Parity of works
Permit conditions
Duration
challenges
Multiple
departments within
Authorities
Wide variety of
charges
Operatives
crossing
boundaries
Good practices when working across different
Authorities
UK Power Networks aims to be Best in Class for Street
Works
Measuring performance
Currently across our regions an average 98% of our works are completed on time. 94% for first time reinstatement.
Eton 6
Information to be kept in one place creating a history for
the works.
Combined Authority meetings
Business Transformation
Summary
• Inconsistency between authorities applying the same
permit scheme
• Inconsistency between permits schemes
• UKPN will strive to ensure we give accurate, timely and
regular updates
• UKPN will continue to build and maintain constructive
dialogue with all authorities
• We simply want to undertake our works safely in the
least amount of time, at an efficient cost, with minimum
disruption to the public
Our future plans for Street Works
Chris Perkins – Strategy Manager Street Works
Our future plans for Street Works
• Use the data we now have on performance to further reduce
overrunning work, the causes of Fixed Penalty Notices and work
durations
• Introduce approved cold lay materials to speed up reinstatement of
small excavations, (poles and frames in the footway) by doing it first
time rather than requiring a revisit (expected improvement in first
time reinstatement = 1.5%)
• Continue to look abroad to see if there are any smart technologies
we can use for electricity work to speed up our work and reduce the
size of excavations. None have been found so far, considered Core
and Vac and Radio Frequency Identification tags.
Our future plans for Street Works
• Evaluating the introduction of Street Works admin training to
improve quality of notification as we have over 900 people raising
and managing notification.
• Reduce the time between stages of work to shorten work durations
• Working with the UK Power Networks transformation team on
ensuring that work flows take into consideration the requirements of
working on the highway
UKPN Street Works stretch targets 2014
Measure Stretch target
Works duration (Average) days for connections and faults < 4.5
Percentage of work completed on time > 98.5%
Percentage of permits accepted by local authorities > 92%
Number of overdue defects 0
Number of s81 defects overdue (> 2 weeks) 0
Percentage of FPNs (paid) <10%
Percentage of first time reinstatement > 97%
Percentage of street works customer complaints 0%
Percentage of 2 hour safety issues responded to on time 100%
Percentage of Cat A defects <3%
Percentage of reinstatement defects received < 4.75%
Any Questions?
Join us again:
Next Critical Friends Panels this
autumn on emergency planning
Next steps
Before we finish
• Complete your feedback form
• Send us additional thoughts
• Invite a colleague to a session
49