24
RANDAL BROWN & ASSOCIATES ENGINEERING L TD. CONSULTING ENGINEERS | LIFE SAFETY & FIRE PROTECTION 105 – 6 LANSING SQUARE TORONTO, ONTARIO CAN/ULC-S1001-11, INTEGRATED S YSTEMS TESTING OF FIRE PROTECTION AND LIFE SAFETY S YSTEMS CAN/ULC-S524-14, INSTALLATION OF FIRE ALARM S YSTEMS CFAA NCR ANNUAL TECHNICAL SEMINAR OCTOBER 15, 2014

ULC Standards Update S524, S1001 Integrated Systems Testing

  • Upload
    ngotu

  • View
    245

  • Download
    7

Embed Size (px)

Citation preview

Page 1: ULC Standards Update S524, S1001 Integrated Systems Testing

RANDAL BROWN & ASSOCIATES ENGINEERING LTD. CONSULTING ENGINEERS | LIFE SAFETY & FIRE PROTECTION

105 – 6 LANSING SQUARE TORONTO, ONTARIO

CAN/ULC-S1001-11, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS

CAN/ULC-S524-14, INSTALLATION OF FIRE ALARM SYSTEMS

CFAA NCR ANNUAL TECHNICAL SEMINAR

OCTOBER 15, 2014

Page 2: ULC Standards Update S524, S1001 Integrated Systems Testing

RANDAL BROWN & ASSOCIATES ENGINEERING LTD. CONSULTING ENGINEERS | LIFE SAFETY & FIRE PROTECTION

105 – 6 LANSING SQUARE TORONTO, ONTARIO

PRESENTER

SIMON CROSBY, CET, CFPS

PROJECT MANAGER, RBA ENGINEERING

CHAIR, ULC SUBCOMMITTEE ON COMMISSIONING

VICE PRESIDENT, CANADIAN FIRE ALARM ASSOCIATION

416-492-5886 X234

[email protected]

Page 3: ULC Standards Update S524, S1001 Integrated Systems Testing

CAN/ULC-S1001-11

Page 4: ULC Standards Update S524, S1001 Integrated Systems Testing

BACKGROUND

• Developed in response to a Technical Change to the 2010 NBCC & NFCC to commission integrated systems as a whole

• Subcommittee had various discussions as to what “commissioning” is

– Commissioning vs. Integrated Systems Testing

• Intent of the NBCC / NFCC were reviewed with NRC to align the ULC S1001 with Building and Fire Codes

Page 5: ULC Standards Update S524, S1001 Integrated Systems Testing

INTEGRATED SYSTEMS TESTING

• Highlights

– Address “gaps” in existing Standards

– Minimum testing to prove integrations

– Testing of integrations with systems in situ

– Not replacement for system review and acceptance by Responsible Design Professionals

– Not replacement or duplication of existing inspection, testing, and verification requirements

Page 6: ULC Standards Update S524, S1001 Integrated Systems Testing

ULC S1001 MAJOR SECTIONS

• Integrated Systems Testing Requirements

– Qualifications

– Integrated Testing Process

– Integrated Testing Requirements

– Documentation

– Periodic Integrated Systems Testing

– Retro Integrated Systems Testing

– Integrated Systems Testing for Modifications

Page 7: ULC Standards Update S524, S1001 Integrated Systems Testing

SCOPE AND QUALIFICATIONS

• Scope

– Methodology to verify and document integrations are installed and operating as per their design

• Participants and Qualifications

– Integrated Testing Participants

• Knowledge and experience with their systems

– Integrated Testing Coordinator

• Knowledge and experience with integrated systems, operation, and methods of validation

Page 8: ULC Standards Update S524, S1001 Integrated Systems Testing

PROCESS

• Planning Phase

– Design Professionals to provide documentation detailing interconnections, system designs, sequences, etc.

– Preparation of the Integrated Testing Plan

– Review of Plan by Design Professionals and AHJs

– Appendix B Guidelines

Page 9: ULC Standards Update S524, S1001 Integrated Systems Testing

PROCESS

• Implementation Phase

– Confirmation systems ready for testing

– AHJ notification

– Receipt of verification documents, approval certificates, design review letters

– Occupant Notification and Alternative Measures

– Implement Test Procedures

– Correct and Retest Failed Integrations

– Document Test Results

Page 10: ULC Standards Update S524, S1001 Integrated Systems Testing

TEST PROTOCOLS EXAMPLES

• Fire Pumps

– Test each interconnection by creating condition

• Emergency Generators

– Test each interconnection by creating condition

– Generator Start-Up Test

• Sprinkler Systems

– Test each interconnection by creating condition

– Acceptance of verification tests

Page 11: ULC Standards Update S524, S1001 Integrated Systems Testing

DOCUMENTATION

• Integrated Testing Report

– Integrated Testing Plan

– Documentation collected during Implementation

– Integrated Testing Forms

• Life Cycle Testing

– Periodic Integrated Systems Testing

– Retro-Integrated Systems Testing

– Testing after Modification

Page 12: ULC Standards Update S524, S1001 Integrated Systems Testing

APPENDIX

• Appendix A

– General information and background from the Working Group on the intent of requirements

– Examples of procedures and approaches that can be considered

• Appendix B

– Guidelines on developing Integrated Testing Plans

Page 13: ULC Standards Update S524, S1001 Integrated Systems Testing

ULC-S1001 CODE ADOPTION

• Proposed Code Changes submitted to reference to ULC-S1001 in the 2015 NBCC & NFCC

• Proposed Code Changes have been reviewed by the Reference Standards Working Group and Standing Committees

• Changes circulated for public comment

Page 14: ULC Standards Update S524, S1001 Integrated Systems Testing

CAN/ULC-S524-14 MAJOR CHANGES

Page 15: ULC Standards Update S524, S1001 Integrated Systems Testing

CAN/ULC-S524-14

• 6th Edition of the Standard published June 2014

• Amendment No. 1 in development

• Reorganization of Standard

Page 16: ULC Standards Update S524, S1001 Integrated Systems Testing

FIRE ALARM EQUIPMENT

• Wireless Devices – Listed equipment, installed to S524 and manufacturer

installation requirements

– Receipt of signal from device within 10 s of activation

– Removal of device to cause trouble identifying device

• Remote Power Supplies – Mounted 1500 - 2400 mm in accessible, conditioned space

– Located so not exposed to electromechanical, RF interference, or noise above manufacturer requirements

– Large scale networks, located in 1 h fire rated electrical room

– Fault to cause trouble at power supply, DCC, and annunciator

Page 17: ULC Standards Update S524, S1001 Integrated Systems Testing

FIRE ALARM EQUIPMENT

• Large Scale Networks

– S524-14: 1000 addresses, and two or more transponders

– Amendment No. 1: 1000 addresses and fire detectors, and two or more transponders

– Campus-Style Networks

• Monitoring Networks

• Command and Control Networks

Page 18: ULC Standards Update S524, S1001 Integrated Systems Testing

VOICE COMMUNICATION

• Audio inputs priority levels

• Requirement to synchronize audit tones and voice messages from multiple zones

• Examples of Voice Messages

• Guidance on Voice Intelligibility

• Automated (Digitized) Voice

Page 19: ULC Standards Update S524, S1001 Integrated Systems Testing

FIELD DEVICES

• Protective covers for devices subject to obvious mechanical damage or vandalism

• Manual stations to be installed 1050 mm to 1150 mm above the finished floor level

• Partitions within 15% of ceiling separate space

• Clearances to ceiling fans and unit heaters

Page 20: ULC Standards Update S524, S1001 Integrated Systems Testing

FIELD DEVICES

• Beam Ceiling Obstructions

– Solid Joists

– Smoke Detectors (beams 10% of room)

– Corridors 4.6 m or less in width

– Small Rooms 84 m2 or less in area

• Under Floor and Above Ceiling Placement

• Elevator Shafts

Page 21: ULC Standards Update S524, S1001 Integrated Systems Testing

FIRE SUPPRESSION SYSTEMS

• Reduced coverage for cross-zoned detectors

• Notification devices to provide unique signal between warning types and base building

• Releasing stations unique appearance & colour from fire alarm manual stations or be signed

• Disconnect switch to allow testing without actuation of fire suppression system

Page 22: ULC Standards Update S524, S1001 Integrated Systems Testing

VISIBLE SIGNALS

• Performance Based Design Option

• Recommended candela for Sleeping Rooms

• Visible Signal Silencing

– Occupant Notification – follow audible devices

– Warning – remain on until fire alarm reset

• Fire Do Not Enter Signs

Page 23: ULC Standards Update S524, S1001 Integrated Systems Testing

ADDITIONAL REQUIREMENTS

• Demarcation box for monitoring connections

• New Appendix Material

– Appendix A – Explanatory information and background from committee

– Appendix F – Annunciation for High Value Asset Fire Protection Systems

Page 24: ULC Standards Update S524, S1001 Integrated Systems Testing

THANK YOU

Simon Crosby

RBA Engineering

[email protected] 416-492-5886 x234