Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
HYDRAULICS BRANCH
OFFICIAL FILE COPY
EYJRhUL!C LABORATORY
NOT 'i"O BE Ei::.11CVED J.'ROivl FILES
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
* * *
* * * * * * *
* * *
* * * * * *
* * * * *
*
*
* *
* *
*
UN I TED SH :ES
DEPARTME�T OF THE INTERIOR
BUREAU OF RECLAMATION
HYDRAULIC LtBORfTORY REPORT �O. 153
hODEL STUDIES OF THE l�ITlfL
REG' LftTION OF FLOW tT t�DERSO� R�NCH DPM, SOiSE PROJECT
3y
FRED LOCHER. flSS0Cl�TE ENG!NEER
De�ver, C0lorarlo Seoter,ber L6, 1944
* * * * * * *
*
* * * * * * *
*
*
* *
* *
* * * *
* *
*
*
* *
* * * * * * * * * * * * * * * * * * * * � * * * * * * * * * *
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF RECLAMATION
Branch of Design and Construction Engineering and Geological Control and Research Division
Denver, Colorado Septenber 26, 1944
Laboratory Report No, 153 Hydraulic Laboratory
Compiled by Fred Locher Reviewed by J. E. Warnock
Subject: Model studies of the initial regulation of flow at Anderson Ranch Dam - Boise Project, Idaho.
1. The original design of the penstock at Anderson Ranch Dam
provided for the flow of water to the turbines and to a branching
line which lead to four 72-inch hollow-jet valves, At the reser
voir end of the.penstock a bulkhead-type gate was provided to allow
for u:mvateri ng the pens tock when necessary. The hollow-jet valves
would have provided for passing discharges up to 10,000 second-feet.
Larger flows which could not be stored in the reservoir would have
been discharged over too spillway. Due to the present emergency, it
was not possible to obtain the valves and to regulate the flow ac
cordingly. To conserve water and later pass it downstream to the
power plants during the dry season, it was necessary to change the
bulkhead gate to a regulating gate and operate the penstocks as ordi
nary outlets through the dam o
2. The regulation of flow with the temporary arrangement was
expected to begin in 1944, at which time it we.s expected that the
?rater level in the reservoir wouln be at elevation 4050. During the
1944 season e.nd part of the 1945 season the revised gate at the pen
stock was to be used for regulation of the flowo At some time during
1945 it was expected that the reservoir would have stored sufficient
water to raise the. level to plus or minus 4105, thereby creating suf
ficient head to make it impractical to use the gate as a regulating
device. At thi t'l point it was planned to place one of the 84-inoh
Boulder needle valves in the conduit for the regulation of flow and
the slide gate was to be returned to its original use as an emergency
bulkhead.
3. The use of the gate as a regulating device presented a prob-.
lem in cavitation which was further complicated by the fact tm.t at
no time during the release of water by. this method was the oondui t ex
pected to flow fullo Further, the intake was considerably above the
horizontal part of the conduit (figure 1), which would ne oeasi tate two
sharp turns in the flow before it reached the outleto It was expected
that this turning of the flow in the upper reaches of the conduit
would cause parts of the conduit to becolll8 filled near the intake, with
the result that severe subatmospheric preasurea and the resulting pit
ting would be obtainedo
4o A 1:40 hydraulic model was constructed to determine the oapac -
ity of the air vents and a suitable location for themo Preliminary ·
tests with the arrangement shown on figure l indicated that satisfac--.'.!: .
tory operation could be obtained by connecting an air-vent pipe be
tween the penstock immediately downstream from the 46-degree bend and
the upstream end of the transitiono As the horizontal part of the
penstock did not flow full. the vent pipe would have allowed air from
this region to flow into the cavity formed in the transition and would
prevent any severe subatmospherio pressures 0
5. The intake center line of this scheme was at elevation
3969.16 (figure l)o As several earth s lides in the reservoir area of
the prototype have already occurred, it appeared advisable to raise
the intake to elevation 4000000 to eliminate the danger of clogging by
some future slide or submerged trasho
6. In the new arrangement the center line of the intake was
placed at elevation 4000000, e.nd the connection to the present instal
lation was effected by a vertical drop "t9 a 90-degree bend at the be
ginning of the horiiontal part of the penstock (figure 2). The first
test with this arrangement showed th.at the water flowing under the gate
2
continued across the vartioal section of the conduit and was deflected
back and forth across the conduit as it dropped down to the horizontal
section, causing a siphon action which would have lowered the pressures
in the prototype to the vapor pressure Qf watero These pressures were
relieved, and the siphon action was partly broken by placing a l50-inch
air vent in the top of the transition downstream from the gates h<JW
ever, the pressures on the bottom of the transition were still suffi
ciently low to cause pittingo This oondition was remedied br placing
a step and another vent in the transition and also clanging the former
l50-inch vent to 20 inches in diameter {figure 3) o
7 o With this arrangement it would m ve been necessary to remove
the step when conditions made it unnecessary to use the gate as a
regulating device o To overcome this objection the step was changed to
a recess (fieure 3) having the same vent �stemo This scheme was
tested for regulation of flow with the gate and under the normal oper
ating conditions of the completed projecto There were no negative
pressures for normal operationo The recess and the vents did not have
any adverse effects on the flows, indicating that it would not be ne
cessary to fill or plug them after they had served their purpose. Some
negative pressure, still prevailed when the gate was used as a regulat
ing device, however, they were not serious enough to warrant the addi
tional cost to alleviate them, inasmuch a s the arrangement was to be
temporaryo The piezoiretric pressures converted to p_rototype, for aera
tion with the step and the. recess, are shown on figure 4o They apply
when the gate is used for regulating the flow.
DISCHARGE C . F S.
IO 4 0 0 - ----- -- -
8000
5880
4000
IO I 7 0
8 2 00
6080
4000
3 2 5 0
DISCHARGE C.F. S.
IO 2 7 0
8800
8 2 00
6070
3745
10 5 9 0
81 00
5 980
32 40
HEAD ON i GATE
FT WATER
I 02 . 0 �---- -
IO 2 . 5
IO 2 . 4
IO 5. 5
4 9. 7
5 I. 7
4 9. 3
5 0 . 8
49. 8
----
-
I
-6.0 ----
- 8. 8 - -- -
-8.4 -- --
-4. 6
- 9.0 ..
- 2 .4 -
- 3. 2
-7.4
- 3.6
.-- ·- --
2
39. 2 ---- --
4.6 -------
5 2 . 4 - -·
60. 8
12 . 0
18 .0 fL----
2 I. 6
28. 0
2 8. 8
PIEZOMETER NUMBER - -
3
4.0
3.6 ,__ _____
14.4
20. 0 - --·- -
- I. 40
I. 00
2 .80
6.40
10.8
-
4
4.0
- 1 .6 -· -·
- 8. 0
-5.6 -- -
3.8
3.4
I. 8
- 1 .4
- -- --
- .20
- -
5 6
- 1.6 -14.6 ----
-5.2 - 12 . 0
-8.0 - 8. 9
-7.2 -
- 1 .2 -
- I. 2 -
-2.4 -
- 4.4 -
- 4.0 -
7
-13. 6 -
- 11 . 6
- 8. 4
- 4.4
-12 .0
- 8.8
- 7. 6
- 4.0
- 2 . 8
PIEZOMETRIC PRESSURES FOR DESIGN 2 (Step in bottom of transition)
HEAD ON PIEZOMETER NUMBER i GATE
FT. WATER I 2 3 4 5 6 7
I 04. 0 17.8 -0.4 38. 8 0.6 - I. 8 -8.4 -12 . 2
IO 2 . 5 19.8 - 2 .0 43. 2 3.0 - I. 8 - 6.2 - 6. 2
IO 3 . 2 20. 6 - 1.2 50.4 5.0 - I. 2 -6. 2 - 6. 2
I 06. 6 25. 0 -7.4 5 7. 6 - 4.6 - 6.6 -4. 2 4.8
I 02 . 0 3.8 - 1.2 20. 4 -15.2 - 4. 8 0.0 0.0
48. 9 8.2 1 .6 8.8 - 0.6 - 0.2 - 5. 0 - 8. 0
48. 4 9.8 0.4 14.8 - 0.2 -0.2 -4. 0 - 6.4
5 5 . 6 I I. 2 - 1.8 26. 2 3.4 - 0.6 -2 .4 - 0.4
4 7. 2 1 1 . 0 - 2 .4 27. 2 9.0 7.0 - 2 . 0 - I. 4
PIEZOMETRIC PRESSURES FOR DESIGN 3 (Recess in bottom of transition)
Note: For piezometer locations see figure
...
·--
8
-4.0
- 4.0
- 1.0
-4.0 ·-
-4.5
- 3.0
0.0
0.2
0.2
8
-10. 4
- 10. 4
- 9. 4
- 8. 2
0.0
- 4. 2
- 5. 0
- 4.0
0.0 '1-i q:; �