Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Unearthing the Past to Chart the Future
INTRODUCTION• Logan City Council provides water and wastewater services to 300,000
people living and working across 957km2 of urban, semi-rural and emergingneighbourhoods.
• The City of Logan water supply network features 2,200km of mains,of which nearly 900km are asbestos cement (AC) pipes.
• Historically, Council’s water mains renewals programs were reactive andaddressed frequently failing AC mains (mainly DN100 reticulation mains).These mains are between 30 and 55 years old, as shown in Figure 1. Failuredata collected by Council indicates that the likely service life of AC mains is60 to 70 years, which means that the risk of pipe breaks and bursts in thecoming years is high.
• Pipefittingsinstalledacrossthecitybefore1980weremadeofunlinedcast iron, and they are now showing signs of severe tuberculation.
Troy Kasper, Priyanthi Samarakoon, Sandamali Weerakoon and Matt ThomsonLogan Water Infrastructure Alliance - Logan City Council, Downer, Cardno and WSP
Testing of AC pipes in the field
Testing of this 1980s AC pipe shows that the magenta areas are sound; the lighter coloured areas are not
Tuberculation in an unlined fitting
Replacement of fittings and mains presented opportunities to collect data on AC mains
2015
2014
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1998
1997
1996
1995
1994
1993
1992
1991
1990
1989
1988
1987
1986
1985
1984
1983
1982
1981
1980
1979
1978
1977
1976
1975
1974
1973
1972
1971
1970
1969
1968
1967
1966
1965
1964
1963
1962
0
Leng
th (k
ms)
110
100
90
80
70
60
50
40
30
20
10
AC PVC DICL CICL PE MSCL UK
AC Mains
Unlined Fittings
Figure 1: COMPOSITION AND QUANTITY OF WATER MAINS INSTALLED OVER TIME
RESULTS• Opportunistic condition assessments in one of the City of Logan’s older
water supply zones (Eagleby DMA 55) showed that:- while age was a factor in the deterioration of AC pipes, there was no direct
correlation between age and pipe failure rates- there was internal and external deterioration of the pipes (see Figure 2)- internal deterioration was not uniform, suggesting that pipe wall
composition during manufacture may have been inconsistent- there was evidence of possible periods of aggressive water in the pipes- results were inconsistent, with deterioration levels varying on each side offittings–possiblytheresultofvaryingqualityofACmainsorconstruction methods.
Percentage of pipe samples with external degradation
Percentage of pipe samples with internal degradation
Percentage of pipe samples with eff ective thickness > 60% (remaining life > 10 years)
Percentage of pipe samples with eff ective thickness > 40% and <–60%
Percentage of pipe samples with eff ective thickness <–40% of original wall thickness
Percentage of pipe samples estimated to fail within 10 years
100%0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
65%
29%
36%
35%
74%
91%
Figure 2: PERCENTAGE OF PIPE SAMPLES WITH DEGRADATION AND ESTIMATED REMAINING LIFE
CONCLUSIONOpportunistic condition assessments and failure analyses of AC water mains have increased Logan City Council’s knowledge of the variable condition of its water supply network. Gaining this knowledge by ‘unearthing the past’ is helping Council to make informed decisions about how to best manage ageing AC mains.
CONDITION ASSESSMENT APPROACH• A risk based approach was used to determine the priority of water mains
renewals in DMAs. This considered:- likelihood of water main failure based on criteria such as age, material,
pressure, environmental conditions (such as reactive clay) and historical performance
- assessment of the consequence of failure based on criteria such as diameter, location and critical customers serviced
- analysis of historical failures and failure modes to determine trends and hotspots.
Akeyfindingwasthatwaterpressureondeterioratedpipewallscontributedto nearly 50% of AC main failures.
• A practical, safe method was developed for opportunistic conditionassessment of AC mains on site, using a phenolphthalein indicator.Test results informed decisions on whether to renew the whole main orjustunlinedfittings.Theonsiteassessmentcouldbesupplementedbytesting of rubber rings and pressure testing of mains as desired.
CHALLENGES AND OPPORTUNITIES• Council recognised that the performance of AC water mains cannot bejudgedonfailurehistoryalone.Historicaldatadoesnotofferaforwardviewof likely pipe failures, or indicate where investment in water main renewalsis a priority. A better approach was required.
• Replacementofunlinedpipefittingsofferedanopportunitytocollectdata on AC mains. This was because replacement of the mains required aclean cut of the pipe. The cut section, particularly at a tee junction wherea hydrant and valve are located, was considered the ideal place for acondition assessment.
• Replacingwatermainsandfittingscanbehighlydisruptiveforcommunitymembers. A challenge was to plan a renewals program which minimised thefrequency and duration of impacts. A way to achieve this was to conduct allrenewals on a district metered area (DMA) basis, replacing all assets whichwere unlikely to provide an additional ten years of service.