Upload
lenhi
View
224
Download
1
Embed Size (px)
Citation preview
Università degli Studi di Pavia
Dottorato di Ricerca in Ingegneria
Elettronica, Informatica ed Elettrica
XXIII Ciclo
The need to coordinate generation and
transmission planning and to ensure
a secure and e�cient reactive power
provision: two key aspects of the
restructured electricity industry
Tesi di Dottorato di:
Ing. Ilaria Siviero
Relatore:
Chiar.mo Prof. Paolo Marannino
Anno Accademico 2009/2010
Contents
1 Introduction 1
1.1 Research motivations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1.1 Generation and transmission planning . . . . . . . . . . . . . . . . . . . . . 2
1.1.2 Reactive support and voltage control . . . . . . . . . . . . . . . . . . . . . . 3
1.2 Research objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.3 Thesis outline . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2 WTLR and power system planning 9
2.1 Power system planning and electricity market e�ciency . . . . . . . . . . . . . . . 10
2.1.1 Electricity market e�ciency . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
2.1.2 Generation system investments and Social Welfare . . . . . . . . . . . . . . 13
2.1.3 Transmission system expansion and Social Welfare . . . . . . . . . . . . . . 15
2.1.4 General considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.2 Power system planning and network security . . . . . . . . . . . . . . . . . . . . . 16
2.2.1 �Measuring� system security . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.2.2 Generation expansion and power system security . . . . . . . . . . . . . . . 18
2.2.2.1 Overload mitigation strategy . . . . . . . . . . . . . . . . . . . . . 18
2.2.3 Transmission planning and power system security . . . . . . . . . . . . . . . 20
2.2.3.1 WTLR and transmission planning . . . . . . . . . . . . . . . . . . 21
2.3 Matlab-coded program for WTLR sensitivity calculation . . . . . . . . . . . . . . . 23
2.3.1 Step 1: security analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
2.3.2 Step 2: ISDF calculation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
2.3.2.1 Distribution factor formulation . . . . . . . . . . . . . . . . . . . . 24
2.3.2.2 Post-contingency distribution factor . . . . . . . . . . . . . . . . . 28
2.3.3 Step 3: WTLR calculation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
2.3.4 Step 4: WTLR graphical representation . . . . . . . . . . . . . . . . . . . . 29
2.4 Application of the procedure to the CIGRE 63-bus system . . . . . . . . . . . . . . 30
2.4.1 Simulation hypotheses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
2.4.2 Base case . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
2.4.3 WTLR-based generation expansion and network security . . . . . . . . . . 34
2.4.4 WTLR-based grid development . . . . . . . . . . . . . . . . . . . . . . . . . 38
2.4.4.1 WTLR procedure results . . . . . . . . . . . . . . . . . . . . . . . 39
2.4.4.2 A WTLR-based metric for transmission planning . . . . . . . . . . 41
2.4.4.3 Validation of the WTLR-based metric . . . . . . . . . . . . . . . . 42
2.4.4.4 An index to prioritize transmission planning . . . . . . . . . . . . 43
i
CONTENTS ii
2.5 Changes in the original Matlab-coded procedure . . . . . . . . . . . . . . . . . . . 45
2.5.1 Introduction of the Line Outage Distribution Factors . . . . . . . . . . . . . 45
2.5.1.1 LODF formulation . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
2.5.1.2 Application to the CIGRE 63-bus system . . . . . . . . . . . . . . 46
2.5.1.3 Using the base ISDFs to compute WTLR sensitivities . . . . . . . 50
2.5.2 Adoption of the distributed slack bus . . . . . . . . . . . . . . . . . . . . . . 51
2.5.2.1 Impact of the choice of the slack bus . . . . . . . . . . . . . . . . . 51
2.5.2.2 Distributed slack bus . . . . . . . . . . . . . . . . . . . . . . . . . 53
2.6 Tests on the Italian EHV system . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
2.6.1 The MVA rating approximation . . . . . . . . . . . . . . . . . . . . . . . . . 57
2.6.1.1 Original procedure results . . . . . . . . . . . . . . . . . . . . . . . 58
2.6.1.2 Check by a standard steady-state security assessment tool . . . . 58
2.6.1.3 Considering the actual voltage magnitudes . . . . . . . . . . . . . 60
2.6.1.4 Considering the actual power �ow limits . . . . . . . . . . . . . . 60
2.6.1.5 Conclusions on the Matlab-coded procedure for WTLR calculation 61
2.6.2 WTLR sensitivity: a tool with several uses . . . . . . . . . . . . . . . . . . 62
2.6.2.1 GENCO viewpoint . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
2.6.2.2 TSO viewpoint . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
2.6.2.3 Interchangeability of generation expansion and transmission devel-
opment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
2.7 Chapter conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88
3 Reactive power service 91
3.1 Ancillary services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92
3.1.1 De�nitions in the U.S. markets . . . . . . . . . . . . . . . . . . . . . . . . . 92
3.1.2 Ancillary services in Europe . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
3.1.3 The Italian ancillary services . . . . . . . . . . . . . . . . . . . . . . . . . . 95
3.2 Reactive power . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
3.2.1 What is reactive power? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
3.2.2 The need for reactive power . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
3.2.3 Reactive power and blackouts . . . . . . . . . . . . . . . . . . . . . . . . . . 98
3.3 Reactive power support as ancillary service . . . . . . . . . . . . . . . . . . . . . . 99
3.3.1 Technical issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
3.3.2 Policy issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
3.3.3 A challenge for System Operator and Regulatory Authority . . . . . . . . . 101
3.3.3.1 Optimal provision for reactive power service . . . . . . . . . . . . 101
3.3.3.2 The e�ect of reactive power on real power and system security . . 101
3.3.3.3 Reactive power management: dispatch versus procurement . . . . 103
3.3.3.4 Reactive power remuneration schemes . . . . . . . . . . . . . . . . 103
3.3.3.5 Energy price volatility . . . . . . . . . . . . . . . . . . . . . . . . . 103
3.3.3.6 Reactive market power . . . . . . . . . . . . . . . . . . . . . . . . 103
3.4 Reactive power management review . . . . . . . . . . . . . . . . . . . . . . . . . . 104
3.4.1 Reactive power service in di�erent deregulated markets . . . . . . . . . . . 104
3.4.1.1 North America . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 104
3.4.1.2 Europe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105
CONTENTS iii
3.4.2 Literature on reactive power pricing and management . . . . . . . . . . . . 106
3.4.3 Possible policy solutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107
3.4.3.1 Decoupling of real and reactive power . . . . . . . . . . . . . . . . 107
3.4.3.2 Zonal reactive power management . . . . . . . . . . . . . . . . . . 108
3.4.3.3 Alternative sources of reactive power supply . . . . . . . . . . . . 108
3.5 Architecture of voltage control system . . . . . . . . . . . . . . . . . . . . . . . . . 108
3.5.1 Hierarchical voltage control system . . . . . . . . . . . . . . . . . . . . . . . 108
3.5.1.1 Basic SVR and TVR concepts . . . . . . . . . . . . . . . . . . . . 110
3.6 Reactive power service in Italy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
3.6.1 Current regulatory framework in Italy . . . . . . . . . . . . . . . . . . . . . 111
3.6.2 Reactive power service by generators . . . . . . . . . . . . . . . . . . . . . . 114
3.6.3 The Italian network voltage control system . . . . . . . . . . . . . . . . . . 115
3.6.3.1 Selection of pilot nodes, control areas, and control plants . . . . . 116
3.7 Optimal Reactive Power Flow program . . . . . . . . . . . . . . . . . . . . . . . . . 117
3.7.1 Compact reduced ORPF model . . . . . . . . . . . . . . . . . . . . . . . . . 120
3.7.2 Reactive power value . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
3.8 Wind energy exploitation and reactive power support . . . . . . . . . . . . . . . . 122
3.8.1 Technical performance requirements for connection of wind farms . . . . . . 123
3.8.1.1 Germany . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123
3.8.1.2 Spain . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124
3.8.1.3 Italy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124
3.8.2 Technology solutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127
3.8.2.1 WTG based reactive power compensation . . . . . . . . . . . . . . 127
3.8.2.2 External reactive power compensation . . . . . . . . . . . . . . . . 128
3.9 Tests on the Italian EHV network . . . . . . . . . . . . . . . . . . . . . . . . . . . 129
3.9.1 Main assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129
3.9.1.1 Wind power production . . . . . . . . . . . . . . . . . . . . . . . . 129
3.9.1.2 SVR control areas, pilot nodes, and controlling generators . . . . . 131
3.9.2 Test cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141
3.9.3 Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141
3.9.3.1 Test case 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141
3.9.3.2 Test case 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151
3.9.3.3 Test case 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 154
3.9.3.4 Test cases 4 and 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . 157
3.9.3.5 Real losses' variation . . . . . . . . . . . . . . . . . . . . . . . . . 160
3.10 Chapter conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161
4 Conclusions 164
A CIGRE-63 bus test system 166
B Power Distribution Factors 169
B.1 Basic distribution factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 169
B.2 Impact of changes in network topology and parameter values . . . . . . . . . . . . 171
B.2.1 Outage of a line . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172
B.2.2 Closure of a line . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172
CONTENTS iv
C Slack bus modeling in load �ow solutions 174
C.1 Single slack bus power �ow . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 174
C.2 Distributed slack bus power �ow . . . . . . . . . . . . . . . . . . . . . . . . . . . . 176
C.2.1 Participation factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 178
D Devices for reactive power support 179
D.1 Synchronous generators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 179
D.2 Distributed generators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 181
D.3 Synchronous condensers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 181
D.4 Supervar machines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 181
D.5 Shunt capacitors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182
D.6 Shunt reactors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182
D.7 Series capacitors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182
D.8 Flexible AC Transmission Systems (FACTS) . . . . . . . . . . . . . . . . . . . . . . 182
D.8.1 Static Var Compensators . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182
D.8.2 Static Synchronous Compensators . . . . . . . . . . . . . . . . . . . . . . . 183
D.8.3 Static Synchronous Series Compensators . . . . . . . . . . . . . . . . . . . . 183
D.8.4 D-var (Dynamic Var) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 183
D.8.5 Distributed SMES (D-SMES) . . . . . . . . . . . . . . . . . . . . . . . . . . 183
D.8.6 Uni�ed Power Flow Controllers . . . . . . . . . . . . . . . . . . . . . . . . . 183
D.8.7 Interline Power Flow Controllers . . . . . . . . . . . . . . . . . . . . . . . . 184
D.9 Wind generators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 184
D.10 User plants . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 184
D.11 Transmission lines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 184
D.11.1 High voltage DC transmission lines . . . . . . . . . . . . . . . . . . . . . . . 185
D.12 Transformers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 185
D.12.1 Transformer taps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 185
D.12.2 Phase Shifting Transformers . . . . . . . . . . . . . . . . . . . . . . . . . . . 185
D.13 Di�erences among equipment types . . . . . . . . . . . . . . . . . . . . . . . . . . . 186
E Italian hierarchical voltage control 188
E.1 Secondary Voltage Regulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 188
E.1.1 SART apparatus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 188
E.1.2 RVR apparatus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 190
E.2 Tertiary Voltage Regulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 191
E.2.1 NVR apparatus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 191
E.3 Control system algorithms and dynamics design . . . . . . . . . . . . . . . . . . . . 192
List of Figures
2.1 Graph illustrating consumer and producer surpluses . . . . . . . . . . . . . . . . . 11
2.2 Productive e�ciency + Allocative ine�ciency . . . . . . . . . . . . . . . . . . . . . 12
2.3 Productive ine�ciency + Allocative e�ciency . . . . . . . . . . . . . . . . . . . . . 12
2.4 Productive ine�ciency + Allocative ine�ciency . . . . . . . . . . . . . . . . . . . . 13
2.5 E�ects of a capacity expansion investment . . . . . . . . . . . . . . . . . . . . . . . 14
2.6 E�ects of a cost reducing investment . . . . . . . . . . . . . . . . . . . . . . . . . . 14
2.7 Technological investments and market e�ciency . . . . . . . . . . . . . . . . . . . . 15
2.8 Overload mitigation strategy using generation . . . . . . . . . . . . . . . . . . . . . 19
2.9 Transmission relief . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
2.10 Network equivalents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
2.11 Example of �le with contingency analysis results . . . . . . . . . . . . . . . . . . . 25
2.12 Example of �le with overloaded branches' ranking . . . . . . . . . . . . . . . . . . 25
2.13 Example of �le with WTLR sensitivities . . . . . . . . . . . . . . . . . . . . . . . . 29
2.14 Example of contourf result for WTLR graphical representation . . . . . . . . . . 30
2.15 Example of WTLR graphical representation . . . . . . . . . . . . . . . . . . . . . . 31
2.16 CIGRE 63-bus test system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
2.17 WTLR graphical representation - Base case . . . . . . . . . . . . . . . . . . . . . . 35
2.18 Node 33V1 WTLR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
2.19 System overload - New generator at node 33V1 . . . . . . . . . . . . . . . . . . . . 36
2.20 Node 5M1 WTLR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
2.21 System overload - New generator at node 5M1 . . . . . . . . . . . . . . . . . . . . 37
2.22 Node 66M1 WTLR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
2.23 System overload - New generator at node 66M1 . . . . . . . . . . . . . . . . . . . . 38
2.24 Network reinforcements for CIGRE 63-bus system . . . . . . . . . . . . . . . . . . 39
2.25 Total system overload for all test cases (decreasing order) . . . . . . . . . . . . . . 40
2.26 WTLR algebraic sum . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
2.27 Social Welfare for all test cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
2.28 Impact of the transaction ∆tst . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
2.29 Density function of the relative errors in line �ow approximations . . . . . . . . . . 48
2.30 Cumulative distribution function of errors in line �ow approximations . . . . . . . 48
2.31 Relative error on WTLR sensitivities using LODFs . . . . . . . . . . . . . . . . . . 50
2.32 ISDF error density function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
2.33 Scatter plot of the relative errors as a function of the ISDF magnitudes . . . . . . 52
2.34 E�ect of the approximations on WTLR sensitivities . . . . . . . . . . . . . . . . . 52
2.35 WTLR values with di�erent slack buses . . . . . . . . . . . . . . . . . . . . . . . . 54
v
LIST OF FIGURES vi
2.36 Cumulative distribution function of |DSISDF − ISDF | . . . . . . . . . . . . . . . 56
2.37 Impact of adopting a distributed slack bus model on WTLRs . . . . . . . . . . . . 57
2.38 Outaged and overloaded 380 kV lines . . . . . . . . . . . . . . . . . . . . . . . . . . 59
2.39 Impact of the MVA rating approximation on WTLRs . . . . . . . . . . . . . . . . 61
2.40 Geographical and virtual Italian zones . . . . . . . . . . . . . . . . . . . . . . . . . 63
2.41 WTLR map - Italian EHV system (year 2013) . . . . . . . . . . . . . . . . . . . . . 64
2.42 Possible new generation sites (year 2013) . . . . . . . . . . . . . . . . . . . . . . . . 64
2.43 Possible new generation sites (year 2015) . . . . . . . . . . . . . . . . . . . . . . . . 66
2.44 WTLR map - Italian EHV system (year 2009) . . . . . . . . . . . . . . . . . . . . . 69
2.45 Critical grid areas of the current Italian transmission system [23] . . . . . . . . . . 70
2.46 WTLR map - Scenarios A (top) and B (bottom) . . . . . . . . . . . . . . . . . . . 74
2.47 WTLR map - Scenarios C (top) and D (bottom) . . . . . . . . . . . . . . . . . . . 75
2.48 Wind generation capacity installed in Italy at the end of 2009 . . . . . . . . . . . . 76
2.49 Wind generation capacity expected in the medium-term . . . . . . . . . . . . . . . 76
2.50 WTLR map - Scenarios A (top) and B (bottom) without the new wind farms . . . 78
2.51 Network reinforcements considered in the study . . . . . . . . . . . . . . . . . . . . 79
2.52 WTLR algebraic sum . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
2.53 WTLR map (Benevento-Foggia reinforcement) . . . . . . . . . . . . . . . . . . . . 84
2.54 WTLR map (middle-Adriatic backbone reinforcement) . . . . . . . . . . . . . . . . 84
2.55 WTLR map (new line Montecorvino-Benevento) . . . . . . . . . . . . . . . . . . . 85
2.56 WTLR map (new line Deliceto-Bisaccia) . . . . . . . . . . . . . . . . . . . . . . . . 85
3.1 Example of a synchronous generator loading capability diagram . . . . . . . . . . . 102
3.2 Hierarchical structure for transmission network voltage control . . . . . . . . . . . 111
3.3 Italian regulation for voltage control and reactive exchanges . . . . . . . . . . . . . 112
3.4 Minimum requirement for the network-side reactive power supply - Germany . . . 125
3.5 PQ diagram of the wind energy plant at the grid connection point - Germany . . . 126
3.6 Common WTG electrical topologies . . . . . . . . . . . . . . . . . . . . . . . . . . 128
3.7 Geographic location of the �fteen wind collection substations . . . . . . . . . . . . 130
3.8 SVR areas for the Italian EHV system . . . . . . . . . . . . . . . . . . . . . . . . . 133
3.9 SVR areas and controlling generators - North Italy . . . . . . . . . . . . . . . . . . 133
3.10 SVR areas and controlling generators - Adriatic side . . . . . . . . . . . . . . . . . 134
3.11 SVR areas and controlling generators - Tyrrhenian side . . . . . . . . . . . . . . . 134
3.12 Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Choice of the pilot node of SVR area 7 . . . . . . . . . . . . 135
3.13 Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Choice of the pilot node of SVR area 8 . . . . . . . . . . . . 136
3.14 Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Choice of the pilot node of SVR area 13 . . . . . . . . . . . . 136
3.15 Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Area 2 (Baggio) . . . . . . . . . . . . . . . . . . . . . . . . . 137
3.16 Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Generating units of La Casella and Piacenza . . . . . . . . . 137
3.17 Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Generating units of Torviscosa and Monfalcone . . . . . . . . 138
3.18 Reactive power margins under AVR control (areas of Dolo, Forlì, and Villanova) . 143
3.19 Nodal marginal values of reactive power - Area 1 . . . . . . . . . . . . . . . . . . . 144
3.20 Nodal marginal values of reactive power - Area 2 . . . . . . . . . . . . . . . . . . . 144
3.21 Nodal marginal values of reactive power - Area 3 . . . . . . . . . . . . . . . . . . . 145
3.22 Nodal marginal values of reactive power - Area 4 . . . . . . . . . . . . . . . . . . . 145
LIST OF FIGURES vii
3.23 Nodal marginal values of reactive power - Area 5 . . . . . . . . . . . . . . . . . . . 146
3.24 Nodal marginal values of reactive power - Area 6 . . . . . . . . . . . . . . . . . . . 146
3.25 Nodal marginal values of reactive power - Area 7 . . . . . . . . . . . . . . . . . . . 147
3.26 Nodal marginal values of reactive power - Area 8 . . . . . . . . . . . . . . . . . . . 147
3.27 Nodal marginal values of reactive power - Area 9 . . . . . . . . . . . . . . . . . . . 148
3.28 Nodal marginal values of reactive power - Area 10 . . . . . . . . . . . . . . . . . . 148
3.29 Nodal marginal values of reactive power - Area 11 . . . . . . . . . . . . . . . . . . 149
3.30 Nodal marginal values of reactive power - Area 12 . . . . . . . . . . . . . . . . . . 149
3.31 Nodal marginal values of reactive power - Area 13 . . . . . . . . . . . . . . . . . . 150
3.32 SVR voltage pro�le of pilot nodes - Case 1 and Case 2 . . . . . . . . . . . . . . . . 152
3.33 Reactive marginal values in pilot nodes - Case 1 and Case 2 . . . . . . . . . . . . . 153
3.34 Map of nodal ¿/Mvarh indicators - Case 2 . . . . . . . . . . . . . . . . . . . . . . 154
3.35 Reactive power margins in Central-Southern Italy - Case 1 and Case 3 . . . . . . . 155
3.36 Reactive marginal values in pilot nodes - Case 1 and Case 3 . . . . . . . . . . . . . 156
3.37 Reactive marginal values in wind collector substations - Case 1 and Case 3 . . . . 157
3.38 Reactive marginal values in wind collector substations - Case 1 and Case 4 . . . . 159
3.39 Voltage pro�le of pilot nodes - Case 2 and Case 5 . . . . . . . . . . . . . . . . . . . 160
A.1 CIGRE 63-bus test system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 167
C.1 Flow-chart of a single slack bus load �ow . . . . . . . . . . . . . . . . . . . . . . . 177
D.1 An example of synchronous generator output capability curve [117] . . . . . . . . . 180
E.1 Hierarchical voltage control for the Italian EHV system . . . . . . . . . . . . . . . 189
List of Tables
2.1 Contingency list (CIGRE 63-bus system) . . . . . . . . . . . . . . . . . . . . . . . 32
2.2 Thermoelectric generation pro�le (CIGRE 63-bus system) . . . . . . . . . . . . . . 32
2.3 Contingency analysis results - Base case . . . . . . . . . . . . . . . . . . . . . . . . 33
2.4 WTLR sensitivities - Base case . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
2.5 Security analysis results for all test cases . . . . . . . . . . . . . . . . . . . . . . . . 40
2.6 Security analysis results - New line 1M1-5M1 or 2M1-5M1 . . . . . . . . . . . . . . 41
2.7 WTLR sensitivities - New line 1M1-5M1 or 2M1-5M1 . . . . . . . . . . . . . . . . 41
2.8 Economic indicators for all test cases (¿/h) . . . . . . . . . . . . . . . . . . . . . . 43
2.9 Index validation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
2.10 Contingency analysis results by using LODFs . . . . . . . . . . . . . . . . . . . . . 49
2.11 Contingency analysis results with di�erent slack buses . . . . . . . . . . . . . . . . 53
2.12 Participation factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
2.13 Contingency analysis results using the distributed slack bus power �ow . . . . . . . 55
2.14 Contingency analysis results (original procedure) . . . . . . . . . . . . . . . . . . . 58
2.15 WTLR sensitivities (original procedure) . . . . . . . . . . . . . . . . . . . . . . . . 59
2.16 Check by a standard steady-state security assessment tool . . . . . . . . . . . . . . 60
2.17 Contingency analysis results (considering the actual voltage magnitudes) . . . . . . 60
2.18 Contingency analysis results (considering the actual power �ow limits) . . . . . . . 61
2.19 OPF results (year 2013) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
2.20 OPF results (year 2015) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
2.21 Contingency analysis results (without doubling the Adriatic backbone) . . . . . . . 67
2.22 Priority list of the new generation sites (year 2015) . . . . . . . . . . . . . . . . . . 68
2.23 Contingency analysis results (year 2009) . . . . . . . . . . . . . . . . . . . . . . . . 69
2.24 Scenarios for assessing Italian EHV development plan bene�ts . . . . . . . . . . . . 71
2.25 Main grid reinforcements (2010 development plan) . . . . . . . . . . . . . . . . . . 71
2.26 Contingency analysis results - Scenario A . . . . . . . . . . . . . . . . . . . . . . . 72
2.27 Contingency analysis results - Scenario B . . . . . . . . . . . . . . . . . . . . . . . 73
2.28 Contingency analysis results - Scenario C . . . . . . . . . . . . . . . . . . . . . . . 73
2.29 Contingency analysis results - Scenario D . . . . . . . . . . . . . . . . . . . . . . . 73
2.30 Contingency analysis results (Benevento-Foggia reinforcement) . . . . . . . . . . . 80
2.31 Contingency analysis results (middle-Adriatic backbone reinforcement) . . . . . . . 80
2.32 Contingency analysis results (new line Montecorvino-Benevento) . . . . . . . . . . 81
2.33 Contingency analysis results (new line Deliceto-Bisaccia) . . . . . . . . . . . . . . . 82
2.34 Summary of the contingency analysis results . . . . . . . . . . . . . . . . . . . . . . 83
2.35 Contingency analysis results (New CCGT power plants) . . . . . . . . . . . . . . . 87
viii
LIST OF TABLES ix
2.36 WTLR values at some nodes in Central-South Italy . . . . . . . . . . . . . . . . . 87
3.1 Payments by Italian consumers for excess withdrawal of reactive energy . . . . . . 113
3.2 Bonus/penalty for reactive power as percentage of reference tari� - Spain . . . . . 127
3.3 Wind power collection substations . . . . . . . . . . . . . . . . . . . . . . . . . . . 130
3.4 Generation marginal costs of di�erent thermoelectric technologies . . . . . . . . . . 131
3.5 OPF results (maximum wind power generation) . . . . . . . . . . . . . . . . . . . . 131
3.6 Sensitivities∣∣∣ ∂QP,k
∂QA,h
∣∣∣ - Decoupling requirement . . . . . . . . . . . . . . . . . . . . . 139
3.7 Diagonal-dominance of the matrix∣∣∣ ∂QP,k
∂QA,k
∣∣∣ . . . . . . . . . . . . . . . . . . . . . . . 139
3.8 Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
3.9 Pilot node voltages and reactive power productions - Case 1 . . . . . . . . . . . . . 142
3.10 Losses' gradient and nodal marginal value in pilot nodes . . . . . . . . . . . . . . . 151
3.11 Pilot node voltages and reactive power productions - Case 2 . . . . . . . . . . . . . 151
3.12 Pilot node voltages and reactive power productions - Case 3 . . . . . . . . . . . . . 155
3.13 Pilot node voltages and reactive power productions - Case 4 . . . . . . . . . . . . . 158
3.14 Pilot node voltages and reactive power productions - Case 5 . . . . . . . . . . . . . 159
3.15 Real losses and their variations with reference to Case 3 . . . . . . . . . . . . . . . 161
A.1 Generator buses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 167
A.2 Load buses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 168
A.3 Transmission lines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 168
D.1 Characteristics of voltage-control equipment [43] . . . . . . . . . . . . . . . . . . . 186
Chapter 1
Introduction
1.1 Research motivations
Electricity markets around the world were for a long time either formed by vertically-integrated,
state-owned companies, or private �rms subject to governmental regulation that were often monop-
olies within their supply area. By the end of the century liberalization processes had been initiated
in many countries all over the world, although the process slowed after the dramatic failure of the
California market in 2000-2001.
The change to free markets is based on several economic and policy motivations that di�er strongly
from country to country. The primary reason for introducing competition in the developed coun-
tries (e. g. North America and Western Europe) is to increase the competition, and thereby also the
economic e�ciency in the operation of the electrical power system. For fast developing countries
(e. g. China and India), the typical reason is to create a more level playing �eld to attract private
investment, thereby relieving the government in funding the electric sector's growth that is cru-
cial to economic development. In addition the technological advancement of gas-�red turbines, in
particular highly e�cient combined cycle turbines, have broken the dominance of coal and nuclear
plants and signi�cantly lowered barriers to entry for private investors in generation.
Several approaches and measurements have been taken, including:
� restructuring: reorganizing the roles of market participants (including regulators and insti-
tutions), not necessarily a �deregulation� of the market;
� liberalization: synonym of restructuring with the aim of obtaining competitive markets;
� corporatization: make state-owned institutions act like private ones;
� privatization: selling state-owned assets to private stakeholders;
� deregulation: removing or simplifying government rules and regulations that constrain the
operation of market forces.
Successful liberalization generally requires: sector restructuring, implementation of competitive
wholesale markets and retail supply, incentive regulation of the grid, independent regulation, and
privatization.
Nevertheless, these processes have given rise to various issues in both planning and operating the
electric energy systems.
1
CHAPTER 1. INTRODUCTION 2
1.1.1 Generation and transmission planning
In the past, the electricity industry featured vertically integrated utilities. As a consequence,
transmission planning was closely coupled to generation planning. Utilities, because they owned
generation and transmission, could optimize investments across both kinds of assets considering
their interchangeability. With respect to operations, utilities routinely scheduled generation day-
ahead and re-dispatched generating units in real-time to prevent the occurrence of congestions.
The costs of such scheduling and re-dispatch were spread across all customers and re�ected in
retail rates. In addition, utilities had good data and forecasting tools to estimate current and
future loads and generating capacity. Because each utility was the sole provider of retail electricity
services, it had considerable information on current and likely future load levels and shapes. Since
each utility was the primary investor in new generation, it had considerable information on the
timing, types, and locations of new generation and corresponding information on the retirement
of existing units. Finally, the amount of wholesale electricity commerce was much less than it is
today and it was much simpler.
In today's electricity industry, generation and transmission are increasingly separated, either
through functional unbundling of these activities or through corporate separation. This de-
integration, combined with the competitive nature of electricity generation, makes it much harder
for transmission planners to coordinate their activities with those of generation owners. Speci�-
cally, transmission planners need detailed information on the timing, magnitudes, and locations of
new generating units; the developers of these facilities are unwilling to share competitive informa-
tion until required to do so (e. g. for environmental permits and for transmission-interconnection
studies).
One critical outcome of the de-integration of generation and transmission, the advent of many
new players (brokers, marketers, and power producers), and the consequent increasing number
of commercial transactions is the more frequent stressing of the transmission grid due to the
occurrence of congestion situations. One of the main reasons for the increasing frequency of
congestion is that the transmission network investments have not kept pace with the increasing
demand for transmission services. In the short-term, the only way to deal with the congestion
problem is through e�ective congestion management, i. e. through deploying e�cient procedures
to coordinate all participants' actions to maintain system reliability. Of necessity, congestion
management is no longer an internal matter, but it involves a system operator, transmission owners
(if di�erent from the system operator), power producers, and load-serving entities. But congestion
has rather serious long-term market e�ects, and consequently impacts the decisions regarding new
investments in both transmission and generation.
Congestion impacts market players in many di�erent ways. Congestion may prevent the use of
lower-priced generators to meet the load and consequently may result in a generation/demand
schedule with higher total costs and entailing losses of market e�ciency. Also, congestion facilitates
the opportunities to exercise market power through gaming by some players to increase their pro�ts.
Since in a competitive electricity market framework the grid is the interface where buyers and
sellers interact with each other, one of the main objectives of network planning is to provide a
nondiscriminatory competitive environment for all stakeholders while maintaining power system
reliability. Therefore, increasing transmission capacity is likely to be necessary to encourage and
facilitate competition among electric market participants, to provide nondiscriminatory access
to cheap generation for all consumers, to alleviate transmission congestion, and to mitigate the
CHAPTER 1. INTRODUCTION 3
possible exercise of local market power, as well as to increase the network reliability and security.
Although generation and transmission planning is no longer an integrated process, as it used
to be in the past, generation expansion decisions may be a�ected by decisions on transmission
expansion and vice versa. For instance, a transmission project may take �ve or ten years, longer
than two years or so for building a gas turbine or a combined cycle power plant. A generation
project may be initiated after the transmission project has commenced, potentially altering the
�nancial assumptions used to justify the transmission project. There is also the substitution e�ect
of transmission, that is, the transmission expansion can cause the substitution (in production)
of some expensive power plants, originally dispatched because of binding network constraints.
So generators are a�ected by transmission enhancements which will either expand their market
opportunities (if they are low-cost) or reduce their market opportunities (if they are high-cost and
have captive customers).
Producers' expansion investments and transmission development plans may con�ict because of
the diversity of their respective interests: on one hand, generation capacity expansion may worsen
existing network congestions and even compromise the e�ectiveness of a planned grid reinforcement;
on the other hand, the development plan of the transmission system can in�uence the planning
decisions taken by power producers, even discouraging the construction of new power plants, and
moreover transmission capacity increase may be not su�cient to allow existing and planned power
plants to be fully exploited.
Furthermore, the competitive business environment of generation pushes investors to faster plan-
ning, shorter deployment times, and less sharing of commercially sensitive information. The reg-
ulated business environment of transmission pushes it to slower planning and longer deployment
times (to accommodate an inclusive public process) and the wide sharing of information.
In conclusion, the split and di�erences between competitive generation and regulated transmis-
sion can lead to investment decisions in both sectors that are sub-optimal from a broad societal
perspective.
1.1.2 Reactive support and voltage control
The main function of an electrical power system is to transport electrical power from generators
to loads. In order to function properly, it is essential that the voltage is kept close to the nominal
value, in the entire power system.
Voltage control is in fact necessary because of the capacitance, resistance, and inductance of trans-
formers, lines, and cables. Since branches have a capacitance, resistance, and inductance, a current
�owing through a branch causes a voltage di�erence between the ends of the branch (i. e. between
the nodes being connected by the branch). However, even though there is a voltage di�erence
between the two ends of the branch, the bus voltage is not allowed to deviate from its nominal
value in excess of a certain value (normally 5% to 10%). Appropriate measures must be taken to
prevent such deviation. Voltage control refers to the task of keeping the bus voltages in the system
within the required limits and of preventing any deviation from the nominal value to become larger
than allowed.
The node voltage is a local quantity, as opposed to system frequency, which is a global or system-
wide quantity. It is therefore not possible to control the voltage at a certain bus from any point in
the system, as is the case with frequency. Instead, the voltage of a certain node can be controlled
only at that particular node or in its direct vicinity.
CHAPTER 1. INTRODUCTION 4
This is achieved di�erently for transmission networks and for distribution grids because of the
di�erent characteristics of the branches in transmission networks and distribution grids and the
divergent numbers and characteristics of the generators connected to both. Transmission networks
mainly consist of overhead lines with very low resistance. The voltage di�erence between two ends
of a line with a high inductive reactance X when compared with its resistance R (i. e. with a low
R/X ratio) is strongly a�ected by what is called the reactive power �ow through the line.
Owing to the characteristics of transmission networks and the connected generators, voltages are
controlled principally by changing the reactive power generation or consumption of large-scale
centralized generators connected to the transmission network. They are very �exible in operation
and allow a continuous control of reactive power generation over a wide range, according to their
loading capability diagram. Sometimes, dedicated equipment is used, e. g. capacitor banks or
technologies referred to as �exible AC transmission systems (FACTS). These are, in principle,
controllable reactive power sources.
In contrast, distribution grids consist of overhead lines or underground cables in which the resis-
tance is not negligible when compared with the inductance (i. e. that have a much higher R/X
ratio than transmission lines). Therefore, the impact of reactive power on bus voltages is less
pronounced than in the case of transmission networks. Further, the generators connected to dis-
tribution grids are not always capable of varying their reactive power output for contributing to
voltage control. So voltages in distribution grids are controlled mainly by changing the turns ratio
of the transformer that connects the distribution grid to the higher voltage level and sometimes
also by devices that generate or consume reactive power, such as shunt reactors and capacitors. In
general, distribution grids o�er fewer possibilities for voltage control.
By using large-scale power plants to regulate voltages in the transmission network and by using
dedicated devices in distribution grids to regulate the voltages at the distribution level, a well-
designed, traditional power system can keep the voltage at all nodes within the allowed band
width.
This was the approach traditionally adopted, when vertically integrated utilities operated power
generating units, on the one hand, and power transmission and distribution systems, on the other
hand. They also handled the voltage control issue, both short-term (day-to-day dispatch of units)
and long-term (system planning).
Owing to recent developments, this situation has been however changed. The liberalisation and
restructuring of the electricity industry has resulted in the unbundling of power generation and
grid operation. These activities are no longer combined in vertically integrated utilities as they
used to be. As a consequence, voltage control is no longer a �natural part� of the planning and
dispatch of power plants. Now, independent generation companies carry out the planning and
dispatch, and, in the long term, conventional power stations that are considered unpro�table will
be closed down without considering their importance for grid voltage control. In addition, the
grid companies have to solve any voltage control problem that may result from the decisions
taken by generation companies. In the short term, this can be done by requiring the generation
companies to re-dispatch. In the long term, additional equipment for controlling the voltage can
be installed. Moreover, the voltage control and the reactive power support are now considered an
ancillary service that grid companies often have to remunerate. Another recent development is that
generation is shifted from the transmission network to the distribution grid. As a result of these
two developments (unbundling and decentralisation), it is becoming more di�cult to control the
voltage in the entire transmission network from conventional power stations only. Grid companies
CHAPTER 1. INTRODUCTION 5
respond by installing dedicated voltage control equipment and by requiring generation equipment
to have reactive power capabilities independent of the applied technology. This means that no
exception is made for wind power or other renewables any longer, as has often been the case until
now.
In particular, among the recent developments that challenge the traditional approach to voltage
control, there is the increasing exploitation of wind energy for generating electricity. Until few
years ago, most wind turbines have been erected as single plants or in small groups and connected
to distribution grids. Now the attention is shifted towards large-scale wind farms to be connected
to the transmission network. The wind farm a�ects the power �ows and hence the bus voltages. As
regards the transmission network, voltages are controlled mainly by large-scale conventional power
plants. If their capability to control voltages throughout the transmission grid is not su�cient to
compensate for the impact of the wind farms on the node voltages, the voltage at some buses can
no longer be kept within the allowed range around its nominal value and appropriate measures
have to be considered and taken.
Concerning this, two issues are particularly important. The voltage control capabilities of wind
turbines are becoming an increasingly important consideration regarding grid connection to ensure
appropriate voltages at their connection point. So grid codes often include some kind of reactive
power requirement for wind farms, usually expressed in terms of power factor range. Moreover, it
is likely that, thanks to its dispatching priority, the wind power production will replace the power
generation of conventional plants so reducing their voltage control capability. The problem will be
more serious if the wind farms are far from the big load centers, even in remote areas or o�shore.
So it may be inevitable to take additional measures to control the grid voltage.
1.2 Research objectives
The research work presented in this thesis investigates the two issues discussed in the preceding
section.
The above considerations have made clear that in liberalised electricity markets there is the need
to better coordinate generation and transmission expansion in order to achieve a more coherent
development of the whole power system, that will favourably a�ect both system operation and
market e�ciency. The �rst part focuses on this issue. A methodology based on the nodal index
called Weighted Transmission Loading Relief, recently proposed in literature, is de�ned. The
WTLR sensitivity seems to be suited to attain the above-mentioned purpose since it is capable of
�measuring� the impact of real power injections into the grid on system security. In particular, its
basic concept is that an injection may help to mitigate the overload on a grid branch by creating
a counter-�ow, so suggesting the importance of strategic generation siting (i. e. of determining
geographic locations where new generation would enhance the system security by creating post-
contingency counter-�ows that would mitigate overloads under contingency conditions). The use
of this tool by a generation owner to assist the de�nition of its expansion plan may thus favour
the system security enhancement. But this is not a task pertaining to power producers in the
restructured electricity industry. Nevertheless, as explained in the previous section, also generation
owners may bene�t from strategic generation siting because network bottlenecks may limit the
dispatchability of new power plants and thereby advantage less e�cient ones. The �rst objective of
the research work is to show this use of the WTLR tool, while the second purpose is to demonstrate
that it can be helpful also to transmission planners. Consequently, the WTLR methodology could
CHAPTER 1. INTRODUCTION 6
allow both generation and transmission planning goals to be reached, even though they are di�erent
and sometimes in disagreement in a liberalised environment. Moreover, since the WTLR main
objective is the network security enhancement, that can be achieved also thanks to an appropriate
generation expansion, the whole power system and especially its operation could bene�t from
adopting this approach.
The second part of the research work deals with the reactive power management in post-deregulation
electricity industry. As results from the preceding section, this topic has become much more impor-
tant after the electricity market liberalisation and especially after the unbundling process, that has
led to the de-integration of generation and transmission. There are many important and crucial
aspects concerning this topic, some deriving from the peculiarities of reactive power supply, some
due to the new liberalised environment, some resulting from the increasing interest in renewable
technologies and particularly in wind power exploitation. The research focuses on three chief is-
sues: the optimal reactive power provision that �ts the needs of system operators, the de�nition
of a possible remuneration scheme for reactive power providers, and the impact of wind power on
voltage control and reactive power support. The main tool used in the analysis is an Optimal
Reactive Power Flow (ORPF) program, designed for hierarchical voltage regulation structures,
such as that developed for the Italian EHV system by its past monopolistic utility. Some nodal
indicators are calculated allowing both economic and security aspects to be investigated. On one
hand, they provide the economic value of VAR sources at a certain bus in the system, so suggesting
a suitable �nancial compensation scheme for reactive power service and the implementation of a
zonal reactive market based on the Secondary Voltage Regulation (SVR) areas; on the other hand,
they identify the network locations (nodes or areas) that are poor in terms of reactive sources,
so giving the transmission planner useful indications about the additional measure to be taken to
control the voltages. The technical requirements for grid connection of wind farms and especially
their possible utilization under primary and secondary voltage regulation are examined to assess
the impact of wind generation on voltage control and the bene�ts resulting from wind farms' par-
ticipation in reactive power support. Finally, the e�ects of the planned network reinforcements are
investigated.
In view of the above discussions, the main objective of this research work is therefore to present
suitable approaches for achieving more coordination between generation expansion and transmis-
sion development, on one hand, and for ensuring a secure and e�cient reactive power provision and
for favouring the integration of wind farms in power systems, on the other hand, in the context of
the new planning and operating paradigms of deregulated electricity industry.
1.3 Thesis outline
This thesis is organized in two main parts which refer to the two topics considered in the research
work.
Chapter 2 deals with the methodology based on the Weighted Transmission Loading Relief sensi-
tivities and its application to power system planning. After investigating the relationship between
generation expansion and transmission planning in a liberalised environment and their respective
e�ects on both electricity market e�ciency and power system security (Sections 2.1 and 2.2), the
WTLR-based methodology is described, and the MATLAB procedure implemented for the cal-
culation and graphical representation of WTLRs is presented in Section 2.3. First, it is applied
to the CIGRE 63-bus test system in order to check the outcomes' correctness and then to de-
CHAPTER 1. INTRODUCTION 7
�ne a possible metric for prioritizing transmission planning (Section 2.4). Some changes made in
the original MATLAB procedure, including the introduction of Line Outage Distribution Factors
(LODFs) and the adoption of the distributed slack bus, are described, and their impact on the
procedure results are analysed in Section 2.5. Finally, in Section 2.6 the methodology is used to
carry out some analyses on the Italian EHV electric system at di�erent projection horizons, with
the aim of demonstrating the potential applications of the WTLR tool for power system planning.
In particular, as regards the producers' viewpoint, some simulations are performed considering a
possible set of new generation sites in order to de�ne a priority list. Instead, as regards trans-
mission planning, the tests on the Italian system presented in the chapter show that the WTLR
procedure can be used to identify the weakest grid areas and elements, to demonstrate the develop-
ment plan bene�ts, to assess the impact of an increasing wind penetration on network security, to
rank a set of planned transmission reiforcements, and to propose new grid reinforcements. Finally,
the interchangeability of generation and transmission investments, in terms of system security
enhancement, is demonstrated.
Chapter 3 looks at the reactive power support and voltage control ancillary service in the restruc-
tured and liberalised environment. First, it brie�y introduces the concept of ancillary services and
proposes a summary of their de�nition in di�erent markets, including the Italian one (Section 3.1).
Then it reviews the essential and basic principles of reactive power support and voltage control,
giving an interesting overview of the main general issues, both technical and regulatory, related
to the procurement and management of these services, and showing the various challenges with
which the System Operator and the Regulatory Authority have to deal, especially concerning the
provision mechanism and the remuneration scheme (Sections 3.2 and 3.3). Section 3.4 presents a
detailed review of the reactive power management topic, brie�y describing the approach to reac-
tive power provision in di�erent deregulated markets in North America and Europe, and making
a summary of the literature on reactive power pricing and management. In Section 3.5 the ar-
chitecture of the voltage control system is considered with particular regard to its organization
into three-level hierarchy, which is the voltage regulation structure set up for the Italian electric
system by its past monopolistic utility (ENEL). In particular, the basic principles of Secondary
and Tertiary Voltage Control are described. Section 3.6 deals with the reactive power service in
Italy, providing an outline of the current regulatory framework and of the main characteristics of
its network voltage control system. The Optimal Reactive Power Flow program (ORPF), that has
a fundamental role in hierarchical voltage control scheme since it computes the optimal voltage
pro�les and reactive levels, is presented in detail, and how to derive an economic value of reactive
power from its solution is delineated (Section 3.7). Section 3.8 investigates the impact of wind
power on voltage control and reactive power procurement, and a summary of some regulatory
requirements with regard to reactive power control in steady-state conditions for wind plants and
of some existing technology solutions is provided. The results of the tests on the Italian EHV
system are presented in Section 3.9. Firstly, the generation pro�les at the �fteen wind collection
substations, connected to the 380 kV network, considered in the analysis, are de�ned by means
of an Optimal Power Flow program. Then the control areas, pilot nodes, and controlling gener-
ators are selected according to some speci�c criteria. The test cases are de�ned considering the
following aspects: what kind of generators operates under voltage control (synchronous generators
and/or wind farms), planned transmission reinforcements in service or not in service, presence of
the large-size wind farms connected to the 380 kV network.
Finally, the main characteristics of the CIGRE 63-bus network will be described in Appendix A.
CHAPTER 1. INTRODUCTION 8
Appendix B will treat the theory of Power Distribution Factors, which has been the basis for deriv-
ing the approximate Injection Shift Distribution Factors (ISDFs), in normal and post-contingency
conditions, and the Line Outage Distribution Factors (LODFs), both implemented in the MAT-
LAB program for WTLR calculation. In Appendix C the issue of slack bus modelling in load �ow
solutions will be discussed, with particular regard to the basic concepts of the distributed slack
bus model and its di�erences with respect to the traditional power �ow formulation. Appendix D
and Appendix E will analyse two aspects of reactive power supply and voltage control thoroughly:
they will describe the devices capable of providing reactive power support and the main technical
features of the Italian hierarchical voltage control system.
Chapter 2
WTLR and power system planning
The evolution of the electricity industry from the past vertically integrated utilities to the nowadays
deregulated and unbundled structures has introduced deep changes in the planning and operation of
electric energy systems. In this new environment the coordination between transmission planning
and generation expansion is no longer assured as it used to be in vertically integrated structures,
where both transmission network and generation power plants belonged to the same utility com-
pany. Traditionally the integrated planning of generation and transmission systems was in fact
the responsibility of vertically integrated utilities under state regulatory oversights. In today's
increasingly competitive electricity markets, self-interested players and competitors participate in
the planning and operation of power systems. Generation companies (GENCOs), as independent
and for-pro�t market entities, are freely and actively making plans for generation expansion, which
could dramatically impact existing transmission �ows and congestions. Customers can also select
their own electric energy suppliers based on economics, power quality, and security. Instead, the
transmission system continues to be regarded as a regulated monopoly. As a consequence, the
transmission system planning is facing credible challenges for managing its operation economics
and security. So the con�ict between these two aspects is inevitable in the restructured electricity
industry planning.
In the VIU (Vertically Integrated Utility) arrangement, the aim of the integrated planning of
generation and transmission systems was to minimize both investment and operation costs, while
supplying demand for energy over a time horizon, keeping the quality and reliability standards
of the network. In the competitive electricity market, as demand grows and new power plants
are installed, increasing transmission capacity is likely to be necessary also to improve market
competition and mitigate the possible exercise of locational market power. In particular, the
Transmission System Operator (TSO) has to de�ne �strong and �exible� transmission expansion
plans to face the numerous uncertainties which can characterize the planning process. The analysis
of present and forecast scenarios of the electric system allows the TSO to determine where, when,
and what kind of network reinforcements need to be built in order to avoid both security and
economic ine�ciencies in the future.
One of the main uncertainties that the Transmission System Operator has to consider in transmis-
sion planning, to ensure a secure, reliable, and uninterrupted electricity supply, is the generation
system development (i. e. size and location of new power plants). In competitive electricity mar-
kets GENCOs' objective for generation resource planning is to maximize expected payo�s over
planning horizons. Such generation system development, which is not necessarily correlated to the
9
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 10
network planning, could also reduce the electricity market e�ciency: it could lead to a bad location
of the cheapest power plants, whose generation would be substituted by that of more expensive
units, because of the occurrence of network congestions. Moreover, it could reduce the expected
e�ectiveness of a grid reinforcement planned by the TSO.
Therefore, a better exploitation of both existing and planned network facilities would be attained
if there were a more coherent development of generation and transmission systems. More coordi-
nation would be justi�ed by the strong interrelationship between these two systems. The planning
decisions taken by power producers can in fact in�uence the development plan of the transmission
system, and vice versa.
Finally, besides being interdependent, generation investments and transmission expansion may be
equivalent in terms of both improving electricity market e�ciency and enhancing power system
security, that is, generation and transmission may be interchangeable.
The chapter will investigate these issues, and then it will describe a methodology, based on a nodal
index called Weighted Transmission Loading Relief (WTLR), capable of assessing the impact of
generation on network security. A MATLAB program for the calculation of this indicator and its
application to a test system (CIGRE 63-bus system) will be presented. Finally, some simulations
on the Italian EHV electrical system will be shown in order to demonstrate the tool usefulness for
generation and transmission planning and especially for attaining a more coherent development of
the whole power system.
2.1 Power system planning and electricity market e�ciency
2.1.1 Electricity market e�ciency
According to an economic de�nition, the Social Economic Welfare is the di�erence between a
product's value to the consumer and its cost of production. It is also the sum of producer pro�t
and consumer surplus in a free market economy. The producer surplus is the amount that producers
bene�t by selling at a market price mechanism that is higher than they would be willing to sell for.
Instead, the consumer surplus is the amount that consumers bene�t by being able to purchase a
product for a price that is less than they would be willing to pay [1].
On a standard supply and demand (S&D) diagram, consumer surplus is the triangular area above
the price level and below the demand curve, since intramarginal consumers are paying less for the
item than the maximum that they would pay. On the contrary, producer surplus is the triangular
area below the price level and above the supply curve, since that is the minimum quantity a
producer can produce (Figure 2.1).
Economic e�ciency is a general term in economics describing how well a system is performing, in
generating the maximum desired output for given inputs with available technology.
A system can be called economically e�cient if:
� no one can be made better o� without making someone else worse o�;
� more output cannot be obtained without increasing the amount of inputs;
� production proceeds at the lowest possible per unit cost.
Productive e�ciency occurs when production of one good is achieved at the lowest possible cost,
given the production of the other good(s). Equivalently, it is when the highest possible output
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 11
Figure 2.1: Graph illustrating consumer and producer surpluses
of one good is produced, given the production level of the other good(s). In other words, it
is the optimum organization of production: �rms produce the demanded quantity of goods or
services (electric energy in our case) at the minimum cost, considering the current best-practice
technological and managerial processes.
Allocative e�ciency occurs when consumers get the maximum quantity of goods or services (elec-
tric energy in our case), given the current production costs. In other words, it is the optimum
management of commercial exchanges.
Necessary and su�cient condition for the Social Welfare maximization is that productive and
allocative e�ciencies are jointly ful�lled. This condition is represented by Figure 2.1, in which
both produced and consumed quantities are the highest possible at the lowest possible cost.
The other market conditions that can occur are the following:
� Productive e�ciency + Allocative ine�ciency (Figure 2.2)
Production costs are the lowest possible, but the market quantity is not the highest possible,
because of ine�ciencies in electric energy exchanges. By causing a di�erence between the
price received by producers and that paid by consumers, the Transmission System Operator
secures the area labeled Congestion Revenue, which comes at the expense of the consumer
surplus and producer surplus that would have existed in case of allocative e�ciency. The
�gone� triangle of Deadweight Loss (DWL) goes to no one because those transactions are
prevented by transmission limits.
� Productive ine�ciency + Allocative e�ciency (Figure 2.3)
Both produced and consumed quantities are the highest possible, given the current production
costs. But the given output could be produced at a lower cost.
� Productive ine�ciency + Allocative ine�ciency (Figure 2.4)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 12
Figure 2.2: Productive e�ciency + Allocative ine�ciency
Figure 2.3: Productive ine�ciency + Allocative e�ciency
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 13
Figure 2.4: Productive ine�ciency + Allocative ine�ciency
The market quantity is not the highest possible and also the production costs are not the
lowest possible.
2.1.2 Generation system investments and Social Welfare
From the viewpoint of Social Welfare, the most relevant investments are those in �xed assets, which
include machinery, buildings and land, and in technology [2].
For our purposes, it is enough to consider only two types of investments in power generation system:
� capacity expansion;
� cost reducing.
Capacity expansion investments enable a �rm to expand the amount of its production volume
that is produced at minimum unit costs. There are two types of �rms which undertake these
investments:
� a �rm already in the sector (left side of Figure 2.5);
� a new �rm, if the market system is competitive.
The e�ects of generating capacity investments are:
� if the investment is made by a new �rm and the market system is non-competing, the market
will become more competitive and the market power will decrease;
� the competitive o�er is expanded for the same price (right side of Figure 2.5);
� the investment can allow capacity/reliability constraints to be ful�lled: for instance, in the
face of demand uncertainty in the short-run, it allows a reserve capacity to be available.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 14
Figure 2.5: E�ects of a capacity expansion investment
Figure 2.6: E�ects of a cost reducing investment
Cost reducing investments consist in adopting new equipments to modernize the production cycle
or in replacement and extraordinary maintenance of existing facilities: from the viewpoint of a
�rm, these investments have the main purpose of reducing the unit costs, as shown by the left side
of Figure 2.6. The consequences on the sector supply are instead represented on the right side of
Figure 2.6.
In conclusion, the e�ects of technological investments on Social Welfare are (Figure 2.7):
� Cost minimization: both expansion capacity and cost reducing investments allow the produc-
tive e�ciency to be improved because the total costs are reduced, tending more and more to
the long-run costs. More precisely, the sector supply will tend to the long-run supply curve,
when the most e�cient �rms have been imitated (by new ones or competitors), while the
least e�cient ones have changed their production and cost structure.
� Market power mitigation: if a new �rm enters the market, there will be more competition
and the allocative ine�ciency will be reduced.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 15
Figure 2.7: Technological investments and market e�ciency
2.1.3 Transmission system expansion and Social Welfare
Transmission system investments consist in developing new network assets and in upgrading the
existing ones. Their main objectives are:
� to develop the interconnections among national areas to reduce grid bottlenecks and network
congestions;
� to increase the transmission capacity of the interconnection corridor between two neighbour-
ing countries;
� to connect new power plants or new loads to the electricity network.
In competitive electricity markets, an increase in transmission capacity can have two di�erent
e�ects on Social Welfare, named [3]:
� substitution e�ect, which was the only economic e�ect of the transmission expansion in
vertically integrated structures;
� strategic or competition e�ect.
On one hand, the transmission expansion can cause the substitution (in production) of some
expensive power plants, originally dispatched because of binding network constraints, by cheaper
ones, so reducing the total generation costs and improving the productive e�ciency (substitution
e�ect).
On the other hand, an increase in transmission capacity can allow market participants to sell/buy
power demanded/produced far away, which encourages competition among �rms, so mitigating the
possible exercise of market power and improving the allocative e�ciency (strategic e�ect).
2.1.4 General considerations
According to the preceding subsections, in competitive electricity markets an increase in transmis-
sion capacity may have the same e�ect of a generation system investment on Social Welfare and
market e�ciency.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 16
The substitution e�ect can allow low-cost power to be produced in greater quantities so improving
the productive e�ciency. In this case, an increase in transmission capacity is equivalent to a
generation investment aimed at expanding the total production capacity (generation expansion
investment) or at reducing the total generation costs (cost reducing investment).
The strategic e�ect can encourage competition among producers and improve the allocative e�-
ciency. In this case, an increase in transmission capacity has the same e�ect of the entry of new
�rms into the market.
Therefore, these brief remarks highlight that generation investments and network expansion may
be equivalent in terms of electricity market e�ciency and Social Welfare improvement.
The next section will also demonstrate that system security may bene�t from an appropriate choice
of new power plants' sites, besides from transmission planning.
2.2 Power system planning and network security
The bulk power system is made up of three main parts: generation, transmission, and load (i. e.
customer electric demand). The electric industry uses terms such as reliable, unreliable or system
reliability as qualitative measures of the relative strength or balance of the bulk electric system.
Reliability is the term used by the electric industry to describe and measure the performance of the
bulk power system. It is the degree to which the performance of the elements of that system results
in power being delivered to consumers within accepted standards and in the amount desired. The
degree of reliability may be quantitatively measured by the range of operating conditions under
which the system performs within acceptable parameters.
For instance, NERC (North American Electric Reliability Corporation) de�nes the reliability of
the interconnected bulk power system in terms of two basic and functional aspects [4]:
� Adequacy: the ability of the bulk power system to supply the aggregate electrical demand
and energy requirements of the customers at all times, taking into account scheduled and
reasonably expected unscheduled outages of system elements.
� Security (or operating reliability): the ability of the bulk power system to withstand sudden
disturbances such as electric short circuits or unanticipated loss of system elements from
credible contingencies.
In plain language, adequacy implies that su�cient generation and transmission resources are avail-
able to meet projected needs plus reserves for contingencies. Instead, security implies that the
power system will remain intact even after outages or equipment failures.
From the static viewpoint, network security can be summarized to include the following conditions:
no loss of load, bus voltages within power quality bounds, line �ows not exceeding thermal limits,
and the system operating away from the point of static voltage collapse.
2.2.1 �Measuring� system security
The transmission system security for a given scenario can be assessed by means of contingency
analysis simulations. Contingency analysis [5] de�nes a set of plausible contingencies that represent
events such as failure or disconnection of network devices. A �contingency list� contains each of the
elements that will be removed from the network model, one by one, to test the e�ects for possible
overloads of the remaining grid elements. In its basic form, contingency analysis executes a power
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 17
�ow calculation for each potential problem that is de�ned by the contingency list: the failure or
outage of each element in the contingency list (e. g. a loss of a transmission line) is simulated in
the network model by removing that element. The resulting network model is solved to calculate
the new power �ows, voltages, and currents for the remaining elements of the model.
The outcomes can be tabulated in order to detect the contingencies that may lead to severe or
critical operating conditions, and to decide remedial actions, such as re-dispatch or load shedding.
They can be also used to determine the transmission lines or transformers that present severe
violations for one or multiple outages, and to rank grid branches according to their relative �weak-
ness�. So this analysis supplies some useful information not only about the need to upgrade the
transmission system, but also about the way of designing its expansion to avoid thermal overloads
under speci�c conditions.
There are several metrics that can be adopted to rank weak grid elements: for example, the
number of contingencies that cause overloads in a speci�c branch or its maximum percentage
overload. Nevertheless, the former does not consider the overload severity, while the latter does
not take into account the number of overloads.
An indicator that captures both the contingency severity and the presence of multiple violations
can be derived as follows [6]. Let:
� PCO% be the branch percentage overload that appears in a line when a contingency occurs;
� PACO% be the sum of all overloads in a particular branch.
In other words, the aggregate contingency overload for a given line (or transformer) jk is calculated
as:
PACO%,jk =∑c
P cCO%,jk c ∈ Contingency List (2.1)
This quantity is expressed in percentage and it is not able to discriminate among voltage levels:
for instance, a 10% overload in a low voltage element would have the same rank as a 10% overload
in a higher voltage element. So it is useful to convert it to MW:
PACO,jk = PACO%,jk ·MVAratingjk (2.2)
The previous expression is based on the approximation that the line MVA rating is a MW limit.
This is commonly done in linear methods and in the DC power �ow.
The PACO expressed in MW is a better index compared to the percentage quantity because it
retains information about the line MVA �ow, e. g. a 20% overload in a 132 kV line should have
lower severity than a 20% overload in a 400 kV line.
The PACO index has the following properties that make it useful for assessing the �weakness� of a
branch:
� if a branch is not overloaded for any contingencies (belonging to the contingency list), then
its PACO will be equal to zero;
� if a branch is either heavily overloaded for a few contingencies or lightly overloaded for lots
of contingencies, its PACO will be high;
� if a branch is heavily overloaded for numerous contingencies, its PACO will be very high;
� the higher the PACO, the �weaker� the branch.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 18
One measure of system security is the amount of thermal overloading that occurs during a set of
simulated contingencies or forced outages. The level of contingent overloading may be expressed as
the sum of MW overloads in all monitored transmission elements and for all simulated contingen-
cies. Since the PACO can be computed for every branch, a system aggregate contingency overload
can be calculated as:
OverloadSY S =∑jk
PACO,jk jk ∈ Overloaded branches (2.3)
For a given line jk and a given contingency c the contribution to the OverloadSY S would be the
amount of MW that the real power �ow on line jk exceeds its rating, when the contingency c
occurs. If the line operates within its limits for all contingencies, then its contribution to the
OverloadSY S will be equal to zero.
Although the OverloadSY S provides a metric of the security of the overall grid, it will tend to be
higher not only for highly stressed systems but also for large systems. In order to make the metric
independent of the network size, it can be divided by the number of branches Nbranches, resulting
in the Thermal Security Index (TSI) of the system:
TSISY S =OverloadSY S
Nbranches(2.4)
Given a contingency set, this metric represents the average MW overload expected in a line in case
of contingency.
2.2.2 Generation expansion and power system security
The continuing growth in demand for electric power, decreased investment in transmission facilities,
and widespread implementation of electricity markets will continue to place increased stress on the
electric transmission network. So, as previously said, there is an increasing need for systematic,
integrated planning processes that, while ensuring energy adequacy, are able to identify the broader
impact of new resources on grid security. These processes would permit utilities to strategically site
power plants based on system security goals, allowing the grid to move toward healthier operating
conditions. The following paragraph will describe a methodology able to capture how generation
impacts system reliability and security, based on a nodal index proposed in literature few years
ago [6].
2.2.2.1 Overload mitigation strategy
The proposed methodology is based on the overload mitigation strategy illustrated in Figure 2.8,
which shows an overloaded line and an injection that helps to mitigate the overload by means of a
counter-�ow. So the goal of strategic generation siting is to determine geographic locations where
new generation would enhance the system security by creating post-contingency counter-�ows that
would mitigate overloads under contingency conditions.
As injections at any place in the system will at least marginally a�ect the �ows everywhere in the
system, the aim is to look for a mechanism to simultaneously maximize the contingency overload
mitigation in multiple congested elements and minimize new overloads in the system.
Since the new generation will be connected to a bus, it is necessary to relate information regarding
weak elements (the problem) to bus injections (the solution). This can be accomplished by calcu-
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 19
Figure 2.8: Overload mitigation strategy using generation
lating the Injection Shift Distribution Factors1 (ISDFs). This sensitivity is de�ned as the change
in a branch MW �ow with respect to the change in a bus MW injection, assuming a �xed sink for
a transfer whose source is the proposed generation:
ISDF bus ibranch jk =
∆MWFlowbranch jk
∆MWInjectionbus i(2.5)
Denoting by n the number of buses in the system, it is clear that for each weak element an n-size
array of sensitivities can be determined. So the ISDFs with respect to multiple weak elements
form a matrix in the bus and weak element dimensions. The highest negative ISDF in this array
corresponds to the bus where a power injection results in the highest reduction of the normal
operation �ow on that element.
Electricity system policy though does not de�ne security based on normal operation �ows, but
rather on contingency conditions (i. e. following the outage of a given line st). Thus post-contingency
ISDFs are required:
ISDF bus ibranch jk,contingency c =
∆PostContMWFlowbranch jk,cont c
∆MWInjectionbus i(2.6)
Note that when contingency conditions are studied, there will be one ISDF for each source bus,
to mitigate each weak branch, under each contingency. The post-contingency sensitivities form a
large three-dimensional object in the bus, weak branch, and contingency dimensions, and they can
be used to design strategies to mitigate contingency overloads.
Since a single locational value is needed for each bus, both the contingency and weak branch
dimensions need to be collapsed to the bus dimension. As a power injection will simultaneously
a�ect several branches under several contingency conditions, it is possible to de�ne an Equivalent
Transmission Loading Relief (ETLR) sensitivity, which corresponds to the impact of injecting
power at a given bus on all branches and under all contingency conditions. The ETLR is simply
the sum of the ISDFs computed for a bus:
ETLRbus i =∑jk
∑c
ISDFbus i,branch jk,cont c (2.7)
1In [6] this sensitivity is called TLR (Transmission Loading Relief).
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 20
where jk ∈ Overloaded branches and c ∈ Contingency List.Although the ETLR represents the simultaneous e�ect of injection, it does not take into account
the severity of the overloads, something that is fundamental for strategic overload mitigation. In
order to consider this important aspect, a weighting mechanism is introduced. So the severity of
the overloads can be incorporated by computing a WTLR (Weighted Transmission Loading Relief)
sensitivity:
WTLRi =Nviol
OverloadSY S
∑jk
ISDF ijkPCO,jk +
∑jk
∑st
ISDF ijk(st)P
stCO,jk
(2.8)
where:
� Nviol is the number of overloads;
� OverloadSY S is the system overload;
� PCO,jk, P stCO,jk are the overloads on branch jk in intact system conditions and following the
outage of the line st respectively;
� ISDF ijk, ISDF
ijk(st) are the Injection Shift Distribution Factors of branch jk with respect
to the injection at bus i in intact system conditions and following the outage of the line st
respectively.
The WTLR represents the locational impact of generation on network security: it corresponds to
the total expected MW contingency overload reduction (in all branches and under all contingencies)
if 1 MW is injected at that particular bus. More precisely, the WTLR of a bus is an indicator which
approximates the total change in the system overload (OverloadSY S) that would be obtained with
a 1 MW injection at that particular bus.
The WTLR sensitivity represents the locational value of the security bene�t obtained with new
generation and it is measured in OverloadSY S per megawatt installed.
Thus the approach allows comparing the reduction of the overall system overload for generation
located at di�erent WTLR locations and it allows ranking the sites where new generation injections
would enhance system security.
Note that the highest negative WTLRs are located at the receiving end of the overloaded elements.
Clearly, injections at these buses will produce counter-�ows in the overloaded elements, which will
reduce their PACO. On the other hand, injections at buses with positive WTLR will produce power
�ows that would worsen the overloads. So if overload mitigation is the goal, then new generation
should be installed at buses that have the lowest WTLR.
2.2.3 Transmission planning and power system security
Maintaining power system security is one of the major challenges that TSOs (Transmission System
Operators) have to face today. In fast moving and de-regulated electricity markets, transmission
companies across the globe often have a dual and con�icting responsibility for maintaining system
security and for achieving high transmission performance levels. So the objective in market-based
transmission planning is to maintain system security within an acceptable level while maximizing
the social welfare (or minimizing the investment and operation costs).
According to the Ministerial Decree D.M. April 4, 2005 [7], the Italian TSO has to de�ne the
development plan of the transmission network to achieve the following objectives:
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 21
� to ensure the security of electricity supply and to meet the demand growth;
� to upgrade the interconnection capacity with neighbouring countries;
� to meet the grid connection requests by the entitled parties;
� to minimize the risk of network congestions;
� to guarantee a secure operation of the network.
According to the Italian grid code [8], the planning process starts from collecting, sorting, and
analysing the data about:
� load prediction;
� new power plants' size and location;
� national power balance and electric power exchanges with foreign countries.
With reference to the projection horizon, some probable scenarios are de�ned and on the basis of
them some reference cases are built and analysed to detect possible critical operational situations
and above all to determine the network reinforcements necessary for their enhancement. Then the
TSO carries out a steady-state security analysis applying the N-1 criterion,2 to set up the initial
development programme of the transmission network, while meeting the following conditions:
� with reference to some typical operational situations, considering the predictable generation
schedules, the power supply must be guaranteed without any violation of security constraints
(limitations on currents in lines and transformers and on voltage magnitudes in grid nodes)
in normal state, i. e. in intact system conditions;
� the outage of single network equipment must not result in thermal overloading of branches,
deterioration of voltage pro�les below permitted range, loss of load.
Obviously, besides the need to maintain power system security, the TSO also checks the di�erent
development options from a techno-economical viewpoint by comparing the estimated construction
costs with the expected bene�ts in terms of reducing the overall system cost. If that is possible,
such assessment considers the costs due to: network congestions, grid losses, risk of loss of load,
predictable tendency of the electricity market, opportunity to increase the transmission capacity
with neighbouring countries.
2.2.3.1 WTLR and transmission planning
The Weighted Transmission Loading Relief sensitivity is based on the overload mitigation strategy
illustrated in Figure 2.8, which exploits the potential e�ect of strategic generation siting on system
security. Even if this is its original application, the approach can be a useful tool for transmission
planning.
A desirable goal of any network upgrade or reinforcement would be to improve the system security
as measured by OverloadSY S . As well explained before, negative WTLR values correspond to sites
where injections will tend to enhance grid security by reducing OverloadSY S , while locations with
positive WTLRs are �poor� for network security, since they will worsen the contingency overloads.
2The N-1 criterion essentially says that an outage of any grid element shall not result in the overloading andsubsequent failure of other elements in the system.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 22
Figure 2.9: Transmission relief
In particular, considerable changes from positive to negative values reveal the presence of congested
grid elements: the region with negative WTLRs is at the receiving end of an overloaded branch,
whereas locations with positive WTLRs are at the sending end. So information supplied by these
sensitivities can be successfully used to identify the most critical grid elements and sections, that
are to be reinforced.
Besides these fundamental indications, the bus WTLR value can be also applied to each end of a
proposed transmission line to linearly estimate the total expected OverloadSY S change consequent
on the addition of a new branch. To enhance system security, new lines should be added to produce
counter-�ows on the lines and transformers that experience contingency overloads as illustrated in
Figure 2.9.
Assume that the power �ow expected from bus j toward bus k is Pjk. If the system is supposed to
be loss-less and linear within a range de�ned by the incremental �ow on the proposed line, then
adding the proposed line will be equivalent to place a generator at bus j with an output of −Pjk
and a generator at bus k with an output of +Pjk, as illustrated in Figure 2.10.
The bus-based WTLR values may then be applied to estimate the impact of a new transmission
line on system security by calculating the following index:
Pjk (−WTLRj +WTLRk) (2.9)
The expected Pjk can be evaluated by adding the line jk to the system and quantifying Pjk with
a full non-linear power �ow calculation.
The simulations on a test system, which will be presented after the description of the procedure
for WTLR calculation coded in the Matlab programming language, will be also used to validate
the above index and particularly to show that, given a set of new transmission lines, it can supply
helpful information to prioritize grid planning.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 23
Figure 2.10: Network equivalents
2.3 Matlab-coded program for WTLR sensitivity calculation
A procedure has been implemented in the Matlab programming language [9] to calculate WTLR
sensitivities and above all to obtain their graphical representation, that shows the grid areas ade-
quate to the installation of new power plants and those requiring network reinforcements.
The computational procedure operates in the following main steps:
1. N and N-1 security assessment to �nd possible branch overloads and consequently the total
system overload OverloadSY S ;
2. calculation of the Injection Shift Distribution Factors in both pre-contingency and post-
contingency conditions;
3. calculation of Weighted Transmission Loading Relief sensitivities by equation (2.8);
4. graphical representation of WTLR factors.
The original procedure is based on these main assumptions:
� the security assessment is performed by means of AC power �ow calculations according to a
traditional contingency analysis;
� the overloads are determined assuming the approximation that the line MVA rating is a MW
limit;
� the ISDFs are calculated considering a single slack bus, i. e. concentrated slack bus.
2.3.1 Step 1: security analysis
As above said, N and N-1 security assessment is performed by means of a sequence of AC load
�ow calculations. According to a standard contingency analysis, the procedure executes a power
�ow calculation in intact system conditions and for each outage included in the contingency list:
the failure or outage of each element in the contingency list (in our case, the trip of a transmission
line) is simulated in the network model by removing that element.
The procedure calls one of the power �ow solvers that are included in MATPOWER package [10]
and can be accessed via the runpf function, so performing a load �ow calculation in N security
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 24
conditions. More precisely, the procedure exploits the default power �ow solver, which is based on
a standard Newton's method using a full Jacobian, updated at each iteration.3
To carry out the security assessment considering the N-1 criterion and so to simulate a transmission
line outage, it has been necessary to make suitable changes in the original runpf function. The
procedure is also able to simulate the system operation following the outage of a line with two
parallel circuits carried by the same pylon (the so called �N-1.5� security criterion). In these cases
it is possible to consider higher power �ow limits: for instance, the user can choose to put 20% on
all line thermal limits.
After each load �ow, the branch overloads (MW) are calculated as:
Overloadjk = Powerflowjk − Limitjk (2.10)
where:
� Limitjk = MVAratingjk =√
3VnIn in intact system conditions;
� Limitjk = k ·MVAratingjk = k ·√
3VnIn in N-1 security conditions (with k ≥ 1, default:
k = 1.2, which puts 20% on all line thermal limits).
The contingency analysis results are organized by contingency and then saved in a �le: as shown
in Figure 2.11, each row lists the contingency that caused at least one overload, together with the
overloaded branch, the violating �ow and percentage, the overload in MW.
The overloaded branches are also organized according to their criticality measured by their total
overload, i. e. the sum of all overloads on that particular branch. This ranking, which is useful to
identify the weakest grid elements, is then saved in a �le: as illustrated in Figure 2.12, each row
lists the overloaded branch, the number of violations, and the total overload.
2.3.2 Step 2: ISDF calculation
The second main step of the procedure is the calculation of Injection Shift Distribution Factors,
�rst in intact system conditions and then considering those transmission line outages that caused
at least one overload.
The following paragraphs have the aim of explaining how to derive the Injection Shift Distribution
Factors in both N and N-1 security conditions, considering a single slack bus [11, 12].
For the sake of simplicity, the DC approximation of the distribution factors has been adopted in
the procedure for the calculation of WTLR sensitivities.
2.3.2.1 Distribution factor formulation
The basis for the distribution factor formulation begins by considering linear circuits with voltage
and current sources interconnected by impedances [11, 15].
Consider an n-bus plus ground network modeled with the admittance matrix referenced to ground.
For a given schedule of constant power bus loads and slack bus 1, a base case A solution satis�es:
3The ENFORCE_Q_LIMS option is set to 1 (default is 0): then, if any generator reactive power limit is violatedafter running the AC power �ow, the corresponding bus is converted to a PQ bus, with the reactive output set tothe limit, and the case is re-run. The voltage magnitude at the bus will deviate from the speci�ed value in order tosatisfy the reactive power limit.If the generator at the reference bus reaches a reactive power limit and the bus is converted to a PQ bus, the �rst
remaining PV bus will be used as the slack bus for the next iteration. This may result in the real power output atthis generator being slightly o� from the speci�ed values.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 25
Figure 2.11: Example of �le with contingency analysis results
Figure 2.12: Example of �le with overloaded branches' ranking
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 26
IA1...
IAn
=
Y11 . . . Y1n...
...
Yn1 . . . Ynn
V A1
...
V An
(2.11)
with each bus injection current IAi coming from the ground through a path not included in [Y ].
The [Y ] matrix may include any line, transformer, load admittance connected between any two
buses or between a bus and ground. For a generator, this injection current is the generator
current. For a load (not included in [Y ]), this injection current is the negative of the load current.
All quantities are in per unit. For this analysis, let slack bus 1 be an ideal voltage source with
voltage �xed as:
V1 = V 01 (2.12)
Eliminating the slack bus current from the network model gives:IA2...
IAn
=
Y22 . . . Y2n...
...
Yn2 . . . Ynn
V A2
...
V An
+
Y21...
Yn1
V 01 (2.13)
Solving for the case A voltages gives:V A2
...
V An
=
Z22 . . . Z2n
......
Zn2 . . . Znn
IA2 − Y21V 0
1
...
IAn − Yn1V 01
(2.14)
The line currents for case A are:
IAjk =V Aj − V A
k
zjk(2.15)
where zjk is the primitive line jk impedance.
Now consider changes in injection currents from case A to case B. The case B network equations
(for unchanged impedances) are:V B2
...
V Bn
=
Z22 . . . Z2n
......
Zn2 . . . Znn
IB2 − Y21V 0
1
...
IBn − Yn1V 01
(2.16)
The line currents for case B are:
IBjk =V Bj − V B
k
zjk(2.17)
From equations (2.14)-(2.17) the change in voltages and line jk current between cases B and A
are: ∆V2...
∆Vn
=
Z22 . . . Z2n
......
Zn2 . . . Znn
∆I2...
∆In
(2.18)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 27
∆Ijk = IBjk − IAjk =
n∑i=2
[Zji − Zki
zjk
]∆Ii (2.19)
where: ∆Ii = IBi − IAi . In cases where bus j or k equal 1, the entries of [Z] are de�ned to be zero.
This change can be written as:
∆Ijk =
n∑i=2
T ijk∆Ii (2.20)
where
T ijk =
Zji − Zki
zjk(2.21)
is the so called Current Transfer Distribution Factor (CTDF).
When the slack bus is represented as a voltage source with loads and other generation represented
as current sources, the solutions given by equations (2.18) and (2.19) are exact. The solution is
instead approximate when constant power loads or additional voltage controlled buses are present.
In power �ow studies, it is customary to convert these to power distribution factors by considering
loss-less conditions and assuming voltages to be near unity:
ISDF ijk =
Xji −Xki
xjk= −bjk (Xji −Xki) (2.22)
where xjk and bjk are the primitive line jk reactance and susceptance respectively.
Introducing the susceptance matrix [B] of DC load �ow, the Injection Shift Distribution Factor
(ISDF) can be written as:
ISDF ijk = Bjk (Xji −Xki) (2.23)
So the change in line real power �ow in response to real power injection changes can be approxi-
mated as follows:
∆Pjk 'n∑
i=2
ISDF ijk∆Pi (2.24)
Given a network with n buses and L branches, the complete ISDF-matrix Ψ can be obtained by
the following matrix calculation [13, 14], which is implemented in the Matlab-coded procedure:
Ψ = BdAX (2.25)
where:
� Bd ∈ RL×L is the diagonal matrix whose elements are the branch susceptances (branch
susceptance matrix);
� A ∈ RL×(n−1) is the branch to node incidence matrix whose row l (with 1 at column j and −1
at column k) is[
0 · · · 0 1 0 · · · 0 −1 0 · · · 0](reduced incidence matrix);
� X = B−1 ∈ R(n−1)×(n−1) is the reactance matrix, which is the inverse of the susceptance
one (reduced nodal reactance matrix).
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 28
It is clear that the sensitivity matrix Ψ is strictly dependent on the choice of the slack bus (i. e.
DC load �ow reference bus) in the system.
2.3.2.2 Post-contingency distribution factor
For the calculation of the Injection Shift Distribution Factors in post-contingency conditions, it is
necessary to determine the inverse of the new susceptance matrix because of the grid topological
changes as a result of the line outage. To do this in a numerically cheap way, we can apply the
Woodbury Matrix Identity (also called the matrix inversion lemma), which generally says that the
inverse of a rank-k correction of a matrix can be computed by doing a rank-k correction to the
inverse of the original matrix [16].
In the special case where we have to calculate the inverse of a rank-1 correction of a matrix (that is
the case of the calculation of the reactance matrix in post-contingency conditions), we can use the
so-called Sherman-Morrison formula [17], which computes the inverse of the sum of an invertible
matrix M and the dyadic product, uvT , of a column vector u and a row vector v:
M−1NEW =
(M + uvT
)−1= M−1 −M
−1uvTM−1
1 + vTM−1u(2.26)
In our case, the new susceptance matrix BNEW following the line st outage is:
BNEW = B + uvT = B − astbstaTst (2.27)
where ast =[
0 · · ·s1 · · · 0 · · ·
t−1 · · · 0
]T(with 1 at column s and −1 at column t),
u = −ast and vT = bsta
Tst.
The new reactance matrix XNEW can be calculated by the following matrix calculation, which is
implemented in the Matlab-coded procedure:
XNEW = B−1NEW = B−1 +B−1ast
[1− aT
stbstB−1ast
]−1bsta
TstB
−1 (2.28)
Therefore, the generic element of XNEW is:
XNjk = Xjk +
(Xsj −Xtj) (Xsk −Xtk)
βst(2.29)
with
βst =1
bst− (Xss − 2Xst +Xtt) (2.30)
2.3.3 Step 3: WTLR calculation
The contingency analysis and the ISDF calculation provide all the data necessary for the WTLR
computation by using equation (2.8).
The procedure allows the user to select the set of grid buses that will be considered for the
calculation of both ISDFs and WTLRs. For instance, if the analysis regards the Italian transmission
system (380 and 220 kV), the user can choose among three di�erent options: all 380 kV nodes, all
220 kV nodes, or the node set included in a �le by the user, which will be read and loaded by the
procedure. The resulting WTLRs are then saved in a �le, as shown in Figure 2.13.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 29
Figure 2.13: Example of �le with WTLR sensitivities
2.3.4 Step 4: WTLR graphical representation
The last step of the procedure is the graphical representation of WTLRs. A preliminary work is
indispensable: since each WTLR factor refers to a single node, which has its own location in the
grid, it is necessary to load an image �le with the �gure of the network considered in the analysis
(using the imread4 function), to display it in a �gure window (using the image5 function), and
then to select the sequence of points [x, y] in the plane, corresponding to the chosen set of grid
nodes, with the ginput function, that enables the user to select points from the �gure using the
mouse for cursor positioning and returns the coordinates of the pointer's position (when a mouse
button is pressed). To avoid repeating these operations whenever the user is going to apply the
procedure on a particular network, it is better to save the selected coordinates in a MAT-�le and
to load them when necessary.
To obtain the WTLR graphical representation, �rst the procedure has to associate each index
(included in a vector z) to the corresponding node, i. e. to its location in the grid and so to its
coordinates x, y in a two-dimensional Cartesian space.
Since the data are not conveniently spaced evenly on a grid, in fact x and y are unevenly spaced
vectors and are not vertices of a rectangular array, the procedure has to use the meshgrid6 function
to create an evenly spaced grid around the range of the data: this can be considered the X-Y
�interpolation space�. Using the original data and the X-Y �interpolation space�, the griddata7
4A = imread(filename, fmt) reads a grayscale or colour image from the �le speci�ed by the string filename. Ifthe �le is not in the current directory, or in a directory on the Matlab path, it is necessary to specify the fullpathname. The text string fmt speci�es the format of the �le by its standard �le extension. The return value A isan array containing the image data. The class of A depends on the bits-per-sample of the image data, rounded tothe next byte boundary.
5The function image creates an image graphics object by interpreting each element in a matrix as an index intothe �gure's colormap or directly as RGB values, depending on the data speci�ed.
6[X, Y] = meshgrid(x, y) transforms the domain speci�ed by vectors x and y into arrays X and Y , which can beused to evaluate functions of two variables and three-dimensional mesh/surface plots. The rows of the output arrayX are copies of the vector x, while the columns of the output array Y are copies of the vector y.
7Z = griddata(x, y, z, X, Y, method) �ts a surface of the form z = f(x, y) to the data in the (usually) nonuniformlyspaced vectors (x, y, z). It interpolates this surface at the points speci�ed by (X,Y ) to produce Z. The surfacealways passes through the data points. X and Y usually form a uniform grid (as produced by meshgrid). Themethod de�nes the speci�ed interpolation method and so the type of surface �t to the data.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 30
Figure 2.14: Example of contourf result for WTLR graphical representation
function calculates the interpolated Z data. Then, the contourf8 function provides a �lled contour
plot that displays isolines calculated from matrix Z, i. e. from the interpolated WTLR values, and
�lls the areas between the isolines using constant colours (an example is shown in Figure 2.14). To
get the �nal WTLR map as in Figure 2.15, the user has to superimpose the grid image on that
produced by the procedure by means of a suitable graphic software.
2.4 Application of the procedure to the CIGRE 63-bus sys-
tem
The above described procedure is �rst applied to the CIGRE 63-bus system [18].
The objective of the application to a small electric system is to demonstrate the e�ectiveness of
the proposed procedure to choose the adequate generation and transmission investments. The
results are also used to de�ne a metric to classify the transmission reinforcements according to
their positive impact on network security and electricity market e�ciency [19, 20].
The main features of the test system, illustrated in Figure 2.16 are summarized in Appendix A.
2.4.1 Simulation hypotheses
The main hypotheses for the simulations regard the contingency list for N-1 security assessment
and the thermoelectric generation pro�le.
8[C, h] = contourf(X, Y, Z, v) draws a contour plot of matrix Z with contour levels at the values speci�ed in vectorv, using X and Y to determine the x- and y-axis limits. When X and Y are matrices, they must be the same size asZ, in which case they specify a surface. X and Y must be monotonically increasing. The colour of the �lled areasdepends on the current �gure's colormap.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 31
Figure 2.15: Example of WTLR graphical representation
Figure 2.16: CIGRE 63-bus test system
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 32
Table 2.1: Contingency list (CIGRE 63-bus system)
Table 2.2: Thermoelectric generation pro�le (CIGRE 63-bus system)
The set of contingencies includes the outages of every 220 and 150 kV line (Table 2.1); if a line is
made up by more than one circuit, the procedure will simulate the trip of one of them only. In N-1
security conditions the real power limits are increased by 20%. In order to assess the transmission
system adequacy, the thermoelectric generation pro�le considered in the analysis results from a
dispatch procedure which does not take into account any network constraints and so does not
introduce any power adjustments (i. e. re-dispatching actions). In this way the security assessment
is able to identify the most critical operation conditions and the weakest grid elements. Table 2.2
summarizes the thermoelectric generation pro�le.
2.4.2 Base case
Table 2.3 summarizes the security analysis outcomes for the base case described in the previous
paragraph. There are 37 transmission limit violations and the total system overload amounts to
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 33
Table 2.3: Contingency analysis results - Base case
1562.4 MW. The line 1M1-3M1 is the weakest grid element with 31 violations and a total overload
of 1226.6 MW; in particular, it is already overloaded in intact system conditions. This is due to
the real power �ow from the low-cost generators at bus 11R3, owned by a self-producer, to the load
buses in area V, which has not enough generation capacity to meet its local demand and whose
generators at bus 92V3 are the most expensive in the system.
Table 2.4 shows the WTLR indices calculated for all grid buses (except for the slack bus 41M3). The
nodes with the smallest WTLR sensitivities, which are the most adequate to host new generating
capacity according to the index de�nition, are situated in areas V and T; instead, adding new
power plants in area R will result in the largest overload increase. Therefore, importing areas are
the best locations for new generating capacity because a power injection at negative-WTLR bus
is able to produce counter-�ows which relieve overloads (for instance, on the line 1M1-3M1).
Figure 2.17 illustrates the WTLR graphical representation: a green or red area corresponds to
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 34
Table 2.4: WTLR sensitivities - Base case
the lowest or highest indices respectively. Changes from negative to positive values (from green
to yellow/red on the map) reveal the presence of congested elements (for instance, the lines 1M1-
3M1 and 75T2-775T2), so identifying the weakest grid sections or areas where new transmission
facilities should be realized.
2.4.3 WTLR-based generation expansion and network security
Considering the basic concept of the WTLR methodology (i. e. overload mitigation strategy using
generation), the most obvious use is strategic generation siting.
Among the set of negative-WTLR buses, three possible new generation sites are selected:
� node 33V1 (base WTLR = -17.07);
� node 5M1 (base WTLR = -10.89);
� node 66M1 (base WTLR = -4.73).
The aim is to evaluate the bene�ts for power system operation resulting from the new real power
injection at each of the above buses and thus to check the correctness of the information provided
by the WTLR values. The tests are carried out considering one site at a time. For example, a
new generator connected to the node 33V1 is added to the network model, its size is increased by
50 MW at a time until the corresponding WTLR becomes positive, and the total system overload
is calculated in each case. The production cost of the new unit is assumed low enough to allow it
to be fully dispatched.
The variations of the index value at the new generation sites and of the system overload are
displayed in Figures 2.18-2.19 (bus 33V1), 2.20-2.21 (bus 5M1), and 2.22-2.23 (bus 66M1).
The di�erences among the three cases are likely to be due to larger or shorter electrical distance
from the most critical grid element, i. e. the line 1M1-3M1.
The results make it evident that:
� the installation of new generating capacity in a negative-WTLR bus allows the total system
overload to be reduced;
� raising the installed capacity, the WTLR value increases while the system overload decreases;
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 35
Figure 2.17: WTLR graphical representation - Base case
Figure 2.18: Node 33V1 WTLR
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 36
Figure 2.19: System overload - New generator at node 33V1
Figure 2.20: Node 5M1 WTLR
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 37
Figure 2.21: System overload - New generator at node 5M1
Figure 2.22: Node 66M1 WTLR
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 38
Figure 2.23: System overload - New generator at node 66M1
� at a certain value of the new generating capacity, the WTLR becomes positive and corre-
spondingly the total system overload starts to increase again;
� the smaller the WTLR in the base case, the quicklier the total system overload decreases by
raising the new generating capacity;
� on one hand, the nodes with the smallest WTLR can be considered the most adequate sites
for installing new units resulting in an e�ective system security enhancement, on the other
hand, these buses might be able to host a smaller generating capacity.
2.4.4 WTLR-based grid development
According to what said for the base case simulation and for the possible use of the information
supplied by the WTLR sensitivities, the realization of a new line connecting the exporting areas
R and F to the importing area V can produce a substantial congestion alleviation, so resulting in
global system security enhancement.
The most obvious choice is to double the connection between the nodes 1M1 and 3M1, since the
existing line is the most critical grid element, as shown by the contingency analysis results in
Table 2.3. The other network reinforcements are selected according to the following criterion:
� from bus → negative-WTLR bus;
� to bus → positive-WTLR bus.
The new line will be an alternative path for power transmission from the exporting areas (yellow-red
colour/positive WTLR) to the importing ones (green colour/negative WTLR).
The set of nodes selected to de�ne the grid reinforcements includes:
� from bus: 9V1, 5M1 (WTLR = -12.24, -10.89 respectively);
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 39
Figure 2.24: Network reinforcements for CIGRE 63-bus system
� to bus: 1M1, 2M1, 8M1 (WTLR = +7.67, +3.63, +3.23 respectively).
So the set of network reinforcements considered in the study comprises the following transmission
lines: 1M1-3M1, 1M1-9V1, 1M1-5M1, 2M1-9V1, 2M1-5M1, 8M1-9V1, and 8M1-5M1 (Figure 2.24).
To make the comparison easier, all new lines are assumed to have the same features of the line
1M1-3M1.
2.4.4.1 WTLR procedure results
The realization of a new line is simulated in the network model by adding that element. The
procedure is then applied to the new grid model in order to calculate the new total system overload
and the new WTLR values.
The security assessment outcomes concerning all test cases are summarized in Table 2.5, which
shows the change in the total system overload and in the number of congestions consequent on the
realization of each of the new transmission lines.
The simulations demonstrate the correctness of the information supplied by the WTLR indices:
adding a new line from a green-coloured area to a yellow/red-coloured one can contribute to
congestion alleviation. All the new lines considered in the analysis have in fact a positive e�ect on
system security.
As shown in Figure 2.25, the lines 1M1-5M1 and 2M1-5M1 are the most e�ective in terms of
network congestion alleviation. They both produce the same redistribution of power �ows on grid
branches and so the security analysis provides the same outcomes (Table 2.6). There are only the
three violations that are caused by the export from area R (1M1-1R1) and by the import into area
T (75T2-775T2, 65T2-665T2) respectively, and that are not a�ected by the network reinforcement.
All the WTLR sensitivities (Table 2.7) are equal to zero except for the nodes of area R, which are
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 40
Figure 2.25: Total system overload for all test cases (decreasing order)
Table 2.5: Security analysis results for all test cases
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 41
Table 2.6: Security analysis results - New line 1M1-5M1 or 2M1-5M1
Table 2.7: WTLR sensitivities - New line 1M1-5M1 or 2M1-5M1
still positive but lower than in the base case, and for some nodes in area T, that are still negative
but higher than in the base case (lower absolute value).
2.4.4.2 A WTLR-based metric for transmission planning
The simulation results described in the previous paragraph have highlighted that:
� a network reinforcement, if properly chosen, can reduce the occurrence and/or the size of
branch overloads;
� consequently, the WTLR sensitivities vary according to the security analysis outcomes, re-
sulting in a more or less considerable decrease in their absolute values.
The second consideration suggests the possibility of de�ning a global index or a metric which can be
used to classify the network reinforcements based on their impact on overall system security. This
metric is the WTLR algebraic sum. The bar charts of Figures 2.25 and 2.26 show an interesting
analogy: the more the total system overload decreases, the more the metric diminishes.
So the global index calculation con�rms that the two lines 1M1-5M1 and 2M1-5M1 are the best
grid reinforcements in terms of security enhancement. On the basis of that, the WTLR algebraic
sum can be considered a measure of system security, as well as the total system overload, i. e.
the amount of thermal overloading that occurs during a set of simulated contingencies or forced
outages.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 42
Figure 2.26: WTLR algebraic sum
2.4.4.3 Validation of the WTLR-based metric
In competitive electricity markets, transmission capacity expansion is necessary to increase Social
Welfare and market e�ciency, besides ensuring a secure, reliable, and uninterrupted electricity
supply.
To validate the WTLR-based metric de�ned in the previous paragraph and so to demonstrate that
the new lines 1M1-5M1 and 2M1-5M1 are the most e�ective also in terms of market e�ciency
improvement, an Optimal Power Flow procedure is applied to each test case and two standard
economic indicators (Social Welfare and Congestion Revenue) are calculated as follows:
� Producer revenue (Pgen i is the production of generator i and pgen i is the nodal marginal
price at the bus to which the generator i is connected):
Revenuegen i = Rgen i = pgen i · Pgen i (2.31)
� Generation cost (according to the hourly cost function of generator i):
Costgen i = Cgen i = C0i + C1iPgen i + C2iP2gen i (2.32)
� Producer surplus:
Πtot =∑i
(Rgen i − Cgen i) (2.33)
� Consumer surplus9 (dj and pj are the load and the nodal marginal price at bus j respectively):
Sc =∑j
(pref − pj) · dj (2.34)
9The demand is supposed inelastic and so it is necessary to �x a reference price for the consumers (pref= 150¿/MWh).
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 43
Table 2.8: Economic indicators for all test cases (¿/h)
� Social Welfare:
W = Πtot + Sc (2.35)
� Congestion Revenue:
CR =∑j
pj · dj −∑i
Rgen i (2.36)
As shown in Table 2.8, all the new lines produce a Social Welfare increase and a consequent Conges-
tion Revenue reduction compared with the base case. More precisely, four network reinforcements,
including the lines 1M1-5M1 and 2M1-5M1, produce practically the same increase in Social Welfare
(about 20200 ¿/h). It follows from this that the grid reinforcements with the largest impact on
network congestion mitigation are also among the most e�ective ones from the point of view of the
electricity market functioning (Figure 2.27).
2.4.4.4 An index to prioritize transmission planning
The preceding paragraphs have described the de�nition and validation of a WTLR-based metric
which could be used to classify network reinforcements on the basis of their impact on both system
security and electricity market e�ciency. Its calculation follows the application of the WTLR
procedure to the new test case, resulting from the addition of the new line to the base case: so
this process has to be repeated for all candidate lines. Compared to this, the methodology brie�y
outlined in subsection 2.2.3 has some advantages: in particular, the index calculation needs only
the WTLR values corresponding to the base case and the estimate of the expected power �ow
on the new line in intact system conditions (see equation (2.9)). The method, which has been
automated and implemented in the Matlab programming language, can be summarized as follows:
� de�ne a list of potential transmission lines;
� perform a standard contingency analysis to calculate the total system overload with reference
to the existing transmission network (base case);
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 44
Figure 2.27: Social Welfare for all test cases
� calculate the WTLR sensitivities (base case);
� quantify the expected real power �ow on the new lines in intact system conditions;
� calculate the indicator with reference to each of the new lines.
The main problem is the evaluation of the power �ow on the new lines. It can be solved by adding
the new line jk to the system and then quantifying Pjk with a full non-linear power �ow simulation.
This process has to be performed for each line.
The list of candidate lines considered for the method validation includes: 1M1-5M1, 1M1-9V1,
2M1-5M1, 2M1-9V1, 8M1-5M1, and 8M1-9V1. Table 2.9 summarizes the results: from and to bus
WTLRs, real power �ow, and index value. According to the index de�nition, a minus sign means
a positive e�ect on system security, i. e. a decrease in total system overload: the lowest values
correspond to the best network reinforcements in terms of security enhancement. Apart from a
few exceptions, the outcomes con�rm the priority order already made clear by applying the WTLR
procedure to calculate the system overload and the WTLR-based metric. The discrepancies, above
all that regarding the lines 2M1-9V1 and 8M1-5M1, are probably due to the approximations (loss-
less system and linearity) considered in the index de�nition.
Therefore, the validation rati�es that the indicator can give a good indication of the impact of a
potential transmission line on total system overload and consequently on overall system security.
Thanks to its main features, especially the easiness of its calculation, it could be adopted to evaluate
new transmission connections and to help the selection of those that provide the most e�ective
improvements to overall system security.
This WTLR-based methodology enables an easily automated process for comparing the e�ects of
new lines on total system overload and above all it can estimate which new connection will have the
greatest marginal bene�t to system security. Thus it has proved to be a fast-screening tool to allow
a transmission system planner to evaluate a given set of alternatives. This fact demonstrates the
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 45
Table 2.9: Index validation
importance of the approach. The ability to screen a certain number of alternatives to determine a
subset of promising ones for further evaluation (e. g. economic analysis) can be very important.
2.5 Changes in the original Matlab-coded procedure
This section will describe the modi�cations made in the original Matlab-coded program for the cal-
culation of WTLRs by introducing the Line Outage Distribution Factors, with the aim of reducing
the number of mathematical operations to be performed and consequently the total computational
time, and by adopting the distributed slack bus in order to remove the ISDF dependence on the
choice of the slack bus.
2.5.1 Introduction of the Line Outage Distribution Factors
As described in section 2.3, given a certain scenario, the basis for the WTLR calculation is a
standard contingency analysis carried out by a sequence of AC load �ow calculations to �nd possible
branch overloads. This step is quite time-consuming, especially for large networks, because the
Matlab-coded procedure performs a power �ow in intact system conditions and for each outage
included in the contingency list. In order to improve this process and above all to reduce the
total computational time, the original procedure is modi�ed in the following way: it performs an
AC load �ow to evaluate the real power �ows in N security conditions, while the real power �ows
following a line outage are determined by means of the so called Line Outage Distribution Factors
(LODFs).
2.5.1.1 LODF formulation
The formulation of the Line Outage Distribution Factors can be derived examining how the outage
impacts may be simulated by net injection and withdrawal changes [21].
First of all, it is necessary to de�ne the so called Power Transfer Distribution Factor (PTDF),
which measures the sensitivity of line MW �ows to 1 MW transfer. So the impact of a ∆tst-
MW transaction from node s to node t on the real power �ow Pjk on the line jk is ∆Pjk and is
determined by:
∆Pjk = PTDF stjk∆tst (2.37)
where the PTDF is de�ned as:
PTDF stjk = ISDF s
jk − ISDF tjk (2.38)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 46
Figure 2.28: Impact of the transaction ∆tst
The line st outage changes the real power �ow in the post-outage network on each line connected
to s by the fraction of Pst. This impact can be simulated by introducing a transaction ∆tst in the
pre-outage network (Figure 2.28). The injection ∆tst adds a change PTDF stst ∆tst on the line st
�ow and a net �ow change of (1− PTDF stst ) ∆tst on all the other lines but st that are connected
to node s. By selecting ∆tst to satisfy:
(1− PTDF st
st
)∆tst = Pst (2.39)
the transaction ∆tst changes the �ow Pjk, jk 6= st, by:
∆Pjk = PTDF stjk∆tst =
PTDF stjk
1− PTDF stst
Pst (2.40)
The term
PTDF stjk
1− PTDF stst
(2.41)
is the Line Outage Distribution Factor of the line jk with respect to the line st outage.
Consequently, the real power �ow on the line jk following the line st outage can be approximated
as:
Pjk(st) ≈ Pjk + LODF stjkPst (2.42)
2.5.1.2 Application to the CIGRE 63-bus system
According to what said in the previous paragraph, after carrying out a load �ow in intact system
conditions and after computing the ISDFs with reference to the original network, the procedure
determines the real power �ows on grid branches in N-1 security conditions by means of the
LODFs. Instead of a sequence of AC load �ow calculations, the procedure thus performs this
matrix computation only:P (1)
...
P (Nout)
=
P...
P
+
LODF (1)
...
LODF (Nout)
. ∗ [ P (out) · · · P (out)]
(2.43)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 47
where:
� all the matrices ∈ RNout×Nb (Nout is the number of line outages in the contingency list and
Nb is the number of grid branches);
� .∗ is the Matlab arraywise multiplication;10
� the n-th row P (n) of the �rst matrix is the vector of the real power �ows following the line
outage n;
� all rows of the second matrix are equal to the vector P of the real power �ows in intact
system conditions;
� the n-th row LODF (n) of the third matrix is the vector of LODFs with respect to the line
outage n: in particular, the element corresponding to the line to be outaged, which cannot
be calculated by equation (2.40), is set at -1 so zeroing the post-contingency power �ow on
that particular line;
� all columns in the fourth matrix are equal to the vector P (out) =[P(1) · · · P(Nout)
]Tof
the real power �ows on the lines included in the contingency list in N security conditions.
The new procedure is applied to the base case of the CIGRE 63-bus system and the new outcomes
are compared with the original ones. The approximations used in the derivation of the Line Outage
Distribution Factors11 introduce an error in the calculation of Pjk(st): the absolute value of the
relative error is computed as: ∣∣∣∣∣Pjk(st) − Exact Pjk(st)
Exact Pjk(st)
∣∣∣∣∣ (2.44)
where Exact Pjk(st) is the real power �ow determined using the AC load �ow (i. e. the exact
method) and Pjk(st) is the result obtained using the distribution factors.
To investigate the quality and robustness of the distribution factors for congestion modelling, the
absolute values of the errors (calculated for every real power �ow) are collected and then their
density function is constructed. The plot in Figure 2.29 shows that the frequency for the relative
errors is high for very small values but rather low for large errors. The corresponding cumulative
distribution function is displayed in Figure 2.30: the plot indicates that the relative errors are
smaller than 2% for more than 90% of the cases, while they are above 1% in about 20% of the
cases.
We, therefore, conclude that the linearization approximation in the derivation of the distribution
factors introduces these errors, but at least for a test system as the CIGRE 63-bus one its e�ect
on the calculation of the real power �ows in N-1 security conditions is very small.
The contingency analysis results obtained using the approximate method are summarized in Ta-
ble 2.10: each row lists the contingency (line st outage), together with the overloaded branch jk,
the LODF, the real power �ows on the lines jk and st in intact system conditions, the post-outage
line jk power �ow,and the relative error (in per cent) on Pjk(st). So, regarding the overloaded
branches, the highest absolute value of the relative error on Pjk(st) amounts to about 3.1%. Ob-
viously, the approximations also a�ect the overloads detected by the contingency analysis: for the
10A. ∗B is the element-by-element product of the arrays A and B.11They are the assumptions used in the derivation of DC power �ow models.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 48
Figure 2.29: Density function of the relative errors in line �ow approximations
Figure 2.30: Cumulative distribution function of errors in line �ow approximations
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 49
Table 2.10: Contingency analysis results by using LODFs
most part, the �LODF overload� is smaller than the �exact� one. So the total system overload,
which amounts to 1521 MW, is lower than that computed by adopting the original procedure
(1562.4 MW).
In the light of these di�erences, though small, it is interesting to estimate the impact that the
approximate method for congestion modelling has on WTLR sensitivities. Figure 2.31 illustrates
the relative errors on WTLRs. It is clear that the error is small for most nodes (lower than 2%),
except for the buses of area T (3÷10%). The absolute errors are however not considerable and so
the qualitative indications provided by WTLRs are still good. We can conclude that, in spite of
the approximations in the derivation of LODFs, the outcomes of the new procedure are acceptable.
The simulations also demonstrate that introducing the distribution factors to detect possible branch
overloads allows the total computational time to be reduced notably. This improvement to the
original procedure allows simulating the line outages by changing the network topology and carrying
out a sequence of AC power �ow calculations to be avoided, since it needs the computation of
LODFs and the matrix calculation in equation (2.43) only.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 50
Figure 2.31: Relative error on WTLR sensitivities using LODFs
2.5.1.3 Using the base ISDFs to compute WTLR sensitivities
To further speed up the Matlab-coded program, another simpli�cation can be introduced: using the
base Injection Shift Distribution Factors, calculated in intact system conditions, to determine the
WTLR sensitivities. In this way, the procedure has not to compute the post-contingency reduced
reactance matrix XNEW , given by equation (2.28), and then the new complete ISDF-matrix Ψ
for each outage.
We �rst investigate the ISDF errors introduced by the changes in the network topology. For each
line outage the original procedure calculates the ISDF for every node in the system. We compute
the relative error for each ISDF by comparing it to the corresponding reference value determined
in N security conditions: ∣∣∣∣∣ISDF post − ISDF base
ISDF base
∣∣∣∣∣ (2.45)
We collect the errors and construct the density function shown in Figure 2.32. This plot demon-
strates that, although the topology changes in the network may result in major impacts on the
value of some particular ISDFs, the fraction of ISDFs which are signi�cantly impacted is relatively
small. The scatter plot in Figure 2.33 shows the size of relative error as a function of the corre-
sponding ISDF magnitude: it reinforces the notion that large errors are associated primarily with
small magnitude ISDFs. These results suggest using the base ISDFs to calculate WTLR sensi-
tivities, since the errors on the distribution factors are relatively small and so this approximation
should not a�ect the resulting indices very much.
The chart in Figure 2.34 displays the WTLRs computed: 1) by applying the original procedure, 2)
by using the base ISDFs, and 3) by using both the LODFs and the base ISDFs. The simulations
indicate that the WTLR errors stay in an acceptable range.
To conclude, the results highlight that the simpli�cations (i. e. using the LODFs for the contingency
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 51
Figure 2.32: ISDF error density function
analysis and the base ISDFs for calculating the WTLRs) do not compromise the quality of the
information supplied by WTLR sensitivities. Furthermore, they allow performing an AC load �ow
calculation and determining the modi�ed ISDF matrix for each outage to be avoided, so resulting
in a notable reduction of the total computational time.
2.5.2 Adoption of the distributed slack bus
Besides being quite time-consuming, especially for large networks, which may not be a real problem
since the WTLRs are useful indices for power system planning, the original procedure has an
e�ective limit: it considers a single slack bus, i. e. concentrated slack bus, in the power �ow
calculations and above all in the ISDF computation.
2.5.2.1 Impact of the choice of the slack bus
We �rst investigate the impact of the selection of the slack bus on the power �ow calculations
and especially on the branch overloads detected by the contingency analysis. The simulations are
performed by applying the original procedure which, as explained in section 2.3, uses a single slack
bus load �ow analysis. Table 2.11 shows the total overload system with reference to �ve di�erent
slack buses: 41M3 (the original one), 11R3, 43F3, 61T3, and 92V3. More precisely, the congestions
are the same for all test cases and there are not big di�erences in the size of the overloads: so the
impact of the system overload errors on WTLR values should be quite small.
As explained in subsection 2.3.2, the ISDF matrix is instead strictly dependent on the selection
of the slack bus in the system. So now we look into the e�ects of changing the slack bus on the
determination of the distribution factors and consequently of the WTLR sensitivities.
Just to investigate this aspect, the choice of the �ve slack buses considered in the simulations is
made in such a way that each of the �ve areas of the CIGRE 63-bus system, one at a time, is
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 52
Figure 2.33: Scatter plot of the relative errors as a function of the ISDF magnitudes
Figure 2.34: E�ect of the approximations on WTLR sensitivities
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 53
Table 2.11: Contingency analysis results with di�erent slack buses
the �sink area� (41M3-area M; 11R3-area R; 43F3-area F; 61T3-area T; 92V3-area V). Figure 2.35
clearly shows that the WTLRs depend strongly on where the slack bus is in the grid. In particular,
the arithmetic mean of the WTLR values is very di�erent in the �ve test cases:
� �41M3 case�: WTLR arithmetic mean = -3.57;
� �11R3 case�: WTLR arithmetic mean = -14.68;
� �43F3 case�: WTLR arithmetic mean = -3.49;
� �61T3 case�: WTLR arithmetic mean = +1.21;
� �92V3 case�: WTLR arithmetic mean = +8.73.
In the original network the slack bus is 41M3, which has been selected because of its baricentric
position in the system. Besides demonstrating the e�ectiveness of the WTLR methodology, the
results described in section 2.4 highlight the quality of the information supplied by the WTLRs
and so, on the light of the above considerations, the correcteness of selecting the node 41M3 as the
slack bus.
The diagram in Figure 2.35 shows that the �43F3 case� is the only similar to the base one and we
thus conclude that the two nodes 41M3 and 43F3 act in like manner as slack bus: they are in fact
�electrically� close, since the high voltage generator bars (44F1 and 4M1) are connected by a double
circuit line. All the WTLRs related to the �11R3 case� are negative because an injection at any
node in the system, which is withdrawn from the slack bus in area R, would produce a counter-�ow
on the lines 1M1-3M1 and 1R1-1M1 so resulting in a large total system overload decrease. On the
contrary, nearly all the WTLRs corresponding to the �92V3 case� are positive: the reasons are just
the opposite of the previous case.
2.5.2.2 Distributed slack bus
Even though the simulations described in the previous paragraph show that the results of the
contingency analysis are little a�ected by the selection of the slack bus, the distributed slack
bus concept is introduced in the power �ow model used by the Matlab-coded procedure. The
traditional Newton-Raphson formulation of the load �ow problem is properly modi�ed introducing
the so called participation factors in order to distribute the real power mismatch due to uncertain
system losses to a particular set of generation units. The complete treatment of this subject is in
Appendix C.
Obviously, the participating sources, chosen to act as the slack bus, are the generators connected
to the �ve nodes considered in the previous paragraph, namely: 41M3, 11R3, 43F3, 61T3, and
92V3. The participation factors ρs are calculated as follows (Table 2.27):
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 54
Figure 2.35: WTLR values with di�erent slack buses
Table 2.12: Participation factors
ρs =Pmax s∑
s∈DsPmax s
(2.46)
where Ds is the set of generation units that function as the slack bus and Pmax s is the maximum
real power by generation unit s.
The contingency analysis results are summarized in Table 2.13. It is clear that removing the
concentrated burden of the slack bus does not cause remarkable changes with respect to the �only
one slack bus� test cases. The outcomes demonstrate that, in case of a single slack bus, selecting
the node 41M3 is correct for the load �ow analysis: the security assessment results in Tables 2.3
and 2.13 are practically the same.
Now we investigate the e�ect of assuming the distributed slack bus on the distribution factors and
consequently on the WTLR values.
We de�ne the Distributed Slack Injection Shift Distribution Factor (DSISDF) as the change in
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 55
Table 2.13: Contingency analysis results using the distributed slack bus power �ow
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 56
Figure 2.36: Cumulative distribution function of |DSISDF − ISDF |
a line real power �ow in response to 1 MW injection at a particular bus and a corresponding
withdrawal at the distributed slack buses assuming participation factor control. The DSISDF
mathematical formulation12 is [22]:
DSISDF ijk = −bjk (Xji −Xki) + bjk
∑s∈Ds
ρs (Xjs −Xks) (2.47)
To evaluate the impact of adopting the distributed slack bus on the distribution factors, we compute
the absolute error for each DSISDF by comparing it to the corresponding reference value (ISDF)
determined by using a single slack bus model:
|DSISDF − ISDF | (2.48)
The cumulative distribution function is displayed in Figure 2.36: the plot indicates that the absolute
errors are smaller than 0.06 for more than 90% of the cases. Since by de�nition the distribution
factors may be at most equal to unity, these di�erences might be even non-negligible.
The WTLR sensitivities are now calculated as follows:
WTLRi =Nviol
(∑jkDSISDF
ijkPCO,jk +
∑jk
∑stDSISDF
ijk(st)P
stCO,jk
)OverloadSY S
(2.49)
Figure 2.37 shows the indices calculated by equation (2.8), i. e. considering a single slack bus
(41M3), and by equation (2.49), i. e. adopting the distributed slack bus, respectively. It is clear
that the di�erences between the ISDFs and the DSISDFs a�ect the WTLR sensitivities which are
in general smaller in case of removing the concentrated burden of the slack bus. However, from a
12The DSISDF formulation is obtained considering the assumptions used in the derivation of DC power �owmodels.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 57
Figure 2.37: Impact of adopting a distributed slack bus model on WTLRs
qualitative viewpoint there are not substantial changes.
We can conclude that in any case the most correct choice is to assume a distributed slack bus
model, so making the ISDFs and the WTLRs completely indipendent of the selection of the slack
bus. But the simulations highlight that the results can be little a�ected by the �only one slack
bus� assumption on condition that the slack bus is suitably chosen.
2.6 Tests on the Italian EHV system
To assess the performances of the WTLR approach and of the Matlab-coded program on large
systems, some tests are carried out on detailed models of the Italian EHV network (380 kV and
220 kV). This section will �rst investigate the impact of assuming the approximation that the line
MVA rating is a MW limit in determining the branch overloads. Then the simulations will show
that the WTLR methodology can be used with di�erent purposes for power system planning.
2.6.1 The MVA rating approximation
As described in section 2.3, the original methodology assumes the approximation that the line
MVA rating is a MW limit and so it ignores both the actual voltage magnitude and the power
factor cosϕ. We now investigate the e�ect of this assumption on security assessment results and
on WTLR sensitivities.
The procedure is applied to the Italian EHV electric system with reference to a summer peak load
condition at the projection horizon of the year 2013. Such a kind of scenario is chosen since the line
current limits allowed in summer are lower than in winter and so it may represent a very stressed
operation condition for the Italian network. The nodal loads, the available power plants, and the
amount of the electricity import refer to what published by the Italian TSO in its development
plan [23] for the projection horizon considered in the study.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 58
Table 2.14: Contingency analysis results (original procedure)
The main hypotheses assumed in the analysis are:
� the power productions of the thermoelectric plants refer to an unconstrained clearing market
point: in other words, the schedule is the result of a λ-dispatching procedure that takes into
account the economic merit order only, while ignoring any transmission system constraint.
As result of the unconstrained market, the Italian transmission system may be harmfully
stressed in peak load conditions, since the main power plants are not always close to the load
areas;
� the N-1 security assessment is carried out including in the contingency list the outages of all
380 and 220 kV lines;
� unlike what we previously assumed for the CIGRE 63-bus system tests, the power �ow limits
considered in N-1 security conditions are not increased by 20% of their rating; so in both N
and in N-1 security conditions they are calculated as:13
Limitjk = MVAratingjk =√
3VnIn (2.50)
2.6.1.1 Original procedure results
The contingency analysis performed by the original Matlab-coded program gives the results sum-
marized in Table 2.14. The Italian 380 kV network at the year 2013, according to the grid devel-
opment plan, is represented in Figure 2.38, which helps us to locate the geographical position of
the outaged and overloaded lines. Some 380 kV bus WTLRs are shown in Table 2.15.
2.6.1.2 Check by a standard steady-state security assessment tool
To control the correctness of the results obtained by assuming the MVA rating approximation,
a standard steady-state security assessment tool is applied to the Italian test case. This tool,
which performs a load �ow calculation for each outage in the contingency list, determines the line
currents and compares them to the corresponding current limits so detecting the actual overloads.
The outcomes are summarized in Table 2.16, which clearly shows that assuming the MVA rating
approximation introduces some errors in the contingency analysis results. All the power �ows ex-
pressed in per cent of the corresponding limits in Table 2.14 are higher than the per cent currents
13The coe�cient k, which allows the line thermal limits to be increased in N-1 security conditions, is set to unity.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 59
Figure 2.38: Outaged and overloaded 380 kV lines
Table 2.15: WTLR sensitivities (original procedure)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 60
Table 2.16: Check by a standard steady-state security assessment tool
Table 2.17: Contingency analysis results (considering the actual voltage magnitudes)
in Table 2.16. Moreover, six violations detected by the original procedure are not con�rmed by
the standard security assessment tool: actually the outage of the 380 kV lines Ferrara Focomorto-
Ferrara Nord, Lonato-Nogarole Rocca, Sermide St.-Crevalcore, Valmontone-Presenzano, and Avel-
lino Nord-Bisaccia (one at a time) do not cause any network congestions, while the outage of the
380 kV line Ariano Irpino-Benevento overloads the 380 kV line Gissi St.-Villanova only.
2.6.1.3 Considering the actual voltage magnitudes
On the basis of the results described in the preceding paragraph, it is appropriate to modify the
original methodology used to calculate the branch overloads in order to take into account the actual
voltage magnitudes instead of their rated values. The power �ow limits are now computed as:
Limitjk =√
3VjIn (2.51)
where it is assumed that the power �ow is from bus j to bus k. The new contingency analysis
outcomes are summarized in Table 2.17: the new method allows only the e�ective overloads to be
detected, even if the per cent power �ows are little smaller than the actual ones.
2.6.1.4 Considering the actual power �ow limits
As well as the bus voltage magnitudes, the load �ow calculations by using the MATPOWER
package allow us to determine the power factors cosϕ and so the actual power �ow limits on grid
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 61
Table 2.18: Contingency analysis results (considering the actual power �ow limits)
Figure 2.39: Impact of the MVA rating approximation on WTLRs
branches. So we can compute the e�ective per cent power �ows and the e�ective MW overloads
(Table 2.18).
The diagram in Figure 2.39 shows the impact of the approximations adopted to calculate the
branch overloads on WTLR sensitivities. It clearly demonstrates that considering the rated voltage
magnitudes, instead of the actual ones, produces the largest errors: the bigger the WTLR absolute
value, the larger the error. On the contrary, ignoring the power factors does not compromise the
quality of the information provided by the indices.
2.6.1.5 Conclusions on the Matlab-coded procedure for WTLR calculation
On the basis of the tests on the Italian EHV system, we can conclude that the MVA rating
approximation is not suitable especially for the operation conditions in which the bus voltage
magnitudes diverge from the corresponding rated values, since in these cases it produces non-
negligible errors in the contingency analysis results and in the WTLR calculation.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 62
Consequently, in the simulations in which it is better not to use this simpli�cation, it is impossible
to adopt the Line Outage Distribution Factors to compute the approximate branch power �ows in
N-1 security conditions, because the actual voltage magnitudes are not calculated by this method.
Moreover, the tests on the Italian EHV network demonstrate another limit of adopting the LODF
simpli�cation: it is not able to detect the line outages that cause the non-convergence of the load
�ow algorithm. For instance, this is the case of the outage of the 380 kV line Dugale-Montecchio in
the North-East: the power �ows, that have to reach the 380/132 kV substations of Montecchio and
Sandrigo to meet the demand of the big load areas in the province of Vicenza, have to cover a long
electrical distance, which produces considerable voltage drops and leads to the system collapse due
to the lack of adequate reactive power resources in the area.
2.6.2 WTLR sensitivity: a tool with several uses
Other simulations aimed at showing several uses and applications of the WTLR methodology are
performed on the Italian EHV network at di�erent projection horizons: the tests will demonstrate
that this methodology could be a useful tool for both generation and transmission planning and
particularly for achieving a more coherent development of the whole power system.
All the simulations, whose results will be presented in the next paragraphs, are carried out con-
sidering the main assumptions described in subsection 2.6.1, except for the fact that the branch
overloads are calculated with reference to the e�ective real power �ow limits.
2.6.2.1 GENCO viewpoint
The WTLR methodology is founded on the basic concepts described in subsection 2.2.2.1. The
obvious use of this tool is thus the strategic generation siting, that is, to determine the geographic
locations where new generation would enhance the system security by creating post-contingency
counter-�ows that would mitigate overloads under contingency conditions. According to this, it
seems that the only advantage of the strategic generation siting is the system security improvement,
which is one of the chief tasks of a System Operator, but which does not involve the Generation
Companies. Also a producer can however bene�t from an exact and appropriate selection of the
sites for new power plants.
In a liberalised electricity market, where there can be a strong competition among power producers,
the transmission system limits have a key role in the clearing of the market. For instance, in Italy
the violation of one or more inter-zonal limits14 produces the separation of the Italian system in
two or more zones during the day-ahead market (the so called �Mercato del Giorno Prima�) and the
network constraints thus a�ect the market results and above all what producer o�ers are accepted.
In the Italian ancillary service market (the so called �Mercato del Servizio di Dispacciamento�) the
intra-zonal transmission constraints are taken into account and a generation re-scheduling occurs
in case of network congestions [24].
Therefore a GENCO, whose main purpose is to maximize its expected pro�ts, may gain some
advantages from an appropriate generation siting. Besides envisaging the supply concentration
and the possible competition with other producers, its expansion plan should consider the areas
14The Italian network is divided in the following zones: six geographical zones (North: Val d'Aosta, Piedmont,Lombardy, Trentino Alto-Adige, Veneto, Friuli Venezia Giulia and Emilia Romagna; Central-North: Tuscany, Um-bria and Marche; Central-South: Latium, Abruzzi and Campania, excepting the Gissi production area; South:Molise, Apulia, Basilicata and Calabria, plus the Gissi production area; Sicily, Sardinia), seven virtual foreign zones(France, Switzerland, Corsica, Corsica AC, Austria, Slovenia, Greece) and �ve limited production areas (Monfalcone,Foggia, Rossano, Brindisi, Priolo), as shown in Figure 2.40.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 63
Figure 2.40: Geographical and virtual Italian zones
which are not limited by existing network bottlenecks or those where the TSO has planned some
grid reinforcements, so that its future power productions will not su�er heavy restrictions due to
some network constraint. The WTLR methodology can give a GENCO some useful indications
about this issue.
The simulations on the Italian EHV network at the year 201315 provide the WTLR graphical
representation in Figure 2.41.
First of all, it can be used to qualitatively identify the best areas and locations for new power
plants so that they should not be heavily limited by the occurrence of network congestions. As
already highlighted by the contingency analysis results, the most critical grid element is the middle-
Adriatic backbone, particularly between the electrical substations of Gissi St. and Villanova: it is
clear that at the projection horizon the least appropriate sites are situated in Southern Italy and
especially on the Adriatic side, where there is already a strong competition and where new power
plants will be installed in the next few years.
Always with reference to a GENCO's expansion plan, the WTLR values pertinent to a given
scenario can be used to rank a set of possible new generation sites. For instance, consider the
following six candidates for a new 800 MW CCGT power plant16 (Figure 2.42):
1. 380 kV node of Acciaiolo;
2. 380 kV node of Marginone;
3. 380 kV node of Suvereto;
4. 380 kV node of Fano;
5. 380 kV node of Villavalle;
6. 380 kV node of Presenzano.
According to the WTLR indications, the six candidates can be ranked in the following way:
15The simulations to which Figure 2.41 refers are carried out by using the modi�ed Matlab-coded program thatconsiders the actual power �ow limits and not the MVA rating approximation.
16The list reports the 380 kV nodes to which the new power plant could be connected.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 64
Figure 2.41: WTLR map - Italian EHV system (year 2013)
Figure 2.42: Possible new generation sites (year 2013)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 65
1. Fano (WTLR = -0.32);
2. Acciaiolo (WTLR = -0.07);
3. Marginone (WTLR = -0.06);
4. Suvereto (WTLR = -0.03);
5. Villavalle (WTLR = -0.02);
6. Presenzano (WTLR = +0.29).
In particular, it follows that the best location for a new power plant is the node of Fano, while the
worst one is the bus of Presenzano. Considering these suggestions in the de�nition of the expansion
plan, the risk of possible limitations due to some network constraint should be reduced. Moreover,
the whole power system will gain some advantages in terms of security enhancement.
This situation may change in consequence of the reinforcement of the Adriatic backbone as planned
by the Italian TSO within 2013-2015:17 the WTLR di�erences may become less notable, but in
any case the node of Presenzano may be still the least attractive because of the strong competition
among the power producers in the area.
A standard Optimal Power Flow, that provides the real power dispatch at the minimum generation
cost, is applied to six new test cases, each of which is derived from the base scenario by adding
one of the six new power plants. The outcomes are then compared to the indications given by
the WTLRs to con�rm (or not) the above-mentioned ranking and to estimate the overall system
bene�t in each case.
The simulations are carried out considering the e�ective generation costs of the thermoelectric
power plants assumed in service, so that no conjecture is made about the producers' o�ers in the
electricity market.
The analysis performed by means of the OPF procedure and considering the N-1 security criterion
highlights that the most critical grid element is the middle-Adriatic backbone, so con�rming that
the new generation sites to the north of this grid section are favoured by their geographical position.
The ranking of the generation sites are validated by evaluating two parameters: the dispatched
power of the new power plants, which �xes their utilization hours, and the variation of the real
power losses, that a�ect the total generation cost and thus the system operation economy. Ta-
ble 2.19 summarizes the OPF outcomes pertinent to the six test cases. So di�erent values of the
dispatched power in the second column are due to the distance (both geographical and electrical)
of the new generation sites from the load areas and also to the concentration of more or less com-
petitive power producers in the zone. The smallest value pertinent to the power plant connected
to the 380 kV node of Presenzano con�rms that it will be disadvantaged by its location because it
will cope with the strong competition in Southern Italy and more precisely in Campania.
The comparison between the outcomes of the two procedure makes it evident that there is an
exact correspondence between the WTLR ranking and the results in Table 2.19. In particular, the
realization of a new CCGT power plant connected to the 380 kV node of Fano will yield the greatest
bene�ts in terms of both system security enhancement, as suggested by the corresponding WTLR,
and reduction in power losses and total generation costs, as highlighted by the OPF calculations.17In the last development plan [23], to overcome the existing power limitations on the production areas in Southern
Italy, the Italian TSO has scheduled to double and reinforce the middle-Adriatic backbone by implementing a seconddouble-circuit line between the existing substations of Villanova and Foggia by 2013-2014. Furthermore, to makethe 380 kV network more meshed and to improve the system reliability and the security of supply, the Italian TSOhas planned to construct a new 380 kV line between the existing substations of Fano and Teramo by 2015.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 66
Table 2.19: OPF results (year 2013)
Figure 2.43: Possible new generation sites (year 2015)
This approach can be used also to evaluate the e�ect of a delay in the completion of the grid
development plan. For instance, consider the Italian EHV electric system with reference to a
summer peak load condition at the projection horizon of the year 2015 and the following set of
possible new generation sites (Figure 2.43):
� 380 kV node of Udine Ovest;
� 380 kV node of Forlì;
� 380 kV node of Teramo;
� 380 kV node of Aliano.
As regards the base 2015 scenario, the steady-state security assessment, on the basis of which
the WTLR sensitivities are calculated, does not detect any network congestions: thanks to the
network reinforcements scheduled by the Italian TSO within 2015, the transmission system is able
to transfer the power �ows generated by the power plants in service towards the load areas without
overloading any grid element. Consequently, it is impossible to determine the indices and to get
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 67
Table 2.20: OPF results (year 2015)
Table 2.21: Contingency analysis results (without doubling the Adriatic backbone)
useful information concerning the sites chosen for the installation of a new 800 MW CCGT power
plant.
The OPF procedure applied to four new test cases, each of which is derived from the base scenario
by adding one of the four new power plants, gives the results in Table 2.20.
Further analyses, using the WTLR tool and considering less positive assumptions about the com-
pletion of the transmission system development plan, are carried out. For example, suppose that
the doubling of the middle-Adriatic backbone between the nodes of Villanova and Foggia is not
completed by 2015, contrary to what is planned by the Italian TSO. The corresponding contin-
gency analysis results are shown in Table 2.21: for the given scenario the only network congestions
regard just the existing 380 kV line Gissi St.-Villanova. According to the resulting WTLR indices,
the four candidates can be ranked as follows:
1. Teramo (WTLR = -2.10);
2. Forlì (WTLR = -1.23);
3. Udine Ovest (WTLR = -1.03);
4. Aliano (WTLR = +2.50).
It is clear that, if the doubling of the middle-Adriatic backbone was not completed by 2015, the
site of Aliano would be the least suitable for installing a new CCGT power plant, as it could be
limited by the occurrence of congestions.
Considering the data in Table 2.20, resulting from the study on the most favourable scenario in
terms of network upgrades, and the WTLR-based ranking, pertinent to the base scenario without
the reinforcement of the middle-Adriatic backbone, we can derive the priority list in Table 2.22.
As pointed out by the second column, any power plants should not be limited by the occurrence of
network congestions, if the grid development plan was completed according to what is scheduled
by the Italian TSO [23]. Indeed, the limitation on the power production at the node of Aliano,
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 68
Table 2.22: Priority list of the new generation sites (year 2015)
to which the lowest dispatched power in Table 2.22 refers, is especially due to a very high supply
concentration in Southern Italy.
To conclude, the analysis suggests that, from the producer's viewpoint, the 380 kV node of Udine
Ovest is the best site for a new CCGT power plant since it has the highest dispatchability. More-
over, it produces the largest bene�ts for the system not only in terms of decrease in real power
losses (-20 MW), but also in terms of security enhancement. Concerning this, suppose that the
main grid reinforcements planned by the Italian TSO in the North-East (i. e. the 380 kV line
Volpago-Venezia Nord and the 380 kV double circuit line Udine Ovest-Udine Sud-Redipuglia) are
not completed by 2015. The outage of the 380 kV line Dugale-Montecchio does not cause any
overloads, but leads to notable voltage drops in the area (see subsection 2.6.1.5). The installation
of a new power plant connected to the 380 kV node of Udine Ovest allows the maintenance of an
adequate voltage pro�le thanks to a better distribution of the real power �ows in the network and
to a larger availability of reactive resources which compensate for the reactive power losses.
2.6.2.2 TSO viewpoint
One of the main tasks of a Transmission System Operator is the system security maintenance. So
one of the main objectives of the grid development plan is to reduce the risk of network congestions
and the existing limitations on the production areas.
Besides being helpful for strategic generation siting, the WTLR methodology can be successfully
used by the TSO to guide transmission planning. Some of its potential applications are:
1. to identify the weakest grid areas, where new transmission facilities have to be installed;
2. to demonstrate the bene�ts of realizing the entire development plan within the prearranged
time limit and thus the consequences of a possible delay;
3. to assess the impact of the generation system expansion on network security;
4. to assess the e�ectiveness of a single grid reinforcement planned by the TSO in terms of
security enhancement and so to rank a set of grid upgrades in order to prioritize transmission
planning;
5. to determine new network reinforcements, to be included in the transmission system devel-
opment plan.
Determination of the most critical grid elements. To prove that the WTLR tool can be
used by the TSO to determine the weakest grid sections, the Matlab-coded program is applied
to the Italian EHV system with reference to a peak load condition of summer 2009. In order to
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 69
Table 2.23: Contingency analysis results (year 2009)
Figure 2.44: WTLR map - Italian EHV system (year 2009)
validate the outcomes, they will be compared with the data published by the Italian TSO in its
last development plan [23].
The contingency analysis results are summarized in Table 2.23, while the WTLR graphical repre-
sentation is illustrated in Figure 2.44.
As expected, the correctness of the outcomes is rati�ed by what reported in [23] about the most
critical grid areas of the current Italian grid (Figure 2.45): more precisely, the procedure results
show the inadequacy of the 220 kV network, especially in the area of Milan (overload of the
line Milano Porta Venezia-Milano Porta Volta), in Campania (overload of the line Frattamaggiore-
Starza Grande), in the North-East (overload of the line Dolo-Camin), and also the critical operation
condition of the 380 kV lines Foggia-Benevento and Gissi St.-Villanova. Obviously, the test case
does not highlight all the operation problems that involve the Italian transmission system: this is
just an example of application to demonstrate the tool usefulness.
The information provided by the WTLR map also prove the need to realize some of the network
reinforcements planned by the Italian TSO: for instance, the transmission capacity increase of the
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 70
Figure 2.45: Critical grid areas of the current Italian transmission system [23]
existing 380 kV line Foggia-Benevento (target year: 2012), the doubling of the 380 kV middle-
Adriatic backbone (target year: 2013/2014), the realization of a new 380 kV double circuit line
between the substations of Camin and Dolo in the North-East (target year: 2011/2013), and the
reinforcement of the network in the area of Milan (target year: 2012).
Assessment of development plan bene�ts. Besides identifying the most critical grid ar-
eas [19, 20], so providing interesting information for transmission planning, the WTLR tool can
be used to demonstrate the bene�ts of completing the realization of all the network reinforce-
ments included in the development plan within the prearranged time limit and thus to assess the
consequences of a possible delay due to some impediment [22].
First a medium-term summer scenario of the Italian EHV system (Scenario A) is considered. A
second scenario (Scenario B) is derived from this one by removing all the network reinforcements
scheduled by the TSO for the �ve-year period 2010-2014. Other simulations are then carried out on
a long-term summer scenario (Scenario C), from which, by eliminating all the grid reinforcements
planned for the �ve-year period 2014-2019, a fourth scenario (Scenario D) is obtained.
Table 2.24 summarizes the main features of the scenarios de�ned to assess the bene�ts of the ten-
year grid development plan [23], while the most important grid upgrades (from north to south)
included in it are listed in Table 2.25.
Tables 2.26 and 2.27 reports the contingency analysis results concerning the medium-term scenar-
ios.
In Scenario B, where the transmission system has the present structure, the major operation
problems, some of which are already in intact system conditions, regard the current inter-zonal
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 71
Table 2.24: Scenarios for assessing Italian EHV development plan bene�ts
Table 2.25: Main grid reinforcements (2010 development plan)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 72
Table 2.26: Contingency analysis results - Scenario A
section between Central-South and South, and precisely: the 380 kV lines Benevento-Foggia and
Matera-S. So�a and the Adriatic backbone, through which a large part of the power production
of Southern Italy �ows towards the big load areas in Campania and in Central Italy. Also the
380 and 220 kV transmission system between the North-West and the North-East is a�ected by
considerable power �ows which cause some overloads in N-1 security conditions, so making the
network reinforcements necessary.
The WTLR graphical representation on the bottom of Figure 2.46, pertinent to Scenario B, and
the WTLR map in Figure 2.44, concerning the current Italian EHV system, can be compared to
assess the impact of the medium-term generation expansion on network security. It is clear that,
if the main points of the development plan were not realized by 2014, so making some existing
critical situations worse, the system operation would be very di�cult: the most critical areas
would be Southern Italy, a�ected by a great generation expansion in recent years and where new
thermoelectric power plants and the largest part of the new wind farms expected in the medium-
term will be installed, and to a lesser extent Piedmont.
The comparison of the two maps in Figure 2.46 qualitatively shows the e�ectiveness of the main
network reinforcements planned by the Italian TSO in terms of system security enhancement: their
completion within 2014 will result in an overall congestion alleviation.
As regards the year 2019, the installation of new generation power plants and the electricity
demand growth could give rise to some operation problems, as shown by Table 2.29 and Figure 2.47
(bottom), above all in Central-Southern Italy, despite the medium-term transmission expansion.
The network reinforcements planned for the �ve-year period 2014-2019 will result in a general
improvement, even though the 380 kV line Matera-S. So�a may be still critical because the current
grid development plan does not include the transmission capacity increase of this line.
Assessment of the impact of an increasing wind penetration on network security.
Given the concepts on which the WTLR indices are based, the most obvious use of this tool
by a Transmission System Operator is the assessment of the generation expansion impact on
system security. For instance, consider the medium-term scenario of the preceding paragraph (i. e.
Scenario A). The Italian EHV system model is de�ned taking into account the wind generation
expansion expected in the next few years.
Figure 2.48 shows the geographical distribution of the total wind generation capacity installed in
Italy at the end of 2009.
To get an idea of the wind power capacity that is expected to be in service in the next two years
(2011/2012), the Italian TSO considers the wind farms for which the investors have already taken a
�nancial commitment to cover the grid connection charges. To outline a possible expansion scenario
with reference to the projection horizon 2014/2015, the TSO takes into account the wind farms
for which the grid connection solution has been accepted and a commitment for the preliminary
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 73
Table 2.27: Contingency analysis results - Scenario B
Table 2.28: Contingency analysis results - Scenario C
Table 2.29: Contingency analysis results - Scenario D
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 74
Figure 2.46: WTLR map - Scenarios A (top) and B (bottom)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 75
Figure 2.47: WTLR map - Scenarios C (top) and D (bottom)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 76
Figure 2.48: Wind generation capacity installed in Italy at the end of 2009
Figure 2.49: Wind generation capacity expected in the medium-term
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 77
plan has been undersigned (Figure 2.49).
Most of the wind power plants will be in the south of Italy and in the two major islands: nearly
6500 MW of wind generation capacity are expected in the short-medium term. The long-range
situation in Sicily, Sardinia, Apulia, Calabria, and Campania is particularly signi�cant: they are
the most favourable areas in terms of wind availability, where about half of all Italian wind farms
will be installed. Note that the wind power plants connected to the medium voltage distribution
network are not displayed in Figure 2.49.
To assess the impact of an increasing wind penetration on system security in terms of network
congestion increase, consider two new test cases derived from the medium-term scenarios of the
previous paragraph (i. e. Scenarios A and B) by removing the wind farms that will be realized
within 2014 and that are supposed to be in service [25-27]. A new scheduling of the thermoelectric
units, still resulting from a merit order dispatch, needs to be introduced. For the most part the
wind power generation is replaced by the most competitive CCGT power plants, which may be
located not only in Southern Italy.
As shown on the top of Figure 2.50, the completion of the grid development plan will lead to a
general improvement in terms of congestion alleviation. The security assessment, on which the
WTLR calculation is based, does not detect any power limit violations in Central-Southern Italy,
mainly thanks to the doubling of the middle-Adriatic backbone, the transmission capacity increase
of the 380 kV line Benevento-Foggia, and the new 380 kV line between the future substations of
Deliceto and Bisaccia.
The comparison between Figures 2.46 and 2.50 shows that the installation of the new wind farms
could increase the occurrence of network congestions: this demonstrates, even more clearly, the
need to carry out the development plan of the Italian transmission system, also considering the
increasing wind penetration.
Ranking of grid reinforcements. Consider Scenario B again. Some new test cases are derived
from it by adding one of the main network reinforcements included in the grid development plan
(one for each test case). The goal is to assess the e�ectiveness of the single network reinforcement,
with reference to the scenario chosen for the simulations, and then to outline a possible �ranking�.
The analysis focuses on Central-Southern Italy. Only the most signi�cant tests and results in terms
of congestion alleviation will be described (see Figure 2.51).
� Case B1: transmission capacity increase of the 380 kV line Benevento-Foggia.
The power plants in the area between the regions Apulia and Molise are now limited because
of the insu�cient transmission capacity of the 380 kV network that does not enable them to
be fully exploited to meet the considerable electricity demand of the neighbouring areas. In
anticipation of the new power plants which are expected to be installed in these regions in
the next few years, the transmission capacity of the existing 380 kV line Benevento-Foggia
needs to be increased. For this reasons, the line will be rebuilt by using higher capacity
wires. Table 2.30 summarizes the contingency analysis outcomes pertinent to the new test
case, resulting from the original one, i. e. Scenario B, by increasing the current limit of the
above-mentioned line (from 1600 A to 2400 A). The main e�ect of this grid reinforcement is
to solve the operation problems that a�ect the existing line Benevento-Foggia: the security
assessment does not detect any overload on it. Consequently, there is a notable decrease in
the indices of the nodes in Southern Italy, though they are still quite high, especially on the
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 78
Figure 2.50: WTLR map - Scenarios A (top) and B (bottom) without the new wind farms
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 79
Figure 2.51: Network reinforcements considered in the study
Adriatic side between the substation of Gissi and the south of Apulia. On the contrary, the
WTLRs of the 380 kV buses of Villanova, Teramo, Rosara, Candia, and Fano decrease. In
particular, the highest and the smallest values refer to the nodes of Gissi St. and Villanova
respectively, since the most critical grid element is the line between these two substations.
� Case B2: doubling of the middle-Adriatic backbone.
The recent development of the electrical system in Southern Italy has led to the limitation of
some power plants, particularly in the areas of Brindisi and Foggia. To overcome these prob-
lems and to avoid further ones in the future, the Italian TSO has planned the reinforcement
of the middle-Adriatic backbone by building a second double circuit line between Foggia and
Villanova. Table 2.31 reports the contingency analysis results concerning this new test case.
It is clear that the doubling of the middle-Adriatic backbone is very important to enhance
the network security. The number of congestions decreases in Central-Southern Italy: the
security assessment detects one violation in the 220 kV transmission system in Campania and
two overloads on the 380 kV line Matera-S. So�a. Therefore, besides solving the operation
problems that a�ect the existing line between the substations of Foggia and Teramo, the grid
reinforcement in question also avoids the congestions on the 380 kV line Benevento-Foggia,
as there is another path to transfer the power production of the generators in Apulia.
� Case B3: new 380 kV double circuit line Montecorvino-Avellino N.-Benevento.
The authorization of new power plants in Calabria, Apulia, and Campania makes the rein-
forcement of the transmission system necessary to remove the limitations on the present and
future power productions due to the occurrence of congestions in the EHV grid in Campania.
The Italian TSO has planned the realization of a new 380 kV double circuit line between
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 80
Table 2.30: Contingency analysis results (Benevento-Foggia reinforcement)
Table 2.31: Contingency analysis results (middle-Adriatic backbone reinforcement)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 81
Table 2.32: Contingency analysis results (new line Montecorvino-Benevento)
Montecorvino and Benevento, together with a new 380/150 kV substation to the north of
Avellino that will be connected to both the new line and the existing 380 kV line Matera-S.
So�a. The contingency analysis results are given in Table 2.32. First of all, the construction
of the new line, which makes the 380 kV network more meshed, solves the congestions on the
380 kV line Benevento-Foggia in consequence of the outage of the 380 kV line Avellino Nord-S.
So�a. This is the main e�ect, even if the size of all the other overloads in Central-Southern
Italy diminishes. Nevertheless, this improvement yields only a small decrease in the positive
WTLR values, especially on the Adriatic side, which re�ects the operation problems of the
middle-Adriatic backbone and of the line Benevento-Foggia.
� Case B4: new 380 kV line Deliceto-Bisaccia.
The Italian TSO has planned the construction of a new 380/150 kV substation near Deliceto
in Apulia that will be connected to the existing 380 kV line Foggia-Candela and that will
collect the power productions of the wind farms expected in the area. It will be connected
also to the future substation of Bisaccia and thus to the existing 380 kV line Matera-S. So�a.
The goal is to make the 380 kV grid more meshed and to reduce the risk of congestion, so
removing the probable limitations on the new power plants in Apulia and on the Adriatic
side, including the wind power production in the area of Candela. As shown by the security
assessment results in Table 2.33, the grid reinforcement in question produces an overall
congestion alleviation. The most evident improvement refers to the 380 kV line Benevento-
Foggia which is not overloaded by the outage of the 380 kV lines Teramo-Villanova and Gissi
St.-Villanova any longer: the power �ows that reach the node of Foggia cannot be conveyed
by the middle-Adriatic backbone; in this case they can �ow not only on the line Benevento-
Foggia, but also on the new line Deliceto-Bisaccia and then on the line Matera-S. So�a. Some
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 82
Table 2.33: Contingency analysis results (new line Deliceto-Bisaccia)
operation conditions however get worse. For instance, the size of the overloads on the line
Benevento-Foggia following the outage of the line Avellino Nord-S. So�a increases, as the
power �ows on the line Matera-S. So�a, once the substation of Bisaccia has been reached,
can be transmitted by the new line towards the bus of Foggia. Moreover, in case of the
outage of the line Benevento-Foggia, besides the congestion on the line Gissi St.-Villanova,
the security assessment detects also the overload on the line Bisaccia-Avellino Nord: the
power �ows, arrived at the bus of Foggia, have to be conveyed partly by the middle-Adriatic
backbone, partly by the new line Deliceto-Bisaccia, since they cannot �ow on the outaged
line Benevento-Foggia.
To de�ne a priority list of the above grid reinforcements, �rstly we can consider the variation of the
total system overload with respect to the base case (Scenario B), which measures the e�ectiveness
of each transmission upgrade in terms of congestion alleviation with reference to the scenario
considered in the study. A summary of the contingency analysis results is given in Table 2.34.
The number of violations and the system overload provide a clear indication of the e�ects of each
transmission reinforcement. As already shown by the detailed description of each test case, the
largest bene�ts derive from doubling the middle-Adriatic backbone, that will indeed a�ect a grid
section on which the TSO has detected some congestions in certain present operation conditions
and which may become more and more critical in the future in view of the expected generation
system development in South Italy and especially considering the growing utilization of wind power.
Furthermore, compared to the other grid reinforcements, it does not consist in constructing a single
line, or in increasing the current limit of an existing one, but in realizing a set of new lines according
to a well-designed scheme so increasing the available transmission capacity of the grid section and
making it more meshed. Also the calculation of one of the two metrics de�ned and validated for
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 83
Table 2.34: Summary of the contingency analysis results
Figure 2.52: WTLR algebraic sum
the CIGRE 63-bus system, that is, the WTLR algebraic sum, strengthens the above conclusions
since it re�ects the size of the reduction of the WTRLs (in absolute value) and consequently of
their algebraic sum in each case (Figure 2.52).
Though the above results provide quantitative data concerning the bene�ts of each transmission
reinforcement, one of the main advantages of the WTLR indices is their ability to be graphically
represented and to supply interesting qualitative information about the most severe congestions
and the most critical grid sections. The next �gures (Figures 2.53-2.56) show the WTLR maps
resulting from the analysis of each test case.
The comparison between the maps before (i. e. relative to Scenario B, see Figure 2.46 on the bottom)
and after adding a grid reinforcement highlights the e�ectiveness of the transmission upgrade in
reducing network congestions in Central-South Italy. This analysis suggests the following priority
order, which is also con�rmed by the total overload values and by the WTLR-based metric:
1. doubling of the middle-Adriatic backbone (12 congestions; total overload = 967.8 MW;
WTLR algebraic sum = +30.49);
2. transmission capacity increase of the line Benevento-Foggia (17 congestions; total overload
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 84
Figure 2.53: WTLR map (Benevento-Foggia reinforcement)
Figure 2.54: WTLR map (middle-Adriatic backbone reinforcement)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 85
Figure 2.55: WTLR map (new line Montecorvino-Benevento)
Figure 2.56: WTLR map (new line Deliceto-Bisaccia)
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 86
= 2173.5 MW; WTLR algebraic sum = +106.21);
3. new double-circuit line Montecorvino-Avellino Nord-Benevento (21 congestions; total over-
load = 2663.1 MW; WTLR algebraic sum = +137.67);
4. new line Deliceto-Bisaccia (23 congestions; total overload = 2943.1 MW; WTLR algebraic
sum = +155.68).
We can conclude that the transmission planner can get useful information for de�ning a priority
list of a set of grid reinforcements by comparing all the WTLR maps which are immediately
comprehensible to everyone, considering the meaning of the indices.
De�nition of new grid reinforcements. The WTLR methodology has been demonstrated
to be a useful tool for determining the most critical grid elements and sections, given a certain
scenario. Therefore, it can be used to de�ne new network reinforcements to be included in the
development plan.
The contingency analysis results (Table 2.28) and the WTLR map (on the top of Figure 2.47) in
Scenario C, which refers to the projection year 2019, indicate that, considering the scenario under
study, the only overloads are on the 380 kV line Matera-S. So�a between the future substations of
Bisaccia and Avellino Nord in case of the outage of one of the two lines Ariano Irpino-Benevento and
Aliano-Matera. These congestions are probably due to some existing limitations obliging the TSO
to operate the line with a current limit of 1920 A, as well as the development of generation and load
expected in the next decade. To solve these operation problems the transmission planner should
take into proper consideration the transmission capacity increase of the line in question, including
it in the development plan. To simulate the realization of the grid upgrade by 2019, the current
limit of the line Matera-S. So�a is increased from 1920 A to 2400 A in the network model used
for the tests (Scenario C). Since the contingency analysis does not detect any congestion, all the
WTLRs in the long-term are equal to zero and the corresponding map is entirely white-coloured.
2.6.2.3 Interchangeability of generation expansion and transmission development
Considering the basic concept of the WTLR methodology, that is, the strategic generation siting
in favour of system security, and the indications given by the WTLR values concerning the most
suitable grid areas for installing new generating capacity, two 800 MW CCGT power plants are
added to the network model in Scenario B and connected to the lowest WTLR buses in Central-
Southern Italy (Villanova = -1.60 and Benevento = -1.78) [22]. The aim is to evaluate the bene�ts
of the new power injections and their e�ects on grid congestion alleviation. The new generators are
dispatched at their rating, while the power production of Apulia and Abruzzi regions is reduced
by the same amount (Case B5).
The above sites are chosen according to their WTLR so that the power injections of the new CCGT
plants help in alleviating the overloads on the lines Ariano Irpino-Benevento and Gissi St.-Villanova.
Negative-WTLR regions are in fact at the receiving end of at least one congested grid element,
while positive-WTLR areas are at the sending end. Real power injections at a negative-value bus
will therefore produce counter-�ows which will contribute to congestion alleviation.
The security assessment results in Table 2.35 are alike to those obtained by realizing the doubling
of the middle-Adriatic backbone (see Table 2.31). Obviously, the network in Northern Italy is
not a�ected by the power production of the new plants, which instead solve all the congestions
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 87
Table 2.35: Contingency analysis results (New CCGT power plants)
Table 2.36: WTLR values at some nodes in Central-South Italy
on the lines Ariano Irpino-Benevento and Gissi St.-Villanova. Also the remaining overloads in
Central-South Italy (on the 220 kV line Frattamaggiore-Starza Grande in Campania region and on
the 380 kV line Teramo-Rosara in Marche region) are practically the same.
The WTLR values of some 380 kV nodes in Central-Southern Italy are in Table 2.36 with refer-
ence to Scenario B, Case B2 (i. e. doubling of the middle-Adriatic backbone), and Case B5 (i. e.
installation of new CCGT plants).
The comparison between the second column and the last one shows that the installation of new
generating capacity at Villanova and Benevento buses signi�cantly improves the network security.
The third and fourth columns con�rm the above considerations on the outcomes of the contingency
analysis. The WTLRs are in fact nearly the same, as the security assessment results are alike.
The tests on Case B2 and Case B5 demonstrate the interchangeability of generation and trans-
mission expansion and especially that, if appropriately located, the real power injection of a new
generating unit may have the same e�ect of a grid reinforcement in terms of system security en-
hancement. Moreover, they prove that the WTLR methodology can be useful to achieve a more
coherent development of the whole power system thanks to a more coordination between generation
expansion and transmission development.
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 88
2.7 Chapter conclusions
Restructuring have introduced competition in the generation and, in some cases, in the retail
segments of the electric power industry. A common element of restructuring is the unbundling of
generation and transmission, with the latter being opened for use by all eligible market participants
under the so called open-access regime. This has greatly transformed the traditional power industry
and introduced many new challenges in all aspects of generation, transmission and system operation
and planning.
The unbundling of generation, transmission, and distribution has resulted in multiple parties in
the business. To foster competition and pre-empt market power abuse, some jurisdiction required
generation divestiture to create more independent generation owners. The generation enterprises,
unlike the integrated utility of the regulated world, have di�erent and sometimes con�icting ob-
jectives. The presence of new structures and the diversity of the many new players in electricity
markets have fundamentally invalidated some assumptions and relationships of the traditional
planning process, bringing new challenges especially to the transmission planning problem.
In the restructured industry, generation expansion decisions are made by individual generation
companies, often not completely known to the authority responsible for transmission planning.
Indeed beyond the �ve- or ten-year horizon, generation scenarios are largely unknown. Moreover,
generation expansion decisions may be a�ected by decisions on transmission expansion and vice
versa. All these aspects resulting from the electricity industry restructuring and liberalisation
may cause a con�ict between generation owners' investments and transmission planners' decisions,
especially because of the diversity of their interests and objectives. This lack of coordination in the
planning process may be a serious problem for the operation of power systems, that are large-scale,
integrated, and complex engineering systems, which intrinsically need a certain level of centralized
coordination to function. In particular, it may have heavy repercussions on network security and
hence on electricity market e�ciency and social welfare.
The chapter has shown the interchangeability of generation and transmission investments and
particularly it has highlighted that generation expansion may have the same (positive) e�ect of
a transmission reinforcement on power system security. The WTLR methodology is based just
on this concept, which suggests the advantages of strategic generation siting not only for network
security enhancement, but also for better and more e�ciently exploiting the available generation
park.
A procedure for the calculation and graphical representation of WTLRs has been implemented
in the Matlab programming language and described in detail in the chapter. It has been applied
to a test system (CIGRE 63-bus network) in order to check the outcomes' correctness. Besides
identifying the most suited network sites for installing new generating units, which is the basic
idea of the WTLR methodology, the contingency analysis results and the consequent WTLR map
provide useful information also about the most critical grid areas and elements. Some simulations
have been performed considering a possible set of new transmission lines for the CIGRE network.
The choice of the grid reinforcements and in particular the selection of the new lines' endings have
been based on the WTLR values: the �from bus� has a negative index, while the �to bus� has a
positive one, so that the new line will certainly alleviate grid congestions and improve network
security. Then a priority list of the new lines has been de�ned according to the total system
overload decrease achieved thanks to each new grid element. This ranking has been validated from
an economic perspective by calculating the social welfare increase by means of an Optimal Power
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 89
Flow procedure. Two simple indicators, which can be used to prioritize transmission planning,
have been proposed: the algebraic WTLR sum, which can be considered a �measure� of overall
system security, as well as the total system overload, and an index that can estimate which new
connection will have the greatest marginal bene�t to network security.
The tests on the CIGRE 63-bus system have suggested some possible modi�cations to be made in
the proposed procedure coded in the Matlab programming language.
The �rst objective has been the reduction of the total computational time. The most time-
consuming phases are the standard contingency analysis, carried out by a sequence of AC load
�ow calculations (one for each line outage), and the calculation of ISDFs in N-1 security condi-
tions. The Line Outage Distribution Factors (LODFs) have been introduced in the determination
of the real power �ows on grid branches in post-contingency conditions, so substituting the stan-
dard contingency analysis. To further speed up the Matlab-coded program, another simpli�cation
has been considered: using the base ISDFs to compute the WTLR indices. The e�ect of these two
approximations has been investigated, showing that they do not cause large errors. The second
objective has been to remove the WTLR dependance on the selection of the slack bus in the grid.
The concept of distributed slack bus has been introduced in both load �ow calculations and ISDF
computation. The simulations have shown that in any case the most correct choice is to assume
a distributed slack bus model, but at the same time they have highlighted that the results can be
little a�ected by the �only one slack bus� assumption on condition that the slack bus is suitably
selected among the grid nodes.
The second part of the chapter refer to the tests on the Italian EHV electric system. First,
the most important limit of the original methodology has been pointed out. The impact of the
MVA rating approximation (i. e. the approximation that the line MVA rating is a MW limit,
so disregarding both the actual voltage magnitude and the power factor) on security assessment
results and WTLR sensitivities has been investigated by means of a standard steady-state security
assessment tool. The check has shown that the MVA rating approximation introduces notable
errors in the contingency analysis results. Therefore, the original Matlab-coded program has been
suitably modi�ed by considering the actual power �ow limits in the calculation of the branch
overloads. The WTLR tool has been then applied to di�erent test cases in order to demonstrate
its usefulness for generation and transmission planning. Although the basic idea of the WTLR
methodology is the strategic generation siting to improve power system security, it can be a helpful
tool also for generation owners, that can bene�t from an appropriate selection of the locations for
installing new power plants: considering the suggestions given by WTLRs in the de�nition of the
expansion plan, the risk of possible limitations due to some network constraint could be reduced.
Moreover, given a certain set of possible new generation sites, the WTLR indices can be used to
de�ne a priority list. Since the fundamental objective at which the WTLR methodology aims is
power system enhancement and this is one of the main tasks of system operators, the obvious
application of the tool is transmission planning. The tests on the Italian EHV network have shown
some of its potential uses. The transmission planner can make use of it to identify the weakest
grid sections and elements, to demonstrate the bene�ts of the grid development plan, to assess the
impact of generation expansion on network security, to de�ne possible priority lists of planned grid
reinforcements, and to determine new network enhancements.
The WTLR sensitivities have therefore proved to be a simple, but e�ective instrument for both
generation and transmission planning. It is based on simple concepts since it is founded on load
�ow calculations and sensitivity computations. But at the same time it is e�ective especially thanks
CHAPTER 2. WTLR AND POWER SYSTEM PLANNING 90
to the graphical representation of WTLRs which, though provides only qualitative information, is
extremely intelligible. We can conclude that its main advantage is to allow a more coherent devel-
opment of the whole power system to be attained, since it exploits the concept of interchangeability
of generation and transmission.
Chapter 3
Reactive power service
Traditionally, electric utilities have been vertically integrated monopolies that have built gener-
ation, transmission, and distribution facilities to serve the needs of the customers. For the past
decade, the electric power industry has been going through a process of transition and restruc-
turing by moving away from vertically integrated monopolies and towards competitive markets.
This has been achieved through a clear separation between transmission and generation activities
(unbundling), as well as by creating competition in the generation sector. The restructuring pro-
cess has created certain class of services such as frequency regulation, voltage and reactive power
control, energy imbalance, and generation and transmission reserves, which are essential to the
power system in addition to the basic energy and power delivery ones. This class of services is
referred to as ancillary services, and they are indispensable to ensure system security, reliability,
and e�ciency. Ancillary services are no longer an integral part of the electricity supply, as they
used to be in the vertically integrated power industry structure, since they are now unbundled and
also priced separately. So the main issues are to identify what kind of services are indispensable to
ensure the electricity supply with certain quality standards, to de�ne the most suitable methods
for their acquisition, to evaluate the exact amount of each service that is necessary to operate the
system reliably, and �nally to set up the proper remuneration mechanisms for the suppliers, if the
regulation provides for this eventuality.
In a competitive environment, the provision of these services must be carefully managed so that
the power system requirements and market objectives are adequately met. The System Operator
is the entity entrusted to their acquisition through commercial transactions with ancillary services
providers. Currently, there is not a single international classi�cation of ancillary services, but each
electricity market has its own de�nition. There are however similarities in the de�nition of the
ancillary services in the di�erent contexts, at least regarding their functions. The main di�erences
are usually in the methods adopted for their provision and remuneration.
Reactive power and voltage support is recognized as ancillary service, since it is essential to ensure
a secure power system operation. From this perspective, the objectives are essentially the main-
tainance of appropriate voltage pro�les in all grid nodes, so guaranteeing certain standards of power
quality, and of su�cient, well-distributed reactive power margins to compensate for disturbances
in case of contingency.
But, in the competitive electricity market environment, the provision of such a service must take
into account the economics in addition to the technical and physical considerations and so depends
on the market players and the electricity market rules. In particular, competition in generation
91
CHAPTER 3. REACTIVE POWER SERVICE 92
makes it important to consider the development of a reactive power market that complements the
existing energy market. Although the cost of reactive power production is much less than that of
real power, reactive power is critical to system reliability since its su�cient provision is necessary
to avoid an extremely costly system collapse. Moreover, under stressed system conditions, reactive
power requirements from some generators are only met at the expense of reducing their real power
output, and hence they signi�cantly increase the cost associated with reactive power production.
Besides this new aspect deriving from the restructuring and liberalisation of the electricity industry,
the increasing attention towards renewable sources and especially towards wind energy has raised
another important issue for power system operation and in particular for reactive power provision.
Wind farms that are large enough to be connected to the transmission system tend to be erected
in remote areas or even o�shore because of their dimension and impact on the scenery. Given that
the bus voltage is a local quantity, it can be di�cult to control the voltage at these distant places
by use of conventional power stations elsewhere in the grid. Therefore, wind turbines are required
to have voltage control capabilities. The voltage control capabilities of wind turbines are becoming
an increasingly important consideration regarding grid connection and also the turbines' market
potential. Furthermore, large-scale wind farms may make it necessary to install voltage control
devices in the transmission network, irrespective of the voltage control capabilities of the wind
turbines themselves: even if the wind turbines have exactly the same voltage control capabilities
as the conventional synchronous generators whose output they replace, there will be no guarantee
that they can ful�l the voltage control task of these generators. Therefore, it may be unavoidable
to consider and take additional measures to control the grid voltage.
These issues will be investigated in the chapter, and in particular an approach, based on an
Optimal Reactive Power Flow (ORPF) procedure, aiming at solving the optimal reactive power
provision problem, considering the di�erent views of buyers and sellers (i. e. the System Operator
and the producers), will be considered. It will allow the determination of the value of VAR support
required to the generation buses for the ful�lment of the constraints imposed by a secure and
economic system operation, while suggesting a suitable �nancial compensation scheme for reactive
power service and above all the implementation of a zonal reactive market based on the Secondary
Voltage Regulation areas. The simulation analyses will focus also on the perspective impact of large
wind power injections on the voltage control performances in the Italian EHV electrical system.
In particular, the outcomes will evaluate the economy and security level achievable in the Italian
system at 2014 peak-load under optimal reactive power schedules. Finally, the tests will allow the
e�ects of the planned network reinforcements to be assessed.
3.1 Ancillary services
As anticipated, the identi�cation of the ancillary services can be di�cult because there is not
a single de�nition internationally recognized. In fact, di�erent approaches can be adopted for
de�ning them.
3.1.1 De�nitions in the U.S. markets
In its Order 888 [28], the Federal Energy Regulatory Commission of the United States of America
(FERC) de�nes ancillary services as �those services necessary to support the transmission of electric
power from seller to purchaser given the obligations of control areas and transmitting utilities within
CHAPTER 3. REACTIVE POWER SERVICE 93
those control areas to maintain reliable operations of the interconnected transmission system�.
FERC Order 888 requires transmission providers to include six ancillary services in an open-access
transmission tari� to maintain reliability within and among the control areas a�ected by the
transmission service. These six services are divided into the following two categories:
� Services that FERC requires transmission providers to o�er and customers to accept from
the transmission provider, and these include:
� scheduling, system control, and dispatch: this service is required to schedule the move-
ment of power through, out of, within, or into a control area in order to maintain
supply-demand balance;
� reactive supply and voltage control from generation sources: the System Operator re-
quires generators to produce (or absorb) reactive power in order to maintain the system
bus voltages within some desired limits.
� Services that FERC requires transmission providers to o�er but which customers can accept
from the transmission provider, third parties, or by self-supply, and these include:
� regulation and frequency response: the use of generation equipped with governors and
automatic generation control (AGC) to follow the instantaneous change in the load in
order to maintain continuous generation-load balance within the control area, and a
scheduled interconnection frequency at 60 Hz;
� energy imbalance: the use of generation to correct for hourly mismatches between actual
and scheduled delivery of energy between suppliers and their customers;
� operating reserve - spinning: spinning reserve service is provided by unloaded generating
units that can respond immediately to correct for generation-load imbalance in the event
of a system contingency;
� operating reserve - supplemental: supplemental reserve service is provided by unloaded
generating units, by quick-start generation, or by interruptible load to correct for
generation-load imbalance in the event of a system contingency; however the response
does not have to be immediate, as in case of spinning reserve, but rather within a short
period of time.
FERC does not specify technical details of the services, and the costing methods for the services
remain ad hoc, varying widely from one provider to another.
Some organizations, including the North American Electric Reliability Council (NERC), do not
agree with the de�nition given by FERC and especially with the name �ancillary services�, since
these services are not auxiliary, but an integral part of the transmission utilities.
In their technical report [33] Hirst and Kirby presents a survey based on the work of several others,
including FERC [28], Houston Lighting & Power [34], the Michigan Public Service Commission [35],
the New York Power Pool [36], and the North American Electric Reliability Council [37]. This
technical report de�nes the ancillary services as those functions performed by electrical generating,
transmission, system-control, and distribution system equipment and people to support the basic
services of generating capacity, energy supply, and power delivery. The authors thus develop the
set of ancillary services by identifying those services that are essential to maintain electric system
reliability, are required to e�ect a transaction, or are a consequence of a transaction. They instead
CHAPTER 3. REACTIVE POWER SERVICE 94
exclude the services that are optional, long-term in nature, too cheap to warrant the costs of
metering and billing, naturally bundled with other services, or very location speci�c. The set of
services comprises scheduling and dispatch and several generating services, such as load following,
reliability, and supplemental reserves, as well as loss replacement and energy imbalance. Finally,
it includes system voltage control, which requires both generating units and transmission system
equipment.
NERC follows up on FERC's initiative by conducting its own more technical study to identify
ancillary services. In particular, NERC refers to ancillary services as Interconnected Operation
Services (IOS) [37], so emphasizing their essential role in the reliable operation of interconnected
bulk electricity systems as the U.S. one. Together with the Electric Power Research Institute
(EPRI), NERC de�nes twelve IOS that are necessary to support the transmission of power at an
adequate level of reliability and security; some of these services are similar to the six ancillary
services required by FERC. They are:
� regulation: using generation or load in order to maintain a minute-to-minute generation-load
balance within the control area;
� load following: the provision of generation and interchange capability required to maintain
the hour-to-hour and daily load variations not covered by regulation service;
� energy imbalance;
� operating reserve - spinning;
� operating reserve - supplemental;
� back-up supply: electric generating capacity used to replace a generation outage or the failure
to deliver generation due to an outage of transmission sources, and to serve a customer's load
that exceeds its generation;
� system control: activities that are required to ensure the reliability of the North American
interconnections, to minimize transmission constraints, and to guarantee the recovery of the
system after a contingency or disturbance;
� reactive power and voltage control from generation sources;
� network stability services from generation sources: using special equipment or devices, such
as power system stabilizers and dynamic braking resistors, at the generating plants to meet
NERC reliability requirements and maintain a secure transmission system;
� system black start capability: the availability of generating units that can start without an
outside electrical supply to take part in the restoration plan after a system blackout;
� real power transmission losses: the provision of capacity to replace energy losses on a trans-
mission system;
� dynamic schedule: the provision of the real-time monitoring, telemetering, computer software,
hardware, communications, engineering, and administration that are needed to electronically
move real energy services associated with generation or load out of its Host Control Area
and into a di�erent Electronic Control Area.
NERC IOS Working Group also identi�es an Ancillary Services Market Framework consisting of
two distinct parts: a resource supply market and an ancillary service delivery market [29].
CHAPTER 3. REACTIVE POWER SERVICE 95
3.1.2 Ancillary services in Europe
The European Directive 2003/54/EC [30] says: �ancillary services means all services necessary for
the operation of a transmission or distribution system�. Among the tasks of Transmission System
Operators, it indicates the responsability for �ensuring a secure, reliable and e�cient electricity
system and, in that context, for ensuring the availability of all necessary ancillary services insofar
as this availability is independent from any other transmission system with which its system is
interconnected�.
European UCTE Operation Handbook [31] gives the following de�nition: �Ancillary services are
Interconnected Operations Services identi�ed as necessary to e�ect a transfer of electricity between
purchasing and selling entities (transmission) and which a provider of transmission services must
include in an open access transmission tari��.
Ancillary services are de�ned by the Union of the Electricity Industry - EURELECTRIC [32]
as �all services required by the transmission or distribution system operator to enable them to
maintain the integrity and stability of the transmission or distribution system as well as the power
quality. Ancillary services are procured by the system operators and are provided by network
users (generators, customers) or system assets�. Acknowledging that several further ancillary
services can be and currently are de�ned in di�erent countries, this report discusses the following
ancillary services: frequency control, voltage control, spinning reserve, standing reserve, black-start
capability, remote automatic generation control, grid loss compensation, and emergency control
action.
A possible general cathegorization is:
� interconnection services:
� frequency response;
� special protection schemes: generator tripping and load shedding;
� generation-demand imbalance services:
� regulation;
� load following;
� contingency reserves: spinning and non-spinning reserves;
� local services:
� reactive support;
� black-start.
3.1.3 The Italian ancillary services
As regards the Italian situation, the ancillary service topic has been treated according to the
guidelines of the European Directive 96/92/EC [38], which have been formally acknowledged by
the Italian Regulatory Authority (Autorità per l'Energia Elettrica e il Gas - AEEG) in [39].
The de�nition of ancillary services accepted in Italy is the following: �set of all the activities
that need to be performed to support the power transmission while maintaining a reliable system
operation and ensuring the required standards of quality and security� [40].
CHAPTER 3. REACTIVE POWER SERVICE 96
The provision of ancillary services by the System Operator is regulated by the regulatory order
168/03 [41], that says:
� in the market for ancillary services, according to its own needs, the System Operator provi-
sions the resources necessary:
� for congestion management;
� to create su�cient reserves;
� to maintain the supply-demand balance in real-time.
� the System Operator organizes the market for ancillary services, which is subdivided into
several phases, consistent with the following objectives and criteria:
� to minimize the costs and to maximize the revenues resulting from the provision;
� to give market participants a clear signal of the economic value of the resources indis-
pensable to the electric system operation;
� to allow market participants to bid according to their cost structures through an appro-
priate de�nition of resources' typologies, market mechanisms, and bids' format;
� to allow the provision costs of the di�erent resources to be clearly identi�ed.
The fourth chapter of the Italian Grid Code [8] deals with the so called �dispatching rules� and in
particular it identi�es the resources indispensable to ensure a secure system operation and certain
standards of power quality:
� resources for congestion management;
� resources for primary reserve: they are used to automatically correct for the istantaneous
generation-load imbalance in the whole European interconnected grid;
� resources for secondary reserve: they are used to compensate the generation-load imbalance
within the Italian system;
� resources for tertiary reserve: they are used to constitute adequate capacity margins;
� resources for energy imbalance in real-time: they are used to maintain the supply-demand
balance, to solve the network congestions, and to restore the necessary margins of secondary
reserve;
� reactive reserve for primary voltage regulation;
� reactive reserve for secondary voltage regulation;
� black-start service;
� load-rejection service, that is, a generation group must maintain its stability in the case of
its disconnection from the grid;
� interruptible load service: it consists in the disconnection of load from the synchronous elec-
tric system, usually performed automatically, to control the system frequency in emergency
situations, and it can be used by the System Operator if the provision of resources in the
market for ancillary services is insu�cient to ensure a secure system operation.
CHAPTER 3. REACTIVE POWER SERVICE 97
3.2 Reactive power
3.2.1 What is reactive power?
Almost all bulk electric power is generated, transported, and consumed in alternating current
networks. Elements of AC systems supply (or produce) and consume (or absorb or lose) two kinds
of power: real and reactive power. Real power accomplishes useful work, while reactive power
supports the voltages that must be controlled for system reliability.
In an AC electrical system, voltage and current pulsate at the system frequency and thus are
described mathematically by sine waves. Voltage is a measure of the potential energy per electric
charge, and current is a measure of the average velocity at which electrons are moving.
Although AC voltage and current pulsate at the same frequency, they peak at di�erent times.
Power is the algebraic product of voltage and current. Over a cycle, power has an average value,
called real power, measured in watts. There is also a portion of power with zero average value that
is called reactive power, measured in vars. The total power is called apparent power, measured in
volt-amperes.
Reactive power has zero average value because it pulsates up and down, averaging to zero; reactive
power is measured as the maximum of the pulsating power over a cycle. Reactive power can be
positive or negative, depending on whether current peaks before or after voltage. By convention,
reactive power, like real power, is positive when it is �supplied� and negative when it is �consumed�.
Absorbing reactive power lowers voltage magnitudes, while producing reactive power increases
voltage magnitudes.
Reactive power in an electric transmission system is just the pulsating transfer of stored energy
between various kinds of electrical components in the system. Because voltage and current are
pulsating, the power on a transmission line also pulsates. In a transmission system, this pulsating
transfer of stored energy results in a loss of power called line losses. Real and reactive power are
in quadrature (90 degrees out of phase) and hence the letter Q is commonly used to designate
reactive power. Real power is commonly designated as P.
Reactive power takes up space on transmission lines. For a transmission line, the square of the real
power plus the square of the reactive power must be less than the square of the thermal capacity
(measured in volt-amperes) of the line. When thermal capacity is exceeded signi�cantly for a
long time, the line will sag, possibly into vegetation, causing a short circuit, or anneal, resulting
in structural damage. Real power losses in transmission lines are proportional to the current in
the line. Because power is the algebraic product of voltage and current, the same power at high
voltages has a lower current, and hence, has lower losses.
Reactive power is di�cult to transport. At high loadings, relative losses of reactive power on
transmission lines are often signi�cantly greater than relative real power losses. Reactive power
consumption or losses can increase signi�cantly with the distance. Transmission losses lead to the
expression that reactive power does not travel well. When there is not enough reactive power
supplied locally, it must be supplied remotely, causing larger currents and voltage drops along the
path [43].
3.2.2 The need for reactive power
Reactive power is directly associated with voltage, and thus voltage control is achieved in electric
power systems by absorbing/delivering reactive power. Voltage control, which implies maintaining
CHAPTER 3. REACTIVE POWER SERVICE 98
the voltage at each bus in the system within de�ned limits, is important for proper operation
of electric power equipment to prevent damage such as overheating of generators and motors, to
reduce transmission losses, and to maintain the ability of the system to withstand disturbances,
such as system faults, loss of generation, or transmission line outage, and prevent voltage collapse.
In general terms, decreasing reactive power causes voltages to fall, while increasing reactive power
causes voltages to rise. A voltage collapse occurs when the system is trying to serve much more
load than the voltage can support.
Inadequate reactive power supply lowers voltage; as voltage drops, current must increase to main-
tain the power supplied to the loads, hence causing the lines to consume more reactive power and
the voltage to drop further. Moreover, if current increases too much, transmission lines will trip,
overloading other lines and eventually causing cascading failures. If voltage drops too low, some
generators will automatically disconnect to protect themselves. Voltage collapse occurs when an
increase in load or loss of generation or transmission facilities causes dropping voltage, which leads
to a further reduction in reactive power from capacitors and line charging, and still further voltage
reductions. If the declines continue, these voltage reductions cause additional elements to trip,
leading to further reduction in voltage and loss of load. The result is a progressive and uncontrol-
lable decline in voltage, because the power system is unable to provide the reactive power required
to supply the reactive power demand.
Insu�cient reactive power at key locations in the system can also result in the inability to transfer
active power beyond a level that is often well below other system limits. As regards this issue, in
order to ensure a secure power system operation, the System Operator has to check the technical
feasibility of potential transactions resulting from energy market clearing; only the transactions
that are within the grid transfer capabilities are allowed. This is particularly important since
currently, electricity markets are usually operated under stressed loading conditions due to the
increased demand and power transfers, so increasing the risk of stability problems. Under such
conditions, system stability limits can be approximated through voltage stability limits.
Finally, reactive power is not only necessary to operate the transmission system reliably, but it can
also substantially improve the e�ciency with which real power is delivered to customers. Increasing
reactive power production at certain locations (usually near a load center) can sometimes alleviate
transmission constraints and allow cheaper real power to be delivered into a load pocket [43].
3.2.3 Reactive power and blackouts
Insu�cient reactive power supply can result in voltage collapse, which has been one of the reasons
for some major blackouts worldwide.
Voltage collapse occurred in the United States in the blackouts of July 2, 1996, and August 10,
1996, on the West Coast. Voltage collapse also factored in the blackouts of December 19, 1978,
in France; July 23, 1987, in Tokyo; March 13, 1989, in Québec; August 28, 2003, in London;
September 23, 2003, in Sweden and Denmark; September 28, 2003, in Italy [43].
While the August 2003 blackout in the United States and Canada was not due to a voltage collapse
as that term has been traditionally used, the �nal report of the U.S.-Canada Power System Outage
Task Force said that �insu�cient reactive power was an issue in the blackout�: dynamic capacitive
reactive power supplies were exhausted in the period leading up to the blackout. The Task Force
also recommended strengthening the reactive power and voltage control practices in all NERC
Regions [44].
CHAPTER 3. REACTIVE POWER SERVICE 99
3.3 Reactive power support as ancillary service
As explained in the preceding section, reactive power needs to be managed in a way to ensure
su�cient amounts are produced to meet demand and so that the electric power system can operate
e�ciently. If reactive power is not properly managed, signi�cant problems such as abnormal
voltages and system instability can occur. Appropriate regulatory policies are thus necessary to
ensure an adequate supply of reactive power at reasonable cost. The rules for procuring reactive
power can a�ect whether adequate reactive power supply is available, as well as whether the supply
is procured e�ciently from the most reliable and lowest-cost sources.
In the past vertically integrated framework, the reactive power management had three main ob-
jectives: maintaining a proper voltage level throughout the network under both normal and post-
contingency operating conditions, minimizing the real power losses, and reducing the risk of current
and voltage violations. In this environment both investment and operation costs regarding reactive
power management were included in transmission and ditribution tari�s and then charged to end
users. The precise knowledge of the power system status and in particular of the generators' avail-
ability allowed the vertically integrated utilities to take the optimal management decisions and to
ful�l all operating requirements. Moreover, the planning and development of reactive resources
were related to that concerning the active ones in the medium-long term.
The restructuring of the electricity industry makes it necessary to revise, from both technical
and economic viewpoint, the methodologies adopted for power system planning, operation, and
control. As regards reactive power service, the general guidelines are still substantially good, while
the provision mechanisms by the System Operators may change.
Currently, most System Operators procure reactive power services from available providers based
on operational experience and expected voltage problems in the system. In real-time, most System
Operators use power �ow programs to dispatch reactive power from the already contracted gen-
erators. There are however several issues and concerns associated with the current procurement
practices and pricing policies for reactive power which call for further systematic procedures to
have more e�cient service management and su�cient reactive power support for a more reliable
power system. Some of these issues are technical limitations associated with power system opera-
tion, while others are policy issues related to the rules under which the electricity market operates
in a certain jurisdiction. These issues have to be carefully examined in de�ning correct provision
and remuneration mechanisms. New policy solutions need to be proposed that �t into the new
shift of paradigm of power system operation. In a competitive electricity market, the objective of
the System Operator should be to provide reactive power ancillary services from possible service
providers at the least cost, while ensuring a secure operation of the power system. Appropriate
pricing structures and payment mechanisms are necessary to achieve such an objective.
An overview of the main general issues related to the procurement and management of reactive
power and voltage support services is proposed in the following subsections [43].
3.3.1 Technical issues
Technical issues include the following:
� The high losses associated with transferring reactive power require that it should be provided
locally. The reactive power procurement therefore depends on the availability of local reactive
power sources. This may result in fewer suppliers generally available to provide the reactive
CHAPTER 3. REACTIVE POWER SERVICE 100
power needed at any individual location. These suppliers are likely to have signi�cant market
power. Moreover, such characteristics imply that reactive power cannot be treated as a
commodity of the same type as real power.
� The value of 1 Mvar support with respect to voltage control and system security varies across
the system. The bene�ts of reactive power from generators, with respect to system security,
have to be considered in the provision of reactive power.
� It is necessary to consider the e�ect of reactive power production of a synchronous genera-
tor on its real power generation. In particular situations reactive power requirements from
a generator can only be met at the cost of reducing its real power output (the so called
opportunity costs1).
� Spot energy market prices are volatile, and they a�ect reactive power prices. This will be a
signi�cant issue if reactive power is managed in the same time frame of real power, since in
this case reactive power prices will be highly a�ected by the energy market prices.
� There are two ways of providing reactive power service: short-term dispatch versus long-term
procurement. If reactive power is provided based on a short-term dispatch, several issues such
as energy market price volatility and the e�ect of reactive power on real power and system
security will arise. On the other hand, long-term procurement can solve most of these issues,
but it does not consider real-time operating conditions.
3.3.2 Policy issues
Policy issues include the following:
� Optimal procurement of reactive power is not always achieved since the System Operators
do not always purchase reactive power at least-cost. In a competitive market environment,
reactive power services should be e�ciently provided from the most reliable and lowest-cost
sources.
� Reactive power ancillary services are not provided by considering all available sources; only
reactive power from generators is considered as an ancillary service and is eligible for �nancial
compensation. This decreases competition due to a lower number of market participants, and
allows the market power to be exercised by certain service providers.
� Poor �nancial incentive and discriminatory payments may result in generators not being
equally compensated. Unless reactive power suppliers are encouraged to participate in fair
agreements, they will not be willing to provide these services. This may impede adequate
and su�cient provision of reactive power support, and it may result in limited number of
service providers, leading to an ine�cient market operation.
1A generator's capacity constraint, which is usually called the loading capability diagram (see Appendix E), playsan important role in calculating its opportunity cost. The capacity constraint is the restriction on the operation ofa generator, which is limited by the synchronous generator armature current limit, the �eld current limit, and theunderexcitation limit. Because of these limits, the production of reactive power may prevent some other alternativecapacity usages. The highest value of the alternative capacity usage is de�ned as the opportunity cost of reactivepower. Assume that the capacity of a generator is used only for producing P and Q and the markets for buying andselling P and Q are always available. According to the de�nition of opportunity cost, the value of the alternativecapacity usage for Q is the pro�t of P that can not be achieved by producing Q [45].
CHAPTER 3. REACTIVE POWER SERVICE 101
� There is a lack of transparency and consistency in planning and procurement process for
reactive power services. This may result in an ine�cient supply of reactive power support,
since reactive power needs and reserves are not clearly de�ned by existing standards.
� Interconnecting standards are assumed to be insensitive to local needs, i. e. without consid-
ering that reactive power needs may vary from one location to another.
3.3.3 A challenge for System Operator and Regulatory Authority
3.3.3.1 Optimal provision for reactive power service
As already explained, in a liberalised electricity market framework the System Operator has to
ensure the same standards of quality and security guaranteed by the past vertically integrated
utilities, but it may have di�culties in meeting these requirements because electricity generation
and distribution do not fall under its competence any longer. This situation is even more compli-
cated with regard to voltage control, considering the di�culties of reactive power to be conveyed
over long distances, the variety of resources and equipments that can be exploited to provide the
reactive power service,2 and the resulting di�culties of their well-coordinated management.
Reactive power provision by the System Operator should be achieved in an optimal manner, and
the choice of an appropriate optimization criterion is essential for the development of competitive
reactive power provision mechanisms. But: what is the best optimization criterion to be adopted
by the System Operator? What is the optimization objective to determine the system reactive
power schedules? Should it be system loss minimization, as has been the usual practice, or should
it be system security maximization or reactive power cost minimization?
3.3.3.2 The e�ect of reactive power on real power and system security
The main function of a synchronous generator is to generate real power to meet the system demand.
Under critical conditions, the System Operator may request or instruct a generator to increase its
reactive power output, which may require a reduction in its real power production. The reactive
power capacity of a synchronous generator is determined by its capability curve, representing its
ability to simultaneously produce real power and generate/absorb reactive power (Figure 3.1).
The boundary of the feasible operating region of the generator is formed by the intersection of
four physical limiting relationships: the minimum loading, the �eld current (�eld heating limit),
the armature current (armature heating limit), and the under-excitation of the generator (under-
excitation limit) [46].
A possible partitioning of the area contained by the generator capability curve into three regions to
represent speci�c operation regimes of the generator has been proposed in [47]. The three-region
model consists of:
1. the obligation to serve region within the capability curve area delimited by the regulatorily
mandated constraints, such as lead/lag power factor or reactive power limits, under which
service is provided;
2. the boundary region speci�ed by the capability curve with the operation of the generator at
its reactive power limits;
2See Appendix E.
CHAPTER 3. REACTIVE POWER SERVICE 102
Figure 3.1: Example of a synchronous generator loading capability diagram
3. the remaining region in the area contained by the capability curve and not belonging to either
of the two regions above.
Operation in the obligation to serve region is not eligible for any additional payment. The operation
in the boundary region may receive payment to compensate for the reduction in the real power
generation so as to allow the required change in the reactive power. Such a change incurs a
loss of opportunity to generate real power and should be, therefore, eligible for opportunity cost
payments for this loss [48]. So any reactive power generation requested by the System Operator
in the boundary region will require a decrease in the real power generation from the already
dispatched levels. Such an e�ect on real power dispatch should be considered when modeling the
reactive power dispatch problem.
The re-scheduling in real power generation associated with an increase in the reactive power re-
quirements may result in an insecure operation of the power system. Hence, the System Operator
needs to check the technical feasibility of the resulting solution after reactive power dispatch pro-
cedures are completed. Therefore, in order to ensure a reliable and secure system operation, it is
important to incorporate system security in the reactive power provision procedures by including
appropriate transmission security constraints, and to consider the e�ect of reactive power dis-
patch on real power dispatch and system security. Transmission security constraints are typically
represented by voltage, thermal, and stability limits.
CHAPTER 3. REACTIVE POWER SERVICE 103
3.3.3.3 Reactive power management: dispatch versus procurement
Reactive power provision can possibly be managed as a short-term provision in which it is dis-
patched from available generators based on real-time system operating conditions. It may be also
managed as a seasonal provision in which it is procured based on long-term agreements between
the System Operator and the service providers. If reactive power is managed concurrently with
the energy market clearing process, some problems may arise such as price volatility and the e�ect
of reactive power on real power and system security.
Currently, most System Operators sign long-term contracts with reactive power service providers,
based on operational experience and knowledge of the system and the expected voltage problems.
In real-time, most System Operators run power �ow programs to determine the required reactive
power dispatch levels from contracted providers. The System Operator has to check if the solution
of the power �ow is not violating any of the security limits. In the case when generators are
operating in the opportunity region, where they are required to back-up their real power generation
to meet the reactive power requirements, the System Operator needs to check if the resulting
operating point after re-scheduling of real power is secure or not.
3.3.3.4 Reactive power remuneration schemes
In a competitive market environment, if reactive power service providers are not properly compen-
sated for their service, they will not have enough incentive to provide the required reactive power
support, which will a�ect the power system operation and security. An important issue that arises
with regard to reactive power markets is then the choice of an appropriate remuneration mecha-
nism. Should it be a market-based auction mechanism where the suppliers provide their reactive
power bids to the System Operator, which in turn determines the best reactive power price using an
appropriate objective function? If so, should it then be a uniform price market for reactive power
with a single reactive power price for the whole system, or a zonal level reactive power auction
market where the system is divided into zones, and separate reactive power prices are determined
for each zone? Should a Locational Marginal Price (LMP) market, in which reactive power price
varies across each bus, be used? If there is no auction market, then reactive power payments could
be set on a contractual basis, with the System Operator entering into bilateral agreements with
the service providers and signing long-term contracts for the required reactive power services.
3.3.3.5 Energy price volatility
Energy prices can be highly volatile under certain system conditions, such as demand spikes or
outages. In a short-term operational time-frame, volatile energy market conditions might have an
impact on reactive power procurement and dispatch procedures.
3.3.3.6 Reactive market power
One of the primary obstacles to the implementation of a competitive market for reactive power
is the possibility of market power arising because of the limited number of reactive power service
providers at a given location. Furthermore, reactive power is a �local� service, and so it must be
procured and provided as close to the demand buses as possible because of the technical issues
associated with transporting reactive power over long distances. Thus in a reactive power market,
it is plausible that some �well-located� suppliers may try to exercise market power by submitting
CHAPTER 3. REACTIVE POWER SERVICE 104
excessively high price o�ers or by withholding reactive power supply in an attempt to increase the
reactive power market price to their own advantage [49].
3.4 Reactive power management review
Reactive power management and payment mechanisms di�er from one electricity market to an-
other, and no uniform structure or design has yet de�ned. There is no fully developed structure
for competition or pricing of reactive power services in any system. Moreover, there is no uni�ed
framework, universally acceptable, for reactive power management. In some cases the pricing is
based on �xed contractual payments, and in other cases based on gross system usage (embedded
cost), while in other markets there is no mechanism for payments. Even the classi�cation of the
obligatory reactive power requirements does not follow any well-de�ned criterion, apart from the
operator's experience [43].
3.4.1 Reactive power service in di�erent deregulated markets
While in current deregulated power systems, provision of real power is fully competitive, no fully
competitive market-approach to reactive power provision exists. It means that the reactive power
service is based on a regulated provision and not a reactive power.
The System Operator generally �xes mandatory requirements for reactive supply by generators,
which can be summarized as follows:
� the generators shall keep power factor to be equal to a certain value: the mandatory reactive
power production (or consumption) decreases according to the reduction of real power;
� the generators shall deliver (or absorb) at least a minimum amount Qmin of reactive power;
� the generators shall maintain voltage level at delivery points to be equal to a certain value;
� a reactive power thresold is de�ned as a percentage of the maximum producible (or consum-
able) according to the capability curve.
Moreover, if the System Operator needs an additional reactive supply (or consumption) to maintain
the security standards, it can:
� impose the generator to supply (or consume) this additional amount according to its capa-
bility curve, while taking into account and respecting the concept of opportunity cost;
� allow the generator to supply or not this additional amount. In case of participation, an
economic agreement between the System Operator and the producer is stipulated.
3.4.1.1 North America
Currently, according to NERC's Operating Policy 10 [50], only synchronous generators are com-
pensated for reactive power provision.
The New York ISO (NYISO) uses an embedded cost based pricing to compensate generators for
their reactive power services, and it also imposes a penalty for failing to provide reactive power.
Generators are also compensated for their lost opportunity costs if they are required to produce
reactive power by backing down their real power output [51].
CHAPTER 3. REACTIVE POWER SERVICE 105
Such opportunity cost payments also exist in PJM Interconnection [52] and California ISO (CAISO).
Provision of reactive power services in the California system is based on long-term contracts be-
tween CAISO and reliable must-run generators; generators are mandated to provide reactive power
within a power factor range 0.9 lagging to 0.95 leading. Beyond these limits, the generators are
paid for their reactive power including a lost opportunity cost payment [53].
The Independent Electric System Operator (IESO) in Ontario, Canada, requires generators to
operate within a power factor range of 0.9 lagging to 0.95 leading and within a +/-5% range of its
rated terminal voltage. The IESO signs contracts with generators for reactive power support and
voltage control, and generators are paid for the incremental cost of energy loss in the windings due
to the increased reactive power generation. The generators are also paid if they are required to
generate reactive power levels that a�ect their real power dispatch, receiving an opportunity cost
payment at the energy market clearing price for any power not generated [54].
3.4.1.2 Europe
In the United Kingdom, the TSO National Grid Electricity Transmission (NGET) invites half-
yearly tenders for both �obligatory reactive power services� which correspond to the base reactive
power that each generator is required to provide, and �enhanced reactive power services� for gen-
erators with excess reactive power capabilities. There are two payment mechanisms: a default
payment agreement, where both the generator and NGET enter into an agreement for service
provision and payments, and a market-based agreement, where generators submit their reactive
power bids to the NGET [55].
Sweden follows a policy wherein reactive power is supplied by generators on a mandatory basis and
without any �nancial compensation. The goal is to keep reactive power �ow on the transmission
system close to zero, especially at certain interfaces. Some large generators are seldom used for
voltage control and are operated at a constant reactive power output. Hydro and thermal units
are required to maintain a capability to inject reactive power of one third the amount of real power
injection (a power factor of approximately 0.90).
Also in Norway reactive power is provided by generators on a mandatory basis and without any
�nancial compensation: all generators is required to supply reactive power within a power factor
range of 0.93 lagging to 0.98 leading. Additional reactive power supply is individually imposed to
generators. The remuneration of these additional provisions is yearly negotiated by the System
Operator and the producers' representatives.
In the Netherlands, individual network companies have to provide for their own reactive power,
usually through bilateral contracts with local generators, who are only paid for the reactive capacity
but not for reactive energy [56].
In Spain the voltage regulation service is provided by both generators (with a net power higher
than 30 MW) and consumers (> 15 MW). There are a compulsory service, which has not any
�nancial compensation, and an optional one. As regards generators, they must have a minimum
margin of reactive power at cosφ = 0.989 (both lagging and leading), equal to 15% of the maximum
real power of the group. Consumers are required to ful�l some obligations depending on the time
band: they shall consume reactive power with cosφ ≥ 0.95 during peak hours, while they are
not allowed to inject reactive power into the grid during o�-peak hours. Besides the compulsory
service, generators and consumers can o�er additional reactive power resources, that are instead
remunerated [57].
CHAPTER 3. REACTIVE POWER SERVICE 106
3.4.2 Literature on reactive power pricing and management
Traditionally, reactive power dispatch has always been viewed by researchers as a loss minimization
problem, subject to various system constraints such as nodal real and reactive power balance,
bus voltage limits, and power generation limits [58-61]. Another approach has been to dispatch
reactive power with the objective of maximizing the system loadability in order to minimize the
risk of voltage collapse [62, 63]. Furthermore, multi-objective optimization models have also been
proposed for the reactive power dispatch problem. In these models, reactive power is dispatched
to achieve other objectives, in addition to the traditional loss minimization, such as maximizing
voltage stability margin [64], or minimizing the voltage and transformer taps deviation [65].
Researchers have been working at reactive power pricing and management in the context of the
new operating paradigms in competitive electricity markets. Both technical and economic issues
associated with pricing of reactive power, along with its optimal provision, have received signi�cant
attention.
Several approaches have been reported in the literature for identifying and analysing the di�erent
cost components associated with reactive power production from synchronous generators. In [45]
Lamont and Fu have provided a comprehensive analysis of the various economic costs of reactive
support from both generation and transmission sources. The cost of reactive support has been
shared in explicit and implicit costs: the former are related to the capital cost of the facilities
and to the operating cost of production, while the latter refer to the Opportunity Costs (OCs).
Luiz da Silva et al have discussed in [66] the practical issues related to the de�nition of a suitable
cost structure for reactive power production, as well as the development of appropriate payment
mechanisms for reactive power providers. Costs of reactive power production are divided into
�xed capital costs and variable costs. A detailed analysis have been carried out for di�erent
variable costs associated with reactive power production from various sources, including generators,
synchronous compensators, static compensators, and shunts capacitors. The authors have proposed
that payments for generators operating as synchronous compensators should be determined based
on the operating time and real power consumption, rather than on reactive power production
or absorption. They also have argued that certain reactive power sources, such as capacitors
and on-load tap changers, should be considered as part of the transmission network and not
as ancillary services' providers. Gross et al have examined in [48] the variable costs of reactive
power production/absorption by a generator, identifying the most dominant cost component, which
is determined as the foregone pro�t of a generator in the real power market consequent to the
obligation to reduce the real power sales for the provision of additional reactive power.
Reactive power pricing policies have been typically based on power factor penalties. With the de-
velopment of real-time or spot pricing theory, there has been signi�cant interest in their application
in the context of competitive electricity markets.
Baughman and Siddiqi have introduced real-time pricing for reactive power in [67], based on the
hourly marginal costs of providing real and reactive power at a given bus. These marginal costs,
which correspond to the added operating expense incurred by the utility to serve an incremental
demand, are obtained by solving a modi�ed optimal power �ow (OPF) that minimizes the total
generation cost subject to operation constraints that include load �ow equations, real and reactive
generation limits, bus voltage limits, and transmission system limits.
In [68] Hao and Papalexopoulos have presented two pricing methods based on reactive power unit
cost measure. In the �rst structure, reactive power production limits are determined by perfor-
CHAPTER 3. REACTIVE POWER SERVICE 107
mance requirements and standards; in this structure, penalties are proposed for service providers
that violate these performance standards, and credits are given for providing extra reactive power
generation beyond the speci�ed standards. The second structure is based on a local reactive power
concept, where the Indipendent System Operator (ISO) procures reactive power services from gen-
erators based on the cost of their reactive power capacity, and then recovers these payments from
load customers according to their demand.
The model proposed by El-Keib and Ma in [69] is based on the calculation of the Short Run
Marginal Costs (SRMCs) by means of a decoupled OPF algorithm: one related to the real sub-
problem, the other related to the reactive sub-problem. In particular, the reactive power optimisa-
tion provides the calculation of the reactive marginal costs, considering the additional real power
generating cost for an increase of the reactive power demand: in this way, also the synchronous
generators operating inside their capability limits are compensated.
In [70], pertinent to the English market, the authors have presented a method for the simulation
and analysis of the reactive power market based on combined capacity and energy payments.
The authors of [71] have focused on the Spanish electric system. The reactive support is divided
in two di�erent services: the reactive energy market and the reactive capacity market.
All these papers are based on the marginal cost theory, supposing that marginal cost can recover
all the costs involved to produce, transport, and deliver reactive power.
An innovative approach for pricing the reactive power ancillary service is presented in [72]. A two-
step approach is proposed. First of all the TSO determines the marginal bene�t of each reactive bid
from an OPF problem, whose objective is to minimize the system transmission losses subject to the
operational constraints. Then the marginal bene�ts are included in a composite objective function,
the Societal Advantage Function (SAF), together with the price bid o�ers of the producers. The
SAF is maximized, seeking contribution to the system performance (in terms of loss reduction)
from reactive power providers with lowest possible cost.
A �rst attempt to de�ne the impact of the existence of a SVR (Secundary Voltage Regulation)
scheme in the EHV system on the reactive pricing structure can be found in [73].
In [47] Zhong and Bhattacharya set up a market-approach in which generators submit bids for
their reactive support and a uniform market price is determined through an auction. Generators
submit their bid for four di�erent types of capacities, one of which is the operating range where
Lost Opportunity Costs (LOCs) are imposed on the generator and another is for the absorption
component. A market price is then determined for each separate component. A composite objective
function containing three di�erently weighted terms is minimized. The ISO performs his choice
balancing three di�erent objectives: minimum cost of reactive power provision, losses minimization
and minimum deviation from the contracted transactions. This approach has been extended by
Zhong et al in [74] by using the concept of voltage control areas to determine a zonal market price
to reduce the possibilities of market power exploitation by generators with strong market position.
3.4.3 Possible policy solutions
3.4.3.1 Decoupling of real and reactive power
On the basis of the discussions in section 3.3, and in particular considering the problems that
arise when both real and reactive power are simultaneously managed and priced by the System
Operator, a possible solution is to decouple these two markets from each other. Decoupling of real
and reactive power markets is possible by placing them in two entirely di�erent operating time
CHAPTER 3. REACTIVE POWER SERVICE 108
frames. This methodology has been suggested in [69, 75]. Such a decoupling implies that the OPF
problem can be separated into two sub-problems. The real power sub-problem essentially provides
the real power dispatch and prices in real-time based on a cost minimization (or social welfare
maximization) market settlement model. The reactive power sub-problem, operating on di�erent
time frames, provides reactive power contracts, prices, and dispatch levels based on appropriate
optimization criteria.
3.4.3.2 Zonal reactive power management
Given the localized nature of reactive power and the common practices amongst most electric
utilities in regards to splitting the whole system into zones or voltage control areas, zonal reactive
power management and pricing might be an appropriate approach. In the case of a system-wide
uniform price, market ine�ciencies resulting from market power being exercised by some reactive
power service providers, anywhere in the system, will a�ect all other providers in the system.
Zonal reactive power pricing, on the other hand, helps isolate and con�ne any existing market
ine�ciencies within the zone. These market ine�ciencies may arise from some service providers
trying to exercise market power by increasing their reactive power price o�ers. In terms of service
provision, zonal reactive power management allows for having additional reactive power reserves for
each zone; this reserve can be called upon by the System Operator in emergency cases associated
with severe contingencies in the system. In general, zonal reactive power management can be
achieved by splitting the system into di�erent voltage control areas [76].
3.4.3.3 Alternative sources of reactive power supply
One of the main challenges associated with reactive power provision is that, so far, only reactive
power support from synchronous generators has been considered as an ancillary service and eligible
for �nancial compensation. With a more liberal reactive power ancillary service provision struc-
ture, there would be more competition due to an increased number of providers. It is important
to examine how other reactive power providers, such as capacitor banks and FACTS controllers,
could participate in the reactive power ancillary service markets to help develop a fully competitive
reactive power market. This particular issue is not studied in this thesis, since the characteristics of
these reactive power resources make them essentially di�erent from generators; hence, appropriate
policies will be required to determine how these resources can be properly compensated for pro-
viding reactive power as an ancillary service. In this thesis, only reactive power from synchronous
generators is considered as an ancillary service [49].
3.5 Architecture of voltage control system
The architecture of the voltage control system can be fully centralized or decentralized or hier-
archical. Here we will describe in detail only the latter scheme, since it is the voltage regulation
structure set up for the Italian electric system by its past monopolistic utility (ENEL).
3.5.1 Hierarchical voltage control system
The voltage control system can be organized into a three-level hierarchy [77, 78]. In short:
1. Primary voltage and reactive power control level.
CHAPTER 3. REACTIVE POWER SERVICE 109
It consists in automatic actions on individual or a limited number of power system equipment
based upon local measurements. It is a local automatic control that maintains the voltage
at a given bus (at the stator in the case of a generating unit) at its set-point. Automatic
voltage regulators (AVRs) ful�l this task for generating units. Other controllable devices,
such as static voltage compensators, can also participate in this primary control. It faces up
to local perturbations such as short circuits close to generating units. The typical response
time scale is between a few milliseconds up to about one minute.
2. Secondary voltage and reactive power control level.
It consists in coordinated actions of control resources within a de�ned part/area of the power
system aimed at maintaining system security. It is a centralized automatic control that
coordinates the actions of local regulators in order to manage the injection of reactive power
within a regional voltage zone. The typical response time scale is between one minute and
up to a few minutes.
3. Tertiary voltage and reactive power control level.
It consists in coordinated global economy and/or security optimization on utility, pool, or
country levels based upon real-time measurements. The typical response time scale is around
10 minutes or longer.
Hierarchical systems based on network area subdivision and automatic coordination of reactive
power resources were �rst studied in Europe for achieving network voltage control. These innova-
tive solutions, named Coordinated Voltage Regulation (CVR) or Secondary and Tertiary Voltage
Regulations (SVR and TVR), depending on their hierarchical level, have been studied in Italy [79-
81], France [82, 83], Belgium [84, 85], and Spain [86, 87]. Some of them operate in real systems
and are extended at the national level. As a result of changes in the organization of European
utilities and the resulting energy markets' deregulation, hierarchical voltage control systems are
increasingly being appreciated and reinforced. In fact, system operators recognize that SVR and
TVR permit both simpli�cation of automatic control of overall transmission network voltages and
recognition of the contributions of di�erent participants to the voltage ancillary service.
Progress and trends in transmission network voltage control require major development and inno-
vation through use of simple, e�ective, automatic control systems, managed and supervised directly
by system operators. Moreover, because voltage control is prevalently a local problem, potential
solutions must consider automatic coordination of local reactive power resources, primarily those
of generators and compensators but also shunt capacitors and reactors, OLTCs, SVCs, and STAT-
COMs. For this reason, the goals (quality and security improvements in network operation) of
voltage ancillary service can be pursued through a decentralized voltage control system, by in-
troducing local coordination in each area/region of the power system. Such coordination requires
exchange of data and signals between the regional dispatcher and local plants/substations: the
more data are exchanged in real-time, on the basis of power system dynamics, the more the volt-
age control system can improve performance and e�ectiveness. The bene�ts of network voltage
control in terms of grid e�ciency, on the other hand, are more strongly linked with inter-area
coordination, requiring e�ective exchange of data and signals among regional dispatchers and the
central/national system operator. In particular, the exchange of measurements with the neigh-
bouring utilities (e. g. boundary bus voltages and tie-line reactive power �ows), as well as the
coordination of mutual control actions, are very important for reducing system losses. The on-line
CHAPTER 3. REACTIVE POWER SERVICE 110
and real-time monitoring of actual EHV control system performance also represents a challeng-
ing opportunity for indubitable correct recognition of power plants' contributions to the voltage
service, in the framework of energy sector liberalization and ancillary market competition. The
main reasons supporting coordinated �automatic� real-time voltage regulation can therefore be
summarized as follows [88]:
� the quality of power system operation is improved, in terms of reduced variation around the
de�ned voltages pro�le across the overall transmission network;
� the security of power system operation is enhanced, in terms of reactive power reserves kept
available by generating units for dealing with emergency conditions;
� the transfer capability of power system is improved, in terms of increased transmissible real
power levels, with reduced voltage instability and collapse risks;
� the e�ciency of power system operation is enhanced, in terms of minimization of real power
losses, reduction of reactive �ows and better exploitation of reactive resources;
� the controllability and measurability of voltage ancillary service is simpli�ed, in terms of
de�nition of functional requirements and performance monitoring criteria.
3.5.1.1 Basic SVR and TVR concepts
The basic concepts of SVR are summarized to permit understanding of the proposed control
system's structure, performance, and advantages:
� the idea of automatic real-time control of hundreds of transmission bus voltages is too com-
plex, very critical, not reliable, and therefore unrealistic and uneconomical;
� the generating units' reactive power is, obviously, the main resource already available in the
�eld, low-cost, and simple to control for network voltage support;
� a realistic simple voltage control system should consider the dominant buses only (a small
amount), thus allowing a sub-optimal but feasible and reliable control solution;
� in order to easily realize the dominant bus (pilot node) idea we call joint-buses those having
high electrical coupling to form a �control area� with voltages close to each other;
� the control structure, based on the subdivision of the grid into several control areas, auto-
matically and, as much as possible, independently regulates each area pilot node voltage;
� the control resource is essentially based on the reactive powers of the largest generating units
in the area (control plants), which mainly in�uence the local pilot node voltage.
The basic idea of TVR comes from the need to increase the system operating security and e�ciency
through centralized coordination of the decentralized SVR structure:
� the pilot nodes' voltage set-points must be adequately updated and coordinated with slower
dynamics than SVR, considering the actual condition of the overall grid and avoiding useless
and con�icting inter-area control e�orts;
� the pilot nodes' voltage set-points can be computed and updated in real-time, considering
the global control system structure and its real-time measurements;
CHAPTER 3. REACTIVE POWER SERVICE 111
Figure 3.2: Hierarchical structure for transmission network voltage control
� the pilot node' voltage set-points have to be optimized to minimize grid losses while still
preserving control margins.
It is necessary to point out that, notwithstanding the goal of minimizing control system complexity,
the e�ort involved in achieving an e�ective control system is in any case considerable when a large
transmission network is involved, as con�rmed by past experience and existing applications. On
one hand, a new power plant apparatus is needed to control the reactive power production of
generating units, as well as of synchronous compensators, according to the local bus-bar or remote
pilot node voltage regulator and taking into account the instantaneous available capability of
the plant generators. On the other hand, a speci�c regional dispatcher regulator is necessary to
automatically maintain pilot node voltages at their scheduled values, controlling the new power
plant apparatus via rapid telecommunications, turning on/o� reactor banks and shunt capacitors,
and ordering OLTCs and FACTS controller set-points. Lastly, a new voltage and reactive power
optimizing regulator is required at the national/utility control level, to coordinate and update all
the pilot node voltage set-points on-line and in real-time (Figure 3.2) [88].
3.6 Reactive power service in Italy
3.6.1 Current regulatory framework in Italy
This subsection brie�y introduces the current legislative, regulatory, and technical framework with
respect to voltage control and to �reactive requirements� for producers and consumers connected
to the Italian grid. Most relevant regulatory orders and technical standards are mentioned in
Figure 3.3.
According to the grid code [8], conventional (i. e. thermal and hydro) power plants shall be able
to operate at over-excitation power factor 0.85 or 0.9 (the value depends on the size and type
of generator) and at under-excitation power factor 0.95. All generating units connected to the
transmission and sub-transmission grids shall contribute to the primary voltage control, that is,
the machines have an automatic voltage regulator and simply regulate the voltage on the generator
CHAPTER 3. REACTIVE POWER SERVICE 112
Figure 3.3: Italian regulation for voltage control and reactive exchanges
bus-bars.
Generating units below 10 MVA can be allowed to provide �xed power factors. It is envisaged
that, in the future, generators unable to provide primary voltage control will have to pay a fee for
it. A complex secondary voltage regulation, including a regulator of reactive power and voltage in
the power plants and the communication systems with the regional voltage regulator, is installed
on all generators and is coordinated by the Italian National Control Center with the objective of
controlling voltages in some selected network buses (called pilot nodes) based on the de�nition of
network control areas. The choice of generators' participating to SVR depends on their capabilities
and system characteristics.
For generating units connected to medium voltage (MV) grids, the standard of Italian Electrotech-
nical Committee CEI 0-16 [89] states that the reactive injection/withdrawal shall allow to operate
medium and low voltage (LV) grids within their nominal voltage +/- 10%. Therefore it shall
be agreed with the local distribution system operator (DSO) and be ruled within the individual
contract of connection.
For consumers and DSOs, the regulatory order 348/07 (electricity tari� regulation for the period
2008-2011) [90] introduced a mandatory framework for payments related to excess reactive energy
withdrawals. All consumers with contractual power higher than 16.5 kW have to pay in case
their average monthly reactive consumption is higher than 50% of their average monthly active
consumption. In case their power factor is below 0.8 (reactive consumption > 75%), an increase
of payments applies as described in Table 3.1. In case the consumer is equipped with a meter
allowing to read hourly withdrawals, the payments are set to zero in light load hours.
The Italian TSO applies the payments of Table 3.1 in case of excess reactive withdrawals at
the connection points with DSOs (except than in light load hours) and takes into account such
payments for de�ning the remuneration of dispatching resources. Further, according to the grid
CHAPTER 3. REACTIVE POWER SERVICE 113
Table 3.1: Payments by Italian consumers for excess withdrawal of reactive energy
code, the TSO can impose to DSOs the power factor in their connection points for voltage quality
and losses reasons. Similarly, DSOs apply the same payments to interconnected DSOs in case of
excess reactive withdrawals (except than in light load hours). DSOs have to transfer the payments
which they collected from grid users and interconnected DSOs to a fund for promotion of energy
e�ciency measures.
The de�nition of the economic value of payments is based on a Decree of Interministerial Committee
on Prices of December 1993, CIP 15/93 [91]. Before the regulatory order 348/07, the application
of payments for excess reactive withdrawals was optional for DSOs, which however had to take
into account their amounts within the cap for distribution revenues (tari� options were subject
to regulatory approval). In the consultation process towards the third regulatory period 2008-
2011, the Italian Regulatory Authority explicitly stated the objective of encouraging consumers to
prevent signi�cant voltage drops in distribution grids and contribute reducing grid losses by means
of mandatory �reactive payments�. Stakeholders were consulted on the opportunity to introduce
a mandatory scheme and were invited to suggest how to size the economic value of payments. Six
respondents out of six agreed with the opportunity to implement a mandatory framework, whereas
there was less consensus on the de�nition of values. Indeed, one respondent suggested to use
the values de�ned by CIP 15/93, one respondent to slightly modify CIP 15/93 values for sake of
simplicity, one respondent to have increasing payments for lower power factors, one respondent to
consider incentive possibilities for consumers with their power factor signi�cantly higher than 0.9,
one respondent to size the payment referring to capital expenditures for compensating equipment,
taking into account a proper pay-back period [92]. The Italian Regulatory Authority started, with
the regulatory order Electricity 48/09 issued in April 2009, the process to review regulation of
reactive energy transits in transmission and distribution grids.
The ultimate aspect related to reactive energy injections and withdrawals is the voltage pro�le
in electricity grids, i. e. the magnitude of voltage provided to customers at all voltage levels. In
Europe, the most important standard regarding voltage characteristics of electricity supplied by
public distribution networks is EN 50160 issued by CENELEC (Comité Européen de Normalisation
Électrotechnique) [93]. It de�nes, describes, and speci�es the main characteristics of the voltage
at a network user's supply terminals in networks below 35 kV. As for supply voltage variation
limits, EN 50160 states that under normal operating conditions, during each period of one week,
95% of the 10 minutes root mean square values of the supply voltage shall be within the range of
contractual voltage +/- 10%. EN 50160 is currently under revision after three years of cooperation
between CEER (Council of European Energy Regulators) and CENELEC. In Italy, minimum and
maximum voltages for transmission and sub-transmission are de�ned yearly, according to provisions
in the quality chapter of grid code. For 380 kV nominal voltage, they are 375 kV-415 kV to be
CHAPTER 3. REACTIVE POWER SERVICE 114
ful�lled 95% of time and 360 kV-420 kV to be ful�lled 100% of time in normal and alert security
state. Further, the Italian Regulatory Authority introduced by its order 333/07 (electricity quality
regulation for the period 2008-2011) a guaranteed quality standard for checking voltage magnitude
and supply voltage variations by the involved DSO upon request of a LV or MV grid user.
3.6.2 Reactive power service by generators
In the Italian power system in the '80s ENEL, the state-owned vertically integrated utility in force
up to 1999, set up a hierarchical structure for network voltage control [79], which is presently
updated, enlarged, and managed by TERNA, the current Italian Transmission System Operator.
According to this, the grid code [8] de�nes two di�erent reactive power services, as anticipated in
the preceding subsection:
1. reactive resources for Primary Voltage Regulation (PVR);
2. reactive resources for Secondary Voltage Regulation (SVR).
The reactive power support for primary voltage regulation is divided into:
� reactive power reserve for primary voltage control of the single generation unit:
it consists in controlling the reactive power production of a generation unit by an automatic
regulation device (AVR - Automatic Voltage Regulator3) capable of modulating the reactive
power delivered by the group considering the variation of the voltage magnitude at its ter-
minals with respect to a certain reference value. Only generating units below 10 MVA can
be allowed to provide �xed reactive power amounts or power factors, subject to the TSO
agreement.
� reactive power reserve for primary voltage control on the high-side bus-bar of a power plant:
it consists in subjecting the reactive power production of all groups in a power plant to
an automatic regulation device (power plant voltage and reactive power regulator4) that is
able to modulate the reactive power delivered by each generation unit based on the voltage
variations on the high-side bus-bar of the power plant with respect to a suitable daily voltage
trend or an operator-de�ned set-point. All power plants with at least one generating unit
above 100 MVA are required to provide this service.
The primary voltage control is a mandatory service, without any �nancial compensation.
The reactive power support for secondary voltage regulation consists in controlling the reactive
power production of all groups in a power plant by a centralized automatic regulation device
capable of modulating the reactive power delivered by each generating unit based on the voltage
variations at some buses selected by the TSO and called pilot nodes. The reactive power regulation
is made according to the reactive level received by a Regional Voltage Regulator (RVR).5
The secondary voltage regulation is now a voluntary service. Therefore, it is important to analyse
possible rules and �nancial compensations related to such voltage regulation service, as well as
their consequences on the performances provided by this structure in a deregulated market.
3In Italian it is called RAT - Regolatore Automatico di Tensione.4In Italian it is called SART - Sistema Automatico per la Regolazione della Tensione di centrale. It can operate
in two di�erent control modes: local operation for primary voltage control on the high-side bus-bar of a power plant,and telecontrol for secondary voltage regulation.
5In Italian it is called RRT - Regolatore Regionale di Tensione.
CHAPTER 3. REACTIVE POWER SERVICE 115
3.6.3 The Italian network voltage control system
The Italian hierarchical voltage control system regulates the voltages of the main EHV buses (pilot
nodes) in a closed loop through real-time control of the reactive resources which most in�uence
these buses. This permits secure transmission network operation, very close to the highest voltage
limits, through rapid control of the main generators (control plants), coordinated by a reactive
power level within the same grid portion (control area) and automatically forced to their limits
only when needed. The Regional Voltage Regulators (RVRs) close the control loops of the pilot
node voltages, providing each area with a speci�c reactive power level which controls the local
power plants' voltage and reactive power regulators (named SART). In turn, the SART closes the
reactive power control loops of the plant units, directly acting on the set-points of the generators'
automatic voltage regulators (AVRs). RVR also controls capacitor banks, shunt reactors, OLTCs,
and SVCs to avoid saturation of area generators. AVR rapid control is referred to as Primary
Voltage Regulation (PVR). The combination of SART [94] and RVR [95] implements the SVR. At
the highest hierarchical control level, a Tertiary Voltage Regulator (TVR) coordinates the RVRs
in a real-time closed loop.
It establishes, on the basis of the actual �eld measurements, the current pilot node voltages which
achieve the minimum feasible grid losses, by slow RVR set-point correction, keeping the system
under control at all times. To achieve this aim, an Optimal Reactive Power Flow (ORPF) for Losses
Minimization Control (LMC) computes, in short (the day ahead) or very short (minutes ahead)
terms, the forecasted optimal voltages and reactive levels, starting from the foreseen/current state
estimation. TVR therefore minimizes the di�erences between the actual �eld measurements and
the optimal forecasted references. This computed �compromise� represents the maximum tenable
voltages plan at any instant. The combination of TVR [96, 97] and LMC [98, 99] forms the National
Voltage Regulator (NVR), which so links ORPF forecasting with real-time optimization of SVR
set-points.
The hierarchical voltage control system has di�erent operation modes, according to its implemen-
tation progresses, maintenance interventions and transient or persistent failures:
� without plant telecommunications, or when the RVR is not operating, SART automatically
regulates the local EHV bus voltage (high-side voltage regulation), according to de�ned
daily trends or the plant operator's voltage set-points, agreed by phone with the regional
dispatcher;
� without system operator's telecommunications or when TVR is not operating, the RVR
autonomously regulates the pilot node voltages of its controlled areas, according to stored
daily trends or the regional dispatcher's chosen set-points, agreed by phone coordination with
national control center;
� when the LMC is not operating, the TVR autonomously coordinates the RVRs, assuming,
as a reference for the optimization of pilot node voltages and reactive power margins, the
available long term forecasted optimal plan or the national control center operator's manual
reference.
The following subsection will consider one of the basic issues for designing the voltage control
system. Other technical characteristics are described in detail in Appendix E.
CHAPTER 3. REACTIVE POWER SERVICE 116
3.6.3.1 Selection of pilot nodes, control areas, and control plants
The three hierarchical levels consist of overlapped closed-loop controls, whose coordination in space
and time requires a careful design of their stability and dynamics to achieve adequate performance
even when faced with contingencies. The design starting point requires proper subdivision of the
overall grid into control areas around the selected pilot nodes, and correct choice of the most
appropriate control plants.
The selection of pilot nodes is based on the intuitive idea that such buses must be chosen among
the strongest ones, able to impose voltages on the other electrically close buses. The design crite-
ria, based on short-circuit capacities and sensitivity matrix computations, also requires electrical
coupling between pilot nodes to be su�ciently low to avoid possible problems of dynamic inter-
action between secondary control loops. With this constraint, in fact, excessive reactive power
exchanges among adjacent control areas, determined by even slight di�erences between the pilot
node voltages imposed by the regulating system, are basically prevented. If network operational
requirements condition pilot node selection by determining excessive electrical coupling between
control areas, the secondary control law should de-couple the dynamic interactions between con-
trol loops. The analytic procedure of selection of pilot nodes consists of a successive re-ordering
of the sensitivity matrix, expressing the dependence of the grid bus voltages on reactive power
injections, with primary voltage regulation operating. The method assumes the load or generation
bus, having the strongest short-circuit capacity, as the �pilot node 1�. All buses with the highest
coupling coe�cient with �pilot node 1� are assumed belonging to �control area 1� and excluded
from subsequent pilot node choices. This procedure, progressively applied, identi�es the other
pilot nodes which are the strongest of the remaining buses and therefore gradually weaker, until
the procedure stops due to insu�cient short-circuit capacity.
The choice of control plants is based on the simple criterion that they must operate in the control
area and have the largest reactive power capability and the highest electrical coupling with the
selected pilot node. Selection of control plants also permits advance recognition of control areas
with consistent reactive power resources, as well as those where the reactive power reserves are
critical and pilot node voltage regulation could more easily reach saturation. The analytic proce-
dure for the choice of control plants requires successive re-organization of the sensitivity matrix,
expressing the dependence of the pilot node voltages on the reactive power injections by generators.
The method assumes all the generators belonging to the �control area i� and having their highest
coe�cient placed in the �pilot node i� row, as potential �control plants i�. All potential plants
with the highest product of sensitivity coe�cient by rated reactive power capability are de�nitely
assumed as �control plant i�.
These simple methods are not computationally heavy and give satisfactory results, once some
threshold values have been re�ned, taking particular network characteristics into account.
For instance, accepting a higher electrical coupling increases the number of pilot nodes but also
requires more complex control laws to deal with closed-loop interaction and dynamic instability
risks. Moreover, frequent re-selection of pilot nodes, even in the case of small network changes, is
required. On the contrary, excessively low electrical coupling reduces the number of pilot nodes
and signi�cantly de-couples their control loops, but at the same time worsens voltage quality.
Similarly, accepting excessively low products of sensitivity coe�cients by rated reactive powers
increases the number of control plants and the corresponding reserve margins, but could require
more unnecessary control infrastructures to permit the participation and coordination of small
CHAPTER 3. REACTIVE POWER SERVICE 117
generators.
The subdivision of the whole system into control areas must be robust and conservative, to prevent
control system recon�guration from becoming too frequent in response to minor network changes.
Relevant structural changes, however, must be analysed to determine their impact on pilot nodes,
control areas and control plant selection, and to adequately re-tune regulation parameters [88].
3.7 Optimal Reactive Power Flow program
As explained in the preceding subsection, the optimal voltage pro�les are determined by an Optimal
Reactive Power Flow program [96]. The ORPF mathematical model is compact reduced:
minF (u) (3.1)
subject to
Xmin ≤ X (u) ≤ Xmax (3.2)
umin ≤ u ≤ umax (3.3)
where u = [vg, qg, rt, qb] is the vector of the reactive control variables and X = [V, Qg] is the
dependent variable vector.
The reactive control variables, on which the optimization algorithm acts, are:
� terminal voltages of the control generation buses that are reactive slack buses, i. e. P-V and
θ-V buses (vg);
� reactive power injections (or withdrawals, if under-excited) by control generators at P-Q
buses or at θ-Q bus6 (qg);
� transformation ratios of OLTC transformers (rt);
� reactive power injections by compensation devices (qb).
The dependent variables, whose values are determined by a load-�ow calculation, after solving the
optimization problem and �nding the optimal values of the control variables, are:
� voltages at P-Q or θ-Q buses, including the so called �sentinel buses�, that are load buses
where it is important to maintain an appropriate voltage pro�le since they characterize the
voltage pro�le of the EHV network7 (V );
� reactive power injections (or withdrawals) by control P-V or θ-V generators (Qg).
The constraints (3.2)-(3.3) represent the technical and operational limitations. Xmin, Xmax, umin,
umax are the lower and upper bounds of dependent and control variables. The dependent variables
X are expressed as linear functions of the control variables u by means of sensitivity relations.
The control variables u have to comply with some technical constraints, including:
� the minimum and maximum voltages of control P-V or θ-V generators;
6This case is uncommon because the real slack bus is usually also a reactive one.7If the operational limits are ful�lled by the �sentinel buses�, also the other load nodes will comply with them.
CHAPTER 3. REACTIVE POWER SERVICE 118
� the minimum and maximum reactive power injections (or withdrawals) by control P-Q or
θ-Q generators, within their capability limits;
� the minimum and maximum transformation ratios of OLTC transformers;
� the maximum reactive power injections by compensation devices.
The dependant variables X have to satisfy some functional constraints, including:
� the minimum and maximum reactive power injections by control P-V or θ-V generators,
within their capability limits;
� the minimum and maximum voltages at P-Q or θ-Q buses;
� the minimum and maximum voltages at sentinel buses;8
� the maximum real power produced by the Q-V bus within its capability limits.
The ORPF program can emphasize the security aspect or the economic one by selecting one of the
following objective functions:
� security: equal distribution of reactive power margins;
� economy: minimum real power losses.
As a usual practice, the second one is considered and in the objective function F (u) a quadratic
function is assumed for the network losses PL (or the real power injection PS by the slack bus).
The introduction of SVR involves the de�nition of:
� pilot nodes of SVR areas (they are of sentinel type);
� generating units belonging to each SVR area;
� alignment constraints for reactive power production by generators of each SVR area.
In each SVR controlled area Ak, the reactive power productions of the Ngk controlling units[qg1 , qg2 , . . . , qgNgk
]must satisfy the alignment constraints (the variable qAk
is the area Ak reactive
level):
qpugj =qgj
qgj max=
QAk
QAk max= qAk
j = 1, . . . , Ngk (3.4)
if the pu level qAkis positive (over-excited area Ak),
qpugj =qgj
qgj min=
QAk
QAk min= qAk
j = 1, . . . , Ngk (3.5)
if the pu level qAkis negative (under-excited area Ak),
where
QAk=
Ngk∑i=1
qgi (3.6)
8The selection of the most signi�cant P-Q buses (sentinel buses) allows functional constraints (3.2) to be stronglyreduced.
CHAPTER 3. REACTIVE POWER SERVICE 119
QAk min=
Ngk∑i=1
qgimin (3.7)
QAk max=
Ngk∑i=1
qgimax(3.8)
are the reactive power production of area Ak and its lower and upper bound.
The variable qAktakes the place of the Ngk reactive productions of the controlling units in the
new formulation of the problem.
If the reactive power �ows between SVR areas (Qrs) are included in the dependent variable vector,
the problem will consider also the functional constraints that they have to satisfy (i. e. minimum
and maximum reactive power �ows between SVR areas).
The ORPF model for the de�nition of the optimal reactive power levels (of each SVR area) and
of all the reactive control variables is given by (Problem P1):
minPS (vg, rt, qA, qg, qb) (3.9)
subject to
Vmin ≤ V (vg, rt, qA, qg, qb) ≤ Vmax (3.10)
Qgmin ≤ Qg (vg, rt, qA, qg, qb) ≤ Qgmax (3.11)
Qrsmin ≤ Qrs (vg, rt, qA, qg, qb) ≤ Qrsmax (3.12)
qpugj = qAkj = 1, . . . , Ngk k = 1, . . . , Nar (3.13)
vgmin ≤ vg ≤ vgmax (3.14)
rtmin ≤ rt ≤ rtmax (3.15)
qAmin ≤ qA ≤ qAmax (3.16)
qgmin ≤ qg ≤ qgmax (3.17)
qbmin ≤ qb ≤ qbmax (3.18)
where qA is the vector of the reactive levels of the Nar SVR controlled areas.
In such a way, the number of the control variables is reduced. The variables vg and qg are pertinent
to the generators not controlled by SVR.
The set of constraints (3.10) contains the limitations on the voltages at P-Q and θ-Q generation
buses (including the generating units belonging to the SVR areas) and at the sentinel buses (in-
CHAPTER 3. REACTIVE POWER SERVICE 120
cluding the pilot nodes). Constraints (3.11) include the capability limits of P-V and θ-V generation
buses; in the adopted model for each bus i these limitations are quadratic functions of Pgi and vgi .
Constraints (3.12) are the limitations on the reactive power interchanges between neighbouring
areas.9 Equalities (3.13) are the area alignment constraints. Finally, constraints (3.14)-(3.18) are
the lower and upper bounds of the control variables.
3.7.1 Compact reduced ORPF model
Starting from a base case solution of the load-�ow equations, the slack power variation ∆PS with
respect to the control variables displacements ∆u is expressed as a second order function of the
variables:
∆PS = ∇PTS ∆u+
1
2∆uTHS∆u (3.19)
where ∇PS and HS are the gradient and the Hessian matrix of PS (u).
The constraints on the dependent variables of the load-�ow equations are linearized at the base
case solution. Therefore the limitations on the voltages at P-Q buses and on the reactive power
productions of P-V buses are expressed by the following linear inequality system:
A∆u ≤ b (3.20)
where A is the sensitivity matrix of the dependent variables with respect to the control variables.
The system (3.20) contains the linearization of the inequality constraints (3.10)-(3.12) and of the
equalities (3.13).
The algorithm used for solving the ORPF problem consists in the iterative solution of quadratic
problems, like the following (Problem P2):
min
(∇PT
S ∆u+1
2∆uTHL∆u
)(3.21)
subject to
A∆u ≤ b (3.22)
∆umin ≤ ∆u ≤ ∆umax (3.23)
HL is the the Hessian matrix of the Lagrangian function of Problem P1. A load-�ow solution
veri�es the satisfaction of constraints (3.10)-(3.12) in P1 and allows the updating of the gradient
vector ∇PS , the matrix of the coe�cients A and the lower and upper bounds of the constraints
in P2.
3.7.2 Reactive power value
The solution of Problem P1 gives the optimal reactive level of each area, the associated pilot
node voltage reference, and the voltage set-points of the other units not operating in the SVR
scheme. Besides the Lagrange Multipliers (LMs) of the equality constraints (3.13) and of the active
inequality constraints (3.10)-(3.12) are available. It is known that the LM gives the variation of the
9This set of constraints is included in the ORPF model only if the secondary voltage regulation operates.
CHAPTER 3. REACTIVE POWER SERVICE 121
objective function when an active constraint experiences a unitary relaxation. The marginal costs
(bene�ts) of the reactive power consumption (production) in the network buses are determined
by a linear combination of the real losses and of the active constraints' sensitivities to the nodal
reactive power injections at the ORPF solution point [100, 101].
The marginal losses' variation consequent to a nodal reactive injection in the bus i is given by:
dPL
dQ=∂PL
∂Qi+
Nar∑k=1
Ngk∑j=1
λAkj∂Qkj
∂Qi+
NQ∑p=1
λV p∂Vp∂Qi
+
NV∑l=1
λQl∂Ql
∂Qi(3.24)
where:
� PL are the real losses in the system (in MW);
� Qi is the reactive power injection at P-Q or θ-Q bus i (in Mvar);
� NQ is the number of P-Q or θ-Q buses in the network;
� NV is the number of P-V or θ-V generation buses in the network;
� λA is the matrix of the LMs of the alignment constraints (3.13);
� λQ are the LMs associated to the NV binding constraints in the inequality set (3.11) (gener-
ators hitting their capability limits);
� λV are the LMs associated to the NQ active constraints in the inequality set (3.10) (voltage
of P-Q buses hitting lower or upper bounds).
Therefore:
� the �rst term is the real losses' variation consequent to a nodal reactive injection Qi in the
bus i (losses' grandient);
� the second term is the real losses' variation consequent to a nodal reactive injection Qi in
the bus i, that would occurr if the alignment equality constraints were relaxed;
� the third term is the real losses' variation consequent to a nodal reactive injection Qi in the
bus i, that would occurr if the constraints on the voltage at P-Q or θ-Q were relaxed;
� the last term is the real losses' variation consequent to a nodal reactive injection Qi in the
bus i, that would occurr if the constraints on the reactive power production/absorption at
P-V or θ-V generation buses were relaxed.
The resulting marginal cost (bene�t) at bus i (in ¿/Mvarh) will depend on the system marginal
price of the electric energy CMWh (¿/MWh):
CMvarhi = CMWh
dPL
dQ(3.25)
In conclusion, this nodal indicator provides the marginal reduction of the hourly cost of real losses
(¿/Mvarh) obtained by the additional injection of 1 Mvar in the selected bus.
The reactive power value in each bus is tightly connected to the technical limitations a�ecting the
system operation and to the operational constraints de�ned by the TSO.
The constraints included in the ORPF program can be classi�ed according to their nature and
to the possibility to be slightly violated (if they are not due to technical or security limitations).
CHAPTER 3. REACTIVE POWER SERVICE 122
The constraints that cannot be violated in any way are de�ned hard constraints. Capability
chart limitations (3.11), depending on the synchronous generator characteristics and on the AVR
design, are hard constraints as well as the alignment constraints (3.13) deriving from SVR. The
limitations on the voltages at the EHV network buses (pilot or sentinel nodes) included in (3.10)
are operational constraints (not necessarily hard) depending on the TSO operational choices and
not strictly related to technical limitations. So they are de�ned soft constraints and their possible
contribution to reactive power marginal value can be disregarded.
3.8 Wind energy exploitation and reactive power support
The voltage control in the network is rendered more di�cult if conventional power stations which
are involved in the voltage control with synchronous generators are replaced by wind energy plants,
and no new devices are provided for reactive power supply.
Wind power plants have in fact certain characteristics that distinguish them from conventional
power generation technologies. Among those, the most impacting reactive power control consider-
ations are [102]:
� Intermittency.
The lack of dispatchability, high variability of power output over time, and lower capacity
factors are in striking contrast with conventional generation sources. Unlike these, the planner
must anticipate that the wind plant may operate anywhere from zero to rated real power
output at any time, without regard to daily or seasonal load patterns.
� Lack of geographic correlation with load.
Another important issue is the low level of geographic correlation between existing transmis-
sion capacity and prime wind resource areas. Consistent high wind speeds are unattractive
for commercial and residential development, so these areas tend to be very sparsely popu-
lated with little electric load. The consequence of this is that, in most cases, wind power
development will occur at weak (i. e. high source impedance) locations in the transmission
network. It follows that these locations would be the most challenging with regard to voltage
regulation and transient stability.
� Asynchronous generation technology.
Up to now, wind turbine generators have, for the most part, utilized asynchronous generator
technology. In the case of variable speed wind turbines, it is able to provide for aerodynamic
e�ciency optimization by adapting the turbine rotor speed to the wind speed. In addition,
it provides for the structural load mitigation necessary to provide acceptable life expectance
in turbulent wind regimes. From a reactive power control standpoint, however, these tech-
nologies perform very di�erently than conventional wound-�eld synchronous generator with
exciters under voltage regulator control.
These three factors frequently create unique local voltage regulation issues not ordinarily encoun-
tered with dispatchable synchronous generating sources.
Initially, wind turbine generators were exempted from contribution to the reactive power. Now
grid codes in an increasing number of contries requires that wind farms take their share in reactive
power balance. The requirements vary from a demand to keep to near zero (unity power factor)
CHAPTER 3. REACTIVE POWER SERVICE 123
to speci�cally de�ned leading and lagging requirements at rated output. The point at which these
requirements are de�ned typically depends on the ownership of the interconnector between the
wind farm and the grid.
The reactive power capability of wind turbines vary widely from that of induction generators
compensated with switched capacitors to generators with full AC/DC converters, with full vector
control, o�ering a variable dynamic response. When available, the capability can be used to control
the reactive power at the terminals of the wind farm, but only at a remote connection point to the
grid if it is electrically very close. Some wind farms operate with secondary voltage control, provided
by a wind farm controller, providing target reactive power set points for individual turbines.
Increased requirements for reactive power controllability will lead to changes in the wind farm
design and/or lead to the application of switched/controlled reactive power compensation. The
application of switched capacitors may have some limitations as capacitor switching tends to have
negative impact on wind turbine gear boxes. Power electronics provide sophisticated means to
dynamically supply reactive power.
It should be noted that the wind generator reactive power control ancillary services may not always
be available as typically wind generators are disconnected when the wind speed is below the cut-
in wind speed. For this reason separate substation based reactive compensation may o�er an
advantage.
Wind farms will typically be connected to the network using one or more radial high-voltage
transmission lines or cables. In the case of AC overhead lines the reactive power characteristics
vary from capacitive to inductive as a function of line loading. In the case of an underground or
undersea AC cable connection, reactive power is supplied to the system and it needs to be absorbed
to avoid overvoltage. For large wind farms planned today, hundreds of kilometres of high-voltage
cables will be connected to the network which will require signi�cant reactive power compensation
installations and will lower the system resonnace frequency. For HVDC connections there are
no reactive power issues between the two terminals, and the reactive power requirements at the
connection point to the grid will typically be determined either by the grid code, or by speci�c
connection agreements [103].
3.8.1 Technical performance requirements for connection of wind farms
In the past, the technical requirements for connecting a generating plant were speci�ed in terms
of large-size synchronous machines due to their exclusive use and dominant impact on the grid.
However, large-scale wind farms are now playing an increasingly important role in many networks,
and their fundamentally di�erent operational characteristics when compared with sinchronous
machines need to be re�ected in modern grid codes. Grid code requirements are tipically neutral
as far as possible, but some have to be speci�c because of the characteristics of wind generation.
A summary of some regulatory requirements with regard to reactive power control in steady-state
conditions for wind plants follows [102].
3.8.1.1 Germany
According to the TransmissionCode 2007 and the subsequent SDLWindV [104, 105], each new
wind energy plant to be connected to the network must meet within the rated operating point the
requirements at the grid connection point according to a variant of Figure 3.4. The transmission
grid operator selects one of the potential variants on the basis of the relevant network requirements.
CHAPTER 3. REACTIVE POWER SERVICE 124
The agreed reactive power range must be able to be completely cycled through within maximum
four minutes and is to be provided at the operating point. Changes to the reactive power speci�ca-
tions within the agreed reactive power range must be possible at all times. The network operator
must specify one of the three variants according to Figure 3.4 by the time of the grid connection
of the wind energy converter on the basis of the relevant network requirements. If the network
operator later requires a variant other than the one agreed, the claim for the system service bonus
will remain una�ected by this.
Apart from the requirements as to the reactive power supply at the rated operating point of the
wind energy plant, there are also requirements concerning operation with an instantaneous real
power, which is less than the operational installed real power. In this case, it must be possible to
operate the wind energy plant at every possible working point in accordance with the generator
output diagram. Figure 3.5 shows the minimum requirement for the reactive power supply from
generating units operating at less than full output at the grid connection point. The highest re-
active power range to be covered and the associated voltage band are indicated in these �gures.
The abscissa indicates the reactive power to be provided in relation to the amount of operational
installed real power in percent. The ordinate indicates the instantaneous real power (in the con-
sumer meter arrow system negative) in relation to the amount of operational installed real power in
percent. Every point within the bordered areas in Figure 3.5 must be able to be started up within
four minutes. The requirement for this can result, depending on the situation, in the network and
denote a supply of reactive power taking priority over the real power output. The operating mode
is coordinated between the operators of the wind energy plant and the operator of the transmission
grid.
3.8.1.2 Spain
Operation of the high voltage transmission system in Spain is under the central control of Red
Eléctrica de España (REE). The Spanish Royal Decree 436/2004, in force till 2007, stated that
the wind plants were not required to participate in steady-state voltage regulation, but were in-
centivized to operate at or above speci�ed power factors by premiums and penalties applied to
the feed-in tari�. A new regulatory system, de�ned in the Spanish Royal Decree 661/2007, has
the aim of further favouring the wind integration in the power system. The incentives/penalties
associated to reactive power service are still e�ective, but now the wind farms above 10 MW may
be required to temporarily change their power factor by the TSO according to necessity.
As incentive to supply reactive power, a bonus or penalty is calculated as a percentage of a reference
tari� which presently has a value of 78.441 ¿/MWh. The percentage rates are shown in Table 3.2.
Alternatively, operators of wind power plants can participate in a reactive power market which,
as of yet, has not been implemented. During peak load, there is an incentive to supply capacitive
power, during o�-peak load there is an incentive to supply inductive power [106].
3.8.1.3 Italy
The Italian Regulatory Authority, with the regulatory order Electricity 98/08 of 25 July 2008 [107],
issued new rules for wind turbine generators (WTGs). It approved a new annex A17 of Italian Grid
Code [108], which requires new WTGs to have the capability to regulate their injection/withdrawal
of reactive power in the range 0.95 inductive power factor - 0.95 capacitive power factor at generator
terminals. The power factor can be kept �xed at a certain value agreed by both the TSO and the
CHAPTER 3. REACTIVE POWER SERVICE 125
Figure 3.4: Minimum requirement for the network-side reactive power supply - Germany
CHAPTER 3. REACTIVE POWER SERVICE 126
Figure 3.5: PQ diagram of the wind energy plant at the grid connection point - Germany
CHAPTER 3. REACTIVE POWER SERVICE 127
Table 3.2: Bonus/penalty for reactive power as percentage of reference tari� - Spain
wind farm's owner.
According to the AEEG Consultation 25/09 [109], the Italian TSO requires to update all pre-
existing WTGs in Southern Italy, Sicily, and Sardinia in order that they have the reactive regulation
capabilities de�ned in Annex A17. This would allow the de�nition - in the future - of reactive power
schedules for WTGs, based on local reactive needs. The Italian Regulatory Authority asked the
TSO to perform a technical survey of existing WTGs, including an estimation of costs for adapting
them to the �reactive requirements� of Annex A17. The resulting technical survey envisages that
costs for �reactive requirements� have an average value of about 5400 ¿ per installed MW.
3.8.2 Technology solutions
A wide range of steady-state and dynamic reactive power control solutions exists for wind plants,
and the proper solution depends not only on the speci�c electrical characteristics of the transmission
system in the area of the plant, but also on the wind turbine generator topology. Most modern
wind turbines utilize one of the three electrical topologies shown in Figure 3.6 [102]:
� line connected induction machines, either cage or wound rotor with slip (rotor resistance)
control (Figure 3.6 A);
� doubly fed induction machines with line connected stators and power converter controlled
rotors (Figure 3.6 B);
� synchronous or induction machines with stators connected through fully rated power con-
verters; induction machines include active recti�ers, while synchronous machines may utilize
either active or passive recti�cation (Figure 3.6 C).
3.8.2.1 WTG based reactive power compensation
The line connected induction machine consumes reactive power for excitation and due to reactive
losses in the stator and rotor winding leakage inductances. Mechanically switched power factor
correction capacitors are frequently applied at the wind turbine terminal to raise the e�ective
CHAPTER 3. REACTIVE POWER SERVICE 128
Figure 3.6: Common WTG electrical topologies
power factor of the machine under steady-state conditions. However, these mechanically switched
capacitors are of limited use in maintaining terminal voltage (and, hence, restraining torque) during
transmission system faults due to the inherent operational delays of the switches.
The doubly fed induction machine has inherent continuously-acting reactive power control capabil-
ity. The rotor side inverter is used to control the �ux producing component of the generator rotor
currents to sink or source reactive power through the stator winding by under or over excitation
of the rotor. When transformed to the rotating reference frame, the rotor currents are DC, and
the machine behaves similar to a conventional wound �eld synchronous machine. A second sink
or source of reactive power is the line-side inverter. The phase angle of the line-side currents with
respect to the line-side voltages is also continuously variable, and the line-side inverter's reactive
power capability remains available even if the wind turbine is not producing real power, e. g. un-
der low wind conditions. Under both steady-state and transient conditions, the reactive current
capability of the wind turbine is limited only by the current ratings of the two inverters.
Likewise, wind turbine generators with full conversion also have inherent continuous-acting reactive
power control capability. The line-side inverter carries the entire real and reactive components of
current, with the desired power factor, under either steady-state or transient conditions, achieved
by commanding appropriate direct and quadrature axis components of line current. Again, the
reactive current capability is limited only by the thermal limits of the power converter or by other
control limits imposed the wind turbine manufacturer [102].
3.8.2.2 External reactive power compensation
For wind plants utilizing turbines without reactive power control capability, or as supplemental
capability where the wind turbines' reactive power capacity is insu�cient to meet steady-state
or dynamic voltage regulation criteria, a number of external solutions are available. For reasons
CHAPTER 3. REACTIVE POWER SERVICE 129
of economy, the external solutions are normally applied at a single location in the wind plant
(typically the medium voltage bus in the plant's collector substation).
The simplest steady-state solutions are combinations of mechanically switched capacitors and reac-
tors. These solutions su�er from a lack of granularity that can only be overcome through reduced
step sizes (increased costs), limited dynamic response due to mechanical switching times, possible
power quality issues due to inrush currents, and signi�cant maintenance costs resulting from the
high number of operations subjected on the switches. Still, where the primary objective of the
reactive power compensation system is to satisfy steady-state voltage regulation concerns, this
remains a viable solution.
3.9 Tests on the Italian EHV network
3.9.1 Main assumptions
Taking into account the objective of assessing simultaneously economy and security, the tests are
carried out on extreme peak load conditions of the Italian EHV system. Economic evaluations
should be intended only to derive locational di�erences of marginal costs of reactive power, as it is
obvious that economic assessments have to be based on several load conditions (in particular, fre-
quent �mid-peak� conditions) or multi-scenario analysis. However, the choice of studying �extreme
peak� is justi�ed by the aim of having a proper assessment of system security under challenging
conditions.
The ORPF procedure is thus applied to a detailed model of the Italian continental electrical system
(380 and 220 kV). A baseline future scenario is de�ned with reference to a peak load condition of
the winter 2014. Fifteen 380 kV wind power collection substations,10 with a total installed capacity
of 5000 MW, are considered in the study [110]: there are nine in Apulia (Troia, S. Severo, Deliceto,
Manfredonia, Cerignola, Spinazzola, Castellaneta, Erchie, and Latiano), two in Campania (Ariano
Irpino and Bisaccia), one in Basilicata (Irsina), and three in Calabria (Carlopoli, Maida, and
Marcedusa). Their geographical location is displayed in Figure 3.7, while Table 3.3 summarizes
their main features:11 the 380 kV lines to which the wind collection substations will be connected
(second column), the amount of the generation capacity installed and connected to each collectors
(third column), and some notes concerning the authorization process (fourth column).
3.9.1.1 Wind power production
Assuming in operation the second 380 kV link between Rizziconi in Calabria and Sorgente in Sicily,
according to the 2010 transmission system development plan, a power exchange of 500 MW from
Calabria to Sicily is supposed, even though actually other values of the exchange (-500 MW, 0 MW)
have been considered and investigated. This choice indeed allows a larger dispatchability of the
wind power generation in Southern Italy.
A traditional SCOPF (Security Constrained Optimal Power Flow), which determines the real power
dispatch at the minimum cost while ful�lling the transmission constraints (i. e. inter-zonal power
limits and current limits on grid branches), is used to estimate the maximum amount of wind
generation consistent with the maintenance of an adequate level of system security. In particular,
10The collector is a 380/150 kV substation which will collect the electric power production by the wind farmsconnected to it.
11All the wind power collection substations, except for Troia, Deliceto, Bisaccia, and Maida, are under authoriza-tion as works related to production initiatives according to the Legislative Decree 387/03.
CHAPTER 3. REACTIVE POWER SERVICE 130
Figure 3.7: Geographic location of the �fteen wind collection substations
Table 3.3: Wind power collection substations
CHAPTER 3. REACTIVE POWER SERVICE 131
Table 3.4: Generation marginal costs of di�erent thermoelectric technologies
Table 3.5: OPF results (maximum wind power generation)
regarding the production costs of the main generation technologies, the ranges in Table 3.4 are
assumed. To simulate the dispatching priority of wind generation, a lower marginal production
cost is considered for this technology so that any wind power curtailment is exclusively due to
binding transmission limits.
In order to estimate the maximum amount of wind generation consistent with the maintenance of
an adequate level of system security, the minimum power that can be produced by some CCGT
plants in Central-South Italy, namely one generating unit of Termoli, Gissi, Modugno, Enipower
Brindisi, Altomonte, Scandale, Simeri Crichi, Rizziconi, and the power plant of Candela, is assumed
to be equal to zero. Therefore, the OPF procedure can exclude them from service and at the
same time allow the wind farms to produce more power. In any case, this assumption takes into
due consideration the need to ensure a su�cient spinning reserve, supposed equal to 50% of the
dispatched wind power, on the thermoelectric units (both coal-�red and CCGT) in service.
The optimization in N-1 security conditions considers the possible outage of the 380 and 220 kV
lines whose trip may lead to exceed the operational limit of at least one grid element with particular
regard to the macro areas Central-South and South.
The OPF results are summarized in Table 3.5 with reference to the maximum amount of wind power
generation that can be produced according to the N and N-1 security criteria. In both cases the
value is lower than the total installed capacity (5000 MW) because of the active network constraints
in the third column. The OPF calculations in N-1 security conditions, that preventively take into
account the possible outage of each of the lines included in the contingency list, make remarkable
changes to the optimal generation schedule in intact system conditions. The active constraints limit
the wind power production which �ows on the 380 kV line Matera-S. So�a, especially between the
future substations of Bisaccia and Avellino Nord.
The baseline scenario is de�ned supposing the real power productions to be �xed and considering
the above OPF results.
3.9.1.2 SVR control areas, pilot nodes, and controlling generators
The selection of SVR control areas, pilot nodes, and controlling generators is made according to
the criteria described in subsection 3.6.3.1.
CHAPTER 3. REACTIVE POWER SERVICE 132
The pilot nodes, whose voltages re�ect the voltage pro�les of neighbouring buses, are suitably
chosen among the sentinel nodes. The selection strategy follows these main requirements [111]:
� generators assigned to a certain area must be capable of highly a�ecting the voltage of the
corresponding pilot node (sensitivity requirement);
� SVR areas should be decoupled as much as possible from the viewpoint of reactive power
support (decoupling requirement);
� reactive power provisions by the controlling generators of a certain area, expressed in p.u.
(the so-called reactive power level), must be as like as possible (alignment requirement).
In order to meet the above conditions, the de�nition of SVR areas is performed by adopting some
speci�c voltage/var sensitivity criteria. Pilot nodes are chosen among the sentinel buses with the
highest short-circuit power. Their selection is based on the sensitivity matrix∣∣∣∂V∂Q ∣∣∣: the lower is
its value, the higher is the short-circuit power.
As regards the sensitivity requirement, the pilot nodes are assumed as P-V buses, while the gener-
ators under SVR are modelled as P-Q ones. For each area k the sensitivity matrix∣∣∣∂QP,k
∂Qj,k
∣∣∣ providesa measure of the e�ectiveness of the remote control action obtained by an additional supply of 1
Mvar by generator j, compared with a possible local control by a SVC (Static Var Compensator)
in the pilot node k: the nearer to unity is this value, the more adequate is the assignment of
generator j to area k.
Taking into account the alignment constraints imposed to the generators included in each SVR
area, the computation of the square matrix∣∣∣ ∂QP,k
∂QA,h
∣∣∣, where QA,h is the reactive power level of
area h, allows the ful�lment of the decoupling constraints to be veri�ed. In a right design of
the SVR areas, the diagonal entries∣∣∣ ∂QP,k
∂QA,k
∣∣∣ should be as nearer as possible to unity, while the
o�-diagonal terms should be as small as possible.
As described in [100, 101, 112], to de�ne a suitable zonal reactive power market, a further re-
quirement should be considered: the marginal values of reactive power produced by generators in
a certain area, calculated by the ORPF, should be similar.
According to these requisites, the Italian continental EHV system is divided into thirteen SVR
areas, as shown in Figure 3.8, where pilot nodes are also highlighted. The controlling generators
assigned to each area are displayed in Figure 3.9 (North Italy: Casanova, Baggio, S. Rocco al
Porto, S. Fiorano, Ostiglia, and Dolo), 3.10 (Adriatic side: Forlì, Villanova, and Brindisi Sud), and
3.11 (Tyrrhenian side: Calenzano, S. Lucia, S. So�a, and Laino).
Other schemes with di�erent SVR areas and/or pilot nodes have been investigated to de�ne the
most appropriate one.
Selection of the pilot node of area 7 (Forlì or Porto Tolle). The pilot node of area 7 is
selected between the buses of Forlì in Emilia Romagna and Porto Tolle in Veneto. The comparison
is made considering the absolute value of the sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ with reference to the controlling
generators in the area (Enipower Ravenna and Porto Corsini). The diagram in Figure 3.12 clearly
shows that the bus of Forlì is the most suitable for being the pilot node of area 7.
Selection of the pilot node of area 8 (Calenzano or Poggio a Caiano). The pilot node
of area 8 is chosen between the buses of Calenzano and Poggio a Caiano, both in Tuscany. The
comparison is made considering the absolute value of the sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ with reference to the
CHAPTER 3. REACTIVE POWER SERVICE 133
Figure 3.8: SVR areas for the Italian EHV system
Figure 3.9: SVR areas and controlling generators - North Italy
CHAPTER 3. REACTIVE POWER SERVICE 134
Figure 3.10: SVR areas and controlling generators - Adriatic side
Figure 3.11: SVR areas and controlling generators - Tyrrhenian side
CHAPTER 3. REACTIVE POWER SERVICE 135
Figure 3.12: Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Choice of the pilot node of SVR area 7
controlling generators in the area (La Spezia, Roselectra, Bargi, and S. Barbara). Since, according
to Figure 3.13, the bus of Bargi St., to which the hydroelectric groups are connected is electrically
closer, to the node of Calenzano, this one is selected as the pilot node in the area.
Selection of the pilot node of area 13 (Laino or Rossano Calabro). The pilot node
of area 13 is chosen between the buses of Laino and Rossano Calabro, both in Calabria. The
comparison is made considering the absolute value of the sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ with reference to
the controlling generators in the area (Altomonte, Scandale, Simeri Crichi, and Rizziconi). The
diagram in Figure 3.14 makes it evident that the bus of Laino is the most suitable for being the
pilot node of area 13, since all the controlling groups are electrically closer to this bus than to the
other.
De�nition of area 3 (pilot node: S. Rocco al Porto). Initially, a scheme, including only
12 SVR areas (i. e. without the area of S. Rocco al Porto), is considered. In this con�guration
the generating units of Piacenza and La Casella are assigned to the area of Baggio. The relevant
sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ are displayed in the diagram of Figure 3.15, which shows that the values
relative to the above-mentioned power plants are the lowest (about half of the sensitivities of the
groups Enipower Ferrera and Turbigo) because of their longer electrical distance from the node of
Baggio and their smaller in�uence on its voltage. These considerations suggest the de�nition of a
new SVR area with the bus of S. Rocco al Porto as pilot node and with the groups of Piacenza
and La Casella as controlling generators. Figure 3.16 con�rms the correctness of this choice.
SVR scheme with 14 areas. The pilot node of area 6 is chosen between the buses of Dolo
in Veneto and Redipuglia in Friuli Venezia Giulia. The computation of the absolute value of the
sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ with reference to the controlling groups in the area (Fusina, Edison Marghera,
CHAPTER 3. REACTIVE POWER SERVICE 136
Figure 3.13: Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Choice of the pilot node of SVR area 8
Figure 3.14: Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Choice of the pilot node of SVR area 13
CHAPTER 3. REACTIVE POWER SERVICE 137
Figure 3.15: Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Area 2 (Baggio)
Figure 3.16: Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Generating units of La Casella and Piacenza
CHAPTER 3. REACTIVE POWER SERVICE 138
Figure 3.17: Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣ - Generating units of Torviscosa and Monfalcone
Torviscosa, and Monfalcone) indicates that the choice of Dolo as pilot node is correct, except for
the generators of Torviscosa and Monfalcone, which are electrically closer to the bus of Redipuglia,
as shown by the diagram in Figure 3.17.
These considerations suggest the de�nition of a new SVR area with the bus of Redipuglia as pilot
node and with the groups of Torviscosa and Monfalcone as controlling generators. But in this
con�guration the decoupling requisite is not ful�lled by the two areas of the northern Adriatic side
(i. e. Dolo and Redipuglia), as shown by the computation of the sensitivity matrix∣∣∣ ∂QP,k
∂QA,h
∣∣∣:∣∣∣∣∂QP,Dolo
∂QA,Dolo
∣∣∣∣ = 0.742Mvar
Mvar
∣∣∣∣ ∂QP,Dolo
∂QA,Redipuglia
∣∣∣∣ = 0.0847Mvar
Mvar∣∣∣ ∂QP,Dolo
∂QA,Redipuglia
∣∣∣∣∣∣ ∂QP,Dolo
∂QA,Dolo
∣∣∣ = 0.11
Ful�lment of decoupling and sensitivity requirements by the adopted SVR scheme.
The ful�lment of the decoupling constraints can be checked by calculating the sensitivity matrix∣∣∣ ∂QP,k
∂QA,h
∣∣∣ (Table 3.6): in a right design of the SVR areas, in fact, the diagonal terms should be as
nearer as possible to unity, while the o�-diagonal ones should be as small as possible.
For further veri�cation of the matrix diagonal-dominance the Euclidean norm ne of the k-th row
vector (k = 1, . . . , Nar) can be calculated and then compared with the in�nity norm ni, i. e. the
diagonal term. The results are summarized in Table 3.7, which highlights the e�ectiveness of the
proposed SVR scheme with the only exception of a weak coupling between the areas of Casanova
and Baggio.
Table 3.8 shows the values of the sensitivity∣∣∣∂QP,k
∂Qj,k
∣∣∣ for all the generators under SVR. It allows
the ful�lment of the sensitivity constraints to be veri�ed: in fact, the nearer to unity is this value,
CHAPTER 3. REACTIVE POWER SERVICE 139
Table 3.6: Sensitivities∣∣∣ ∂QP,k
∂QA,h
∣∣∣ - Decoupling requirement
Table 3.7: Diagonal-dominance of the matrix∣∣∣ ∂QP,k
∂QA,k
∣∣∣
CHAPTER 3. REACTIVE POWER SERVICE 140
Table 3.8: Sensitivities∣∣∣∂QP,k
∂Qj,k
∣∣∣
CHAPTER 3. REACTIVE POWER SERVICE 141
the more adequate is the assignment of generator j to area k. Considering the unhomogeneity of
the indices in certain SVR areas, the generating units with the lowest sensitivities (for example,
the power plant of Ponti sul Mincio in the area of Ostiglia) could be excluded from the secondary
voltage control.
3.9.2 Test cases
The de�nition of the test cases aims at assessing the perspective impact of large wind power
injections on the voltage control performances in the Italian EHV electrical system and the bene�ts
that may be achieved thanks to the network reinforcements included in the development plan,
evaluating the economy and security level achievable in the Italian system at 2014 peak-load under
optimal reactive power schedules.
The test cases are therefore de�ned considering the following aspects:
1. what kind of generators operates under voltage control (synchronous generators and/or wind
farms);
2. planned transmission reinforcements in service or not in service;
3. presence of the wind farms connected to the �fteen collection substations in Table 3.3.
They can be summarized as follows:
1. Case 1: only synchronous generators operating under voltage control-transmission reinforce-
ments in service-wind farms' power factor equal to unity.
2. Case 2: only synchronous generators operating under voltage control-transmission reinforce-
ments not in service-wind farms' power factor equal to unity.
3. Case 3: only synchronous generators operating under voltage control-transmission reinforce-
ments in service-no wind farms.
4. Case 4: synchronous generators and wind farms operating under voltage control-transmission
reinforcements in service.
5. Case 5: synchronous generators and wind farms operating under voltage control-transmission
reinforcements not in service.
All the simulations consider the operation of AVR only and the operation of both AVR and SVR.
Obviously, the use of the ORPF program will also allow the determination of the optimal reac-
tive power schedules that �t the needs of the system operator, and the de�nition of a possible
remuneration scheme for reactive power providers.
3.9.3 Results
3.9.3.1 Test case 1
The test case 1 considers the transmission network reinforced as planned by the Italian TSO for
the year 2014 and a wind farms' power factor equal to 1.
Table 3.9 summarizes some ORPF results for Case 1 for both AVR and SVR: voltage magnitudes
in pilot nodes and the total reactive power production of each area calculated as the ratio between
CHAPTER 3. REACTIVE POWER SERVICE 142
Table 3.9: Pilot node voltages and reactive power productions - Case 1
the actual value Q and the maximum QREF . These results show that the Eastern Adriatic coast,
i. e. areas of Dolo, Forlì, and Villanova, is characterised by a relatively high utilization (0.67-
0.79 p.u.) of its reactive resources, which are however relatively poor compared to other areas,
especially in the area of Forlì and Villanova. In the case of generators under SVR, there is a small
decrease. Voltage values are within their acceptable limits, with minimum voltage 388 kV in S.
So�a (South-West of Italy).
Under primary voltage control, the ORPF procedure, which calculates the optimal voltage refer-
ence for each generation unit while minimizing the real power losses, generally raises the voltage
magnitude at the grid buses with respect to the pre-optimization condition. Nevertheless, the
exploitation of the controlling groups may not be optimal because of their di�erent utilization
and consequently some generators may have very small reactive power margins. In fact, the main
objective of AVR is to raise the voltages as much as possible, thus reducing the real power losses
in the system, by reducing the line currents and by compensating for the reactive losses thanks to
the increase of the reactive production of the line capacitances. Figure 3.18 shows some signi�cant
examples with reference to the areas of Dolo, Forlì, and Villanova.
The additional constraints on the controlling generators under SVR has just the aim of aligning
their reactive power productions with the reactive level of the corresponding area, thus ensuring
the reactive margins being uniformly distributed among the groups. These constraints usually
increase the control capability, so increasing the network security level also in case of disturbances
that may require considerable amounts of reactive power to be available. Therefore, while gen-
erally reducing the real power losses in the system, the Secondary Voltage Regulation primarily
pursues the goal of security maintenance through the ful�lment of the alignment constraints. For
this reason, the voltage magnitudes are usually lower than under AVR only. As shown in Ta-
ble 3.9, the biggest reductions refer to the pilot nodes Dolo (AVR: 401.81 kV; SVR: 395.21 kV)
and Forlì (AVR: 408.10 kV; SVR: 403.02 kV). The Primary Voltage Regulation increases the volt-
ages compared to the pre-optimization condition, but the distribution of the reactive margins
within the above-mentioned areas is quite irregular. The introduction of SVR and especially of
the alignment constraints reduces the voltage in the pilot nodes by about 5-6 kV, while reducing
the total reactive power production and hence increasing the reactive margin with respect to both
the pre-optimization condition and PVR operation only.
CHAPTER 3. REACTIVE POWER SERVICE 143
Figure 3.18: Reactive power margins under AVR control (areas of Dolo, Forlì, and Villanova)
As explained before, though the objective function of the ORPF procedure is the minimization
of the real power losses in the grid, the optimization under SVR has a second goal, that is, the
alignment of the reactive power generations in each control area to increase the system security.
In fact, the real losses amount to 469.37 MW under AVR and 475.74 MW under SVR. Their
variations with respect to the pre-optimization condition are -3.87% and -2.57% respectively.
The results show the bene�ts of determining the reference values for voltage regulators, also under
AVR only, by using an appropriate reactive power optimization procedure. First, the system
operation economy takes advantage from it since it allows the real losses to be reduced. Also the
system security is improved because the voltage magnitudes in the system are usually increased
under both AVR and SVR compared to the pre-optimization condition. This is an important
e�ect above all in the case of particularly stressed operating conditions. Moreover, the outcomes
demonstrate the importance of adopting the Secondary Voltage Regulation since it allows the
reactive resources to be better exploited, increasing the available reactive power margins and
hence the system controllability.
Besides these technical aspects, that are important for the System Operator, another issue, con-
cerning the de�nition of a suitable remuneration scheme for reactive power providers, can be
investigated and a possible solution can be proposed on the basis of the ORPF procedure results.
As described in subsection 3.7.2, the optimization tool calculates an economic indicator that indi-
cates the value of the reactive resources in a node: the nodal marginal value of reactive power. It
is determined by the in�uence of the reactive injection on the real power losses (MW/Mvar) and
their cost (in this study: 100 ¿/MWh) and it is based on the calculation of some sensitivity coef-
�cients that, for a particular system condition, can be given by the ORPF dispatching procedure.
So this nodal indicator provides the marginal reduction of the hourly cost of real losses (¿/Mvarh)
obtained by the additional injection of 1 Mvar in the selected node.
Figures 3.19-3.31 show the nodal marginal values of reactive power in each control area with
CHAPTER 3. REACTIVE POWER SERVICE 144
Figure 3.19: Nodal marginal values of reactive power - Area 1
Figure 3.20: Nodal marginal values of reactive power - Area 2
CHAPTER 3. REACTIVE POWER SERVICE 145
Figure 3.21: Nodal marginal values of reactive power - Area 3
Figure 3.22: Nodal marginal values of reactive power - Area 4
CHAPTER 3. REACTIVE POWER SERVICE 146
Figure 3.23: Nodal marginal values of reactive power - Area 5
Figure 3.24: Nodal marginal values of reactive power - Area 6
CHAPTER 3. REACTIVE POWER SERVICE 147
Figure 3.25: Nodal marginal values of reactive power - Area 7
Figure 3.26: Nodal marginal values of reactive power - Area 8
CHAPTER 3. REACTIVE POWER SERVICE 148
Figure 3.27: Nodal marginal values of reactive power - Area 9
Figure 3.28: Nodal marginal values of reactive power - Area 10
CHAPTER 3. REACTIVE POWER SERVICE 149
Figure 3.29: Nodal marginal values of reactive power - Area 11
Figure 3.30: Nodal marginal values of reactive power - Area 12
CHAPTER 3. REACTIVE POWER SERVICE 150
Figure 3.31: Nodal marginal values of reactive power - Area 13
reference to the pilot nodes12 and the high-voltage bus-bars of the P-Q controlling generators.
These indicators are generally smaller when only AVR operates, while they are usually increased
under SVR because of a larger contribution of the losses' gradient and the presence of the alignment
constraints. Table 3.10 shows the contribute of the losses' gradient and the nodal marginal value
of reactive power in the pilot nodes under both AVR and SVR.
Figures 3.19-3.31 make it evident that the reactive power value is higher in those areas where the
grid is less meshed (for instance, in Southern Italy), the load is big (for example, in the areas of
Baggio, Dolo, and S. So�a), and the reactive resources are poor (for instance, in the areas of Forlì
and Villanova). This means that the adopted methodology is able to evaluate the importance of
the reactive resources for system operating security and above all to introduce di�erentials among
the grid buses according to their location in the network: the more indispensable the reactive
source, the higher its economic value and remuneration.
Apart from a few exceptions, regarding in particular the generators of Ponti sul Mincio in the area
of Ostiglia and Modugno in the area of Brindisi Sud, the nodal marginal value of reactive power in
a pilot node can be assumed as representative of the others. The variability of the nodal marginal
costs is strictly related to the variability of the sensitivity∣∣∣∂QP,k
∂Qj,k
∣∣∣: the greater is the homogeneity of
these sensitivities, that is, the better is the position of the pilot node with respect to its controlling
groups, the smaller is the variability of the nodal marginal values of reactive power.
We can conclude that the adoption of a hierarchical voltage control architecture and especially of
the secondary regulation level can be the basis for implementing a suitable remuneration scheme
for reactive providers, which are compensated for their service according to their position in the
grid. In fact, the subdivision of the network into SVR areas, if appropriately de�ned, can be a good
way to implement a regional (zonal) reactive power market. The selection of the control areas and
of the generators under SVR must thus take into account also the homogeneity among the nodal
12The pilot node in each �gure is labelled with *.
CHAPTER 3. REACTIVE POWER SERVICE 151
Table 3.10: Losses' gradient and nodal marginal value in pilot nodes
Table 3.11: Pilot node voltages and reactive power productions - Case 2
marginal values of reactive power within a certain area.
3.9.3.2 Test case 2
The test case 2 is de�ned as Case 1, except for the assumption that the transmission system has
its present structure. The simulations have in fact the aim of assessing the consequences of a
possible delay in the completion of the grid development plan and thus the bene�ts deriving from
the transmission system reinforcement.
Table 3.11 summarizes some ORPF results for Case 2 for both AVR and SVR: voltage magnitudes
in pilot nodes and the total reactive power production of each area.
In Case 2 there is a signi�cant reduction of reactive power margins in all Central-Southern areas
(Villanova, S. Lucia, Brindisi, S. So�a, and Laino), where the overall increase of reactive injection is
1115 Mvar under AVR and 1088 Mvar under SVR, while it is 1539 Mvar under AVR and 1488 Mvar
under SVR in the whole Italy. Further, there is a signi�cant reduction of voltages in Villanova and
S. So�a, that drop to very low values (Figure 3.32):
� Villanova
396.57 kV → 370.50 kV under AVR only;
CHAPTER 3. REACTIVE POWER SERVICE 152
Figure 3.32: SVR voltage pro�le of pilot nodes - Case 1 and Case 2
393.96 kV → 367.28 kV when also SVR operates.
� S. So�a
388.12 kV → 372.83 kV under AVR only;
388.12 kV → 372.01 kV when also SVR operates.
Indeed, under SVR, saturation of reactive capabilities occur in Villanova control area, causing the
drop of Villanova voltage to 367 kV. Also the reactive margins of the areas of S. Lucia, S. So�a,
and Laino decrease, with a reactive zonal production of about 0.75, 0.70, and 0.79 p.u. respectively
under SVR. Only the area of Brindisi Sud in Southern Italy is not critical, although also its reactive
power production increases: it is in fact �rich� in terms of available reactive resources compared to
its load.
This test case, which refers to a very stressed operating condition, as shown by the low voltage
values in Central-Southern Italy and on the Adriatic side, demonstrates even clearlier the need to
use an ORPF procedure to determine the set-points for voltage regulators. At present the grid in
these areas is poorly meshed and hence the reactive power resources need to be exploited as well
as possible.
Besides these indications about power system management, the results highlight the need for the
completion of the transmission system development planned by the Italian TSO for the year 2014.
In particular, the saturation of reactive resources in Villanova area underlines the importance of
doubling the Adriatic backbone between the substations of Villanova and Foggia. In case of delay in
the authorization and realization of this network upgrade, it would be necessary to install adequate
reactive compensation devices, e. g. capacitor banks, in view of the power system expansion in the
medium term.
Figure 3.33 displays the values of the economic indicator ¿/Mvarh: as already explained, the
greater is the value, the more critical is the corresponding area. Reactive power injections and
CHAPTER 3. REACTIVE POWER SERVICE 153
Figure 3.33: Reactive marginal values in pilot nodes - Case 1 and Case 2
withdrawals in the areas of Villanova, S. So�a, and Laino have the highest marginal costs:
� Case 1
Villanova AVR - SVR: 1.641 - 1.795 ¿/Mvarh;
S. So�a AVR - SVR: 1.376 - 1.776 ¿/Mvarh;
Laino AVR - SVR: 1.286 - 1.614 ¿/Mvarh.
� Case 2
Villanova AVR - SVR: 3.583 - 4.098 ¿/Mvarh;
S. So�a AVR - SVR: 3.110 - 3.509 ¿/Mvarh;
Laino AVR - SVR: 2.716 - 2.975 ¿/Mvarh.
These economic indicators are characterized by signi�cant regional variations, ranging from 0.2
¿/Mvarh in Northern Italy up to 4.1 ¿/Mvarh on the Adriatic side of Central Italy. Moreover,
the economic indicators demonstrate the improvements achievable thanks to the major grid rein-
forcements, as they double in the most critical areas in Case 2 without grid reinforcements.
A map of ¿/Mvarh indicators for the Italian EHV system is shown in Figure 3.34: the highest
values (blue-green coloured regions) refer to Central-South Italy, because of its poorly meshed grid,
if not properly reinforced, and the large-size wind farms that are expected in the medium term
and whose power production is likely to substitute the thermoelectric one. The map con�rms
the considerations at the ending of the preceding paragraph about the possible implementation
of a regional-based reactive power remuneration mechanism: the subdivision in homogeneously
coloured zones respects the division of the Italian EHV system into the SVR areas in Figure 3.8,
so demonstrating the usefulness and the e�ectiveness of the proposed methodology [113].
Since the ¿/Mvarh indicators and hence their graphical representation identify the grid locations
where the reactive resources are more valuable from an economic point of view because of their
CHAPTER 3. REACTIVE POWER SERVICE 154
Figure 3.34: Map of nodal ¿/Mvarh indicators - Case 2
indispensability for power system operation, the information provided by the map can be also used
by the transmission planner to easily identify the poorest grid areas in terms of reactive capability
where additional measures have to be taken to control grid voltages.
3.9.3.3 Test case 3
A third case (named Case 3) is analysed to assess the impact of wind generation on voltage
pro�les and reactive power margins essential to preserve the system security and controllability
in case of contingency. The wind power production is assumed to be zero and it is substituted
by an equivalent amount produced by combined cycle gas turbines (CCGT) in Southern Italy.
Transmission reinforcements are supposed in service.
Table 3.1213 gives the voltage magnitudes in pilot nodes and the total reactive power production
of each area in Mvar and in p.u..
In Case 3 the reactive power margins in Central-Southern Italy are higher than in Case 1 (-
576 Mvar under AVR and -434 Mvar under SVR), especially in Villanova control area, as shown
in Figure 3.35, which displays the Mvar still available in each control area.
Figure 3.36 compares the marginal costs of reactive power in pilot nodes in Case 3 vs. Case 1, while
Figure 3.37 considers the 380 kV wind power collection substations. The presence of wind power
generation with �xed power factor (equal to unity) in Case 1 (and maybe real power re-dispatching
13The reactive power margins in per unit are calculated considering the reference values QREF of the base case(Case 1) to allow the comparison with the other test cases, although the maximum reactive power capabilities inSouthern Italy in Case 3 are higher because the wind farms are substituted in production by thermoelectric unitswhich can participate to reactive power support and voltage control.
CHAPTER 3. REACTIVE POWER SERVICE 155
Table 3.12: Pilot node voltages and reactive power productions - Case 3
Figure 3.35: Reactive power margins in Central-Southern Italy - Case 1 and Case 3
CHAPTER 3. REACTIVE POWER SERVICE 156
Figure 3.36: Reactive marginal values in pilot nodes - Case 1 and Case 3
as well) causes a substantial increase in marginal costs of reactive power in Central-Southern Italy,
especially in the areas of Villanova, S. So�a, and Laino:
� Villanova
0.702 ¿/Mvarh under AVR only;
0.926 ¿/Mvarh when also SVR operates.
� S. So�a
0.784 ¿/Mvarh under AVR only;
1.083 ¿/Mvarh when also SVR operates.
� Laino
0.804 ¿/Mvarh under AVR only;
1.025 ¿/Mvarh when also SVR operates.
The reactive control in the area of Brindisi is less critical than in the areas of Villanova, S. So�a,
and Laino, as witnessed by the nodal marginal costs in its three 380 kV wind power collection
substations (Erchie, Latiano, and Castellaneta), because its reactive resources are greater than
in the neighbouring areas. The nodal marginal cost of reactive power in Castellaneta is higher
than the values in Erchie and Latiano, which are closer to Brindisi large thermoelectric generation
units. Nodal reactive marginal costs in Carlopoli, Maida, and Marcedusa are somewhat lower than
the value in Laino, which is their pilot node. Nodal reactive values in all other wind collection
substations are similar to the value in Villanova. The results of Case 3 show that, even with the
same system and generation external conditions and real power market price (cost of losses), actual
very high or very low production of wind power can lead to signi�cant di�erences of nodal reactive
values in the most critical network areas.
CHAPTER 3. REACTIVE POWER SERVICE 157
Figure 3.37: Reactive marginal values in wind collector substations - Case 1 and Case 3
3.9.3.4 Test cases 4 and 5
Finally, two analyses are performed considering di�erent hypotheses about the �reactive charac-
teristics� of WTGs (capability to control their power factor in the range 0.95 over-excited/0.95
under-excited), according to the provisions of annex A17 of the Italian Grid Code [108]. The pos-
sible participation of WTGs to voltage control, both AVR and - more theoretically - SVR (thanks
to the exploitation of suitable power electronics devices) is studied in Case 4 with all grid reinforce-
ments and in Case 5 without reinforcements. A new control area (area of Foggia) is de�ned and
some wind power generators in Apulia and Campania (Deliceto, S. Severo, Manfredonia, Cerignola,
and Troia) are assigned to it. The others are instead assigned to the areas of Brindisi Sud (Irsina,
Castellaneta, Erchie, and Latiano), S. So�a (Ariano Irpino, Spinazzola, and Bisaccia), and Laino
(Marcedusa, Maida, and Carlopoli).
The additional reactive resource is about 1250 Mvar, according to the allowed power factor range:
0.95 under-excited/0.95 over-excited. The reactive power productions in Central-Southern Italy
in Case 4 are lower than in Case 1 (about -402 Mvar under AVR and -200 Mvar under SVR),
with main changes in Villanova area, while the voltage pro�le does not show signi�cant variations.
As given in Table 3.13, reactive power margins available in the most critical areas improve. In
particular, as regards Villanova area, whose reactive capability is the same of Case 1, its reactive
margin increases:
� under AVR: from 0.21 p.u. in Case 1 to 0.79 p.u. in Case 4;
� under SVR: from 0.24 p.u. in Case 1 to 0.75 p.u. in Case 4.
This reduction is due to the reactive power production by the wind farms' generators belonging
to Foggia control area, which produce about 280 Mvar under AVR operation and nearly 360 Mvar
when also SVR functions.
CHAPTER 3. REACTIVE POWER SERVICE 158
Table 3.13: Pilot node voltages and reactive power productions - Case 4
The bene�ts of WTG participation to voltage control are re�ected by decreasing nodal reactive
values with respect to Case 1:
� Case 1
Villanova AVR - SVR: 1.641 - 1.795 ¿/Mvarh;
S. So�a AVR - SVR: 1.376 - 1.776 ¿/Mvarh;
Laino AVR - SVR: 1.286 - 1.614 ¿/Mvarh.
� Case 4
Villanova AVR - SVR: 1.384 - 1.453 ¿/Mvarh;
S. So�a AVR - SVR: 0.968 - 1.056 ¿/Mvarh;
Laino AVR - SVR: 0.350 - 0.432 ¿/Mvarh.
Figure 3.38 displays the nodal reactive marginal costs in wind collector substations: it con�rms
the overall decrease in reactive power values in Central-Southern Italy thanks to the contribution
of the wind generators to reactive support.
The test case 5 is derived from Case 2 assuming that the wind farms' generators participate to
voltage regulation. Case 2, in which all network upgrades are not supposed in service, represents
a very stressed operating condition from the viewpoint of reactive power provision by the System
Operator, because the reactive resources in some grid areas are not enough to support voltage so
that in some nodes it drops under 370 kV. Also the simulation on Case 5 has the aim of assessing
the possible bene�ts that may derive from the participation of the wind farms to voltage control
and reactive power support. Table 3.14 summarizes some ORPF outcomes.
The comparison between Case 2 (Table 3.9) and Case 5 (Table 3.14) makes it clear that the
contribution of WTGs to voltage regulation can be very important to manage the system with
an adequate security level, particularly in stressed operation conditions. The availability of more
reactive resources in Southern Italy causes a substantial increase in voltage magnitudes in the most
critical areas (Villanova and S. So�a), which are now within the acceptable range (Figure 3.39).
The bene�ts already shown in the preceding test case are very crucial in Case 5. For instance,
as regards Villanova area, its reactive margin increases notably and in particular the new reactive
CHAPTER 3. REACTIVE POWER SERVICE 159
Figure 3.38: Reactive marginal values in wind collector substations - Case 1 and Case 4
Table 3.14: Pilot node voltages and reactive power productions - Case 5
CHAPTER 3. REACTIVE POWER SERVICE 160
Figure 3.39: Voltage pro�le of pilot nodes - Case 2 and Case 5
resources in the neighbouring area of Foggia allow the saturation of the reactive capability in
Villanova area to be avoided:
� under AVR: from 0.07 p.u. in Case 2 to 0.24 p.u. in Case 5;
� under SVR: from saturation in Case 2 to 0.13 p.u. in Case 5.
The highest nodal marginal values change as follows:
� Case 2
Villanova AVR - SVR: 3.583 - 4.098 ¿/Mvarh;
S. So�a AVR - SVR: 3.110 - 3.509 ¿/Mvarh;
Laino AVR - SVR: 2.716 - 2.975 ¿/Mvarh.
� Case 5
Villanova AVR - SVR: 2.909 - 3.254 ¿/Mvarh;
S. So�a AVR - SVR: 2.817 - 3.043 ¿/Mvarh;
Laino AVR - SVR: 2.264 - 2.687 ¿/Mvarh.
3.9.3.5 Real losses' variation
The importance of transmission system development, from both economic and security point of
view, is demonstrated also by real losses' variation in the various test cases, as shown in Table 3.15.
The most favourable scenario is Case 3, i. e. without wind power generation, while Cases 2 and
5 have the highest losses because of the absence of network reinforcements (about 100 MW addi-
tional losses, i. e. 20% of power losses in the grid model under study). Bene�ts can be quanti�ed
multiplying the reduction of real power losses by the price of real power determined by market
CHAPTER 3. REACTIVE POWER SERVICE 161
Table 3.15: Real losses and their variations with reference to Case 3
clearing. In the cases without grid reinforcements, WTG participation to voltage regulation (Case
5) allows a 25 MW decrease of real losses compared to Case 2. The security increase, already
remarked by the comparison of reactive margins Case 4 vs. Case 5, would also reduce the practical
need for constraining on expensive generators in South Italy.
3.10 Chapter conclusions
Liberalised electricity markets consider voltage regulation and reactive power support as an ancil-
lary service. Reactive power is required for transmission of real power, voltage and system control,
and normal operation of power systems. Therefore, reactive power service can be considered one
of the most important ancillary services in electricity market. However, the origin and the main
characteristics of reactive power, �rst of all its very local nature and its highly limited ability to
travel in the network, raise some di�culties in its management in a deregulated environment. The
acquisition and pricing of the reactive power and voltage support services is the major challenge.
In vertically integrated structures, one utility operated power generation units, on the one hand,
and transmission and distribution systems, on the other hand. It also handled the voltage control
issue, both in the short-term (day-to-day dispatch of units) and long-term (system planning). The
cost of this service was implicitly taken into account in the cost of the energy supply for end
consumers.
As a consequence of the restructuring of electric industry and the resulting deintegration of gen-
eration and transmission, the reactive power support and the voltage regulation are no longer an
integral part of the electricity supply. Further, the competition requires that the costs associated
with this ancillary service is made explicit by means of suitable methods. The provision mecha-
nism and above all the tari� structure for reactive power must thus consider the di�erent views of
buyers and sellers. The former, the TSO, tends to give a �societal� evaluation of available reactive
resources based on the expected bene�ts deriving from their utilization. The latter, producers, on
the contrary, aim at the economic compensation in order to recover costs that they incur, while
sometimes forgetting the concept that voltage regulation and reactive power support are essential
system services needed to deliver the real power which they supply to consumers. Main task of
the TSO is to determine the value of the reactive power support required to the generation buses
in order to �t its needs for a secure and e�cient system operation. Also a consistent reactive price
structure for �nancial compensation of reactive power providers needs to be de�ned: the basis for
its implementation can be the estimated values of the reactive support in grid nodes.
Besides the above aspects which derive from the peculiarities of reactive power service and the
restructuring process, among the recent developments that challenge the traditional approach to
voltage control, there is the increasing concern towards wind energy exploitation for generating
CHAPTER 3. REACTIVE POWER SERVICE 162
electricity. An increasing penetration of wind power, normally characterised by limited reactive
support and voltage control capabilities and displacing thermoelectric generation with greater
capabilities, causes a reduction of the reactive resources available in the power system. For this
reason, transmission operators and planners and wind project developers alike are facing increasing
challenges with regard to reactive power control. The economies of scale of larger and larger plants
and increasing development of sites far from load centers are contributing factors. Regulations and
standards in this area are in a state of �ux as a result of the rapid changes in market incentives and
in the wind turbine technology itself. Wind turbine and power system equipment manufacturers
are responding to these challenges by making technical solutions available to the project planner,
and regulations and standards with regard to wind reactive power capability are slowly catching
up with the market.
The analysis has investigated three main issues: the optimal reactive power provision that �ts the
needs of system operator, the de�nition of an economic compensation structure for reactive power
suppliers, and the impact of wind power on voltage control and reactive power support. The study
has focused on the Italian case with reference to the projection horizon of the year 2014 in peak
load conditions, and the simulations have been carried out by means of an Optimal Reactive Power
Flow (ORPF) procedure and by considering the voltage control structure designed for the Italian
EHV network.
The problem has been analysed mainly from the TSO perspective, though the adoption of a
hierarchical voltage regulation architecture and of a suitable reactive power optimization program
allow a possible remuneration scheme for reactive power providers to be de�ned. In particular,
in addition to the voltage and reactive reference values for the voltage regulators, resulting from
the optimization of the reactive power schedule problem, the ORPF procedure calculates a nodal
indicator (¿/Mvarh) which represents the marginal real losses' variation consequent to a nodal
reactive injection in a certain grid bus and thus gives a �measure� of reactive power value. These
indicators provide signi�cant price signals needed for the economic compensation for reactive power
supply so quantifying the reactive power cost in grid nodes and identifying the system areas where
this resource is particularly valuable.
The simulations on the Italian EHV continental system has demonstrated that the power sys-
tem operation bene�ts from the optimization of the reactive power schedule problem also under
Automatic Voltage Regulation (AVR) only, from both technical (voltage increase) and economic
(real losses' reduction) point of view. The adoption of a higher voltage control level (SVR) allows
system security to be further enhanced since, while minimizing real power losses, it aligns the
reactive power margins of the controlling generators in each SVR areas, so increasing the system
controllability.
Moreover, the determination of nodal marginal reactive values by the ORPF procedure can be used
to propose a reactive pricing structure suitable for deregulated electric market frameworks. The
tests described in the chapter have highlighted that the presence of an adequate HVC (Hierarchical
Volatge Control) scheme and above all an appropriate subdivision of the electrical system into SVR
control areas can be useful to de�ne a zonal structure for eventual locational di�erences in reactive
power valorisation.
Finally, the test cases, to which the ORPF program has been applied, have been de�ned with the
aim of assessing the expected impact of an increasing penetration of wind energy in the Italian
transmission system, on the one hand, and the bene�ts deriving from the realization of the major
network reinforcements planned by the TSO, on the other hand.
CHAPTER 3. REACTIVE POWER SERVICE 163
In order to quantify wind impact on voltage regulation and reactive support, both the economic
aspect, represented by the nodal marginal values, and the security one, based on the reactive power
margins available on controlling generating units and on their usability to cope with possible per-
turbations, have been investigated. The results could be taken into account when evaluating the
eventual update of the regulatory treatment of the voltage control ancillary service and of reactive
transits at the connection points across grids. Speci�c results have shown that the optimization
outcomes vary remarkably depending on the actual high or low level of wind production. Further,
the e�ect of WTGs' participation in voltage control and reactive power support has been analysed.
The simulations have shown that their participation to primary and also secondary voltage regu-
lation can be helpful to increase the reactive resources available in a certain grid area, which can
be indispensable especially in very stressed operating conditions.
Finally, the tests' outcomes have underlined the need to complete the grid development plan de�ned
by the TSO for the medium term for a better exploitation of reactive resources, also in view of the
expected growth of wind power.
Chapter 4
Conclusions
The research work presented in this thesis has focused on the consequences of the deintegration
of generation and transmission resulting from the restructuring and liberalisation of the electricity
industry. In the new environment these activities are no longer combined in vertically integrated
utilities as they used to be. The objectives of power producers and system operators are completely
di�erent and thus the new situation has introduced new challenges a�ecting both planning and
operation of power systems.
The �rst part of the research work has dealt with the relationship between generation expansion and
transmission development in presence of competition on the supply side. The objective has been
to demonstrate that a more coordination in the planning process of generation and transmission
systems can contribute to a more coherent development of the whole power system enhancing
its operational reliability and security and improving electricity market e�ciency. The need for a
well-coordinated planning activity is based on several considerations, particularly on the reciprocal
dependence between the development decisions of these two systems.
The methodology described in Chapter 2 is based on the concept that generation and transmis-
sion investments can be interchangeable and, if properly de�ned, they can favourably a�ect both
system operation security and market e�ciency. The implementation in the Matlab program-
ming language of the procedure for calculating and plotting Weighted Transmission Loading Relief
(WTLR) sensitivities and the tests on the CIGRE 63-bus network and then on the Italian EHV
electric system have highlighted the e�ectiveness of these nodal indices for the selection of invest-
ments in both generation and transmission. In particular, it has proved to be a useful tool for
transmission planner since it is able to provide very interesting information about the weakest grid
sections and the impact of generation expansion on network security, and to help the grid planner
to de�ne possible priority lists of planned reinforcements and to determine new network upgrades.
Further, it can be used to underline the bene�ts of the grid development plan and the importance
of its realization and to send generation owners clear indications about the most suitable grid areas
for installing new power plants in order to avoid possible limitations on power production due to
some network constraint.
Besides these application aspects, which have been demonstrated and shown by the simulations'
outcomes, an important phase of the research work has been to investigate the limits of the original
WTLR methodology and to propose possible solutions. The �rst objective has been the reduction
of the total computational time of the Matlab-coded procedure by introducing the Line Outage
Distribution Factors (LODFs) to calculate the real power �ows in post-contingency conditions, and
164
CHAPTER 4. CONCLUSIONS 165
by using the base ISDFs, that is, in intact system conditions, to compute the WTLRs. The second
objective has been to remove the WTLR dependence on the selection of the slack bus in the grid.
Therefore, the concept of distributed slack bus has been introduced in both load �ow calculations
and ISDF computation. Finally, the MVA rating approximation, that is the main limit of the
original methodology, has been removed by suitably modifying the original Matlab-coded program
to consider the actual power �ow limits in the calculation of branch overloads.
The second part of the research work has focused on the reactive power service in a liberalised
environment. The three main issues investigated in Chapter 3 have been: the optimal reactive
power provision that �ts the needs and requirements of system operator, the de�nition of a �nancial
compensation structure for reactive power suppliers, and the impact of wind power on voltage
control and reactive power support.
The analysis has been carried out considering the perspective of system operators, which are re-
sponsible for a secure and reliable system operation and for the acquisition of all services, including
reactive power support and voltage regulation, indispensable for maintaining adequate standards
of power quality. Therefore, they have the task of implementing a suitable structure for e�ciently
managing this ancillary service and of assessing which resources are required according to both
economic and technical (i. e. grid topology) criteria. The adoption of a HVC scheme and an Op-
timal Reactive Power Flow procedure to de�ne its reference values (voltage and reactive power)
has proved to be an interesting starting point for the implementation of an e�cient mechanism for
reactive power provision by the TSO. Furthermore, on the basis of the estimated values of reactive
power when Secondary Voltage Regulation operates, a consistent reactive pricing structure and an
e�ective economic compensation scheme for reactive power suppliers can be de�ned.
Besides the above general issues, the tests carried out on the Italian EHV network with reference
to the projection year 2014 have investigated other two aspects: on the one hand, the impact of the
wind farms expected for the medium term in Southern Italy, and, on the other hand, the bene�ts
of realizing the major network reinforcements planned by the Italian TSO. The forecasted increase
of wind power has in fact various implications in system design, planning, and operation. The
analysis has assessed the impact on voltage control, taking into account the current legislative,
regulatory, and technical framework with respect to voltage regulation and reactive requirements
for producers connected to the Italian national transmission grid. Further, WTGs participation in
voltage control has been considered and the outcomes have shown that it can be an e�ective way
to integrate wind power in electrical systems. Finally, some speci�c simulations have highlighted
the need for the completion of the transmission system development planned by the TSO, to better
exploite the available reactive resources and to support the increasing wind penetration. Therefore,
simulation results and conclusions that are derived from them might be useful in power system
planning and for regulatory purposes as well.
Appendix A
CIGRE-63 bus test system
The CIGRE 63-bus test system [18], shown in Figure A.1, has been used in this thesis to implement
and test the proposed Matlab-coded procedure for the calculation and graphical representation of
the Weighted Transmission Loading Relief (WTLR) sensitivities. Moreover, it has been used to
implement some modi�cations in the original WTLR methodology: the introduction of the Line
Outage Distribution Factors (LODFs) and the adoption of the distributed slack bus concept.
The system can be divided in �ve areas, named R, M, F, T, and V. The buses of each area
are labeled with an integer number with three �gures, the area code, and the voltage level. For
instance, the buses 11R3, 65T2, and 9V1 belong to area R, T, and V respectively, and are referred
to the voltage levels 15 kV, 150 kV, and 220 kV.
The system encompasses a total demand of 2080 MW and has 63 nodes, 112 branches (lines and
transformers), and 16 thermoelectric generators. Bus 41M3 is selected as the slack bus.
The generators' cost curves are quadratic functions of the production P :
C(P ) = C0 + C1P + C2P2 (A.1)
Area R represents an independent power producer, area M is the main grid at 220 kV, while areas
F, T, and V can represent three sub-transmission systems at 150 kV with embedded generation.
The prices of the generators in areas R and F are very low, while prices o�ered in area V are very
high.
Demand is supposed inelastic and so the aggregate consumer curve is represented by a vertical line
in the diagram quantity-price.
The data for generator buses is provided in Table A.1, including the generators' limits and the
three coe�cients of the cost curves. The demand at load buses are given in Table A.2. The data
for the transmission lines connecting system buses is given in Table A.3.
166
APPENDIX A. CIGRE-63 BUS TEST SYSTEM 167
Figure A.1: CIGRE 63-bus test system
Table A.1: Generator buses
APPENDIX A. CIGRE-63 BUS TEST SYSTEM 168
Table A.2: Load buses
Table A.3: Transmission lines
Appendix B
Power Distribution Factors
B.1 Basic distribution factors
We consider a system with N + 1 buses and L lines [13, 14]. We denote by N = {0, 1, 2, . . . , N}the set of buses, with the slack bus at bus 0, and by L = {l1, l2, . . . , lL} the set of transmission
lines and transformers that connect the buses in the set N . We denote each element l ∈ Lby the ordered pair l = (i, j) with the convention that the direction of the �ow on line l is
from node i to node j. The serial admittance of line l is gl − jbl, the real power �ow is fl and
f = [f1, f2, . . . , fL]T . The net real power injection at node n ∈ N is denoted by pn and we de�ne
p =[p1, p2, . . . , pN
]T. Transactions are represented by the set of power injection-withdrawal
(I −W ) node pairs, W = {w1, w2, . . . , wW }, with each element in this set denoted by the ordered
triplet w = {m, n, t} representing an I−W node pair with from node m, to node n, in the amount
t.
We study the response of the real line �ow to changes in nodal injections. Consider the nodal
injection vector p and the corresponding real line �ow vector f . Denote the system state by
s =[θT , V T
]T, where θ =
[θ1, θ2, . . . , θN
]T(V =
[V 1, V 2, . . . , V N
]T) is the voltage phase
angle (magnitude) vector. Denote the reference conditions by p(0), s(0) and f (0) that satisfy both
the equations:
g(s(0))− p(0) = 0 (B.1)
h(s(0))− f (0) = 0 (B.2)
where equation (B.1) represents a statement of the real power �ow equations and the component
l of h(·) is the expression for the real �ow on line l = (i, j), l ∈ L:
hl (s) = gl
[(V i)2 − V iV jcos (θi − θj)
]+ blV
iV jsin (θi − θj) (B.3)
For a small change ∆p that changes the value from p(0) to p(0) + ∆p, we denote by ∆s (∆f) the
corresponding change in the state s (real line �ows f). We assume the system stays in balance for
the change ∆p and neglect the changes in losses so that, for every MW increase in the injection at
node n 6= 0, there is a corresponding MW increase in the withdrawal at the slack node 0. In other
words, ∆p0 = −∑
n∈N , n 6=0
∆pn. We apply the �rst order Taylor's series expansion near the reference
169
APPENDIX B. POWER DISTRIBUTION FACTORS 170
point s(0):
g(s(0) + ∆s) = g(s(0)) +
(∂g
∂s
)s(0)
∆s+ h.o.t. (B.4)
h(s(0) + ∆s) = h(s(0)) +
(∂h
∂s
)s(0)
∆s+ h.o.t. (B.5)
For �small� ∆p, ∆s is small and so we neglect the higher order terms (h.o.t.). We furthermore
assume (∂h/∂s)s(0) to be non-singular and henceforth drop the bar in the notation so that:
∆s ≈[∂g
∂s
]−1∆p (B.6)
∆f ≈ ∂h
∂s∆s =
∂h
∂s
[∂g
∂s
]−1∆p (B.7)
The sensitivity matrix in equation (B.7) depends on s(0) and this dependence on the system
operating point makes it less than practical for power system applications.
To simplify the computation of the sensitivity matrix, we next introduce the assumptions used in
the derivation of DC power �ow models and make use of the reduced nodal susceptance matrix:
B = ATB′A (B.8)
whereB′ = diag [b1, b2, . . . , bL] is the diagonal branch susceptance matrix and A = [a1, a2, . . . , aL]T
is the branch-to-node incidence matrix with the row l of the matrix: al =
[0 . . . 0
i1 0 . . . 0
j
−1 0 . . . 0
]T.
We assume B to be non-singular. Under these assumptions, s reduces to θ and the expressions for
the partial derivatives become ∂g/∂θ≈ B and ∂hl/∂θ≈ blal. We furthermore de�ne A = B′A to
be the admittance weighted branch-node incidence matrix, then
∆f ≈ AB−1∆p = Ψ ∆p (B.9)
We henceforth replace the approximation by the equality:
∆f = Ψ ∆p (B.10)
The L × N matrix Ψ = AB−1 is an approximation of the sensitivity matrix and is called the
Injection Shift Distribution Factor (ISDF) matrix. Since A and B are solely determined by the
network topology and the line parameters, Ψ is independent of s(0). The ISDF of a line l ∈ L with
respect to a change in injection at node n ∈ N , n 6= 0 is the element ψnl in row l, column n of
Ψ. Note that ψnl is de�ned implicitly under the assumption that there is a corresponding change
∆p0 in the injection at the slack node 0 with ∆p0 = −∆pn. Therefore, the ISDF is dependent on
the slack bus. As the location of the slack bus changes, the values of the ISDFs may change. The
notion of the ISDF may be extended to include the slack bus 0. Since the injection and withdrawal
buses are identical in this case, ψnl ≡ 0 for any l ∈ L.
In many applications, the impacts of changes in the quantity of an I −W node pair on the real
line �ows are of interest. We may evaluate the change in the real �ow on a line l due to a change
∆t in the transfer quantity of an I −W node pair w = {m, n, t} ∈ W with ISDFs. This change is
APPENDIX B. POWER DISTRIBUTION FACTORS 171
represented by setting ∆pm = ∆t = −∆pn. The corresponding real �ow change on line l is
∆fl = ψml ∆pm + ψn
l ∆pn = (ψml − ψn
l ) ∆t (B.11)
The ISDF di�erence term is called the Power Transfer Distribution Factor (PTDF) of line l with
respect to the I −W node pair w ∈ W and is de�ned by
ϕ(w)l =
∆fl∆t
= ψml − ψn
l (B.12)
In this case, the compensation at the slack bus cancels out since ∆pm −∆pn =(∆pm −∆p0
)−(
∆pn −∆p0). As such, the PTDF is independent of the slack bus.
A line l = (i, j) is radial if either Hi = {l} or Hj = {l}, where Hi (Hj ) is the set of lines that
connect to node i (j). For the radial line l with Hi = {l}, i 6= 0,
ψnl =
{1
0
if n = i
otherwise(B.13)
since the only impact on line l comes from the injection at node i. For any other line l 6= l, the
injection change at the terminal nodes i and j has the same impact,
ψil
= ψj
l∀l 6= l (B.14)
B.2 Impact of changes in network topology and parameter
values
The ISDFs and PTDFs play a key role in congestion modeling used in the new competitive envi-
ronment. Clearly, these factors are evaluated for a given topology and parameter values and an
operating point that satis�es, to a greater or lesser extent, the assumptions cited in the previous
section. However, in many cases of interest, there are changes in the network topology, parameter
values and the operating point, while the ISDFs and PTDFs are held constant in the applications
in which they are used. Such usage, in e�ect, neglects the impacts of these changes. In this section,
we evaluate the e�ect of these changes.
We �rst consider the impacts of changes in network parameters. Let us denote by L′ = {l′1, l′2, . . . , l′L} ⊆L the subset of lines whose parameters are changed. For each line l′ ∈ L′, its line susceptance ischanged from bl′ to bl′+∆bl′ . Denote the analogues of the matricesB′ (L×L), A and Ψ (L×N) cor-
responding to the lines in L′ byB′L′ = diag[bl′1 , bl′2 , . . . , bl′L′
](L′×L′), AL′ =
[al′1
, al′2, . . . , al′
L′
]Tand ΨL′ =
[ψ
l′1, ψ
l′2, . . . , ψ
l′L′
]T(L′ × N) where ψT
l′is row l′ of Ψ , the ISDF matrix. Let
∆B′L′ = diag[∆bl′1 , ∆bl′2 , . . . , ∆bl′
L′
], ∆bl′ 6= 0, ∀l′ ∈ L′. The changes in L′ result in changing the
B matrix into B + AT
L′∆B′L′AL′ . This, in turn, changes each row of the ISDF matrix by:
∆ψT
l=
∆bl
blψT
l−bl + ∆bl
blψT
lA
T
L′
(B′L′∆B′−1L′ + ΨL′A
T
L′
)−1ΨL′
−ψT
lA
T
L′
(B′L′∆B′−1L′ + ΨL′A
T
L′
)−1ΨL′ per l /∈ L′
(B.15)
APPENDIX B. POWER DISTRIBUTION FACTORS 172
The derivation of equation (B.15) is straightforward using the Sherman-Morrison-Woodbury for-
mula.
For l /∈ L′, the L′-dimensional row vector φT
l,L′ = −ψT
lA
T
L′
(B′L′∆B′−1L′ + ΨL′A
T
L′
)−1establishes
the relation between the pre-change real �ows fL′ =[fl′1 , fl′2 , . . . , fl′L′
]Tand the change ∆fl in
the real �ows on line l /∈ L′ due to the parameter changes with ∆fl = φT
l,L′fL′ . Particularly,
φl,l′
= −ψi′
l − ψj′
l
bl′
∆bl′+(ψi′l′ − ψ
j′
l′
) (B.16)
is proportional to the quantity ψi′
l − ψj′
l , if L′ = {l′ = (i′, j′)}. Note that if both B and B +
AT
L′∆B′L′AL′ are non-singular, B′L′∆B′−1L′ + ΨL′AT
L′ is invertible.
B.2.1 Outage of a line
Network topology changes such as line outages and line additions may be considered as special
cases of parameter changes. For example, for the outage of a line l′ = (i′, j′), L′ = {l′}, AL′ = aTl′
and ∆bl′ = −bl′ , so that:
∆ψT
l=
−ψT
l′if l = l′
ψi′
l − ψj′
l
1−(ψi′l′ − ψ
j′
l′
)ψT
l′otherwise
where the factor
φl,l′ =ψi′
l − ψj′
l
1−(ψi′l′ − ψ
j′
l′
) (B.17)
is called Line Outage Distribution Factor (LODF) which establishes the relationship between the
pre-outage real �ow fl′ on line l′ and the change ∆fl on the real �ows on line l 6= l′ due to the
outage of line l′ with ∆fl = φl,l′fl′ . Note that ψi′
l′ − ψj′
l′ = 1 only when {l} is a cutset of the
network. In that case, the outage of line l breaks the system into two separate subnetworks and
the ISDFs needs to be rede�ned for each subnetwork.
B.2.2 Closure of a line
Another example is the addition of a line l′ = (i′, j′). Two possible situations of interest are:
1. l′ is a radial line with i′ /∈ N whose addition results in L = L ∪ l′ and N = N ∪ i′. We may
apply equations (B.13) and (B.14) to construct the augmented ISDF matrix
Ψ =
[Ψ ψi′
0T 1
](B.18)
where ψi′ = ψj′ , the column j′ of Ψ.
APPENDIX B. POWER DISTRIBUTION FACTORS 173
2. l′ is a new line with i′, j′ ∈ N whose addition results in L = L ∪ l′. We de�ne a new ISDF
row vector ψT
l′= aT
l′B = bl′ aTl′B and construct the augmented (L+ 1)×N ISDF matrix
Ψ =
[Ψ + ∆Ψ
ψT
l′+ ∆ψT
l′
](B.19)
where ∆ψT
l′and each row of ∆Ψ is determined by ∆ψT
l= −
ψi′
l − ψj′
l
1−(ψi′l′ − ψ
j′
l′
)ψT
l′.
Appendix C
Slack bus modeling in load �ow
solutions
Power �ow analysis is a basic tool for power system studies. In a traditional power �ow with a
single slack bus model, one generator bus is selected to be the voltage phase angle reference and
balances the power mismatch due to uncertain system loss. Without the angle reference bus, that
is, if all buses are included in the Newton-Raphson formulation, the Jacobian matrix will certainly
be singular: so the slack bus allows the solution of the non-linear set of power �ow equations to be
feasible. The loss-compensating characteristic of the slack bus means that total losses are assigned
to only one slack bus: in fact, since the power losses in the network are not known in advance, to
maintain the real power balance in the system one cannot specify the real power generated at all
generators.
However, in the actual operation of electric power systems there is no single slack bus, instead
there are many generators distributed geographically throughout the system which take on the
function of a slack bus. So the concept of slack bus, as the voltage phase angle reference, is a
mathematical necessity but its loss-compensating characteristic has no physical relationship to any
generator bus. Exception arises when a small system is linked to a much bigger system via a single
tie line (single bus). In this case, one can represent the large system with an equivalent generator,
which can hold the voltage constant and generate as much power as needed, i. e. the slack bus
features. For instance, in a distribution network fed by a substation, the transmission network
acts as a slack bus with respect to the distribution network.
In the light of these considerations, a distributed slack bus power �ow is a better tool, even if the
adoption of a single slack bus usually does not represent a problem in a well de�ned deterministic
load �ow problem.
C.1 Single slack bus power �ow
The load �ow real power equations in a single slack bus model are [114]:
∆Pi = P i − Ci − Pi(θ1, . . . , θn−1, Vm+1, . . . , Vn−1) i ∈ [1, n− 1]
∆Ps = P s − Cs − Ps(θ1, . . . , θn−1, Vm+1, . . . , Vn−1) + ∆Pimb
(C.1)
174
APPENDIX C. SLACK BUS MODELING IN LOAD FLOW SOLUTIONS 175
where:
� buses 1, . . . ,m are P-V buses, buses m + 1, . . . , n − 1 are P-Q buses, and bus n is the slack
bus;
� ∆Pi is the real power mismatch at bus i;
� P i and Ci are the real power generation and the real load at bus i respectively;
� Pi(θ1, . . . , θn−1, Vm+1, . . . , Vn−1) is the sum of the real power �ows on the branches connected
to bus i: it is a function of the voltage phase angles and magnitudes;
� ∆Pimb is the real power unbalance due to uncertain power losses.
Denote the vector of the real power unknowns by:
∆θ = [θ1, θ2, . . . , θm, θm+1, . . . , θn−1,∆Pimb]T (C.2)
By linearizing the system (C.1) around the equilibrium point:
∆Pi =∑n−1
j=1
∂Pi
∂θj∆θj + 0 ·∆Pimb i ∈ [1, n− 1]
∆Ps =∑n−1
j=1
∂Ps
∂θj∆θj + 1 ·∆Pimb
(C.3)
The load �ow real power equations, that can be solved by the Newton-Raphson method, can be
formulated as follows:
∆P1
∆P2
...
∆Pn−1
∆Ps
=
∂P1
∂θ1
∂P1
∂θ2· · ·
∂P1
∂θn−10
∂P2
∂θ1
∂P2
∂θ2· · ·
∂P1
∂θn−10
......
......
...
∂Pn−1
∂θ1
∂Pn−1
∂θ2· · ·
∂Pn−1
∂θn−10
∂Ps
∂θ1
∂Ps
∂θ2· · ·
∂Ps
∂θn−11
·
∆θ1
∆θ2...
∆θn−1
∆Pimb
(C.4)
Figure C.1 shows the �ow-chart of a single slack bus load �ow procedure. At each iteration the
load �ow Jacobian is updated and the new system state is determined. The voltage phase angles
θi, the voltage magnitudes Vi, and the slack bus injection As are updated, after calculating the
real and reactive state variables (∆θi and ∆Vi):
θ(k+1)i = θ
(k)i + ∆θ
(k)i i ∈ [1, n− 1]
V(k+1)i = V
(k)i + ∆V
(k)i i ∈ [m+ 1, n− 1]
A(k+1)s = A
(k)s + ∆P
(k)imb
(C.5)
The convergence is achieved when the real and reactive power mismatches are lower than the given
tolerances. At the end, the slack bus power generation has to be updated on the basis of the �nal
APPENDIX C. SLACK BUS MODELING IN LOAD FLOW SOLUTIONS 176
injection calculated by the procedure:
Ps = As + Cs (C.6)
where Ps, As, Cs are the real power generation, the real power injection, and the real load at the
slack bus respectively.
Usually, the largest generator is arbitrarily proposed as slack in absence of better criteria, which
is a good choice in case the total imbalance is relatively large [115]. Other suggested criteria for
single slack bus selection are [116]: a) have the largest short-circuit current, b) have a large number
of lines connected to it, c) have a voltage leading all other voltages of the system.
C.2 Distributed slack bus power �ow
The basic concept is that of de�ning a small set of generation units which function as the slack bus
to balance the real power mismatch due to uncertain system losses. In particular, it is distributed
to these generation units according to the so called participation factors ρi.
To introduce the distributed slack bus, the load �ow equations have to be properly modi�ed. So
the system (C.1) becomes:
∆Pi = P i − Ci − Pi(θ1, . . . , θn−1, Vm+1, . . . , Vn−1) + ρi∆Pimb i ∈ [1,m]
∆Pi = P i − Ci − Pi(θ1, . . . , θn−1, Vm+1, . . . , Vn−1) i ∈ [m+ 1, n− 1]
∆Ps = P s − Cs − Ps(θ1, . . . , θn−1, Vm+1, . . . , Vn−1) + ρs∆Pimb
(C.7)
By linearizing the system (C.7) around the equilibrium point:
∆Pi =∑n−1
j=1
∂Pi
∂θj∆θj + ρi∆Pimb i ∈ [1,m]
∆Pi =∑n−1
j=1
∂Pi
∂θj∆θj + 0 ·∆Pimb i ∈ [m+ 1, n− 1]
∆Ps =∑n−1
j=1
∂Pi
∂θj∆θj + ρs∆Pimb
(C.8)
Only the last column of the load �ow real power Jacobian has to be modi�ed introducing the
participation factors ρi of those P-V buses that act as the slack bus:
∆P1
...
∆Pm+1
...
∆Ps
=
∂P1
∂θ1· · ·
∂P1
∂θm+1· · · ρ1
......
......
...
∂Pm+1
∂θ1
...∂Pm+1
∂θm+1
... 0
......
......
...
∂Ps
∂θ1· · ·
∂Ps
∂θm+1· · · ρs
·
∆θ1...
∆θm+1
...
∆Pimb
(C.9)
APPENDIX C. SLACK BUS MODELING IN LOAD FLOW SOLUTIONS 177
Figure C.1: Flow-chart of a single slack bus load �ow
APPENDIX C. SLACK BUS MODELING IN LOAD FLOW SOLUTIONS 178
At each iteration the load �ow Jacobian, modi�ed according to matrix calculation (C.9), is updated
and the new system state is determined. After calculating the real and reactive state variables (∆θiand ∆Vi), not only the voltage phase angles θi and the voltage magnitudes Vi, but also the real
power injections at the buses that participate in redistributing the real power losses, are updated:
θ(k+1)i = θ
(k)i + ∆θ
(k)i i ∈ [1, n− 1]
V(k+1)i = V
(k)i + ∆V
(k)i i ∈ [m+ 1, n− 1]
A(k+1)i = A
(k)i + ρi∆P
(k)imb i ∈ [1,m]
A(k+1)s = A
(k)s + ρs∆P
(k)imb
(C.10)
When the convergence is achieved, the real power generations at the distributed slack buses have
to be updated on the basis of the �nal injections calculated by the procedure:
Pi = Ai + Ci i ∈ [1,m]
Ps = As + Cs
(C.11)
C.2.1 Participation factors
As explained in the previous paragraph, a distributed slack bus is modelled using scalar participa-
tion factors to assign the unknown system loss to the participating sources. In the distributed slack
bus model, the system real power losses are treated as an unknown and distributed to participating
sources according to their assigned participation factors. The sum of all participation factors is
one:
Ngen∑i=1
ρi = 1 (C.12)
where Ngen is the number of generation units that participate in balancing the power mismatch
due to uncertain system loss.
There are several methods to calculate the participation factors. The �rst one, which is also the
simplest, de�nes the participation factor ρi as follows:
ρi =Pmax i∑Ngen
i=1 Pmax i
(C.13)
where Pmax i is the maximum real power by generation unit i.
Another method considers the participation factors of each generator to the economic load dispatch
(ELD).
Appendix D
Devices for reactive power support
The devices that provide reactive power support can be divided into two categories, static and
dynamic. Static devices can only be switched on and o� manually if they are installed with
switching abilities. They deliver a �xed amount of reactive power when switched on and they are
only capable of limited switching operations. They are therefore not able to respond to reactive
power needs instantaneously. Dynamic devices are instead capable of regulating their reactive
output according to requirements for voltage levels in real-time. The dynamic nature of reactive
support devices is much more desirable and so more valuable than the output from static ones,
which are more applicable in dealing with seasonal �uctuations in reactive power demand or in
supplying basic, invariable load at speci�c points in the system [43].
D.1 Synchronous generators
Most generators connected to the electricity grid are synchronous generators. Generator settings
can be adjusted to produce combinations of real and reactive power. When the generator increases
its reactive power output, its real power capability may need to be reduced if the generator reaches
its limits.
A generator's output capabilities depend on the thermal limits of various parts of the generator
and on system stability limits. Thermal limits are physical limits of materials such as copper, iron
and insulation; if the generator overheats, insulation begins to degrade and over time this could
result in equipment damage. Increasing real power output of a generator heats up the armature.
Increasing reactive power output heats up the �eld windings and the armature. To supply reactive
power, the generator must increase the magnetic �eld to raise the voltage that it is supplying to
the power system; this means increasing the current in the �eld windings, which is limited by
the thermal properties of the metal and insulation. The �eld current is supplied by the generator
exciter, which is a DC power supply connected to the generator. The �eld current can be quickly
adjusted by automatic control or with a dial to change the reactive power supplied or consumed
by the generator. Stability limits are determined by the ability of the power system to accept
delivery of power from the connected generator under a de�ned set of system conditions including
recognized contingencies. All generators connected to a power system operate at the same electrical
frequency; if a generator loses synchronism with the rest of the system, it will trip o�-line to protect
itself.
Figure D.1 is an example of a generator capability set, or curve. Due to the shape of the boundary,
179
APPENDIX D. DEVICES FOR REACTIVE POWER SUPPORT 180
Figure D.1: An example of synchronous generator output capability curve [117]
it is referred to as a D-curve. It has three components, labeled �eld heating limit, armature heating
limit and core-end heating limit.
The armature current limit is a circle with a radius VtIa, centered at the origin, and expressed by
the following equation:
P 2G +Q2
G ≤ (VtIa)2 (D.1)
The �eld current limit, on the other hand, is a circle with radiusVtEf
Xsat
(0,−
V 2t
Xs
)and expressed
by the following equation:
P 2G +
(QG +
V 2t
Xs
)2
≤
(VtEf
Xs
)2
(D.2)
where:
� PG is the real power generation of the synchronous generator;
� QG is the reactive power generation of the synchronous generator;
� Vt is the terminal voltage of the synchronous generator at which its capability curves are
calculated;
� Ia is the rated armature current of the synchronous generator at which its capability curves
are calculated;
� Ef is the excitation voltage of the synchronous generator;
� Xs is the synchronous reactance of the synchronous generator.
The core-end heating limit constrains the generator's capabilities in under-excited mode.
APPENDIX D. DEVICES FOR REACTIVE POWER SUPPORT 181
Reactive power supply from generators requires a minimal additional amount of fuel or real power
from the network. The cost of a generator depends on the capacity, fuel type and voltage level.
Because the reactive power constraints in generators are thermal and equipment takes some time to
heat to the point of degradation, generators are designed to provide signi�cantly increased amounts
of reactive power output for short periods. A generator can increase or decrease reactive power
output smoothly and almost instantaneously within its designed capabilities. Generators have a
longer response time if the real power output needs to be adjusted or the generator is o�-line; the
generator ramp rate and start-up time will determine how quickly the generator can adjust its
reactive power output in these situations. Generators have high maintenance costs due to their
moving mechanical parts and cooling systems.
D.2 Distributed generators
Distributed generators are small power sources including microturbines, fuel cells and engine gen-
erators connected to lower-voltage electric distribution systems. They may be owned by utilities
or by customers, and are often owned by large industrial plants. Distributed generators have the
same reactive power characteristics as large generators, they produce dynamic reactive power and
the amount of reactive power does not necessarily decrease when voltage decreases. The reactive
power output can be quickly adjusted within the generator operating limits, but will require more
time if the generator needs to be started or its real power output needs to be adjusted. The major
advantage of distributed generators is that they provide reactive power capability locally, often at
the site of large loads, reducing reactive power losses in transmission lines [118].
D.3 Synchronous condensers
Synchronous condensers are another type of dynamic reactive support device. They are basically
unloaded synchronous generators, i. e. they run without a prime mover or a mechanical load. They
deliver reactive power at leading or lagging power factor as their static counterparts, but they
possess many advantages over static devices. The most important is their ability to continuously
handle �uctuating local demand for reactive power and their reactive output is not a�ected by
system voltage conditions. Power factor correction with synchronous condensers also provides
lower line losses and so helps the real power transmission. They are rotating machines with moving
parts and therefore need signi�cantly more maintenance than their static alternatives accompanied
by maintenance costs.
D.4 Supervar machines
Supervar machines are rotating machines, much like motors and generators, that use high tem-
perature superconductor technology. They serve as reactive power �shock absorbers� for the grid,
dynamically delivering or absorbing reactive power, depending on the voltage level of the trans-
mission system. They are speci�cally designed for continuous, steady-state dynamic var support
while having multiples of their rated output in reserve for transient problems.
APPENDIX D. DEVICES FOR REACTIVE POWER SUPPORT 182
D.5 Shunt capacitors
Capacitor batteries can be either switched or �xed to the power grid although the latter is not
very desirable unless a basic, invariable local reactive power demand is present at the bus or its
surroundings. Switched capacitor banks are nonetheless considered static devices due to their
reactive power output being unadjustable whilst switched on. In addition, their reactive output
is proportional to the square of the bus voltage. This causes the output of a capacitor to be low
during low voltage periods when extra reactive power is likelier to be needed more, rendering the
capacitor less useful. Their advantages are that they can be bundled up to match the static reactive
power demand and individually added, removed, and replaced as needed. They are also light, most
often free of any required cooling and are relatively inexpensive on their own.
D.6 Shunt reactors
Shunt reactors, like their capacitor counterparts, can be either switched or �xed to the grid.
Reactors have the opposite e�ect to that of capacitors: they absorb reactive power from the power
grid. They are mainly used to compensate for the line capacitance in long overhead transmission
lines and cable systems. Their purpose is to keep the voltage from rising during light load periods
by absorbing excess local reactive power.
D.7 Series capacitors
Series compensation is based on controlled insertion and removal of series capacitors in AC trans-
mission lines. Series capacitors provide reactive power to the power system according to the square
of the line current: the higher the line current, the more reactive power support. Due to charac-
teristics of the impedance of a series capacitor compared to that of the line impedance, a series
compensated transmission line is electrically reduced to a shorter distance, so increasing its transfer
capability.
D.8 Flexible AC Transmission Systems (FACTS)
FACTS are technologies that increase �exibility of transmission systems by allowing control of
power �ows and increasing stability limits of transmission lines. There are several varieties of
FACTS devices. Some of the FACTS devices for reactive power management are static var com-
pensators (SVC), static synchronous compensators (STATCOM), static synchronous series com-
pensator (SSSC), dynamic var (D-var), distributed superconducting magnetic energy storage (D-
SMES), uni�ed power �ow controller (UPFC), and interline power �ow controller (IPFC) [119].
D.8.1 Static Var Compensators
Static var compensators (SVCs) are basically shunt capacitors and reactors connected to the grid
through and controlled by thyristors. They therefore possess many of the same physical char-
acteristics as static capacitor banks. They are however regarded as dynamic control because of
the addition of the fast switching capabilities of the thyristors brings dynamic properties to the
compensators.
APPENDIX D. DEVICES FOR REACTIVE POWER SUPPORT 183
D.8.2 Static Synchronous Compensators
Static synchronous compensators (STATCOMs) are devices that use power electronic technology
to synthesize reactive output to the grid. They convert a DC voltage source to a 3-phased output
at system frequency with capabilities to control both amplitude and phase-angle of the output.
STATCOMs are made to both generate and absorb reactive power and because of the power
electronics utilization the output range is symmetric, i. e. equal generation and consumption capa-
bilities. The response time of the STATCOM is similar to that of the SVC, but the STATCOM's
reactive output is not as sensitive to voltage degradation as the SVC's since the output of the
STATCOM falls linearly with voltage instead of proportionally to the square of the voltage. In
addition, a STATCOM device is slightly less space consuming than an SVC, but the STATCOMs
are slightly more expensive.
D.8.3 Static Synchronous Series Compensators
The Static Synchronous Series Compensator (SSSC) is a series device of the Flexible AC Trans-
mission Systems (FACTS) family using power electronics to control power �ow and improve power
oscillation damping on power grids. The SSSC injects a voltage in series with the transmission line
where it is connected, 90º phase-shifted with the load current, operating as a controllable series
capacitor. The basic di�erence, as compared with series capacitor, is that the voltage injected by
an SSSC is not related to the line current and can be independently controlled.
D.8.4 D-var (Dynamic Var)
D-var voltage regulation systems dynamically regulate voltage levels on power transmission grids
and in industrial facilities; D-var is a type of STATCOM. D-var dynamic voltage regulation systems
detect and instantaneously compensate for voltage disturbances by injecting leading or lagging re-
active power to the part of the grid to which the D-var is connected. D-var systems provide dynamic
var support for transmission grids that experience voltage sags, which are typically caused by high
concentrations of inductive loads, usually in industrial manufacturing centers, or from weaker por-
tions of the transmission grid, typically in remote areas or at the end of radial transmission lines.
D-var systems also are suited to address the need for dynamic var support at wind farms.
D.8.5 Distributed SMES (D-SMES)
A superconducting magnetic energy storage (SMES) system is a device for storing and instanta-
neously discharging large quantities of power. A distributed-SMES (D-SMES) system is a new
application of proven SMES technology that enables utilities to improve system reliability and
transfer capacity. D-SMES is a shunt-connected Flexible AC Transmission (FACTS) device de-
signed to increase grid stability, improve power transfer and increase reliability. Unlike other
FACTS devices, D-SMES injects real power as well as dynamic reactive power to more quickly
compensate for disturbances on the utility grid.
D.8.6 Uni�ed Power Flow Controllers
A Uni�ed Power Flow Controller (UPFC) is an electrical device for providing fast-acting reactive
power compensation on high-voltage electricity transmission networks. The UPFC is a versatile
APPENDIX D. DEVICES FOR REACTIVE POWER SUPPORT 184
controller which can be used to control real and reactive power �ows in a transmission line. The
concept of UPFC makes it possible to handle practically all power �ow control and transmission line
compensation problems, using solid state controllers, which provide functional �exibility, generally
not attainable by conventional thyristor controlled systems. The UPFC is a combination of a
static synchronous compensator (STATCOM) and a static synchronous series compensator (SSSC)
coupled via a common DC voltage link. It is capable of controlling simultaneously or selectively,
all the parameters a�ecting the power �ow in a transmission line. The parameters usually are
voltage, impedance, and phase angle.
D.8.7 Interline Power Flow Controllers
An Interline Power Flow Controller (IPFC) consists of two series voltage sources converters (VSCs)
whose DC capacitors are coupled, allowing real power to circulate between di�erent power lines.
When operating below its rated capacity, the IPFC is in regulation mode, allowing the regulation
of the P and Q �ows on one line, and the P �ow on the other line. In addition, the net real power
generation by the two coupled VSCs is zero, neglecting power losses.
D.9 Wind generators
The intermittent nature of wind power generation is particularly challenging when it comes to power
system operations. The uncontrollable operations of windmill farms make it di�cult to assign any
de�nite reactive power supply to the generators, especially older windmills, which are commonly
equipped with asynchronous generators. Such generators do not contribute any reactive power to
the grid but rather deliver power at lagging power factor meaning that they draw reactive power
from the grid. Newer installations are equipped with �xed capacitor banks or power electronics
like SVCs at their grid connection point.
D.10 User plants
All user plants connected to the network may contribute to voltage regulation, absorbing power
with a power factor greater than a certain minimum value. This goal, technically attainable by
correcting the power factor, can be easily achieved by means of the same static devices used in the
transmission network, mainly capacitors.
D.11 Transmission lines
Electric transmission lines have both capacitive and inductive properties. The line capacitance
supplies reactive power, while the line inductance consumes reactive power. At a loading known
as Surge Impedance Loading (SIL), the reactive power supplied by the line capacitance equals
the reactive power consumed by the line inductance, meaning that the line provides exactly the
amount of Mvar needed to support its voltage. Lines loaded above SIL consume reactive power,
while lines loaded below SIL supply reactive power. The amount of reactive power consumed by a
line is related to the current �owing on the line or the voltage drop along the line; the amount of
reactive power supplied by a line is related to the line voltage.
APPENDIX D. DEVICES FOR REACTIVE POWER SUPPORT 185
When an overhead transmission line is lightly loaded, the capacitance of the line generates more
reactive power than is absorbed by the inductive component and the line generates reactive power.
If the line becomes heavily loaded, the inductive reactance starts to absorbs more reactive power
than the capacitive component generates. This results in the line overall consuming reactive power
and therefore reactive power has to be supplied to the line in order to maintain a decent voltage
pro�le.
The capacitances have greater e�ect at higher voltage levels. Because of the capacitive nature of
HV transmission cables the inductive component of the conductors generally never absorbs more
reactive power than the shunt capacitances manage to generate. Cables therefore generate reactive
power which often has to be compensated to maintain voltage levels.
D.11.1 High voltage DC transmission lines
High voltage DC transmission lines (HVDC) transmit power via DC (direct current). Because DC
transmission lines are transmitting power at zero hertz, the reactive power consumption on the
line is zero. The converters require reactive power for the conversion process typically in the range
of 40% of the power rating of each of the converter terminals. The reactive power is required to
compensate for the reactive power consumption in the converter transformers and to maintain an
acceptable AC voltage level on the AC side of the converter terminals. Much of this reactive power
requirement is provided by shunt capacitors and �lters. Therefore, a properly designed HVDC
system is essentially self-su�cient in reactive power.
D.12 Transformers
Transformers are electromagnetic devices that convert power from one voltage level to another;
they are inductive devices and therefore consume reactive power.
D.12.1 Transformer taps
Large power transformers are generally equipped with �voltage tap changers�, with tap settings
to control the voltages either on the primary or secondary sides of the transformer by changing
the amount and direction of reactive power �ow through the transformers1. Tap changers do not
consume or supply reactive power; taps force voltage on one side of the transformer up, at the
expense of lowering the voltage on the other side. Taps can be thought of as pumping reactive
power from one side of the transformer to the other to regulate voltage. The tap changers can
be controlled to automatically adjust to system conditions. Transformers can be categorized as
semi-dynamic reactive power support devices. They deliver continuous voltage control, however,
they are slow in doing so.
D.12.2 Phase Shifting Transformers
Phase Shifting Transformers (PSTs), also called Phase Angle Regulators (PARs), allow system
operators to control real power �ow. Phase shifting transformers have taps that control the phase
angle di�erence across the transformer. Increasing the phase angle di�erence across a transformer
has the e�ect of increasing the impedance of the line, which will reduce the amount of real power
1They are called OLTC transformers (On Load Tap Changing transformers).
APPENDIX D. DEVICES FOR REACTIVE POWER SUPPORT 186
on the line. Phase shifting transformers are usually installed to control real power �ow, especially
along parallel paths. Phase shifting transformers are also a useful tool for reactive power control.
Controlling the real power �ow along a line allows for control of the reactive power consumed or
produced by the line.
D.13 Di�erences among equipment types
Generators, synchronous condensers, SVCs, and STATCOMs all provide fast, continuously control-
lable reactive support and voltage control. OLTC transformers provide nearly continuous voltage
control but they are slow. Because the transformer moves reactive power from one bus to an-
other, the control gained at one bus is at the expense of the other. Capacitors and inductors
are not variable and o�er control only in large steps. An unfortunate characteristic of capacitors
and capacitor-based SVCs is that output drops dramatically when voltage is low and support is
needed most. The output of a capacitor, and the capacity of an SVC, is proportional to the square
of the terminal voltage. STATCOMs provide more support under low-voltage conditions than
do capacitors or SVCs because they are current-limited devices and their output drops linearly
with voltage. The output of rotating machinery (i. e. generators and synchronous condensers) rises
with dropping voltage unless the �eld current is actively reduced. Generators and synchronous
condensers generally have additional emergency capacity that can be used for a limited time.
Voltage-control characteristics favour the use of generators and synchronous condensers. Costs,
on the other hand, favour capacitors. Generators have extremely high capital costs because they
are designed to produce real power, not reactive power. Even the incremental cost of obtaining
reactive support from generators is high, although it is di�cult to unambiguously separate reactive-
power costs from real-power costs. Operating costs for generators are high as well because they
involve real-power losses. Finally, because generators have other uses, they experience opportunity
costs when called upon to simultaneously provide high levels of both reactive and real power.
Synchronous condensers have the same costs as generators; but, because they are built solely to
provide reactive support, their capital costs do not include the prime mover or the balance of plant
and they incur no opportunity costs. SVCs and STATCOMs are high-cost devices, as well, although
their operating costs are lower than those for synchronous condensers and generators [117].
Table D.1: Characteristics of voltage-control equipment [43]
APPENDIX D. DEVICES FOR REACTIVE POWER SUPPORT 187
Di�erences in e�ectiveness and costs of the di�erent devices dictate that reactive power generally is
provided by a mix of static and dynamic devices. The cost of reactive power service depends upon
the choice of equipment. The costs of satisfying static reactive power demands are much lower
than those of satisfying dynamic reactive power demands. While capital costs tend to dominate,
the costs of providing reactive power also include generator fuel costs, operating expenses and the
opportunity costs from not generating real power. The capital costs of static sources of reactive
power, such as capacitors, are orders of magnitude lower than the capital costs of dynamic sources,
such as generators, SVCs, and synchronous condensers.
Table D.1 shows the speed of response, voltage support and costs for the di�erent sources of reactive
powers and does not include transformer tap changers. The ability to support voltage means the
ability to produce reactive power when voltage is falling. The availability of voltage support
indicates how quickly a device can change its reactive power supply or consumption. Disruption is
low for devices that can smoothly change reactive power output and high for devices that cannot
change reactive power output smoothly [43].
Appendix E
Italian hierarchical voltage control
The hierarchical voltage control scheme, presented in Chapter 3 and shown in Figure E.1, provides
closed-loop real-time regulation of voltages at the main buses (pilot nodes) of the transmission
network, through coordinated control of the reactive power resources associated with each pilot
node (control area), mainly those of generators (control plants). The most signi�cant levels of this
hierarchical control realize the Secondary and Tertiary Voltage Regulations (SVR and TVR). SVR
is a decentralized control scheme which automatically maintains the pilot node voltage at its set-
point, through the adjustment of the reactive powers of local control generators and compensators:
this area level control has a dominant time constant of 50 s.With a slower dynamics, SVR [80, 99]
can also switch local shunt reactors/capacitor banks and control OLTCs and SVCs. Conversely,
TVR [96, 98] acts on the overall transmission network, with a dominant time constant of about
5 min, automatically updating all the pilot nodes voltage set-points. TVR aims at both minimizing
network losses and improving operation voltage security.
The hierarchical voltage control scheme is very simple in comparison with other theoretical and
unrealistic centralized schemes due to the small number of EHV controlled buses and telecommu-
nication requirements. Notwithstanding the pursued objective of system complexity minimization,
the e�ort to achieve an e�ective control system is still considerable, especially for large transmission
networks.
E.1 Secondary Voltage Regulation
E.1.1 SART apparatus
SART1 [120] regulates the units' reactive power or local EHV bus-bar voltage by controlling the
AVR set-points and sharing out total generated reactive power among power plant units in a
balanced way. In the �rst control mode, SART regulates the reactive powers of local generators,
according to the reactive level received from the Regional Voltage Regulator. In the second mode,
it regulates the local high-side bus-bar voltage on the basis of a suitable daily voltage trend or an
operator-de�ned set-point. In both these control modes, the reactive power of each generator is
controlled through a closed loop whose set-point is obtained by multiplying the reactive level signal
by the generator's reactive power limit. Over/under excitation unit reactive limits are computed,
in real-time, as a function of the actual values of real power and voltage, also taking into account
1In the past it was called REPORT.
188
APPENDIX E. ITALIAN HIERARCHICAL VOLTAGE CONTROL 189
Figure E.1: Hierarchical voltage control for the Italian EHV system
APPENDIX E. ITALIAN HIERARCHICAL VOLTAGE CONTROL 190
the actual operating conditions of the generator cooling system.
SART recognizes particular network contingencies (power plant islanding, local bus-bars isolation,
etc.) in real-time on the basis of local information and chooses the most suitable control mode
accordingly. It also adapts the regulation parameters according to the identi�ed equivalent external
reactance seen from the bus-bar (network side). Under steady-state operating conditions, the
reactive level signal is limited between minimum and maximum excitation. During transients
these limits can be exceeded, according to the generators' overloading capabilities, thus permitting
the highest network support in response to heavy perturbations. SART's dynamic behaviour is
characterized by dominant time constants of about 5 s and 50 s for unit reactive power and EHV
bus-bar voltage control respectively. The reactive power gradient is limited on the basis of generator
constraints in the case of major perturbations.
E.1.2 RVR apparatus
RVR [95] is installed at the regional control centers. It regulates at the same time, but with
independent and parallel operation, the voltages of its pilot nodes through real-time remote control
of the reactive power productions of those power plants with the greatest impact on pilot node
voltages. For this purpose, RVR de�nes and updates the value of its area reactive power levels
through a separate voltage regulator for each pilot node in the region, whose main characteristics
are:
� the regulation law is of the proportional-integral type, with an adaptive control algorithm
which keeps loop dynamics unchanged in real-time, taking into account the number and
actual capabilities of the plants participating in pilot node voltage regulation, as well as the
equivalent external reactance experienced by the pilot node;
� full dynamic de-coupling among di�erent pilot node voltage control loops within the same
region, to avoid oscillations of reactive power between neighboring areas: for this purpose
it is also possible to select a positive, null or negative static droop for pilot node voltage
regulation;
� each pilot node voltage regulator can be started without any preliminary manual alignment
of control generator voltages, and its set point value can be determined locally by either the
manual calibrator (manual local reference) or the stored pro�les (automatic local reference).
Otherwise it is received by remote from TVR. Tracking functions among pilot node voltage
calibrators and corresponding controlled magnitudes enable switching between the RVR's
di�erent operation modes at any time without causing noise for controlled variables.
For each area, one or two vicarious pilot nodes can be chosen to deal with possible tele-measurement
equipment failures at the main pilot node. The con�guration of the control system in the region can
be also modi�ed taking into account network changes and in response to requests coming from TVR.
The regulation areas can be con�gured on-line in terms of control plants (participating in pilot node
voltage control), peripheral plants (performing local high-side voltage control), stations reactive
reserves under SVR control, and control law parameters. In particular network con�gurations,
some control plants may gravitate to an area close to that they electrically belong to, due to their
geographic position. These boundary plants, considered peripheral ones in the initial con�guration,
can either participate in tele-control of their pilot nodes or of the neighboring ones, as the grid
con�guration varies. In the automatic operation mode, based on local reference, the set-point value
APPENDIX E. ITALIAN HIERARCHICAL VOLTAGE CONTROL 191
of each pilot node voltage is automatically updated on the basis of a voltage pro�le associated with
the current day and stored in the RVR. The voltage daily generic pro�le consists of 96 values
corresponding to the set-point values to put into operation every quarter of an hour. During such
an interval, the reference of the pilot node voltage is automatically updated every minute, on the
basis of a tracking ramp, from the current reference value to that foreseen for the start of the
subsequent quarter of an hour.
E.2 Tertiary Voltage Regulation
E.2.1 NVR apparatus
NVR [121] includes the real-time regulator TVR and the optimal forecasting controller LMC.
TVR has two main objectives: minimizing network losses and increasing load margins in the
transmission network in response to heavy operating conditions (critical from the voltage stability
viewpoint). These goals are basically achieved by proper coordination between the TVR and the
SVR: TVR establishes network voltages by updating the voltage set-points optimization of the
pilot nodes, at any cycle. The TVR uses the last available minimum losses ORPF as the voltages-
reactive powers reference and achieves minimum feasible losses by minimizing a real-time control
function OF (see equation (E.6)).
The load margin is maximized by the automatic and real-time coordinated control contemporarily
exercised by SVR on all reactive resources, according to the SVR control philosophy. In terms of
stability, TVR and RVRs operate to prevent units from reaching their over-excitation limits: in
the presence of the TVR, this condition is in fact related to the tap-changer reverse action which
normally anticipates the triggering of the voltage collapse mechanism. Whenever the reactive power
control margins made available to SVR are strongly reduced as a result of severe perturbations
or abnormal load patterns, the TVR attends the grid voltage reduction to the minimum allowed
by the operating conditions, progressively renouncing the not applicable optimal forecasted grid
voltage pro�le. The TVR will therefore avoid the risk of instability by allowing the power plants
under SVR to operate at their capability limits only when transmission network voltages are very
low even though all the network's reactive power resources are engaged for voltage support. In
this way there is a reduced risk of the triggering of a voltage collapse in response to intervention
of over-excitation limits, and the overall loadability of the transmission system is increased.
The second NVR main function is achieved by the LMC controller, which de�nes the optimal
forecast voltage plan required as input by the TVR. This very slow o�-line ORPF computing is
the main LMC activity, taking into account the estimation of system state and the constraints
determined by the hierarchical structure of the SVR and its control ties (pilot nodes and control
power plants). On the basis of a forecasted state estimation, LMC computes in advance (i. e. the
day before) the provisional optimal voltage and reactive power plan, which is stored and used by
the TVR. If the TVR recognizes signi�cant di�erences between expected and real system operating
conditions, it requires the LMC to compute the updated optimal forecasted voltage plan based on
the last system state estimation (which, in the best case, could refer to about �ve minutes before).
This delayed ORPF will be continuously computed by LMC every state estimation update and
sent to the TVR until the stored and new optimal forecasted voltage plans resemble each other. In
addition, the LMC shows and compares, for each area, on-progress daily traces of the pilot node
voltage and required set-point, the reactive power levels operating on the plants and the optimal
APPENDIX E. ITALIAN HIERARCHICAL VOLTAGE CONTROL 192
forecasted references used by the TVR.
E.3 Control system algorithms and dynamics design
In the hierarchical voltage control system, the inner loop is typically faster than the outer one,
in such a way as to achieve substantial dynamic de-coupling between overlapped levels. In other
words, the time-decomposition criterion requires that the dominant time constant of any external
control loop be higher than the dominant time constants of all its internal loops. Such a criterion
is applied to unit voltage regulation, unit reactive power control, EHV bus voltage regulation, pilot
node voltage regulation, and pilot nodes voltage set-point optimization:
� AVR closes the conventional unit voltage control loop, which is basically of the proportional-
integral type. It is characterized by closed-loop dynamics dominated by a time constant of
about 0.5 s.
� Unit reactive power control within SART de�nes, in closed-loop and real-time, the AVR
voltage set-point VREF in the range between minimum Vmin and maximum value Vmax,
which obtains the unit reactive power production QG corresponding to its reference value
QREF :
VREF = KIQ
[∫ t
0
(QREF −QG) dt
]Vmax
Vmin
(E.1)
where KIQ is the regulator integral gain, tuned in such a way that the closed loop has a
dominant time constant of 5 s. The fastest AVR dynamic responses, mainly required in
response to major local network perturbations, are then not signi�cantly a�ected by the
reactive power loop. The reference value QREF is obtained from the product of the reactive
power level qLEV by the unit capability limit QLIM , computed on-line according to the actual
operating conditions of the electrical generator and cooling system:
QREF = qLEVQLIM (E.2)
� The reactive power level qLEV may be provided by the local EHV bus-bar voltage regulator
(SART in high-side voltage control) or by the pilot node voltage regulator (RVR control).
Both of them de�ne, in closed-loop and real-time, the reactive level qLEV in the interval
between its minimum qmin = −100% and maximum value qmax = +100%, which achieves
the EHV bus-bar or pilot node voltage VP corresponding to its reference value VPREF :
qLEV =
[KPV (VPREF − VP ) +KIV
∫ t
0
(VPREF − VP ) dt
]qmax
qmin
(E.3)
where KPV and KIV are the regulator proportional and integral gains respectively, tuned
in such a way that the closed loop has minimum-phase and a dominant time constant of
50 s. The fastest contribution to the dynamic responses is properly given by proportional
correction.
� The pilot node voltage set-point VPREF may be provided by the local daily trend (RVR
automatic setting) or by the regional dispatcher operator (RVR manual setting) or voltage
APPENDIX E. ITALIAN HIERARCHICAL VOLTAGE CONTROL 193
set-point optimization (TVR output). The latter de�nes the most appropriate pilot node
voltage set-points VPREF for secure/e�cient operation, on the basis of an integral law of the
optimal variations ∆VPREF with respect to the present voltage values VP :
VPREF = KIT
[∫ t
0
(Q2 +R2S−2
)−1Q2(VP − V 0
P
)dt]VPmax
VPmin
+
+KIT
[∫ t
0
(Q2 +R2S−2
)−1R2S−1
(qLEV − q0LEV
)dt]VPmax
VPmin
(E.4)
where KIT is the regulator integral gain, tuned in such a way that the closed loop has a
dominant time constant of 5 min, and S is the sensitivity matrix between area reactive levels
∆qLEV and pilot node voltages ∆VPREF
∆VPREF = S∆qLEV (E.5)
Relation (E.4) integrates the result of the TVR objective function minimization, which is based on
the actual network state estimation and the forecasted optimal voltages and reactive powers plan:
OF =[VP + ∆VPREF − V 0
P
]TQ2[VP + ∆VPREF − V 0
P
]+
+[qLEV + S−1∆VPREF − q0LEV
]TR2[qLEV + S−1∆VPREF − q0LEV
] (E.6)
where [VP ] and [qLEV ] are the vectors of pilot node voltages and area reactive power levels;[V 0P
]and
[q0LEV
]are the vectors of the optimal forecasted pilot node voltages and area reactive power
levels; Q2 and R2 are weight matrices whose selection allows bestowing a privilege on pilot node
voltage di�erences, rather then on the e�ort of control area reactive power levels. The compromise
reached by TVR, when the available optimal forecasted plan does not �t the real situation, should
properly consist in the achievement of the highest voltage plan consistent with real operating
conditions, which minimize network losses as much as is feasible. To achieve this result it is
necessary to preserve system controllability, even if close to the limits, in such a way as to avoid
the disastrous consequences of open-loop operation. In this condition, in fact, the uncontrolled
voltages determine undesired heavy reactive power �ows, which increase system losses and worsen
the operation e�ciency. TVR is therefore the correct and necessary completion of the hierarchical
automatic real-time voltage control system.
Bibliography
[1] L. Cabral, �Introduction to industrial organization�, MIT Press, Cambridge, Massachusetts
(USA), 2000
[2] CESI, �Survey on the requirements of the transmission planning process and classi�cation of
the relative indicators�, Milan, 2004, in Italian, online at: www. ricercadisistema.it
[3] T.-O. Léautier, �Transmission constraints and imperfect markets for power�, Journal of Reg-
ulatory Economics, 19:1 27-54, 2001
[4] NERC - North American Electric Reliability Council, �Reliability assessment guidebook ver-
sion 1.2�, April 2009, online at: www.nerc.com
[5] A. J. Wood and B. F. Wollenberg, �Power generation, operation, and control�, Second Edition,
John Wiley & Sons, 1996
[6] S. Grijalva and A. M. Visnesky Jr., �The e�ect of generation on network security: spatial
representation, metrics, and policy�, IEEE Transactions on Power Systems, Vol. 21, No. 3,
August 2006
[7] Ministero delle Attività Produttive, Ministerial Decree April 20, 2005, �Concession of elec-
tricity transmission and dispatching in Italy to the company GRTN S.p.A.�, O�cial Gazzette
n. 98, April 29, 2005, in Italian
[8] Terna S.p.A., �Italian transmission and dispatching grid code�, updated version, January
2010, in Italian, online at: www.terna.it
[9] The Mathworks, �MATLAB 7 Getting started guide�, online at: www.mathworks.com
[10] R. D. Zimmerman and C. E. Murillo-Sánchez, �MATPOWER-A MATLAB power sys-
tem simulation package version 3.2-User's manual�, September 21, 2007, online at:
http://www.pserc.cornell.edu/matpower/
[11] P. W. Sauer, �On the formulation of power distribution factors for linear load �ow methods�,
IEEE Transactions on Power Apparatus and Systems, Vol. PAS-100, No. 2, pp. 764-769,
February 1981
[12] W. Y. Ng, �Generalized generation distribution factors for power system security evaluation�,
IEEE Transactions on Power Apparatus and Systems, Vol. PAS-100, No. 3, pp. 1001-1005,
March 1981
[13] M. Liu and G. Gross, �Role of distribution factors in congestion revenue rights applications�,
IEEE Transactions on Power Systems, Vol. 19, No. 2, pp. 802-810, May 2004
194
BIBLIOGRAPHY 195
[14] M. Liu and G. Gross, �E�ectiveness of the distribution factor approximations used in con-
gestion modeling�, Proceedings of the 14th Power Systems Computation Conference (PSCC
2002), Sevilla, Spain, June 24-29, 2002
[15] P. W. Sauer, K. E. Reinhard, and T. J. Overbye, �Extended factors for linear contingency
analysis�, Proceedings of the 34th Hawaii International Conference on System Sciences, 2001
[16] M. A. Woodbury, �Inverting modi�ed matrices�, Memorandum Rept. 42, Statistical Research
Group, Princeton University, Princeton (NJ), 1950
[17] J. Sherman and W. J. Morrison, �Adjustment of an inverse matrix corresponding to a change
in one element of a given matrix�, Annals of Mathematical Statistics, vol. 21, No. 1, pp.
124-127, 1950
[18] �Application of optimization techniques to study power system network performance�, Tech-
nical Brochure 122, CIGRE Task Force 38.04.02 Report, October 1997
[19] C. Genesi, P. Marannino, I. Siviero, F. Zanellini, E. M. Carlini, and P. P. Pericolo, �Coor-
dinated transmission and generation planning to increase the electricity market e�ciency�,
Proceedings of 16th Power Systems Computation Conference (PSCC 2008), Glasgow, UK,
July 14-18, 2008
[20] C. Genesi, P. Marannino, I. Siviero, F. Zanellini, E. M. Carlini, and P. P. Pericolo, �Coor-
dinated generation and transmission expansion in the liberalized electricity market�, AEIT,
No. 9, pp. 42-49, September 2008, in Italian
[21] T. Güler, G. Gross, and M. Liu, �Generalized line outage distribution factors�, Power En-
gineering Letters, IEEE Transactions on Power Systems, Vol. 22, No. 2, pp. 879-881, May
2007
[22] C. Genesi, P. Marannino, M. Montagna, S. Rossi, and I. Siviero, �Power �ow based indices
for the coordination of transmission and generation system planning�, Proceedings of IEEE
PowerTech 2009, Bucharest, Romania, June 28-July 2, 2009
[23] Terna S.p.A., �Development Plan of the National Electric Transmission Network�, 2010,
online at: www.terna.it
[24] GME S.p.A. (Gestore dei Mercati Energetici), �The Italian electricity market vademecum�,
2009, in Italian, online at: www.mercatoelettrico.org
[25] C. Genesi, P. Marannino, M. Montagna, S. Rossi, I. Siviero, E. M. Carlini, and P. P. Peri-
colo, �Impact of network reinforcements on wind power dispatchability�, Convegno Nazionale
AEIT 2009, Catania, September 27-29, 2009, in Italian
[26] F. Careri, C. Genesi, P. Marannino, M. Montagna, S. Rossi, and I. Siviero, �Wind power
generation and transmission system planning: the Italian case�, 15th IEEE Mediterranean
Electrotechnical Conference 2010 (MELECON 2010), Malta, April 25-28, 2010
[27] C. Genesi, P. Marannino, M. Montagna, S. Rossi, I. Siviero, E. M. Carlini, and P. P. Pericolo,
�Impact of transmission system expansion on wind generation dispatchability�, L'Energia
Elettrica, No. 4, Vol. 87, July-August 2010, in Italian
BIBLIOGRAPHY 196
[28] FERC - Federal Energy Regulatory Commission of the United States of America, �Promot-
ing wholesale competition through open access non-discriminatory transmission services by
public utilities�, Docket No. RM95-8-000, Order No. 888, Issued April 1996
[29] NERC - North American Electric Reliability Council, Interconnected Operations Services
Working Group (IOSWG) Report, �De�ning interconnected operations services under open
access�, Issued March 1997
[30] Directive 2003/54/EC of the European Parliament and of the Council of 26 June 2003 con-
cerning common rules for the internal market in electricity and repealing Directive 96/92/EC,
O�cial Journal of the European Union, n. L176/37, July 15, 2003
[31] UCTE - Union for the Co-ordination of Transmission of Electricity, �Operation Handbook�,
June 2004
[32] EURELECTRIC, �Ancillary services: unbundling electricity products � An Emerging Mar-
ket�, February 2004
[33] E. Hirst and B. Kirby, �Ancillary services�, Oak Ridge National Laboratory, Technical Report
ORNL/CON 310, February 1996
[34] Houston Lighting & Power, �Comments to the Federal Energy Regulatory Commission in
Docket Nos. RM 95-8-000 and RM 94-7-001�, Houston, TX, August 1995
[35] Michigan Public Service Commission, �Opinion and order after remand�, Case Nos. U-10143
and 10176, Lansing, MI, June 1995
[36] New York Power Pool, �New York Power Pool presentation on ancillary services�, Prepared
for FERC Dockets RM95-8-000 and RM94-7-001, Schenectady, NY, November 1995
[37] NERC - North American Electric Reliability Council, �Interconnected Operations Services
Reference Document�, Version 1.0, Princeton, NJ, November 1995
[38] Directive 96/92/EC of the European Parliament and of the Council of 19 December 1996 con-
cerning common rules for the internal market in electricity, O�cial Journal of the European
Union, n. L27, pp. 20-29, January 30, 1997
[39] AEEG - Autorità per l'Energia Elettrica e il Gas, �Discipline of the technical and economic
conditions for electricity wheeling and for some network services�, regulatory order 13/99,
February 18, 1999, in Italian, online at: www.autorita.energia.it
[40] GRTN - Gestore della Rete di Trasmissione Nazionale, �Technical requirements for connec-
tion�, v. 3, March 1, 2001, in Italian
[41] AEEG - Autorità per l'Energia Elettrica e il Gas, �Rules for the supply of the public service of
electricity despatch and for the provisioning of the necessary resources following an economic
merit order, pursuant to articles 3 and 5 of the legislative decree n. 79/99�, regulatory order
168/03, O�cial Gazette - Ordinary supplement, n. 16, January 30, 2004, in Italian, online
at: www.autorita.energia.it
[42] F. Alvarado, B. Borissov, L. D. Kirsch, and Laurits R. Christensen Associates, Inc., �Reac-
tive power as an identi�able ancillary service�, prepared for Transmission Administrator of
Alberta, Ltd., March 18, 2003
BIBLIOGRAPHY 197
[43] FERC - Federal Energy Regulatory Commission of the United States of America, Sta� Re-
port, �Principles for e�cient and reliable reactive power supply and consumption�, Docket
No. AD05-1-000, February 4, 2005
[44] U.S.-Canada Power System Outage Task Force, �Final report on the August 14, 2003 blackout
in the United States and Canada: causes and recommendations�, Issued April 2004
[45] J. W. Lamont and J. Fu, �Cost analysis of reactive power support�, IEEE Transactions on
Power Systems, Vol. 14, No. 3, pp. 890-895, August 1999
[46] A. R. Bergen, �Power System Analysis�, Prentice Hall, New Jersey, 1986
[47] J. Zhong and K .Bhattacharya, �Toward a competitive market for reactive power�, IEEE
Transactions on Power Systems, Vol. 17, No. 4, pp. 1206-1215, November 2002
[48] G. Gross, S. Tao, E. Bompard, and G. Chicco, �Unbundled reactive support service: key
characteristics and dominant cost component�, IEEE Transactions on Power Systems, Vol.
17, No. 2, pp. 283-289, April 2002
[49] I. El-Samahy, K. Bhattacharya, and C. A. Cañizares, �A uni�ed framework for reactive
power management in deregulated electricity markets�, Proceedings of 2006 IEEE PES Power
Systems Conference and Exposition (PSCE '06), pp. 901-907, October 29-November 1, 2006
[50] NERC - North American Electric Reliability Council, �Operating Policy 10 on Interconnected
Operation Services�, Draft-3.1, Issued February 2000
[51] NYISO - New York Independent System Operator, �Ancillary Services Manual�, Issued March
2008, online at: www.nyiso.com
[52] PJM Interconnection LLC, �PJM open access transmission tari��, Sixth revised, vol. 1,
Issued March 2008, online at: www.pjm.com
[53] CAISO - California Independent System Operator Corporation, �Ancillary services require-
ment protocol�, FERC electricity tari�, First replacement, vol. 2, October 2000, online at:
www.caiso.com
[54] IESO - The Independent Electricity Market Operator, �Market rules for the Ontario elec-
tricity market�, March 2007, online at: www.ieso.ca
[55] NGET - National Grid Electricity Transmission, �The Connection and Use
of System Code (CUSC) - Schedule 3�, v1.4, Issued November 2007, on-
line at: http://www.nationalgrid.com/NR/rdonlyres/513F95AA-4EBC-468E-BE70-
2FA25FA5CFB0/21627/Sch3v14.pdf
[56] J. Zhong and K. Bhattacharya, �Reactive power management in deregulated power systems
- A review,� Proceedings of the IEEE Power Engineering Society Winter Meeting, vol. 2, pp.
1287-1292, January 2002
[57] REE - Red Eléctrica d'España, �Procedimientos de Operación del Sistema�, online at:
http://www.ree.es
BIBLIOGRAPHY 198
[58] M. A. El-Kady, B. D. Bell, V. F. Carvalho, R. C. Burchett, H. H. Happ, and D. R. Vierath,
�Assessment of real-time optimal voltage control�, IEEE Transactions on Power Systems,
Vol. 1, pp. 98-107, May 1986
[59] K. R. C. Mamandur and R. D. Chenoweth, �Optimal control of reactive power �ow for
improvements in voltage pro�les and for real power loss minimization�, IEEE Transactions
on Power Apparatus and Systems, Vol. 100, pp. 3185-3194, July 1981
[60] J. Qiu and S.M. Shahidehpour, �A new approach for minimizing power losses and improving
voltage pro�le,� IEEE Transactions on Power Systems, Vol. 2, pp. 287-295, May 1987
[61] N. Deeb and S. M. Shahidehpour, �Linear reactive power optimization in a large power
network using the decomposition approach,� IEEE Transactions on Power Systems, Vol. 5,
pp. 428-438, May 1990
[62] V. Ajjarapu, P. L. Lau, and S. Battula, �An optimal reactive power planning strategy against
voltage collapse,� IEEE Transactions on Power Systems, Vol. 9, pp. 906- 917, May 1994
[63] A. Berizzi, P. Bresesti, P. Marannino, G. P. Granelli, and M. Montagna, �System-area op-
erating margin assessment and security enhancement against voltage collapse,� IEEE Trans-
actions on Power Systems, Vol. 11, pp. 1451-1462, August 1996
[64] C. T. Su and C. T. Lin, �Fuzzy-based voltage/reactive power scheduling for voltage security
improvement and loss reduction,� IEEE Transactions on Power Delivery, Vol. 16, pp. 319-323,
April 2001
[65] N. Grudini, �Reactive power optimization using successive quadratic programming method,�
IEEE Transactions on Power Systems, Vol. 13, pp. 1219-1225, November 1998
[66] E. Luiz da Silva, J. J. Hedgecock, J. C. O. Mello, and J. C. Ferreira da Luz, �Practical
cost-based approach for the voltage ancillary service�, IEEE Transactions on Power Systems,
Vol. 16, pp. 806-812, November 2001
[67] M. L. Baughman and S. N. Siddiqi, �Real time pricing of reactive power: theory and case
study results,� IEEE Transactions on Power Systems, Vol. 6, No. 1, pp. 23-29, February 1991
[68] S. Hao and A. Papalexopoulos, �Reactive power pricing and management�, IEEE Transac-
tions on Power Systems, Vol. 12, No. 1, pp. 95-104, October 1997
[69] A. A. El-Keib and X. Ma, �Calculating short run marginal costs of active and reactive power
productions�, IEEE Transactions on Power Systems, Vol. 12, No. 2, pp. 559-565, May 1997
[70] S. Ahmed and G. Strbac, �A method for simulation and analysis of reactive power market�,
IEEE Transactions on Power Systems, Vol. 15, No. 3, pp. 1047-1052, August 2000
[71] B. J. Gil, T. G. San Roman, J. J. Alba Rios, and P. Sanchez Martin, �Reactive power pricing:
a conceptual framework for remuneration and charging procedures�, IEEE Transactions on
Power Systems, Vol. 15, No. 2, pp. 483-489, May 2000
[72] K. Bhattacharya and J. Zhong, �Reactive power as an ancillary service�, IEEE Transactions
on Power Systems, Vol. 16, No. 2, pp. 294-300, May 2001
BIBLIOGRAPHY 199
[73] E. Nobile and A. Bose, �A new scheme for voltage control in a competitive ancillary service
market�, Proceedings of XIV PSCC Conference, Session 40, Paper 4, Sevilla (Spain), June
2002
[74] J. Zhong, E. Nobile, A. Bose, and K. Bhattacharya, �Localized reactive power markets using
the concept of voltage control areas,� IEEE Transactions on Power Systems, Vol. 19, No. 3,
pp. 1555-1561, 2004
[75] V. L. Paucar and M. J. Rider, �Reactive power pricing in deregulated electrical markets
using a methodology based on the theory of marginal costs�, Proceedings of the IEEE Large
Engineering Systems Conference on Power Engineering, pp. 7-11, July 2001
[76] P. Lagonotte, J. C. Sabonnariere, J. Y. Leost, and J. P. Paul, �Structural analysis of the
electrical system: application to the secondary voltage control in France�, IEEE Transactions
on Power Systems, Vol. 4, pp. 479- 486, May 1989
[77] CIGRE WG 38-02-03 ELETTRA - April 1991 �Improvement of voltage control�
[78] GRTN - Gestore della Rete di Trasmissione Nazionale, �Participation to the voltage control�,
Technical guide, May 2000, in Italian, online at: www.terna.it
[79] V. Arcidiacono, �Automatic voltage and reactive power control in transmission system�,
Proceedings of CIGRE-IFAC Survey Paper E, Florence, Italy, September 1983
[80] S. Corsi, �The secondary voltage regulation in Italy�, in Panel Session - 2000 IEEE PES
Summer Meeting, Seattle, WA, July 16-20, 2000
[81] S. Corsi, M. Pozzi, U. Bazzi, M. Mocenigo, and P. Marannino, �A simple real-time and on-
line voltage stability index under test in Italian secondary voltage regulation�, in Proceedings
of CIGRE, Paris, France, 2000
[82] J. P. Paul, J. Y. Leost, and J. M. Tesseron, �Survey of secondary voltage control in France:
present realization and investigation�, IEEE Transactions on Power Systems, Vol. 2, May
1987
[83] H. Lefebvre, D. Fragnier, J. Y. Boussion, P. Mallet, and M. Bulot, �Secondary coordinated
voltage control system: feedback of EDF�, in Panel Session - 2000 IEEE PES Summer
Meeting, Seattle, WA, July 16-20, 2000
[84] J. P. Piret, J. P. Antoine, and M. Subbe, �The study of a centralized voltage control method
applicable to the Belgian system�, in Proceedings of CIGRE, Paris, France, 1992
[85] J. Van Hecke, N. Janssens, J. Deude, and F. Promel, �Coordinated voltage control experience
in Belgium�, in Proceedings of CIGRE, Paris, France, 2000
[86] J. L. Sancha, J. L. Fernandez, A. Cortes, and J. T. Abarca, �Secondary voltage control: anal-
ysis, solutions, simulation results for the Spanish transmission system�, IEEE Transactions
on Power Systems, Vol. 11, pp. 630-638, May 1996
[87] L. Layo, L. Martin, and M. Álvarez, �Final implementation of a multilevel strategy for
voltage and reactive control in the Spanish electrical power system�, in Proceedings of PCI
Conference, Glasgow, Scotland, UK, 2000
BIBLIOGRAPHY 200
[88] S. Corsi, M. Pozzi, C. Sabelli, and A. Serrani, �The coordinated automatic voltage control of
the Italian transmission grid - Part I: reasons of the choice and overview of the consolidated
hierarchical system�, IEEE Transactions on Power Systems, Vol. 19, No. 4, pp. 1723-1732,
November 2004
[89] AEEG - Autorità per l'Energia Elettrica e il Gas, �Annex A of the Regulatory Order Elec-
tricity 33/08: Italian technical standard CEI 0-16�, Second Edition, July 2008, in Italian,
online at: www.autorita.energia.it
[90] AEEG - Autorità per l'Energia Elettrica e il Gas, �Annex A of the Regulatory Order
348/07 - Full regulatory text about electricity tari�s for transmission, distribution and
metering for the regulatory period 2008-2011, December 29, 2007, in Italian, online at:
www.autorita.energia.it
[91] Italian Interministerial Committee on Prices, Provision 15/93 of 14 December 1993
[92] AEEG - Autorità per l'Energia Elettrica e il Gas, �Synthesis of responses to consultation on
electricity tari�s for transmission, distribution and metering 2008-2011�, October 2007, in
Italian
[93] CENELEC - Comité Européen de Normalisation ÉLECtrotechnique, �Voltage characteristics
of electricity supplied by public distribution networks�, Standard EN 50160, September 2007
[94] S.Corsi, R. Chinnici, R. Lena, G. Vannelli, U. Bazzi, and E. Cima, �General application to
the main ENEL's power plants of an advanced voltage and reactive power regulator for EHV
network support�, Proceedings of CIGRE, Paris, France, 1998
[95] S. Corsi, V. Arcidiacono, U. Bazzi, R. Chinnici, M. Mocenigo, and G. Moreschini, �The
regional voltage regulator for ENEL's dispatchers�, Proceedings of CIGRE, Paris, France,
1996
[96] S. Corsi, P. Marannino, N. Losignore, G. Moreschini, and G. Piccini, �Coordination between
the reactive power scheduling and the hierarchical voltage control of the EHV ENEL system�,
IEEE Transactions on Power Systems, Vol. 10, No. 2, pp. 686-694, May 1995
[97] A. Berizzi, S. Sardella, F. Tortello, P. Marannino, M. Pozzi, and G. Dell'Olio, �The hier-
archical voltage control to face market uncertainties�, Proceedings of Bulk Power System
Dynamics and Control, IREP V Conf., Onomichi, Japan, 2001
[98] S. Corsi, M. Pozzi, P. Marannino, F. Zanellini, M. Merlo, and G. Dell'Olio, �Evaluation of
load margins with respect to voltage collapse in presence of secondary and tertiary voltage
regulation�, Proceedings of Bulk Power Systems Dynamics and Control, IREP V Conf.,
Onomichi, Japan, 2001
[99] P. Marannino, F. Zanellini, A. Berizzi, D. Medina, M. Merlo, and M. Pozzi, �Steady state
and dynamic approaches for the evaluation of the loadability margins in the presence of
the secondary voltage regulation�, Proceedings of MedPower Conference, Athens, Greece,
November 2002
[100] P. Marannino, F. Stefanelli, F. Zanellini, M. Delfanti, and M. Merlo, �Impact of real losses
and operational constraints on the reactive support value in presence of a hierarchical voltage
BIBLIOGRAPHY 201
control�, Proceedings of IEEE Bologna Power Tech Conference, Bologna, Italy, June 23-26,
2003
[101] P. Marannino, F. Zanellini, G. Marelli, M. Merlo, and G. Piccini, �Assessing the Mvar
generation values to price the reactive support to a hierarchical voltage control�, Proceedings
of VI Bulk Power System Dynamics and Control Symposium, Cortina d'Ampezzo, Italy,
August 2004
[102] M. Behnke and A. Ellis, �Reactive power planning for wind power plant interconnections�,
2008 IEEE Power and Energy Society General Meeting - Conversion and Delivery of Electrical
Energy in the 21st Century, Pittsburgh, PA, USA, July 20-24, 2008
[103] CIGRE WG B4.39, Summary of Technical Brochure 370 �Integration of large scale wind
generation using HVDC and power electronics�, ELECTRA no. 242, February 2009
[104] H. Berndt, M. Hermann, H. D. Kreye, R. Reinsch, U. Scherer, and J. Vanzetta, �Trans-
mission Code 2007. Grid and system regulations of the German grid utilities�, Verband der
Netzbetreiber VDN e.V.1, 2007, in German
[105] �Ordinance on System Services by Wind Energy Plants (System Ser-
vice Ordinance - SDLWindV)�, 2010, online at: http://www.erneuerbare-
energien.de/�les/pdfs/allgemein/application/pdf/sdl_windv_en.pdf
[106] J. M. Rodríguez, O. Alonso, M. Duvison, and T. Domíngez, �The integration of renewable
energy and the System Operation: The Special Regime Control Centre (CECRE) in Spain�,
2008 IEEE Power and Energy Society General Meeting - Conversion and Delivery of Electrical
Energy in the 21st Century, Pittsburgh, PA, USA, July 20-24, 2008
[107] AEEG - Autorità per l'Energia Elettrica e il Gas, Regulatory Order Electricity 98/08 on veri-
�cation of transmission and dispatching grid code regarding management of wind generation,
July 25, 2008, in Italian, online at: www.autorita.energia.it
[108] Terna S.p.A., Annex A17 of the Italian transmission and dispatching grid code, �Control
and protection systems for wind turbine generators - Technical requirements for connection�,
August 2008, in Italian, online at: www.terna.it
[109] AEEG - Autorità per l'Energia Elettrica e il Gas, Consultation 25/09 on options for dis-
patching electrical energy produced by non-programmable renewable sources, July 27, 2009,
in Italian, online at: www.autorita.energia.it
[110] E. M. Carlini, P. P. Pericolo, P. Marannino, I. Siviero, and R. Vailati, �Impact of wind gener-
ation on the voltage control ancillary service and the development of the Italian transmission
system�, CIGRE Session 2010, Paris, France, August 22-27, 2010
[111] V. Arcidiacono, S. Corsi, A. Natale, and C. Ra�aelli, �New developments in the applications
of ENEL transmission system automatic voltage and reactive control�, CIGRE Meeting,
Report 38/39-06, Paris, France, 1990
[112] P. Marannino, M. Merlo, G. Piccini, and F. Zanellini, �Reactive power support value and
hierarchical voltage control�, AEIT, No. 7, July-August 2006, in Italian
BIBLIOGRAPHY 202
[113] F. Careri, C. Genesi, P. Marannino, M. Montagna, S. Rossi, I. Siviero, �De�nition of a zonal
reactive power market based on the adoption of a hierarchical voltage control�, Proceedings of
7th International Conference on the European Energy Market (EEM 2010), Madrid, Spain,
June 23-25, 2010
[114] Z. Yonggang, �Analysis of voltage collapse for applications in real-time�, PhD Thesis in
Electrical Engineering, XI Ciclo, Dipartimento di Ingegneria Elettrotecnica, Politecnico di
Milano, in Italian
[115] A. Gómez Expósito, J. L. Martínez Ramos, and J. Riquelme Santos, �Slack bus selection to
minimize the system power imbalance in load-�ow solutions�, IEEE Transactions on Power
Systems, Vol. 12, No. 2, pp. 987-995, May 2004
[116] L. L. Freris and A. M. Sasson, �Investigation of the load-�ow problem�, Proc. IEE, Vol. 115,
No. 10, pp. 1459-1470, October 1968
[117] B. Kirby and E. Hirst, �Ancillary service details: Voltage control,� Tech. Rep. ORNL/CON-
453, Oak Ridge National Laboratory - Energy Division, December 1997
[118] J. D. Kueck, B. J. Kirby, L. M. Tolbert, and D.T. Rizy, �Tapping Distributed Energy Re-
sources,� Public Utilities Fortnightly, pp. 46-51, September 2004
[119] J. Dixon, L. Morán, J. Rodríguez, and R. Domke, �Reactive Power Compensation Technolo-
gies, State-of-the-Art Review�, Proceedings of the IEEE, Vol. 93, No. 12, December 2005
[120] GRTN - Gestore della Rete di Trasmissione Nazionale, �Power plant voltage and reactive
power regulator�, October 2003, in Italian, online at: www.terna.it
[121] C. Brasca, R. Chinnici, M. Pozzi, and M. Zaramella, �Practical implementation aspects of a
multilevel control solution for voltages and reactive regulation in electrical power systems�,
in Proceedings of Process Control and Instrumentation Conference, Glasgow, Scotland, UK,
2000