UNIVERSITY OF GEORGIA. IMPLEMENTING GUIDANCE FOR THE REPORTS ON USE OF FUNDS PURSUANT TO THE AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 Contract & Grants. Topics. First Time Reports - Overview Quarterly Reporting During Term of Project Pass Through Responsibilities Lessons Learned - PowerPoint PPT Presentation

Citation preview

Page 1: UNIVERSITY OF GEORGIA

UNIVERSITY OF GEORGIA

IMPLEMENTING GUIDANCE FOR THE REPORTS ON USE OF FUNDS PURSUANT TO THE AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009

Contract & Grants

Page 2: UNIVERSITY OF GEORGIA

Topics First Time Reports - Overview Quarterly Reporting During Term of

Project Pass Through Responsibilities Lessons Learned Procedures for Consistency Final Reports

Page 3: UNIVERSITY OF GEORGIA
Page 4: UNIVERSITY OF GEORGIA

Quarterly Reports

Department will provide data for technical fields – including job impact, sub contract and vendor info, by completing ARRA Grant Reporting Worksheet

Contracts & Grants (C&G) will complete financial fields and upload templates to FederalReporting.gov (FR.gov)

Page 5: UNIVERSITY OF GEORGIA

Prime Recipient Responsibilities Implement and follow appropriate data

collection and reporting procedures to ensure that Section 1512 responsibilities are met in a timely and effective manner

Conduct data quality reviews to prevent material omissions and/or significant reporting errors

Address any corrections in a timely and effective manner

Page 6: UNIVERSITY OF GEORGIA

PI/Department Responsibilities Maintain close contact with all

subrecipients, and any vendors who receive a single payment exceeding $25,000

Collect as much information regarding job impact data as soon as possible

Keep supporting documentation in case reports are questioned by awarding agency

Complete ARRA Grant Reporting Worksheet by quarterly deadline, typically 5 days after quarter ends

Page 7: UNIVERSITY OF GEORGIA

C&G Responsibilities Create and maintain control sheet for

reports due Review department provided data,

and obtain clarification if necessary Complete financial fields Register with and upload templates to

FR.gov Follow-up on any items noted during

review period

Page 8: UNIVERSITY OF GEORGIA

Data Quality Accurate, Complete

and Timely Reporting Must avoid material

omissions and significant reporting errors

Public should be fully informed

Public should not be misled or confused

Page 9: UNIVERSITY OF GEORGIA

Due Dates Technical Data due to C&G by the 5th day

after quarter end close C&G will upload prior to FR.gov deadline –

typically 10 days after quarter end Calendar Quarters: March, June,

September and December Dates may have to be adjusted depending

upon FR.gov performance and Recovery Board guidance

Page 10: UNIVERSITY OF GEORGIA

Q&A? My award date is prior to 12/31/2009, but

my budget period begins after 12/31/2009. Do I have a report due?

A Yes, a zero report will be required.? My total award is less than $25,000. Is a

report due?A No, if we are the prime. If we are a sub, we

have to comply with individual contract terms.

Page 11: UNIVERSITY OF GEORGIA

Quarterly Reporting During Term of Project Reports are cumulative, except job data

(current quarter only) Review comments from agency and adjust

as necessary Make certain you incorporate any previous

agency comments for data that remains constant

Use C&G FTE Calculation Worksheet for consistency (second tab on ARRA Grant Reporting Worksheet)

Page 12: UNIVERSITY OF GEORGIA

Pass Through Responsibilities If we receive pass-through ARRA funds, we

must comply with the reporting terms in the contract.

Currently, most require us to forward our reports to the prime

Approximatley 25% delegate the authority to us for uploading to FR.gov as a subrecipient

Information requested is the same, but in different formats

Page 13: UNIVERSITY OF GEORGIA

Timing of Sub Reporting When UGA is the prime – report sub

activity in the quarter invoices are paid

When UGA is the sub – Prime determines timing. Most contracts require monthly reporting, as contracts were issued before FR.gov and Recovery Board guidance was finalized.

Page 14: UNIVERSITY OF GEORGIA

Lessons Learned

Page 15: UNIVERSITY OF GEORGIA

Late Awards For the quarter ending 9/30/2009,

several awards were discovered on the readiness tools, as accounts had yet to be created. Only two were due to delays within UGA. Most were awarded by the agency in the last few days of September. Reports were required for these late awards.

Page 16: UNIVERSITY OF GEORGIA

Procedures for Consistency Naming convention for ARRA Worksheet:

ARRA_4 digit quarter_account numberEx: ARRA_0610_1021RU033001

NIH e-mail to Jane Magrino [email protected]

NSF, other Federal (prime) e-mail to Joy Hirsch [email protected]

Pass Through: e-mail to your Grants Specialist for Reporting

Page 17: UNIVERSITY OF GEORGIA

Q&A? Where do I report job impact data for a

subrecipient, or vendor who received a single payment in excess of $25,000?

A Job impact data for subs and vendors has to be combined with the prime data. The sum is reported on the prime tab – see row 32 on Federal reporting template. Agencies are backing down from the inclusion of vendor job impact data. Example: Shared Instrumentation awards are excluded from having to report job impact for vendors.

Page 18: UNIVERSITY OF GEORGIA

Q&A? What is the difference between

FederalReporting.gov and Recovery.gov?A FederalReporting.gov is an inbound solution

for data collection. Award recipients and agencies provide the data mandated by ARRA. Recovery.gov is a public site. Data from FR.gov rolls into Recovery.gov as early as the due date of our quarterly reports. Coverage maps and standard reports will be available on Recovery.gov.

Page 19: UNIVERSITY OF GEORGIA

Q&A? Can I view FederalReporting.gov

without a User ID and Password?A Yes. You can view messages

regarding due dates; download templates, data models, OMB webinars, and other reference material; and the FAQ’s.

Page 20: UNIVERSITY OF GEORGIA

Q&A? What if I receive a “mailbox full”

message when I send my ARRA Grant Reporting Worksheet to C&G?

A Alternate mailboxes: [email protected] [email protected] [email protected]

Page 21: UNIVERSITY OF GEORGIA

Final Reporting Recipients are no longer required to

submit reports when: The award period has ended, and All Recovery funds are received (draw-

down, reimbursement or invoice); or The award has been terminated or

cancelled

Page 22: UNIVERSITY OF GEORGIA

Contracts & Grants

Contact Information:Tammy Ebert, Associate Director706 227 [email protected]