23
Update from ND Transmission Authority ED&T Committee John Weeda Director, ND Transmission Authority February 13, 2019 1

Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Update from ND Transmission Authority

ED&T CommitteeJohn Weeda

Director, ND Transmission AuthorityFebruary 13, 2019

1

hfarnsworth
Text Box
APPENDIX E
Page 2: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Agenda

• Summary of ND Transmission Capacity Study by Power System Engineering (PSE)

• Modeling of the ND grid through 2038• Nodal pricing analysis

• Summary of Industry learnings• MISO/SPP presentations• Midwest Governor Association meetings• Texas grid modeling

• Conclusions• Opportunities and Impacts in ND• What can ND do

2

Page 3: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Transmission Capacity Study Executive Summary• Generation interconnect requests are greatly outpacing forecasted demand

within North Dakota• There has been approximately 20% success rate on interconnections• Western ND load annual growth is projected at 1.2%, remainder of ND

projected at 0.8%• Modeling shows thermal and voltage violations increase from 2022 to 2026

and become very high in the 2038 analysis• Wholesale power pricing has become negative in the 2016-2019 review

and increased peaks and valleys in the $/MWHr prices• Replacing the energy from 900 MW of coal generation would require

approximately 1,727 MW of additional wind generation

3

Page 4: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Study executive summary continued

• In 2018 coal generation of 900 MW contributed 5,600,000 MWHr of energy to demand. Matching the equivalent amount of wind generation to that requires an additional 831 MW of charging capacity and 1,831 MW of discharge output from energy storage.

• Significant additional high voltage AC or DC transmission will be required to continue to grow generation interconnects especially in the 10 to 15 year horizon and this generation will be mostly export

• Other Studies such as the CapX2050 are also important for North Dakota, especially as it relates to out of state impacts to the ND grid

4

Page 5: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Generation and Demand as studied

5

Page 6: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Examining the North Dakota Export Limit

6

Page 7: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

What does the export limit mean to ND?

• Limited ability to inject generation into the MISO and SPP grids in the near term

• Injection capacity declining between 2022 and 2026 and by 2038 having negative injection capacity

• Generation curtailment will result from these export limits• Locational Marginal Prices for ND Generation will continue to fall

without additional high voltage transmission• In summary, North Dakota will be a less attractive place to do

generation business!

7

Page 8: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

How will the system perform?

8

Page 9: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Voltage on the grid will also be impacted

9

Page 10: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Pricing on the grid is also showing more volatility

10

Page 11: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Increasing renewable opportunity with storage

• Simulate using wind to meeting the demand that is currently met by 900 MW of coal capacity

• Replace with 1727 MW of wind generation• Goal is to levelize the surplus and deficit that would result from wind

generation without storage• Storage for this scenario is 5,600 GWHr• Current storage prices are huge - estimates of $250/MWHr suggesting

a cost of $1.4 Billion one time capital costs

11

Page 12: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Illustration of the hourly surplus and deficit improvement

12

Page 13: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Illustration of the annual storage

13

Page 14: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Conclusions

• Transmission within ND is highly utilized and running out of capacity• Interconnection requests are far exceeding growth in demand• Lines that export from ND are also nearing capacity and show need

for high voltage additions to accommodate increased export• Planning wind to replace existing base load generation requires

installation of storage far beyond what has been demonstrated on commercial scale at this time

• Increasing congestion on full transmission lines is showing an impact on Locational Marginal Pricing (LMP) and expects it to continue downward pressure

14

Page 15: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Quantifying the Opportunity/ Risk

• Opportunity• Additional development of wind resources in ND• Development of an electric storage industry in ND• Economic activity of building additional transmission lines

• Risks• Public acceptance of major additional generation • Electric storage technology changes and storage in ND becomes a stranded

investment• Full cost of wind following end of Production Tax Credits causes downturn in

the industry• Transmission lines that are added are not in the right place or do not get fully

utilized

15

Page 16: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Tying these results together with MISO and SPP and the work of the Midwest Governors Association(MGA)

• MISO (RIIA) Renewable Integration Impact Assessment Shows rapid rise in complexity above 30% renewable generation

• Transmission is less than a majority of the complexity• Cost and complexity have a correlation• ND currently at 25.2% per 2018 Energy Information Administration (eia)

• SPP in a very high wind region• Faces challenges such as loss of 1400 MW an hour for 8 hours on 12/12/19• Often has wind offering into market at minus $25 to $30 per MWhr• Has natural gas at negative pricing at times in their Southwest region so wind

and natural gas are competing to drive the market down16

Page 17: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Continued work with MISO, SPP and MGA

• Agreement that transmission is needed, but barriers exist• Who pays - about 10 years ago Multi Value Projects were socialized into

electric rates throughout the region including ND• No good long term planning process that coordinates generation and

transmission• No authority over decisions of plant shutdown for resource adequacy of the

grid• Long distance transmission crosses over state lines and utility territories that

all have a “what is in it for me” interest• General public does not have an awareness of the magnitude of transmission

lines and generation facilities that are needed for the desired low carbon future - thus siting and permitting challenges

17

Page 18: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

MISO, SPP and MGA continued

• Focus is on energy cost - capital cost hidden in most cases• Most new generation being built for tax credits as opposed to

replacement• Utilities are holding on to interconnections even when there is a

retirement• A frequent scenario to achieve high level of renewable energy is to

overbuild - up to 7 or 8 times in some analyses• Will time of day conversion (storage) be at the generation or

consumption end of transmission

18

Page 19: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

MISO, SPP and MGA continued

• Dispatchable Intermittent resources only accredited at 15% unless demonstrated higher (some feel there should be no accredited capacity)

• How do you plan dispatchable resources for days when there is no wind or sun

• Will overbuild result in facilities that do not have a positive rate of return financially

• Many MGA members are promoting renewable energy in their state for economic development and don’t want out of state instead even though the return on investment is higher elsewhere

• Lack of agreement on who pays for transmission could keep renewable development at a standstill in many area for years

19

Page 20: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

A policy perspective by Texas Public Policy Foundation

• Transitioning Texas to 50% wind and solar by 2030 would cause annual cost to rise 250% compared to 2018.

• Reaching 100 percent wind and solar would increase cost by nearly 10 times

20

Page 21: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Information from Xcel Energy report to MGA on March 19, 2019• Costs increase steeply over ~60% annual renewables• At 100%, “overbuilding” grid capacity as much as 8X peak is required• No Great solution to use or store surplus renewable generation• 100% renewable scenarios create long-term imbalances of supply and

demand• Requires 8-16 weeks of storage• Storing all excess generation to avoid curtailment would cost trillions

21

Page 22: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Information about California shared by Xcel

22

Page 23: Update from ND Transmission Authority ED&T Committee · ED&T Committee John Weeda. Director, ND Transmission Authority. February 13, 2019. 1. APPENDIX E. ... • Wholesale power pricing

Important steps ahead

• Evaluate generation portfolios on cost of capacity as well as energy • Adding a mechanism for the market to reward capacity is essential• Encourage MISO and SPP to set standards for how reliability can be

assured with a proper generation mix of dispatchable and renewable resources

• Prepare the public for the impact of transitioning the grid in terms of land use, visual impacts and cost so landowner fatigue or rate payer resistance does not prevent the vision

• Planning results in grid investment that will provide investors a sound business solution with return on capital as well as operating expense.

23