Upload
others
View
18
Download
0
Embed Size (px)
Citation preview
David Knoll
11th EPRI Superconductivity Conference
Houston, TX 2013
Update on AEP/Bixby Project and HTS Cable
Commercialization Prospects
HTS TriaxTM
American Electric Power (AEP)
HTS TriaxTM Cable System
13.2kV ● 3000A ● 69MVA
• 200m cable in duct-bank
• TriaxTM splice
• TriaxTM terminations
• Multiple 90º bends
• Cooling system (open cycle)
Energized: Aug 2006
De-Energized: Oct 2012
Project funded by U.S. DOE
Southwire: Project Lead • Development
• Cable
• Terminations
• Splice
• Installation
• Substation infrastructure
• Operation
AMSC: HTS 1G BSCCO wire
Praxair: Cooling system
HTS TriaxTM
Site Layout
Manhole with splice
North Termination
Liquid Nitrogen Return Line
South Termination
LN Cooling System
HTS TriaxTM Cable
LN
HTS TriaxTM Overview
PH1
PH2
PH3
N
Dielectric
Cryostat
70mm
150 mm
Phase Connections
Neutral
Dielectric
Dielectric
HTS TriaxTM
Open Cycle Cooling
Subcooler
Heat Exchanger
LN2
Supply
Tank 11,000gal
Pulse
Tube(s)
Cable
Backup
LN2 GN2
Nominal temperature = 70K
Nominal pressure = 90-100psia
Truck in LN: 3 or 4 deliveries per week
HTS TriaxTM
Auxiliary System Information
COOLING SYSTEM CONTROL SYSTEM INSTRUMENTATION
Vacuum Pumps HMI Temperature
Heat Exchangers PLC’s Pressure
Valves & Piping Software Flow
Tanks & Vaporizers
Circulation Pumps
Tankers
138 kV
HTS Cable 0.4 W
2
2
1
1
1
3 2 14
3
3
5
112 SPR
Inst.
OC
Inst.
OC
12
11
3
4
4
Bus B
Bus A
3
9
5
7
8
5
3
N.C.
HTS TriaxTM
Substation Circuit
13.2 kV TX
138kV / 13.2kV
Parallel Conventional
feed
HTS TriaxTM
System Operation
COMMUNICATION TO AEP
Status 0: Cable not ready to energize
- not in optimal state
- repair
Status 1: Cable ready to energize
Status 2: Parameter(s) out of range
- Have time to respond
- Fix or switch cable manually
- make-then-break
Status 3: Dangerous condition
- Risk of gas phase in cable
- Major component failure
REQUIRED MANUAL SWITCHING TO ENERGIZE CABLE
System Commissioning DC Current Testing: 6000A High Voltage: VLF 20kV (30 min)
Voltage Soak: 13.2kV (24 hr.)
AEP-Bixby Triax Cable Cooldown
-220
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
40
0:02:01 12:03:41 0:05:21 12:07:01 0:08:41 12:10:21 0:12:01 12:13:41
Time
Deg
C
System Operation
1.5 days
AEP-Bixby HTS Cable - Power On
8 August 2006
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
2600
9:09:00 10:21:30 11:34:00 12:46:30 13:59:00 15:11:30 16:24:00 17:36:30 18:49:00 20:01:30
Time
Am
ps
-210
-208
-206
-204
-202
-200
-198
-196
Tem
pert
ure
P1
P2
P3
N
TI102
TI104
TI105
TI106
System Operation Bixby HTS Cable Load Curve
1Jan2008 - 14July2008
0
500
1000
1500
2000
2500
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
0:00
:00
Date/Time
Cu
rre
nt
(Am
ps
)
Phase 1
Phase 2
Phase 3
Neutral
Bixby Load Curve
August 6 - 10, 2008
0
500
1000
1500
2000
2500
3000
0:00:00 0:00:00 0:00:00 0:00:00 0:00:00
Date/Time
Cu
rre
nt
(Am
ps
)
Phase 1
Phase 2
Phase 3
Neutral
2,715 A
HTS TriaxTM
Transients
27kA
Open
Breaker
17kA
More than 100 transients recorded
Most < 10,000A
Average = 6,500A
Maximum = 27,000A
ΔT not noticeable unless cooling plant went down
HTS TriaxTM
Cable Availability
2008 – 2010 (26,280 hr.)
cable at operating temp: 26,000 hr.
current on cable: 23,000 hr.
AVAILABILITY (cable ≤ 75K):
26,000 hr. 99% availability
OUTAGE = DE-ENERGIZED CABLE
AVAILABILITY = CABLE ≤ 75K
Dec 2006 – Oct 2012 (51,800 hr.)
44,000 hr. of data recorded
cable at operating temp: 42,500 hr.
current on cable: 35,000 hr.
AVAILABILITY (cable ≤ 75K):
42,500 hr. 97% availability
Cable Outages
Necessary vs. Nuisance
Few necessary outages:
• Circulation pump failure
• Vacuum pump failure
• Leaking valve
Most are nuisance outages.
Redundancy prevented the cable system from being in danger
Health of the cable system was never in danger
Nuisance Examples
• Temperature transmitter failure
- algorithm calculated gas-phase “status 3”
• Tank over-pressure during filling “status 2 or 3”
• House power loss “status 3”
• Improper control system settings “status 2”
• PLC failure “status 2 or 3”
• Operator Error “status 2 or 3”
HTS TriaxTM
End of Service Testing
At this point : HTS TriaxTM Hardware was proven successful
Next Step: Southwire / Ultera took on an effort to commercialize HTS cable Technology
• Utilized DOE funding originally slated for Entergy
• Funding was reduced and to be applied to tackling outstanding commercial barriers
end of service testing on Bixby cable
CABLE TESTS ON AEP-TRIAXTM CABLE
1. Heat load testing: analyze heat loads under different operating conditions
• Analyze historical data
• Higher operating temperatures
• Various flow rates and configurations
2. High voltage testing
• at original operating temperature
• at higher operating temperature
3. High current testing
• Up to 6,000A
• Compare results to original commissioning results
HTS TriaxTM
Heat Load Testing
System Heat Load vs. Time
2007-2011
REFRIGERATION SYSTEM+CABLE+TERM
CABLE + TERM
CABLE ONLY
Loss
(kW
)
Time (hr x 104)
Current (A)
Loss
(kW
)
CABLE ONLY
CABLE + TERM
REFRIGERATION SYSTEM+CABLE+TERM
System Heat Load vs. Current
2007-2011
Heat Load Testing
SYSTEM OPTIMIZATION: IMPACTS OF OPERATING AT HIGHER TEMPERATURE
Cable Inlet Temperature (K)
He
at L
oad
(W
)
RESULTS:
• Difficult to correlate operating temperature and loss.
• Did see correlation b/w ambient temperature and loss
• Need high temperature resolution to get good data
• Largest impact is in termination copper parts
ΔT of 5K adds ~100W
• higher operating temperature has a low impact on system loss
0ºC
1ºC
6ºC
8ºC
20ºC
28ºC
26ºC
27ºC
1720A
18ºC
8
74
A
20ºC
1143A
24ºC
1
14
6A
26ºC
1270A
27ºC
1
61
8A
No Load
With Load
HTS TriaxTM
High Voltage Testing
PURPOSE:
• Partial discharge (PD) baseline at 70K
• Partial discharge (PD) up to 75K
• Compare results
TESTING:
• Voltage on one phase at a time
(other phases grounded)
• PD measurement up to 20kVrms
• Dwell at 20kV
North Termination HTS Cable
LN F
eed
LN F
eed
PH1 PH2 PH3
South Termination HTS Cable
LN F
eed
PD Detector
PH1
High Voltage
PH2 PH3
South Termination HTS Cable
LN F
eed
PD Detector
High Voltage
PH1 PH2 PH3
North Termination HTS Cable
LN F
eed
LN F
eed
PH1 PH2 PH3
South Termination HTS Cable
LN F
eed
PD Detector
PH1 PH2 PH3
High Voltage
North Termination HTS Cable
LN F
eed
LN F
eed
PH1 PH2 PH3
HTS TriaxTM
High Voltage Testing
PD Inception Voltages at 70K supply temperature South Termination North Termination Cable Splice PH 1 4.3 kV 7.6 kV >20 kV >20 kV PH 2 >20 kV >20 kV >20 kV >20 kV PH 3 16 kV 16 kV >20 kV >20 kV
HTS TriaxTM
High Voltage Testing
PD Inception Voltages at 75K supply temperature South Termination North Termination Cable Splice PH 1 ~ 3 kV 13.2 kV >20 kV >20 kV PH 2 >20 kV >20 kV >20 kV >20 kV PH 3 17.3 kV 17.3 kV >20 kV >20 kV
70K
75K
1. Phase 1 terminations show PD at or below operating voltage
• Project ended - not able to determine cause at this time
• Cable withstood 20kV in spite of showing low PD
2. No PD in cable or splice
3. Based on this analysis, the PH1 terminations have operated some time with PD
• Need to study affects of PD on LN impregnated systems
HTS TriaxTM
High Current Testing (by ORNL) PURPOSE: analyze high current-voltage response and compare 2006 vs. 2012 data
looking for performance degradation
• Expected Ic = 7000-7500A for each phase.
• Power supplies limited to 6000A cannot measure Ic of cable
• Two phases were measured simultaneously – minimizes inductance
ph1
ph2
ph3
ph1ph2ph3
gnd
gnd
North termination
South termination
DC 6 kA power source (Two 3 kA dc power
supplies)
Undergroundcable splice
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
0 1 2 3 4 5 6 7
Vo
lta
ge [
V]
Current [kA]
ph3 June 2006
ph3 August 2012
High Current Testing (by ORNL)
2006
2012
2012
2012
PHASE 3 : V-I CURVE
RESULTS:
1. Total resistance of circuit = 0.15 – 0.17mΩ
- resistance at superconducting-to-normal transition estimated at 15mΩ
2. Similar V-I characteristics before and after 6 years of service
very little (if any )degradation
PHASE 2 : V-I CURVE
HTS TriaxTM
Lessons Learned
CABLE, TERMINATIONS, SPLICE
1. Technology is robust: thermal cycles and high current transients do not damage the system.
2. HTS wires show no degradation.
3. Need to study effects of PD - does not seem to degrade the system in the short-term.
• Next generation TriaxTM Termination: PDIV > 20kV (2.5U0) in full scale tests.
4. Need to consider higher operating temperatures
• Up to and above 75K
• Data shows no performance degradation
• Enable more efficient cooling systems
5. Ambient temperature has an effect on system heat load
• Improve thermal insulation systems
• Improve current lead designs
HTS TriaxTM
Lessons Learned
INSTRUMENTATION
1. Sensors themselves are robust
• RTD, Thermocouple, Rosemount pressure sensor, differential flow meter: all good
2. Instrumentation transmitters need to be industrial type
• Harsh outdoor environments
• Need protection against transients which are typical in substations
3. Need redundancy
• Protection systems should have more than one point of reference
• Eliminate nuisance trouble alarms and unnecessary shut-downs.
CONTROL SYSTEM
1. Most important: build redundancy into algorithms
• Conservative design for safety is okay, but need to prevent nuisance shut-downs.
HTS TriaxTM
Lessons Learned
COOLING SYSTEM
1. Systems are robust today
• Cryogenic systems are not new, so they are inherently reliable
2. Need full redundancy on active components
• Maintainable / replaceable without system shutdowns
3. Need to monitor and maintain thermal insulation systems
• Source of significant heat load, thus risks to efficiency
• Maintainable without system shutdowns
4. Vibration can be for fixed components
• Mechanical fatigue and failure
5. Simple is good
• Generally, cryogenic experts are required to operate such systems
• Can the LN supply systems be simplified so that anyone can operate it?
6. Need a lot of work on efficiency.
HTS CABLE COMMERICIALIZATION
COMMERCIAL BARRIERS
1. Capital cost still very high
• Today: $15M-$20M per mile
• 5+ Years: $10M-$15M per mile
2. Cryogenics not optimized for cables
• Size reductions are necessary
• Need to be simple to operate
• Expensive to operate – both open and closed-cycle need better efficiency
3. Need factory test capability for cable, terminations and splices
4. Need long-length system studies (greater than 1km)
• Figure how to manage cool-down / recovery times
• Managing heat load
5. Need optimized repair and maintenance schemes
• Today, system repair is on the order of months
• Need to optimize component designs for efficient repair
HTS CABLE COMMERICIAL PROSPECTS
CONGESTED URBAN AREAS
1. Retrofit existing duct-bank
• replace low capacity MV with ultra-high capacity medium voltage
2. Remote substation
• move high voltage facilities to remote areas
• pipe in transmission-level power at medium voltage
3. Substation Inter-tie
• Share substation equipment (transformers)
• Increase redundancy and reliability.
• Avoids the need for extra high voltage infrastructure to meet reliability