Update On CTH. AP (Midway Rd.) & LP Calumet County Highway Department July 15, 2008

Update On CTH. AP (Midway Rd.) & LP

  • Upload
    chavi

  • View
    49

  • Download
    0

Embed Size (px)

DESCRIPTION

Update On CTH. AP (Midway Rd.) & LP. Calumet County Highway Department July 15, 2008. 2008 PROGRESS CTH. LP THROUGH JULY 15 TH. ALL UNDERGROUND WATER, SANITARY & STORM SEWER HAS BEEN INSTALLED AND TESTED ON CTH. LP FROM CTH. AP ROUND-A-BOUT, SOUTH TO WHERE NEW MIDWAY ROAD IS ALIGNED. - PowerPoint PPT Presentation

Citation preview

Page 1: Update On CTH. AP (Midway Rd.) & LP

Update On CTH. AP (Midway Rd.) & LP

Calumet County Highway DepartmentJuly 15, 2008

Page 2: Update On CTH. AP (Midway Rd.) & LP
Page 3: Update On CTH. AP (Midway Rd.) & LP
Page 4: Update On CTH. AP (Midway Rd.) & LP

2008 PROGRESS CTH. LP THROUGH JULY 15TH

• ALL UNDERGROUND WATER, SANITARY & STORM SEWER HAS BEEN INSTALLED AND TESTED ON CTH. LP FROM CTH. AP ROUND-A-BOUT, SOUTH TO WHERE NEW MIDWAY ROAD IS ALIGNED.

• ASPHALT RESTORATION HAS TAKEN PLACE AND THE ROAD IS OPEN TO TRAFFIC.

• ANTICIPATED COUNTY FUNDS = $ 52,383.00

Page 5: Update On CTH. AP (Midway Rd.) & LP

2008 PROGRESS CTH. AP/MIDWAY RD. THROUGH

JULY 15TH • ALL UNDERGROUND WATER, SANITARY &

STORM SEWER HAS BEEN INSTALLED AND TESTED ON THE NEW PORTION OF ROADWAY FROM HUCKLEBERRY LN. EAST TO CTH. LP.

• VEGETATIVE RESTORATION WILL TAKE PLACE AS SOON AS WEATHER PERMITS.

• ANTICIPATED COUNTY FUNDING APPLIED TO THIS PORTION IS $ 32,541.00

Page 6: Update On CTH. AP (Midway Rd.) & LP

2008 PROGRESS CTH. AP/MIDWAY …CONT’D:

• UNDERGROUND WATER, SANITARY & STORM SEWER FROM CTH. LP WEST TO EISENHOWER DRIVE WILL BE COMPLETED IN FALL OF 2008 AS SOON AS ALL AQUISITION OF PROPERTY IS OBTAINED. APPROXIMATE COUNTY FUNDING IS $ 63,168.00

• ROADWAY ALIGNMENT OF MIDWAY NEEDS TO BE SHIFTED SLIGHTLY NORTH DUE TO WETLANDS THAT WERE DISCOVERED DURING THE WETLAND DELINIATION PROCESS THAT WAS PERFORMED BY THE CITY’S CONSULTANT ON THE PROJECT. 3 PARCELS WERE AFFECTED BY THE CHANGE.

• COUNTY FUNDING OF LAND ACQUISITION ON PROJECT FROM HUCKLEBERRY TO EISENHOWER ESTIMATED AT APPROXIMATELY $ 355,000.00.

Page 7: Update On CTH. AP (Midway Rd.) & LP

MIDWAY RD. WEST OF LP

Page 8: Update On CTH. AP (Midway Rd.) & LP

MIDWAY RD. EAST OF CTH.LP

Page 9: Update On CTH. AP (Midway Rd.) & LP

MIDWAY EAST OF CTH. AP

Page 10: Update On CTH. AP (Midway Rd.) & LP

MIDWAY EAST

Page 11: Update On CTH. AP (Midway Rd.) & LP

MIDWAY EAST OF CTH. LP

Page 12: Update On CTH. AP (Midway Rd.) & LP

LOOKING TOWARDS 2009 CTH. LP

FROM CTH. AP ROUND-A-BOUT SOUTH TO NEW MIDWAY ROUND-A-BOUT:

• GRADE, GRAVEL & ASPHALT PLACEMENT

• COUNTY HIGHWAY DEPARTMENT ANTICIPATES PARTNERING WITH OUTAGAMIE COUNTY HIGHWAY ON THE CONSTRUCTION

Page 13: Update On CTH. AP (Midway Rd.) & LP

2009 CONTINUED

• NEW MIDWAY RD. AT INTERSECTION WITH CTH. AP CONCRETE ROUND-A-BOUT INSTALLATION

• NEW MIDWAY RD. AT INTERSECTION WITH CTH. LP CONCRETE ROUND-A-BOUT INSTALLATION

• COUNTY FUNDING ESTIMATED AT APPROXIMATELY $ 425,500.00

Page 14: Update On CTH. AP (Midway Rd.) & LP

2009 CONTNUED

• GRADE, GRAVEL & ASPHALT ON ENTIRE PORTION OF NEW MIDWAY AND CTH. LP FROM CTH. AP TO NEW MIDWAY.

• COUNTY FUNDING APPROXIMATELY $ 491,400.00

Page 15: Update On CTH. AP (Midway Rd.) & LP

LOOKING TOWARDS 2010 CTH. LP

• CTH. LP FROM ROUND-A-BOUT SOUTH TO MIDWAY RD. ROUND-A-BOUT TOP LAYER OF ASPHALT APPLIED BY COUNTY HIGHWAY DEPARTMENT.

Page 16: Update On CTH. AP (Midway Rd.) & LP

LOOKING TOWARDS 2010 CTH. AP/MIDWAY RD.:

• NEW MIDWAY ROAD ALIGNMENT TOP LAYER OF ASPHALT APPLIED FROM HUCKLEBERRY LN. TO EISENHOWER DRIVE APPLIED BY CALUMET COUNTY HIGHWAY DEPARTMENT.

Page 17: Update On CTH. AP (Midway Rd.) & LP

2010 CONTINUED:

• CTH. AP/MIDWAY ROAD ASPHALT REMOVED AND CONCRETE APPLIED FROM KERNAN TO HUCKLEBERRY LN.

• COUNTY FUNDING APPROXIMATELY $ 425,000.00

Page 18: Update On CTH. AP (Midway Rd.) & LP

PROJECT SUMMARY

• CALUMET COUNTY IS CONTINUING TO WORK WITH THE CITY OF APPLETON TO DEVELOP AN INTERGOVERNMENTAL AGREEMENT REGARDING THE PROJECTS. ALL FUNDING LISTED FOR 2009-2010 IS APPROXIMATE BASED ON PROJECTED FIGURES.

Page 19: Update On CTH. AP (Midway Rd.) & LP

QUESTIONS