For more information see http://space.ucsf.edu or contact [email protected] Update April - May 2017 Real Estate, Planning & Capital Programs Parnassus Seismic Renovation Program Clinical Sciences Building (CSB): Soft demolition substantially complete. Currently bidding for contractor for next phase. Next phase of work will resume in late Spring 2017 with hard demolition and construction. Utility Relocation, Phase I: Saunders Court substantially complete. Next phase to resume late Summer 2017 What is happening? The new CSB Anticipated completion date for the renovation is early 2019. See http://space.ucsf.edu/clinical- sciences-building for projected floor plans and learn about open plan workspace design, which combine private offices with flexible open space. CSB 7th Floor demo MRIV completed construction parking lot

Update - Space@UCSF | [email protected] more information see or contact [email protected]. Update. April - May 2017. Real Estate, Planning & Capital Programs. Parnassus

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Update - Space@UCSF | Space@UCSF...For more information see or contact cristina.morrison@ucsf.edu. Update. April - May 2017. Real Estate, Planning & Capital Programs. Parnassus

For more information see http://space.ucsf.edu or contact [email protected]

UpdateApril - May 2017Real Estate, Planning & Capital Programs

Parnassus Seismic Renovation Program

Clinical Sciences Building (CSB): Soft demolition substantially complete. Currently bidding for contractor for next phase. ▪ Next phase of work will resume in late

Spring 2017 with hard demolition andconstruction.

Utility Relocation, Phase I: Saunders Court substantially complete. Next phase to resume late Summer 2017

What is happening?

▪▪

The new CSBAnticipated completion date for the renovation is early 2019. See http://space.ucsf.edu/clinical-sciences-building for projected floor plans and learn about open plan workspace design, which combine private offices with flexible open space.

CSB 7th Floor demo

MRIV completed construction parking lot