Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Upgrade of the Horizontal Test Facility
at FNAL
Michael Tartaglia
LARP/HiLumi Program Management Group
02 August 2017
Stand 4 Refurbishment Plan Overview
• April 2016 Conceptual Design Options & Cost Estimates
– Refinement of previous work dating to 2014 and before
• July 2016 DOE CD-0, emphasis on tunnel ready deliverables
– 1.9K, 18kA, magnetic measurements & alignment
• Working Group Meetings (Nov ‘16, Feb & June ‘17)
– Refinement, discussion of details, cost estimates, schedules
– Still developing integrated schedule w/high level milestones
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL2
Overview
• Follow up on Meeting #2 (2/16/17) [update since 6/8]– Acceptance Requirements, Interfaces from CERN expected January 2018
• Cold Hipot Voltage requirement is expected to be increased to 1800 V.
– Revision of “on” and “off” project scope completed (cryo, mechanical)
– SWF and M&S estimates revised accordingly
– QPM SWF and M&S estimates (FY18 “off project”) evaluated
– Labor and Cost Summary Overview Completed
• Integration of Tom Page “interconnect” estimates in progress [in BOEs]
– Review & Refinement of schedules started, in progress
• Tool for assessing resources and tracking progress
• High Level Milestones still to be added [good progress]
• Test Stand Refurbishment Status– Feedbox Top Plate Insert Removed
– Refurbishment of “15kA” Current Leads well under way[3 leads done]
• [SC lead assembly still to do]
– Procurement of Flexible Leads in progress [Ordered]
– Cryogenic Upgrades will start soon [Quench and K.Pump Started in July]
6/08/2017M. Tartaglia | Stand 4 Refurbishment Status Update3
Upgrades Overview
• Cryogenic and Control/Monitoring Systems
• Mechanical Systems
• Power and Protection Systems
• Magnetic Measurement Systems
Designs led by veterans of the IR Quad test program, joined by
new generation of engineers and scientists to develop upgrades
(but with a different department structure than in the past)
Plans represent understanding of cryo-assembly deliverables
and test acceptance requirements discussed in July 2016
Final acceptance requirements, interface definitions in Jan 2018
Ongoing discussion with CERN to establish ASAP
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL4
T&I FTE Summary
6/08/2017M. Tartaglia | Stand 4 Refurbishment Status Update5
Task Labor Type
FY17
OFF FY17 ON FY17 TOT
FY18
OFF FY18 ON
FY18
TOT
Cryo M-ENG 0.08 0.17 0.25 0.33 0.26 0.59
M-TECH 0.14 0.1 0.24 0.36 0.18 0.54
DESIGNER 0 0.14 0.14 0.08 0.05 0.13
Mechanical M-ENG 0.16 0.16 0.03 0.12 0.15
M-TECH 0.43 0.43 0.3 0.19 0.49
DESIGNER 0 0.13 0.13 0 0.22 0.22
Quench Protection E-ENG 0 0.8 0.8
E-TECH 0 0.57 0.57
S-DEV 0 0.14 0.14
TOTALS BY FY FY17 FY18 TOTAL OFF TOTAL ON
DOES NOT INCLUDE INTERCONNECTS, COMMISSIONING
M-ENG 0.41 0.74 0.44 0.71
M-TECH 0.67 1.03 0.80 0.88
DESIGNER 0.27 0.35 0.08 0.53
E-ENG 0 0.8 0.80 -
E-TECH 0 0.57 0.57 -
S-DEV 0 0.14 0.14 -
BOE Summary
6/08/2017M. Tartaglia | Stand 4 Refurbishment Status Update6
Resource Role Year 1* Notes Estimate Source
Mechanical Technician 2,635Various assembly and fabrication work
Past experience with the old LHC quadrupole
magnets
Mechanical Technician Sr 2,634Various assembly and fabrication work
QC Technician 160 Inspection and QC of test stand components and
equipment
Procurement Specialist 160Procurement and communication with outside vendors
Past experience with the old LHC quadrupole
magnets
Mechanical Engineer 1,568Design of components
Past experience with the old LHC quadrupole
magnets
Mechanical Engineer Sr 1,704Design of components
Cryogenics Engineer 480
Design of cryogenics system components
Past experience with the old LHC and mu2e cryo
systems
Cryogenics Engineer Sr 520
Design of cryogenics system, components
Past experience with the old LHC and mu2e cryo
systems
Electrical Engineer 300Electrical wiring and checkouts
Electrical Engineer Sr 300Electrical wiring and checkouts
Designer 3,248Design and drafting of test stand components
Past experience with the old LHC quadrupole
magnets
Welder 112Welding cryogenics system components
Past experience with the old LHC quadrupole
magnets
T&I ON Project plus interconnect & commissioning estimates (TPage)
*This work is likely to extend into FY19
Test Stand 4 Upgrade – Cryogenics
• The Midway Kinney Pump Room will be used for 1.9 K testing.
– Includes redundant pumping capacity (4 pump skids installed)
– Eliminates costly refurbishment of IB1 Kinney Pump skids
– Only final connections are required to complete the pumping line
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL7
[ In Progress ~40%]
Test Stand 4 Upgrade – Cryogenics
• Buffer Tank 1 will capture quench gas.
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL8
New piping required
Stand 4
[ In Progress ~40%]
Test Stand 4 Upgrade – Cryogenics
• New piping/transfer lines required (controlled DT cool down)
– LN2 supply to bath, GN2 from bath (Vacuum-Jacketed)
– GHe supply lines to bath HX and bath bypass
– Mixed GHe flow to test stand (V-J)
• Modify existing piping
– LHe supply from Storage Dewar
– LHe supply to test stand
• Mass flow control required on 2 GHe supply lines
• Valve and instrument upgrades [started purchases]
• Test stand ‘hardening’ to reduce He losses
• Update insulating vacuum system [purchasing pumps]
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL9
4.5 K LHe Operations – Test Stand Upgrades/Modifications
• Test Stand Cryogenic Controls [Reqs in process FY17]
– Plan to upgrade to new PLC
– All monitoring (T, P, Flow, LL) through PLC modules
• iFix/iHistorian archive, plus gateway to DAQ system archive
– Hipot requirement
• Cryo Assembly Sensor Monitoring
– Automated precision splice measurements
• New Labview/Keithley nV-meter system development [just deployed]
– Will replace old VME/Unix system for T, SG sensors
• Labview-based solutions now under consideration
• Requesting additional resources for this development (MSD)
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL10
Test Stand 4 Upgrade – Control & Monitoring Systems
Cost & Labor Overview
6/08/2017M. Tartaglia | Stand 4 Refurbishment Status Update11
• Cryo (Rabehl) Schedule
Stand 4 Upgrade Summary SWF (Fully Loaded)
M&S (Fully
Loaded)
Weld+MachineShop
M&S (Fully Loaded)
System Task FY17 OFF FY17 ON
FY18
OFF FY18 ON FY17 OFF
FY17
ON
FY18
OFF FY18 ON
FY17
OFF
FY17
ON
FY18
OFF
FY18
ON
Cryo Safety Documentation 5,702 42,527 20,500 0 0 0 0 0 0 0 0
Quench Line 20,621 6,216 16,329
Stand Hardening 6,534 0 3,140
Pumping Line Tie-in 9,118 1,243 6,280
Xfer Line, LN2 to subcooler 14,254 4,973 6,908
GN2 Vent from subcooler 16,303 2,486 6,908
GHe inlet to subcooler 6,499 2,486 5,024
GHe oulet from subcooler to FB 8,558 8,059 0 1,243 0 4,528
Xfer Line, Distribution Manifold 21,204 27,350 6,469
Xfer Line, Storage Dewar to Dist.
Manif. 27,590 27,590 7,459
Insulating Vacuum System 11,433 11,433 24,864 22,378 3,234 3,234
Test Stand Controls PLC Upgrade 102,363 59,674 0
LN2 supply to FB 14,054 4,973 1,941
Valve & Instrument Upgrades 21,783 14,918 3,234
Cryogenic Safety Review 40,999 0 0
TOTALS 41,975 88,141 162,589 116,829 7,459 9,946 139,478 43,512 25,749 18,841 17,162 12,937
• Principal Mechanical Upgrade elements
– Disassemble, refurbish and re-assemble the Feedbox Top Plate insert
• Two “15 kA” AMI vapor-cooled current leads; remove 3rd lead (?)
• New 10 A lead (SSW of ea. Cold mass) + New: 20A TRIM Leads
• 80 K thermal shield and baffles, current lead vacuum sleeves
• Rework LTS bus sections
• Integrate the CLIQ Leads with (6) existing 500 A corrector leads
• Provide enhanced Hipot stand-off voltage of 1.8 kV
– Provide/preserve the ability to perform full aperture Magnetic
Measurements (2 [3 ?] leads at 18 kA) and SSW (10 A) at 1.9K
• Design, fabricate components, and assemble a Warm Finger optimized for
the 150 mm aperture (100 mm diam. Probe)
• Refurbish existing/develop new probe drive, optimized for FERRET probe
• Enlarge Return End opening for larger aperture Warm Finger
– Develop Test Stand Interfaces to Magnet and modify the Feed Box and
Return End Can piping
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL12
Test Stand 4 Upgrade – Mechanical Systems
• Refurbishing the Feed Box
• Note: No modifications to the
Feedbox ASME Code vessel
required
Test Stand 4 Upgrade – Mechanical
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL13
• End Box Interfaces, Adapters
– Mech. interface from the Feed Box and Return end can to the
cryogenic, vacuum, power, and instrumentation features on the cold
mass. [some design, modeling effort already in progress]
• No valves are envisioned in these interface/adaptor “box/es”
• Only comprised of piping, (with provisions for thermal contraction), a
nitrogen cooled thermal shield, and MLI
• If this is a separate “box” at the Feed End then it is likely to remain as a
“permanent” extension of the feedbox after the initial setup and use
– Tasks to Perform: [starting Jan ‘18]
• Develop a Layout and Design for the Lead and Return End Interfaces
• Specify and procure the Adapter/Interface Box/es
• Perform acceptance tests and install
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL14
Test Stand 4 Upgrade – Mechanical
Cost & Labor Overview
6/08/2017M. Tartaglia | Stand 4 Refurbishment Status Update15
• Mechanical (Sylvester) Schedule
Stand 4 Upgrade Summary SWF (Fully Loaded)
M&S (Fully
Loaded)
Weld+MachineShop
M&S (Fully Loaded)
System Task FY17 OFF FY17 ON
FY18
OFF FY18 ON FY17 OFF
FY17
ON
FY18
OFF FY18 ON
FY17
OFF
FY17
ON
FY18
OFF
FY18
ON
Mechanical Feed Box 30,929 15,978 27,005
Lead End Interface Box 32,443 12,432 5,652
Return End Interface Box 20,745 12,432 2,512
Return End Can 12,155 0 3,140
Warm Finger Assembly 41,518 18,648 10,048
Power 44,283 15,751 3,140
Cryostat Supports 48,293 12,432 31,401
Magnetic Meas. Drive System
(Refurb.) 55,248 43,512
TOTALS 0 116,729 55,248 113,635 0 50,377 43,512 37,296 0 40,193 0 42,705
Reminder: Interconnects, commissioning not included here
• 30 kA Power System [in good shape]
– 6 5000 A/ 30V PEI supplies
– Configurable Dump Switch & Resistor (2.5 to 90 W)
• In continuous use at VMTF, very good condition
• Connects to VMTF or Stand 4 via flex water-cooled cables
• Will upgrade to 1500 MCM flex leads [req in process]
• Will perform LCW system maintenance
– (hoses, T-switches, interlocks)
• Hard copper bus is adequate for >20 kA
• Quench Detection System
– Existing VME/Unix system to be completely replaced
• Isolation Amplifiers – replicate new design (in use 4 yrs)
• Redundant AQD and DQD; new AQD designed, now prototyping
– Programmable validation time for spikes
• DQD & Quench Logic in cRio/PXI FPGA-based system with Labview Interface
• Will replicate system currently at Mu2e Solenoid Test Facility, MICE (in use 4 yrs)
• Must develop/improve a new Labview Power Supply Controller w/ QD interface
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL16
Test Stand 4 Upgrade – Power & Protection Systems
• Heater and CLIQ Protection Systems
– Assume CERN will provide heater and CLIQ power supply units
– FNAL interface them to QD system and Test Stand
• CLIQ units in use at VMTF with old QD interface
• New heater interface, number of supplies = 16
• Protection System-Magnet Interfaces
– Hipot requirement
• IsoAmps tested to 1.8 kV
• Current Lead rating – verifying 4.5 kV insulation rating (15kA, 500A)
– Surface re-sealing, GN2 purge in “clam-shells” to prevent moisture
• Existing VT, Heater wires rated much higher, but need testing
• Must test and verify/fix current-limiting resistors
• Potted Instrumentation connectors should be OK; tested to 4 kV pin-pin
– Voltage Taps
• Awaiting decision: Existing Hypertronics in He pipes, vs vacuum feed-throughs
• New Cabling effort; cable length considerations
– Heater Connections
• Same question; how many?
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL17
Test Stand 4 Upgrade – Power & Protection Systems
Cost & Labor Overview
6/08/2017M. Tartaglia | Stand 4 Refurbishment Status Update18
• Quench Protection & Monitoring (Orris)
• T&I Summary (no interfaces & commissioning)
Stand 4 Upgrade Summary SWF (Fully Loaded)
M&S (Fully
Loaded)
Weld+MachineShop
M&S (Fully Loaded)
System Task FY17 OFF FY17 ON
FY18
OFF FY18 ON FY17 OFF
FY17
ON
FY18
OFF FY18 ON
FY17
OFF
FY17
ON
FY18
OFF
FY18
ON
Protection
Systems Quench Protection & Monitoring 0 0 344,047 0 0 0 126,897 0 0 0 0 0
SWF FY17
OFF FY17 ON FY18 OFF FY18 ON
M&S FY17
OFF FY17 ON FY18 OFF FY18 ON
WELD/VMS
FY17 OFF FY17 ON
FY18
OFF FY18 ON ALL
TOTALS $41,975 $204,870 $561,885 $230,464 $7,459 $60,323 $309,887 $80,808 $25,749 $59,034 $17,162 $55,643 $1,655,257
TOTAL OFF
PROJECT $435,334 $317,346 $42,911 $795,591
TOTAL ON
PROJECT $603,860 $141,131 $114,676 $859,667
• Separate BOE exists
• FERRET Probe
– For precision end field
scans
• Translation System
– 2 options considered
• Refurbish Old
• Develop New/modern
– If Refurbish:
• Inspect and/or replace
internal components &
rubber drive belt
• Service pneumatic and
electronic components
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL19
Test Stand 4 Upgrade – Magnetic Measurement Systems
– Magnetic Measurement DAQ solutions exist
• Newly developed SSW software and hardware now deployed
– First of a series in new extensible Labview framework
• Old Rotating Coil DAQ and software can be used
– Some concern about age, reliability, support
• Improved rotating coil system desired
– development in progress
• DAQ and motion control hardware and software
– resource limited effort
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL20
Test Stand 4 Upgrade – Magnetic Measurement Systems
• Test Stand upgrade designs are mature
– Result of considerations that began several years ago
– At the “Advanced Preliminary” level, in good shape for CD-1
– Highly detailed cost/labor estimates and schedules developed
– Risks are low, Project schedule is achievable
– Final design details require final FRS and acceptance requirements
• Cryogenic and Mechanical upgrades have begun
– Quench, Power, Control, Monitoring, Measurement Systems in FY18
• Resource Concerns
– Need to revisit Interface/Commissioning labor needs (Jan ‘18)
• Will Tom Page lead, or other (e.g., LK)?
– Mechanical Technicians
• Progress has been slower than planned due to Mu2e activities
– Electrical Technicians and Engineers
• Big Mu2e commitment on same time scale; techs always a limitation
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL21
Test Stand 4 Upgrade – Conclusions
• Backup Slides
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL22
Test Stand 4 Upgrade – Cryogenics
• The upgraded Stand 4 cryogenic system will allow controlled cool-
down and controlled warm-up
– Successfully implemented at VMTF, MICE/Mu2e Solenoid Test Facility
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL23
Test Stand 4 Upgrade – Cryogenics
• Design aims to minimize
LHe usage by:
– Using an external LN2 bath
for controlled cool-
downs/warm-ups. (repurpose
Tevatron sub-cooler)
– Replumbing the LHe supply
to the test stand to eliminate
the Distribution Box from the
circuit. (very old, high heat
load; build new He transfer
line)
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL24
4.5 K LHe Operations – Test Stand Design
Test Stand 4 Upgrade – Cryogenics
• Controlled cool-down
– Magnet can be cooled from 300 K to 180 K
by mixing 300 K GHe with 80 K GHe from
the LN2 bath (100 K DT). GHe of the
appropriate temperature is supplied to the
feed box GHe supply port.
– The remainder of the controlled cool-down
below 180 K will mix LHe and 80 K GHe in
the feed box tubing.
– Feed box temperature sensor needs to be
added to the insert and located near the
bottom fill port.
• Controlled warm-up
– Warming the magnet using an LN2 bath
and a 100 K DT would not require any LHe.
• Otherwise, Test Stand 4 can operate at
4.5 K as presently configured.
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL25
4.5 K LHe Operations – Test Stand Design
Feed boxGHe supply
L
FC
FCT
Feed boxLHe supply
Test Stand 4 Upgrade – Cryogenics
• 15 kA vapor-cooled leads can operate at 18 kA with sufficient
mass flow. Lower static heat load than new 20 kA leads
– Recently tested at VMTF under varied conditions (He vapor content)
– Demonstrated stable operation up to 20 kA
– Will add a heater in feedbox to assure adequate lead flow
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL26
Projected - LQXF
Stand 4 –
LQXB01
VMTF with 500 liter
dewar supply
VMTF with
cryoplant supply
0.1 V maxallowed
Return End Can (as installed for IR Quads)
• Disassemble the existing End Can
• Machine larger openings (vacuum
vessel and thermal shield) and
flange for HiLumi WF pass through
– WF, probe insertion through Return
End
• Weld Pipe stub and flange
assembly for WF interface/vacuum
seal
• Adapt/re-route existing piping to
match up with cold mass piping
• Relocate bus port to above beam
port
• Re-assemble
Test Stand 4 Upgrade – Mechanical
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL27
• Return End Can Modifications
– Provides a “turnaround” for the
cryogenics and power
• End Box Interfaces, Adapters: Designer Modeling
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL28
Test Stand 4 Upgrade – Mechanical
Feed End1 – Heat Exchg2 – Bus Ports3 – Cooldn Ports4 – Beam Tube5 – Connector Port
12
3
5
4What provisions?Assumed no Service Module
Sliding Ring (O-ring provision)trapped at ends, for mating to vacuum sleeve?
• End Box Interfaces, Adapters: Designer Modeling
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL29
Test Stand 4 Upgrade – Mechanical
Turnaround End
1 – Heat Exchg2 – Bus Ports3 – Cooldn Ports4 – Beam Tube Port5 – Connector Port
1 2
2
3
4
Needed details: port terminations, flange sizes, thermal shield, seal design; beam screen?
Test Stand 4 Upgrade – Mechanical
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL30
• New Vacuum Vessel Supports
Features will include:
• Ability to precisely move the
cryostat assembly in X,Y, and Z;
and to fix the support once desired
movement is achieved
• Ability to stably support the weight
of the cold mass and cryostat
assembly
• Ease of installation and removal
• Note: 25 ton crane capacity
Test Stand 4 Upgrade - Quench Protection Design
– Implement redundancy from the connection to the magnet voltage tap
wires through to the power supply and dump circuit – no single point
failure modes
– Implement a three tier quench protection system
• Tier 1 – Digital Quench Detection (FPGA) will be used for the
Primary QP
• Tier 2 – Analog Quench Detection will be used for the Reductant
QP
• Tier 3 – System Monitor, Logic Analyzer with First Fault Detection,
Fast Logger, Data management
– Standard quench signals include: Whole Coil, Whole Coil – IDot,
Bucked Half Coils, Cu Leads , SC Leads, and Ground Fault
• The two magnet whole coils will be treated as half coils for bucking
• The SC thru bus will have to be protected – Summed with SC
Leads
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL31
Test Stand 4 Upgrade - QD Isolation Amplifiers
Custom Versus Commercial –
– Custom hardware solutions will only be used when necessary
• The isolation amplifiers are a custom design but will be outsourced for
commercial fabrication
• 32 Channel Isolation Amplifier Box: Uses AD215 IA isolation amplifiers
• Fisher HV connectors will be used for the inputs, which will match the
existing test stand 4 HV quench cables
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL32
Test Stand 4 Upgrade – Cryogenics Risk
• Available LHe inventory remains a risk.
– Re-ran the IB1 LHe usage model with the same parameters used
previously….
• 255 l/hr average liquefaction rate
• 8,000 liter usable LHe inventory
• A second liquefier is not installed
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL33
Test Stand 4 Upgrade – Cryogenics Risk
• Available LHe inventory remains a risk.
– …but with updated loads.
• Latest Stand 4 run plan and 18 kA operation (2 x 15 kA leads)
• Only VTS-2 & 3 are used for LCLS-II production testing
• VTS LHe usage rates from operational data
• Interdewar transfer between VTS-2 and VTS-3
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL34
Test Stand 4 Upgrade – Cryogenics Risk
• Results show Stand 4 + 3 VTS-2/3 test cycles/week cannot be
supported.
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL35
Prototype and first 2 Production Production
Test Stand 4 Upgrade – Cryogenics Risk
• Stand 4 + 2 VTS-2/3 test cycles/week also cannot be
supported.
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL36
Prototype and first 2 Production Production
Test Stand 4 Upgrade – Cryogenics Risk
• Support of Stand 4 + 1 VTS-2/3 test cycle/week will require
close coordination of the test programs.
8/02/2017Michael Tartaglia | Upgrade of Horizontal Test Facility at FNAL37
Good days – some inventory margin Bad days – no inventory margin