Upload
andrea-watson
View
214
Download
1
Tags:
Embed Size (px)
Citation preview
US Army Corps of Engineers
BUILDING STRONG®
HSDRRS/MRL ConsiderationsBriefing to Coastal Protection and Restoration Authority Board
Thomas A. Holden Jr., P.E.Deputy for Programs and Project ManagementNew Orleans DistrictU.S. Army Corps of Engineers
27 March 2013
Thomas A. Holden Jr., P.E.Deputy for Programs and Project ManagementNew Orleans DistrictU.S. Army Corps of Engineers
27 March 2013
BUILDING STRONG®
Slide 3
Updates
In March of 2012 briefed CPRAB and identified need to follow up on three items:
1. Overtopping rates above the crossover point 2. Armoring MRL above the crossover point 3. LPV 149 Tie-In to MRL
BUILDING STRONG®
Slide 4
Item 1: Overtopping for 1% Event
Along the west bank of the MRL above RM 85.5 (west bank crossover point) and the east bank above 81.5 (Caernarvon tie-in) there are isolated locations that do not meet the MR&T authorized grade or the1% HSDRRS design elevation
USACE concluded that these locations are acceptable for a positive finding for the Levee System Evaluation Report (LSER) based on:
Average overtopping rates along an entire reach
Performance capabilities of established turf
Capabilities of interior drainage
BUILDING STRONG®
Slide 5
Locations That Do Not Meet 1% HSDRRS Elevation
Slide 5
RM 85.5 West bank crossover point
RM 77.5 East bank crossover point
BUILDING STRONG®
Slide 6
Item 2: Armoring Needs
Armoring is not a requirement for a positive LSER
No authority to armor above the crossover point on the MRL
At the locations that do not meet the 1% design elevation, analysis shows that the overtopping rates for the 500 year event exceed the 0.5 cfs/ft threshold for armoring
Although overtopping rates exceed the armoring threshold, studies at Colorado State show well established turf performs well up to 4 cfs/ft
BUILDING STRONG®
Slide 7
500 yr Overtopping Rates Based on Existing Elevations
Based on 0.2% 50%CI Overtopping MR&T; assumes RM 70 to RM 85.5 constructed to 1% design elevation with EAMsOvertopping rates for 500yr event in cfs/ft
BUILDING STRONG®
Slide 8
Item 3: LPV 149 Tie-In to MRL Higher elevation transition tie-in from HSDRRS floodwall to MRL is necessary (from El +21.5 to
+24.0 feet)
T-wall and earthen levee tie-in options were investigated – earthen tie-in is recommended plan
Work will extend 100 linear feet up river and 30 linear feet down river along the MRL from the T-Wall
65% Design in Progress
Expect to advertise: August 2013
LPV 149 Typical Section HSDRRS and MRL Earthen Levee Tie-in
BUILDING STRONG®
HSDRRS-MRLMississippi River Levees provide risk reduction
Riverine Flood Event
Based on 1973 Project Flood Flowline (refined) plus freeboard
Freeboard can vary for east and west bank
Flood Control Act of 1928 (Authorized MR&T)
1% Hurricane Event
Based on storm surge, coincident river flow, and associated waves
Goal is to provide risk reduction for 1% chance exceedance
Hurricane and river flow are independent events, but both must be considered in analysis
Emergency Supplemental Appropriations Act (4th Supp. 2006) – (Authorized HSDRRS)
Slide 10
BUILDING STRONG®
Orientation - Definitions Crossover Point - The point at which the MR&T authorized design
grade is equal to the 1% HSDRRS design grade
For 2011 this is RM 85.5 on the West Bank and RM 77.3 on the East Bank
The 1% HSDRRS elevations govern downstream and the MR&T elevations govern upstream of this point
HSDRRS-MRL Co-Located - The area along the MRL where HSDRRS and MR&T coexist and HSDRRS design elevations govern
Engineered Alternative Measures - Alternative measures have been constructed to raise the levee height to the 1% elevation while still staying within the existing footprint. EAMs meet LSER requirements
Resilient Features - Construction work which will ensure the WBV-MRLs meet all applicable design and O&M requirements
Slide 11
BUILDING STRONG®12
March 2009
• Draft “Mississippi River Levees Assessment” complete. Identified need to raise MRL for Hurricane events
January 2010
• Design Summit - experts invited to review modeling and design of 1% HSDRRS along the river
April 2010
• Alternatives to raise both east and west bank levees to meet the 1% HSDRRS design grade based on initial modeling completed in March 2009.
July 2010
• Based on design summit revised analysis for modeling waves and how they form on the river.
• Completed quality control and agency technical reviews
• Existing east bank MRL were sufficient
• Work required on west bank MRL to RM 85.5
March 2011
March 2012
• Commitment to complete further analysis on overtopping rates for east and west bank above the crossover points
• Provide SLFPA-E letter addressing several questions and concerns (April 2012)
• Completed analysis of overtopping rates
• No change to work required on MRL for 2011
Timeline
BUILDING STRONG®
Slide 15
2011 Crossover
West Bank RM
85.5
East Bank RM 77.5
Total
15.5 miles 0 miles 15.5 miles
2021 Crossover
West Bank RM
89
East Bank RM 79.5
Total
3.5 miles 0 miles 3.5 miles
2057 Crossover
West Bank RM
95.5
East Bank RM 91
Total
6.5 miles 9.5 miles 16 miles
Miles of work required as crossover point moves upriver in future years
MRL Future Needs
Slide 15
85.5
95.5
77.5 79.581.5
70
91
89
BUILDING STRONG®
Slide 16
ISAAC EOC Briefing Mississippi River Update
West Point a la Hache
IHNC Lock
Carrollton
Baton Rouge
12.4 ft
11.3ft
12.4ft
Still Rising….