Permitting Actions Permitting Actions SequenceSequence

1. 1. Levee District is the Permitting AuthorityLevee District is the Permitting Authority

2. Applicant requests permit from local levee district (letter).2. Applicant requests permit from local levee district (letter).

3. Joint site visit w/Levee District, Corps & applicant if necessary.3. Joint site visit w/Levee District, Corps & applicant if necessary.

4. Corps provides response and recommendation to Levee District 4. Corps provides response and recommendation to Levee District (letter).(letter).

5. Levee District approves or denies request. Copy furnished Corps.5. Levee District approves or denies request. Copy furnished Corps.

Page 3: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Permit Information Permit Information RequiredRequired

1. Description of proposed work1. Description of proposed work Discuss proposed activities near leveeDiscuss proposed activities near levee

excavation, utility crossing, ramp, etc.excavation, utility crossing, ramp, etc. Crossing levee or parallel leveeCrossing levee or parallel levee

2. Site Map 2. Site Map Quad map showing the location of the proposedQuad map showing the location of the proposed Coordinates of work (GPS or Lat. Long.)Coordinates of work (GPS or Lat. Long.) Section, Township, RangeSection, Township, Range

3. Plan Sheet3. Plan Sheet Plan view of proposed work with dimensions from leveePlan view of proposed work with dimensions from levee

4. Profile Sheet4. Profile Sheet Cross section view of work with dimensions from levee.Cross section view of work with dimensions from levee.

Page 4: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Some levee Some levee districts use districts use permit permit application application forms.forms.

Page 5: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Common Permit Actions onCommon Permit Actions onRed River LeveesRed River Levees

Ramp ConstructionRamp Construction

Utility CrossingUtility Crossing

Electric Powerline CrossingElectric Powerline Crossing

Pipeline construction, up-and-over & directional drillingPipeline construction, up-and-over & directional drilling

Excavation adjacent to leveesExcavation adjacent to levees

Page 6: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Ramp Crossing LeveeRamp Crossing Levee

Page 7: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Utility Crossing LeveeUtility Crossing Levee

Page 8: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Pipeline Crossing Pipeline Crossing LeveeLevee

Page 9: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Excavation Near Excavation Near LeveeLevee

Page 10: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Power Pole InstallationPower Pole InstallationRequirementsRequirements

LEVEE

POWERPOLE POWERPOLE

40’ 40’

RIVERSIDE LANDSIDE

MININUM VERTICAL CLEARANCE VOLTS CLEARANCE 0-750 18 FEET 750 -15,000 20 FEET15,000 – 50,000 22 FEET

Page 11: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Directional Drill under Directional Drill under LeveeLevee

without Supporting Soil without Supporting Soil BoringsBorings

Red River

R/S L/S

300’ minimum distanceat maximum depth

25’ minimum depthBelow river bed

Levee

Directional Drill path

Page 12: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Directional Drill Supported Directional Drill Supported with Soil Boringswith Soil Borings

Red River

R/S L/S

300’ minimum distance for penetrating pervious sands

25’ minimum depthBelow river bed

Levee

Pervious SandsDirectional drill path

Page 13: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Directional Drill Exit Directional Drill Exit on Riverside of Leveeon Riverside of Levee

Red River

Levee50 Year Bank Migration Line

Exit point and pipeline to be minimum 10 ft. from levee stability control line at all times.

Directional Drill Path

Min. 10’

R/S L/S

Page 14: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Utility Crossing DetailUtility Crossing Detail

Page 15: US Army Corps of Engineers Vicksburg District Permit Process
Page 16: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Ramp Crossing DetailRamp Crossing Detail

Page 17: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Ramp Crossing DetailRamp Crossing Detail

Page 18: US Army Corps of Engineers Vicksburg District Permit Process

US Army Corpsof Engineers

Vicksburg District

Borrow Pit DetailBorrow Pit Detail