7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
1/65
WATER SUPPLY
PLUMBING II
MOS 21K, SKILL LEVELS 1 AND 2
Subcourse EN5111
EDITION B
United States Army Engineer SchoolFort Leonard Wood, Missouri 65473-8929
11 Credit Hours
Edition Date: April 2005
SUBCOURSE OVERVIEW
This subcourse will enable you to join and install various kinds of pipes that can be used tocomplete the water supply system of a building. Made of different materials, these pipes must becut and the ends prepared for fitting connections to form leakproof joints. These connections aremade with threaded joints, fused joints, and compression joints, depending on the type of pipingmaterial used. As the water supply pipeline runs are installed, they must be supported withhangers and holders. Sometimes, the building structure must be cut into when installing the watersupply pipeline runs for the lavatories, sinks, and water closets. Once a rough-in water supplysystem is installed, it is tested for leaks. This water supply subcourse is presented in two lessons,each corresponding to a terminal learning objective.
Appendix Ccontains a metric conversion chart.
There are no prerequisites for this subcourse.
The lessons reflect the doctrine that was current at the time this subcourse was prepared. In yourown work situation, always refer to the latest official publications.
Unless this publication states otherwise, masculine nouns and pronouns do not refer exclusivelyto men.
TERMINAL LEARNING OBJECTIVE:
ACTION: You will learn to perform tasks related to preparing and connecting pipes
and installing pipeline runs for a water supply system.
CONDITION: You will be given the materials contained in the subcourse.
STANDARD: To demonstrate proficiency, you must achieve a minimum score of 70percent on the subcourse examination.
i
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
2/65
TABLE OF CONTENTS
Subcourse Overview
Lesson 1: Water Supply System and Piping Materials
Part A: Identifying the Types of Piping Materials
Part B: Measuring the Pipes
Part C: Preparing the Piping Materials
Practice Exercise
Lesson 2: Rough-In Water Supplies and Water Supply Pipeline Runs
Part A: Installing Stops (Valves)
Part B: Using Fittings on Water Supply Pipeline Runs
Part C: Installing Water Supply Pipeline Runs
Part D: Supporting Water Supply Pipeline Runs
Part E: Testing the Water Supply System for Leaks
Practice Exercise
Appendix A: List of Common Acronyms
Appendix B: Recommended Reading List
Appendix C: Metric Conversion Chart
EN5111 Edition B Examination
ii
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
3/65
LESSON 1
WATER SUPPLY SYSTEM AND PIPING MATERIALS
Critical Task: 052-248-1002
OVERVIEW
LESSON DESCRIPTION:
This lesson covers the identification, measurement, and preparation of piping materials forinstallation into a water supply system. It also covers the identification of fittings and the use ofjoint connections.
TERMINAL LEARNING OBJECTIVE:
ACTION: You will learn to describe the procedures used to prepare galvanized-steel/iron, plastic, and copper pipes for joint connections.
CONDITION: You will be given the material contained in this lesson.
STANDARD: You will correctly answer the practice exercise questions at the end of thislesson.
REFERENCES: The material contained in this lesson was derived fromField Manual(FM) 3-34.471 and Technical Manual(TM) 5-551K.
INTRODUCTION
A plumber must have the ability to join and install various kinds of pipes that can be used tocomplete the water supply system of a building. These pipes are made of different materials, andmany times they will have to be cut and their ends prepared for fitting connections to formleakproof joints. These connections are made with threaded joints, fused joints, and compressionjoints depending on the type of pipe.
PART A: IDENTIFYING THE TYPES OF PIPING MATERIALS
1-1. Piping Materials. The layout or repair of a water supply system requires that pipes aremeasured to specific lengths, cut, and the cut ends prepared to form joints. Pipe lengths can bemeasured in several ways. The measurement must allow for the pipe engagement into a fittingand the dimension of a fitting. Table 1-1 gives the pipe characteristics and uses in a plumbingsystem.
1-1
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
4/65
Table 1-1. Pipe Characteristics and Uses
SYSTEM
TYPE OF PIPE RIGID FLEXIBLE WATER WASTE
Cast-iron soil pipe:Hub and spigotDouble hubHubless
***
***
Galvanized-steel/iron pipe * * *
Copper tubing:K1
L2
M3
DWV
****
**
***
*
Plastic pipe:PB
PEPVCCPVC4
ABS
***
*
* ***
*
*
1 Thick wall2 Medium wall3 Thin wall4 CPVC is used for cold- and hot-water lines.
a. Galvanized-Steel/Iron Pipe.Galvanized-steel/iron pipe (Figure 1-1) can be usedfor hot- and cold-water supply distribution, certain drainage applications, and vent installations.
It is made from mild carbon steel and is galvanized to prevent rust. It is joined with a threadedjoint in pipe-to-pipe or pipe-to-fitting connections. This pipe comes in three strengths: (1)standard, (2) extra strong, and (3) double extra strong. The definitions Schedule 40 and Schedule80 also describe pipe strengths. Schedule 40 standard is most commonly used in plumbing.Galvanized-steel/iron pipe should not be used underground and should be stored in a dry place. Ifthe pipe ends are threaded, they must be protected from damage. This pipe comes in 21-footlengths.
Figure 1-1. Galvanized-Steel/Iron Pipe
1-2
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
5/65
b. Copper Tubing. Copper tubing (Figure 1-2) is lightweight, easily joined, andcorrosion-resistant. It can be rigid or flexible and it is classified by its wall thickness. It is usedfor hot- and cold-water supply lines, certain drainage applications, and venting. Rigid coppertubing is hard-tempered and comes in 20-foot lengths. It does not bend, so changes in directionmust be made with fittings. Flexible copper tubing is soft tempered, easily bent for changes in
direction, and comes in coils of 40 to 100 feet.
Figure 1-2. Copper Tubing
K is a thick-walled, rigid or flexible copper tubing available in 20-foot lengthsor 100-foot coils. Diameter sizes range from 1/4 inch to 12 inches.
L is a medium-walled, rigid or flexible copper tubing available in 20-footlengths or 100-foot coils. Diameter sizes are the same as K.
M is a thin-walled, rigid copper tubing available in 20-foot lengths. Diametersizes are the same as K.
Drain, waste, and vent (DWV) copper tubing is available in 20-foot lengths.Diameter sizes range from 1 1/4 to 8 inches.
1-3
Rigid
Flexible
LK
LK M
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
6/65
c. Plastic Pipe. Plastic pipe (Figure 1-3) is lightweight and can be rigid or flexible. Itis easily joined and is corrosion-resistant. It can be used for water supply or waste systems. It isused for hot- or cold-water piping and for DWV piping. Plastic pipe is joined with solventcement. Plastic pipe is classified by the acronym for the type of material from which it is made.
(1) Polyvinyl chloride (PVC). PVC pipe is cream or white colored and usedonly for cold-waterlines, sanitary drainage, and venting. It comes in 10- and 20-foot lengths.Diameter sizes range from 1/2 to 6 inches.
(2) Chlorinated polyvinyl chloride (CPVC). CPVC pipe is light or creamcolored and used for hot-waterlines. It can also be used for cold-water lines. It comes in 10-footlengths. Diameter sizes are 1/2 and 3/4 inch.
(3) Acrylonitrile butadiene styrene (ABS). ABS pipe is black or gray and usedfor aboveground and belowground sanitary drainage and venting. It comes in 10- and 20-footlengths. Diameter sizes range from 1 1/4 to 6 inches.
(4) Polybutylene (PB). PB pipe is black or dark gray and used for cold-waterlines. It is available in 100-foot coils or more. Diameter sizes range from 3/4 to 2 inches. It iscostly, requires special fittings, and is not widely used.
(5) Polyethylene (PE). PE pipe is black and used for cold-water lines andsprinkler systems. It comes in 100-foot coils. Diameter sizes range from 3/4 to 2 inches.
NOTE: Check local plumbing codes to determine if the plastic pipe is authorized for
installation.
Figure 1-3. Flexible Plastic Pipe
1-4
PB and PE
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
7/65
d. Engagements. A pipe engagement is the distance the pipe goes into a fitting. Thisdistance is determined by the nominal size diameter of the pipe. Table 1-2 shows the correct pipeengagement into a fitting based on the type of piping material and the nominal size diameter ofthe pipe.
Table 1-2. Pipe Engagement in Fittings
Type of Fitting MaterialNominal Size Diameter
(in inches)Approximate Pipe
Engagement (in inches)
1/81/43/81/23/41
1 1/41 1/2
23
1/43/83/81/29/1611/1611/1611/163/41
1/43/81/23/41
1 1/41 1/2
5/163/81/23/4
15/161
1/18
1/2
3/411 1/41 1/2
234
1/2
5/83/411/1611/163/4
1 1/21 3/4
2345
6
2 1/22 3/4
33
3
1-5
Steel, threaded (pipe-joint compound)
Copper (solder)
Plastic (solvent cement)
Cast-iron (oakum and lead)
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
8/65
e. Fitting Dimension.A fitting dimension is needed when determining the amount ofpipe required for installation. The fitting dimensions for all types of water supply fittings aredetermined in the same way. A fitting dimension is the distance from the center of the fitting tothe end of the fitting (Figure 1-4).
Figure 1-4. Determining a Fitting Dimension
1-6
Fitting dimension
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
9/65
PART B: MEASURING THE PIPES
1-2. Determining Pipe Measurements. Fittings are part of a pipe-run length. The total-lengthmeasurement must include the distance (engagement) a pipe goes into a fitting and the dimensionof the fitting. This part describes determinations and definitions of pipeline runs and plumbing
measurements.
a. End-to-Center Measurement.An end-to-center measurement is the distancebetween the end of the pipe and the center of the fitting. Use the formula: the length of pipeequals the end-to-center measurement minus the fitting dimension plus the pipe engagement(Figure 1-5).Figure 1-6provides an example of the computation used for an end-to-centermeasurement. This method is the same for all types of piping.
Figure 1-5. End-to-Center Measurement
End-to-center = 48 "
Minus fitting dimension = 48 " 1" = 47"
Plus pipe engagement = 47 " + 1/2" = 47 1/2"
Length of pipe = 47 1/2 "
Figure 1-6. Computation Example for an End-to-Center Measurement
1-7
Fitting dimensionEnd-to-center
Pipe engagement
1"
End-to-center
1/2"Pipe
Fitting dimension
Pipe engagement
48"
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
10/65
b. Center-to-Center Measurement. A center-to-center measurement is used whenpipe fittings are on each end of the pipe and is the distance between the centers of the fittings.Use the formula: the length of pipe equals the center-to-center measurement minus both fittingdimensions plus both pipe engagements (Figure 1-7).Figure 1-8 shows the computation used fora center-to-center measurement. This method is the same for all types of piping.
Figure 1-7. Center-to-Center Measurement
Center-to-center = 52 "
Minus both fitting dimensions = 52 " (1 1/4" + 1 1/4")
Plus both pipe engagements = 49 1/2 " + (1/2" + 1/2")
Length of pipe = 50 1/2 "
Figure 1-8. Computation Example for a Center-to-Center Measurement
1-8
Center-to-center
Pipe engagement
Fitting dimension
Pipe
Center-to-center
Pipe engagement
Fitting dimension
Pipe
1/2" 1/2"
52"
1 1/4" 1 1/4"
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
11/65
c. Face-to-Face Measurement. A face-to-face measurement is the distance betweenthe faces of each fitting. Use the formula: length of pipe equals face-to-face measurement plusboth pipe engagements (Figure 1-9).Figure 1-10 shows the computation used for a face-to-facemeasurement. This method is the same for all types of piping.
Figure 1-9. Face-to-Face Measurement
Face-to-face = 46 "
Plus both pipe engagements = 46" + 1/2" + 1/2"
Length of pipe = 47 "
Figure 1-10. Computation Example for a Face-to-Face Measurement
1-9
Face-to-face
Pipe engagement
Pipe
1/2" 1/2"
Face-to-face46"
Pipe engagement
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
12/65
PART C: PREPARING THE PIPING MATERIALS
1-3. Preparing Galvanized-Steel/Iron Pipe for a Joint Connection. The followingprocesses may be required to prepare galvanized-steel/iron pipe for installation: cutting,removing burrs, and threading of the pipe ends.
a. Cutting the Pipe. Table 1-3 explains how to cut a pipe, using a single-wheel pipecutter.
Table 1-3. Cutting the Pipe Using a Pipe Cutter
Step 1. Determine the length of the pipe, and mark the spot for the cut.
Step 2. Lock the pipe tightly in a vise with the cutting mark about 8 inches from the vise.
Step 3. Open the jaws of the cutter by turning the handle counterclockwise.
Step 4. Place the cutter around the pipe with the cutting wheel exactly on the mark. The rollers will ensurethat a straight cut is made.
Step 5. Close the pipe cutter jaws lightly against the pipe by turning the handle clockwise.
Step 6. Give the handle a quarter turn clockwise when the cutting wheel and rollers have made contact
with the pipe.
Step 7.Apply cutting oil, and rotate the cutter completely around the pipe by making a quarter turn on thehandle for each complete revolution around the pipe. Continue the action until the pipe is cut.
NOTE: When a pipe cutter is not available, use a hacksaw and ensure that the cut is as square aspossible to simplify threading the pipe.
1-10
Pipe
Handle
Single-wheel pipe cutter
Cutting wheel
Measured mark
Vise
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
13/65
b. Removing Burrs. Table 1-4 explains how to remove burrs from the cut end of apipe.
Table 1-4. Removing Burrs
Step 1. Lock the pipe tightly in a vise or leave it in the vise from the cutting process.
Step 2. Push the reamer into the pipe.
Step 3. Turn the reamer clockwise in short, even strokes while keeping steady pressure against the pipeuntil all the inside burrs are removed from the cut end.
Step 4. Use a fine-metal file to remove burrs from the outside of the pipe.
1-11
Pipe reamer
Pipe
Vise
Gloves
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
14/65
c. Threading Pipe Ends. Table 1-5 explains how to thread pipe ends.
Table 1-5. Threading Pipe Ends
Step 1. Insert the correct size die into the diestock.
Step 2. Slide the diestock over the pipe, and apply pressure with one hand.
Step 3. Turn the stock handle slowly clockwise (using the other hand) until the die has taken a bite onthe pipe.
Step 4. Apply cutting oil to the die as the stock handle is given one complete clockwise turn and backedoff a quarter turn.
Step 5. Repeat this action until 1/4 inch of the pipe is beyond the diestock. The pipe is now threadedproperly.
Step 6. Turn the handle in a counterclockwise direction to remove the pipe.
NOTE: There are several types of threads, such as fine, course, and plumbing and pipefitting
threads, identified as national pipe threads (NPT). Pipe threads are cut at a taper. Identify pipedies as NPT to ensure that this is the type being used for pipe threading.
1-12
Vise
Steel pipe
Stock handle
Diestock
Gloves
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
15/65
1-4. Preparing Copper Tubing Ends for a Joint Connection. The following processesmaybe required to prepare copper tubing for installation: cutting; removing burrs; and preparingsoldered, flared, mechanical-compression, or swaged joints.
a. Cutting the Copper Tubing. Table 1-6explains how to cut the tubing, using a tubecutter or a fine-tooth hacksaw (32 teeth per inch).
Table 1-6. Cutting the Copper Tubing
Step 1. Determine the length of copper tubing required, and mark the spot for the cut.
Step 2. Set the cutting wheel on the mark, and turn the cutter knob clockwise to get a bite on the tubing.
Step 3. Hold the tubing firmly with one hand, and turn the cutter clockwise around the tubing with theother hand until the tubing is cut.
Step 4. Use a fine-tooth hacksaw if a tube cutter is not available. This requires placing the copper tubingin a miter box to get a square cut.
1-13
Cutting wheelCopper tubing
Tube cutter
Hacksaw
Miter box
Copper tubing
Gloves
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
16/65
b. Removing Burrs. Push the reamer blade into the tubing, and turn the tubingclockwise with even strokes. Continue until all the burrs are removed from the cut end.
c. Preparing a Soldered Joint. Soldered joints are used to connect rigid coppertubing.Figure 1-11 displays the tools and materials needed.
Figure 1-11. Tools and Materials Needed for Soldered Joints
1-14
Emery clothSolder wire
Flux and brush
Propane torch
Wire brushSteel wool
FLUX
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
17/65
d. Preparing a Flared Joint. A flared joint is used with flexible copper tubing. Theflare on the end of the tubing can be made with a flaring tool or a flanging tool.Figure 1-12displays the tools needed to prepare a flared joint.
Figure 1-12. Tools Needed for a Flared Joint
1-15
Flaring tool
Flanging tool
Flared fitting
Flared end
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
18/65
e. Preparing a Mechanical-Compression Joint. A mechanical-compression joint isused to connect a fixtures water supply tubing to the shutoff valves.Figure 1-13 shows amechanical-compression joint.
Figure 1-13. Materials Needed for a Mechanical-Compression Joint
f. Preparing a Swaged Joint. A swaged joint is used to connect two sections of rigidthin-walled copper tubing without using a fitting. The tools required are a swaging-tool set and a
ball-peen hammer.Figure 1-14 displays the tools needed to prepare the tubing for a swaged joint.
Figure 1-14. Tool Needed for a Swaged Joint
1-16
Fitting
TubingCompression ring
Compression nut
Swaging-tool set
Ball-peen hammer
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
19/65
1-5. Preparing Rigid and Flexible Plastic Pipes for Joint Connections. The followingprocesses maybe required to prepare plastic pipe for installation: cutting, removing burrs, andpreparing joints. Table 1-7explains how to cut plastic pipe and remove burrs for jointpreparation.
Table 1-7. Cutting Plastic Pipe and Removing Burrs
Step 1. Determine the length of pipe required, and mark the spot for the cut.
Step 2. Place the pipe in a miter box. and cut the pipe with a hacksaw or fine-tooth handsaw. Use a miterbox to get a square cut.
Step 3. Remove burrs from both the inside and outside of the pipe with a pocketknife. Use sandpaper if apocketknife is not available.
1-17
Hacksaw Pipe
Miter box
Pocketknife
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
20/65
LESSON 1
PRACTICE EXERCISE
Instructions: The following items will test your grasp of the material covered in this lesson.There is only one correct answer for each item. When you complete the exercise, check youranswers with the answer key that follows. If you answer any item incorrectly, restudy that part ofthe lesson that contains the portion involved.
1. Identify the type of piping that is not used in a water supply system.
A. Cast-iron
B. Copper tubing
C. Galvanized-steel/iron
D. Plastic
2. Refer to Table 1-8. What is the pipe engagement for 3/4-inch steel, threaded pipe?
A. 3/8 inch
B. 3/4 inch
C. 9/16 inch
D. 11/16 inch
Table 1-8. Pipe Engagement
Pipe Size(in inches)
Approximate Engagement Into a Hub(in inches)
3/81/23/41
1 1/4
3/81/2
9/1611/1611/16
1-18
Steel, threaded (pipe-joint compound)
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
21/65
3. Refer toFigure 1-15. What is the required length of pipe needed when using aface-to-face measurement?
A. 50 1/2 inches
B. 51 1/2 inches
C. 52 1/2 inches
D. 53 1/2 inches
Figure 1-15. Determining Length of a Pipe
4. Which fitting shown inFigure 1-16shows a correct fitting dimension?
Figure 1-16. Fitting Dimension
1-19
A
B
C
D
Pipe
3/4" 3/4"
Face-to-face52"
Pipe engagement
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
22/65
5. When do you apply the cutting oil in threading a galvanized-steel/iron pipe?
A. Before you begin
B. After each complete turn
C. After each complete turn and backed off a quarter turn
D. After each complete turn and backed off a half turn
6. Refer toFigure 1-17. What is the length of pipe when you use an end-to-centermeasurement?
A. 47 3/4 inches
B. 45 3/4 inches
C. 44 3/4 inches
D. 43 3/4 inches
Figure 1-17. Determining Length of a Pipe
7. What tool is used to cut galvanized-steel/iron pipe?
A. Cross saw
B. Pipe saw
C. Pipe cutter
D. Rip saw
1-20
4"
1 3/4"
48"
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
23/65
8. What two tools are used to flare the ends of flexible copper tubing?
A. Swaging and flanging
B. Flaring and flanging
C. Swaging and flaring
D. Flanging and swatting
9. What tool is used to cut plastic pipe?
A. Knife
B. Hacksaw
C. Coping saw
D. Back saw
10. What type of plastic pipe can be used on both a water supply system and a waste system?
A. ABS
B. PB
C. PE
D. PVC
1-21
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
24/65
LESSON 1
PRACTICE EXERCISE
ANSWER KEY AND FEEDBACK
1. Identify the type of piping that is not used in a water supply system.
A. Cast-iron (Table 1-1)
B. Copper tubing
C. Galvanized-steel/iron
D. Plastic
2. Refer to Table 1-8. What is the pipe engagement for 3/4-inch steel, threaded pipe?
A. 3/8 inch
B. 3/4 inch
C. 9/16 inch (Table 1-2)
D. 11/16 inch
Table 1-8. Pipe Engagement
Pipe Size(in inches)
Approximate Engagement Into a Hub(in inches)
3/81/2
3/41
1 1/4
3/81/2
9/1611/1611/16
1-22
Steel, threaded (pipe-joint compound)
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
25/65
3. Refer toFigure 1-15. What is the required length of pipe needed when using aface-to-face measurement?
A. 50 1/2 inches
B. 51 1/2 inches
C. 52 1/2 inches
D. 53 1/2 inches (paragraph 1-2c and Figure 1-10)
Figure 1-15. Determining Length of a Pipe
4. Which fitting shown inFigure 1-16shows a correct fitting dimension?
Figure 1-16. Fitting Dimension
1-23
A
B (paragraph 1-1eand Figure 1-4)
C
D
Pipe
3/4" 3/4"
Face-to-face52"
Pipe engagement
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
26/65
5. When do you apply the cutting oil in threading a galvanized-steel/iron pipe?
A. Before you begin
B. After each complete turn
C. After each complete turn and backed off a quarter turn (Table 1-5)
D. After each complete turn and backed off a half turn
6. Refer toFigure 1-17. What is the length of pipe when you use an end-to-centermeasurement?
A. 47 3/4 inches
B. 45 3/4 inches (paragraph 1-2a and Figure 1-6)
C. 44 3/4 inches
D. 43 3/4 inches
Figure 1-17. Determining Length of a Pipe
7. What tool is used to cut galvanized-steel/iron pipe?
A. Cross saw
B. Pipe saw
C. Pipe cutter (paragraph 1-3a and Table 1-3)
D. Rip saw
1-24
4"
1 3/4"
48"
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
27/65
8. What two tools are used to flare the ends of flexible copper tubing?
A. Swaging and flanging
B. Flaring and flanging (paragraph 1-4d and Figure 1-12)
C. Swaging and flaring
D. Flanging and swatting
9. What tool is used to cut plastic pipe?
A. Knife
B. Hacksaw (Table 1-7)
C. Coping saw
D. Back saw
10. What type of plastic pipe can be used on both a water supply system and a waste system?
A. ABS
B. PB
C. PE
D. PVC (Table 1-1)
1-25
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
28/65
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
29/65
LESSON 2
ROUGH-IN WATER SUPPLIES AND WATER SUPPLY PIPELINE RUNS
Critical Task: 052-248-1002
OVERVIEW
LESSON DESCRIPTION:
This lesson covers the installation of stops (valves) and fittings on water supply pipeline runs.This lesson also covers the installation and support of these pipeline runs during the buildingconstruction phase and testing the water supply system for leaks.
TERMINAL LEARNING OBJECTIVE:
ACTION: You will learn to describe the procedures used to connect, install, andsupport a rough-in water supply system.
CONDITION: You will be given the material contained in this lesson.
STANDARD: You will correctly answer the practice exercise questions at the end of thislesson.
REFERENCES: The material contained in this lesson was derived fromFM 3-34.471 andTM 5-551K.
INTRODUCTION
As the water supply pipeline runs are installed with fittings, they must be supported with hangersand holders. Many times, a plumber must cut into the building structure to place water supplypipeline runs to service lavatories, sinks, and water closets that are to be installed. The plumberalso tests the rough-in water supply system for leaks when it is completely installed.
2-1
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
30/65
PART A: INSTALLING STOPS (VALVES)
2-1. Stops. A water supply service starts outside the building at the water main and then entersthe building. Tap the water main with a self-tapping machine, and lay a water service line withstops (valves) to enter the building in the basement or crawl space. The water supply service
water line to a building has three stops: corporation, curb, and meter (Figure 2-1).
Figure 2-1. Corporation, Curb, and Meter Stops
a. Installing a Corporation Stop. Water mains are usually cast iron, 8 inches or morein diameter. If the main is less than 8 inches in diameter, the tap should be 2 inches or smaller.Table 2-1 explains how to tap into a water main and install a corporation stop, using a water-main self-tapping machine.
2-2
Curbstop
Shutoff (gate valve)
Meter stop
Building foundationCorporation stop
Stopbox
Water main
RoadGrade
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
31/65
Table 2-1. Tapping a Water Main
Step 1. Dig to expose the pipe at the point where the tap is to be made. Dig as close to the top of thewater main as possible.
2-3
Ratchet handle
Boring bar
Feed yoke
Friction collar
Cap
Cylinder
Flap-valve handle
Saddle
Gasket
Water main
Bypass
Combination drill and tap
Flap valve
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
32/65
Step 2. Clean all dirt and rust off the pipe at the point.
Step 3. Place the gasket of the water-main self-tapping machine on the pipe, and set the saddle of themachine on the gasket.
Step 4. Wrap the chain around the pipe, and tighten it to clamp the water main self-tapping machine to thepipe.
Step 5. Remove the cap from the cylinder of the machine, and place the combination drill and tap in theboring bar.
Step 6. Reassemble the machine by putting the boring bar through the cylinder and tightening the cap.
Step 7. Open the flap valve between the compartments.
Step 8. Start drilling the hole by applying pressure at the feed yoke and turning the ratchet handle until thedrill enters the main.
Step 9. Back off the feed yoke when the tap starts threading the hole to prevent stripping the threads.
Step 10. Continue to turn the boring bar until the ratchet handle can no longer be turned without extraforce.
Step 11. Remove the tap from the hole by reversing the ratchet. Then back the boring bar out by turning itcounterclockwise.
Step 12. Close the flap valve between the upper and lower compartments.
Step 13. Drain the water from the cylinder through the bypass.
Step 14. Remove the cap and drill tool. Place a corporation stop in the boring bar, ensuring that the stopis closed.
Step 15. Repeat steps 6 and 7.
Step 16. Turn the ratchet handle to thread the corporation stop into the pipe.
Step 17. Repeat step 13.
Step 18. Remove the cap from the cylinder, and unbolt the boring bar from the corporation stop.
Step 19. Remove the lower chamber from the pipe.
Step 20. Inspect for leaks.
Step 21. Tighten the corporation stop with a suitable wrench, if it leaks.
2-4
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
33/65
b. Installing a Curb Stop. Curb and meter stops control the water entering thebuilding. Table 2-2 explains how to install a curb stop.
Table 2-2. Curb Stop
Step 1. Position the curb stop in a suitable place between the curb and the building.
Step 2. Set the curb stop in a cast-iron stop box that has a variable telescopic length.
Step 3. Join the curb stop to the service piping with a compression joint when using copper tubing for thewater service.
NOTE: The curb stop provides a shutoff of the water supply outside a building.
2-5
Curb stop
BuildingEarth grade
CurbStreet
Stop box
Water service line
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
34/65
c. Installing a Meter Stop. After running the water service lines through the side ofthe building and closing the holes around the service pipe with waterproof cement, install thewater meter and meter stop. The meter stop is a ground-joint valve, which controls and shuts offthe flow of water into the building. Table 2-3 explains how to install a meter stop.
Table 2-3. Meter Stop
Step 1. Place the meter stop as near as possible to where the water service pipe enters the building.
Step 2. Position the water meter near the meter stop valve.
Step 3. Open the meter stop valve to measure the amount of water being used in the building.
2-6
Shutoff (gate valve)
Meter stop
Building foundation
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
35/65
PART B: USING FITTINGS ON WATER SUPPLY PIPELINE RUNS
2-2. Galvanized-Steel/Iron Fittings. This part shows threaded drainage fittings used forgalvanized-steel/iron pipes and explains how to make a threaded joint connection. Ts(Figure 2-2) are used when a water supply pipeline run branches at a 90-degree angle. Elbows
(Figure 2-3) are used to change the direction of a water supply pipeline run. Couplings(Figure 2-4) are used to connect two lengths of pipe.
Figure 2-2. Ts
Figure 2-3. Elbows
2-7
Branch
Run Outlet
Branch
BranchRun
OutletOutlet
Side-outlet T
Run
Reducing T (external) Reducing T (internal)
Standard T
NOTE: Branch and run can be reversed.
90 elbow 45 elbow
Y-elbow(or side-outlet elbow)
Reducing elbowStreet elbow
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
36/65
Figure 2-4. Couplings
2-3. Joint Connections. The threads of drainage fittings are at a slight angle (Figure 2-5).This angle causes horizontal drainage pipes to slope about 1/4 inch per foot. Table 2-4explainshow to make a threaded joint connection.
Figure 2-5. Slope of Horizontal Drainage Pipes
2-8
Standard coupling Reducing coupling Eccentric reducing coupling
Extension piece
Fitting
1/4" slope per foot
90 angle
Pipe
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
37/65
Table 2-4. Making a Threaded Joint Connection
Step 1. Check the fitting threads for cleanliness and damage. If necessary, clean with a wire brush orreplace the fitting.
Step 2. Repeat step 1 for the pipe threads.
Step 3. Apply pipe joint compound or Teflon tape to the pipe threads only.
Step 4. Screw the fitting on hand tight.
Step 5. Tighten the fitting, using two pipe wrenches. Use one pipe wrench on the fitting and theother on the pipe, turning clockwise.
2-9
Wrench
Pipe JointCompound
Pipe threads
Pipe Fitting
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
38/65
2-4. Copper Fittings. Various types of copper tubing fittings for soldered and compressionjoints are shown inFigure 2-6. The preparation for each type of joint will be described in greaterdetail.
Figure 2-6. Fittings for Copper Tubing
2-10
Female adapterMale adapter Coupling
T45 elbow90 elbow
Male adapter Female adapter Coupling
45 elbow90 elbowT
Solder Fittings
Copper Compression Fittings
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
39/65
2-5. Joint Connections for Copper Tubing. There are several different types of joints forcopper tubing. A soldered joint is used to connect rigid copper tubing; a flared joint is used withflexible copper tubing; a mechanical-compression joint is used with flexible copper tubing toconnect the water supply tubing of a fixture to the shutoff valve; and a swaged joint is used toconnect two sections of rigid thin-walled copper tubing without using a fitting.
a. Soldered Joint. Soldered joint connections for copper tubing are made with flux,solder, and a heat source. The flux permits even spreading of molten solder over the surfacessoldered. The molten solder flows into the space between the fitting and the tubing. Table 2-5explains how to make a soldered joint.
Table 2-5. Soldered Joint
Step 1. Inspect the end of the tubing to be sure it is round, free of burrs, and cut square.
Step 2. Clean the outside end of the tubing and the inside of the fitting to a bright shine with emery cloth orfine steel wool.
Step 3. Apply a thin coat of flux to the shined end of the tubing and fitting.
Step 4. Push the fitting on the tubing, and give it a quarter turn to spread the flux evenly.
Step 5. Heat the connection with a torch, applying the flame on the fitting.
Step 6. Apply the solder to the joint when the flux is bubbling. The solder will flow into and completelyaround the joint.
Step 7. Clean the joint, using a clean rag.
NOTE: A well-soldered joint should have an even bead around the entire joint.
2-11
Flux
50-50Solder
Torch
Fitting
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
40/65
b. Flared Joint. A flared joint is used with flexible copper tubing. The flare on theend of the tubing can be made with a flaring or flanging tool. Table 2-6explains how to make aflared joint, using a flaring tool or a flanging tool.
Table 2-6. Flared Joint
Step 1. Inspect the end of the tubing to ensure that it is free of burrs and is cut square.
Step 2. Remove the flange nut from the fitting, and slide its unthreaded end onto the tubing first.
Step 3. Flare the end of the tubing with either a flaring tool or a flanging tool.
Flaring tool method. Loosen the wing nuts on the flaring tool, and place the tubing in thecorrect size hole. Make the tubings end even with the tools surface. Tighten the wing nuts.Turn the yoke cone down into the tubing until the flare fills the beveled pad of the hole.
Flanging tool method. Hold the flanging tool on the end of the tubing so it is centered andstraight. Tap the flanging tool, using a ball-peen hammer, until the flare fills the recess in theflanging nut.
Step 4. Slide the flare/compression nut up to the flared end, and screw it on the fitting hand tight, thentighten the flare/compression nut.
2-12
Nut wing
Flaring tool
Copper tubing
Ball-peen hammer
Flanging tool
Flange nut
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
41/65
c. Mechanical-Compression Joint. A mechanical-compression joint is used withflexible copper tubing to connect the water supply tubing of a fixture to the shutoff valve.Table 2-7explains how to complete a mechanical-compression joint.
Table 2-7. Mechanical-Compression Joint
Step 1. Cut or bend the tubing to the required length.
Step 2. Slide the compression nut onto the tubing.
Step 3. Slide the compression ring onto the tubing.
Step 4. Screw the compression nut onto the fitting by hand.
Step 5. Tighten the nut. The ring compresses to form a sealed leakproof joint.
2-13
Fitting
TubingCompression ring
Compression nut
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
42/65
d. Swaged Joint. A swaged joint is used to connect two sections of rigid thin-walledcopper tubing without using a fitting. The connection is soldered to form a leakproof joint. Thetools required are a swaging-tool set and a ball-peen hammer. Table 2-8 explains how tocomplete a swaged joint.
Table 2-8. Swaged Joint
Step 1. Inspect the tubing end to make sure it is free of burrs and is cut square.
Step 2. Place the correct size swaging tool into the tubing (with one hand), centered and straight.
Step 3. Tap the swaging tool firmly with the ball-peen hammer to enlarge the end of the tubing.
Step 4. Connect the two sections of tubing, and solder the joint.
2-14
Swaged end
Swaging tool
Swaging tool
Copper tubing
Ball-peen hammer
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
43/65
2-6. Fittings for Rigid and Flexible Plastic Pipe. The various types of fittings for rigid andflexible plastic pipes are shown inFigure 2-7. The preparation for each type of pipe and fittingattachment will be described in greater detail.
Figure 2-7. Fittings for Rigid and Flexible Plastic Pipes
2-15
Solvent Weld
Slip
Sanitary Pipe
Long sweep TYVent TSanitary T
T 90 elbow Coupling Male adapter
Coupling45 elbow90 elbowT
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
44/65
a. Completing a Solvent-Cement Weld Joint. This joint is made by using a cleaningprimer and solvent cement on the pipe and fitting. Solvent cement consists of a plastic filler(same material for each type of plastic pipe) dissolved in a mixture of solvents. Use theappropriate solvent cement for the type of pipe being used. The solvent cement melts the plasticof the pipe and the fitting to weld them together. Since solvent cement sets fast, a plastic pipe
joint is completed quickly. Table 2-9 explains how to join rigid plastic pipe with a solvent-cement weld joint.
Table 2-9. Solvent-Cement Weld Joint
Step 1. Inspect the pipe end for burrs and the fitting for cracks.
Step 2. Clean the pipe and the inside of the fitting with an authorized cleaning primer, using a clean rag.
Step 3. Coat the outside of the pipe end and the inside of the fitting with solvent cement.
Step 4. Push the pipe as quickly as possible into the fitting as far as it will go. A small bead of cement willbe visible.
Step 5. Give the fitting a quarter turn to spread the solvent cement evenly.
Step 6. Hold the joint connection for about 30 seconds to be sure it is solidly set.
Step 7. Wipe off all excess cement.
2-16
Solvent cement
Fitting
Pipe
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
45/65
b. Completing an Insert Fitting Joint. This joint is made by sliding and clampingflexible plastic pipe onto an insert fitting. Table 2-10 explains how to join flexible plastic pipewith an insert fitting joint.
Table 2-10. Insert Fitting Joint
Step 1. Slide a clamp over the flexible pipe.
Step 2. Push the pipe onto the insert fitting to the last serration.
Step 3. Slide the clamp over the pipe, and tighten the clamp with a screwdriver.
PART C: INSTALLING WATER SUPPLY PIPELINE RUNS
2-7. Water Supply Pipeline Runs. Install the water supply pipeline runs during the buildingconstruction. The following steps will make it easier to rough-in water supply pipeline runs withfittings, support these pipeline runs, and test the rough-in water supply system joints for leaks.
The water supply pipeline runs consist of distribution lines, branch lines, and riser lines that willservice the fixtures or equipment.
a. Main Distribution Lines. Install this waterline, with all fittings required for thebranch lines, between or through the floor joist from the meter stop. The pipe size will be thesame as the water service line.
2-17
Clamp
Flexible pipe
Insert fitting
Clamp
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
46/65
b. Branch Lines. From the fittings on the distribution line, install the branch linesbetween or through the floor joist to those fixture points that the fixture riser lines will service.
c. Fixture Riser Lines. Table 2-11 shows how the different waterlines connect tocomplete the water supply system and explains how to install fixture supply pipe risers.
Table 2-11. Main Distribution, Branch, and Fixture Riser Lines
Step 1. Install fixture supply pipe risers from the branch line fittings by drilling holes through the sole plate orfloor.
Step 2. Set the risers with fittings to connect the water supply.
Step 3. Set the air chamber to control the pipe noise.
2-18
Cold-water distribution line from meter stop
Cap
Air chamber
T
Wall stud
Sole plate
Fixture riser line
T with nipple anda 90 elbow
Branch line
Floor joist
90 elbow
Hot-water distribution line from water heater
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
47/65
2-8. Water Supply Pipeline Runs.
a. Installing Water Supply Pipeline Runs Through a Floor Joist. Table 2-12 explainshow to install rough-in water supply pipeline runs through a floor joist.
Table 2-12. Installing Water Supply Pipeline Runs
Step 1. Determine which water supply pipeline runs require installation through the floor joist.
Step 2. Find the center of the floor joist.
Step 3. Drill a hole through the center of the joist. The hole cannot be larger than 1/4 of the depth of thejoist. For example, if you are using a 2- by 8-inch joist, the hole cannot be any larger than 2 inches.
2-19
Hole
Floor joist
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
48/65
b. Notching and Bracing a Joist. Notches can be at the top or bottom of a joist. Thenotch width should be slightly larger than the outside diameter of the pipe. Table 2-13 explainshow to cut a notch in a joist and to brace the joist.
Table 2-13. Notching and Bracing a Joist
Step 1. Determine the width of the notch.
Step 2. Cut both sides of the notch to the proper depth with a handsaw. The notch depth can be no morethan a quarter of the joist depth. For example, if the joist depth is 8 inches, then the maximum notch depthwould be 2 inches (1/4 of 8 = 2)
Step 3. Use a hammer and a sharp wood chisel to cut away the wood between the notch cuts.
Step 4. Place a 2- by 2-inch board on each side of the joist when the notch is on the top.
Step 5. Center boards under the notch and nail in place.
Step 6. Center a steel plate over the notch when it is on the bottom of the joist.
Step 7. Nail the plate into place.
2-20
Handsaw2" x 8" floor joist
Wood chisel
Width of the notch
Depth of thenotch
2" x 2" boards
Steel plate
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
49/65
c. Cutting and Bracing a Wall Stud. Table 2-14 explains how to cut and brace a wallstud.
Table 2-14. Cutting and Bracing a Wall Stud
Step 1. Cut the notch from the top or bottom half of the stud. A notch cut from the top cannot be greaterthan 1/2 of the depth of the stud. A notch cut from the bottom cannot be greater than 1/3 of the depth ofthe stud.
Step 2. Ensure that the width of the cut-out notch is able to take the pipe size to be installed.
Step 3. Measure the depth of the wall stud before cutting notches.
Step 4. Brace all notch cuts in the wall studs with water supply pipeline runs.
Step 5. Ensure that the studs with the notch cuts have a steel plate centered over the notch.
Step 6. Nail the plate into place.
2-21
Wall stud
Depth of stud
Width of thenotch basedon pipe size
Depth of notch
Brace steel plate
Pipeline run
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
50/65
PART D: SUPPORTING WATER SUPPLY PIPELINE RUNS
2-9. Pipe Supports. Horizontal and vertical water supply pipeline runs with fittings must besupported. The length of the pipeline runs, their locations, and the joints will determine where toplace the pipe supports. There are many types of pipe supports designed to hang or support the
pipeline run (Figure 2-8). The building material and types of pipes will, in many cases, determinethe kind of supports to use.
Figure 2-8. Pipe Hangers
2-22
Pipe strap
Wall hanger
Adjustable hanger
Common hanger
Common hanger
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
51/65
a. Supporting Horizontal Water Pipes. Use tube clamps, U-hooks or self-nailinghooks, perforated bands, and one-hole clamps to support a horizontal water supply pipeline runto a joist.Figure 2-9 shows these types of pipe supports.
Figure 2-9. Supporting Horizontal Water Pipes
2-23
Tube clamp
One-hole clamp
Pipe
Joist
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
52/65
b. Supporting Vertical Water Pipes. Use wood blocking to attach the pipe supports(Figure 2-10). The pipe supports that can be used to support a vertical water piping run are tubeclamps, one-hole clamps, and perforated bands.
Figure 2-10. Supporting Vertical Water Pipes
2-24
Stud
Sole plate
Pipe
Wood blocking
Tube clamp
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
53/65
PART E: TESTING THE WATER SUPPLY SYSTEM FOR LEAKS
2-10. Water Supply System Test. Once the rough-in water supply system is completed, testthe system for leaks, using the water test or air test. Locate and repair any leaks at once, andretest the system.
a. Water Supply System Test. Table 2-15 explains how to test a system with water.
Table 2-15. Water Supply System Test
Step 1. Seal the branches and vent lines, and place a test plug in the test T.
Step 2. Fill the system with water, and check for a drop in the water level.
Step 3. Check each joint for leaks if the water level drops noticeably. The test is satisfactory if the waterlevel does not fall more than 4 inches in a 30-minute period.
Step 4. Make leaking joints watertight, and replace any defective material.
2-25
Cap
All T openings are capped
during the test
Wall stud
Sole plate
T with nipple anda 90 elbow
From meter stop
Floor joist
90 elbow
From water heater
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
54/65
b. Air Test. A special plug, through which air is pumped into the watersupply system, is required for this test. Perform an air test, using the following steps:
Step 1. Apply an air pressure of about 5 pounds per square inch (measured by agauge).
Step 2. A drop in the mercury column on the gauge shows a leaky joint. In asatisfactory test, the line should hold 5 pounds per square inch for 15 minutes.
Step 3. Listen for the sound of escaping air to help locate leaks. If no sound isheard and pressure is falling, apply a soap solution to the joints in the area of theleak. If there is a leak, bubbles will form.
2-26
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
55/65
LESSON 2
PRACTICE EXERCISE
Instructions: The following items will test your grasp of the material covered in this lesson.
There is only one correct answer for each item. When you complete the exercise, check youranswers with the answer key that follows. If you answer any item incorrectly, restudy that part ofthe lesson that contains the portion involved.
1. Identify which of the following is not a stop for a service water line to a building.
A. Building stop
B. Corporation stop
C. Curb stop
D. Meter stop
2. Which of the following stops shuts off the water supply outside of the building?
A. Building stop
B. Corporation stop
C. Curb stop
D. Meter stop
3 Where is the pipe joint compound applied for a threaded drainage fitting joint for
galvanized-steel/iron pipe?
A. Fitting threads only
B. Pipe threads only
C. Pipe and fitting threads
D. All threads
4. Where is the heat applied to make a soldered joint for copper tubing?
A. Pipe
B. Flux
C. Fitting
D. Solder
2-27
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
56/65
5. Identify which of the following is not a type of copper tubing joint connection.
A. Soldered joint
B. Flared joint
C. Mechanical-compression joint
D. Solvent-cement weld joint
6. What is the largest-sized hole that can be drilled though the center of a 2- by 8-inch floorjoist for a pipeline run?
A. 1 inch
B. 2 inches
C. 3 inches
D. 4 inches
7. What is the maximum depth that a notch can be cut in a floor joist?
A. 1/4 of the joist depth
B. 1/3 of the joist depth
C. 1/2 of the joist depth
D. 2/3 of the joist depth
8. What is the maximum depth that a notch can be cut at the bottom of a wall stud?
A. 1/4 of the depth of the stud
B. 1/3 of the depth of the stud
C. 1/2 of the depth of the stud
D. 2/3 of the depth of the stud
2-28
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
57/65
9. What is used to brace the bottom of a joist or the lower half of a wall stud?
A. Steel plate
B. Wood blocking
C. Pipe strap
D. Plastic plate
10. What is the number of minutes water is kept in a rough-in water supply system during awater test?
A. 15
B. 20
C. 25
D. 30
2-29
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
58/65
LESSON 2
PRACTICE EXERCISE
ANSWER KEY AND FEEDBACK
1. Identify which of the following is not a stop for a service water line to a building.
A. Building stop (paragraph 2-1 and Figure 2-1)
B. Corporation stop
C. Curb stop
D. Meter stop
2. Which of the following stops shuts off the water supply outside of the building?
A. Building stop
B. Corporation stop
C. Curb stop (Table 2-2)
D. Meter stop
3 Where is the pipe joint compound applied for a threaded drainage fitting joint forgalvanized-steel/iron pipe?
A. Fitting threads only
B. Pipe threads only (Table 2-4)
C. Pipe and fitting threads
D. All threads
4. Where is the heat applied to make a soldered joint for copper tubing?
A. Pipe
B. Flux
C. Fitting (Table 2-5)
D. Solder
2-30
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
59/65
5. Identify which of the following is not a type of copper tubing joint connection.
A. Soldered joint
B. Flared joint
C. Mechanical-compression joint
D. Solvent-cement weld joint (paragraphs 2-5 and 2-6a)
6. What is the largest-sized hole that can be drilled though the center of a 2- by 8-inch floorjoist for a pipeline run?
A. 1 inch
B. 2 inches (Table 2-12)
C. 3 inches
D. 4 inches
7. What is the maximum depth that a notch can be cut in a floor joist?
A. 1/4 of the joist depth (Table 2-13)
B. 1/3 of the joist depth
C. 1/2 of the joist depth
D. 2/3 of the joist depth
8. What is the maximum depth that a notch can be cut at the bottom of a wall stud?
A. 1/4 of the depth of the stud
B. 1/3 of the depth of the stud (Table 2-14)
C. 1/2 of the depth of the stud
D. 2/3 of the depth of the stud
2-31
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
60/65
9. What is used to brace the bottom of a joist or the lower half of a wall stud?
A. Steel plate (Tables 2-13 and 2-14)
B. Wood blocking
C. Pipe strap
D. Plastic plate
10. What is the number of minutes water is kept in a rough-in water supply system during awater test?
A. 15
B. 20
C. 25
D. 30 (Table 2-15)
2-32
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
61/65
APPENDIX A
LIST OF COMMON ACRONYMS
ABS acrylonitrile-butadiene-styrene
CPVC chlorinate polyvinyl chloride
DWV drain, waste, and vent
EN engineer
FM field manual
MOS military occupational specialty
NPT national pipe threads
PB polybutylene
PE polyethylene
PVC polyvinyl chloride
TM technical manual
A-1
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
62/65
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
63/65
APPENDIX B
RECOMMENDED READING LIST
The following publications provide additional information about the material in the subcourse.You do not need this material to complete the subcourse.
FM 3-34.471.Plumbing, Pipe Fitting, and Sewerage. 31 August 2001.
TM 5-551K.Plumbing and Pipefitting. 29 July 1971.
B-1
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
64/65
7/30/2019 US Army Engineer Course - Plumbing II - Water Supply (2005 Edition) EN5111
65/65
APPENDIX C
METRIC CONVERSION CHART
This appendix complies with current Army directives which state that the metric system will beincorporated into all new publications. Table C-1 is a metric conversion chart.
Table C-1. Metric Conversion Chart
US Units Multiplied By Metric Units
Feet 0.30480 Meters
Inches 2.54000 Centimeters
Inches 0.02540 Meters
Inches 25.40010 Millimeters
Metric Units Multiplied By US Units
Centimeters 0.39370 Inches
Meters 3.28080 Feet
Meters 39.37000 Inches
Millimeters 0.03937 Inches