Upload
sonya-borom
View
214
Download
0
Embed Size (px)
Citation preview
UTILITIES
Project Update for the City of St. Augustine
Beach Community Sewer System Installation
1
October 21, 2009
UTILITIES
Introduction
• Welcome
• Project Description
• Construction Expectations
• Fees and Costs
• Information needed from residents– Provide contact information on sign-in sheet– Private underground utility locations– Verification of proposed sewer lateral location
2
UTILITIES
Introduction
• Representatives– City of St. Augustine Beach
• Marc Chattin, Public Works Director• Max Royle, City Manager
– St. Johns County Utility Department• Mickhael Sulayman, PE, Chief Engineer• Aaron Zambo, PE, Project Manager
– Engineer: CDM • Cecile Toupiol, PE, Project Manager• Lindsey Riemenschneider, EI, Task Manager
3
UTILITIES
Improved Environmental and Public Health
• High density development• High groundwater table and floods
– Poorly drained soils with seasonal high groundwater levels
– Low lying areas
• Aging septic tanks– Water table separation– Undersized relative to current code
• Impacts to water bodies– Environmental quality degradation of the Matanzas
River Basin– Approved shellfish harvesting areas decreased 4
UTILITIES
Project Description
• There are over 700 homes currently utilizing septic systems for wastewater treatment in St. Augustine Beach that are included in this project and will be served by a gravity sewer system
• Homeowner connection to sewer system is recommended but is NOT mandatory until septic tank failure
5
UTILITIES
Project Status
• Public Meetings were held in April 2009 to discuss project with neighborhoods
• Design completed at 100% in April 2009• Design received Loan and Stimulus (SRF &
ARRA) funding in June 2009• Project went to Bid in July 2009• Bid opening was held in August 2009• In September 2009, 5 different contractors were
selected to construct 7 projects• Construction to start in Oct-Nov 2009 6
UTILITIES
Anticipated Construction Schedule
• Anticipated construction schedule is subject to change based on site conditions and weather
7
UTILITIES
Working Hours
• Typical hours of operation for construction activities– Monday through Thursday from 7 am to 5 pm: Regular
Construction– Friday from 7 am to 12 pm: Regular Construction– Friday from 12 pm to 5 pm: Clean-up and Restoration
only– If necessary, after hours for specific locations with prior
approval and resident notification
8
UTILITIES
Minimal Disruption and Impact
• Construction shall be conducted in a way to minimize impact on the residents
• Contractors will use the County/City dust control and noise attenuation standard including:– Equipment will have silencers or mufflers to operate
with the least possible noise– Water sprinkling, temporary enclosures and other
suitable methods will limit amount of dust and dirt
9
UTILITIES
Safety and Supervision
• Safety is the main priority and construction
areas will always be covered and off limits during non-working hours
• On-site supervision to ensure safety will include:– Resident Project Representative– Full-time Construction Foreman– Frequent visits from SJCUD Representative
10
UTILITIES
Typical Residential Connection Setup
11
UTILITIES
Protection of Private Property
• The work will be in the public Right-of-Way– SJCUD construction ends at the cleanout/property
line– Construction will not necessarily extend across the
entire ROW
• Protection of private property– Contractor will not enter or occupy private land
outside of easements without permission– Mailboxes will be temporarily re-located if needed
• Notification will be provided to residents if any planned disruption in utility service 12
UTILITIES
Restoration and Access
• All disturbed pavement and driveways will be restored on a regular basis– Testing, backfill, and re-pavement will be required
every 1,000 linear feet. – It is anticipated that asphalt or driveways will never be
left unpaved for more than 30 days
• Residents will be able to access homes every night
13
UTILITIES
Maintenance of Traffic
• Contractor will follow Maintenance of Traffic plans to re-route traffic and pedestrians as necessary– Contractor will contact emergency services and police
department every Monday– Emergency vehicles will always have access
14
UTILITIES
Project Completion
• At the end of construction, the Contractor will:– Clean-up the site and dispose of excess material– Restore the site to existing conditions based on
pre-construction video• Roadway, sidewalks, driveways, landscaping, fences
15
UTILITIES
Residential Responsibilities
• Residents will be responsible for irrigating any replaced sod or plants after contractor releases it
• Residents will be responsible for informing SJCUD of any private work completed near Right-of-Way after October 2009
16
UTILITIES
Abandonment of Septic System
• Abandonment permitted through local State of Florida Dept. of Health, Environmental Health Division– 64E-6.011, F.A.C; Form DH 4015– Local Contact – John Cochrane 823-2514 x104– DOH Abandonment Fee is $225 per parallel “Blackwater”
system
• State of Florida licensed Plumbing Contractor or Septic System Contractor can abandon system– Can also perform Voluntary inspection of system to
determine operating condition17
UTILITIES
• Typically, water and sewer infrastructure fees are built into the price of a new home and range from $10,000-$20,000
• Homeowner Plumber Installation Cost = $2,500 (approx.)• Includes work to connect and abandon septic tank
• Abandonment Permit (per blackwater system) = $225
• Current Sewer Unit Connection Fee = $2,296 (single family dwelling)
• Current Monthly Fees (Wastewater) = $11.03 (base)+ $3.48 / 1,000 gal (max. 10,000 gal. per dwelling unit)
• Additional average wastewater bill for COSAB is ~$25
• Payment plan is available for Unit Connection Fee ONLY18
Example Fees for Residents
UTILITIES
• Summary of Example Fees
$2,296 Connection Fee
$225 Abandonment Permit
$2,500 Plumber’s Estimate
$5,021 Example Fee
Monthly fee = ~$25
19
Example Fees for Residents
UTILITIES
• Program is prescribed in Utility Ordinance• Applies only to residential accounts• Rate is currently 5% fixed APR• Term is 1 to 7 years at property owner’s discretion• Charged on utility bill• Payment plan is recorded with Clerk of Courts• Due on Sale of Residence• No pre-payment penalty
20
UCF Payment Plan
UTILITIES
Project Contacts Minorca and Atlantic Beach
• For general information during business hours:Aaron ZamboProject Manager, St. Johns County904-209-2628
• For emergencies that occur after business hours please see the emergency contact sheet for your neighborhood
21
UTILITIES
Any Questions?
22
UTILITIES
Project Update for the City of St. Augustine
Beach Community Sewer System Installation
23
October 21, 2009