UTILITY WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 kV & ABOVE) VIS-A-VIS PROGRAMME DURING 2016-2017 1. 2. 5. 6. 4. 7. 8. 3. Land Acquisition Civil works completed Structure,tra nsformer,su bstation eqpt. received 9. Structure,tra nsformer,su bstation eqpt. erected 10. Capacity Tested/ Commissio ned (MVA) Cummulative progress till date Sl No Name of Sub-Stations Date of Award Capacity (No.xMVA) Voltage Ratio (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated 12. 13. Remark As on 31-AUG-2016 DAMODAR VALLEY CORPORATION (DVC) 1 Gola (2x80MVA) 160 DEC-15 NIT floated on 11.11.2015. NIT Cancelled on 25.02.16. 100% 0% 0% 220/132 0% 0 Sub-Stations: Page 1 of 72

UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

Embed Size (px)

Citation preview

Page 1: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

UTILITY WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220kV & ABOVE) VIS-A-VIS PROGRAMME DURING 2016-2017

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

DAMODAR VALLEY CORPORATION (DVC)

1 Gola (2x80MVA) 160 DEC-15 NIT floated on 11.11.2015. NIT Cancelledon 25.02.16.

100% 0% 0%220/132 0% 0

Sub-Stations: Page 1 of 72

Page 2: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

POWER GRID CORPORATION OF INDIA LIMITED (PGCIL)

1 Agra HVDC 1500 AUG-13 AUG-16 Pole-I test commissioned in Oct'15. Pole -IIcharged in Aug'16. Commissioning expectedshortly.

100% 99% 100%±800 98% 0

2 Alipurduar (HVDC) S/S 3000 MAR-17 Supply, civil works & erection underprogress.Pole-I ant. by Dec'16 & Pole-II byMar'17.Balance land acquisition for EarthElectrode station under process.

100% 54% 45%±800 25% 0

3 Bay Extn. Kurukshetra HVDC(GIS) S/S

0 DEC-16 Engg. in progress.100% 0% 0%±800 0% 0

4 Biswanath Chariyali & AgraHVDC terminal (Pole-II)

1500 AUG-16 Commissioned 08/16.100% 100% 100%±800 100% 1500

5 Biswanath Chariyali S/S 1500 AUG-16 Pole-I test commissioned in Oct'15. Pole -IIcharged in Aug'16. Commissioning expectedshortly.

100% 99% 100%±800 98% 0

6 Champa (Addl) S/S 3000 MAR-18 work under progress.100% 20% 10%±800 0% 0

7 Champa S/S 3000 JUL-15 FEB-17 Work under progress. Pole-I expected byNov'16 & Pole-II by Feb'17.

100% 72% 75%±800 65% 0

8 Extn. Agra S/S 3000 DEC-15 MAR-17 Work under progress. Pole-I ant. by Dec'16& Pole-II by Mar'17.

100% 25% 20%±800 0% 0

9 Kurukshetra (Addl.) S/s 0 MAR-18 Work under progress.100% 20% 10%±800 0% 0

10 Kurukshetra S/S 3000 JUN-15 FEB-17 Engg., supply, civil works & erection underprogress.Land acquired in Apr'13. Pole-I expected byNov'16 & Pole-II by Feb'17.

100% 77% 80%±800 62% 0

11 Agra S/S 500 JUL-17 Award placed in Sep'15. Engg. in progress.100% 0% 0%765/400 0% 0

12 Ajmer S/S 2x1500 APR-17 APR-17 Award placed in Apr'15. work underprogress.

100% 25% 10%765/400 5% 0

13 Angul S/S (Bus Arrangment) 2x1500 APR-19 Award under progress.100% 0% 0%765/400 0% 0

14 Banaskanta S/S 2x1500 APR-18 APR-18 Award placed in Sep'15. Work underprogress.

100% 25% 5%765/400 0% 0

Sub-Stations: Page 2 of 72

Page 3: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

15 Banaskanta S/S 2x500 APR-18 APR-18 Award placed in Sep'15. Work underprogress.

100% 25% 5%765/400 0% 0

16 Bay Aligarh (GIS) 0 APR-18 Award placed in Oct'15. Engg. in progress.100% 0% 0%765/400 0% 0

17 Bay Dharajaygarh S/S 0 JUN-17 Work under progress. Completion matchingwith line.

100% 99% 95%765/400 95% 0

18 Bay Extn. Angul S/s 0 JUN-17 Work under progress. Completion matchingwith line.

100% 80% 70%765/400 55% 0

19 Bay Extn. Aurangabad S/S 0 MAR-17 work under progress.100% 95% 99%765/400 95% 0

20 Bay Extn. Balia S/S 0 MAR-16 Commissioned in Mar'16.100% 100% 100%765/400 100% 0

21 Bay Extn. Banaskantha S/S 0 JUL-18 Award placed in Mar'16. Engg. in progress.100% 0% 0%765/400 0% 0

22 Bay Extn. Bhiwani S/S 0 OCT-16 Work under progress.100% 92% 90%765/400 90% 0

23 Bay Extn. Fatehpur S/S 0 SEP-16 Award placed in Apr'15. Work underprogress.

100% 65% 65%765/400 10% 0

24 Bay Extn. Gwalior S/S 0 APR-18 Award under progress.100% 0% 0%765/400 0% 0

25 Bay Extn. Hyderabad S/S 0 MAY-18 Work under progress.100% 70% 50%765/400 45% 0

26 Bay Extn. Jabalpur (Gadarwara-A)

0 MAY-17 Award placed in Apr'16. Engg., supply &civil work under progress.

100% 10% 5%765/400 0% 0

27 Bay Extn. Jabalpur PS 0 APR-18 Award placed in Aug'15. Work under progress.

100% 15% 10%765/400 0% 0

28 Bay Extn. Jaipur S/S 0 OCT-16 Deposit work by RVPNL.100% 75% 80%765/400 60% 0

29 Bay Extn. Kurnool S/S 0 DEC-15 Commissioned in Dec'15.100% 100% 100%765/400 100% 0

30 Bay Extn. Nagapattinam S/S 0 SEP-15 Commissioned in Sep'15.100% 100% 100%765/400 100% 0

31 Bay Extn. Raichur S/S 0 DEC-15 Commissioned in Dec'15.100% 100% 100%765/400 100% 0

Sub-Stations: Page 3 of 72

Page 4: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

32 Bay Extn. Raipur Pooling Station 0 DEC-16 Work under progress. Matching with line.100% 95% 95%765/400 95% 0

33 Bay Extn. Ranchi (Dharmjaygarh)S/S

0 DEC-15 Commissioned in Dec'15.100% 100% 100%765/400 100% 0

34 Bay Extn. Salem Pooling Station 0 0% 0% 0%765/400 0% 0

35 Bay Extn. Wardha S/S 0 DEC-16 Work under progress. Matching with line.100% 95% 95%765/400 95% 0

36 Bay Extn. Wardha S/S 0 MAR-17 Award placed in Aug'15. Work underprogress.

100% 50% 15%765/400 20% 0

37 Bay extn. Ajmer S/S 0 APR-18 APR-18 work under progress.100% 15% 5%765/400 0% 0

38 Bay extn. Angul S/S 0 DEC-15 JUN-17 Engg. supply, civil works & erection underprogress. Completion matching with line.

100% 80% 70%765/400 55% 0

39 Bhiwani (Addl.)S/S 333 AUG-15 Commissioned in Aug'15.100% 100% 100%765/400 100% 0

40 Bhuj Pooling Station 2x1500 JUL-18 JUL-18 Award placed in Mar'16.Engg. in progress.100% 0% 0%765/400 0% 0

41 Champa Pooling Station 6x1500 MAY-14 OCT-16 400KV bay charged in May'15.ICT-I commissioned in Jun'15 & ICT-II inMar'16.Balance works under progressDelayed due to delay in land acquisation.

100% 80% 85%765/400 60% 0

42 Chilakaluripeta S/S 2x1500 APR-19 APR-19 Award under progress.0% 0% 0%765/400 0% 0

43 Chittorgarh S/S 2x1500 APR-17 APR-17 Award placed in Apr'15. Work underprogress.

100% 20% 10%765/400 5% 0

44 Cuddapah S/s 2x1500 JUL-18 Award placed in Feb'16. Engg. & civil workunder progress.

100% 1% 0%765/400 0% 0

45 Extn Kanpur S/S 0 MAR-17 Work under progress.100% 62% 32%765/400 26% 0

46 Extn. Aurangabad (PG) 0 MAR-16 SEP-15 Commissioned in Sep'15.100% 100% 100%765/400 100% 0

Sub-Stations: Page 4 of 72

Page 5: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

47 Extn. Chittorgarh S/S 0 APR-18 APR-18 Work under progress.100% 15% 10%765/400 5% 0

48 Extn. Gaya S/S 0 JUN-19 Award under progress.100% 0% 0%765/400 0% 0

49 Extn. Jabalpur (vindhyachal)Pooling Station

0 JUN-18 Award placed in Apr'16. Engg. in progress.100% 0% 2%765/400 0% 0

50 Extn. Jharsaguda (Sundergarh)Pooling Station

0 JUN-18 Award under progress.100% 0% 0%765/400 0% 0

51 Extn. Jharsuguda S/S 0 DEC-15 JUN-17 Works under progress. Completion matchingwith line.

100% 80% 70%765/400 62% 0

52 Extn. Kanpur (GIS) 0 JUN-16 MAR-17 Award placed in Feb'14. Work underprogress.

100% 100% 85%765/400 90% 0

53 Extn. Lucknow S/S 0 MAR-17 Work under progress.100% 67% 35%765/400 30% 0

54 Extn. Lucknow S/S 0 APR-13 MAR-15 Commissioned.100% 100% 100%765/400 100% 0

55 Extn. Meerut S/S 0 MAR-15 MAY-15 Commissioned in May'15.100% 100% 100%765/400 100% 0

56 Extn. Moga S/S 0 MAR-15 MAY-15 Commissioned in May'15.100% 100% 100%765/400 100% 0

57 Extn. Patna S/S 0 JUN-19 Award under progress.100% 0% 0%765/400 0% 0

58 Extn. Raigarh S/S 1500 JUL-16 DEC-16 Award placed in May'14. Work underprogress.

100% 75% 70%765/400 50% 0

59 Extn. Ranchi S/S 0 MAR-17 MAR-17 Work under progress.100% 65% 40%765/400 30% 0

60 Extn. Solapur (PG) 0 MAR-16 SEP-15 Commissioned in Sep'15.100% 100% 100%765/400 100% 0

61 Extn. Solapur S/S 0 JAN-18 Award placed in Apr'16. Engg. & civil workunder progress.

100% 5% 0%765/400 0% 0

62 Extn. Tuticorin S/S 0 SEP-14 DEC-16 Work under progress.100% 85% 90%765/400 60% 0

63 Extn. Varanasi S/S 0 MAY-15 MAR-16 Commissioned in Mar'16.100% 100% 100%765/400 100% 0

Sub-Stations: Page 5 of 72

Page 6: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

64 Extn. Vindhyachal PoolingStation

1500 JUL-17 Award placed in Aug'15.work underprogress.

100% 65% 40%765/400 0% 0

65 Extn. vindhyachal (Jabalpur)Pooing Station

0 JUN-18 Award placed in Apr'16. Work underprogress.

100% 10% 15%765/400 0% 0

66 Gaya (ICT) S/S 500 DEC-16 Award placed in Jun'15.100% 0% 0%765/400 0% 0

67 Hyderabad (Maheshwaram)(GIS) S/S

2x1500 MAR-18 MAR-18 Award placed in May'15. Works underprogress.

100% 60% 40%765/400 30% 0

68 Jharsuguda (Sundargarh) S/S 2x1500 APR-19 Award under progress.100% 0% 0%765/400 0% 0

69 Jharsuguda Pooling Station 2x1500 JUN-15 JAN-16 Commissioned in Jan'16.100% 100% 100%765/400 100% 0

70 Jhatikara S/S 500 APR-18 Award placed in Aug'15.Engg. in progress.100% 0% 0%765/400 0% 0

71 Kanpur (GIS) S/S 2x1500 OCT-14 JUL-16 Commissioned 07/16.100% 100% 100%765/400 100% 3000

72 Kudgi (GIS) S/S 0 DEC-15 DEC-15 Commissioned in Dec'15.100% 100% 100%765/400 100% 0

73 Meerut (Aug.) 1500 OCT-17 Award placed in Mar'15. Engg., civil work &supply under progress.

100% 30% 10%765/400 0% 0

74 Nizamabad S/S 2x1500 MAY-18 MAR-17 Award placed in May'15. Work underprogress.Efforts being made to complete inFY 2016-17.

100% 70% 50%765/400 45% 0

75 Orai S/S 2000 APR-18 APR-18 Award placed in Oct'15. Engg. & civil workunder progress.

100% 1% 0%765/400 0% 0

76 Padghe S/S 2x1500 AUG-14 MAR-17 Supply, civil works & erection underprogress.

100% 85% 95%765/400 85% 0

77 Parli S/S 2x1500 JAN-18 JAN-18 All packages awarded.100% 0% 0%765/400 0% 0

78 Pune (GIS) S/S 2x1500 JUN-16 Commissioned 02/15. (Reported Late100% 100% 100%765/400 100% 3000

79 Raipur (Extn.) 1500 DEC-16 Award placed in Aug'15. Work underprogress.

100% 40% 25%765/400 10% 0

80 Sasaram (2nd Trf.) S/S 1500 MAR-140% 0% 0%765/400 0% 0

Sub-Stations: Page 6 of 72

Page 7: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

81 Srikakulam S/S 2x1500 JUN-15 DEC-16 Works under progress Completion matchingwith Srikakulam - Vemagiri TBCB line &associated downstream system at Vemagiri.

100% 95% 95%765/400 90% 0

82 Tehri (GIS) 4x800 NOV-17 OCT-17 Award placed in Mar'15. Engg., civil work &supply under progress.

100% 35% 5%765/400 0% 0

83 Vemagiri Pooling Station (GIS) 2x1500 JUN-14 DEC-16 Work under progress. Efforts being made tocomplete matching with line.

100% 80% 60%765/400 45% 0

84 Vemagiri-II Pooling Station (PG) 2x1500 NOV-17 DEC-16 Supply, civil work & erection underprogress. Efforts being made to completematching with line.

100% 80% 60%765/400 45% 0

85 Warora Pooling Station 2x1500 NOV-17 NOV-17 Award placed in Apr'16. Engg. in progress.100% 0% 0%765/400 0% 0

86 (Repl) Purnea S/S 370 NOV-16 ICT- I commissioned in Jul'15. Balance workunder progress.

100% 90% 90%400/220 65% 0

87 Agra (Extn.) 315 JUL-17 JUL-17 Award placed in Sep'15. Engg. in progress.100% 0% 0%400/220 0% 0

88 Alipurduar HVDC S/S 630 MAR-17 Supply, civil works & erection underprogress. Pole-I ant. by Dec'16 & Pole-II byMar'17.Land acquisition balance for Earth Electrodestation, under process.

100% 54% 45%400/220 25% 0

89 Aurangabad (Extn.) 630 OCT-12 MAR-17 Sub station commisisoned alongwith bothICT's in Jan'14. Balance works underprogress. Commissioned matching with line.

100% 98% 100%400/220 98% 0

90 Bagpat (ICT-II) S/S 500 JUN-16 Commissioned 06/16.100% 100% 100%400/220 100% 500

91 Balipara (2nd ICT) 315 MAY-17 MAY-16 Commissioned 05/16.100% 100% 100%400/220 100% 315

92 Ballabhgarh (Aug.) 740 JUN-16 DEC-16 ICT-I commissioned in Feb'16. Balancework under progress.

100% 83% 87%400/220 60% 0

93 Baripada (Addl.) 500 NOV-16 Award placed in Jun'14. Work underprogress.

100% 100% 100%400/220 80% 0

Sub-Stations: Page 7 of 72

Page 8: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

94 Bay Barh (Switchyard) 0 JUN-15 Commissioned in Jun'15.100% 100% 100%400/220 100% 0

95 Bay Extn Alipurduar 0 JAN-18 Bays available/ ready. Commissioningmatching with line.

100% 0% 0%400/220 0% 0

96 Bay Extn. Madhugiri S/S 0 MAY-17 Award placed in Dec'14. Work underprogress.

100% 60% 40%400/220 30% 0

97 Bay Extn. Allahabad S/S 0 JUL-15 APR-16 Ready for commissioning.Gen. project delayed.

100% 100% 100%400/220 100% 0

98 Bay Extn. Allahabad S/S 0 MAR-17 Work under progress.100% 100% 82%400/220 90% 0

99 Bay Extn. Amritsar S/S 0 SEP-16 Work under progress.100% 60% 50%400/220 40% 0

100 Bay Extn. Aurangabad S/S 0 SEP-17 Work under progress.100% 20% 5%400/220 0% 0

101 Bay Extn. Bachau S/s 0 MAR-16 Commissioned in Mar'16.100% 100% 100%400/220 100% 0

102 Bay Extn. Bagpat S/S 0 NOV-11 NOV-16 Work under progress. Completion matchingwith line.

100% 99% 100%400/220 96% 0

103 Bay Extn. Balia S/S 0 NOV-14 JAN-14 Commissioned in Jan'14.100% 100% 100%400/220 100% 0

104 Bay Extn. Balipara S/S 0 AUG-13 SEP-15 Commissioned in Sep'15.100% 100% 100%400/220 0% 0

105 Bay Extn. Bhinamal S/S 0 JUL-17 Award placed in Sep'15. Engg.& civil workunder progress.

100% 10% 2%400/220 0% 0

106 Bay Extn. Biharshariff 0 DEC-16 Work under progress. Completion delayeddue to delay in manufacturing of Reactorsby M/s BHEL. Now matter being taken up.

100% 35% 40%400/220 20% 0

107 Bay Extn. Biharshariff S/S 0 OCT-16 work under progress.Works on halt due tonon-availability of S/D.

100% 100% 100%400/220 75% 0

108 Bay Extn. Biswanath ChariyaliS/S

0 FEB-13 DEC-17 Completion matching with line (Line workalmost stalled due to agitation against bigdam)/delay in Generation.

100% 15% 0%400/220 0% 0

109 Bay Extn. Boisar S/S 0 OCT-16 Navsari - Navi mumbai line is now to beterminated at Boisor S/Stn in place of

100% 98% 98%400/220 98% 0

Sub-Stations: Page 8 of 72

Page 9: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

Mumbai. Works under progress.Commissioning matching with line.

110 Bay Extn. Champa S/S 0 APR-17 Award placed in oct'14. Engg. in progress.100% 0% 0%400/220 0% 0

111 Bay Extn. Dehar S/S 0 DEC-16 Work under progress.100% 80% 70%400/220 50% 0

112 Bay Extn. Dharmapuri S/S 0 MAY-17 Work under progress.100% 95% 90%400/220 85% 0

113 Bay Extn. Dichpally S/S 0 MAR-17 Work being executed by APTRANSCO ondeposit basis. Efforts being made tocomplete in FY 2016-17.

100% 0% 0%400/220 0% 0

114 Bay Extn. Farakka S/S 0 DEC-16 Award placed in Mar'15.Work underprogress.

100% 60% 70%400/220 35% 0

115 Bay Extn. Gokarna S/S 0 DEC-16 Award placed in Mar'15. Work underprogress.

100% 75% 80%400/220 50% 0

116 Bay Extn. Gooty S/S 0 JUL-17 Award placed in Mar'15. Work underprogress.

100% 20% 0%400/220 0% 0

117 Bay Extn. Gorakhpur S/S 0 JUN-15 Commissioned in Jun'15.100% 100% 100%400/220 100% 0

118 Bay Extn. Gwalior S/S 0 SEP-17 Award under progress.100% 0% 0%400/220 0% 0

119 Bay Extn. Hissar S/S 0 JUN-15 Commissioned in Jun'15.100% 100% 100%400/220 100% 0

120 Bay Extn. Indore (Khandwa) S/S 0 DEC-16 work under progress. Matching with line.100% 95% 95%400/220 92% 0

121 Bay Extn. Jallandhar S/S 0 DEC-15 Commissioned in Dec'15.100% 100% 100%400/220 100% 0

122 Bay Extn. Kaithal S/S 0 AUG-17 Work under progress.100% 50% 40%400/220 30% 0

123 Bay Extn. Khammam(Nagarjuneasagar) S/S

0 DEC-15 Commissioned in Dec'15.100% 100% 100%400/220 100% 0

124 Bay Extn. Kishanganj S/S 0 MAR-16 Commissioned in Mar'16.100% 100% 100%400/220 100% 0

125 Bay Extn. Kota S/S 0 NOV-17 Award placed in Aug'15. Engg. in progress.100% 0% 0%400/220 0% 0

Sub-Stations: Page 9 of 72

Page 10: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

126 Bay Extn. Kota S/S (PG) 0 JUN-17 Work completed. Commissioning matchingwith line.

100% 100% 100%400/220 100% 0

127 Bay Extn. Koteshwar S/S 0 DEC-16 Testing under progress.100% 100% 100%400/220 100% 0

128 Bay Extn. Kurukshetra (Jind) S/S 0 MAR-18 Award placed in Nov'15. Civil work underprogress.

100% 5% 0%400/220 0% 0

129 Bay Extn. Madhugiri S/S (Salem-I)

0 DEC-16 Work under progress.100% 85% 95%400/220 70% 0

130 Bay Extn. Maithon (Durgapur)S/S

0 JAN-16 Commissioned in Jan'16.100% 100% 100%400/220 100% 0

131 Bay Extn. Malerkotal (GIS) S/S 0 SEP-16 work under progress.100% 80% 60%400/220 50% 0

132 Bay Extn. Mysore S/S 0 OCT-15 Commisisoned in Oct'15.100% 100% 100%400/220 100% 0

133 Bay Extn. Nagapatnam (PS) S/S 0 JUL-15 SEP-16 Award placed in Dec'14. Work underprogress.

100% 95% 90%400/220 85% 0

134 Bay Extn. Nakodar 0 DEC-15 Commissioned in Dec'15.100% 100% 100%400/220 0% 0

135 Bay Extn. Nellor S/S 0 JUL-17 Award plaved in Mar'15. work underprogress.

100% 20% 0%400/220 0% 0

136 Bay Extn. Nellore PS 0 MAR-16 Commissioned in Mar'16.100% 100% 100%400/220 100% 0

137 Bay Extn. Orai S/s 0 APR-18 Award placed in Oct'15. Engg. & civil work inprogress.

100% 1% 0%400/220 0% 0

138 Bay Extn. Padhe S/S 0 MAR-17 Engg., civil work & supply under progress.MSETCL S/S at Kudus dalayed due totermination of main contract and re-tendered. Critical

100% 15% 10%400/220 0% 0

139 Bay Extn. Patna S/S 0 FEB-15 Commissioned in May'15.100% 100% 100%400/220 100% 0

140 Bay Extn. Raigarh (Kotra) S/S 0 APR-16 Commissioned in Apr'16.100% 100% 100%400/220 100% 0

141 Bay Extn. Rajgarh S/S 0 SEP-16 Work under progress.100% 85% 80%400/220 55% 0

Sub-Stations: Page 10 of 72

Page 11: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

142 Bay Extn. Roorkee S/S 0 MAY-16 Comissioned in May'16.100% 100% 100%400/220 100% 0

143 Bay Extn. Saharanpur S/S 0 MAY-16 Commissioned in May'16.100% 100% 100%400/220 100% 0

144 Bay Extn. Salem S/S 0 DEC-16 Work under progress.100% 97% 98%400/220 90% 0

145 Bay Extn. Sasaram S/S 0 DEC-16 work under progress.100% 90% 78%400/220 50% 0

146 Bay Extn. Satna S/S 0 SEP-17 Award placed in Jun'15. work underprogress.

100% 20% 5%400/220 0% 0

147 Bay Extn. Sholapur S/S 0 MAR-17 Award placed in Jun'15. Work underprogress.

100% 60% 50%400/220 20% 0

148 Bay Extn. Shujalpur S/S 0 FEB-16 Commissioned in Feb'16.100% 100% 100%400/220 100% 0

149 Bay Extn. Singrauli S/s 0 MAR-17 work under progress.100% 75% 82%400/220 35% 0

150 Bay Extn. Somanahalli S/S 0 DEC-16 Work almost completed, completionmatching with line.

100% 98% 98%400/220 98% 0

151 Bay Extn. Trissur S/S 0 FEB-17 Award placed in Sep'14. Engg. in progress.100% 0% 0%400/220 0% 0

152 Bay Extn. Tuticorin PS 0 DEC-16 Work under progress.100% 85% 90%400/220 60% 0

153 Bay Extn. Vijayawada S/S 0 0% 0% 0%400/220 0% 0

154 Bay Extn. Wagoora S/S 0 MAR-18 MAR-18 Engg. & civil work under progress.100% 6% 0%400/220 0% 0

155 Bay Extn. Yelahanka (GIS) 0 JUL-17 Award placed in Mar'15. Engg. & civil workunder progress.

100% 10% 0%400/220 0% 0

156 Bay extn. Bidadi (GIS) 0 DEC-15 SEP-16 Award placed in Dec'14. Work underprogress.

100% 80% 70%400/220 0% 0

157 Bay extn. Chamera S/S 0 AUG-14 AUG-14 Bay commissioned in Aug'14.100% 100% 100%400/220 100% 0

158 Bay extn. Deharadun S/S 0 NOV-14 DEC-16 Supply & erection under progress.Commissioning matching with line.

100% 100% 99%400/220 98% 0

Sub-Stations: Page 11 of 72

Page 12: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

159 Bay extn. Dubri (Mendhasal) S/S 0 0% 0% 0%400/220 0% 0

160 Bay extn. Kishanpur S/S 0 JUL-13 OCT-16 Works under progress.100% 97% 96%400/220 90% 0

161 Bay extn. Kishenpur S/S 0 NOV-14 DEC-16 Supply & erection under progress.Commissioning matching with line.

100% 100% 99%400/220 98% 0

162 Bay extn. Kota S/S 0 MAR-15 JUN-17 Work completed. Commissioning matchingwith line.

100% 100% 100%400/220 100% 0

163 Bay extn. Narendra S/S 0 APR-15 DEC-15 Commissioned in Dec'15.100% 100% 100%400/220 100% 0

164 Bay extn. Navsari S/S 0 OCT-16 OCT-16 Award placed in Dec'14. Works underprogress.

100% 95% 95%400/220 65% 0

165 Bay extn. Panchkula S/S 0 AUG-14 MAR-15 Commissioned.100% 100% 100%400/220 100% 0

166 Bay extn. Purulia S/S 0 MAR-17 MAR-17 Purulia bay to be executed by West Bengalon deposit work basis. Bay at Purulia to beconstructed in New S/S at Purulia(WBSETCL) due to space constraint. Interimarrangement to be made accordingly byWBSETCL.

100% 65% 40%400/220 30% 0

167 Bay extn. Rajpura S/S 0 AUG-14 JUN-16 Commissioned in Jun'16.100% 100% 100%400/220 100% 0

168 Bay extn. Sonepat S/S 0 JUL-17 AUG-17 Award placed in Mar'15. Work underprogress.

100% 50% 40%400/220 30% 0

169 Bay extn. Vapi S/S 0 OCT-16 OCT-16 Work under progress.100% 95% 92%400/220 60% 0

170 Betul (GIS) S/S 630 DEC-16 Award placed in Dec'14. Engg.,supply, civilwork & erection under progress. Completionmatching with line

100% 95% 95%400/220 90% 0

171 Bhuj Pooling Station 2x500 JUL-18 JUL-18 Award placed in Mar'16. Engg. in progress.100% 0% 0%400/220 0% 0

172 Bongaigaon (2nd ICT) S/s. 315 DEC-17 DEC-17 Award placed in Nov'15. Engg. in progress.100% 0% 0%400/220 0% 0

173 Cuddapah (Extn.) 500 FEB-17 FEB-17 Award placed in Sep'14. Work underprogress.

100% 65% 54%400/220 48% 0

Sub-Stations: Page 12 of 72

Page 13: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

174 Daltonganj 2x315 NOV-12 JUN-17 Due to delay in handing over land, M/sAlstom not agree to take up the work.Re-tendered & award placed in May'16.Engg. in under progress.Down stream network also not envisaged byJSEB.

100% 0% 73%400/220 0% 0

175 Damon (Extn.) 500 OCT-16 Award placed in Jun'15. work underprogress.

100% 90% 65%400/220 50% 0

176 Dehradun 2x315 NOV-16 Completion matching with line.100% 99% 100%400/220 98% 0

177 Dwarka -I (GIS) S/S 2000 MAY-17 MAY-17 Award under progress. Land underacquisation.

0% 0% 0%400/220 0% 0

178 Extn. Bachau S/S 0 JUL-18 Award placed in Jan'16. work in progress.100% 10% 5%400/220 0% 0

179 Extn. Baharampur S/S 0 APR-18 Award placed in Aug'16.100% 0% 0%400/220 0% 0

180 Extn. Bina S/S 125 JUL-16 FEB-16 Commissioned in Feb'16.100% 100% 100%400/220 100% 0

181 Extn. Chaibasa S/S 63 MAR-17 MAY-16 Commissioned in May'16.(under TBCBrout).

100% 100% 100%400/220 100% 0

182 Extn. Chittorgarh S/S 0 APR-17 APR-17 Award placed in Jul'15. Engg in progress.100% 0% 0%400/220 0% 0

183 Extn. Chittorgarh S/S 0 MAR-17 Deposit work by RVPNL.100% 0% 0%400/220 0% 0

184 Extn. Dulhasti S/S 0 NOV-140% 0% 0%400/220 0% 0

185 Extn. Farakka S/S 0 APR-18 Award placed in Aug'16.100% 0% 0%400/220 0% 0

186 Extn. Hindupur S/S 0 JUL-18 To be implementation by APTRANSCO.100% 0% 0%400/220 0% 0

187 Extn. Indore S/s 2x500 JUL-18 Award placed in Jan'16. work underprogress.

100% 2% 5%400/220 0% 0

188 Extn. Itarsi S/S 500 JUL-18 Award placed in Jan'16.100% 0% 5%400/220 0% 0

Sub-Stations: Page 13 of 72

Page 14: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

189 Extn. Jaipur (Sourth) (RAPP) 0 NOV-17 Award placed in Aug'15. Engg. in progress.100% 0% 0%400/220 0% 0

190 Extn. Jaipur (South) S/S 0 NOV-17 Award placed in Aug'15. Engg in progress.100% 0% 0%400/220 0% 0

191 Extn. Jalandhar (Samba) 0 JUL-17 Award placed in Jan'16. Work underprogress.

100% 30% 20%400/220 15% 0

192 Extn. Jeerat S/S 0 APR-18 Award placed in Aug'16.100% 0% 0%400/220 0% 0

193 Extn. Kaithal S/S 0 OCT-16 Work under progress.100% 50% 40%400/220 30% 0

194 Extn. NP Kunta S/S 0 JUL-18 Engg. & civil work commenced from May'16.100% 5% 0%400/220 0% 0

195 Extn. Parli Switching Station 0 FEB-18 Award placed in Apr'16. Engg. & civil workunder progress.

100% 5% 0%400/220 0% 0

196 Extn. Sagardighi S/S 0 APR-18 Award placed in Aug'16.100% 0% 0%400/220 0% 0

197 Extn. Salem (Madhugiri II) S/S 0 0% 0% 0%400/220 0% 0

198 Extn. Samba (Jalandhar) 0 NOV-18 Award placed in Jan'16. Work underprogress.

100% 30% 15%400/220 10% 0

199 Extn. Sankhari S/S 0 APR-18 APR-18 Award placed in Sep'15. Engg. in progress.100% 0% 0%400/220 0% 0

200 Extn. Subhashgram S/S 0 APR-18 Award placed in Aug'16.100% 0% 0%400/220 0% 0

201 Extn. Tuticorin Pooling Station 0 APR-17 APR-17 Award placed in Apr'15. Work underprogress.

100% 4% 0%400/220 0% 0

202 Extn. Tuticoring Pooling Stn.(Kudukulom)

0 JUL-18 Award placed in May'16.100% 0% 0%400/220 0% 0

203 Extn. Vadodara S/S (GIS) 2x500 JUL-16 DEC-16 Award placed in Jun'15. Work underprogress. Matching with GETCO line.

100% 50% 50%400/220 5% 0

204 Extn. Vemagiri (PG) S/S 0 JUL-18 Award placed in May'16.100% 0% 0%400/220 0% 0

205 Extn. Yelahanka (GIS) S/S 0 JUL-17 Work under progress.100% 10% 0%400/220 0% 0

Sub-Stations: Page 14 of 72

Page 15: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

206 Extn. madhugiri (Salem II) S/S 0 0% 0% 0%400/220 0% 0

207 Extn. of 2 nos. bays Imphal S/S 0 MAY-18 Award placed in Jul'16.100% 0% 0%400/132 0% 0

208 Extn. of 2nos. GIS bays atSilchar S/S

0 MAY-18 Award placed in Jul'16.100% 0% 0%400/132 0% 0

209 Farakka (Aug.) (500-315) 185 OCT-16 Engg., supply, civil work & erection underprogress. Shifting of ICT from Pusali underprogress.

100% 75% 55%400/220 35% 0

210 Gooty (Extn.) 500 FEB-17 FEB-17 Award placed in Sep'14. Engg., supply civilwork & erection under progress.

100% 75% 50%400/220 40% 0

211 Gurgaon (Aug.) 4th ICT S/S 500 JUN-16 MAR-17 Award placed in Dec'14.work underprogress.

100% 70% 50%400/220 30% 0

212 Gurgaon (Extn.) 500 MAY-16 DEC-16 Award placed in Nov'14. Work underprogress.

100% 30% 85%400/220 50% 0

213 Hamirpur (Extn.) 315 MAY-16 DEC-16 Award placed in Nov'14. Work underprogress.

100% 35% 20%400/220 15% 0

214 Hyderabad (Ghanapur) (Extn.) 500 FEB-17 FEB-17 Award placed in Sep'14. Work underprogress.

100% 82% 73%400/220 65% 0

215 Imphal S/S (upgradation) 2x315 MAY-18 Award placed in Jul'16.100% 0% 0%400/132 0% 0

216 Jalandhar (Extn.) 500 MAY-16 JUN-16 Commissioned 06/16.100% 100% 100%400/220 100% 500

217 Jamshedpur (Aug.) (500-3415) 185 NOV-16 Awarded in Jun'14. Engg., supply & civilwork under progress. ICT to be transportedfrom Patna after replacement.

100% 60% 90%400/220 0% 0

218 Jharkhand Pool (Chandwa)Switching GIS

0 JUL-16 Commissioned 07/16.0% 0% 0%400 0% 0

219 Kaithal S/S 315 JUL-17 Award placed in Sep'15. Engg.& civil workunder progress.

100% 6% 0%400/220 0% 0

220 Kala Amb S/S 7x105 JUL-17 Work under progress.100% 60% 5%400/220 0% 0

221 Khammam (Extn.) 500 FEB-17 FEB-17 Award placed in Sep'14. Works under100% 65% 55%400/22 20% 0

Sub-Stations: Page 15 of 72

Page 16: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

progress.0

222 Kishanganj (GIS) S/S 2x315 SEP-16 Sub station commissioned alongwith ICT-I inMar'16. ICT-II expected by Sep'16 (delayeddue to flooding/ water logging).

100% 100% 100%400/220/33

99% 0

223 Kohlapur S/S (GIS) 0 APR-15 NOV-15 Commissioned in Nov'15.100% 100% 100%400/220 100% 0

224 Kotputli S/S 630 DEC-140% 0% 0%400/220 0% 0

225 Kurukshetra S/S 2x1500 JUN-15 NOV-16 400KV bays ready for commissioning inDec'15. Balance work under progress.

100% 99% 99%400/220 99% 0

226 Maduri (Addl.) S/S 500 JUL-17 Award placed in Mar'15. work underprogress.

100% 15% 20%400/220 10% 0

227 Maithon S/S (500-315) 370 OCT-16 Work under progress.100% 65% 50%400/220 40% 0

228 Mandola S/s (Aug.) ICT-II(Replacing 315 MVA with 500MVA ICT)

185 APR-16 Commissioned 04/16.100% 100% 100%400/220 100% 185

229 Mandola S/s (Aug.) ICT-III(Replacement of 315 MVA by500 MVA)

185 MAY-16 Commissioned 05/16.100% 100% 100%400/220 100% 185

230 Mapusa (ICT) S/S 315 ICT commissioned in oct'13.100% 100% 100%400/220 100% 0

231 Misa (Aug.) S/S (Replacement4x105 MVA by 2x500 MVA)

2x500 MAY-18 GIS portion award in Jun'16 & AIS portion inJul'16.

100% 0% 0%400/220 0% 0

232 Mysore (Extn.) 500 FEB-17 SEP-16 Award placed in Sep'14. Work underprogress.

100% 80% 70%400/220 60% 0

233 N.P. Kunta Pooling Station S/S(ICT-I)

500 APR-16 Commissioned 04/16.100% 100% 100%400/220 100% 500

234 N.P. Kunta Pooling Station S/S(ICT-II & III)

1000 JUL-16 Commissioned 07/16.100% 100% 100%400/220 100% 1000

235 Narendra (Aug) (2x500-2x315) 370 FEB-17 FEB-17 Award placed in Sep'14. Engg. in progress.100% 0% 0%400/220 0% 0

Sub-Stations: Page 16 of 72

Page 17: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

236 Navi Mumbai (GIS) 630 SEP-10 DEC-16 Sub station is ready. Commissioningmatching with LILO line (under ROW) nowplanned to be completed using underground cable. Cable trench work underprogress. Severe ROW problem. Critical.Due to severe ROW portion at Navi-Mumbaiend, Line was decided to be terminated atKudus S/Stn. of MSETCL. Also 220KV downstream system (under MSETCL scope)delayed. Critical.

100% 100% 100%400/220 100% 0

237 Pandiabil S/S (ICT-I & II) 1000 JUN-16 Ready for Commissioned 06/16.100% 100% 100%400/220 100% 1000

238 Parbati (PS) 630 JUN-16 MAR-17 work under progress.100% 40% 52%400/220 30% 0

239 Patna (Aug.) (500-315) 370 NOV-16 Award placed in Jun'14. Work underprogress. Execution work held up due to non-availability of S/D which is now expected inSep'16.

100% 60% 65%400/220 20% 0

240 Pugalur (Extn.) 500 FEB-17 FEB-17 Award placed in Sep'14. Engg. & civil workin progress.

100% 5% 0%400/220 0% 0

241 Pusali (Aug.) (500-315) 370 NOV-16 ICT-I commissioned in Mar'16. Balanceworks under progress.

100% 70% 60%400/220 50% 0

242 Rajarhat (GIS) S/S 2x500 MAR-17 Work under progress. Completion delay dueto delay in land acquisation (land acquired inFeb'14).

100% 85% 85%400/220 55% 0

243 Rajarhat (GIS) S/S 2x315 APR-16 MAR-17 Land acquired in Feb'14. supply, civil works& erection under progress.

100% 85% 85%400/220 55% 0

244 Rajghat S/S (GIS) 2000 MAY-17 MAY-17 Award placed in Apr'15. Engg. in progress.100% 0% 0%400/220 0% 0

245 Rangpo S/S (GIS 16x105+3x100

NOV-13 MAR-16 Commissioned.100% 100% 100%400/220 100% 0

246 Rewa Pooling Station 3x1500 MAR-17 Work under progress.100% 15% 8%400/220 0% 0

Sub-Stations: Page 17 of 72

Page 18: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

247 SVA at 400/220 kV New WanpohS/S (+)300 MVAR/(-)200 MVAR

0 DEC-16 Work stopped due to disturbance in Kashmirsince 07.08.16

100% 65% 62%400/220 82% 0

248 SVC at 400/220 kV Kankroli s/s(+)600 MVAR/(-)400 MVAR

0 OCT-16 Work under progress.100% 90% 95%400/220 82% 0

249 SVC at 400/220 kV Ludhiana S/S(+)400 MVAR/(-)300 MVAR

0 OCT-16 work under progress.100% 85% 75%400/220 60% 0

250 Saharanpur S/S 2x315 NOV-12 MAY-16 Commissioned 05/16.100% 100% 100%400/220 100% 630

251 Samba (Extn.) S/S 315 MAY-16 DEC-16 Engg.,supply, civil work & erection underprogress.

100% 80% 70%400/220 70% 0

252 Satenapalli (Narasaraopeta) &Garividi (AP) S/S

0 APR-19 Award under progress.0% 0% 0%400/220 0% 0

253 Silchar (New) S/s 400 OCT-16 Major part of sub station chargedprogressively from Mar'12 to Oct'12.Balance Work under progress.

100% 99% 99%400/220 99% 0

254 Silchar S/S (New) 200 DEC-12 OCT-16 Major part of sub station chargedprogressively from Mar'12 to Oct'12.Balance under progress.

100% 99% 99%400/220 99% 0

255 Solapur (Aug.) 315 OCT-15 OCT-15 ICT commissioned in Oct'15.100% 100% 100%400/220 100% 0

256 Somanahalli S/S 500 FEB-17 AUG-16 Commissioned 08/16.100% 100% 100%400/220 100% 500

257 Somannm S/S 2x500 0% 0% 0%400/220 0% 0

258 Tirunelveli Pooling station (GIS) 2x500 APR-17 APR-17 Award placed in Apr'15. work underprogress.

100% 20% 0%400/220 0% 0

259 Trichy (Extn.) 500 FEB-17 FEB-17 Award placed in Sep'14. Engg. & civil workin progress.

100% 5% 0%400/220 0% 0

260 Tughlakabad S/S (GIS) 2000 JUL-17 JUL-17 Award under progress.Land yet to beacquired.

0% 0% 0%400/220 0% 0

261 Uttra (Pindiabil) S/S 630 MAR-16 JUN-16 Sub station completed in Jun'16.Commissioned in Jul'16.

100% 100% 100%400/220 100% 0

Sub-Stations: Page 18 of 72

Page 19: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

262 Vijayawada (Extn.) 500 FEB-17 FEB-17 Award placed in Sep'14. Work under progress.

100% 58% 50%400/220 24% 0

263 Wanpon (Extn.) S/S 420 DEC-16 Work stopped due to disturbance in Kashmirsince 07.08.16

100% 65% 62%400/220 82% 0

264 Warangal (Extn.) 500 FEB-17 FEB-17 Award placed in Sep'14.Work underprogress.

100% 78% 58%400/220 10% 0

265 Yelahanka (GIS) 2x500 JUN-13 MAR-17 Completion matching with line.Uncertain.100% 99% 99%400/220 98% 0

266 extn. Dharmapuri (Salem New)S/S

0 MAY-17 work under progress.100% 95% 90%400/220 85% 0

267 Anuppur S/S 160 0% 0% 0%220/132 0% 0

268 Balipara S/S 120 DEC-17 DEC-17 Award placed in Nov'15. Engg. in progress.100% 0% 0%220/132 0% 0

269 Bay Extn. Amargarh S/s 0 JUL-17 Not in scope in POWERGRID.100% 0% 0%220/132 0% 0

270 Bay Extn. Kishanganj S/S 0 NOV-16 Work under progress.100% 90% 90%220/132 70% 0

271 Bay Extn. New Melli (GIS) 0 0% 0% 0%220/132 0% 0

272 Bay Extn. Siliguri (Purena) S/S 0 NOV-16 work under progress.100% 67% 60%220/132 35% 0

273 Drass S/S 4x16.67 MAY-17 Award placed. Work under progress.100% 50% 60%220/66 20% 0

274 Kargil S/S 7x16.67 MAY-17 land yet to be acquired.0% 0% 0%220/66 0% 0

275 Khalsti S/S 4x16.67 MAY-17 Work under progress.100% 40% 40%220/66 10% 0

276 Kopili S/S 100 DEC-17 Award placed in Nov'15. Engg. in progress.100% 0% 0%220/132 0% 0

277 Legship S/S 100 NOV-16 Work yet to be awarded by PGCIL.0% 0% 0%220/132 0% 0

278 Leh S/S 7x16.67 MAY-17 Award placed. Work under progress.100% 60% 10%220/66 10% 0

279 Phursungi S/S 200 0% 0% 0%220/33 0% 0

Sub-Stations: Page 19 of 72

Page 20: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

280 RPH (Aug). S/S 60 0% 0% 0%220/132 0% 0

281 Wagoora (Ext.) S/ S 0 MAR-17100% 0% 0%220 0% 0

282 Bay Extn. Sujyamaninagar S/S 0 JAN-16 Commissioned in Jan'16.100% 100% 100%132/33 100% 0

283 Imphal S/S 2x50 APR-13 ICT-I (50MVA) commissioned in Mar'13 &ICT-II commissioned in Apr'13.

100% 100% 100%132/33 100% 100

284 Melriat S/S (Upgadable to 400kV)

2x50 JUN-17 Supply, civil works & erection underprogress. Completion matching with line.

100% 80% 65%132/33 10% 0

285 Namsai S/S 2x15 JUN-17 Work under progress. Completion matchingwith associated lines. Critical.

100% 65% 100%132/33 20% 0

286 Nirjuli S/S (Repl.) 80 MAR-16 ICT-I commissioned in Feb'16 & ICT-II inMAr'16.

100% 100% 100%132/33 100% 0

287 Roing S/S 2x15 DEC-16 Work under progress. Completion matchingwith associated lines. Critical.

100% 92% 100%132/33 92% 0

288 Tezu S/S 2x15 MAR-17 Work under progress. Completion matchingwith associated lines. Critical.

100% 88% 100%132/33 85% 0

Sub-Stations: Page 20 of 72

Page 21: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

ASSAM ELECTRICITY GRID CORP. LIMITED (AEGCL)

1 Kukumara S/S (2x50) 100 JUN-16 All testing and test charge completed.Awaiting the Mirza Azara 132 kV line to becompleted.

100% 90% 100%220/132 98% 0

2 Rangia S/S (2x100) 200 JUN-12 JUN-16 SS completed/charged on 24.06.2013.Awaiting completion of the line.

100% 100% 100%220/132 100% 0

3 Sonapur (2x100) 200 MAR-13 JUN-16 Work in progress.100% 60% 90%220/132 0% 200

Sub-Stations: Page 21 of 72

Page 22: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED. (APTRANSCO)

1 Gani S/S 2x315 JAN-17 642 Nos. out of 892 nos. foundations and187 Nos. out of 1026 Structure erectioncompleted. and construction of compound wall are inprogress.Foundation works are in progress.

100% 75% 80%400/220 0% 0

2 Garividi (Marala) 630 DEC-16 Purchase order was issued on15.11.2014.Levelling under progress. 562Nos. out of 578 Nos. foundations , 390 Nos. out of 700Nos.Structure erection and 130 Nos. out of449 Nos. equipment erection completed. Construction of Controlroom and Compound wall are underprogress.

100% 85% 65%400/220 50% 0

3 Hindupur S/S 3x315 Works commenced.100% 3% 0%400/220 0% 0

4 Jammalamadugu 630 DEC-16 Bus-I charged on 29.06.2016 from Narnoorto Jammalamadugu line.Works underprogress. The voltage ratio is400/220/132kV in place of 400/220 kV.

100% 98% 100%400/220 95% 0

5 Kalikiri 630 LOI issued on 16.09.2015.The detailedpurchase order issued in Nov'2015.Site handed ovder on 23.06.2016.

100% 0% 0%400/220 0% 0

6 Kamavarapukota 630 MAR-16 DEC-16 Purchase order issued on 13.03.2014.463Nos. foundations out of 488 Nos.foundations,501 Nos. out of 555 Nos. structure erectionand 299 Nos. out of 407 Nos. equipmenterection completed. Works under

100% 85% 85%400/220 80% 0

Sub-Stations: Page 22 of 72

Page 23: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

progress.

7 Kurnool S/S 2x315 0% 0% 0%400/220 0% 0

8 Podili S/S 630 LOI issued on 16.09.2015. DetailedPurchase order issued in Nov2015.

75% 0% 0%400/220 0% 0

9 Sattenapally 630 MAR-14 The substation was idle charged on26.02.2014 with 1No.315 PTR and put intocommercial operation from 31.03.2014. 2nd315 MVA PTR was charged on 24.04.2014.

null% null% null%400/220 null% 630

10 Uravakonda S/S 2x315 JUL-16 Commissioned 07/16.100% 100% 100%400/220 100% 630

11 Chakrayapet 200 MAR-17 Site handed over on 16.04.2016.Leveling ofsite works under progress.

100% 2% 0%220/132 0% 0

12 Gaddamvaripalli 50 JUN-16 Works under progress100% 100% 100%220/11 96% 0

13 Goddumarri 100 MAY-16 Works completed.100% 100% 100%220/11 100% 0

14 Gollapuram 200 NOV-16 Works are under progress.100% 80% 90%220/132 85% 0

15 N.P. Kunta Poling Station 160 APR-16 Commissioned 04/16.100% 100% 100%220/33 100% 160

16 Porumamilla 200 AUG-16 works are under progress.100% 95% 95%220/132 95% 0

17 Tirumalayapalli 300 DEC-16 Works are under progress.100% 60% 85%220/132 50% 0

18 Vajrakarur 100 JUL-16 Commissioned 07/16.100% 100% 100%220/132 100% 100

19 Yellanur 50 MAR-14 Substation charged on 27-03-2014.100% 100% 100%220/11 100% 50

Sub-Stations: Page 23 of 72

Page 24: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

BIHAR STATE ELECTRICITY BOARD (BSEB)

1 Barauni (TPS ) (ICT) 300 Award under process.0% 0% 0%220/132 0% 0

2 Biharshariff S/S 150 DEC-160% 0% 0%220/132 0% 0

3 Bihta (GSS) S/S 320 JUL-16 Work holdup due to approach road.100% 100% 5%220/132/33

0% 0

4 Bodhgaya (2nd Trf.) 150 DEC-160% 0% 0%220/132 0% 0

5 Dehri (Addl.) S/S 100 DEC-160% 0% 0%220/132 0% 0

6 Kishanganj S/S 320 DEC-16100% 10% 5%220/132/33

1% 0

7 Motipur (GSS) S/S 320 DEC-16100% 0% 0%220/132/33

0% 0

8 Musahari S/S 320 MAR-17 Work holdup due to land issues.0% 0% 0%220/132/33

0% 0

9 Pusauli S/S 300 MAY-16100% 100% 100%220/132/33

98% 0

10 Samastipur S/S 100 SEP-16100% 0% 0%220/132/33

0% 0

11 Supaul/Lokhi S/S 320 DEC-160% 0% 0%220/132/33

0% 0

Sub-Stations: Page 24 of 72

Page 25: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

CHHATTISGARH STATE POWER TRANSMISSION CO. LTD. (CSPTCL)

1 Jagdalpur S/s 630 NOV-14 DEC-16 Work under progress.100% 50% 50%400/220 50% 0

2 NSPCL (2x315 MVA) ICT-II 630 MAR-17 Failed during S C test. Under repair.100% 100% 100%400/220 100% 0

3 Borjhara S/S 2x160 MAR-17 Order Placed.100% 0% 0%220/132 0% 0

Sub-Stations: Page 25 of 72

Page 26: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

DELHI TRANSCO LIMITED (DTL)

1 Bamnoli S/S (Addl.) 315 MAR-180% 0% 0%400/220 0% 0

2 Gopalpur GIS 1000 MAR-220% 0% 0%400/220 0% 0

3 Mundka S/S (Addl.) 315 MAR-180% 0% 0%400/220 0% 0

4 Rangpuri GIS 2000 MAR-230% 0% 0%400/220 0% 0

5 Shalimarbagh GIS 2000 MAR-210% 0% 0%400/220 0% 0

6 220 KV Bays at Shalimar Bagh (2Nos.)

0 NOV-16 NOV-16100% 25% 50%220 15% 0

7 220 KV Bays at Vasant Kunj ( 2Nos.)

0 NOV-16 NOV-16 work not started due to permission of treecutting awaited from forest officer.

100% 0% 25%220 0% 0

8 220 KV bay at Masjid moth 0 OCT-16 OCT-16100% 0% 4%220 0% 0

9 AIIMS (Aug.) 100 MAR-170% 0% 0%220/33 0% 0

10 Bamnauli GIS 320 MAR-210% 0% 0%220/66 0% 0

11 Barwala (Rohini Sector-34) 320 MAR-230% 0% 0%220/66 0% 0

12 Budella S/S 320 MAR-180% 0% 0%220/66 0% 0

13 Budhpur GIS 320 MAR-210% 0% 0%220/66 0% 0

14 Chandrawal GIS 300 MAR-190% 0% 0%220/66 0% 0

15 DSIIDC Bawana (Addl.) 160 JAN-16 Commissioned 01/16 (Late Reported).100% 100% 100%220/66 100% 160

16 Dhansa/Jaffarpur/Jhatikalan 320 0% 0% 0%220/66 0% 0

17 Geeta Colony (Addl.) 100 MAR-170% 0% 0%220/33 0% 0

18 Gopalpur GIS 320 MAR-180% 0% 0%220/66 0% 0

19 Janakpuri GIS 320 MAR-200% 0% 0%220/66 0% 0

20 Jasola GIS 320 MAR-200% 0% 0%220/33 0% 0

21 Kanjhawala (Addl.) 160 FEB-16 Commissioned 02/16 (Late Reported).100% 100% 100%220/66 100% 160

Sub-Stations: Page 26 of 72

Page 27: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

22 Karol Bagh GIS 300 MAR-190% 0% 0%220/33 0% 0

23 Lodhi Road (GIS) 100 JUL-12 DEC-16 Dismantling of existing switch yard and thenconvert in to GIS.There are constraints in execution of workdue to non availability of shut downs.

100% 83% 72%220/33 60% 0

24 Maharanibagh GIS 300 MAR-190% 0% 0%220/33 0% 0

25 Maidan Garhi / IGNOU GIS 320 MAR-210% 0% 0%220/66 0% 0

26 Mangolpuri GIS 320 MAR-200% 0% 0%220/66 0% 0

27 Masjid Moth (Addl.) 100 MAR-170% 0% 0%220/33 0% 0

28 Masjid Moth (Addl.) 100 JUN-14 MAR-170% 0% 0%220/33 0% 0

29 Mayur Vihar GIS 320 MAR-220% 0% 0%220/66 0% 0

30 Mehrauli (Replacement) (160-100)

60 MAR-210% 0% 0%220/33 0% 0

31 Najafgarh (Replacement) (160-100)

120 MAR-210% 0% 0%220/33 0% 0

32 Narela (Replacement) (160-100) 60 MAR-210% 0% 0%220/33 0% 0

33 Nehru Place GIS 300 MAR-210% 0% 0%220/33 0% 0

34 Okhla (Replacement) (160-100) 120 MAR-210% 0% 0%220/33 0% 0

35 Panjabi Bagh GIS 300 MAR-190% 0% 0%220/33 0% 0

36 Pappankalan-II (Addl.) 160 DEC-15 Commissioned 12/15 (Late Reported).100% 100% 100%220/66 100% 160

37 Pappankalan-III 320 MAR-17 MAR-17100% 7% 0%220/66 0% 0

38 Patparganj (Addl.) 100 JUN-16 MAY-160% 0% 0%220/33 0% 0

39 Patparganj (Aug.) 100 MAR-170% 0% 0%220/33 0% 0

40 Patparganj (Replacement) (160-100)

120 MAR-210% 0% 0%220/33 0% 0

41 Peeragarhi (Addl.) 100 JUN-16 MAR-170% 0% 0%220/33 0% 0

Sub-Stations: Page 27 of 72

Page 28: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

42 Preet Vihar GIS 300 FEB-16 OCT-16 2 nos. 100 MVA Pr. Trf, 33 kV power cableare yet to be supplied.

100% 95% 75%220/66 70% 0

43 R.K. Puram GIS 160 MAR-180% 0% 0%220/66 0% 0

44 R.K.Puram GIS 100 MAR-180% 0% 0%220/33 0% 0

45 Replacement of 100 MVA by 160MVA at Pappankalan-I

60 FEB-16 Commissioned 02/16 (Late Reported).100% 100% 100%220/66 100% 60

46 Sanjay Gandhi Transport Nagar(SGTN) GIS

320 MAR-190% 0% 0%220/66 0% 0

47 Sarita Vihar (Addl.) 100 JAN-16 Commissioned 01/16 (Late Reported).100% 100% 100%220/66 100% 100

48 Sarita Vihar (Replacement) (160-100)

60 MAR-210% 0% 0%220/33 0% 0

49 Subzi Mandi GIS 100 MAR-210% 0% 0%220/66 0% 0

50 Tikri Khrd GIS 320 MAR-180% 0% 0%220/66 0% 0

51 Tughlakabad S/S 320 MAR-180% 0% 0%220/66 0% 0

Sub-Stations: Page 28 of 72

Page 29: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

ELECTRICITY DEPARTMENT, GOVT. OF MANIPUR (ED, Manipur)

1 Yurembam (Aug.) S/S 3X33.5 MAR-13100% 0% 0%132/33 0% 0

Sub-Stations: Page 29 of 72

Page 30: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

GOA ELECTRICITY DEPARTMENT (ED- GOA)

1 Kadamba GIS 2x100 MAR-19 Proposals have been forwarded toGovernment. The approval is awaited fromFinance Department.

0% 0% 0%220/110 0% 0

2 Ponda s/s (Addl.) 1x50 MAR-19 Letter of Intent will be issued to RECTPCLshortly, who has been appointed as ProjectManagement consultant(PMC). Necessaryapprovals have been obtatined from theGovernment.

0% 0% 0%220/33 0% 0

3 Soccorro S/S 320 MAR-170% 0% 0%220/33 0% 0

4 Tivim (3rd Trf.) (Aug.) 1x100 MAR-17 Work in progress.100% 0% 0%220/110 0% 0

5 Tuem GIS 3x63 MAR-19 Letter of Intent will be issued to RECTPCLshortly, who has been appointed as ProjectManagement consultant(PMC). Necessaryapprovals have been obtatined from theGovernment.

0% 0% 0%220/33 0% 0

6 Verna GIS 2x160 MAR-19 Proposals have been forwarded toGovernment. The approval is awaited fromFinance Department.

100% 0% 0%220/110 0% 0

Sub-Stations: Page 30 of 72

Page 31: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

GUJARAT ENERGY TRANSMISSION CORP. LIMITED (GETCO)

1 Achchhalia S/S 2x315 100% 0% 0%400/220 0% 0

2 Amreli (ICT addition) 500 MAR-17100% 100% 100%400/220 80% 0

3 Bhachunda GIS (Dist. Kutch) 3x100 100% 0% 0%400/220 0% 0

4 Bhogat GIS (Dist. Jamnagar) 2x500 100% 0% 0%400/220 0% 0

5 Bhogat S/S 1x315 .0% 0% 0%400/220 0% 0

6 Charanka S/S 2x315 DEC-16 WIP100% 100% 100%400/220 98% 0

7 Chhara S/S 315 0% 0% 0%400/220 0% 0

8 Fedra S/S 2x315 100% 0% 0%400/220 0% 0

9 Halvad 315 MAR-15 400/220/66KV system back charged on Dt.:31.03.14.

100% 100% 100%400/220 100% 630

10 Kasor (Aug.) 315 AUG-16 Commissioned 08/16.100% 100% 100%400/220/33

100% 315

11 Kasor (ICT addition) 1x315 JUN-16100% 100% 100%400/220 100% 0

12 Keshod S/S 630 0% 0% 0%400/220 0% 0

13 Kosamba (ICT addition) 500 DEC-16100% 90% 50%400/220 0% 0

14 Pipavav S/S 1x315 100% 0% 0%400/220 0% 0

15 Prantij S/S 2x315 100% 0% 0%400/220 0% 0

16 Rajkot (Hadala) ICT-II 315 MAY-16100% 0% 0%400/220 0% 0

17 Sankhari S/S 2x315 0% 0% 0%400/22 0% 0

Sub-Stations: Page 31 of 72

Page 32: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

0

18 Veloda (Sankhari) S/S 1000 OCT-16 02 Nos. 160MVA 220/66KV TR. charged onDt: 18.03.16 and Dt: . 29.03.16. 01No.500MVA 400/220KV Tr. charged on Dt:31.03.16. 80MVAr 400KV Bus Reactorcharged on Dt: 31.03.16.

100% 95% 96%400/220 96% 0

19 Agthala (Aug.) 100 AUG-16 Commissioned 08/16.100% 100% 100%220/66 100% 100

20 Asodar S/S 1x100 Dropped0% 0% 0%220/66 0% 0

21 Babara (Dist. Amreli) S/S 2x160 0% 0% 0%220/66 0% 0

22 Babara (Dist. Amreli) S/S 2x150 0% 0% 0%220/132 0% 0

23 Bagasara S/S 1x100 0% 0% 0%220/66 0% 0

24 Bechraji S/S 200 Back Charged, line work under progress100% 100% 100%220/66 100% 200

25 Bhachunda GIS (Dis. Kutch) 2x160 WiP100% null% 0%220/66 0% 0

26 Bhestan S/S 1x100 Commissioned. Name changed to Popda(Bhestan)

100% 100% 100%220/66 100% 300

27 Bhogat GIS (Dist. Jamnagar) 2x160 100% 0% 0%220/66 0% 0

28 Chhatral (Aug.) 100 AUG-16 Commissioned 08/16.100% 100% 100%220/66 100% 100

29 Dhanaj S/S 2x100 MAR-18 Substatio name is replace with Gatrad100% 45% 0%220/66 0% 0

30 Gatrad S/S 3x100 MAR-18100% 45% 10%220/132/66

10% 0

31 Gondal S/S 2x100 0% 0% 0%220/66 0% 0

32 Gotri 1x160 MAR-17 WIP100% 65% 60%220/66 45% 0

33 Jasdan 200 DEC-12 As land was not suitable so field office areconveyed to search for fresh land.Dropped

100% 0% 0%220/132 0% 200

34 Kalavad GIS (Dist. Jamnagar) 3x160 100% 0% 0%220/66 0% 0

35 Kalavad S/S 1x100 0% 0% 0%220/66 0% 0

36 Kalawad 100 JUN-16100% 0% 0%220/66 0% 0

Sub-Stations: Page 32 of 72

Page 33: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

37 Kansari (Aug.) 60 AUG-16 Commissioned 08/16.100% 100% 100%220/66 100% 60

38 Kerala S/S 2x100 100% 0% 0%220/66 0% 0

39 Khambhalia S/S 200 WIP100% 0% 0%220/66 0% 0

40 Kim (Aug.) 100 AUG-16 Commissioned 08/16.100% 100% 100%220/66 100% 100

41 Mehsana (Aug.) 50 AUG-16 Commissioned 08/16.100% 100% 100%220/132 100% 50

42 Methoda S/S 200 0% 0% 0%220/66 0% 0

43 Mota (Aug.) 110 AUG-16 Commissioned 08/16.100% 100% 100%220/66 100% 110

44 Moti Gop S/S 3x160 100% 0% 0%220/66 0% 0

45 Nani Hamirpur S/S 50 MAR-15 Commissioned100% 100% 100%220/11 100% 50

46 Navlakhi S/S 2x100 Dropped0% 0% 0%220/66 0% 0

47 Prantij S/S 2x100 0% 0% 0%220/66 0% 0

48 Rajkot (Nyara) (Aug.) 60 AUG-16 Commissioned 08/16.100% 100% 100%220/66 100% 60

49 Rajkot-II S/S 2x100 0% 0% 0%220/66 0% 0

50 Salejada (Aug.) 100 AUG-16 Commissioned 08/16.100% 100% 100%220/66 100% 100

51 Saria 100 DEC-12 Retender is carried out for Erectionpackage.LOI issued for SCADA package.Major equipments will be supplied byGETCO.

100% 35% 65%220/132 0% 0

52 Suva 200 JUN-16 A/T issued for total turnkey package.100% 40% 12%220/66 6% 200

53 Talaja S/S 1x100 0% 0% 0%220/66 0% 0

54 Vadala 100 MAR-13 WIP100% 11% 0%220/66 0% 0

55 Vallabhipur S/S 100 FEB-15 Commissioned100% 100% 100%220/66 100% 100

56 Vyankatpura 100 JUN-16100% 7% 0%220/66 0% 0

Sub-Stations: Page 33 of 72

Page 34: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

HIMACHAL PRADESH POWER TRANSMISSION CORP. LTD. (HPPTCL)

1 Gumma S/S 2x315 0% 0% 0%400/220 0% 0

2 Lahal S/S 630 JAN-180% 0% 0%400/220 0% 0

3 Pragati Nagar (2nd Trf) 315 JUL-160% 0% 0%400/220 0% 0

4 Pragati Nagar S/S 315 JUL-160% 0% 0%400/220 0% 0

5 Wangtoo (GIS) S/S 630 0% 0% 0%400/220 0% 0

6 Wangtoo S/S 630 AUG-170% 0% 0%400/220 0% 0

7 Barsaini S/S 63 MAR-160% 0% 0%220/33 0% 0

8 Bhokto S/S 31 FEB-16 JUN-16100% 70% 60%220/66 50% 0

9 Dehan S/S 200 0% 0% 0%220/132 0% 0

10 Karian S/S 63 MAR-13 OCT-16 Trf. transportation issued due to narrowroad/bridge.

100% 70% 100%220/33 0% 0

11 Koti S/S 200 0% 0% 0%220/132 0% 0

12 Lahal S/S 63 JAN-17 DEC-160% 0% 0%220/33 0% 0

13 Mandhala 100 0% 0% 0%220/66 0% 0

14 Mazra GIS 2x100 Under planning stage.0% 0% 0%220/132 0% 0

15 Sunda S/S 200 MAR-17 DEC-16 Substation is being constructed with fundssourced from ADB.

0% 0% 0%220/132 0% 0

16 Taran tulla (Addl.) 100 0% 0% 0%220/132 0% 0

Sub-Stations: Page 34 of 72

Page 35: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

HARYANA VIDYUT PRASARAN NIGAM LIMITED (HVPNL)

1 Barhi S/S 200 OCT-16 work in progress100% 70% 60%220/132 25% 0

2 Gurgaon Sector - 33 200 DEC-16 Work in progress.100% 81% 75%220/66 47% null

3 Gurgoan Sector - 20 (GIS) 300 DEC-16 Work in progress100% 85% 95%220/66 72% 0

4 Gurgoan Sector -57 200 DEC-16 work in progress. Firm has been requestedto expedite the work.

100% 75% 70%220/66 30% 0

5 HSIIDC Rai S/S 200 MAR-17 Physical possession of land not given byHSIIDC. Proposal for up-gradation of 132 kVS/Stn. Rai to 220 kV level is approved.Work is yet to be start.

0% 0% 0%220/132 0% 0

6 Hukmawali S/S 200 JUL-16 Commissioned 04/16 (Late Reported).100% 100% 100%220/132 100% 200

7 Kaul S/S 100 MAY-16 Commissioned 05/16.100% 100% 100%220/132 100% 100

8 Meerpur Kurali S/S 200 OCT-16 Work in progress.Firm has been requestedto expedite the work.

100% 57% 40%220/66 32% 0

9 Panchgaon S/S 320 SEP-16 Work in progress100% 70% 60%220/66 55% 0

10 Panchkul Sector- 32 S/S 200 JUL-17 Work stopped by firm. Contractual problem.Court case.Re-bidding at the risk & cost offirm is under process.

100% 78% 15%220/66 2% 0

11 RGEC, Sonipat S/S 200 DEC-16 Work in progress.100% 70% 70%220/33 45% 0

12 Roj-Ka-Meo 2x160 JUL-17 Work in progress.100% 15% 0%220/66 0% 0

13 Roj-Ka-Meo 100 JUL-17 Work in progress.100% 15% 0%220/33 0% 0

14 Sector -6, Sonipat S/S 200 DEC-16 Work in progress. Firm has been requestedto expedite the work.

100% 48% 5%220/33 0% 0

15 Sonta S/S (ICT-I) 100 MAY-16 Commissioned 05/16.100% 100% 100%220/66 100% 100

Sub-Stations: Page 35 of 72

Page 36: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

J&K POWER DEVELOPMENT DEPARTMENT (JKPDD)

1 Alchi. S/S 6.3 NOV-12 Commissioned 11/12.100% 100% 100%66/11 100% 6

2 Gramthong S/S 60 SEP-12 Commissioned.100% 100% 100%66/11 100% 60

3 Himya 60 JUL-13100% 30% 0%66/11 0% 0

4 Kargil S/S 60 SEP-12 Commissioned.100% 100% 100%66/11 100% 60

5 Khalsi 60 JUL-13 Commissioned100% 100% 100%66/11 100% 60

6 Khangral (Bodhkharbu) 60 SEP-14 Commissioned.100% 100% 100%66/11 100% 60

7 Kharu 60 DEC-13 Commissioned100% 100% 100%66/11 100% 60

8 Leh 2x6.3 DEC-12 Commissioned 12/12.100% 100% 100%66/11 100% 13

9 Mulbeck 60 SEP-15 Commissioned.100% 100% 100%66/11 100% 60

10 Nimoo S/S 60 JUL-13 Commissioned.100% 100% 100%66/11 100% 60

11 Sankoo S/S 60 SEP-14 Commissioned.100% 100% 100%66/11 100% 60

12 Alusteng S/S 320 JAN-17 Transformers received.Due to technicalreasons work get delayed.

100% 70% 80%220/132 20% 0

13 Budgam (Aug.) 160 DEC-16 Works planned for execution during 12thFive year Plan (2012-17). Funding to bearranged.

100% 99% 100%220/132 100% 0

14 Budgam (Aug.) 2nd Trf. 160 MAR-17 Works planned for execution during 12thFive year Plan (2012-17). Funding to bearranged.

0% 0% 0%220/132 0% 0

15 Lassipora S/S 320 MAR-17 Works planned for execution during 12thFive year Plan (2012-17). Funding to bearranged.

0% 0% 0%220/132 0% 0

16 Mirbazar (Aug.) 160 MAR-17 Works planned for execution during 12thFive year Plan (2012-17). Funding to bearranged.

0% 0% 0%220/132 0% 0

17 Yonus Wahipora (Kupwara) S/S 320 MAR-17 Works planned for execution during 12thFive year Plan (2012-17). Funding to bearranged.

0% 0% 0%220/132 0% 0

18 Zainkote (Aug.) 3x150 DEC-12 MAR-17 Work under prgoress.Works planned for100% 0% 0%220/13 0% 0

Sub-Stations: Page 36 of 72

Page 37: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

execution during 12th Five year Plan (2012-17). Funding to be arranged.

2

Sub-Stations: Page 37 of 72

Page 38: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

JHARKHAND STATE ELECTRICITY BOARD (JSEB)

1 Latehar S/S 2x315 0% 0% 0%400/220/132

0% 0

2 Patratu (New) S/S 2x315 0% 0% 0%400/220 0% 0

3 Chatra S/S 400 MAR-17 Delay due to non-availability of fund naxalaffected area.

0% 0% 0%220/132/33

0% 0

4 Giridih S/S 400 SEP-16 Tender invited vid NIT.0% 0% 0%220/132/33

0% 0

5 Govindpur (New) S/S 400 OCT-160% 0% 0%220/132/33

0% 0

6 Jainamore (Bokaro) S/S 400 SEP-16 Tender is in awarding stage.0% 0% 0%220/132/33

0% 0

7 Jasidih S/S 400 SEP-16 Tender is in awarding stage.0% 0% 0%220/132/33

0% 0

8 Lohardaga S/S 2x150 0% 0% 0%220/132 0% 0

Sub-Stations: Page 38 of 72

Page 39: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

KARNATAKA POWER TRANSMISSION CORP. LIMITED (KPTCL)

1 Electronic city S/S 2x500 MAR-17 Land under dispute and the matter is in HighCourt. Line work: To be tendered.

0% 0% 0%400/220 0% 0

2 Gadag (Doni) S/S 2x500 LOI issued on 29.07.2016.0% 0% 0%400/220 0% 0

3 Gulbarga S/S 1000 Land acquired. Geo tech survey workawarded on 18-Jul-16. Bill of Materialsissued and estimate is under preparation.

0% 0% 0%400/220 0% 0

4 Jagalur S/S 2x500 LOI issued on 29.07.2016.0% 0% 0%400/220 0% 0

5 Chinthamani (Aug.) 100 JUL-16 AUG-16 Work is under progress.100% 90% 70%220/66 70% 0

6 Gowribidanur (Aug.) 100 NOV-12 AUG-16 Transformer supplied on 11-May-16. Work isunder progress.

100% 95% 100%220/66 95% 0

7 Hosadurga S/S 2x100 0% 0% 0%220/66 0% 0

8 Jigani (2x150) 300 MAR-13 MAR-17 220 kV side: PC tests to be completed.

Incoming line scheme changed. Tenderfloated. Source line awaited.

100% 95% 100%220/66 100% 0

9 Kanakapura (Aug.) 100 MAR-15 AUG-16 All equipment on 220 kv & 66 kv side cableduct completed. Equipment earthingcompleted. M/s BHEL 100 MVA powertransformer alloted on 01.02.2016. C&Rpanel.

100% 90% 90%220/66 90% 0

10 Koppal S/S 2x100 MAR-17 Work short closed vide O.M. No.:CEE/TZ/GLB/SEE(O)/AEE-3/2014-15/3830-37, Dated:12.09.2014 of Chief Engineer Electy.,Transmission Zone, KPTCL., Gulbarga. Tobe retendered.

100% 0% 0%220/110 0% 0

11 Kudligi (Badeladaku) S/S 200 MAY-14 NOV-16 Transformers, CTs, PTs and majorequipment erection completed. Work

100% 75% 90%220/66 90% 0

Sub-Stations: Page 39 of 72

Page 40: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

under progress.

12 Magadi S/S 200 MAY-15 NOV-16 Work under progress.100% 20% 20%220/66 20% 0

13 Mallat (Manvi) S/S 200 AUG-14 DEC-16 Work under progress.100% 60% 60%220/66 60% 0

14 Mittemari S/S 200 JUL-15 JAN-17 Work under progress.100% 25% 50%220/66 50% 0

15 Mughalkod S/S 2x100 0% 0% 0%220/110 0% 0

16 Pavagada S/S 100 JUL-14 NOV-16 Transformers received and erected.Earthing of equipments and cable layingunder progress.

Terminal bays at 220 KV Madhugiri station:Equipment erection under progress.

100% 50% 100%220/66 70% 0

17 Ramanagar(Kothipura) (2nd ICT) 1x100 DEC-07 DEC-16 Stn :All works at both 220kV & 66kV sidecompleted.2nd 100 MVA Tr to be alloted. Contract isterminated on 25.01.2016.Tendered on10.05.2016 for balance work.

220KV TB at Tubinakere:PC testscompleted except bus stability test.220 KV TB at Bidadi:Approval for shutdownof Bus 1 & 2 is reqd for erection of balanceBPIs & bus extension work. Line clear willbe availed after completion of PC tests.

100% 100% 100%220/66 100% 0

18 Shivanasamudram S/S 2x100 0% 0% 0%220/66 0% 0

19 Vikas Tech Park (2x150) 300 OCT-11 MAR-17 220kV and 66kV side PC tests & SAS workcompleted. PC test on power transformers &batteries will be taken up duringcommissioning. Portion of incoming line isUG cable and the work is under tenderstage.

100% 95% 100%220/66 100% 0

Sub-Stations: Page 40 of 72

Page 41: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

Source line awaited.

Sub-Stations: Page 41 of 72

Page 42: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

KERALA STATE ELECTRICITY BOARD (KSEB)

1 Kanjikkod (Add.Tr.) 50 This work is not included in the Plan for2015-16. May be deleted.

0% 0% 0%220/110 0% 0

Sub-Stations: Page 42 of 72

Page 43: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

M.P. POWER TRANSMISSION CORPORATION LIMITED (MPPTCL)

1 Badnawar (2x315) 630 0% 0% 0%400/220 0% 0

2 Balaghat / Kimapur S/S 315 0% 0% 0%400/220 0% 0

3 Handia S/S 630 0% 0% 0%400/220 0% 0

4 Mandsaur S/S 0 0% 0% 0%400/220 0% 0

5 Sagar S/S 630 0% 0% 0%400/220 0% 0

6 Ujjain S/S 630 0% 0% 0%400/220 0% 0

7 Barwaha S/S 160 0% 0% 0%220/132 0% 0

8 Bhopal S/S 160 0% 0% 0%220/132 0% 0

9 Gandhinagar S/S 160 0% 0% 0%220/132 0% 0

10 Gorabazar S/S 160 0% 0% 0%220/132 0% 0

11 Gudgaon S/S 0 0% 0% 0%220/132 0% 0

12 Hoshangabad S/S 160 0% 0% 0%220/132 0% 0

13 Indore S/S 160 0% 0% 0%220/132 0% 0

14 Jaora (Upgradation) 0 0% 0% 0%220/132 0% 0

15 Kanwan S/S 0 0% 0% 0%220/132 0% 0

16 Kukshi S/S 160 0% 0% 0%220/132 0% 0

17 Mandideep S/S 160 0% 0% 0%220/13 0% 0

Sub-Stations: Page 43 of 72

Page 44: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

2

18 Morena S/S 320 0% 0% 0%220/132 0% 0

19 Mugalyia-chhap s/s 160 JUN-16 Commissioned 06/16.100% 100% 100%220/132 100% 160

20 Pandhurna S/S 160 0% 0% 0%220/132 0% 0

21 Pithampur-II S/S (Upgradation of132 kV S/S)

160 APR-16 Commissioned 04/16.100% 100% 100%220/132 100% 160

22 Ratangarh S/S 0 0% 0% 0%220/132 0% 0

23 Sailana S/S 0 0% 0% 0%220/132 0% 0

24 Sendhwa S/S 0 0% 0% 0%220/132 0% 0

25 Shajapur (Addl. 2nd Unit) 160 APR-16 Commissioned 04/16.100% 100% 100%220/132 100% 160

26 Shankargarh / Khsipra S/S 160 0% 0% 0%220/132 0% 0

27 Sidhi S/S 160 0% 0% 0%220/132 0% 0

28 Susner S/S 0 0% 0% 0%220/132 0% 0

29 Suwasara S/S 0 0% 0% 0%220/132 0% 0

30 Nalkheda(Aug.) 40 0% 0% 0%132/33 0% 0

31 Vijaipur (Aug.) 40 0% 0% 0%132/33 0% 0

Sub-Stations: Page 44 of 72

Page 45: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

MAHARASHTRA STATE ELEC. TRANSMISSION COMPANY LTD. (MSETCL)

1 Aurangabad III (Ektuni) S/S (ICT-I)

1500 MAY-16 Commissioned 05/16.100% 100% 100%765/400 100% 1500

2 Alkud S/S 500 JAN-17 Work in progress.100% 81% 80%400/220 73% 0

3 Aurangabad II 1000 SEP-16 400kV Bus charged on 21.05.2014. Work inProgress.

100% 85% 80%400/220 55.3% 0

4 Chandrapur-II 1000 AUG-16 Priority Bay 410, 426, 408 (Tie Bay) and 409,411, 412, 428, 429, 404, 405 commissionedfrom 30.12.2013 to 13.3.2014

100% 91.98% 96%400/220 77.46% 0

5 Hinjewadi II (GIS) 2x500 JUN-16 Outdoor GIS at Hinjewadi -II test charged on19.12.2015.400/220/33kV,167 MVA ICTs & its bays,400kV& 220kV GIS Bays test charged on30.05.2016.400kV line side jumpering is balance forwant of completion of line.

100% 100% 100%400/220 99.28% 0

6 Koradi-II (ICT-II) 500 SEP-16 Work in progress.100% 83.26% 90%400/220 81.9% 0

7 Kudus S/S 2x500 MAR-17 Work in progress.100% 50% 80%400/220 12% 0

8 Nanded (Kumbhargaon)S/S (ICT-II)

500 JUN-16 Commissioned 06/16.100% 100% 100%400/220 100% 500

9 Anjangaon S/S 1x100 MAR-17 Arbitral award- Group C. Tendering underprocess for balance work.

100% 40% 30%220/132/33

2% 0

10 Ballarshah S/S 50 SEP-16 Minor civil work is balance.100% 98% 100%220/132,220/33

91% 0

11 Bhokardhan (2nd Trf.) 50 AUG-120% 0% 0%220/33 0% 0

12 Chakan S/S 100 SEP-16 50 MVA TF-I charged on 06-03-201650 MVA TF-II Charged on 23-03-2016100 MVA ICT-I charged on 30.03.2016

100% 92% 100%220/132 92.36% 0

13 Krishnoor S/S 200 JUN-17 Arbitral award- Group C. Tender for100% 53% 56%220/13 9% 0

Sub-Stations: Page 45 of 72

Page 46: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

balance work to be refloated.2/33

14 Lonand MIDC S/S 150 DEC-16 220/132 KV 100MVA ICT is commissionedon Dt. 29.02.2016.220/33 KV 50MVA T/F is commissioned onDt. 23.03.2016.Work in progress.

100% 92% 85%220/132,220/33

70% 0

15 Lonideokar S/S 100 JAN-17 Work in progress.100% 95% 100%220/132 94.53% 0

16 Majarsumbha S/S 25 SEP-16 1x25MVA, 220/33 KV T/F II is Charged onDt.08.03.2016

100% 99% 100%220/132 94.3% 0

17 Malegaon -II S/S 100 DEC-12 JAN-17 Arbitral award- Group C. Tendering inprocess for balance work.

100% 44% 45%220/132 32% 0

18 Mankapur S/S 2x100+2x50

DEC-17 Work is done slow by agency.100% 12.79% 95%220/132,220/33

0% 0

19 New Pardi S/S 200 DEC-17 Work in Progress.100% 54.34% 95%220/132 67% 0

20 Phulumbri S/S 50 JUN-16 Work in progress.100% 99% 100%220/33 97% 0

21 Pimpalgaon S/S 100 DEC-16 SS back charged from 132 kV on dt.20.03.2014.Balance works-Bus and earthwire stringing, cabletermination, Earthmat/ Earthpits, PLCCworks,SCADA, testing works.

100% 100% 95%220/132 95% 0

22 Purtur S/S 50 MAR-17 Work is in progress.100% 90% 90%220/33 88.5% 0

23 Purtur S/S 200 MAR-17 Work is in progress.100% 90% 90%220/132 88.5% 0

24 Uppalwadi S/S 2x100+2x50

DEC-17 Work is slow by agency.100% 34.81% 80%220/132,220/33

0% 0

25 Vairag S/S 50 Work in progress.100% 75% 80%220/33 51% 0

26 Vile Bhagad S/S 50 MAR-17 S/S. almost completed.100% 90% 95%220/33 90% 0

27 Wada-II S/S 100 OCT-15 2 X 100MVA, 220/33-22kV T/Fs.100% 90% 100%220/22 95% 0

Sub-Stations: Page 46 of 72

Page 47: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

commissioned on dt. 31.05.2015 &31.10.2015 respectively.

28 Warud S/S 200 FEB-14 S/s back charged on 28.02.14100% 94.38% 100%220/132 92.7% 0

Sub-Stations: Page 47 of 72

Page 48: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

MEGHALAYA ENERGY CORP. LTD. (MeECL)

1 Killing S/S 630 FEB-15 Work executed by Power Grid. Theexpenditure for the substation is inclusive ofthe LILO line. Both the LILO & thesubstation works are completed &commissioned on 22.02.2015. The project iscompleted except for some civil works whichare delayed due to fund constraint.

100% 100% 100%400/220 100% 630

2 Ampati S/S (2x25) 50 MAR-17 Soil testing & retaining wall,temporary shed,boundary wall fencing, staff barrack,levelling of land for 132 kV & 33 kVswitchyard, transformer pad - 1 no.completed.Works for control room, 3-storied staffquarter, 4- unit staff barrack & transformerpad No.2 are in progress.Overall progress is 50% completed.

100% 25% 90%132/33 0% 0

3 Lad Nongkrem S/S 40 MAR-17 Land levelling, retaining wall, approach road& culvert, transformer pad,Fencing,securitybarrack, side drain and gate at the front side& security shed, filtration of transformercompleted. Construction of control roombuilding is in progress.Overall sub-station work is 30% completed.

100% 50% 50%132/33 0% null

4 Mawphlang S/S 40 FEB-12 Work completed. One transformer iscommissioned on 23.12.2011 & 2ndtransformer commissioned on 20.02.2012.

100% 100% 100%132/33 100% 40

5 Mendipathar S/S 40 MAR-17 Substation is charged with 132/ 33 kV 20MVA transformer No. 1. 132/33 kV 20MVAtransformer No. 2 is placed on the pad andthe work for 132 kV

100% 100% 100%132/33 90% 20

Sub-Stations: Page 48 of 72

Page 49: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

switchyard for transformer No. 2 is inprogress.Overall progress 92% completed.

6 Mustem S/S 40 NOV-15 Work completed and substationcommissioned on 20.11.2015

100% 100% 100%132/33 100% 40

7 Praharinagar S/S 25 DEC-16 Land procurement process completed.Topological survey for sub-station iscompleted

0% 0% 0%132/33 0% 0

8 Rongkhon (Aug.) S/S 50 DEC-16 The transformer augmentation of thesubstation has been completed on20.10.2012. Other works relating to PLCC,RTU & 33kV switchyard; the materialsprocurement is in progress. Overall status is90% completed.

100% 90% 90%132/33 90% 20

Sub-Stations: Page 49 of 72

Page 50: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

ORISSA POWER TRANSMISSION CORPORATION LTD. (OPTCL)

1 Lapanga S/S 630 NOV-160% 0% 0%400/220 0% 0

2 Mendhasal ICT -III 315 0% 0% 0%400/220 0% 0

3 Aska S/S 320 JUN-170% 0% 0%220/132/33

0% 0

4 Atri (Karadagadia ) 2nd ICT S/S 160 AUG-16 Commissioned 08/16.100% 100% 100%220/132/33

100% 160

5 Balasore (ICT-III) 160 DEC-160% 0% 0%220/132 0% 0

6 Baliguda S/S 40 JUN-170% 0% 0%220/33 0% 0

7 Bargarh (New) S/S 320 AUG-160% 0% 0%220/132/33

0% 0

8 Bonai S/S 80 DEC-16 Since the Agency M/s U.B.Engineering hasdelayed the work, it is offloaded from thecontractor's scope and re-tendering is done.A fresh work order was placed on M/s JDConstruction, Balasore and the work isgoing on.

100% 35% 60%220/33 40% 0

9 Chandaka - B GIS S/S 320 0% 0% 0%220/132/33

0% 0

10 Cuttack S/S 2x100 DEC-16 The work order placed on M/s TeslaTransformers on 21.09.2011.

100% 100% 100%220/132 100% 0

11 Dhamara S/S 200 MAR-17 The work oredr placed on M/s TeslaTransformers on 17.07.2013 on M/s TeslaTransformers was cancelled and may bedeleted at present

0% 0% 0%220/132/33

0% 0

12 Goda Chhak S/S 320 MAR-170% 0% 0%220/132/33

0% 0

13 INFOCITY-II GIS (Bhubaneswar)S/S

80 JUL-160% 0% 0%220/33 0% 0

14 Jayapatana S/S 320 FEB-180% 0% 0%220/132/33

0% 0

Sub-Stations: Page 50 of 72

Page 51: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

15 Kalimela S/S 40 FEB-180% 0% 0%220/33 0% 0

16 Kasipur S/S 40 0% 0% 0%220/33 0% 0

17 Keonjhar GIS S/S 80 JUN-170% 0% 0%220/33 0% 0

18 Kesinga S/S 2x160 DEC-16 The Work Order placed on M/s A.K.Das &Associates, Bhubaneswar on 27.07.2012

100% 50% 50%220/132 40% 0

19 Kuanrmunda S/S 200 DEC-16 Due to site condition the work was offloadedfrom the Executing Agency.

100% 40% 45%220/132/33

0% 0

20 Laxmipur S/S 20 0% 0% 0%220/33 0% 0

21 Malkanagiri S/S 80 SEP-160% 0% 0%220/33 0% 0

22 Narasinghpur S/S 40 0% 0% 0%220/33 0% 0

23 Pratapassan S/S 320 DEC-160% 0% 0%220/132/33

0% 0

24 Puri (Samangara) ICT-II S/S 160 AUG-16 Commissioned 08/16.100% 100% 100%220/132 100% 160

Sub-Stations: Page 51 of 72

Page 52: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

PUNJAB STATE TRANSMISSION CORPORATION LIMITED (PSTCL)

1 Dhuri (Addl.) 500 FEB-17 FEB-17 Works in progress.100% 85% 40%400/220 0% 0

2 Rajpura S/S (2x500) (ICT-I) 500 JUN-16 Commissioned 06/16.100% 100% 100%400/220 100% 500

3 Ablowal (Addl.) 100 MAR-17 MAR-17 Civil works in progress100% 60% 0%220/66 0% 0

4 Abohar (Addl.) 100 AUG-16 AUG-16 Commissioned 08/16.100% 100% 100%220/66 100% 100

5 Ajitwal (Addl.) 100 MAR-17 MAR-17 Work is in progress100% 65% 30%220/66 30% 0

6 Badal (New) S/S 100 JUN-16 Commissioned 06/16.100% 100% 100%220/66 100% 100

7 Badshahpur (Addl.) 100 OCT-16 OCT-16 Work is in progress100% 72% 40%220/66 0% 0

8 Bhai S/S 100 Energised on no load on 23.1.13 from 66 KVand loaded on 14.06.13

100% 100% 100%220/132 100% 0

9 Bhari 160 SEP-16 OCT-16 Work is in progress100% 95% 90%220/66 80% 0

10 Bhawanigarh 160 DEC-16 DEC-16 Work is in progress100% 93% 85%220/66 50% 0

11 Dhanaula (Aug.) 100 AUG-16 OCT-16 Work is in progress100% 85% 90%220/66 90% 0

12 Jadla S/S 160 JUN-16 Commissioned 06/16.100% 100% 100%220/66 100% 160

13 Kanjli (Aug.) 100 DEC-16 DEC-16 Work is in progress100% 75% 50%220/66 40% 0

14 Ladowal 160 MAR-17 MAR-17 Work is in progress100% 50% 40%220/66 20% 0

15 Majra S/S 160 JUN-16 Commissioned 06/16.100% 100% 100%220/66 100% 160

16 Mastewala (Aug.) (Addl.) 100 MAR-17 Work is in progress100% 60% 5%220/66 0% 0

17 Nurmehal (Aug.) 100 NOV-16 Work is in progress100% 85% 40%220/66 40% 0

18 Rajpura (Addl.) 100 SEP-16 DEC-16 1x500 MVA,400/220 KV Transformercommissioned on 28.06.2016 on no load.Further work is in progress

100% 85% 90%220/66 85% 0

19 Sarna (Addl.) 100 APR-16 Commissioned 04/16.100% 100% 100%220/132 100% 100

20 Science city (Jalandhar) 100 JUL-16 OCT-16 Test charged on 07.12.15 on 132 KV100% 92% 90%220/132 90% 0

Sub-Stations: Page 52 of 72

Page 53: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

POWER TRANSMISSION CORP. OF UTTARAKHAND LTD. (PTCUL)

1 Karanprayag (GIS) 630 JUN-17 Construction of Substation as perConnectivity schedule of generators inYamuna Valley.

0% 0% 0%400/132 0% 0

2 Pipalkot (THDC) 2x315 work delayed due to agitation by localvillagers

0% 0% 0%400/220 0% 0

3 Pipalkoti (GIS) 630 DEC-16 Re-invitation of bids is in process & sent toADB for uploading on website/ date ofsubmission of bid was 25th July, 2013. Bidis under evaluation an likely to be awardedby II nd quarter of 2014.

100% 0% 0%400/132 0% 0

4 Srinagar S/S 2x315 DEC-12 JUL-16 Commissioned 07/16.100% 100% 100%400/220 100% 630

5 Almora 200 JUN-17 DPR Prepared.sending DPR to fundingagency is under process.

0% 0% 0%220/132 0% 0

6 Baramwari (GIS) 100 MAR-17 Revised Drawings has been submitted byM/s Siemens and has been approved.Totalprogress 4%.

0% 0% 0%220/132 0% 0

7 Ghansali (GIS) 60 AUG-17 contract terminated with M/SCGL,retendering is in progress

100% 0% 0%220/132 0% 0

8 Harrawala (GIS) 100 MAR-17 contract done with M/s Kanohar Electricalslim work is in progress

0% 0% 0%220/33 0% 0

9 Imlikhera (2x50) 100 MAR-17 Tendering is under progress0% 0% 0%220/33 0% 0

10 Jaffarpur S/S 100 JUN-16 Tendering completed. LoA is issued to M/sVariegate project pvt. limited.Land transferis under progress,land tranfer approval isgranted

0% 0% 0%220/33 0% 0

11 Mori (GIS) 100 MAR-18 Construction of Substation as perConnectivity schedule of generators inYamuna Valley.

0% 0% 0%220/33 0% 0

Sub-Stations: Page 53 of 72

Page 54: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

12 Nogaon 100 MAR-18 Construction of Substation as perConnectivity schedule of generators inYamuna Valley.

0% 0% 0%220/33 0% 0

13 Pantnagar (Aug.) 100 MAR-17 Tendering is under progress0% 0% 0%220/132 0% 0

14 Piran Kaliyar (GIS) 100 MAR-17 contract done with M/S Safety and controldevices.

0% 0% 0%220/132 0% 0

15 Puhana (GIS) 100 MAR-17 Differed till further order.0% 0% 0%220/33 0% 0

Sub-Stations: Page 54 of 72

Page 55: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

RAJASTHAN VIDYUT PRASARAN NIGAM LIMITED (RVPNL)

1 Akal (Aug.) 500 0% 0% 0%400/220 0% 0

2 Babai S/S 630 NOV-16 Fire wall work 100% completed & balancework and transformer filtration work underprocess.

100% 95% 80%400/220 78.33% 0

3 Bhadia Pooling Station 945 100% 65% 65%400/220 60% 0

4 Bhadla S/S 1500 MAR-17 400kV works under progress. 220kV sideyard is ready and charged.

100% 0% 0%400/220 0% 0

5 Chittorgarh (ICT-II) S/S 315 SEP-16 GSS work is almost complete andcommissioning is subject to completion of400 KV transmission line(Bhilwara-Chittorgrah) which is being constructedunder supervision of the SE(T&CBhilwara/Ajmer.

100% 100% 0%400/220 0% 630

6 Deedwana S/S 630 PPP0% 95% 100%400/220 99.83% 0

7 Jaisalmer -2 S/S 2x500 0% 0% 0%400/220 0% 0

8 Jodhpur (New) S/S 2x315 0% 0% 0%400/220 0% 0

9 Ramgarh S/S 1500 MAR-17 1.Revised NOA placed on dt.2.2.15. Date ofcommencement of work is yet to be decided.2. In ADB Projects the date ofcommencement is decided from date ofrelease of advance payment release.Payment of 10% advancement towardsservice part is yet to be released as the firmhas not claimed the same.

100% 100% 85%400/220 53% 0

10 Amberi S/S 100 JAN-17 Major earth cutting is involved at site of GSSis in hilly area.Electrical work will be startedafter executing of levelling &

100% 34% 30%220/132 null% 0

Sub-Stations: Page 55 of 72

Page 56: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

earth work by Civil wing.

11 Bajju S/S 160 Under KFW0% 0% 0%220/132 0% 0

12 Bamantukda S/S 100 0% 0% 0%220/132 0% 0

13 Bansur S/S 100 APR-16 Commissioned 04/16.100% 100% 100%220/132 100% 160

14 Bhadia Pooling Station 3x160 commissioned0% 0% 0%220/132 0% 0

15 Bherunda S/S 160 Equipment foundation 134/141, 1/2 Trans.foundation work completed.

null% 90% 80%220/132 43.33% 0

16 Bherunda S/S 160 MAR-17 Equipment foundation 135/1410% 90% 80%220/132/33

45% 0

17 Chatrail S/S 160 AUG-17 Under KFW100% 0% 0%220/132 0% 0

18 Goner S/s 100 SEP-15 AUG-16100% 85% 90%220/132/33

50% 0

19 Jhalmand S/S 100 MAR-17 NIT yet to be issued. Likely to be completedin 2016-17.

0% 0% 0%220/132 0% 0

20 Kanasar S/S 160 JUN-16 Commissioned 06/16.100% 100% 100%220/132 100% 160

21 Kolayat S/S 160 under KFW100% 0% 0%220/132 0% 0

22 Lakhesara S/S 160 Dropped0% 0% 0%220/132 0% 0

23 Mandelgarh S/S 100 SEP-16 100% B/W & 100% C/R work,Cable tranch95% work completed. Gantry work pending .

100% 96% 92%220/132 72% 0

24 NPH Jodhpur S/S 320 MAR-170% 100% 100%220/132/33

20% 0

25 Nawalgarh S/S 0 0% 0% 0%220/132 0% 0

26 Pokaran S/S 160 Upgrade to 400 KV GSS.100% 0% 0%220/132 0% 0

Sub-Stations: Page 56 of 72

Page 57: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

27 Pratapgarh (Upgradation) 100 AUG-16 GSS shall be completed upto Aug. 16 .Commissioning is subject to allotment ofpower transformer. 220 KV Pratapgarh-Chittorgarh(400 KV GSS) lie work is beingmonitered by the SE(T&C) Udaipur

100% 95% 90%220/132 80% 0

28 Ramgarh S/S 3x160 MAR-170% 0% 0%220/132 0% 0

29 Undoo S/S 320 Under KFW0% 0% 0%220/132 0% 0

30 mandelgarh S/S 100 JUN-16 100% B/W & 100% C/R work cable through95% completed.

100% 96% 85%220/132 61.16% 0

Sub-Stations: Page 57 of 72

Page 58: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

TAMILNADU TRANSMISSION CORPORATION LTD. (TANTRANSCO)

1 Ariyalur S/S 2x1500 MAR-19 Tender floated with due date of opening on16.09.16

100% 0% 0%765/400 0% 0

2 North Chennai Pooling Station(GIS)

3x1500 APR-19 Specification is under approval for floatingtender

0% 0% 0%765/400 0% 0

3 Anaikadavu S/S 1030 DEC-14 OCT-16 Control room finishing work under progress.Yard: Tower foundation and equipmentfoundation completed. Transformer erectionunder progress.

100% 90% 90%400/230-110

90% 0

4 Dharmapuri (Palavady) 1030 NOV-15 SEP-16 Control room and structure erction works areunder progress. Plinth work 100%completed. 1x200 MVA and 1x315 MVA ICTerection works are completed. 2nd 200 MVAreceived at site.

100% 90% 95%400/230-110

95% 0

5 Kamudhi S/S 2x315+2x100

JUL-16 SEP-16 Testing is under progress100% 100% 100%400/230-110

100% 0

6 Kanarapatty S/S 2x500+4x200

JUN-15 DEC-16 Control room, Plinth and structure erectionworks are completed. Equipment erectionand cable duct works are completed.2x200MVA and 1x500 MVA ICT erections worksare completed and oil circulation work to betaken up

100% 100% 75%400/230-110

75% 0

7 Karamadai S/S 945 AUG-16 Commissioned 08/16. (3x315)100% 100% 0%400/230 100% 945

8 Manali (GIS) 2x315+1x200

SEP-16 MAR-17 Work are under progress100% 60% 30%400/230-110

30% 0

9 Pavoorchatram (Tennampatty) 2x315+2x100

MAR-18 Work awarded on 25.01.16 and commencedon 25.03.16. Soil testing work completed.

100% 5% null%400/230-110

null% 0

Sub-Stations: Page 58 of 72

Page 59: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

10 Pulianthope (GIS) 3x315 MAR-18 BLTC Note is under approval for award ofwork.

100% 0% 0%400/220 0% 0

11 Rasipalayam S/S 1030 NOV-15 OCT-16 Control room :All worksCompleted.Electrification and finishingworks under progress. Earth mat 10%completed. Transformer erected and testingunder progress.

100% 90% 95%400/230 95% 0

12 Sholinganallur (Ottinmbakkam)S/S

2x315+1x100

DEC-16 All works are nearing completion. P&CTesting is under progress

100% 95% 95%400/230-110

95% 0

13 Thoppankundu S/S 600 DEC-14 OCT-16 Control room - First floor roof slab levelcompleted. Equipment foundation in 400 KVside completed and 110 KV side 90%completed. Cable duct 70% completed.

100% 80% 65%400/110 65% 0

14 Vellalaviduthi (Pudukkottai) 2x315+2x100

APR-18 Electrical and Civil estimates are underscrutiny

0% 0% 0%400/230-110

0% 0

15 Ambattur (3dr Main Road) (JICA) 200 MAR-15 DEC-16 Work under progress. Control room work95% completed. Plinth work 90% completed.Cable duct work completed. 1x100 MVATransformer erected.

100% 90% 95%230/110 95% 0

16 Central CMRL (GIS) (JICA) 2x100 AUG-15 SEP-16 Substation work completed and will beenergised on completion of 230 kV Cablework.

100% 100% 100%230/110 100% 0

17 Devigarh (Aug.) (2nd Addl.) 160 Not related to TANTRANSCO0% 0% 0%220/66 0% 0

18 Echur (Purisai) (JICA) S/S 200 SEP-15 AUG-16 Commissioned 08/16 (2x100).100% 100% 100%230/110 100% 200

19 Gurubarapally S/S (2nd Auto Tr.) 100 MAY-16 Commissioned 05/16.100% 100% 100%220/110 100% 100

20 Jambunathapuram 2x100 APR-16 DEC-16 Work under progress. Plinth and structureerection completed. Transformer 75%completed.

100% 95% 85%230/110 85% 0

Sub-Stations: Page 59 of 72

Page 60: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

21 KIDS Park (3r Auto Trf.) 100 APR-16 Commissioned 04/16.100% 100% 100%220/110 100% 100

22 Kadalangudy (Aug.) (100-80) 20 DEC-15 Commissioned 12/15.100% 100% 100%220/110 100% 20

23 Kanchipuram S/S 2x100+1x16

APR-14 MAR-17 Control room Ist floor roofingcompleted.Other yard works are underprogress. Electrical works are to beawarded.

100% 20% 5%230/110 5% 0

24 Kinnimangalam (JICA) S/S 2x100 AUG-15 MAY-16 All works are completed. Substation will becommissioned on completion of line works.

100% 100% 100%220/110 100% 0

25 Kumbakonam (JICA) S/S 2x100 AUG-15 MAR-17 All works are completed. Substation will becommissioned on completion of line works.

100% 100% 100%230/110 100% 0

26 Kurukathi S/S 100 DEC-16 Control room work completed. Plinth andStructure erection work are completed.Equipment erection is under progress. Earthmat work completed.

100% 95% 95%220/110 95% 0

27 Mambalam (GIS) 320 JUL-17 JUL-16 Work awarded on 02.01.2016 andDismantling works are completed. CMDAapproval awaited. Test piles works areunder progress.

0% 0% 0%230/110 0% 0

28 Membalam (GIS) 2x160 MAR-18 Work awarded on 02.01.16 and Dismantlingworks are completed. CMDA approvalawaited.Test piles works are underprogress.

0% 0% 0%230/110 0% 0

29 Mondipatti (TNPL Premises) 200 APR-16 MAR-18 Control room work 90% completed and SSEworks are being awarded.

100% 90% 0%230/110 0% 0

30 Mosur S/S (4th Addl. Auto tr) 100 AUG-16 Commissioned 08/16.100% 100% 0%220/110 100% 100

31 Narimanam S/S 2x100 JUN-19 Specification is under approval for floatingtender

100% 0% 0%230/110 0% 0

32 Neyveli S/S 480 APR-17 JUN-19 Tender floated with due date of opening on15.09.16

100% 0% 0%230/110 0% 0

Sub-Stations: Page 60 of 72

Page 61: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

33 Poiyur (JICA)S/S 100 AUG-15 DEC-16 All works are completed. Sub station will becommissioned on completion of line works.

100% 100% 100%230/110 100% null

34 Porur UG (GIS) 300 APR-16 MAR-18 LOA to be perused.100% 0% 0%230/110 0% 0

35 RA Puram (GIS) UG (JICA) 200 JUL-15 MAR-17 Case cleared and work commenced.Transformer plinth work completed. GISbuilding roof slab shuttering work andreinforcement work under progress.

0% 25% 20%220/33/11

20% 0

36 Samayanallur S/S 2x100 JUN-19 Estimate is under scrutiny for specificationapproval.

100% 0% 0%230/110 0% 0

37 Sankarapuram S/S 200 APR-18 Estimate is under scrutiny for specificationapproval.

0% 0% 0%230/110 0% 0

38 Savasapuram S/S 2x100 APR-14 MAR-17 Control room and SSE works are awardedand commenced. Structure erection andequipment erection works are underprogress. Transformer Plinth completed.

100% 20% 45%230/110 45% 0

39 Shenpagapudur (JICA) 2x100 JUN-15 MAR-17 Control room concreting and concreting forequipment foundation is under progress.Plinth 70% completed.

100% 15% 15%230/110 15% 0

40 Singapuram S/S (ICT-I) 100 SEP-13 MAY-16 Commissioned 05/16.100% 100% 100%220/110 100% 100

41 Singapuram S/S (ICT-II) 100 Test charged on 02.05.16 with 1x100 MVAAuto Transformer

0% 0% 0%220/110 0% 0

42 TNEB HQ (GIS) (JICA) S/S 200 APR-12 DEC-17 Tender floated with due on 28.09.16100% 0% 0%230/110 0% 0

43 Thirupattur S/S 200 APR-18 Estimate is under scrutiny for specificationapproval.

0% 0% 0%230/110 0% 0

44 Thuvakudy S/S 200 APR-17 JUN-19 Specification is under approval for floatingtender

100% 0% 0%230/110 0% 0

45 Tiruchuli (NearMuthuramalingapuram)

500 SEP-16 Works are nearing completion100% 100% 95%230/110 95% 0

46 Tirupur (JICA) 2x100 APR-16 MAR-17 control room and Transformer plinth worksare under progress.

100% 20% 10%230/110 10% 0

Sub-Stations: Page 61 of 72

Page 62: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

47 Uddanapally S/S 200 APR-16 MAR-18 Site handed over on 24.08.15 Estimate isunder preparation

100% 0% 0%230/110 0% 0

48 Valayapatty S/S 200 APR-15 MAR-17 Work under progress. 1 no.80 MVATransformer erected and Oil circulation isunder progress.

100% 100% 85%230/110 85% 0

49 Vannikonendal S/S 300 MAR-15 The substation may be deleted from fromthe list since the administrative approval forthe same has been cancelled.

0% 0% 0%230/110 0% 0

Sub-Stations: Page 62 of 72

Page 63: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

TRIPURA STATE ELECTRICITY CORPORATION LIMITED (TSECL)

1 Ambassa (Aug.) 25 AUG-13 Commissioned 08/2013.100% 100% 100%132/33 100% 25

2 Banduar (Aug.) 15 SEP-13 Commissioned 9/13.100% 100% 100%132/11 100% 15

3 Budhjungnagar (Aug.) 25 MAR-17 LOA issued100% 0% 0%132/33 0% 0

4 Dharmanagar (Aug.) 25 SEP-13 Commissioned 9/13.100% 100% 100%132/33 100% 25

5 Garod Tilla (Aug.) 10 MAR-17 Tender Evaluation in process.100% 0% 0%132/11 0% 0

Sub-Stations: Page 63 of 72

Page 64: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

TRANSMISSIPN CORPORATION OF TELANGANA (TSTRANSCO)

1 630 MVA, 440/220 kV NirmalS/S

630 JUN-17 Leveling works under progress.100% 2% 0%400/220 0% 0

2 Asupaka S/S 630 SEP-15 SEP-16 Control room works under progress ,balanceworks under progress

100% 100% 97%400/220 91% 0

3 Dindi S/S 0 MAR-17 Levelling under progress.Foundationscommenced.

100% 73% 38%400/220 0% 0

4 Julurupadu S/S 0 JUN-17 Foundations under progress.100% 29% 0%400/220 0% 0

5 Maheswaram S/S 0 JUN-17 Works are under progress.100% 30% 20%400/220 20% 1000

6 Narsapur (Medak Dist.) S/s 2x315 DEC-16 Works under progress100% 90% 90%400/220/132

75% 0

7 Nirmal S/S 0 JUN-17 levelling work under progress.100% 2% 0%400/220 0% 0

8 Shankarpally (Extn.) 630 Works completed.0% 100% 100%400 100% 0

9 Bonguloor S/S 200 1 no. 100MVA Transformer and linecommissioned on 02.04.2015. balanceworks to be completed by 31.10.2015

0% 0% 0%220/132/33

0% 0

10 Dichaplly (Aug.) 315 FEB-17 Works are in progress100% 90% 70%220/132 70% 0

11 Hayathnagar 2x50 JUL-16 All works completed except panel erection.100% 100% 100%220/33 100% 0

12 Huzumagar S/S 200 MAR-17100% 0% 0%220/132/33

0% 0

13 Imliban (GIS) 2x160 SEP-12 JUL-16 Control room and Module room works areunder progress.

100% 100% 100%220/132 100% 0

14 Jadcherla S/S 200 0% 0% 0%220/132 0% 0

15 Jangaon S/S 200 100% 0% 0%220/132 0% 0

16 Manikonda S/S 2x100 DEC-18 Works commenced.100% 5% 0%220/132 0% 0

17 Nagole (Uppal) S/S 200 JUL-16 All Sub station works completed. Sub100% 100% 100%220/13 0% 0

Sub-Stations: Page 64 of 72

Page 65: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

station along with connected line is expectedto be commissioned by Nov-2015

2/33

18 Parigi (ICT-I) S/S 100 APR-16 Commissioned 04/16.100% 100% 100%220/132 100% 100

19 Singotam X Road 2x20 JUL-16100% 100% 100%220/33 2% 0

20 Sircilla S/S 200 0% 0% 0%220/132 0% 0

21 Thimmajipet S/S 200 MAR-170% 0% 0%220/132 0% 0

22 Veltoor (Aug.) 315 FEB-17 Works under progress.100% 90% 70%220/132 70% 0

Sub-Stations: Page 65 of 72

Page 66: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

U.P. POWER TRANSMISSION CORPORATION LTD. (UPPTCL)

1 Agra (UP) S/S 3000 AUG-16 MAY-16 S/s at Sl. no. 1 & 3 are the same.100% 30% 0%765/400 0% 0

2 Fatehbad S/S 3000 AUG-16100% 75% 70%765/400 55% 0

3 Agra (South) S/S 600 AUG-16 SEP-16 WIP- 42%100% 50% 0%400/132 7% 0

4 Banda S/S 630 OCT-16 WIP- 44%100% 67% 80%400/220 38% 0

5 Mathura S/S 2x315 AUG-16 SEP-16 WIP-50%100% 71% 0%400/220 31% 0

6 Noida Sec-148 S/S 1000 FEB-17100% 0% 0%400/220/132

0% 0

7 Orai S/S 630 SEP-16 WIP- 75%100% 81% 93%400/220 91% 0

8 Azamgarh (Aug). (160-100) 60 APR-16 Commissioned 04/16. (Reported Late).100% 100% 100%220/132 100% 60

9 Baghpat S/S 100 MAY-16 Commissioned 05/16.100% 100% 100%220/132 100% 100

10 Bah S/S 200 SEP-16 WIP- 95%100% 94% 0%220/132 96% 0

11 Bahraich S/S 2x100 JUN-16 Commissioned 06/16.100% 100% 100%220/132 100% 200

12 Bansi S/S 2x100 AUG-16 Land handed over to UPRNNL Ltd vide thisoffice letter No-44 dated 10.01.13. Work inprogress 42%

100% 0% 0%220/132 0% 0

13 Barahua S/S 100 AUG-16 Commissioned 08/16.100% 100% 100%220/132 100% 100

14 Bhelupur 60 MAY-16 Commissioned 05/16.100% 100% 100%220/132 100% 60

15 Bhelupur -ICT -II (New). S/S 100 JUN-120% 0% 0%220/132 0% 0

16 Charla (2nd Trf.) 160 JUN-13 Already energized on 20.12.12.100% 100% 100%220/132 100% 200

Sub-Stations: Page 66 of 72

Page 67: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

17 Debai (ICT-II) S/S 100 DEC-150% 0% 0%220/132 0% 0

18 Kanpur Road 3x60 OCT-16 WIP- 10%100% 54% 0%220/33 3% 0

19 Madhuvan S/S 160 DEC-16 Land Available WIP 7%100% 2% 0%220/132 0% 0

20 Mahoba S/S 100 JUN-16 Commissioned 06/16.100% 100% 100%220/132 100% 100

21 Moradabad (Aug.) (160-100) 60 MAY-16 Commissioned 05/16.100% 100% 100%220/132 100% 60

22 Morti S/S 1x160 DEC-16 Work in progress 85%.100% 86% 90%220/132 75% 0

23 Nighasan S/S 200 MAR-16 Commissioned 03/16. (Reported Late.)100% 100% 100%220/132 100% 200

24 Noida Sec-148 1x160 100% 0% 0%220/132 0% 0

25 Pratap Vihar S/S 1x160 JUL-17 Land Available. WIP 7%100% 14% 0%220/132 0% 0

26 Sahibabad-II S/S 2x100 Land Under id.0% 0% 0%220/132 0% 0

27 Sikandra Rau S/S 160 JUN-16 Commissioned 06/16.100% 100% 100%220/132 100% 160

28 Siyana S/S 2x160 Earlier Land allotment being pending atU.P.Govt level since 23.08.14, an alternateland is Identified in village Rukhi.

0% 0% 0%220/132 0% 0

Sub-Stations: Page 67 of 72

Page 68: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

As on 31-AUG-2016

WEST BENGAL STATE ELECTRICITY TRANSMISSION CO. LIMITED (WBSETCL)

1 Gokarna S/S 630 NOV-15 JUL-16100% 98% 100%400/220 98% 630

2 New Chanditala S/S 630 JUN-16 AUG-16100% 69% 80%400/220 60% 710

3 New Purulia (N.PPSP) S/S 0 SEP-16 APR-17100% 45% 25%400 0% 0

4 Alipurduar S/S 320 NOV-16 MAR-17100% 45% 35%220/132 0% 320

5 Egra (ICT-II) S/S 160 JUL-16 Commissioned 07/16.100% 100% 100%220/132 100% 160

6 Egra S/S 160 JUN-16 MAY-16 Commissioned 05/16.100% 100% 100%220/132 100% 160

7 Sadaipur S/S 320 APR-16 MAR-17100% 55% 60%220/132 0% 320

8 Vidyasagar Park (ICT-I & II) 320 JUL-14 JUL-16 Commissioned 07/16.100% 100% 100%220/132 100% 320

Sub-Stations: Page 68 of 72

Page 69: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

ADANI POWER LTD. (APL)

1 Rajnandgaon Switching station 0 NOV-18 AUG-17100% 0% 0%765 0% 0

2 Morena 2x315 MAY-18 APR-17100% 0% 0%400/220 0% 0

Essel Infra Projects Ltd. (ESSEL)

1 Warangal S/S 2x1500 0% 0% 0%765/400 0% 0

2 Darbhanga (GIS) 1000 JUN-16 JUN-16 Prohibition of sand mining in Bihar from Feb2016 to 3rd Mar 2016.

100% 80% 80%400/220 40% null

3 Motihari (GIS) 400 AUG-16 AUG-16 1.Due to flooding at Motihari sub-stationland in Aug/Sep 2015, the construction workwas totally stopped during this period.2. Due to Geotechnical surprise at Sub-station land, ground improvement wasrequired to be done before start ofconstruction work for safety of foundations.Accordingly, ground improvement was doneand same has taken additional 04 -05months time.

100% 70% 40%400/132 20% null

NORTH KARANPURA TRANSMISSION CO. LTD. (NKTCL)

1 Gurgaon 2x500 NOV-13 DEC-160% 0% 0%400/220 0% 0

PATRAN TRANSMISSION COMPANY LIMITED (PATRANTCL)

1 Patran S/S (ICT I & II) 1000 MAY-16 JUN-16 Commissioned 06/16.100% 100% 100%400/220 100% 1000

South East UP Power Transmission Company Limited (SEUPPTCL)

Sub-Stations: Page 2 of 5

Page 70: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

1 Mainpuri S/S 2000 JUL-16 Sublease agreement between UPPTCL andSEUPPTCL is still pending.17% has already been tested.

100% 94% 99.7%765/400 80.5% 0

2 Aurai (Ckt-I) 630 JUN-16 Land is available, however some of the land( gram samaj - 2.2 Ha) needs to betransferred to UPPTCL/Energy departmentof UP by DM Bhadohi (Sant Ravi DasNagar) for which necessary communicationhas been provided to DM Bhadohi byUPPTCL and also by Special secretary (Revenue) for transferring it to UPPTCL andsame is under process.

77.4% 21% 23.5%400/220 0% null

3 Gonda S/S 630 JUN-16100% 96.5% 97%400/220 91.5% 0

4 Sultanpur Road (Ckt-I) 1000 JUN-16100% 11.5% 17%400/220 0% 0

5 Aurai (Ckt-II) 320 JUN-16 Land is available, however some of the land( gram samaj - 2.2 Ha) needs to betransferred to UPPTCL/Energy departmentof UP by DM Bhadohi (Sant Ravi DasNagar) for which necessary communicationhas been provided to DM Bhadohi byUPPTCL and also by Special secretary (Revenue) for transferring it to UPPTCL andsame is under process.

77.4% 21% 23.5%220/132 0% 0

6 Gonda (Ckt-II) 200 JUN-16100% 96.5% 97%220/132 91.5% 0

7 Sultanpur Road (Ckt-II) 320 JUN-16100% 11.5% 17%220/132 0% 0

Sub-Stations: Page 3 of 5

Page 71: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

STERLITE GRID LTD. (SGL)

1 Amargarh (GIS) S/S 630 AUG-14 OCT-17 Force majeure events due toBandh,Shutdown,Curfew,Bad Law & OrderSituation in J&K & suspension of work dueto Armed Conflict & Blockade from8.7.2016,Change in Law:a.AdditionalSwachh Bharat [email protected]% has beenadded in Ser. Tax wef 15.11.2015 as perMinistry of Finance b.Additional 0.5% KrishiCESS has been included in ser.tax wef.1.6.2016 c.Increase in J&K [email protected]% to14.5% dt. wef.1.7.2016; same intimated toLTTCs.

100% 17% 0%400/220 0% 0

2 Kadarpur 2x500 0% 0% 0%400/220 0% 0

3 Prithala 2x500 0% 0% 0%400/220 0% 0

4 Sohna Road 2x500 0% 0% 0%400/220 0% 0

Shekhawati Transmission Service Company Limited (SKHWTTSCL)

1 Nawalgarh 100 DEC-160% 0% 0%220/132 0% 0

TORRENT POWER LTD (TOR. POW. (UNOSUGEN))

1 Bharuch/Dahej 1500 .0% 0% 0%765/400 0% 0

TALCHER TRANSMISSION CO. LTD. (TTCL)

1 Behrampur. S/S 2x315 OCT-12 DEC-160% 0% 0%400/220 0% 0

WESTERN U.P. POWER TRANSMISSION CO. LTD. (WUPPTCL)

Sub-Stations: Page 4 of 5

Page 72: UTILITY WISE REPORT INDICATING STATUS OF … WISE REPORT INDICATING STATUS OF CONSTRUCTION OF SUB-STATIONS (220 ... (kV/kV) 11. Original Commissioning Schdule Revised/ Anticipated

1. 2. 5. 6.4. 7. 8.3.

LandAcquisition

Civil workscompleted

Structure,transformer,su

bstationeqpt.

received

9.

Structure,transformer,su

bstationeqpt. erected

10.

CapacityTested/

Commissioned

(MVA)

Cummulative progress till date

SlNo

Name of

Sub-Stations

Date ofAward

Capacity(No.xMVA)

VoltageRatio

(kV/kV)

11.

Original

Commissioning Schdule

Revised/Anticipated

12. 13.

Remark

1 Greater Noida AIS (ICT-1) 1500 100% 99% 98%765/400 98% 0

2 Greater Noida AIS (ICT-2) 1500 APR-16 Commissioned 04/16.100% 100% 100%765/400 100% 1500

3 Hapur AIS 2x1500 MAY-16100% 94% 88%765/400 85% 0

4 Ataur GIS 2x500 MAY-16100% 88% 75%400/220 45% 0

5 Dasna GIS 2x315 AUG-16100% 70% 50%400/220 5% 0

6 Greater Noida AIS 2x315 MAY-16100% 98% 98%400/220 98% 0

7 Hapur AIS 2x500 JUN-16100% 93% 88%400/220 82% 0

8 Indirapuram GIS 2x500 JUN-16100% 96% 92%400/220 55% 0

9 Nehtaur (Bijnor) AIS 2x200 AUG-16100% 90% 88%400/132 77% null

10 Sikandrabad AIS (ICT-1) 500 JUN-16 Commissioned 06/16.100% 100% 100%400/220 100% 500

11 Sikandrabad AIS (ICT-2) 500 APR-16 Commissioned 04/16.100% 100% 100%400/220 100% 500

12 Ataur GIS 3x60 JUN-16100% 55% 35%220/33 0% 0

13 Dasna GIS 2x100 AUG-16100% 20% 8%220/132 0% 0

14 Indirapuram GIS 3x60 MAY-16100% 78% 60%220/33 15% 0

Sub-Stations: Page 5 of 5