Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
UWE Estates and Facilities Design Guide
Issue 1.3
UWE Design Guide for Buildings
i
Table of Contents
Chapter 1: Introduction
Chapter 2: Design governance
Chapter 3: UWE Strategies
Chapter 4: Space planning
Chapter 5: Fabric and structural design
Chapter 6: Mechanical engineering design
Chapter 7: Electrical engineering design
Chapter 8: IT Infrastructure
Chapter 9: Landscaping, biodiversity and infrastructure
Chapter 10: Audio Visual (AV) Infrastructure
Appendices
Management of Appendices
Throughout the design guide, there are references to a range of external documents (such as
British Standards and BSRIA guidance) and UWE documents (such as UWE drawings standards or
strategy documents).
Designers are expected to have their own access to third party documents. Where these are freely
available, hyperlinks have been embedded in the design guide.
Internal, UWE documents will predominantly be made available through hyperlinks embedded in the
design guide.
The intention of using hyperlinks is to avoid the need for continually updating and issuing a suite of
generic appendices.
Where specific documents have been written to support this design guide, they will be provided as
a discrete appendix.
UWE Design Guide for Buildings
ii
Change Control
Please note that this change control log must be used for changes to any part of the design guide: The individual parts do not have their own change control records.
Version
Number1
Date of
Issue 2 Author(s) 3 Brief Description of Change(s) 4
1.0 30/05/17 N Bell, N Cooper,
S Brennan Complete rewrite of existing Design Guide.
1.1 03/10/17 N Bell
Minor alterations to security standards requested by
A. Hennessy. Minor alterations to gender neutral
and wellbeing spaces: Wording was unclear.
Incorporated minor change to IT standard (re: no
suspended ceiling in comms room). Approval by
Masterplan Executive.
1.2 06/11/17 N Bell
Following meeting with E&D, added clarification
about wellbeing rooms at 3.6.1 and about half-
height walls in engineering/robotic areas (in 5.8.2).
Clarification added to the need for glazing to protect
modesty (at 5.7.4). The option for laboratory/
workshop furniture to have an adjustable height and
to be available at different locations (at 1.2.3). The
need for at least one gender neutral toilet to be self-
contained in a row of cubicles (at 3.3.2.1).
1.3
11/12/17 N Bell Incorporation of AV design as Chapter 10. Approval
by the Campus 2020 board on 06/12/17. ‘Draft’
removed.
1 Add in a version number of the document. This will help you track your changes. Your first draft version of the Report
would be Version 1.0. Any minor changes after your first draft could be labelled 1.1., 1.2 and so on. When a significant
number of changes are being made or when your Report has reached a milestone (for example, it is ready for internal
review), you could then change your Version to 2.0 or 3.0. Remember to change the footer at the same time.
2 Indicate the date you are working on the Report. This, along with your version number, will help you keep track of the
most up-to-date version.
3 More than one person will contribute to the report and it is important to indicate who worked on the Report, on what
date and in what specific areas. If you have questions later, you can then easily refer back to the specific author.
4 Identify what section was changed and provide a brief description of why the changes took place.
UWE Estates and Facilities Design Guide
Chapter 1: Introduction
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 1
Table of Contents
1.1 Introducing the design guide ........................................................................................ 2
1.2 Designing an Experience .............................................................................................. 2
1.2.1 New Pedagogical Approaches ................................................................................ 2
1.2.2 Catering for different aesthetics ............................................................................. 5
1.2.3 Laboratory/workshop design .................................................................................. 6
1.2.4 Student Accommodation ........................................................................................ 6
1.3 Introduction to UWE .................................................................................................... 7
1.4 Introduction to the Design Guide .................................................................................. 8
1.4.1 What is design? .................................................................................................... 8
1.4.2 Scope of the Design Guide..................................................................................... 8
1.4.3 When does the Design Guide apply? ....................................................................... 8
1.4.4 Design Guide Ownership & Updating ...................................................................... 8
1.4.5 Structure of the Design Guide ................................................................................ 9
1.4.6 Designer Responsibilities ....................................................................................... 9
1.5 Strategy 2020 ........................................................................................................... 10
1.5.1 Core Values ........................................................................................................ 10
1.5.2 Priorities ............................................................................................................ 10
1.5.3 Key enablers ...................................................................................................... 11
1.6 General Design Principles ........................................................................................... 12
1.6.1 Considering ‘adjacencies’ ..................................................................................... 14
1.6.2 Physical, mental and spiritual wellbeing ................................................................ 14
1.7 Masterplan ................................................................................................................ 15
Selected Glossary ................................................................................................................ 16
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 2
1.1 Introducing the design guide
The design guide explains the overarching principles, functional requirements and technical
standards for our buildings and infrastructure which ultimately allow UWE to deliver it’s core
function: To educate and prepare students for life after their course. This chapter explains:
What the design guide is and when it is to be used
UWE’s overarching strategy, Strategy 2020, and how it influences design principles
First of all, it is important to establish what good educational design might look like and how it can
be achieved. It would be completely erroneous to assume a building that complies with building
regulations or British Standards will achieve this aim.
1.2 Designing an Experience
By altering our built environment we are ‘designing an experience’ for our students and staff.
The Higher Education sector has radically changed since these design guides were first issued in
2011. It is increasingly important that we offer attractive, inclusive, sustainable and functional
learning, teaching, social and living environments, or environments that blend these roles. Our
built environment must be flexible enough to cope with changing demands and teaching methods.
It is only through consultation that we will determine how the built environment will effectively
support and impact on the student experience, remembering that no two faculties are the same.
Chapter 2 of this design guide explains the different stakeholders at UWE.
1.2.1 New Pedagogical Approaches
The traditional model of education involved a tutor disseminating information to a fairly passive
group of students in a classroom setting. Students might complete work outside of the classroom.
As technology developed, these outside activities moved to a digital format (‘blended learning’).
There are now very different approaches to education with an increasing move towards active and
collaborative learning experiences. In a ‘flipped classroom’ approach, group work, discussions and
individual/self-directed learning occur within the premises, facilitated by the tutor, and traditional
teaching may occur at home with students watching online presentations. Lecture capture is
therefore now a standard UWE requirement in teaching rooms. This technology also gives some
disabled students or students with caring responsibilities etc. new options for accessing lectures.
Clearly, laboratory or workshop-based classes will have very specific requirements.
On average each student has 3 electronic devices and uses them as an integral part of their
learning experience (e.g. videoing lectures to review at their own pace or making notes on tablets).
This leads to vastly different power requirements than when the University was first built (and
challenges for bringing power to desks etc. within large floor areas).
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 3
The faculty is best placed to explain their pedagogical approach, how this needs to drive design and
their expectations of how this may change in coming years.
Seating areas in corridors allows students to
engage in directed discussions or participate in
informal mentoring. These facilities also offer
opportunities for people to rest as needed.
A collaborative work station, creating a pod connected
to but separate from adjoining corridors. It overcomes
the institutional (and potentially disorienting and
intimidating) appearance of long, featureless corridors.
A collaborative workstation, within a learning zone. It facilitates discussion. Cabling enables shared use of a
monitor. High backed sofas create a ‘booth’ while the lightweight chairs can be moved to enable a
wheelchair user to make use of the space (although it would have been preferable if one of these chairs had
arm rests to help people sit/stand). Technology is embedded into these workstations, with USB charging
points, video capture for skype calls etc. This enhances the flexibility of these spaces (taking away a need
for video conferencing suites) and mirrors how many students use technology in their day-to-day life.
Traditional teaching methods are still needed. While tiered seating is sometimes used, new styles
of layout are emerging (e.g. ‘Harvard style’). They all present practical challenges. For example,
access to fixtures or equipment, such as projectors, above tiered seating needs careful thought.
These rooms often have fixed seating and some rows may be inaccessible to someone with mobility
impairments. An entire row or section of moveable furniture at the front and back of the room (as
long as they are accessible) gives people choice about where to sit, so will not be stigmatized by
sitting in a ‘disabled area’, and offers space for assistive equipment and support.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 4
A social/café space immediately outside traditional classrooms becomes a ‘break out’ areas for students. This creates a vibrant, multi-use space.
Multi-functional spaces can (obviously) be used for many
purposes and will be utilised much more effectively than
single-use spaces. UWE is then not left heating, cooling
and cleaning empty spaces.
Social spaces can become self-directed or collaborative
learning zones with appropriate choice of furniture and
provision of power (as demonstrated to the right).
A flexible learning space is often presented as a large
space with wheeled/reconfigurable tables and chairs
enabling a room to be set up in a variety of patterns1.
Other, more progressive ideas include:
Wheeled bookshelves/cabinets enabling the layout of
a large space to be reconfigured.
Use of acoustic blankets as room dividers.
Worktables with pull down power enabling them to be used in different locations and for
different purposes (down for laptop/tool use, up for discussions and model-making etc.).
Provide sufficient space at PC terminals to enable students to work with ‘study-buddies’. This
could benefit disabled students who are supported by assistants.
It should also be noted that flexible spaces are also a key component of our business continuity
strategy: We can quickly reconfigure areas to accommodate different functions in the aftermath of
an incident. Large spaces are also generally more accessible, presenting fewer doors to navigate.
The provision of building services (and IT infrastructure for AV equipment and video capture
technology etc.) needs careful consideration if large areas can be reconfigured to prevent creating
zones which are overheated/cooled and adjacent areas are inadequately serviced.
1 Furniture selection will influence how accessible a facility is. UWE expects designs to incorporate tables at
varying heights, with good space beneath to accommodate wheelchairs. Seats with arms will assist someone to stand if they need additional support. Lightweight furniture, with hand holds, can be easily moved.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 5
Example from Northumbria University, showing collaborative learning spaces and learning ‘pods’. While
many students will enjoy the blend of social and learning spaces offered by a collaborative spaces, this will
not suit every student, assignment or subject matter and mixed provision is needed. Individuals with
cognitive or hearing impairments could struggle to hear or process information in loud, busy, open spaces.
There may also be scope for individuals to control the climate within pods, suiting their individual needs.
To reiterate, it is beyond the scope of the design guide to predict the exact requirements of
faculties or to predict changes in pedagogical approaches and technology. It is only through
effective consultation that a design team will appreciate what is needed.
1.2.2 Catering for different aesthetics
To meet the expectations of our students, it is important that UWE is ‘de-institutionalised’. This is
reflected in our branding but must be conveyed by our built environment.
Each faculty will also have it’s own aesthetics, depending on the subjects it teaches and the
demographics and expectations of students. Some strive for a corporate look, others aspire to be
relaxed or artistic, while others may want or need a clinical, scientific or industrial appearance.
While this design guide encourages standardisation (to help achieve best value), designers must
accept that each project will need to be judged on its own merits.
Regardless of these variations, any teaching walls (i.e. walls on which images are projected) must
be painted 00NN 16/000 – Grey. This accentuates the screen and benefits students with certain
cognitive or visual impairments who might struggle if faced with a large, white wall.
Room booking systems, connected to tablets,
enables the University to utilise space much
more effectively and hands control over to the
students. Students are able to quickly check
whether/when rooms are available and can
book the space. This creates a more flexible,
agile and empowering learning experience.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 6
1.2.3 Laboratory/workshop design
Laboratories and workshops have requirements above and beyond traditional teaching spaces. In
some cases, this includes a need for safety features such as door interlocks and high levels of
containment to prevent inadvertent release of substances. UWE requirements are detailed in:
UWE Health and Safety Standards, available here (click ‘here’)
General, discipline-specific requirements are contained in later chapters of this design guide
Some equipment or processes have specific operational requirements (e.g. in relation to humidity,
temperature or dust control) which cannot be described here or in health and safety standards.
Achieving these standards requires a co-ordinated response from the entire design team. At RIBA
stage 1 (i.e. while discussing and developing the client brief), the UWE Project Manager will identify
specialist spaces within their project scope. Project management processes ensure that:
Appropriate stakeholders are consulted. Health and Safety standards name some of the
roles that should be involved in design and planning of work in laboratories and workshops
Capable, specialist designers are appointed
Appropriate Estates staff provide Technical Assurance (as discussed in Chapter 2)
A plan is put in place to ensure packages of design are co-ordinated
Principles of accessibility and inclusivity must be embedded in design e.g. providing some work
tables of different/adjustable heights and a mixture of seating, offering some with arm and back
rests. Offering these in different locations in a room prevents creating a ‘disabled area’.
1.2.4 Student Accommodation
Many students opt to live on campus and accommodation has a significant impact on student
experience. UWE has delivered various projects to construct blocks of student accommodation. A
typical model consists of a number of en-suite flats with shared kitchen facilities, although some
studio flats are available. As part of its commitment to inclusivity, UWE offers a range of options to
make on-site living an affordable proposition to students from different backgrounds.
There are no standard templates for accommodation. Student expectations change and it is
essential that design teams consult with accommodation services and review existing provision (in
and outside UWE) as they develop designs. It is crucial not to have pre-conceived notions.
Fire safety is, of course, a critical consideration. On top of the generic requirements for fire safety
in flats, UWE requires that hobs are only induction hobs.
Elsewhere, this design guide discusses the requirements for ensuring that appropriate numbers of
student flats are accessible and can be readily retrofitted with assistive devices. Regardless of
whether the flats are designed to be accessible it is important that communal areas are accessible
as students may receive disabled visitors (or there may be disabled reception staff etc.).
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 7
1.3 Introduction to UWE
The University of the West of England (UWE) is a modern, growing University. It is one of Britain's
most popular universities with around 30,000 students and 3,000 staff and is the largest provider of
Higher Education in the South West of England. Students come to UWE from all parts of the UK, as
well as a significant number of international students. UWE consists of 4 main campuses:
Frenchay: UWE Bristol’s main campus, lies 4 miles north of Bristol city centre
City Campus: Home to the University’s creative and cultural subjects. It consists of
Bower Ashton, Arnolfini and other city centre properties including Spike Island and
Watershed.
Glenside campus: Home to UWE Bristol’s Faculty of Health and Applied Sciences
Gloucester: Based in Alexandra Warehouse, this is the Department of Nursing and
Midwifery's Gloucester campus.
Campus maps and information can be found here (please click ‘here’).
There are 4 Main Faculties, listed below, supported by Facilities and other professional services:
Business and Law (FBL)
Arts, Creative Industries and Education (ACE)
Environment and Technology (FET)
Health and Applied Sciences (HAS)
Further details can be found here: http://www1.uwe.ac.uk/aboutus/departmentsandservices
UWE recently rose 13 places in The Times and Sunday Times Good University Guide 2017 and is
currently ranked fifth amongst the 12 universities in the south west (September 2016).
The University is committed to providing high quality, stimulating spaces that attract and retain
students, staff and investors and reflects the University’s vision. To do this, it requires a flexible
and sustainable estate that is fit for purpose; a University that can meet changing needs of higher
education and assist the University in retaining its competitive edge within the HE sector.
In a survey of students carried out in July 2015 (source: www.aude.ac.uk) it was found that:
67% stated facilities were key in choosing a University
71% agreed the look of the University was important
As well as investing in building stock, the University is building its visual identity with new branding,
wayfinding and a presence project.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 8
1.4 Introduction to the Design Guide
1.4.1 What is design?
This design guide applies to all design relating to a structure (buildings, roads, landscaping etc. or
services fixed to or within them). It is useful to understand what we mean by design. UWE will
use the definition from the guidance to the Construction (Design and Management) Regulations:
The term ‘design’ includes drawings, design details, specifications, bills of quantity
and calculations prepared for the purpose of a design.
‘Design’ is very broad and applies to designers include architects, engineers and surveyors.
1.4.2 Scope of the Design Guide
This design guide has been developed to ensure that any future construction project for UWE,
whether new build or refurbishment, is designed utilising the same parameters and principles. It
will ensure that all new University property and refurbishments of older University properties are
developed to a consistently high standard. This design guide is relevant to any designer working
on the UWE built environment, including contractors with design responsibilities.
This design guide is supported by a range of appendices which will be referred to throughout.
1.4.3 When does the Design Guide apply?
Again, UWE will be guided by the Health and Safety Executive’s guidance to CDM.
The designer’s duties apply as soon as designs…are started. This includes concept
design, competitions, bids for grants, modification of existing designs and relevant
work carried out as part of feasibility studies. It does not matter whether planning
permission or funds have been secured.
In other words, the design guide should be applied from the very earliest phases of every
construction project, no matter how big or small it might be. The design guide applies to the
whole design process, including changes made during RIBA Stage 5 (the Construction Phase).
1.4.4 Design Guide Ownership & Updating
UWE Estates and Facilities will review and update this design guide on an annual basis to consider
changes in statute, industry best practice, University policy etc. In practice, this will happen
following the busy summer works period, to capture lessons learned. UWE will undertake ad hoc
reviews and amendments in light of significant changes between formal reviews.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 9
1.4.5 Structure of the Design Guide
The Design Guide is divided into 9 Chapters, each dealing with a separate aspect of design.
1 Introduction (this current document)
2 Design governance
UWE’s expectations of how the design process will be managed, including drawing standards,
UWE’s approach to BIM, technical assurance, management of derogations etc.
3 General design
Core UWE strategies relating to equality and diversity, sustainability etc. and their impact on design.
4 Space planning design
An overview of space requirements for different functional areas within the University.
5 Fabric and structural design
Detailed requirements relating to the structure and fabric of buildings. There is also a section on
catering design.
6 Mechanical engineering design
Detailed requirements informing the selection and design of mechanical plant and installations.
7 Electrical engineering design
Detailed requirements informing the selection and design of electrical systems.
8 IT Infrastructure
Cabling design and requirements
9 Landscaping, biodiversity and infrastructure
This covers the external areas, including landscaping, roads, parking and other aspects civil
engineering, planting schemes etc.
1.4.6 Designer Responsibilities
This Design Guide is based on past UWE experiences and the University’s future goals and
ambitions. It does not absolve external design consultants of their legal or contractual
responsibilities under health and safety legislation, statutory requirements or design/professional
duties and liabilities.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 10
1.5 Strategy 2020
Strategy 2020 maps out the journey UWE is taking as a University until 2020 to ensure our
graduates are well positioned for the future.
The outstanding learning experience we provide at UWE Bristol supports the development of
innovative, creative and courageous graduates who are passionate about their subjects and curious
to learn more. But equipping our students to play their part in a changing, fast-moving global
economy requires that we keep developing, keep enhancing and keep investing in what we do.
This document is available on the UWE website and outlines the vision and mission in more detail.
See: http://www1.uwe.ac.uk/aboutus/visionandmission/strategy.aspx
1.5.1 Core Values
It is crucial that project teams understand the core values of the University. It is perhaps useful to
think of these values as UWE’s statement of identity: They are the qualities that are most
important to UWE. The values will underpin the strategic decisions of the University.
Ambitious. We’re not afraid to shape, challenge and tackle the big issues, to take the initiative
and pave the way. To set our sights high for ourselves and our students.
Innovative. We create new opportunities for the people who work and study with us. We
embrace different ideas and pioneer new and better ways of doing things.
Connected. We have strong connections, both close to home and around the world. Networks
and communities feed into and enhance everything we do as a University.
Enabling. We instil a thirst for new knowledge, its creation and application, and help people
and organisations to be the best they can be.
Inclusive. We invest in making UWE Bristol a supportive and inspiring place to learn and work
– somewhere where diversity of experience and perspective is encouraged, and learning and
research is accessible to as many people as possible
1.5.2 Priorities
UWE has four priorities which might be thought of as strategic objectives. They are how the
values will manifest themselves. The priorities are:
1 Outstanding learning
2 Ready and able graduates
3 Research with impact
4 Strategic partnerships, connections and networks
The most important priorities for the University are therefore the learning experience and outcomes
in terms of student employability and meaningful research.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 11
1.5.3 Key enablers
There are two key enablers which will support the achievement of UWE’s priorities, one of which is
highlighted below. This enabler leads naturally to the General Design principles which follow.
Key enabler 2 Place: Resources, estate and infrastructure
A strong and confident financial position, a robust approach to strategic management, and a
sustainable learning environment where our people can flourish.
We achieve this by:
taking a clear and transparent approach to strategic management that allows us to
prioritise, be accountable, take responsibility, and reward people for their contribution,
while encouraging the innovation and agility that is essential to achieving our ambition
operating in a sustainable way, and being respected and recognised for our management
standards across our strategic and financial planning, health and safety, equality and
diversity, and sustainability measures
creating a learning environment that is flexible, open and digitally connected, which
supports innovation and the shared generation of ideas and solutions across all our
campuses
encouraging sustainable and healthy behaviours that underpin all that we do.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 12
1.6 General Design Principles
To meet the ambitions of Strategy 2020, our designs must meet a range of objectives. The
following considerations should be at the forefront of the project teams mind from the earliest
stages of a project. Many of these objectives are supported by specific strategies, as detailed in
Chapters 2 and 3 of this design guide.
Projects will be audited and benchmarked by UWE to ensure the work commissioned by us will
meet our expected standards and achieves these objectives. All construction projects will be
subject to a post completion review, with new builds and major refurbishments incorporating HEFCE
Guide to Post Occupancy Evaluation principles. Given the stated priorities of the University,
functionality and quality are likely to be assessed primarily by evaluating the extent to which a
design enhances the learning, living and research experience of students.
Design
objective
Designers will be challenged to explain/demonstrate…
Learning
Experience
How does this design enhance the learning experience, the quality of research,
and the capability of students to progress after their studies?
How does the project/design fit the business plan or strategy for the department
or faculty?
Partnerships Have we involved the right stakeholders within UWE?
To what extent does this design (or the way the project is managed) promote
partnerships with businesses and communities?
How does the project impact on our community and business partners?
Inclusive To what extent does this design create an accessible and inclusive environment?
Does it meet the different religious and faith needs of staff and students?
What barriers will it present to people who want to access or use this space?
Flexibility
and future-
proofing
To what extent can the space be altered to account for changes in technology,
educational practices, market changes, government policy and the environment?
To what extent can plant/technical spaces be reconfigured to allow for changing
patterns of energy use, availability and cost?
Value for
money
How does the design support the University in achieving a “strong and confident
financial position”?
To what extent does the design represent good value for money?
In practice, this will be achieved through a number of measures:
1 Ensuring that projects align with faculty/UWE strategies which will help to
prevent later changes to the project scope.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 13
2 Do not confuse low cost with ‘value for money’ or expensive with good
quality. See the case study, below.
3 Achieving cost certainty and deliver projects within budget. This requires
effective governance and project management arrangements.
4 Rationalising stock or cleaning and maintenance regimes through greater
standardisation.
5 Paying close attention to the whole life cost of our assets. Our ambition is
to achieve an efficient and reliable estate, with high utilization and low
maintenance/downtime.
6 Designing for efficient maintenance and management of our Estate. This
includes providing sufficient access and information.
Student
recruitment
& retention
How does the design create an environment which encourages students to
select and remain at UWE? This helps us achieve a “strong and confident
financial position”.
Sustainable How has the design minimised our negative impacts and maximised the
sustainability benefits of the project?
Does the design promote positive wellbeing?
Healthy and
safe
What residual risks will the design leave for the people constructing, maintaining
and using the new structure?
Has the health and safety team been consulted regarding the fire strategy?
How will the design cope with the large number of person movements at core
times (at the start and end of the day, at the end of lectures?)
To what extent has the design accommodated the demands posed by the end-
users in a higher education establishment?
We recognise that there may be times when different design objectives may appear to be in
competition. The project team will need to openly discuss this as and when it arises, but always
using UWE’s values and priorities as touchstones to inform those conversations.
Case study: Cost vs Value for Money
A new building was constructed with a large area of new, external planting. An external tap was
removed from the design to reduce costs. Every time that plants need watering (which can be
several times a week) a bowser is brought across the campus and through student-occupied
areas.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 14
1.6.1 Considering ‘adjacencies’
Designers already appreciate that their designs are located within and must be designed for a
specific context. Specifically we encourage design/project teams to think holistically and consider:
1. The impact on infrastructure beyond your site boundaries. For example, the entire wayfinding
strategy for a site may need to be revised in light of a new building and should be an integral
part of the design rather than an afterthought. More generally, how will the project influence
the flow of people through the rest of the campus? Do not just consider the immediate users.
2. Whether the project is aligned with the masterplan strategy (as discussed below). Will there be
a clash in the future (either visually or in terms of access to/from a future construction site or in
relation to services/utilities)? Would we need to adapt or even demolish your brand new or
newly refurbished structure to accommodate a future project?
3. Changing the maintenance strategy so that vehicles, such as mobile elevated work platforms or
cranes, will be required to travel over or operate on unsuitable surfaces.
4. Dealing with historical damage/defects within or immediately outside project boundaries which
would impact on the finished building if they are not dealt with (e.g. repairing damaged
flagstones along the main route to the new building).
5. The impact of the project while it is being built. University life will need to continue and it is
crucial that designers play their part. To give some examples:
a. Consider how the design or location of site hoarding/protection could be used to reduce
or enhance the visual or operational impact of a project.
b. The use of pre-fabricated elements may reduce the duration of the construction phase
c. The project can be a learning opportunity for relevant courses.
1.6.2 Physical, mental and spiritual wellbeing
The 2013-2020 sustainability plan states “UWE Bristol aims to provide a positive and enjoyable
student, staff and visitor experience. It aims to enhance everyone’s health and wellbeing by
creating and promoting healthier working, learning and social environments.” Design teams are
encouraged to think broadly about wellbeing. For example, they could consider providing:
Facilities that promote healthier forms of travel (please refer to the UWE transport strategy in
Chapter 3 of this guide)
Communal and social spaces/experiences to create a sense of community
Access to spaces that allow private reflection and solitude. Multi-function wellbeing spaces can
help to meet this ambition and are discussed in Chapter 3 of this guide
Space for artwork that can promote discussion and reflection
Facilities that promote inclusion, and do not create barriers to access (Chapter 3 of this guide
discusses inclusive design)
Access to fitness and sports facilities (see the UWE sports vision in Chapter 3 of this guide)
Facilities to meet religious beliefs (please refer to the section on faith and spirituality in Chapter
3 of this guide)
It is only through consultation that you will be able to determine what facilities are needed in a
particular building/space (which will be influenced by the proximity of facilities in adjacent areas).
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 15
1.7 Masterplan
UWE Board of Governors agreed a Paper “Towards a Master Plan Implementation Strategy” in
November 2010 which sets out the background for the development of the University over the next
25 years.
Recent projects include a new Bristol Business School (completed in 2017), new student
accommodation, investment in our City Campus and Glenside Campus and the redevelopment of
Robotics space on Frenchay Campus. Other projects and investments have included a new
Students’ Union and the acquisition and refurbishment of Bush House (Arnolfini) in the centre of
Bristol.
As discussed above, under “adjacencies”, it is crucial that design teams understand the overall
ambitions and designs for the area surrounding their project and how their own designs and
specifications impact on and must align with the masterplan.
Case study: District Heating
A district heating scheme was envisaged as part of the Frenchay masterplan (to help support
UWE’s sustainability ambitions). Individual structures were identified for connection to the
Central Heating Plant. The project teams for those structures installed necessary pipework as
part of their own projects. When the Central Heating Plant is finally installed it can be connected
with limited disruption.
UWE Design Guide for Buildings
C h a p t e r 1 | I n t r o d u c t i o n I s s u e 1 . 3 P a g e | 16
Selected Glossary
B&CE: Building and Civil Engineering
BISRIA: Building Services Research and Information Association
BRE: Building Research Establishment
BREEAM: Building Research Establishment Environmental Assessment Method
BSI: British Standards Institute
CA: Contract Administrator
CDM: The Construction (Design and Management) Regulations 2015
CIBSE: Chartered Institution of Building Services Engineers
CETTS: (A University Department) Central Examination and Teaching Timetabling Services
E&D: Equality and Diversity
HEFCE: Higher Education Funding Council for England
SKA HE: The RICS environmental assessment tool to rate and compare environmental
performance of fit-out projects. Named after Skansen (an interior fit-out contractors which
initiated the project)
H&S: Health and Safety
HSE: The Health and Safety Executive
LCC: Life Cycle Cost
M&E: Mechanical and Engineering
O&M: Operations and Maintenance
RIBA: Royal Institute of British Architects
RICS: Royal Institute of Chartered Surveyors
UWE: University of the West of England
VE: Value Engineering
WLC: Whole Life Cost
UWE Estates and Facilities Design Guide
Chapter 2: Design Governance
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1
Table of Contents
2.1 Introduction to Design Governance ............................................................................... 2
2.2 Consulting to create a usable design ............................................................................. 2
2.3 Aesthetic and visual impact .......................................................................................... 3
2.4 Project Governance ..................................................................................................... 4
Project Management ............................................................................................. 4
Standards governing design work ........................................................................... 4
Construction (Design & Management) Regulations 2015 (CDM) ................................ 5
Management of occupied buildings including sequential handover ............................. 6
Departures from Standards and Specifications ......................................................... 6
Technical Assurance .............................................................................................. 7
Named, Specialist Contractors ................................................................................ 7
2.5 Designing for Facilities Management & Maintenance ....................................................... 8
Design features to improve access for plant/technical areas ..................................... 8
Lessons Learned ................................................................................................... 9
Facilities for cleaning ........................................................................................... 10
2.6 Designing for Business Continuity ............................................................................... 11
2.7 Designing for Climate Resilience ................................................................................. 12
2.8 Overview of Asset Management at UWE ...................................................................... 14
2.9 Cost-in-use ............................................................................................................... 14
Cost-in-use evaluations on major capital projects .................................................. 14
Evaluations on minor capital projects (under £2.5m exc. VAT) ................................ 16
Standards .......................................................................................................... 16
References ......................................................................................................... 16
2.10 Soft Landings ............................................................................................................ 17
Information required at handover ........................................................................ 17
2.11 Post Occupancy Evaluation (POE) ............................................................................... 18
2.12 BIM, Asset Capture, Drawing Standards and the Common Data Environment ................. 18
2.13 Temporary Works Design ........................................................................................... 20
Temporary Road/Footpath/Car Parks (and managing Closures/Diversions) .............. 21
Disturbance of soft-landscaping ........................................................................... 21
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 2
2.1 Introduction to Design Governance
The purpose of this chapter of the design guide is to set out how UWE expects the design
process to be managed. Specifically, it explains:
The need to consult relevant stakeholders and identifies who they might be
How the Construction (Design and Management) Regulations need to be approached at UWE
The role of UWE staff responsible for Technical Assurance and management of derogations
UWE’s approach to BIM and drawing standards
UWE’s approach to life cycle costs, softlandings and post-occupancy evaluation
The need to design an estate which is resilient and easy to maintain and clean
The management of temporary work design
2.2 Consulting to create a usable design
Designers will need to engage a range of stakeholders in a timely manner to create a functional
design. On a project-by-project basis, the team must determine who needs to be consulted, how
and when (UWE project processes provide an aide memoire).
These stakeholders inform design and project planning by explaining requirements, sharing
expertise or consulting with their own stakeholders. Do not assume knowledge of how spaces will
be used or expect one stakeholder to have all the answers. Examples of how they can help are:
Faculties can establish student user groups to help develop briefs and assess proposed designs.
Cleaning services can test the ‘cleanability’ of proposed products where they deviate from UWE
standards and advise on the impact this will have on cleaning regimes and costs.
CETTS (Central Examination and Time Tabling Service) can report on current space utilisation
and model the space requirements or impacts of a proposed project.
The following is a list of the UWE internal stakeholders which project teams may need to liaise with.
End users. This may be:
o Academic & technical staff
o The library
o The Centre for Sport
o Accommodation services
o Student Union
o A professional service
CETTS
Sustainability team
Grounds team
Energy team
Business risk management
Cleaning Services
Catering
MTC service provider
Community Liaison Officer
Travel and access
UWE Marketing
Hospitality Services
IT Services
Insurance manager
Equality & Diversity
Faith & Spirituality
Printing and stationary
Security
Health & Safety team inc. fire and construction leads
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 3
2.3 Aesthetic and visual impact
Designers are encouraged to create buildings and spaces that produce visual impact and inspire
users. Iconic facades do not reflect the values and ethos of the University. The internal design
and fit out must maximize student experience.
Experience at UWE has confirmed that less conventional designs requires close attention to co-
ordination and quality assurance, particularly in relation to contractor-led packages.
Designers must obviously ensure that any project’s physical impact on the surrounding area, local
communities and environment is in keeping and must satisfy the Local Authorities requirements.
Designers must ensure that a relative scale to any proposed development is maintained through
well-proportioned routes and spaces. Hard and soft landscaping must be used to ensure that
buildings compliment their surroundings and a sense of scale through softening of the outline of the
building is achieved. At the edges of any development, the design team must ensure that a strong,
open, accessible and active interface is achieved with the surrounding areas on all elevations.
Effective co-ordination is required between all the design disciplines to achieve the overall, desired
standard of appearance.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 4
2.4 Project Governance
Project Management
Effective project management ensures that project objectives can be met. Projects are to be
managed with regard to the principles set in Achieving Excellence in Construction suite of
Procurement Guides and managed in the spirit of Prince II.
Needless to say, it is crucial that designers refer to and help clarify the client’s brief to establish
what is in and out of scope. The client’s budget for the project may include the cost of certain
items required post-completion and during the project’s operational use.
Standards governing design work
Projects will be, as a minimum, designed and constructed in compliance with but not limited to:
All relevant Acts of Parliament, Statutory Instruments and associated codes of practice or
guidance
The requirements of the Building Regulations
All relevant EN Structural Eurocodes
British Standards, Specifications and Codes of Practice, including BS 8300 ‘Design of
buildings and their approaches to meet the needs of disabled people — Code of practice’
The requirements of the Local Authority and utility supply companies
Standard UWE Specifications
BRE Green Guide for Specification
The BREEAM rating which has been agreed or other, relevant standard. This may include
RICS SKA HE but this needs agreeing on a project-by-project basis as this standard may not
be appropriate for all projects.
The LPC Design Guide for the Fire Protection of Buildings.
CIBSE guidance.
BSRIA guides that are specifically referred to in the text of the design guide.
Loss Prevention Standards (also known as Red Book Live)
All as current at the time of appointment and further revisions prior to final design sign off.
UWE will require design teams to evidence – or may seek to verify for itself – that these standards
have been complied with. UWE project processes set out how this will be achieved.
In addition, standards such as ISO 14001:2015 environmental management system inform UWE’s
strategies and will therefore indirectly impact upon design.
A number of Chapters of the design guides are specifically written to explain how the above
standards are to be interpreted and applied in UWE and may introduce additional standards.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 5
Construction (Design & Management) Regulations 2015 (CDM)
UWE has a suite of documents setting out how it will comply with it’s duties as a Construction Client
and where relevant, as a Principal Designer and Designer. As a general principle, UWE will seek to
appoint the designer with most control over the design team as Principal Designer.
Designers must identify and manage risks associated with their designs, to the people who are
constructing, adapting etc. their structures (now or in the future), the people who are maintaining
or cleaning the structure or the people who will ultimately be using their designs.
Design risk management
As a client, UWE has identified design features that create or mitigate risks for future maintenance
and for users of their buildings and infrastructure, or which may pose risks to staff or students in
the vicinity of construction projects. The UWE design guides may take the following actions:
Insist that certain design features must be included or excluded
Encourage or discourage certain design features
If a design feature is discouraged, yet there is a compelling case for including that feature, it must
be evaluated using a design risk register and discussed with the UWE project lead and principal
designer.
Designers must be aware of the HSE’s ‘Red, Amber and Green’ list of design features which appears
in the industry guidance for designers (found here, please click ‘here’). If a designer wants to
include any ‘red’ or ‘amber’ design details they must also record these on the risk register.
The principal designer will help to determine precisely how risks are recorded and tracked. As part
of this process it is critical that designers consider and record how the new structure, plant and
services will be maintained. As explained later, this information must be included in the health and
safety file.
Designers need to be mindful that the population in a higher education setting is not the same as in
a commercial, retail or other urban environment. One of the key differences is that there are
peaks of population movement which designs must accommodate.
Designer’s responsibilities for risks during the construction phase
Designers can influence the risks posed to staff, students, UWE operations and contractors during
the construction phase.
UWE has developed a Safety Pack that sets out requirements and expectations of contractors on
UWE sites, e.g. stipulating the minimum separation distance between buildings and skips, the
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 6
standards of site protection, loss prevention standards for sheeting. It also highlights site-specific
hazards that project teams need to be aware of, such as hazardous vents on certain roofs.
All designers and project managers must review the contractor’s safety pack and consider how
their own decisions will affect the contractor’s ability to comply. If the project team imposes
excessive constraints on a project (e.g. in terms of time and space) it may not be possible for
contractors to comply with the Pack. Alternatively, the project team could make decisions that
create subsequent delays or risks because hazards were not identified and mitigated early enough.
From the earliest stages of the project, the team must be considering:
What surveys etc. are required to identify hazards and agree how risks can be mitigated,
perhaps through changes of design or project scope.
The logistics for delivering a safe and efficient project. Consider site boundaries, compound
space, traffic routes for construction traffic and likely sequencing/timing of work (which
could be reduced by pre-fabrication). This information must be reflected in contract
documents and the package of pre-construction information. Enabling works packages may
be needed.
Services must be protected - When making connections to existing services, the project will
need to determine the condition and capacity of the existing services and upgrade where
necessary. Where services to occupied buildings will be disrupted, the scope of the project
must include provision of alternative supplies in advance of diversion or disconnections.
The project must consider and mitigate the impact on access routes to and around the site
(for pedestrians, construction traffic, UWE deliveries, maintenance operations, emergency
vehicles etc.). See the section on temporary footpaths, later.
Developing a site constraints plan to convey the ‘buildability’ constraints and challenges.
Management of occupied buildings including sequential handover
After balancing a range of competing risks, costs and constraints, a decision may be reached that
the building being altered will remain partially occupied throughout the course of the works, or
there will be staged handover. Public protection measures and/or the handover programme must
be established in as much detail as possible before tendering for the principal contractor (so that
they will allow for this in their costs and programme etc.). The softlanding process will help the
project team to establish a well-managed handover programme, including identifying what
certificates and warranties will need to be in place before any handover commences.
Departures from Standards and Specifications
While trying to set out minimum standards in these design guides, the University does not wish to
stifle innovation. Innovation is a core value of Strategy 2020 and design teams are encouraged to
be creative and forward thinking. UWE will accept departures from standards/specifications.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 7
These departures may be allowed if there is a specific and direct advantage to the University.
Economic advantage will be evaluated using a whole life cost model to ensure that the university
obtains value for money through the life of the building. There may be factors other than
economic that may justify a departure from standard. UWE project processes describe how
departures from these standards will be managed (using derogation schedules). Design teams
must also be aware that UWE will ensure a technical assurance function is allocated to certain
projects who will review/comment on design proposals.
Technical Assurance
UWE contract and project management documents set out how technical assurance is to be
managed which will vary depending on the size and complexity of the project, the form of contract
etc. Designers will be informed what design information (including specifications) need to be
submitted, when and to whom and the process for discussing and resolving queries or reviewing
and approving derogations.
Projects must have a drawing release schedule which will ensure that the pre-construction phase is
being adequately managed and co-ordinated (including ensuring designers are being given
adequate time), designs are progressing in a timely manner and that individuals in technical
assurance or principal designer roles have sufficient time to discharge their own duties.
To support this process, UWE must be provided with co-ordinated designs details and drawings.
Co-ordinated drawings are essential: It is frankly pointless issuing a disembodied design for
comment as problems predominantly arise through the interface with other designs. Use of BIM
(as discussed later) will support more effective design co-ordination.
Named, Specialist Contractors
Design teams must be aware that UWE will sometimes require the use of named, specialist
contractors who have design responsibilities. It is the responsibility of the lead designer (supported
by the Principal Designer) to ensure these packages are co-ordinated with the overall design.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 8
2.5 Designing for Facilities Management & Maintenance
The demands of maintaining and managing a new structure and plant/services is a fundamental
part of the design process. It requires a co-ordinated response from all disciplines.
Consultants must adopt the principles and process outlined in the current version of BS 8536-1 and
BS 8526-2 ‘Briefing for design and construction. Code of practice for facilities management’.
Access and maintenance and/or plant replacement strategies are needed on all projects (unless
agreed otherwise). In brief, an outline strategy must be produced during RIBA Stage 3 consisting of
descriptive text and supporting drawings to show the provision for safe and practical maintenance
and replacement. A detailed strategy must be developed during RIBA stage 4. Before the project
proceeds, the documents must be reviewed by the Principal Designer, UWE maintenance team and
staff responsible for Technical Assurance. The documents form part of the health and safety file.
The first year of maintenance of some items of large plant (e.g. lift, boiler, chiller) will be the
responsibility of the principal contractor. This will be clarified in contract documents. The
intention is to encourage project teams to carefully consider ‘maintainability’ at design stage and, in
the pre-tender stage, to identify maintenance responsibilities.
Design features to improve access for plant/technical areas
Designers must apply “Defence Works Functional Standard, Design & Maintenance Guide 08: Space
requirements for plant access, operation and maintenance” to determine access/maintenance space
requirements, particularly within plant rooms. As a result, adequate space for maintenance,
removal and replacement shall be provided around all plant (to a minimum of manufacture’s
requirements). Chapters 6 and 7 explain that UWE will adopt BSRIA BG6 on projects with a
construction value of £2.5m (exc. VAT) or more. This will help ensure adequate space is provided.
The table below sets out UWE’s preferred and least preferred options relating to some recurring
issues that have rendered designs difficult to maintain or clean. If a design team wishes to
introduce a least preferred option, the derogation and change management processes must be
followed and the proposal accompanied by a design risk evaluation. This evaluation may be an
entry in the design risk register but may potentially be a more detailed justification explaining the
constraints that led to this design. If approved, the proposed management of the issue must be
fully addressed in access and maintenance/plant replacement strategies starting in RIBA Stage 3.
Most Preferred Options Least Preferred Options
External plant in a ground level, secure
compound or in a dedicated ground floor
plantroom with external, vehicular access
Roof mounted plant. In this case, the plant replacement
strategy must explain how crane operations will be managed
Internal plant areas (requiring large items of plant and
equipment to be moved through the building)
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 9
Most Preferred Options Least Preferred Options
All plant and maintainable components
accessible from permanent walkways
Lights, sensors etc. that require specialist access equipment,
closure of access routes and/or extensive work at height to
maintain or a requirement to work above tiered lecture
seating
Light fittings/sensors etc. that can be
reached with minimal work at height (e.g.
low level lights with high level reflectors)
Technical areas accessed from circulation
routes (or a dedicated, external doorway)
Maintenance workers having to enter occupied rooms
(especially teaching room) to access technical areas
Plant within buildings can be
removed/replaced without dismantling the
surrounding envelope
The need to dismantle elements of the structure/ envelope
(e.g. sacrificial panels, bulkheads, casing) to remove/ replace
plant or to access flanges/valves
Access to technical areas (or roofs which
require maintenance access) via an
extension of the stair core
Access to roofs/technical areas by ladders
Plant areas with sufficient space to
reasonably accommodate changes in future
(e.g. to cope with a changing climate)
including space to erect lifting gear
Plant areas that are sized to the minimum acceptable
thresholds with no space for future changes
Walkways clear of floor mounted or low
level pipework/ducts which create the risk
of trips and damage, or require workers to
stoop.
Obstructive pipework/ducts (which must be suitably
protected from damage or causing harm)
Ducts/areas that operatives must crawl to enter or reach. If
accepted by UWE, the design must comply with BS 8313
Maintenance workers having to enter a confined space
Materials drawn from UWE’s standard
specifications and can be cleaned using
standard equipment
Bespoke materials, esp. if they need specialist/unique
equipment to clean
In addition, the following measures must also be observed:
Escape routes within plant rooms/areas must be well defined. Where determined by the fire
strategy, there shall be a second means of escape provided.
Where plant is roof mounted (other than on concrete plinths), a clearance of 450mm must be
maintained below any item of plant, pipework or ductwork running on or across roof finishes to
enable roof maintenance to be carried out without the need to remove or raise services.
UWE contains a number of areas where access is restricted due to hazardous processes e.g.
laboratories. Isolation valves etc. must be located outside of these areas so that, in an
emergency, supplies can be shut off without exposing workers to risk.
Lessons Learned
In addition to the items above, UWE have encountered other a range of other problems that must
be avoided in future. These include:
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 0
1) Constructing upstands on roofs that require louvres and damper blades to be removed to give
access to motors and actuators. With the blades removed, a 5 storey, unguarded fall is
created. Hatches would have enabled the actuators to be accessed from a position of safety on
the roof.
2) Designers specifying end of line products as a cost saving exercise, meaning that spare parts
are no longer produced and the plant is obsolete on the day it is installed.
3) Risers which employees could or need to enter but which lack a load bearing floor
4) No or inadequate fire stopping details
5) Mechanical installations (or elements thereof such as pump heads) lacking details of weights,
lifting points etc. leading to delays and complications during replacement/removal
6) Handover documentation has historically not detailed the management strategy if
plant/equipment removal/replacement requires the use of cranes, lifting beams, sacrificial
panels etc. or other activity that pose operational difficulties or a significant risk to contractors
or UWE staff, students or assets.
7) Constructing canopies on the side of existing buildings, preventing access for window/gutter
cleaning and with no alternative strategy being considered.
8) Plantroom thresholds which render it difficult or impossible to use wheeled, mechanical lifting
aids to transport plant and equipment.
Facilities for cleaning
Buildings do not clean themselves! Designs
need to provide adequate facilities to
facilitate cleaning. The requirements for a
typical cleaning store is set out to the right.
During the design phase the housekeeping
team will determine the cleaning strategy
based on the proposed structure (including
surface finishes etc.) and activities within it.
The strategy may go through various
iterations and become progressively more
detailed as the design develops. Specific
items of equipment – and associated storage
etc. facilities – may be needed
A hard, impermeable floor surface
Plenty of storage space
Adequate ventilation & temperature control
(to aid drying and preserve correct chemical
temperatures)
Good lighting
A sluice sink
Hot and cold water supply
Racked shelving
Hanging racks for mops
Appropriate storage facilities for hazardous
substances (and to contain spills)
Potentially, washing machine plumbing (for
cleaning mop heads, depending on the size of
the building)
Potentially, charging points for cleaning
equipment.
External cleaning (glazing, guttering) or other challenging cleaning operations (e.g. high level
cleaning within an atrium) must be addressed in the access and maintenance strategy.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 1
2.6 Designing for Business Continuity
In short, UWE does not want to face long down times of assets due to inappropriate product
selection or subsequent delays in repairing/replacing assets. As a simple example, to reduce costs
it may be tempting to purchase a cheaper, end-of-line item of plant. Spare components quickly
become increasingly expensive and difficult to source, leading to long periods of down time or
potentially a very expensive operation to replace a piece of plant that can no longer be maintained.
Life Cycle Cost analysis (discussed elsewhere) may highlight potential risks being presented by
design/asset selection. As also discussed elsewhere, UWE has a number of mechanisms for
approving derogations and the UWE Technical Authority (or other staff responsible for Technical
Assurance) may challenge designs/selections based on the risks that they present. Design and
project risk registers must be used to highlight risks to the resilience of the new structure. There
may be requests to hold one or more specific resiliency workshops to identify and resolve issues.
Specific actions to increase resiliency are:
Within later chapters and the detailed specifications you may see some features that must be
used. This may be because they offers certainty of supply or certainty about durability and
reliability.
The life expectancy/reliability of critical plant (i.e. plant and equipment that would render a
building unusable if it failed) must not be a victim of value engineering.
Build redundancy into critical systems (e.g. back up boilers).
Avoid if possible, single points of failure.
Manual override systems are generally more resilient than complex solutions.
Utilities, IT and communication cabling must enter a building at diverse points.
Avoid products/systems with a single source of supply or long lead times, especially when they
are critical assets. If this cannot be avoided then it may be necessary to hold spares.
If critical assets require highly specialist skills or equipment to maintain, consideration must be
given to:
o Ensuring there is more than one company who can reasonably maintain the asset (in
case one ceases trading)
o Ensuring there is satisfactory 24/7 365 response, including a suitable response time
o Choosing alternative equipment
o Upskilling the UWE term contractor to enable them to carry out the task themselves
As discussed elsewhere, designers must think beyond the immediate boundaries of their own
design. When recording risks or holding risk/resiliency workshops please consider: What else
could be effected if a building or asset fails? What critical services might be delivered from that
building that may need to be relocated? Risks may ultimately be escalated to UWE’s operational
risk registers.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 2
2.7 Designing for Climate Resilience
For the University to continue to provide a high quality of service for the long term, the university
needs to design for business continuity within a changing climate. This section not only relates to
the long-term broad issues such as climate change, but also the immediate (0-5 year) impacts on
maintaining University operations.
Climate resilience/adaptation impacts on all aspects of the design and designers will need to
consider:
Fabric Performance and whole building design
M&E specification
Surface water drainage
Water and Energy security
Ecosystem services1
Plant replacement strategies
Whole life costing
Transport provision
o Designed to maintain reasonable operation during adverse weather events; and,
o Designed to minimise local air pollution on campus.
Not all these aspects may be relevant to a particular building or civil project, however they must be
reviewed with UWE staff responsible for Technical Assurance to scope-out and prioritise.
The University has introduced new targets addressing Climate Change Adaptation in the UWE
Sustainability Plan 2013-2020, which are largely based on the Adaptation section of the AUDE
Green Scorecard2. In brief, the relevant targets, are:
A3 - Flood risk - new projects: For any new buildings or major refurbishments (projects with
a construction value of £2.5m (exc. VAT) or more), at RIBA stage 2, to carry out an assessment
of flood risk with an inclusion for climate change, to ensure all major changes to the estate are
fully protected for 1 in 100 year events.
A5 - Overheating - new projects: For any new buildings or major refurbishments (projects
with a construction value of £2.5m (exc. VAT) or more), at RIBA stage 2, to use future weather
tapes, in assessing resilience of new buildings and refurbishments, and ensure buildings are
designed to cope with temperatures expected during their first refurbishment cycle (~25yrs).
The UWE Design Guide will be the mechanism to ensure this is adopted on all projects.
In all cases, the University are looking for a holistic approach to adapting to a changing climate and
expect designers to use the following principles:
1 Ecosystem services is a broad term representing the ways that the built environment, and building users, can benefit from ecosystems. For example, provision of blue and green landscaping to effect the microclimate
from local cooling via evapotranspiration; or the use of tree planting to provide summer solar shading. 2 AUDE Green scorecard: https://www.aude.ac.uk/Login?p=/resources/sustainability/green-scorecard/ (note that login details are needed and it is therefore necessary to register with the site).
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 3
1. Long term - Passive designs: Designs that work with, and compliment the environment
rather than against it. For example, considering orientation of the building to minimise solar
gains, avoiding onerous adaptation to building facades or relying on cooling plant.
2. Robust designs: Designing details and finishes that will be robust in adverse weather
conditions (storms and gales, flooding, heavy snow etc.)
3. Flexible designs: Designs that allow room for additional plant, or adapting to alternative
fuels etc.
These principles are not intended to add excessive capital costs onto projects, but rather allow for
whole life designs to be considered.
Assessing flood risk
Designs for new builds must produce a flood risk assessment making an allowance for climate
change. Designers must use the Governments guidance “Flood risk assessments: climate change
allowances”3 to produce the risk assessment. The Upper, Higher and Central allowances must be
used for the time period ‘2050s’ (2040 to 2069) to provide sensitivity analysis. The Guidance also
provides parameters to help designers ascertain which scenario must be chosen for a particular type
of project. The University sites are in different Flood Zones and therefore the scenario assessment
must be considered on a project by project basis.
Assessing overheating
As noted in 6.6, passive measures should be exploited as far as possible to reduce or avoid the
need for mechanical cooling.
In addition to any requirements under building regulations, projects must demonstrate that they are
operable and comfortable under 2020 climatic conditions and, with the addition of defined practical
strategies if necessary, under 2050 conditions. CIBSE TM524 guidance: The Limits of Thermal
Comfort: Avoiding Overheating in European Buildings provides further information for designers.
Where dynamic thermal modelling is included in the scope of works, the following CIBSE Design
Summer Year (DSY) weather data must be used for assessing overheating risk, based on the
UKCIP09 climate change scenarios.
2020 conditions Cardiff 2020s High emissions scenario 90th percentile
2050 conditions Cardiff 2050s Medium emissions scenario 90th percentile
The results of the modelling must be presented to UWE staff responsible for Technical Assurance to
inform early design decisions related to orientation, fabric, and building servicing. The purpose is to
help the University to assess the risk of design decisions and consider level of future proofing and
flexibility in the design that may be required for the future to adapt to the changing climate.
3 https://www.gov.uk/guidance/flood-risk-assessments-climate-change-allowances 4 http://www.cibse.org/Knowledge/knowledge-items/detail?id=a0q20000008I7f5AAC
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 4
2.8 Overview of Asset Management at UWE
Buildings can be be conceptualised as a collection of assets (such as fabric, electrical and
mechanical systems and components thereof). Relevant UWE assets are logged, and where
necessary barcoded, for management within the University’s CAFM system (Archibus). This system
is used for many purposes, but not least to plan all proactive and reactive maintenance activities.
It is essential that projects to construct or refurbish buildings are accompanied by accurate
information about new or updated assets. Subsequent sections of this Chapter of the design guide
discuss the soft-landing and handover processes and UWE requirements for how and when asset
information is captured. These requirements apply regardless of the size of the project (but are
tailored to suit different sizes of project).
Of course, it is also important to select and design assets to be cost effective to use and maintain.
This is the role of cost-in-use evaluations, discussed next. As explained earlier, sensible design
also ensures that assets can be maintained (and eventually replaced) efficiently and safely.
2.9 Cost-in-use
Only a small percentage of overall costs are associated with capital/construction expenditure in
procuring or refurbishing a building or infrastructure. The remaining costs arise from running,
managing and maintaining assets. Therefore, great care needs to be taken to ensure that what is
provided at handover stage is suitable and fit-for-purpose for its’ ongoing life. UWE believes that
sustainable buildings and infrastructure will help to minimise operating costs as well as safeguarding
the environment and promoting the well-being of staff and students.
Cost-in-use evaluations on major capital projects
To deliver UWE’s commitment, all Major Capital Projects (projects with a construction value of
£2.5m (exc. VAT) or more) will fully follow the Life Cycle Cost process below.
During the investment planning stage (RIBA Stage 0/1)
Whole life costing is to be used to provide a high level economic prediction of the project’s out-turn
costs, to enable UWE to make informed investment decisions regarding whether the project is
viable, sustainable and represents best value (this will be part of a wider academic, sustainability
and environment assessment). The definition of Life Cycle Cost (LCC) verses Whole life Cost is best
described by quoting ISO 15686 – 5 ‘’Life Cycle Costing covers the initial construction and through-
life activities associated with a built asset, whereas Whole Life Costing also includes non-
construction activities and income generation such as receiving rent from tenants.’’
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 5
During conceptual planning (RIBA Stage 2)
Life cycle costing is to be used as part of a strategic option appraisal process, to inform the
selection of fundamental or cost significant elements, such as structure, envelope, services etc.
During the detailed Design Stage (RIBA Stage 3/4)
LCC is to be used to appraise and select the detailed design options from a life cycle cost and
performance perspective and to optimize the LCC plan.
In some circumstances system and equipment selection will be obvious and upon agreement with
UWE Estates, detailed and formal evaluation may not be necessary.
However, where two or more options are viable on technical, economic and other grounds LCC
evaluation will be required; this must be performed using industry standard models (which are
explained below). This must be issued, making recommendations to the PM/ responsible for
Technical Assurance, who will give ultimate direction of the best way forward.
During the tendering process
To compare a bid’s competitiveness and to test the project affordability.
During the construction and handover stages (RIBA Stage 5/6)
Set up the LCC in use budgets using a Operational Funding Plan, based on life cycle cost planning
using the construction and/or refurbishment costs.
During the lifetime use of the constructed asset (RIBA Stage 7)
Benchmarking of actual operational cost as part of HEFCE Soft Landings. Post contract evaluations
are to be undertaken (after a suitable time interval) to assess the actual building performance
against the design performance.
All LCC evaluations are to be shared amongst the design team and UWE in an electronic format to
enable all parties to conduct a thorough investigation of the structure of the model.
Value Engineering
Value Engineering (VE) is not a cost reduction exercise. The intention is to find alternative and
better value solutions to deliver the same or improved outcomes for the end user, rather than
undermining functional requirements or performance of a structure in the pursuit of cost savings.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 6
VE must be based upon sound LCC evaluations. For example; if a plant purchase is likely to
save money throughout its life expectancy, but have a substantial impact upon the capital budget
then this must be taken into account in any capital decision.
Along with any cost model, an evaluation of the item’s performance must be included in order to
establish the consequences of any trade off in the purchasing decision.
Evaluations on minor capital projects (under £2.5m exc. VAT)
LCC is to be adopted proportional to the value and nature of the specific scheme, the parameters to
be agreed and recorded at RIBA Stage 1 by the Project Manager. For example, a project based
largely on selection and installation of replacement plant may undertake some measure of LCC.
Standards
LCC are to be carried out in accordance with BS ISO 15686-5, using best practice as defined by
BSRIA BG 67/2016 ‘A BSRIA Guide Life Cycle Costing’ and the BCIS/BSI publication PD156865
‘Standardized Method of Life Cycle Costing for Construction Procurement (SMLCC)’: A supplement to
BS ISO 15686-5 ‘Buildings & constructed assets - Service life planning’ - Part 5: ‘Life cycle costing’.
Selection of the discount rate and the study period will be set in agreement with the university,
based upon the bespoke nature of the particular project.
Life cycle lengths must be presented as options within any evaluations to enable UWE to make
informed decisions regarding likely future usage profiles. The project team must provide energy
performance certificates with the completed building information.
The design life expectancy of the building will be stated in the individual project particulars,
however, it must be recognised that University Buildings are often retained far in excess of this
notional figure, individual components therefore need to be robust in nature.
References
Reference and consideration must be given to the requirements of the following best practice:
ISO 15686-5 2011. Buildings and constructed assets - Service life planning
BSRIA BG 67/2016 ‘A BSRIA Guide Life Cycle Costing’
BCIS/BSI ‘Standardized Method of Life Cycle Costing for Construction Procurement - A
supplement to BS ISO 15686-5 ‘Buildings & constructed assets - Service life planning’ - Part 5:
‘Life cycle costing’
BREEAM (Building Research Establishment Environmental Assessment Method)
BS 8544 Guide for life cycle costing of maintenance during the ‘in-use’ phases of buildings
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 7
2.10 Soft Landings
The ultimate goal of a construction project is, obviously, to deliver a functional structure that meets
UWE’s requirements. To achieve this, UWE needs to work collaboratively with internal and external
stakeholders, designers and consultants to determine their functional and technical requirements,
objectives and targets (which may go beyond those stipulated in this design guide) and the
information, training, support and aftercare that are needed to use/operate the building.
‘UWE BSRIA Soft Landing Requirements for Design Team’ sets out what needs to be done and
when, to achieve these ambitions. The following text is adapted from that document, which is
available in full as an appendix to this Design Guide.
UWE are committed to adopting the BSRIA Soft Landings philosophy on all major new build and
refurbishment projects from concept to 18-months post-completion. For the post-occupancy
evaluation, UWE uses the guidance set out by HEFCE.
It is the University’s intention to incorporate BSRIA Soft Landings, as defined in BSRIA BG38,
BSRIA BG4 and associated documents as part of its post-completion requirements. The
successful tenderer will be required to include the appropriate resources and commitment to
fully achieve this ambition.
The BSRIA Soft Landings Framework sets out core principles for client, designers and
constructors for the design, handover and post-completion stages of a building project.
It includes pre-handover familiarisation and training.
Soft Landings emphasises an enhanced handover process and post completion after care.
However, UWE believe that the full benefits of the approach are realised by embedding it right
from the start of the project. The aim is to develop a collaborative framework where the client
and design teams focus on outcomes and work together to agree challenging but realistic
targets that are reviewed and refined throughout the design and procurement process.
The requirements and expectations within ‘UWE BSRIA Soft Landing Requirements for Design
Team’ have been taken from the BSRIA guide BG45 on how to procure soft landings.
Information required at handover
Later, this design guide discusses drawing standards and asset information requirements.
UWE project processes set out the information required at handover and also provides templates to
enable project teams to identify and track the required documentation. This includes Health and
Safety File information (including access and maintenance strategies), Fire Safety Information
(referred to later) and the information that is often called the ‘Operation and Maintenance’ (or
O&M) manual.
Information must be supplied in a particular electronic format, as explained in project processes.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 8
2.11 Post Occupancy Evaluation (POE)
UWE has a POE strategy which has been incorporated into the UWE project processes. Full Post
Occupancy Evaluation (POE) is usually required on any UWE projects with a construction value of
£2.5m (exc. VAT) or more. This will require a more in-depth “investigative” and “diagnostic”
approach to the POE process.
Lower value projects will take a more focussed (“indicative”) approach to POE, usually involving a
site visit and performance scorecards to be completed to identify any key lessons to be learned.
The Project Manager will, at the outset of the project, determine the precise approach that POE will
take.
For example, the precise POE process for a project to install district heating plant would be very
different to a large, new building with numerous technical area and laboratories and this would be
different from the POE for a refurbishment of a ‘back office’ building.
In brief, the POE evaluates the process used to procure, design and build the project, the functional
performance of the building and the technical performance.
UWE will work with designers to ensure stakeholders requirements and expectations, are clearly
articulated and considered. By setting out project objectives, intended benefits and POE
requirements at the outset, designers and consultants can allocate sufficient resources to ensure
they can contribute meaningfully to a positive POE process.
2.12 BIM, Asset Capture, Drawing Standards and the Common Data Environment
UWE has set out its approach to BIM, and its specific information requirements, in “UWE Employer’s
Information Requirements (EIR)”. All new buildings, or future refurbishments of buildings that
have been modelled in BIM, must comply with this document.
UWE will not retrospectively apply BIM for buildings that were built prior to these standards coming
into force. Refurbishments of existing buildings will therefore not be subject to BIM, unless the
University has identified a clear advantage in doing so (which will be explained in the project brief).
The objectives of our information requirements are to:
Maximise production efficiency through adopting a coordinated and consistent approach to
working in BIM.
Define the standards, settings and best practices that ensure delivery of high quality data and
uniform drawing output across an entire project.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 1 9
Ensure digital BIM files are structured correctly to enable efficient data sharing whilst working in
a collaborative environment across multi-disciplinary teams.
To facilitate data exchange and collaboration, UWE may require designers to share information in a
‘common data environment’. This is planned to be hosted in Newforma.
Even where projects fall outside BIM, the team must still comply with our asset capture procedures
“UWE Asset Information Requirements (AIR)”, which is included as an appendix. This ensures our
assets are appropriately recorded. This underpins our maintenance regime and is vitally important.
Without it, we could fail to comply with statutory obligations to maintain assets or assets could fail
leading to disruption and risks. Unless we know what we need to maintain we cannot adequately
resource our maintenance operations.
Finally, UWE has comprehensive guidance regarding general drawing standards.
http://www.uwe.ac.uk/facilities/estates/drawings/DrawingStandards/drawingstandards.shtml
The documents which apply to different types of projects are:
BIM Projects
Non-BIM Projects
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 2 0
2.13 Temporary Works Design
Temporary works are defined in BS 5975 as any solution that (to paraphrase) enables permanent
works to be accessed and/or built. It covers everything from excavations to scaffolding, piling
mats, propping and site hoarding.
The Health and Safety Executive has also produced their own guidance, SIM 02/2010/04, which
complements the British Standard.
For the avoidance of any doubt:
Temporary works are designed. The designers are therefore bound by this design guide.
UWE will sometimes provide constraints, specifications and considerations for temporary works
designers. A number of these requirements can be found in the UWE Contractor’s Safety Pack,
specifically:
o Hoarding and site protection
o Requirements for temporary footpaths
o Public protection measures to be incorporated into scaffold design.
Please note that designers are required to review and consider the UWE Contractor’s Safety
Pack. It is the responsibility of the designer to ensure the design is structurally sound,
depending on location, ground and environmental/weather conditions etc.
Contract documents, pre-construction information and Employer’s requirements may further
inform temporary works design
In line with BS 5975 and SIM 02/2010/04, the Principal Contractor (PC) must have a temporary
works co-ordinator who will oversee design and management of temporary works. On smaller
projects with simple temporary works, those responsibilities may be discharged by the site
manager or another member of the site team. Temporary works co-ordination will never be
the responsibility of UWE.
The PC must set out in their Construction Phase Plan (CPP) how they will manage temporary
works. UWE will review those arrangements as part of their duty as client to ensure a CPP is in
place and adequately manages significant risks.
Temporary works must be checked. UWE does not have the capacity to provide a technical
check of temporary works design.
A number of temporary works operations are designated by UWE as high risk activities and
requires a contractor to gain approval before commencing (under the approval to work system,
explained in the Safety Pack). UWE staff will, at that stage, be involved in reviewing temporary
works design. This is for the purposes of establishing that it has met UWE specifications (e.g.
whether site plans show that hoarding, signage and/or temporary footpaths will be positioned
where agreed). This is not the technical check required by BS 5975 and SIM 02/2010/04.
UWE Design Guide for Buildings
C h a p t e r 2 | D e s i g n G o v e r n a n c e I s s u e 1 . 3 P a g e | 2 1
Temporary Road/Footpath/Car Parks (and managing Closures/Diversions)
Proposed closure/diversion of roads/footpaths must be identified during the pre-construction phase
(this is part of considering the ‘adjacencies’ of a project, as discussed in Chapter 1 of this guide).
Proposeds route and anticipated dates (if known) must be discussed with the UWE transport team.
The impact of diversions on emergency vehicles, maintenance operations etc. must be considered.
The proposed route of temporary footpaths must be inspected as early as reasonably practicable to
consider the following and agree actions (which may be included in the contractor’s scope of work):
The adequacy of existing surfaces that might be used and/or the standards required of
temporary surfaces that may need to be formed
The standard/adequacy of lighting
The numbers of pedestrians using the new footpath
The interface with vehicular traffic
Alterations to wayfinding/signage (including responsibility for providing additional signage)
Accessibility of alternative routes must be assessed (we have had examples of wheelchair users
diverted via an extremely steep footpath or across gravel that they were unable to navigate). For
example, if a temporary crossing point did not have a dropped kerb, a temporary ramp may need to
be formed or a dropped kerb may need to be constructed (with tactile paving etc.).
Inconvenience/increased travel distances caused by temporary routes must be minimised as far as
is reasonably practicable.
UWE expects Chapter 8 (Traffic Safety Measures & Signs for Road Works and Temporary Situations)
to be adhered to as far as reasonably practicable (click ‘Chapter 8’ to see the guidance). Designers
can support compliance by ensuring the considerate location of temporary crossing points etc.
The need for a diversion must be recorded and shown on a site constraints plan.
Diversion or disruption of the public right of way through Frenchay Campus will be subject to close
and early attention during the pre-construction phase, and will be the subject of consultation with
relevant stakeholders inside and outside UWE. The UWE Transport team will support this process.
Disturbance of soft-landscaping
It will sometimes be necessary to create a temporary footpath or road surface over soft
landscaping. This must be discussed with the grounds team at the earliest opportunity: They will
need to agree the temporary provision and how landscaping will be remediated afterwards. This is
discussed in more depth in the chapter addressing infrastructure, biodiversity and landscaping.
UWE Estates and Facilities Design Guide
Chapter 3: UWE Strategies
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1
Table of Contents
3.1 Introduction to UWE Strategies .................................................................................... 3
3.2 Accessible and inclusive design ..................................................................................... 3
3.2.1 Inclusive Design Features ...................................................................................... 4
3.2.2 General advice for designers .................................................................................. 4
3.2.3 Applying the UWE Principles during the RIBA Plan of Work ....................................... 6
3.3 Strategy for Welfare Facilities ....................................................................................... 8
3.3.1 General design considerations ................................................................................ 8
3.3.2 Creating inclusive and accessible facilities ............................................................... 9
3.4 Security Systems Strategy .......................................................................................... 11
3.4.1 A balanced approach ........................................................................................... 11
3.4.2 Impact of Security on Fire evacuation ................................................................... 11
3.5 Designing a Sustainable University .............................................................................. 12
3.5.1 Sustainable Design Stages ................................................................................... 13
3.5.2 General principles ................................................... Error! Bookmark not defined.
3.5.3 Sustainability - Actions to be taken by the design team .......................................... 13
3.5.4 Other considerations informing product selection ................................................... 15
3.5.5 Funding Opportunities for Sustainability Measures ................................................. 15
3.6 Design for Wellbeing ................................................................................................. 16
3.6.1 Multi-function, wellbeing spaces ........................................................................... 16
3.7 Religion and Belief ..................................................................................................... 17
3.8 Fire Strategy ............................................................................................................. 18
3.8.1 Fire Safety Standards .......................................................................................... 18
3.8.2 Information requirements .................................................................................... 18
3.8.3 Consultation with UWE Health and Safety Team (HST) .......................................... 19
3.8.4 Design responsibilities for fire safety during construction ........................................ 19
3.8.5 Fire Stopping ...................................................................................................... 20
3.9 Printer Allocation Policy .............................................................................................. 21
3.9.1 Fire Risk Assessment ........................................................................................... 21
3.10 UWE Sport Vision ...................................................................................................... 22
3.10.1 How the Estate supports the UWE Sports Vision .................................................... 22
3.11 UWE Transport Strategy ............................................................................................ 23
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 2
3.12 Signage and Wayfinding Strategy ............................................................................... 23
3.12.1 Physical Signage ................................................................................................. 24
3.12.2 Electronic signage ............................................................................................... 24
3.12.3 Wayfinding Apps and mapping tools ..................................................................... 25
3.12.4 An inclusive and accessible Wayfinding Strategy .................................................... 25
3.13 Occupancy Hours ...................................................................................................... 25
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 3
3.1 Introduction to UWE Strategies
The purpose of this Chapter of the design guide is to examine specific UWE strategies and how
they impact on design. They influence all aspects of design. These strategies include:
Accessibility and Inclusivity
Welfare Facilities
Security
Sustainability
Wellbeing
Religion and belief
Sports
Fire
Signage and Wayfinding
Printer Allocation
3.2 Accessible and inclusive design
UWE is committed to providing an environment that is welcoming, accessible and inclusive for a
diverse population of students, staff and visitors.
Inclusive design is, quite simply, good design. It means helping everyone to have a good
experience by creating an environment that is welcoming and usable for all. UWE strives to
prevent any section of our community feeling frustrated, ignored, segregated or stigmatized. UWE
recognises that people “disabled” by the built environment include:-
People with impairments (including people who have temporary or fluctuating impairments)
Elderly people
Children
Parents with children
Women and men (or those who identify with neither or both genders)
People who feel excluded because of lifestyle, sexual orientation, culture, ethnicity, religion,
low income or other factors.
UWE is bound by the Public Sector Equality (PSED) duty both as an employer and service provider
under Section 149 of the Equality Act 2010. Design teams are expected to adopt best practice
inclusive design principles from the outset to support UWE in meeting these duties. The quality of
University experience must be equal for all users and delivered to a high standard.
Particular attention is needed during the refurbishment of existing building stock where reasonable
adjustments may be needed. UWE buildings have been built at different times to different
standards and some are listed. There may be limits on what adjustments can reasonably be made
to the built environment and end-users may need to look at the planning and organisation of their
activities to accommodate the needs of staff and students. However, refurbishment projects in
these buildings can often be used to improve accessibility or introduce features that make the
building more inclusive.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 4
To achieve these aims, and create an environment that supports equity, equality and dignity in use,
UWE is working to the following principles:
Providing the same means of use for all users, identical when possible, equivalent when not
Avoiding stigmatizing or segregating any users
Respecting the dignity of the individual
Integrating inclusive principles into the design process
Mainstreaming inclusive design: It is not an add-on extra or “special needs” interest
The Equality Challenge Unit has produced useful, additional guidance for design teams in “Managing
Inclusive Design for Higher Education (2009)”, available here (click ‘here’).
Inclusive Design Features
The purpose of this design guide is not to duplicate the requirements set out in Part M of the
Building Regulations and BS 8300. Those documents represent minimum standards and only
address issues of physical access. Inclusive principles and design features, which go beyond Part
M and BS 8300, have been embedded throughout this design guide. They have been derived from
consultation with stakeholder groups, lessons learned on past projects and contributions from the
Centre for Accessible Environments.
It is not UWE’s intention to have a stand-alone section on accessible and inclusive design features.
Instead, these features will be integrated into the relevant Chapters of the design guide. This will
hopefully help ensure that inclusive design is not treated as a ‘bolt on’ to the design process.
By embedding inclusive design principles into the design guide, project teams on smaller projects
(less than £2.5m (exc. VAT) construction value) will be equipped to develop inclusive and accessible
designs without the need for external access consultants. Projects of this scale will typically be
refurbishments and opportunities will be sought to enhance the accessibility and inclusivity of
existing buildings. To achieve that, extant access audits will be used to inform project scopes.
On larger projects (projects with a construction value of £2.5m (exc. VAT) or more) the intention
will be to include as many of these design features as possible into the major refurbishment or new
building. As explained later, an access consultant must be appointed on projects of this value.
General advice for designers
The design and layout of UWE buildings, interior and exterior fixtures, fittings and furniture
and external spaces must be flexible enough to reasonably accommodate future changes.
Designs will allow sufficient space, or flexibility to create the space, for assistive equipment,
assistance dogs, personal assistants and communication support workers etc.
Staff and student will have the capacity to adjust lighting, acoustics and internal climate
wherever reasonable and when compatible with other commitments, such as sustainability.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 5
Where possible, designers will take a consistent approach to the specification of access
equipment across the campus. This can benefit users who require familiarity with equipment
and who may not be able to cope with change. This also simplifies repair and replacement.
Where the design guide or specifications are not adequate to meet a specific need, review
access features that have worked well on previous projects and specify good quality
products that are consistent or compatible with those existing. These features must be
incorporated into this design guide or associated specifications.
Where the guide states that features are ‘to be considered’, design teams need to consult
more widely (as explained below) to understand what features are reasonable. Where
compromises are required due to space, budget or other constraints, or there is no current
demand, allow for future retrofitting where reasonable. Examples include pre-fitting
pipework to accommodate a future accessible WC or level access shower and pre-wiring
above doors to anticipate future power assisted door operators or hold-open détentes.
We recommend designers spend 10 minutes watching UWE Bristol’s wheelchair challenge
(click the underlined text). This highlights some of the challenges that designs can present.
Sufficient provision must be made for powered wheelchair charging.
Provide fixtures and fittings that require minimal physical effort to operate (e.g. powered
access doors with buttons that can be used with minimal force) and ensure they are in a
practical location (e.g. a door open device must be adjacent to the door that it operates).
Consider the wider implications of accessible features. For example a new ramp along a
front elevation, could impact on window cleaning and maintenance for upper floors. During
those works, the ramp may be inaccessible and temporary access arrangements needed.
A selected example of design features mentioned elsewhere in the design guide (which will
therefore not be discussed in detail here) include:
Multi-function wellbeing spaces (which can be used for a variety of functions such as space
for religious observance, quiet reflection or for new mothers to express and store milk).
Welfare facilities, including accessible and gender neutral provision.
Facilities for faith and religion.
The need to provide a choice of open plan and enclosed spaces (to cater for different
acoustic and cognitive impairments) or to provide privacy where needed.
Consideration of the impact of temporary routes.
The electrical chapter requires:
o The provision of evacuation lifts
o Visual and audible fire alarms in selected locations
o Hearing assistance systems in teaching spaces
The chapter on landscaping, biodiversity and infrastructure contains:
o Requirements for spaces to be provided for three wheeler motorcycles, tricycles,
recumbents an adapted bicycles
o Requirements for making pedestrian routes accessible
o Requirements for accessible car parking
o Mixed selection of external seating including some with seat backs and arms
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 6
The chapter on fabric and structural design addresses:
o Principles governing selection of furniture and furnishings
o Visual contrast
o Acoustic considerations
o Principles of horizontal and vertical circulation
o Use of powered doors and hold open devices
o Accessibility of student accommodation
The UWE Bristol Fire Standards discusses personal emergency evacuation plans (PEEP) as well as
discussing some elements of design (e.g. in relation to disabled refuge provision).
Applying the UWE Principles during the RIBA Plan of Work
On projects with a construction value of £2.5m (exc. VAT) or more, a National Register of Access
Consultants (NRAC) accredited Access Consultant must be involved from RIBA stage 2. They must
have expertise relating to wider diversity issues e.g. be aware of cultural factors – not just physical.
RIBA Plan of
Work
Core Inclusive Design Activities
0 Strategic
Definition
The project requester undertakes an equality analysis when requesting a project.
This is issued to the UWE Equality and Diversity team for review and comment.
1 Preparation
and Brief
Estates meet with the project requestor and review the equality impact analysis
(and any feedback received from the Equality and Diversity team) to understand the
impact for the design brief, budget etc.
Estates review existing access audits to identify opportunities (and funding sources)
for the project to address outstanding actions.
During the development of the brief, consider ‘adjacencies’ (as explained in Chapter
1 of this guide): Identify opportunities to introduce elements into the current
project that improve inclusion and access for adjacent buildings. E.g. a new ramp
to a building might offer shared access to an adjacent building which lacks a ramp.
Undertake a desktop review of any feasibility proposals. This may involve one or
more focus groups which may be recommended by the Impact Analysis.
2
to
4
Design
Stages
For projects with a construction value of £2.5m (exc. VAT) or more Estates will:
o Undertake a formal Access Audit of the existing and proposed site to identify
issues to be considered in the design process.
o Consult with the UWE equality and diversity team and with one or more target
user focus groups (starting at RIBA stage 2) and agree appropriate
communication process and dates for ongoing consultation. The E&D team will
arrange an accessible venue, transport and communication support (but costs
are to be funded by the project).
The design team develops design to comply with the design guide, including
accessibility/inclusivity features. Where features are ‘to be considered’, they will be
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 7
RIBA Plan of
Work
Core Inclusive Design Activities
discussed with the requester/focus groups to determine which features are
reasonable to include in the brief.
The access consultant will review designs as they develop, contribute to consultation
events and stage gate reviews and provide a commentary in end of stage reports.
Derogations are considered and managed by Estates.
Develop and regularly review ongoing Design and Access Statement and Building
Regulations Approved Document M access tracking schedule as required for
statutory authorities, listed building or other 3rd party consents
Ensure that all access and inclusion elements in design proposals are
comprehensively specified, approved and signed off prior to issuing tender
documentation to contractors.
5 Construction Regularly review accessibility of temporary signage, access routes, surfaces,
hoardings, obstructions and control of dust and noise to ensure that safe inclusive
access is maintained during the construction phase.
Arrange for Access Consultant to attend site meetings, review material samples and
provide ongoing access/inclusion advice during the construction phase as necessary
(for projects with a construction value of £2.5m (exc. VAT) or more).
6 Handover Undertake Access Audit (for projects with a construction value of £2.5m (exc. VAT)
or more) and Snagging Schedule of completed works and undertake remedial action
as required.
The UWE softlanding approach may require training/briefing of relevant staff and
students in the use of accessible features.
Handover documentation to include details of/instruction for use of accessible
features.
Provide new or revised access management plan for the building.
Update emergency evacuation plans to reflect changes to the building(s).
7 Use Monitor accessibility feedback from users over 18 month post-occupancy period and
collate findings.
Undertake 18 month post-occupancy evaluation.
Complete remedial actions and update access management plan as needed.
Document findings and lessons learned in the overarching campus access strategy.
This could lead to a change of project management processes and will lead to a
review of the design guide and associated specifications.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 8
3.3 Strategy for Welfare Facilities
The effective design of welfare facilities requires close co-ordination between the different design
disciplines. Problems can arise if these facilities are seen as the sole province of the ‘public health’
engineer. Welfare facilities can be the most challenging (and emotive) issues facing design teams.
Adequate welfare facilities support a number of other UWE strategies such as equality and diversity
(E&D), sports and sustainability (e.g. showers close to bike shelters to promote cycling and support
our strategies on wellbeing and reducing car usage). As a result, UWE’s approach to welfare
facilities is discussed in this Chapter, amongst other overarching strategies.
Compliance with Building Regulations, the Workplace (Health, Safety and Welfare) Regulations and
relevant British Standards (e.g. BS 8300) are not sufficient to provide a workable solution for UWE.
A ‘like-for-like’ approach to refurbishment of welfare facilities is not acceptable: Standards have
changed and the configuration of existing welfare facilities may need significant alterations.
General design considerations
UWE has had to deal with a legacy of poorly considered design:
Accessible toilets that cannot be accessed by a wheelchair user.
Sometimes dimensions do not comply with BS8300. In other cases a
‘compliant’ facility has been positioned in an inaccessible location, for
example where a structural column prevents a wheelchair from
manoeuvring into the facility (the photo to the right, taken in a newly
refurbished hotel in 2017, illustrates this general principle).
Toilets that are too small. The minimum width is 800mm. The Metric
handbook and other documents illustrate how these toilets should be
set out, including making provision for sanitary bins.
Floors lacking appropriate falls to enable use of floor drainage.
Inappropriate finishes to walls, e.g. bare paint work which is stained by cast off water. As
explained in the Chapter on Fabric and Structural Design, ceramic wall/floor tiles are to be
avoided: Vinyl wall and floor finishes are preferred.
Hand driers above other fixtures or features that are damaged by cast off water.
Floor drains not being positioned appropriately to help deal with issues such as cast off water.
The use of vanity units in accessible facilities preventing wheelchairs moving close to the sink.
Integrated panel systems (IPS) should be used to conceal toilet cisterns (urinal traps must be
exposed to facilitate cleaning). Vanity units are to be used if there is a row of sinks. Cubicles
require coat/clothes hooks.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 9
Shower facilities and associated changing rooms are to be included wherever practicable.
Depending on the anticipated demand on welfare facilities, clothes storage and drying facilities may
be required and/or ventilation may require close attention. UWE shower facilities used by high
numbers of cyclists have suffered from damp, odour etc. especially if clothes dry naturally.
Any sports facilities on campus are to have accessible WC, shower and change provision.
As ever, designers must consider adjacencies: E.g. If there are no shower facilities within
reasonable walking distance of a new building then there is much more impetus to install them.
UWE is keen to use effective design of welfare facilities to support our sustainability ambitions. As
discussed elsewhere, UWE wishes to explore the use of boreholes or greywater, and this could
potentially be used for toilet flushing. UWE’s requirement for sensor taps and hand driers, and
various other design features detailed elsewhere in this guide and the associated specifications,
minimises both direct and indirect water usage (e.g. water associated with laundry operations).
Creating inclusive and accessible facilities
On all projects, design teams must ensure:
All WCs that are accessible to ambulant users with lever or easy press taps and locks easily
operable with a single, closed fist. Jeflock Accessible toilet locks fully meets this requirement.
The provision of fully accessible toilets (i.e. unisex, accessible WC) to comply with Part M of the
Building Regulations in terms of travel distances (which helps dictate numbers required) and BS
8300 in terms of design.
As per Part M, in any separate-sex toilet, at least one cubicle must be fully designed for
ambulant, disabled people in line with BS 8300. Any row with four or more cubicles must also
have one enlarged cubicle for people who need extra space (including travelling with luggage).
The doors of accessible toilets should be power-assisted wherever possible.
Ensure that all Accessible WCs can be accessed directly without passing through a Male or
Female WC area, as a disabled user may be assisted by a member of the opposite sex.
Where there is more than one Accessible WC in a building, provide a choice of left and right
hand transfer. These can alternate between floors, with lift access.
Facilities for disabled users must have an alarm, complying with BS 8300, linked to an external
flashing and audible beacon with the following poster displayed under the beacon: “When Light
Flashes and Alarm Sounds, Contact East Reception on 0117 3289999 for assistance.”
Fire alarms are visual as well as audible in all accessible WCs and standard WCs, particularly in
cubicles where partitions are taken up to the ceiling with no gap above the door.
Designers must ensure that on all new builds and major refurbishments:
The equality and diversity teams are consulted to have a meaningful input on the design of
welfare facilities. Meetings may be facilitated by the E&D team.
They liaise with Faith and Spirituality as to the provision of a Wudu/Ritual Washing facility or
any other requirements to support specific faiths.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 0
Establish if a larger Hygiene Room/Changing Places WC with dual transfer, variable height
changing bench, level access shower and tracked ceiling hoist is needed. These benefit users
who need personal assistance with using the WC, showering and changing. Location on campus
will depend on where demand is likely to be greatest and where it can be most easily reached.
Wheelchair accessible ensuites to campus residential accommodation to have fused spur power
points pre-fitted to accommodate future tracked ceiling hoists and automatic wash and dry
shower toilets.
Part M of the Building Regulations show hand driers positioned 800-1000mm above floor level.
UWE prefers them to be the centre of this range to suit people of different heights.
Gender neutral toilets
As a general principle, UWE aspires for each building to have at least one gender neutral toilet. On
large buildings (nominally anything more than 50 m in length), facilities will be provided as a
minimum on alternate floors. Major refurbishments must be used to consider retrofitting gender
neutral provision. However, as discussed elsewhere, these aspirations may not always be
achievable as UWE must work within the physical constraints of existing structures, drainage etc.
UWE prefers gender neutral toilets with self-contained provision
(i.e. bowl, hand washing/drying facilities, female sanitary bin).
Self-contained cubicles occupy considerably more room than
cubicles with shared handwashing facilities and requires
considerably more servicing. Space or other constraints may lead
to solutions with shared hand-washing etc. provision. This should
be dealt with as a derogation. Ideally at least one cubicle will be
self-contained to maintain the sense of safety of someone who
does not feel secure washing hands etc. in a communal sink.
The photo to the right shows gender neutral welfare facilities at
Bower Ashton. The furthest cubicle is a combined gender neutral/
accessible facility. A standalone, accessible WC would need to be available to both genders, but it
is as an accessible, unisex WC, and would not count as a gender neutral facility. Please note that
this particular sign is no longer acceptable, and is too high for someone in a wheelchair to read.
The preferred choice of signage is a toilet pictogram with no representation of people
(example shown to the right). If this will not work in a particular circumstance, the
image used for gender neutral toilets at Bower Ashton (shown above) may be
proposed as a derogation. Accompanying text must read “Gender Neutral Toilet”.
Labelling gender neutral toilets as “for everyone”, “available for all” etc. is only to be used if they
are genuinely accessible for all. Signs must be replaceable with relative ease in response to
growing awareness and new thinking around issues of gender identity.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 1
3.4 Security Systems Strategy
Any new buildings or refurbishments which extend, amend or could impair security systems must be
discussed with the Security Manager (Head of Operations and Security). They will assess the
scheme (in consultation with Estates and the occupying clients) and ensure the design provides the
correct level of access control and security for that space. They may advise on specific measures
required during the construction phase while security arrangements may be compromised.
Security must be considered holistically from the earliest stages of design. Concerns about, for
example, positioning of doors and windows or the creation of ‘blind spots’ can be addressed early.
Security is only one design consideration. The security strategy aims to ensure a balance is
achieved between securing and safeguarding the campuses and the people using them, whilst
maintaining open campuses which can be used flexibly and can meet differing user needs.
UWE is not signed up to any specific security standards (e.g. Secured by Design) but this may be
required on specific projects.
Where security systems are deployed they must be fit for purpose. Dysfunctional systems lead to a
false sense of security and upset in the event of an incident. Security systems used at UWE are:
Programmable Access Control and
Door Monitoring
CCTV (with legally-required signage)
Intruder Detection Systems (IDS)
Physical Locks
24/7 manned guarding presence on each campus.
Further guidance on the infrastructure requirements are set out in a later chapter. Designers must
ensure containment for security systems is included and co-ordinated with the rest of the works.
A balanced approach
The security strategy is a proportionate response, balancing the risks (including of acts of terrorism)
against our ambition to have open, accessible and inclusive campuses. Under the Counterterrorism
and Security Act 2015, UWE is a Specified Authority and has an explicit legal duty to prevent people
being drawn into terrorism. Our approach to inclusivity, including providing faith spaces, is an
important mechanism for fulfilling this duty.
The design guide reflects our assessment of foreseeable security risks and scenarios. We are not
over-specifying our structures, glazing etc. to withstand purely hypothetical incidents. However,
the risks are reviewed routinely and may lead to changes in future.
Impact of Security on Fire evacuation
Doors on escape routes and final exits that are fitted with security devices must satisfy the
requirements of fire safety: It must be possible for any person to easily and immediately open
them in an emergency.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 2
3.5 Designing a Sustainable University
UWE’s vision is to embed sustainability throughout everything we do, from the courses we teach to
the back-of-house services that keep the university running. Our Estate is no exception to this rule,
and sustainability must be a strong theme throughout any new development.
UWE has a sustainability plan covering from 2013-2020 found here (click ‘here’). The Plan sets out
a series of objectives and targets. Designers must familiarise themselves with these aspirations and
consider how their achievement can be supported through the design of new spaces.
The University demonstrates its commitment to environmental sustainability through its certification
to the international standard BS:EN ISO14001:2015. The certification requires continuous
improvement in environmental performance through the whole institution: Our estates, services
and educational provision. The standard requires the university to consider the lifecycle impact of its
products and services.
Figure 1: Ventilation strategy for R Block Phase 2, a BREEAM Excellent building
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 3
Sustainable Design Stages
Throughout the design stages, the University expects consideration of the following criteria:
Develop Brief Use sustainability performance as one criteria in the selection of team members.
Sustainable design features and requirements are embedded throughout the Design Guide and designers should be familiar with all relevant chapters.
Establish stakeholders sustainability expectations/requirements.
Establish and utilise benchmarks, targets or measurements for the project. These could include BREEAM, BRE Green Guide to Specification, BRE
Sustainability Check List, RICS SKA HE assessment tool, EPC targets and other relevant standards/methods of assessment (incl. Building Regulations Part L).
Begin implementing BSRIA soft landings (which are explained in UWE project management processes).
Concept design Designers must consider the lifecycle implications of their designs and product
selections. Specifically, from concept design onwards projects should seek to minimise resource depletion and environmental degradation, and be resilient to
a changing environment, by considering the following criteria:
Maintenance
Water (incl. future availability and cost)
Energy (incl. future availability and cost)
Climate change (as explained elsewhere)
Materials
Transport
Ecology
Waste
Evaluate and incorporate new technologies and concepts.
Scheme Design Prepare prediction checklist of chosen assessment tool.
Use post occupancy evaluations/lesson learned from their past projects to make informed decisions e.g. refer to monitoring of energy performance from past
projects to provide guidance on how Part L building regulations can be
exceeded or achieved in a cost effective manner.
Detailed Design Incorporate UWE Design Guide requirements and recognised best practice.
Consider clashes through use of BIM to eliminate basic design errors such as:
Tall cupboards blocking vents
Partitions being erected without consideration of existing vents and/or radiators (creating one very hot room and one very cold one)
TRV positioned behind desks
Less-efficient plant selected to suit available space, rather than the
design providing sufficient space at the outset.
Construction Procurement of contractors, suppliers and materials based on their ability to meet sustainable KPI’s.
Assessment Feedback Benchmarking against energy use targets
Post Occupancy Assessment
Sustainability - Actions to be taken by the design team
UWE’s Sustainability Plan contain specific measures that impact on the design of new structures.
Specific actions that the design team must make towards meeting these are set out below.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 4
Subject Specific actions to be taken or considered by the design team
Campus
Development
Projects with a construction value of £2.5m (exc. VAT) or more: Project briefs may
augment the requirements of this design guide by defining specific sustainability/
energy standards to be met under certification schemes such as BREEAM or SKA. Pre-
assessments must be carried out by accredited assessors at key stages of the design
process together with a corresponding reconciliation of cost and value.
Target CO2 emissions rate must exceed those set out in approved document L2A by a
minimum of 5%. At the design stage the designers must model the in-use energy
consumption including unregulated emissions.
All designs to comply with detailed stipulations in this design guide.
Carbon
Management
New buildings must have an Energy Performance Certificate (EPC) in line with the
Directive1, to be provided by the person carrying out the construction project.
Seek locally sourced materials and services to minimise transport impact.
Select products with low whole life carbon emissions.
Avoid over-specifying of materials, and consider embedded carbon.
Agree a target Energy Performance rating for new buildings. The minimum is B.
CIBSE guide TM39 (Building energy metering) must be followed for new buildings and
major refurbishments. See the Mechanical Engineering Chapter for further details.
Refurbishment projects with a construction value of £2.5m (exc. VAT) or more must
consider energy efficiency improvements to existing building fabric and systems (as
detailed in the relevant chapters within this design guide).
The University’s Carbon Management Plan (click here to see it) may initiate specific
projects to reduce emissions.
Orienting and designing buildings to maximise natural light but minimise solar gain
High heat gain activities (PC labs, data centres etc) are located:
o Away from excessive solar gains (e.g. north facing façade)
o To maximise free cooling opportunities (e.g. with an external wall)
Renewable
energy
The following renewable energy sources must be investigated at all opportunities (and
could potentially drive fundamental decisions such as building orientation):
Solar thermal
Solar PV
CHP
Wind
Air source/ground source heat pumps
Biomass/Biofuel (under particular circumstances)
Waste &
reuse of
materials in
construction
UWE has a 95% recovery target for waste. Projects with a construction value over
£300,000 exc. VAT must have a site waste management plan (SWMP) to predict waste
streams and plan to prevent, reuse and recycle. UWE project management processes
explain what is required.
1 The directive is Energy Performance of Buildings Directive 2002/91/EC. An EPC is also required for
refurbishments if a building is modified to have more or fewer parts than it originally had and the modification
includes the provision or extension of fixed services for heating, air conditioning or mechanical ventilation.
Referenced from ‘A Guide to energy performance certificates for the construction, sale and let of non-
dwellings’ 2nd edition July 2008, Communities and Local Government.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 5
Subject Specific actions to be taken or considered by the design team
Note that SWMP are essential for the effective planning/costing of the work (e.g.
making sufficient space allowance for storage or plans for traffic movements).
Given the scale of work at UWE, we expect project teams to consider ‘adjacencies’ and
co-ordinate their approach to waste management: Waste from one project could
potentially be reused on another (e.g. inert demolition waste could be used as hard
core for another project).
Designs should be based on the principles of the “circular economy” which is:
“restorative and regenerative by design, and which aims to keep products, components
and materials at their highest utility and value at all times”.
Consider recyclability of materials and recycling pathways of high maintenance/short-
life products (e.g. flooring).
Designers to avoid specifying, as far as reasonably practicable, toxic substances (which
could contribute to an incident, or become hazardous waste in future).
Water UWE has a standard specification for fittings for WC refurbishments to aid water
efficiency including WCs, taps, urinals and associated controls.
Include water conservation measures within the design.
Use of rainwater and grey-water harvesting must be investigated for new builds and
major refurbishments. Where possible a gravity fed system must be specified. For
refurbishments, if retrofitting an internal system is not viable, the collection of
rainwater must be considered for grounds watering purposes.
Potential use of boreholes is being investigated at Frenchay.
Biodiversity Grounds design to comply with Chapter 9 of this design guide to seek the best
ecological options/opportunities.
Climate
Change
adaptation
Develop designs for operating under 2020 climatic conditions together with defined
practical strategies for operating under 2050 conditions as set out in section 2.7 of this
Guide. Particular attention should be paid to avoiding overheating.
Other considerations informing product selection
Designers must consider the impact on the environment when selecting materials (e.g. avoid over-
specifying the use of cement). UWE encourages all designers to use A rated materials/products
from the BRE Green Guide to Specification wherever reasonably practicable, and in addition to use
materials in accordance with the RICS SKA HE assessment tool. Other requirements are set out in
the Chapter addressing Fabric and Structural design.
Funding Opportunities for Sustainability Measures
If certain projects require additional funding to enable more sustainable travel or the most energy
efficient option to be installed, then the Energy and Travel Teams within Facilities must be
consulted to discuss possible opportunities to access external funding.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 6
3.6 Design for Wellbeing
It is believed we spend around 90% of our lives in buildings and these environments significantly
impact our health and wellbeing, and ultimately our productivity and performance. Staff costs
represent 90% of operating costs of an organisation (compared to 1% for energy costs). Even
modest increases in performance and productivity (or reduced turnover, absenteeism etc.) brought
about by thoughtful, “human-centred design” can lead to significant benefits for individuals and the
organisation. The importance of user experience to our students and staff, and the value of
human-centred design, must be considered alongside more traditional measures of whole life cost
and capital costs during the design and delivery of campus development.
Measurable aspects of wellbeing such as light, air quality and temperature are no less important
than connection to nature and a sense of ownership. Later chapters of the design guide set out
UWE’s approach to creating a comfortable environment. Often, thoughtfully placed design features
can support positive wellbeing, as well as other UWE strategies. For example, trees can reduce
solar gains and create a pleasant environment.
Buildings and external landscapes shall be designed with consideration of the university’s smoking
policy, found here (click ‘here’ to see it). In brief, building design and signage should discourage
people from smoking outside buildings, particularly where smoke can enter doors/windows.
Multi-function, wellbeing spaces
Designers and project team must consider providing at least one multi-function space within new
buildings or major refurbishments (projects with a construction value of £2.5m (exc. VAT) or more).
These spaces can be used for:
Space for quiet reflection or prayer
Wellbeing activities (e.g. physiotherapy exercises)
First aid provision
New and expectant mothers (including where breastfeeding mothers can express/store milk)
Diabetics can self-inject etc.
They must be colour neutral and image free and the equivalent size of a one person office. Where
reasonable, especially in larger buildings, consideration should be given to two spaces: One to
cater for physical wellbeing (first aid etc.), the other for mental/spiritual wellbeing.
Spaces catering for physical wellbeing should be equipped with refrigerators and storage (including
a ‘sharps bin’). Doors will need to be equipped with locks so that people will not be disturbed.
The justification and requirements of these spaces would need to be made on a project by project
basis after consultation with the stakeholders. Sufficient measures must be put in place by the end
users to ensure the space does not become a store room or overflow work space.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 7
3.7 Religion and Belief
UWE is committed to provide an inclusive learning and working environment where students and
staff of all religions or beliefs, or those who have no belief, can thrive.
Designers need to be aware that UWE is facing a growing set of challenges to meet the religious
and spiritual needs of our community. In no particular order these are:
Almost one third of our student population (approximately 10,000 students) identify themselves
as having a religion and as such, they may wish to use existing faith facilities
We are actively recruiting from communities and regions with strong faith traditions and the
numbers of students who actively and routinely use faith facilities is increasing
The existing facilities are struggling to cope with twice the demand it was built to acommodate.
However, numerous ‘pockets’ of provision are not desirable unless there is consideration of how,
in practice, they will be supported.
Historically faith provision has been considered in a piecemeal and reactive manner.
With the completion of new student residences in Frenchay, we have more students living on
site leading to increased demands but also different patterns of demand.
The existing Community Hub is celebrating it’s 40th Anniversary in 2019, but (given the
comments above) UWE is considering the need for alternative facilities.
The legal landscape is developing and the Counterterrorism and Security Act 2015 places an
explicit legal duty on UWE as a Specified Authority, to prevent people being drawn into
terrorism. Our approach to religion and belief is a key element of how we meet that duty.
Faith provision must be ‘front of house’ and readily accessible.
Faith facilities may be used as safe spaces in the event of a major incident.
Designers must consult the University’s Coordinating Chaplain in the Faith and Spirituality Team
ahead of any major refurbishment or new build (projects with a construction value of £2.5m (exc.
VAT) or more). The Chaplain will organise further consultation as required. For example, the
Community Hub is overseen by a board of trustees which must be consulted on changes and faith
groups would be consulted on their own specific requirements.
The design team will be assisted in determining what provision may be needed, or how we can
improve access to existing facilities. Where specific features are needed (e.g. a faith room or ritual
washing facilities), the design team will be advised on what is required.
Generally, faith spaces must be designed to cater for a multitude of faiths (creating a multi-faith
space). As explained above, the UWE chaplain must be consulted to help the project team
evaluate the likely demand and peak times of use (which will influence the size of the space),
design etc.
A later chapter of this guide discusses memorial plaques. In brief, they are not encouraged.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 8
3.8 Fire Strategy
Fire Safety Standards
Buildings must be designed using BS 9999:2008 (Code of practice for fire safety in the design,
management and use of buildings) unless fire safety engineering using BS 7974 is needed.
The UWE Health and Safety Team (HST) must be consulted regarding the proposed fire strategy.
The HST have produced a comprehensive suite of documents, known as Fire Safety Standards
(FSS), that outline the functional requirements of fire precautions on the UWE estate, including
provision for people with disabilities, fire doors etc. The documents can be found here (click ‘here’).
The Electrical engineering and IT infrastructure chapters of this design guide provides more
technical details regarding fire detection and alarm, emergency lighting etc.
Information requirements
Project teams for both refurbishments and new builds must consult the UWE Health and Safety
team and provide fire strategy information.
Regulation 38 of the Building Regulations & Fire Safety Information
Designers must provide Fire Safety Information if they are erecting, extending or changing the use
of a building. Fire Safety Information relates to the design and construction of the building or
extension, and the services, fittings and equipment provided in or in connection with the building or
extension which will assist the responsible person to operate and maintain the building or extension
with reasonable safety. This must be provided not later than the date of completion of the work, or
the date of occupation of the building or extension, whichever is the earlier.
UWE undertakes numerous projects which alter existing fire protection systems but which do not
represent an extension or change of use.
UWE Requires designers and project teams to comply with Regulation 38 of the Building
Regulations regardless of the scope of the project.
UWE’s specific requirements are set out in project processes. In short, design and project teams
must comply with Appendix G of Part B of the Building Regulations and Appendix H of BS 9999.
That chapter of the design guide also address commissioning fire protection systems, such as
detection/alarm, smoke control etc.
A building cannot be accepted if fire protection systems are not operational and if required fire
safety information is missing.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 1 9
Consultation with UWE Health and Safety Team (HST)
The UWE HST is a key stakeholder. UWE has a range of mechanisms to ensure the HST are
notified of projects at RIBA stage 1 to ensure that obligations under CDM 2015 are met.
UWE is also the ‘Responsible Person’ under the Regulatory Reform (Fire Safety Order) 2005 and
must have an active role in assessing the impact that the project will have on existing fire safety
arrangements during construction and after handover.
Consultation with the HST Fire Advisor must commence at the equivalent of RIBA stage 2 (Concept
Design). Critical decisions will be reached during this stage about architectural, building services
and structural engineering and Fire Safety must be an integral consideration. Further, construction
strategies will have developed to the point that the team will understand the wider impact of the
project on UWE operations, staff and students.
Design responsibilities for fire safety during construction
Designers have a role to play in reducing fire risks during the construction phase. The Joint Code
on Fire Prevention in Construction Sites provides guidance to designers and places a number of
requirements on them. The code generally applies on projects over £2.5m but it can also apply to
lower value but high-risk contracts. The code states that “the design should be assessed to ensure
that fire risk and potential for damage have been fully considered to keep to a minimum during
construction and use.” The lead designer must ensure this is done.
On all projects, regardless of value, UWE requires that designers consider the following items which
are copied verbatim from the joint code:
The use of non-combustible and non-flammable materials to reduce fire loads
Materials and methods that avoid the need for hot work on site
Design details that prevent the passage of smoke and flames up through a building during
the construction phase
Design of access routes to enable the contractors to construct buildings in such a manner as
to retain safe evacuation routes during the construction phase
Design for fire fighting/alarm systems to allow early use – possibly on a partial use basis.
HSE guidance HSG168 (Fire Safety in Construction), highlights the need for effective communication
between dutyholders. This ensures, for example, fire compartment walls are identified and
designs/programmes allow for temporary fire-stopping. The Principal Designer plays a key role in
collating and distributing this information and reviewing design risk information. The HST reviews
the Principal Contractor’s plan for managing fire risks, which is part of the Construction Phase Plan.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 2 0
Fire Stopping
Any specifications or other designs for fire stopping around linear joint seals, service penetrations
and small cavities must confirm to the current edition of the Association for Specialist Fire
Protection’s Red Book Fire Stopping And Penetration Seals For The Construction Industry). The
following table is taken from that Book and shows the permitted applications of fire stopping
products. Fire stopping should be an integral design consideration, rather than an afterthought, to
ensure that it is aesthetically in keeping/co-ordinated with the fabric and mechanical designs.
Table: Permitted application of generic fire stopping products
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 2 1
3.9 Printer Allocation Policy
Designers need to make adequate provision for printing. To do that in a consistent and planned
manner they need to aware of the UWE Printer Allocation Policy.
In the past, printers have been purchased without regard to the lifetime cost of the device. Savings
can be delivered to the University if the proliferation of printers is halted, more people share devices
and personal printers become the exception rather than the rule.
The aim of the “Allocation Policy” is to provide guidelines for future printer deployment. Printing and
Stationery (PSS) is a key stakeholder for any project and must be consulted as soon as it is clear
that printers may need to be moved/removed/replaced or added.
They will help assess current and future printing demands, advise on printer specifications and
locations, including the space needed for printing supplies, and help the project team to apply the
basic principles of the Printer Strategy. Some general points to note are:
A space approximately 1.5m x 1.5m is required for each printer which will be floor-standing.
Smaller machines are available where usage will be low but may need to sit on a worktop or
desk.
Devices will need 1 x TSSO (1 outlet for the machine and 1 for a servicing technician’s use).
Each will require 1 x wired data outlet. Direct connection to a PC will only be permitted in
highly exceptional circumstances as this seriously restricts sharing. Connection of printers to
the network via WiFi is not currently supported.
Power and data sockets must not be located in floor boxes where there is any likelihood, now or
in the future, of the printer covering the floor box.
Storage space for paper and other consumables will be required. For larger machines in high-
use areas storage for up to 30 boxes of paper may be required.
Space will be required to maintain and repair the machine. The machine will need to be moved
out of position and rotated to access some parts and this has to be conducted in a safe space
for the technician and other personnel.
Consideration must be given to providing sound-deadening screens in areas that will be quiet to
avoid disturbing occupiers of the room.
Please note that printers being introduced as part of a project must be purchased out of project
funds. There is no central budget for new provision.
Fire Risk Assessment
The increased use of shared printers and copiers has led to electrical equipment moving from a
room, fitted with a door, into escape routes, which people will need to use in an emergency. This
creates a fire hazard in what is expected to be a relatively sterile area, free from combustible
materials, ignition sources and obstructions.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 2 2
Under no circumstances must a printer workstation be located:
• In residential accommodation
• In a protected staircase
• Where there is an escape route in a single direction only.
• Where the workstation would reduce the available escape width below 1000mm.
The following standards must be referred to when making decisions about printer locations:
FSS05: Maintaining the Means of Escape HSS11: Circulation Space
3.10 UWE Sport Vision
Providing facilities for health, physical activity and sport will support UWE in meeting the ambitions
set out in the UWE Bristol Strategy 2020. Sports facilities are used for a range of purposes beyond
physical activity and sports, such as occupational health assessments. There is a strong
association between physical activity and physical and mental wellbeing.
Therefore, the UWE Sports Vision is to provide every student with the opportunity to play sport or
take part in healthy activity at a time and level appropriate to them.
How the Estate supports the UWE Sports Vision
Designers must engage with the Centre for Sport to notify them of forthcoming projects affecting or
expanding sports facilities and determine their requirements from the masterplan or specific
buildings. They will, in consultation with users, advise on the facilities that are needed and specific
design features (e.g. floor finishes) required to make those facilities functional and attractive.
The Centre for Sports can suggest creative uses of relatively small internal or external spaces to
help delivers the Sports Vision, and ultimately support Strategy 2020. Therefore, they must be
consulted ahead of major refurbishments or new builds.
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 2 3
3.11 UWE Transport Strategy
The University promotes the following general principles in regard to design of new and refurbished
transport infrastructure on campus. Many of the issues mentioned here are discussed further in
the Chapter addressing hard- and soft-landscaping:
Provision for transport users needs in a hierarchy, with pedestrians, cyclists and disabled users
at the top, followed by public transport users and then private motorcycles and cars.
Application of the UK Governments ‘Manual for Streets’ guidance (click this link to see it),
including especially shared space principles.
Spatial separation of transport infrastructure on campus, with the central areas of campuses
primarily designed for pedestrians, with parking peripheral to the site.
Consideration of all transport needs, including safe and efficient servicing access and
consideration of access for all modes including motorcycle, taxi, emergency vehicles etc.
Access and maintenance/plant replacement strategies may also require MEWP/Crane access.
Promoting use of electric vehicles by introducing charging points.
Legible pedestrian routes for key routes within campus to be strengthened through the design
process (see the signage and wayfinding strategy next).
Cycle facilities in new builds shall have adequate sheltered and secure cycle parking, lockers and
showers, including facilities for disabled persons who may use a hand-powered cycle and
require wheelchair storage. New cycle parking to follow Bristol City Council guidance (click this
link to see it).
The design team must work closely with the Local Authority to ensure that all requirements for the
site specific transport strategy, traffic assessment and environmental impact assessment are met.
UWE has a risk assessment addressing the interface of vehicles and pedestrians. Any designs that
change or introduce new interfaces must be discussed with the UWE Travel and Access Team.
3.12 Signage and Wayfinding Strategy
Effective wayfinding can have a significant impact on the life of the University: It enables staff,
students and visitors to navigate and move smoothly through our buildings and estate, helps to
reduce confusion or anxiety and creates an inclusive environment. Wayfinding also reinforces the
UWE brand, by creating a consistent theme that reflects UWE’s values and aspirations, and provides
critical information that supports a range of other strategies (e.g. fire and wellbeing). In contrast,
ineffective wayfinding (e.g. lack of information about accessible routes or facilities) can create
unnecessary barriers and stress. UWE has therefore created a standard specification which sets
out in detail the design and application of signage to support efficient wayfinding.
Different user groups have varying demands in terms of information required and preferred
methods of communication, so UWE has identified a multi-strand strategy to enable improved
wayfinding around and between its campuses. This strategy consists of:
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 2 4
Physical signage and wayfinding totems (both internal and external)
Electronic signage
Wayfinding apps and online mapping tools
Physical Signage
UWE has engaged a specialist signage and wayfinding consultant (ABG Design) to work with the
University on a new physical signage strategy consisting of a new signage family. This will be
applied to future capital projects and a phased replacement/update programme to existing signage
will be undertaken. In brief, project teams need to be aware that:
Different types of signs exist for different functions, providing ever increasing levels of detail to
allow individuals to find their destination. This represented in the image, below. If changes
are being made to the layout of a building (e.g. adding/removing rooms or facilities such as
showers or cycle parks), the wayfinding signs must be traced back to determine what signs
need to be updated. The project budget and programme must allow for these amendments.
Certain signs require power and/or data or controls (e.g. for lighting and remote change of the
display). Projects which install or change signage will need to allow for these supplies.
Please contact Estates for the current specification for signage.
Electronic signage
The dynamic, ever-changing nature of University activity and space allocations means that physical
signage can quickly become out-dated and is costly to update. Electronic site display screens and
signs are therefore used at key locations around campuses – particularly at entry points and near
receptions/information points. The displayed content can be controlled remotely and highlights
UWE Design Guide for Buildings
C h a p t e r 3 | U W E S t r a t e g i e s I s s u e 1 . 3 P a g e | 2 5
current events or important information. On all Estates projects, electronic signage must be
considered alongside physical static signage. This can be particularly useful for teaching spaces or
meeting rooms, where wall-mounted tablets can display live timetables of room bookings or
scheduled teaching. Project teams must allow for the addition of power and data in these cases.
Wayfinding Apps and mapping tools
Along with physical signage on site (whether fixed or electronic) there is an emerging requirement
for mapping tools which can be used on mobile devices. UWE has engaged with a company called
MapsPeople to create a web-based mapping tool, which sits on top of the Google Maps platform.
This allows users to navigate across complex sites using step-by-step directions and to select
preferences or certain criteria such as accessible routes only. Another feature of the wayfinding
app is that users can search for specific facilities which may not otherwise be signpost on physical
signage (e.g. specific room numbers). As this is further developed, it is envisaged that this
becomes a more prominent wayfinding tool which can be embedded in various communications
such as emails, open day or event information etc. This technology will be developed in
consultation with users, including targeted focus groups to ensure it is accessible and inclusive.
An inclusive and accessible Wayfinding Strategy
In addition to the various, inclusive features mentioned above, the strategy will ensure:
Accessible routes are shown on signage diagrams.
Location of accessible and gender neutral WCs, faith or wellbeing spaces are indicated on ‘Type
4’ floor plans.
Symbols to WC doors and to other main spaces to be raised and tactile.
Signage to be of a matte finish.
All physical maps to be marked with a ‘you are here’ identifier.
3.13 Occupancy Hours
Our occupancy hours can drive various aspects of the design, such as heating, lighting, security etc.
The precise details will need to be established on a project-by-project basis. The Mechanical
Engineering Chapter has further information on core hours. In brief, core hours are:
Space Hours
Office space 08:00 – 18:00pm
Teaching 08:30 – 18:00pm
Sports 07:00 – 22:30pm
Library/IT areas Up to 24 hours (potentially also throughout vacation periods which must be carefully considered when planning the security strategy)
Student accommodation 24 hr
UWE Estates and Facilities Design Guide
Chapter 4: Space Standards
UWE Design Guide for Buildings
C h a p t e r 4 | S p a c e S t a n d a r d s I s s u e 1 . 3 P a g e | 1
Table of Contents 4.1 Introduction to Space Management 2
4.1.1 The role of the space management team in design 2
4.2 Functional Requirements in all Buildings 2
4.3 Space Types 3
4.4 Space Standards 5
4.4.1 Space Allocation 5
4.4.2 Notes on calculating space requirements 6
4.5 Room numbering 6
UWE Design Guide for Buildings
C h a p t e r 4 | S p a c e S t a n d a r d s I s s u e 1 . 3 P a g e | 2
4.1 Introduction to Space Management
It is imperative that the University’s estate be both efficient and effective. The Space
Management team, in conjunction with the Central Timetabling Unit, Estates and Facilities
and the Faculties are tasked with achieving this through maximising utilisation rates and
creating space that is as flexible, functional and future-proofed as possible.
This Chapter of the design guide sets out:
The different functional requirements in buildings, which impact on space allocation
General design requirements of different space types
The specific space allowances for certain types of spaces
UWE’s approach to room numbering
Designers should be familiar with Chapters 1, 2 and 3 before commencing design work.
4.1.1 The role of the space management team in design
It is useful to understand the role of the Space Management team and some of the ways in
which they can directly influence or contribute to design. The team assists UWE and project
teams to better utilise space by:
Liaising with faculties and departments regarding their current and future space needs
and providing advice regarding room layouts and best use of space;
Recommending the remodelling and reconfiguring of existing space where there is
evidence that it is inadequately used or ill-equipped;
Setting space standards, as detailed below.
4.2 Functional Requirements in all Buildings
For the efficient future management of the completed building, a number of building
management facilities (e.g. plant rooms) will be required. In addition to these a number of
other facilities are a prerequisite in all buildings:-
At least one cleaner’s room on each floor (see Chapter 2 of the design guide);
The number of toilets will be calculated by the possible numbers of persons within the
building at a change in timetabled periods. Design considerations influencing welfare
facilities are addressed in Chapter 3 of the design guide;
Shower rooms, changing rooms and drying rooms will be provided dependant on usage;
Lobbies and reception areas need to be bright and welcoming and clearly delineated, in
order that visitors know where to report and gain information;
Hub rooms/switch rooms and/or communications cabinets;
Waste storage will be required according to the waste strategy for the building and
surrounding campus, available from the Waste and Sustainability team.
UWE Design Guide for Buildings
C h a p t e r 4 | S p a c e S t a n d a r d s I s s u e 1 . 3 P a g e | 3
First aid facilities (this is potentially one use for multi-function wellbeing rooms, as
discussed in Chapter 3 of this design guide);
The Design Team will be required to develop and incorporate furniture layout orientation
with UWE appointed framework furniture suppliers;
All furniture to adhere to UWE’s approved furniture standards.
Signage (internal and external) to comply with UWE’s signage specification;
4.3 Space Types
Below are some guidelines on space planning within buildings. The guidelines are not
exhaustive. Consultants and contractors are encouraged to engage with the Space
Management and Design Team early in any project. This team will be able to give a more
comprehensive understanding of room types and sizes.
The University has a vast assortment of spaces, which can be largely classified in the
following list. The classifications used by the Space Team are based on data sets that form
part of statutory and in-house returns such as Estates Management Record (EMR) reports to
HESA, TRAC and RAM data for financial returns.
Space Type Description and Space Considerations
Lecture
Theatres
Large teaching rooms with fixed tiered seating used for traditional didactic delivery
of taught modules to larger groups. These are all centrally scheduled spaces which
are used by all Faculties and Services. Recently the University has commissioned a
number of Harvard style lecture theatres to meet the demand in changes to
teaching in some areas. Lecture Theatres are planned to meet overall institutional
needs and, where possible, link to other spaces to ease traffic flow. IT and AV
requirements should be discussed with the University’s IT service.
Large
Teaching
Rooms /
Event spaces
Large rooms with mobile furniture which are generally used for delivering taught
modules to larger groups. Centrally scheduled spaces used by all Faculties and
Services. Generally, rooms should accommodate classes of 50 (this is subject to
change as teaching methods evolve therefore please liaise with the University’s
Space Manager on current demands). IT and AV requirements should be discussed
with the University’s IT service. Please bear in mind these rooms may be used for
exam purposes and this should be considered when specifying furniture. Such
large spaces can pose challenges for delivering effective natural lighting and
discussions about the implications will need to start during RIBA stage 2.
General
Purpose
Teaching
Space
Agile rooms with movable furniture to suit different teaching styles. Centrally
scheduled spaces used by all Faculties and Services. Generally, rooms should
accommodate classes of 25 (this may change as teaching methods evolve
therefore please liaise with the University’s Space Manager on current demands).
IT requirements should be discussed with the University’s IT service. These rooms
may be used for exams and this should be considered when ordering furniture etc.
UWE Design Guide for Buildings
C h a p t e r 4 | S p a c e S t a n d a r d s I s s u e 1 . 3 P a g e | 4
Space Type Description and Space Considerations
Meeting
Spaces
Rooms designated for formal/informal meetings. Centrally and locally scheduled
space, available to all. Power and data points should be provided. Liaise with the
UWE Space Manager on current needs/sizes of meeting rooms.
Interview
Rooms
Private spaces where confidential matters can be discussed by between two to six
people. Power and data points are required. Interview rooms will require higher
standards of acoustic insulation and may also need panic alarms. The use of
blinds, frosting etc. should be considered if visual privacy is also needed.
Receptions
Reception desks should be designed to a consistent corporate image, provide
sufficient working space, be accessible and have hidden cabling. Receptions
should be light and welcoming with soft seating provided.
Office Space
Office space to support business activities. These may be individual, shared or
open plan and include storage provision and ancillary spaces. Office space is non-
scheduled space apart from hot desks which may be locally scheduled. No-one
should have more than one desk unless there is a justifiable reason. The norm is
open plan arrangement for Professional Services and most academic staff to be in
offices of up to four. Refer to the space standards below as a guide. Contact the
University’s Space Manager for advice on layout and furniture requirements.
Storage An allowance should be made for storage dependant on occupiers and use of
building. Please refer to Space Manager on requirements.
Specialist/
Research/
Teaching
Laboratories
Special purpose space which does not typically lend itself to other uses (although
some laboratories may allow for dual/multi-purpose use). Targeted use which may
be centrally or locally scheduled space. Please note these spaces need determining
early as they may have structural, mechanical, electrical, drainage and ventilation
implications above “normal” space usage. Please refer to the Space Manager
regarding the additional allocation of specialist space per academic subject.
General
Laboratories
Laboratories should be fit for purpose, flexible and adaptable for use by other
faculties, where possible. Please note these spaces need determining early as they
have structural, mechanical and electrical implications above “normal” space usage.
PC
Laboratories
General PC laboratories, with non-specialist software or hardware. Centrally
scheduled space, used by all Faculties. IT requirements should be discussed with
the University’s IT service. Power, data & ventilation requirements to be specified.
Open Access
Learning or
Group Work
Space
Flexible, ad-hoc and locally bookable spaces used to facilitate individual and group
learning. Mainly non-scheduled space, with some bookable spaces. For use by all
students. Wi-fi, power and data requirements to be specified.
Library
Spaces
Library space will include a mixture of library and individual student and group
work study. Please liaise with the Head of Library Services and Space Manager on
current space needs and trends.
Staff Social
Areas,
Kitchens and
Tea Points
Tea points, staff kitchen areas and staff common rooms should be informal areas
which may or may not be in the immediate vicinity of offices and could be shared
between one or more faculties or service. Specification to be agreed at space
management level, with input from Faculty or Service.
UWE Design Guide for Buildings
C h a p t e r 4 | S p a c e S t a n d a r d s I s s u e 1 . 3 P a g e | 5
Space Type Description and Space Considerations
Catering
Facilities
The design and need for central catering areas within buildings should involve
discussions with the Catering Manager and Space Manager to fully understand the
University’s requirements. Cafes and catering are addressed in the fabric and
structural chapter of this guide. Furniture to be specified in conjunction with Space
Management and Design Team to suit type of catering space being commissioned.
Sports
Facilities
Sporting facilities (as discussed elsewhere) support a number of UWE strategies.
Any future design proposal that relates to sporting facilities will require the design
team to adopt the University’s excellent standards and incorporate readily accepted
industry standards. Equipment to be sourced in conjunction with Head of Sport.
Toilets/
Showers
Toilets and shower areas will be designed to be sufficient for building occupancy
levels and be compliant with the current legislation, best practice, etc.
Quiet Rooms Multi-use spaces for rest and recovery, quiet contemplation should be considered.
These should be non-bookable with vacant/in-use sign on door. The décor should
be conducive to relaxation and should be designed with multiple use in mind.
4.4 Space Standards
UWE has a Space Standards Guide that is used as a guideline when calculating space needs.
Space standards recognise differing space needs according to use and subject area. These
standards are not prescriptive but are a baseline for high level modelling. The standards are
rarely used in isolation and other issues (e.g. the building structure/layout building) and
specific operational requirements will be considered. Consult the space management team
who will assist the project team to apply these standards, especially for teaching areas.
4.4.1 Space Allocation
Office Space Space min m2 / person Notes
Single Office with Meeting Space 12 - 15 Designated Senior Staff or other specific requirement
Single Office 9 As above
Shared / Open Plan Office 6.5 Staff
Meeting Area in Open Plan 2.5 Where group-working is a necessity
Meeting Room 2.5
Additional Administrative
Space
Space min m2 up to
3,000 students
Notes
Student facing administrative
space
50 (+10 m2/extra 1,000
students)
Includes reception and hand in areas
Social Spaces m2 per person
Restaurants / Cafés – dining areas 0.2
Restaurants / Cafés – kitchens 0.17
Communal areas – students 0.7
Communal areas – staff 0.9
UWE Design Guide for Buildings
C h a p t e r 4 | S p a c e S t a n d a r d s I s s u e 1 . 3 P a g e | 6
4.4.2 Notes on calculating space requirements
Office Space: An allocation based on the types of staff, the actual staff numbers except
for job share, hourly paid lecturers and other ‘hot deskers’.
Teaching and Specialist Space: Allocations based on teaching delivery requirement and
open access learning space / laboratory or other specialist requirement. Please refer to
UWE’s Space Manager on the latest standard for specialist spaces.
Please note that the sizes specified for office space are not necessarily an entitlement but an
overall measurement for different categories of staff per organisational unit.
Storage should initially be considered as part of the allocation for office space. Additional
space and storage requirements may be considered on an individual basis. For example, to
give room for carers or space for a small personal fridge for medication etc. Offices must be
designed with some spare capacity to cater for future, reasonable adjustments.
4.4.2.1 Ensuring space allowances support accessibility
UWE recognises that some staff and students need assistive equipment or support (e.g. a
personal assistant or guide dog). Space standards are the minimum space/person.
Additional space will be made available where required and the design guide requires that
spaces are flexible enough to accommodate future changes.
4.5 Room numbering
Room numbering within a building must be correct, consistent and clearly identifiable.
Room numbers assist people in finding their way around a building and link to systems
and data relating to fire alarms, asset management, maintenance works requests and
asbestos. Room numbering confusion could cause problems in managing these issues.
The Space Management Team will allocate room numbers and has produced a Room
Numbering Policy (SPP3, click ‘SPP3’ to see it) which must be strictly adhered to.
The topography of the Frenchay campus poses challenges for room numbering (and at
first glance can appear counter-intuitive). However, a slice through the campus would
find all floors at the same elevation given the same number.
Under no circumstances can any staff (internal or external) assign their own numbers.
UWE Estates and Facilities Design Guide
Chapter 5: Fabric & Structural Design
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1
Table of Contents
5.1 Introduction ................................................................................................................ 3
5.1.1 Designing for flexible use ...................................................................................... 3
5.2 Furniture and furnishings ............................................................................................. 4
5.3 Accessibility of Student Accommodation ........................................................................ 4
5.4 Structural details ......................................................................................................... 5
5.4.1 Structural engineering ........................................................................................... 5
5.4.2 Imposed Loads and Performance ........................................................................... 5
5.4.3 Foundations ......................................................................................................... 6
5.4.4 Structural Form .................................................................................................... 6
5.4.5 Timber Frame ....................................................................................................... 6
5.5 Circulation Principles .................................................................................................... 7
5.5.1 Building Entrances ................................................................................................ 7
5.5.2 Reception ............................................................................................................. 7
5.5.3 Steps and stairs .................................................................................................... 7
5.5.4 Horizontal circulation ............................................................................................. 8
5.5.5 Vertical circulation ................................................................................................ 8
5.6 Sustainable Material Selection ...................................................................................... 9
5.7 Building fabric and envelope ...................................................................................... 10
5.7.1 External Envelope ............................................................................................... 10
5.7.2 Roof (including rooflights) ................................................................................... 10
5.7.3 Roof lights ......................................................................................................... 11
5.7.4 Windows ............................................................................................................ 11
5.7.5 External Doors .................................................................................................... 12
5.7.6 External Finishes................................................................................................. 13
5.7.7 Rainwater Goods ................................................................................................ 14
5.8 Internal Finishes ....................................................................................................... 15
5.8.1 General Provision ................................................................................................ 15
5.8.2 Internal Walls & Doors ........................................................................................ 15
5.8.3 Plasterboard ....................................................................................................... 17
5.8.4 Tiles .................................................................................................................. 17
5.8.5 Suspended Ceilings ............................................................................................. 17
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2
5.8.6 Flooring ............................................................................................................. 18
5.8.7 Painting ............................................................................................................. 20
5.8.8 Vision Access/visual contrasts .............................................................................. 20
5.8.9 Acoustics ........................................................................................................... 20
5.8.10 Fixtures and Fittings ............................................................................................ 20
5.9 Provision for storage, deliveries and movement of materials ......................................... 21
5.10 Catering design ......................................................................................................... 21
5.10.1 Lessons learned .................................................................................................. 22
5.10.2 Production Kitchens ............................................................................................ 22
5.10.3 Deli/Café/Bar Style Operation .............................................................................. 23
5.10.4 Vending Operation .............................................................................................. 27
5.10.5 Tea Points .......................................................................................................... 28
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 3
5.1 Introduction
Chapters 1, 2 and 3 of this Design Guide set out the overarching principles and functional
requirements for this design guide. All designers should familiarise themselves with these sections.
Each project will have specific requirements, limitations, challenges, and opportunities that affect a
project’s cultural, environmental, technological, and aesthetic contexts.
The client faculty or service will have their own vision of the end result. While wanting to satisfy
those expectations, practical issues and design or construction constraints may require those initial
concepts to be reviewed and revised. To provide confidence and mitigate surprises, the Designer will
arrange regular meetings with the stakeholders to communicate progress and explain and discuss
design development.
This guide must be read in conjunction with the UWE’s Standard Specification. UWE will consider
alternative products if the change is considered to be for the better and provides acceptable life cycle
costs and resiliency, including ease of maintenance and availability of replacement components. The
derogation process (explained in Chapter 2.0) shall be used to help manage the process.
The UWE is a progressive University and welcomes the use of new technology after the balance of
risks and benefits have been established and evaluated.
5.1.1 Designing for flexible use
To provide flexible space, Designers should assume future changes in use and internal layout but not
at the expense of appearance, acoustics, thermal capacity or stability. The requirement for flexible
spaces will obviously influence the structural form, and lead to the use of non-load bearing internal
walls where practicable.
There will need to be ample accessible service routes to accommodate future alterations or expansion
of services as technology and teaching techniques evolve. Raised floors and/or generous supply of
floor ducts is to be included with all projects to avoid trailing leads and to assist with future alterations
and flexibility of room layout.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 4
5.2 Furniture and furnishings
The Faculty/Client will lead in the selection of furniture and furnishings. The package may be removed
in all or part from the building contract in order for the client to manage. The Designer will liaise with
the client accordingly and provide advice and practical guidance as necessary.
As alluded to in Chapter 1 of this Design Guide, the choice of furniture and furnishings impacts on
the student experience, influences how flexible and accessible a space is and alters perception of
the space. There will be variation in furniture/furnishings in social and learning spaces.
Designers must ensure internal spaces have flexibility to accommodate a choice of furniture
arrangements to suit a range of users. There should be a choice of seat, bench and desk/workstation
heights (including sinks and fittings), with and without arms/backrests and visually contrasted from
room finishes. Sink fittings are to be operable by someone with reduced manual dexterity. Experience
has shown that the colour of furniture needs to be considered alongside the colour/quality of lighting:
The light can radically alter perception of furniture colour.
Tables, desks and seating to be movable and designed to enable disabled users to sit with colleagues,
particularly in canteen/refectory areas and common rooms. Some seating should be more enclosed,
providing more privacy or a quieter area.
Furniture in offices should strive for more conformity, and the UWE preference is for 1600mmx800mm
straight desks with under-desk pedestals. The inclusion of sit/stand workstations helps make the
environment more widely accessible.
5.3 Accessibility of Student Accommodation
All the principles set out here, and in the rest of the Design Guide, are equally applicable to student
accommodation. Specific requirements are needed to ensure that accommodation is accessible:
A suitable number of rooms should be accessible or can be readily remodelled as accessible
accommodation. Generally, this should represent 5% of the bedrooms, but will be influenced
by the Equality Impact Analysis. For ease of access these will normally only be provided at
ground floor level.
These rooms will need to be large enough to accommodate assistive equipment and personal
assistants and have level access ensuite shower rooms.
Shared use wheelchair accessible kitchens will be required in these flats.
Residents will be able to manage the temperature of their own rooms.
Accessible bedrooms and ensuite ceilings are to be capable of supporting a tracked hoist, with
pre-fitted fused spur power point at high level. These may be retrofitted at a future date.
The consequential structural requirements are discussed later.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 5
Vibrating pillow/mattress and visual/audible fire alarms may be required in bedrooms. This
will be determined by the Personal Emergency Evacuation Plan (PEEP). Please see the
electrical engineering chapter for more details.
5.4 Structural details
5.4.1 Structural engineering
It is imperative that during the feasibility stage for alterations to an existing building consideration is
given to how potential structural changes may affect the stability of a building. The level of complexity
must be taken into account when assessing the level of professional competency required to
undertake the structural survey and subsequent design. Engaging appropriate professionals at the
earliest opportunity is paramount. The entire feasibility of a project could be decided on the outcome
of their investigation.
5.4.2 Imposed Loads and Performance
In general, loading will be in accordance with the appropriate current standards. Flexibility in use is
a key requirement. Open plan areas should be designed with the capacity to accommodate additional
partition walls which may be required in the future and that office space may change to meeting
rooms etc. UWE therefore encourages a large grid and as large as possible finished floor to finished
ceiling height commensurate with a reasonable cost.
With office accommodation, floors should be designed so that filing cabinets can be positioned mid
span, away from external walls.
If permitted within Town and Country Planning rules, and where structurally/economically feasible,
additional capacity should be included so that it is possible to increase the height of the building by
subsequently adding additional storeys.
Student accommodation designated for current or future disabled students and disabled toilet facilities
are to be appropriately designed (in terms of ceiling height and structure) for the fitting of personal
hoists (or retro-fitting if there is no current demand). Ceiling fixing for hoists is preferred to the use
of a steel gantry.
The structural capacity of roofs should allow for the opportunity to add additional plant without having
to undertake subsequent structural work.
Structural information must be incorporated within the handover documents. Typically this is in the
form of the ‘key structural principles’ section of the health and safety file with cross-referencing to
relevant drawings.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 6
Ground floor circulation spaces should be capable of supporting and storing mobile plant with the
safe loading details clearly identified within the handover documents (e.g. a floor loading diagram
within the access and maintenance strategy).
5.4.3 Foundations
A ground investigation report is a prerequisite to any detailed foundation design. Sustainability and
holistic thinking should come to the fore; for example, passive design options such as ground source
heat pumps could be incorporated.
Consideration must also be given to temporary measures to stabilise ground when excavating around
existing buildings, and bridging details around services.
As mentioned earlier, where practicable foundations are to be designed to accommodate additional
storeys which can be added in the future.
Lift pits are to be suitably designed to prevent any ingress of ground water entering the pit or
adversely affecting the lift shaft components. Suitable detailing during foundation design is preferred
to subsequent tanking remedies.
5.4.4 Structural Form
The design team will produce a report on the options for the superstructure which will be based on
the recommended foundation design solution. A further report will be required once the option has
been decided, detailing load paths and mechanisms. The report will form part of the building design
documentation required.
The University is not adverse to the use of prefabricated elements such as bathroom pods, for
example. However, evidence will be required to demonstrate how quality will be assured in the off-
site manufacturing process. Furthermore, future maintenance/replacement of these pods would need
to be carefully considered and explained in access and maintenance strategies.
Use of pre- and post- tensioned and cantilevered elements should be the subject of a risk evaluation
(within a design risk register) to ensure that future adaptations/demolitions can be undertaken safely.
5.4.5 Timber Frame
Due to the risk of fire, a risk evaluation (typically within a design risk register) is required for any
proposed timber framed structures on UWE sites.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 7
5.5 Circulation Principles
5.5.1 Building Entrances
See comments on external doors, later.
Ensure that entry control communication units are visual as well as audible and can be accessed
from both a standing and seated position.
Avoid separate entrances for disabled users. In practice, this may mean we would not have
revolving doors and a separate disabled entrance. Instead, designers could create a small lobby
with 2 automatic doors which everyone can use.
Doors must not have ‘lips’: They create a barrier to wheelchairs and can be a trip hazard.
5.5.2 Reception
Ensure Reception desks are accessible to all users, including operation by disabled members of
staff. This is often and simply achieved by providing a seated working position for reception staff
and level access to desks.
Where possible, avoid providing a separate lowered section at one end for wheelchair users and
make the main part of the counter accessible to all.
Provide enhanced lighting, acoustic treatment and hearing enhancement system to counter area.
5.5.3 Steps and stairs
Lips shall be used on the side edges of steps where there are gaps between the step and the wall
– to prevent sticks and crutches from slipping off the step or materials falling.
If possible steps shall be removed from the design (except for protected stairs between floors).
Steps with associated ramps are acceptable (please note that steps may aid the mobility of those
using leg prostheses for whom ramps can be problematic).
All steps need handrails on both sides.
The contrast strip shall be on the nosing of the step (not before it).
Stair risers shall be solid (no floating stairs).
Glass must not be used for the tread or riser of stairs. Great care shall be used when considering
the use of glass for the sides of stairways.
Consideration shall be given to recessed lighting of steps (lighting is discussed elsewhere)
Although students at UWE are adults, the facilities are open to the general public who may be
accompanied by young children. The design of the stair guarding should reflect this. Approved
Document Part K section 1.1.19 refers.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 8
5.5.4 Horizontal circulation
Where feasible, width of corridors should permit wheelchair users passing in two directions.
Consider chamfering or angling corners to facilitate wheelchair user turning and to enable deaf or
hard of hearing users to see others approaching.
Corridor doors will be fitted with hold open détentes and power assisted opening devices.
Doors should not have ‘lips’: They create a barrier to wheelchairs and can be a trip hazard.
Avoid use of digital keypads: UWE normally requires swipe card access (see the security strategy
in Chapter 3).
5.5.5 Vertical circulation
For short rises and ease of maintenance, ramps are preferable to lifts, if gradients are shallow
and lengths are not excessive or circuitous.
Install passenger lifts larger than the minimum 1100mm x 1400mm in Part M wherever possible,
to facilitate wheelchair turning within the lift.
Fold-down stairclimber platform lifts are not recommended as they can obstruct the clear width
of stairs and compromise means of escape.
Freestanding enclosed vertical platform lifts to be not less than Part M 1100mm x 1400mm
minimum size, with power assisted doors. The lift must be able to take the load imposed by
motorised mobility aids.
Enclosed platform lift controls to have single press button operation, so that users are not required
to keep continuous pressure on the button for the full extent of travel.
All lifts should be operable independently without requiring staff assistance. These should be
evacuation lifts where possible: See the electrical engineering chapter for more details.
As explained elsewhere, it is important that push button devices are positioned in close and
sensible proximity to the door they operate: Individuals cannot be expected to dash from the
button and the door. Unfortunately, this item has to be included in light of lessons learned.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 9
5.6 Sustainable Material Selection
In addition to selecting materials to fit the brief and, as are outlined elsewhere in this document,
designers shall also take account of the sustainability impact of the materials selected. This entails
taking a life cycle perspective regarding the choice of material, i.e. from cradle to end-of-life or
preferably cradle-to-cradle (which means considering the reuse of the material).
To support our sustainability commitments, UWE requires designers to follow the principles below:
Consider the source of materials – locally sourced generally being preferable
Consider the reputational risks associated with extraction activities
Consider the embodied carbon of materials selected
Minimise waste on and off site
Plan for the reuse of materials produced as part of the construction phase
Make use of reused or recycled content in construction materials.
Use materials with ease of repair, maintenance and end-of-life dismantling in mind
Minimise the use of toxic and/or polluting materials in the design
Be able to report environmental impact, recycled content and embodied carbon of materials
Materials supply to comply with all applicable legislation throughout its supply chain
Materials should be sourced/produced under internationally acceptable environmental, social and
ethical guidelines and standards (for example, FSC for timber).
UWE encourages all designers to use A rated materials/products from the BRE Green Guide to
Specification wherever reasonably practicable, and in addition to use materials in accordance with the
RICS SKA HE assessment tool.
UWE advocates the use of high density polyethylene (HDPE) over PVC, apart from in the case of
underground ducts. The designer will need to consider an array of factors to select/specify the
appropriate material for underground pipework.
The supply chain will ideally evidence conformance to ISO14001, EMAS or equivalent.
To support our sustainability commitments, UWE requires designers to specify materials that are
robust to the wear and tear of an institutional facility. Frenchay is an exposed site and masonry must
have good resistance to moisture, frost and not susceptible to staining.
The cost and risks of maintenance and cleaning must be considered. Pre-finished materials are
preferred to materials which require painting or other ongoing cyclic maintenance activities.
Apart from aesthetic reasons, materials selected for the external fabric should not be prone to fading
when continually exposed to the elements (timber and copper are obvious exceptions). Materials
should be resistant to degrading as a result of exposure. Likewise, all exposed elements should be
easily cleanable.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 0
5.7 Building fabric and envelope
Building segregation is to be considered at design stage – keeping teaching spaces and offices in
separate zones to enable areas to be zoned off during holidays. This also extends to fire stopping
(discussed elsewhere) and compartmentation, which should be an integral consideration of the design
and installed as early as possible. Retrospective fire stopping can leave a poor aesthetic finish and
means the building has been vulnerable to fire spread for much if not all of the Construction Phase.
The performance at all junctions and intersections will be maintained. All openings within the envelope
are to be compatible visually and technically with the external walls.
Further guidance on the use of insulation materials is given in the LPC Design Guide for the Fire
Protection of Buildings 2000.
5.7.1 External Envelope
The materials selected for the envelope must be robust, readily available, preferably obtainable locally
with a minimum life span of 60 years and not subject to early surface deterioration. This is especially
relevant when selecting a facing brick. Plastic coated products are to be avoided unless the durability
of the coating has been proven and is protected by a sound warranty.
5.7.2 Roof (including rooflights)
The roof structure shall be designed and installed in accordance with the wind loadings and exposure
conditions and particularly at Frenchay Campus which is particularly exposed. Weather tightness, high
insulation and vapour control performance will be maintained across all roofs, including interfaces
with external walls.
Wherever possible, designs should prevent the need for access onto roofs. If routine access is
required to a roof a fixed means of access must be provided. UWE’s preference is that access should
be via a stairway (e.g. extension of the stair core) rather than ladder. Level, stable routes should be
provided over roofs (e.g. a walkway of suitable construction fitted on to a profiled roof system).
Locks should only be operable by designated, off-suite keys.
A detailed risk evaluation is required in the following circumstances:
Access is to be via a ladder rather than stairs
Fall restraint system is required. If so, the installation must be a Latchways system and positioned
so that it requires the use of a 1500mm lanyard, it must be compliant with Part L, it must be
accompanied by a calculation package, design life must be not less than 25 years, all components
should be stainless steel and installers must be approved by the system supplier.
Access to the roof is via a trapdoor/ opening roof light.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 1
Fall arrest equipment is not to be used on roofs at UWE.
Permanent fixed guarding is the preferred edge protection.
Roof drainage is to be designed in accordance with BS 12056-3:2000.
5.7.3 Roof lights
Roofs which are partially or entirely glazed should be designed to prevent breakages or a fall.
UWE will never commission or accept a walk-on glazed roof (while accepting they are technically
feasible, the University sees no reason to incur the expense and residual risk).
Upstands, non-fragile surfaces and, where necessary, handrails should be used to prevent people
inadvertently walking or falling onto (and falling through) glazed roofing. Signage and demarcation
of designated routes may be used to supplement the preceding measures.
Designs should minimise the need to clean gutters and rainwater goods and glazing to roofs. The
access and maintenance strategy should explain how this will be done.
Designers must consider maintenance access to control gear and operators for roof lights or vents.
As explained in the Chapter 2, these should be accessible from a place of safety (e.g. on a protected
roof, with no risk of falls). The access & maintenance strategy (described in Chapter 2) must explain
how glazing panels will be replaced in the event of breakage.
When replacing slate roofs or installing a new slate roof, subject to Listed Consent and general
Planning conditions, consideration should be given to the use of artificial products with high levels of
recycled content. This may be specifically relevant to the Glenside campus.
5.7.4 Windows
Windows are to be pre finished with no need for subsequent cyclic maintenance such as
painting/staining or sealing. UPVC window systems must be avoided.
The design of the windows should permit cleaning of the external glass to be undertaken from within
the room if possible, or by pole fed systems externally. The window cleaning methodology is to be
included in the access and maintenance strategy.
In mechanically ventilated buildings, opening windows are to be restricted to 150mm max. In
naturally ventilated buildings windows this shall be 300mm max. If there will be vulnerable users
(e.g. a nursery), the opening must be 100mm max. Ironmongery to be robust, suitable for
institutional use and subsequently available for the recommended life of the window.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 2
Silicon is only to be used as a secondary form of sealant, not the primary form of weatherproofing.
It should be possible to reach and operate the control of openable windows, skylights or ventilators
in a safe manner (i.e. people are not at risk of falling). Where this is not possible due to an obstacle
or excess height, tele-flex or similar control gear is to be provided. Where there is a danger of falling
from height, tamper-proof devices should be provided to prevent the windows opening too far.
No window, skylight or ventilator shall be positioned when opened which is likely to expose any person
to a risk to their health or safety. Open window, skylight or ventilators should not project into an area
where persons are likely to collide with them. The bottom edge of opening windows should normally
be at least 800mm above floor level, unless there is a barrier to prevent falls.
Manifestation, preferably in etched glass, to be used wherever there is a risk of collision of persons
or where modesty may be compromised. For example, floor-to-ceiling external windows or glass
balconies could potentially pose a threat to the dignity of someone wearing a skirt or shorts.
The function of the room is to be considered at the design stage to facilitate the appropriate level of
privacy. Permanent obscured glazing should be used rather that retrofitted films.
Daylight glare to be controllable by blinds.
5.7.4.1 Large glazed panels
Glazed panels should be sized to allow replacement to be undertaken using simple manual handling
techniques with simple mechanical lifting aids. The need for the use of cranes, even ‘spider’ mini-
cranes, to replace panels should be avoided wherever possible. If a designer believes (on balancing
the competing design considerations) large panels are the best design solution, it must be discussed
with the Principal Designer and recorded in the ‘design risk register’. The access and maintenance
strategy should also detail how this operation would be carried out.
5.7.5 External Doors
Robust external doors will be provided to all entrances and means of escape positions. Additional
doors will be required to plant rooms and refuse areas. Typically, main entrances will be double
doors, fully glazed, automated (operated by sensors and push button controls) and have level access
wherever possible. Buttons must be in close proximity to the doors.
Doors on a maintenance route must be wide and high enough to accommodate any necessary mobile
plant which has been considered necessary for subsequent maintenance activities.
Access control, currently card reader system, to be fitted to enable doors to be secured as and when
needed, such as out of hours. Chapter 3 explains the UWE security strategy and please refer to the
separate Chapter 8 details the IT infrastructure needed to support the strategy.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 3
Fittings and ironmongery are to be of a high quality, robust stainless steel. Lock cylinders to be euro-
profile on UWE Kaba master Suite.
PVCU external doors must be avoided. Where doors are fully glazed, the door is to have a mid rail to
resist twisting and reduce subsequent re-glazing costs. The rail at the door head is to have a minimum
depth of 150mm.
Doors must not have ‘lips’: They create a barrier to wheelchairs, trolleys etc. and can be a trip hazard.
The factory applied colour to steel or aluminium doors is to be resistant to fading, this particularly
applies to the UWE red.
5.7.6 External Finishes
5.7.6.1 Cladding
Cladding to be lightweight with high thermal performance and good aesthetic appearance. The chosen
finish should mitigate solar gain and consideration should be given to the careful use of colours.
The cladding system is to be integral with the glazing system with a minimum 40 year lifespan. The
system is to be suitable for exposed conditions with stainless steel fixings.
Silicon is only to be used as a secondary, and never the primary, form of sealant.
UWE has trialled and pioneered the use of pre-fabricated straw bales into R Block 2. Amongst other
benefits, it is a highly insulating product and this approach should be considered in future designs.
In order to facilitate construction and replacement, cladding panels must be in unit sizes to allow easy
handling using readily available plant/equipment and trade skills. The need for a crane during
subsequent replacement of any parts should be avoided wherever possible. If a designer believes
(on balancing the competing design considerations) large panels are the best design solution, it must
be discussed with the Principal Designer and recorded in the ‘design risk register’. The methodology
must be included in the access and maintenance strategy within the health and safety file.
The design of the system should consider independent removal of individual panels to allow for
maintenance and replacement of damage and insertion of additional openings for new windows etc.,
or to allow working access for future refurbishments of upper floors.
If may be foreseeable that during the life of the building, high level access will be required on the
external façade of a clad building. An access and maintenance strategy and design risk evaluation
(contained within the ‘design risk register’) should confirm what access is required and what access
equipment is to be used, particularly if it is not possible to tie in.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 4
If timber cladding is to be used, designers must consider the flammability of the cladding and ensure designs and specifications (e.g. off-site impregnated treatment (not coating which discolours timber and requires re-coating)) limit the risk or extent of loss due to fire. BS9999 offers some further information about the management of the fire risk posed by timber cladding.
5.7.6.2 Curtain Walling
Curtain walling to be of good aesthetic appearance with passive measures to reduce solar gain if
necessary (such as brise soleil, overhangs) and specialist glazing. Transoms and mullions to give clear
sight lines and be integral to system used.
The design should comply with the recommendations of the Centre for Window and Cladding
Technology (CWCT) ‘Standard for systemised building envelopes.’ with particular regard to;
• Internal and external environment
• Air permeability
• Thermal performance
• Access and safety
• Design life
5.7.6.3 Render
Render to be to current British Standards and be fully bonded to substrate with a good appearance
and colours to be sympathetic to surroundings. The render is to be self-coloured. The surface is not
to attract dirt and debris and is to be easily cleanable with low pressure water.
Detailing of adjacent cills, capping, flashings etc., to prevent moisture penetration. Roof overhangs
to be of sufficient dimensions to avoid “drip” staining.
Where external wall insulation is to be utilised the protective render is to be self-coloured, sufficiently
robust to resist light impact damage and when damage has occurred, easily repaired without the
need for specialist equipment or expertise. In the long term, the system should allow over painting.
5.7.7 Rainwater Goods
UWE prefers the use of cast aluminium or iron rainwater goods. If, on balancing different design
considerations, plastic is preferred, high density polyethylene (HDPE) is preferred over PVC.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 5
5.8 Internal Finishes
5.8.1 General Provision
• Robust durable finishes appropriate to each functional space.
• For renovation projects, consider the building’s character and existing finishes. All material
patches should blend as closely as possible. Some buildings on campus have an existing palette
that must be matched. Coordinate with the UWE PM.
• All specified materials must demonstrate suitability for use in an institutional setting, with similar
regularity of cleaning and maintenance.
• Colour-through homogeneous materials are preferred.
• Avoid material(s) that require routine sealing or significant specialized maintenance.
• O&M documents must clearly identify and note all finishes, including extent of coverage.
• Stencil fire rating above ceiling at all fire-rated walls, in 150mm high letters at 6m centers.
• All finishes must complete curing & drying (off-gassing) prior to Substantial Completion
5.8.2 Internal Walls & Doors
Internal walls shall be designed and constructed so they provide a secure and stable partition between
areas and spaces throughout the campus. The type and nature of any internal wall will have to be
discussed and agreed by UWE Estates prior to construction, and this will be based on the general
location, use of the room / area and the possible need for future flexibility.
Where block work is to be used, blocks should not weigh more than 20kg to reduce manual handling
risks during construction or subsequent alterations. A risk evaluation (contained within the ‘design
risk register’) is required if a designer wishes to specify blocks in excess of this weight.
Consideration to be given when constructing new stud partitions to incorporate additional support
battens for the UWE Toprail support system (or radiators etc.). When constructing corridor walls, fire
resistance, durability, robustness and good sound resistance is essential. If masonry corridor walls
cannot be provided (it is the UWE preference that corridor walls are masonry), 9.5 mm plywood can
be included behind the plasterboard to provide added resistance against penetration damage.
Internal doors will be provided to provide safe and effective access through all internal spaces and
escape routes. Doors and ironmongery are to comply with all current Building Regulations, Approved
Document part M and BS 8300.
Where doors form part of fire compartment they should fully comply with the requirements of BS9999
and provide equal protection to the surrounding walls. Corridor and main circulation doors to have
hold open devices linked to and released on fire alarm activation.
Doors must not have ‘lips’: They create a barrier to wheelchairs, trolleys etc. and can be a trip hazard.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 6
Timber doors are to be self-finished to negate the need for subsequent redecorating. The head rail is
to have a minimum depth of 150mm.
Fittings & ironmongery are to be of a high quality finish, robust stainless steel. Locks to be of a
suitable profile to fit UWE Kaba 20 cylinders.
Where doors (or gates/shutters etc.) are powered they must ‘fail safe’. The electrical design guide
provides details of the required interface with the fire alarm system.
Fire doors in corridors and circulation spaces are to be held open with magnetic hold back devices
which release automatically when the fire alarm is activated. If doors need to be closed, a powered
door is the preferred solution. If this is not practicable then low resistance closers should be utilised.
UWE is willing to trial free-swing door closure devices following an evaluation of cost/risk vs benefits.
All fire doors and frames are to be manufactured and installed as a single unit and appropriately
certified before hand over.
If half-height internal walls are used (typically used to demark zones or functional areas in robotic or
engineering buildings), they should either be short enough that someone in a wheelchair can look
over or vision panels etc. should be positioned at appropriate points.
5.8.2.1 Physical Locks
Physical key locks are used across UWE. UWE deploy a system of suited locks in order to manage
and maintain suitable access. Any locks being installed must be agreed with the Security Systems
Team to ensure the correct suite is being used. See the Chapter on IT infrastructure for information
about door access control.
Physical locks are to be installed, as a minimum, on the following doors:
All external doors including those with access control
All internal perimeter doors including those with access control which mark the perimeter of a
Faculty/Service area, e.g. HAS internal perimeter doors
Offices
Cleaners’ cupboards
Lecture Theatres
Plant rooms
Comms rooms
Workshops
Laboratories
High risk rooms including those with access control
Other rooms as discussed and agreed with occupying clients and dependant on site specific use
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 7
5.8.3 Plasterboard
• Plasterboard must not be used on ceilings without UWE’s express permission (as it has historically
concealed pipework etc.)
• If it is permitted, adequate access provisions shall be made.
• Where pipes and cables are boxed in access must be provided.
• Plasterboard should meet WRAP requirement for recycled content.
• Plasterboard wall linings are not deemed suitable for high trafficked locations (i.e corridors),
communal areas (i.e. social spaces) or student accommodation. Plasterboard wall linings should
be assessed for suitability, but restricted to teaching, learning or office areas, unless otherwise
authorized by UWE Estates.
• Consideration should be made for ply-backed detailing or alternatively the use of wall-board.
• Wet areas and/or tile backer board:
Use cement backer board for tile.
Paper-faced moisture resistant gypsum board panels are not permitted.
5.8.4 Tiles
5.8.4.1 Floor Tiles
Cross-fall finished floor to floor drains.
Maintain adequate substrate to prevent lifting of tiles due to thermal dynamic movement of hidden
services.
Glazed or polished tiles are prohibited.
5.8.4.2 Wall Tiles
Colour contrasts to comply with BS 8300 (see visual contrast, elsewhere).
Ceramic floor and wall tiles should not be used in wet areas (including kitchens, laundries and
academic areas requiring high levels of hygiene). Instead, UWE prefers the use of vinyl safety
flooring and flexible vinyl systems. The solution can also include a vinyl ceiling finish (see below).
5.8.5 Suspended Ceilings
Ceilings should be designed to be easily accessible for maintenance and other access
requirements, such as future technology installations. The depth of void must be adequate to
accommodate integrated light fittings and the layout of the grid must align with M&E design.
Ceilings within a wet, humid or hygienic environment including areas that require regular cleaning
will have a product selected to suit the conditions. This can include interlocking vinyl planks.
Tile size (unless planks) generally will be 600 x 600 with painted perimeter shadow batten.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 8
5.8.5.1 Voids created by suspended ceilings
The void created by a suspended ceiling should be 600mm minimum deep under flat structural soffits
in order to accommodate services. This distance can be reduced depending on the nature of services
with the void: Mechanical and electrical designs must be co-ordinated with the fabric/structural
design to inform these decisions.
5.8.6 Flooring
• Approved flooring systems and products for specific locations and uses are provided in the UWE’s
Standard B&CE Specification.
• In general, flooring (both internal and external) shall be non-slip (even when wet).
• Flooring must comply with general provisions in BS8300.
• Flooring shall not “turn up” the wall more than 150mm without a colour change.
• Building entrance: Primary & secondary walk off barrier matting with metal trim as applicable.
• Lift floors: Rubber tiles, classified under EN 685 for heavy use (standards 23,32 and 41).
• Wet laboratories: Use chemical resistant flooring (also see comments in ‘specialist areas’, below).
• Stair Treads & Risers: Colour contrasts to comply with current guidance.
5.8.6.1 Specialist areas
Due to the diverse range of activities undertaken at UWE, there will inevitably be circumstances when
standard flooring solutions are inappropriate. Examples: In one workshop there was the potential
for freshly welded metal or droplets of molten metal to come into contact with the floor. Potentially,
some substances may be handled which require or prohibit the use of very specific floor finishes.
Following the UWE project processes will help the team to arrive at a considered and suitable solution:
The project brief will establish anticipated teaching activities. The implications for design and
specification must be established through discussion (e.g. the weight, temperature or physio-
chemical properties of materials or substances etc. that may come into contact with the floor).
Flooring solutions should be identified that meet the demands/constraints.
Technical data and samples of bespoke products should be obtained and discussed with the client
and cleaning services. The faculty may need to adopt specific management arrange-ments for
the floor, leading to changes in risk assessments or standard operating procedures.
Potentially, there may be a mixture of bespoke floor finishes through a technical area. The
reasoning behind the various selections may be lost over time and eventually activities may
change, meaning that the chosen floor surfaces become inappropriate. Handover documentation
should explain why the various, bespoke floor surfaces were chosen. This might be conveyed in
a simple, annotated plan included in the O&M information.
The HSE slip assessment tool (http://www.hse.gov.uk/slips/sat/index.htm) should be used if there is
doubt about the ability of a bespoke product to reasonably prevent slips and provides information
that can help influence cleaning regimes or faculty operating procedures.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 1 9
5.8.6.2 Raised floors
No raised floors at UWE must be classified as light under the MOB PF2 PS standard (or BSEN 12825
Class 1 and 2). The majority of office and teaching spaces will be MOB PF2 PS medium standard (or
BSEN 12825 Class 3 and above). Circulation spaces may need to be MOB PF2 PS heavy standard (or
raised floors may be inappropriate) depending on the anticipated loads. See ‘imposed loads and
performance’ earlier. Any raised floor should be a minimum distance of 250mm from floor finish to
structural floor to allow for services.
5.8.6.3 Prohibited flooring materials
Specialty flooring: bamboo, cork and laminate.
Wood flooring, except at gymnasiums and certain other specialized functions.
Masonry flooring: Not permitted if it has significant fill and/or requires routine sealing or significant
specialized maintenance.
5.8.6.4 Carpeting
For offices, circulation spaces and lecture rooms carpet tiles is the preferred option. Details are
provided in the Standard Specification.
Any existing carpeting removed for renovation must
be recycled where possible. Justification must be
provided for non-compliance.
Construction; Solution dyed, bleach proof nylon
construction. The use of polypropylene pile carpet is
to be avoided.
Minimum manufacturer’s warranty for wear, edge
ravel, tuft bind, delamination and static control:
o Barrier matting: 5 years
o Offices, teaching rooms and other areas: 10
years.
UWE wishes to avoid staining around drinking
fountains due to leaks and spills (as shown to the
right). The choice of fountain and selection of floor
covering should limit these unsightly stains.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2 0
5.8.7 Painting
• Manufacturers, products and colour ranges are to be restricted to the palate given in the UWE’s
Standard B&CE Specification.
• The UWE will consider the use of water based undercoat and gloss finishes where appropriate.
5.8.7.1 Teaching Walls
In teaching spaces, teaching walls (i.e. the walls on which images will be projected etc.) must be
00NN 16/000 – Grey. This helps to accentuate the screen and is of great benefit to students with
certain cognitive and visual impairments.
5.8.8 Vision Access/visual contrasts
The need for contrasting colours between floors and walls and doors; stair treads and risers;
doors and handles; walls with switches/sockets etc. is well established.
While the UWE standard specifications support effective contrast, it is incumbent on designers
to review colour contrast of adjoining materials and seek advice if in doubt.
Busy, highly patterned surfaces to be avoided.
Columns can be at risk of ‘blending in’ to the background and may need manifestations to ensure
they are visually distinct.
5.8.9 Acoustics
Provide appropriate acoustic absorbing surfaces to teaching and meeting spaces and in particular
to reception, refectory, assembly and sports/leisure areas where there are hard surfaces and
reverberation.
Ensure adequate sound resistance of structure to ensure acoustic separation, particularly between
teaching spaces, interview rooms, residential accommodation and performance areas.
5.8.10 Fixtures and Fittings
UWE buildings will require ‘Toprail’ flexible wall furniture system in teaching rooms, offices and
specific corridor locations (to solid or suitably reinforced stud partition walls only).
Notice boards located within corridors or escape routes are to be enclosed.
Specialist fixtures and fittings for science laboratories, computer laboratories, engineering
workshops etc. will be specified separately according to building/room use. However, designers
are invited to bring their expertise forward and suggest solutions.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2 1
5.9 Provision for storage, deliveries and movement of materials
Through consultation with stakeholders, design teams must establish the storage and delivery
requirements. Lack of storage is a frequent source of frustration. Different faculties and services
have different requirements. In some cases, storage (e.g. for hazardous substances) must be secure
and have a range of other controls and precautions (e.g. alarms, general or forced ventilation etc.).
In relation to deliveries, the access and maintenance strategy should set out where and how materials
will be delivered to the building. Design teams will need to consider:
Catering supplies
Teaching materials
Stationary supplies and office equipment (including desks and photocopiers)
Materials required for routine maintenance and life cycle redecoration/refurbishment
Such considerations are likely to inform the size of lifts and specification of doors (such as double leaf
or leaf-and-a-half) especially into plant areas, on main access routes etc.
5.10 Catering design
An attractive, varied and efficient catering experience supports many of UWE’s overarching priorities,
as set out in Strategy 2020 and other strategic policies. Specifically, it promotes (amongst other
things):
Positive student experience
Wellbeing of staff and students
Inclusivity by meeting varying dietary needs and requirements
Value for money (e.g. through more efficient services or by designing catering facilities that can
be changed to respond quickly and cheaply to changing food trends)
Hospitality and catering are one of Estate’s key stakeholders (as described earlier in this design guide).
It is critical that they are engaged early enough to have a meaningful input into design. They should
therefore be involved by at least the start of RIBA stage 3 (developed design).
In practice, catering and hospitality will be taking a brief from their own stakeholders, using this to
assess catering needs for the new or refurbished space, ensuring this fits into the overarching catering
strategy for the campus then preparing more detailed specifications for the design team.
The project brief (and budget) should clarify who is responsible for providing plates, cutlery, trays,
cooking utensils etc.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2 2
5.10.1 Lessons learned
There are numerous examples of designs which have not met the needs of Catering and Hospitality.
They typically occur because catering and hospitality are not consulted early enough or because the
principles in this design guide are not followed. Examples include:
Imposing limited space, which cannot accommodate the equipment or activities which catering
services require to provide the services required by the end users.
Not installing water supplies, drainage and/or extraction which prevents a catering facility
being upgraded to meet changing requirements
Inadequate power supplies, equipment needs are compromised by an insufficient power grid.
Expansion proves very expensive to provide retrospectively.
Improper brief, unclear final outcome leads to a project failing to meet stakeholders’
requirements or last minute fixes that add expense or do not provide the required service.
5.10.2 Production Kitchens
This section of the design guide relates to deli/café/bar and vending operations. While many of the
general principles in this section will hold true for production kitchens (e.g. the need for adequate
storage), production kitchens are significantly larger, complex, busy spaces with a diverse array of
catering equipment and activities.
Much more detailed analysis will be required to determine what represents ‘adequate’ storage or
washing facilities, for example. There is a need for very high standards of co-ordination between
mechanical and electrical services, incorporation of numerous safety devices (e.g. emergency cut off
devices) and liaison with other UWE stakeholders (e.g. the UWE Fire Advisor).
In practice, Catering and Hospitality will need to be involved at the concept design stage.
It should be noted that kitchens should be capable of accommodating duplicated appliances to cater
for specific dietary requirements.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2 3
5.10.3 Deli/Café/Bar Style Operation
The guideline will enable the main aspects of design to be considered in developing a brief for the
design of the style of catering operation.
Considerations will be given to:-
Design
General layout and room specifications
Service Style
Mechanical and Electrical to include IT and phone lines
General Service Requirements
Finishes
5.10.3.1 Design
The design of modern retail Deli/Cafe catering outlet should only be undertaken by a specialist
catering Design Company with experience in delivering a “Turnkey” package.
A detailed brief can be provided by the client utilising this guideline as starting point.
This process ensures that the design is Client-based with a full understanding of the commercial
aspects and technical issues demanded from the proposed outlet.
The Outlets should be so designed to create a modern bright space with the emphasis on a de-skilled
or semi-skilled food production, and able to offer a range of quality light meals, snacks, sandwiches
and beverages. Consideration to design if location to be licensed for the sale of alcohol.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2 4
5.10.3.2 General Layout and Room Specifications
The operation will ideally be a self-sufficient unit but could be partly supplied via a larger local central
catering operation.
Stores for storage of back up stock would be required as will modular refrigeration & freezer units.
Ventilated dry storage should be provided with adequate shelving space for holding stock equivalent
to 30 days.
Modular cold storage units would ideally be divided into three areas, High risk storage, low risk storage
and freezer storage. This facilitates the implementation of the food handling elements of the food
safety act.
Depending on style an area would also be required for the Chef Manager to receive goods and to
conduct cashing up. This would normally be sited close to the entry point for goods.
There will only be a limited use of crockery with disposables being used in the main. A dishwasher
system however maybe required for the washing of crockery and utensils and this should be sited
within an area away from food preparation areas.
This operation will produce waste and therefore, consideration should be given to separating food
waste from waste that can be recycled.
Waste areas should be identified as under counter and external recyclable waste bins. External
enclosed bin areas should be considered within the design or have a holding facility away from food
preparation areas whereby waste can be stored prior to being taken to main waste storage areas.
A separate lockable COSHH cupboard with shelving and Belfast bucket sinks should be provided for
cleaning and chemicals.
5.10.3.3 Kitchen Design
The operation is dependent upon a minimum of food being prepared on site and therefore the space
required is relevant to the operation. However, sufficient space should be given to produce food in a
safe and organised manner maintaining separate areas for high and low risk food preparation.
The operation should allow raw and cooked foods to be prepared in separate areas, having dedicated
refrigeration, sinks and prep benches for those areas.
Cooking equipment should be adequate for use, with the extra ability to meet demands for increased
business. Low intensity food production methods are advised for Deli/Cafe/Bar style food operation
refrigeration and oven and frying equipment to be selected for purpose of design. Extraction fan to
be fit for purpose of selected equipment.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2 5
A balance of equipment power requirements should be achieved with a view to having a mix of gas
and electrical cooking equipment. Additional electrical power to be available for any future additional
equipment needed.
Separate sinks are required for food use and cleaning use. Adequate hand wash sinks are required.
Sinks to be accessible to users with reduced dexterity.
The catering environment to be temperature controlled with adequate fresh air make up and if
feasible adequate natural light.
All finishes within the service area should be of an impervious nature and cleanable with the ability
to be regularly sanitized.
The position of pest control measures will need to be discussed/agreed with the current contractor
and considered in the design.
The potential need for duplicated appliances to cater for specific dietary requirements must be
established early on: This will have significant implications for space requirements, as well as
services.
5.10.3.4 Service Style
Operation is relatively low skilled with the emphasis being placed upon low intensity food production.
The main service counter would be approximately 6 metres in length with a back counter around the
same. Again this would depend on location and space available.
Space should be given to chilled ambient, hot, option and retail space for grab and go.
The design elements of the flow of customers should be considered to reduce dwell time and queuing
issues. This may affect the type of coffee machines utilised which could be self-service, barista style
or bean to cup.
Consideration should be given to the careful management of staffing levels required to operate the
food service points. Staff should be able to migrate between counters during quieter periods. Staff
should be adequately trained in all areas of food production and service.
The food service counters should include:
Limited hot section Chilled Deli and salad section Hot Snacks
Grab and go, with easy access to tills for speed of service to include-cold drinks sandwiches
and boxed salads etc.
Quality coffee and hot beverage offer on back or front counter
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2 6
Each area of the counter outlet will serve and display from either hot (dry heated solid tops)
or cold (chilled self-selection and served) units. This could be of a mobile nature for use
elsewhere or fixed as part of the shop fitting.
Space on the counter and their approaches should provide for the merchandising of trading
up items. Each outlet will require power and data connections to operate POS systems and
widescreen confirmation of service times and menu offerings
Easy access or dispense of free drinking water to be available in all food service outlets
5.10.3.5 Finishes
Consideration should be taken in applying the selection of kitchen finishes in order to ensure
compliance with health and safety and the food safety act.
Ceramic floor and wall tiles are not permitted.
Ceiling finishes should have a plastic faced cleanable tile on a white corrosion resistant grid.
A 600mm2 grid is advisable. Light fittings should be enclosed vapour proof fittings with
diffusers fitted in to the ceiling grid.
Floors should be anti-slip vinyl or quartz screed with 120-150mm coved edges.
Wall finishes should be of a cleanable and impervious nature vinyl sheeting with an integral
biocide is advised.
Doors should be manufactured with cleanable laminate surfaces.
All paint surfaces should be either low VOC Matt or eggshell.
Food server counters should be manufactured in stainless steel with decorative polymer
counter tops or granite, and have decorative laminates to the front facing elevations. Any
joins to be finished in impervious materials that are suitable for the area.
Impulse space should be designed in to the counter along with an element of retail.
Back counters should be manufactured in stainless steel with stainless steel work surfaces.
5.10.3.6 Seating area
Social spaces should have a variety of seating which would suit the varied dining styles offered.
The mix of seating ideally would include fixed seating, breakfast bars and soft seating areas.
The colour scheme should be so designed as to create a bright and airy environment with the
use of neutral tones accented with stronger feature colours.
Flooring to be cleanable and possibly include some carpeted areas where soft seating is
present.
The use of audio visual facilities should be utilised within the space for information purposes,
therefore data cables would be required in those areas.
As discussed elsewhere, small power should be supplied.
More generally, the seating area can be used as a social or breakout areas and may need to
accommodate televisions, marketing screens etc. These requirements will be established in
the initial brief and may necessitate the provision of power, data etc. which should be allowed
for within the project and co-ordinated into the overall design.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2 7
5.10.4 Vending Operation
5.10.4.1 General
The intention of this guideline is to seek to provide a modern efficient Vending Service.
This guideline will enable the main aspects of design to be considered in developing a brief for the
design of a Vending Operation.
Vending can be used to capture sales in areas of significant footfall or designed to provide an
additional out of hour’s service to back up retail catering operations.
It can be used to provide a service in remotely located areas away from the main Catering operations.
Vending machines have changed significantly in recent years and can be used to supply a range of
hot and cold food and drinks. There may need to be mains water, small power and potentially
drainage. Consideration will therefore need to be given to -
Mechanical and Electrical requirements
Design
General Service Requirements
5.10.4.2 Design
The design of a retail Vending Operation should only be undertaken by a specialist in Supplying
Vending or a catering design company with experience in delivering such a service.
A detailed brief can be provided by the client utilising this guideline as basis on which to commence
the design process.
This process ensures that the design is client based with a full understanding of the commercial
aspects and technical issues demanded from the proposed outlet. The Outlets should be so designed
to create a discreet vending operation which is carefully sited and fits well within a given social space.
A Vending operation will require the use of a remote storage facility sufficiently large enough to hold
back up stock particularly where the supply of chilled drinks are required through vending. Space is
also required for storage of hot beverage product and drinks cups.
It may be that chilled back up space is required where sandwich and chilled snack are held in
situations where the vending machines are stocked more than once per day.
The stores should be adequately lit and well ventilated. Dry storage should be provided with adequate
space for holding stock equivalent to 3-5 days.
All stock is subject to the requirements of the Food Safety Act.
UWE Design Guide for Buildings
C h a p t e r 5 | F a b r i c & S t r u c t u r a l D e s i g n I s s u e 1 . 3 P a g e | 2 8
Vending produces waste and therefore, consideration should be given the provision of separating wet
waste from waste that can be recycled. To this effect consider the use of waste and recycling units
adjacent to the vending area. As mentioned above, drainage may need to be considered.
5.10.4.3 General Service Requirements
The University Health and Safety Advisor should be consulted at an early stage of the design process
to ensure that the vending is not sited so to cause any restriction or hazard in public spaces and will
satisfy statutory regulations.
Social spaces may be adjacent to the vending and consideration should be given to a variety of
seating which would suit the operation.
Vending is often best placed within a shop fitted housing which can be designed and built to
complement the local scheme.
Consider the use of anti-slip flooring to the area immediately in front of the vending machines due to
the potential slip hazard created by spillage.
5.10.5 Tea Points
Tea points are required within large office areas and will be a minimum area of 4m2 and will consist
of Vinyl flooring, overhead and under counter storage, sink, fridge dishwasher and fridge.
UWE Estates and Facilities Design Guide
Chapter 6: Mechanical Engineering Design
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 2
Table of Contents 6.1 General Mechanical Design Principles ............................................................................ 3
6.2 Management of Mechanical Design ............................................................................... 4
6.2.1 Initial Survey and review of existing asset information ............................................. 4
6.2.2 Design Co-ordination ............................................................................................. 4
6.2.3 Initial Load Assessment ......................................................................................... 4
6.2.4 Plant, System Selection and Location ...................................................................... 4
6.2.5 Statutory Guidance and Practice Recommendations ................................................. 5
6.3 Stage Gate Approvals (RIBA Stages 2-6 2013) ............................................................... 5
6.4 Schedule of Statutory Notifiable Plant: .......................................................................... 6
6.5 Commissioning: Mechanical .......................................................................................... 6
6.6 General Principles Governing the HVAC strategy ............................................................ 6
6.7 Pumped Water and Air Circuits ..................................................................................... 8
6.8 Acoustics .................................................................................................................... 9
6.9 Metering ..................................................................................................................... 9
6.9.1 Heat Meters ....................................................................................................... 10
6.9.2 Electric meters.................................................................................................... 10
6.9.3 Gas and Water meters ........................................................................................ 10
6.10 Disposal Systems ...................................................................................................... 11
6.11 Laboratory/Industrial Waste Drainage ......................................................................... 11
6.12 Pumping of Drainage ................................................................................................. 11
6.13 Piped Supply Systems ................................................................................................ 12
6.14 Heating Pipework ...................................................................................................... 12
6.15 Hot & Cold Water Services ......................................................................................... 13
6.15.1 General .............................................................................................................. 13
6.15.2 Hot Water Service ............................................................................................... 14
6.15.3 Sustainable designs ............................................................................................ 15
6.16 Natural Gas............................................................................................................... 15
6.17 Medical/laboratory gas ............................................................................................... 16
6.18 Refrigerant Pipework ................................................................................................. 16
6.19 Mechanical Heating/Cooling/ Refrigeration Systems ...................................................... 17
6.19.1 General Temperature Performance Requirements .................................................. 17
6.19.2 Heating .............................................................................................................. 17
6.19.3 Cooling .............................................................................................................. 18
6.20 Ventilation/Air Conditioning Systems ........................................................................... 20
6.20.1 Mechanical Ventilation ......................................................................................... 20
6.20.2 Fire Strategy ...................................................................................................... 21
6.21 Central control/building management system............................................................... 21
6.22 Approved Mechanical Suppliers ................................................................................... 23
6.23 Approved Mechanical Contractors ............................................................................... 23
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 3
6.1 General Mechanical Design Principles
Designers must read Chapters 1, 2 and 3 of this Design Guide, as well as this Chapter, before
commencing any mechanical design work.
This chapter provides designers with an insight into what should be taken into account when
preparing their designs and the issues that should be considered to ensure that a building services
installation can be practically installed, efficiently maintained and will meet the client’s written and
implied aspirations for the short-, medium- and long-term.
This chapter sets out the minimum standards of engineering services to be applied throughout the
estate, they are not intended to stifle innovation or technical advances.
It is the wish of the Estates department to adopt low carbon principles within its design. A
fundamental requirement is therefore to design out any avoidable energy requirements. Demand
reduction takes priority over covering energy requirements through low carbon or renewable
sources. The design should apply the principles of Low Carbon Design:-
Understand energy use in the building type
Use the form & fabric of the building to minimise energy demand
Focus on insulation and air tightness
Use high efficiency building services with low carbon fuel
Manage energy within the building
Use renewable energy systems
The Building Services design should follow the principles of the energy efficiency hierarchy:-
Reduce demand by using passive measures
Use energy efficient equipment and controls
Use low carbon and renewable technologies
The Building Services design should consider implications of a changing climate as detailed in
Chapter 2 of this Design Guide. UWE use their buildings throughout the year and therefore all
buildings shall be thermally modelled as being occupied during the summer months.
The building services design should comply as a minimum with any local building planning
conditions, but this should not be considered as the design standard, but improved upon where
possible to meet both the University’s energy performance and carbon targets.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 4
6.2 Management of Mechanical Design
Chapters 1 and 2 of this guide states that all designers must consult with a range of stakeholders
including end-users and the Facilities department, during design development. This may be in the
form of structured liaison meetings organised by the internal or external project manager.
Mechanical designers, depending on their exact discipline and the nature of the project, will need to
take the following actions:
6.2.1 Initial Survey and review of existing asset information
Survey existing services and ascertain the implications of any new works. A condition survey
may be required for works within existing areas. The designer is responsible for checking the
suitability of all existing water supplies, drainage capacity etc. at project inception.
Consideration and review of case studies and technical papers of similar applications.
Consider budgetary and energy conservation requirements.
6.2.2 Design Co-ordination
Analysis of the building’s façade in conjunction with the building designer and structural
engineer to assess thermal performance and ultimately to increase energy efficiency.
Liaise with all members of the design team including the building designer and structural
engineer to provide an integrated building/ structural / services installation. This must include
coordination of mechanical builders work requirements, plant space and significant apertures
within the structure.
Coordination is also required with the electrical services designer regarding the power and
control requirements for the mechanical services.
External Shading should be considered in conjunction with the building designer to consider the
full implications including minimising the effects of unwanted heat gain to occupied space. This
should be done from building conception.
6.2.3 Initial Load Assessment
This is required for early assessment of the plant space requirements for co-ordination with the
building designer.
BSRIA documents and Institutes/CIBSE rules of thumb can be used as a check.
6.2.4 Plant, System Selection and Location
Selected to maximize operational efficiency and availability.
To suit ambient conditions (thermal & noise) during all seasons.
Continuity with existing plant and manufacturers where appropriate.
Consideration of maintainability and the minimisation of impact within occupied spaces
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 5
Consideration and review of case studies and technical papers of similar application.
Consideration of plant operation at part load should be made, with the use of fully modulating
plant preferred where considered economic.
The University prefers major plant such as chillers to be located at Ground Level. If this does
not appear achievable approval will be required from the UWE Estates Team. See the section
on maintenance access in Chapter 2 of this guide for further information.
6.2.5 Statutory Guidance and Practice Recommendations
The Building Services design is to follow best practice recommendation, which includes, but is not
limited to:
Bristol Water Regulations.
UWE Standard Mechanical Specifications.
Building Services Research & Information Association (BSRIA) Publications
Chartered Institution of Building Services Engineers (CIBSE) Guides & Technical Memoranda;
Institute of Plumbing (IoP) Standards; and
Heating & Ventilating Contractor’s Association (HVCA) DW series documentation.
The designer shall inform and advise UWE of any conflict between the above, and seek UWE
approval of proposed resolution.
6.3 Stage Gate Approvals (RIBA Stages 2-6 2013)
On major capital projects (nominally any project over £2.5m), UWE will adopt BSRIA BG6 Design
Framework for Building Services to manage the allocation of design responsibilities. At the
discretion of the UWE Project Manager, BG6 shall be applied to projects of lower value (especially
where there is a heavy emphasis on building services).
BG6 contains a number of pro-forma templates to be used at different RIBA stages. Due to the
fact that UWE is an informed client, most of the pro-forma 1 activities have been or will be carried
out in-house by UWE (e.g. obtaining and providing existing building information) and other project
processes are in place to ensure this is done.
Therefore, design teams will only be required to use pro-forma 2 onwards contained in BG6.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 6
6.4 Schedule of Statutory Notifiable Plant:
The mechanical designer must consider the statutory requirements for all of the following
installations and advise the Facilities CA\Engineer of their project implications via the reporting
process detailed within the appendices of this design guide:-
• Legionella Risk Assessment, schedule of legionella susceptible plant. • Bristol Water, notifications. • Refrigerant plant. • Boilers • Pressure vessels and MPHW calorifiers (heating, CHW, refrigerant or CWS), schedule of
plant. • COSHH tests, schedule of plant.
Certificates for the factory pressure testing of boilers, calorifiers and other pressure vessels should
be specified at tender and provided at handover stage
6.5 Commissioning: Mechanical
The designer should ensure that systems are fully commissionable (and self-balancing where
economically viable).
Commissioning devices should be installed to manufacturer’s recommendations and accessible for
future use.
CIBSE commissioning codes, BREEAM and BSRIA guides should be adhered to.
10-15% of all values should be checked by the mechanical designer.
100% of all safety interlocks (and all fire dampers’ operation) should be witnessed by the designer.
6.6 General Principles Governing the HVAC strategy
The Building Services Consultant should:
• Note that UWE expects the maximum use possible of natural ventilation in all its buildings. • Ensure that the thermal mass of the building can be used to minimise summer overheating. • Evaluate the use of mixed-mode ventilation systems with heat recovery • Consider the use of external solar shading to minimise summer overheating
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 7
The following hierarchy shall be adopted for the avoidance of summertime overheating:
1. Natural Ventilation
2. Mechanical Ventilation
3. Mechanical Ventilation with phase change medium
4. Other passive cooling methods such as ground coupled ventilation
5. Forced Refrigerative (mechanical) cooling
The European Energy Performance of Buildings Directive Article 9, in conjunction with the UK
Building regulations Part L has imposed strict limits on forced cooling. Forced refrigerative cooling
shall only be considered once all other means of achieving the required conditions have been
exhausted, including passive cooling systems.
To avoid the need for cooling systems the following principles should be adopted as appropriate:
Heat releasing equipment should be sited in areas with openable windows, free natural
ventilation or naturally cool areas e.g. basements etc.
Heat releasing equipment should therefore be located close to external walls (or externally),
to facilitate natural cooling. The equipment should not be positioned where it could be
susceptible to solar gain.
A large population of heat releasing equipment should not be installed in a single area or in
areas where there are large occupancy levels.
Only the necessary quantity of machines/equipment should be installed.
Local extract ventilation systems used to remove heat from source wherever possible
In areas not mechanically cooled the Building Regulations Approved document L2 performance
standard for avoidance of summertime overheating for learning, teaching and office areas shall be
adopted. The performance standard shall be extended to include all internal building spaces which
will be utilised by staff and students e.g. corridors and stairwells. UWE use their buildings
throughout the year and therefore all buildings and all rooms shall be thermally modelled as being
occupied during the summer months.
The above refers to comfort cooling only. When the function of an area requires specific operating
conditions i.e. processes, specialist equipment, chemical storage etc. then such areas will be
assessed independently. If it is concluded that cooling or air conditioning is necessary then these
shall be in addition to Local Exhaust Ventilation systems.
When designing mechanical cooling for IT Comms rooms this needs to be selected with energy
efficiency in mind and consideration of PIR sensors with higher set back temperatures to save
energy when the rooms are not occupied.
Adequate double-sided cross-flow ventilation is difficult to achieve in buildings with widths
greater than about 15 metres, (offices 6 metres deep with openable windows on either side
of a central 3 metre corridor). Buildings which rely on natural ventilation can have high
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 8
summer ventilation rates with no energy penalty. Summer ventilation rates may need to be
ten times greater than those achieved in winter to avoid overheating. There is some evidence that
natural ventilated buildings can be “healthier” than some air-conditioned or mechanically ventilated
buildings.
Buildings can be designed to use a mechanical ventilation system with heat recovery during
the heating season, and natural ventilation from opening windows during summertime.
During the heating season, the windows should be locked shut or have interlocking controls to
avoid heating when the windows are open. This type of servicing arrangement is termed
‘mixed mode’ and recent data from the Building Services Research Establishment has shown that
office buildings with mixed-mode systems can use less energy than either continuously
mechanically ventilated or air-conditioned buildings.
Natural ventilation can be provided from windows, ventilation slots in window frames, solar driven
stack-effect or from purpose-made controllable through-wall systems. Thermal comfort may also be
influenced by the exposed thermal mass of the building: a lightweight building will respond rapidly
to changes in external conditions, whereas with a heavyweight structure a noticeable damping
effect on internal temperatures may occur. The use of suspended ceilings effectively removes the
thermal mass of the floor slab from the thermal response of the building, allowing more rapid
variations in temperature. Figures from the BRE suggest that for naturally ventilated offices with
internal blinds overheating can be reduced to 10 days per year or less. Where external blinds are
used, overheating would occur on average for only 3 days or less per year.
Re-use of low grade heat, such as heat rejection from chiller plant should be fully considered both
with respect to the building under design and/or buildings in the vicinity.
6.7 Pumped Water and Air Circuits
Water pumped circuits should have at least 100% standby (excluding HWS secondary, where a
spare pump shall be provided).
+10% to be added to all pump duties (head & flow) to make allowance for commissioning
tolerances.
In the first instance variable volume pumps/fans with static pressure control via the BMS should be
considered. This is also important when future expansion of the installation is envisaged.
Variable speed drives should utilised where possible and have differential pressure sensors rather
than switches.
Local visual indication via temperature and pressure gauges should be provided in addition to BMS
sensors (BMS sensors alone are insufficient).
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 9
6.8 Acoustics
Please also refer to the appendix addressing Acoustic performance requirements.
Noise from building services should not exceed the noise rating (NR) values listed below. This
includes noise from the normal operation of heating, ventilation and air conditioning plant. Higher
levels may be permissible during purge ventilation. When planning ventilation duct runs, they
should as far as possible avoid crossing partition walls, and where this is inevitable a crosstalk
silencer must be incorporated so that the sound insulation requirements listed in section 3.6 are
met.
Designs should aim to ensure that plantrooms operate at 78db or less. If sound pressure level is
between 79db-82db then a warning sign should be installed on the door stating that hearing
protection should be worn if individuals are in the room for more than half a day. In addition,
visual and auditory fire alarms should be installed. If sound pressure will exceed 82db then a
detailed risk evaluation is required to provide details of the required management strategy. Plant
rooms must not operate at 88db or above.
Type(s) of room Maximum NR Value
Academic staff and admin offices NR 35
Cafeterias, coffee bars etc NR 40
Class rooms, lecture rooms, seminar rooms and tutorial rooms Audio visual and video conference rooms Language laboratories
NR 30
Drama studios, music practice rooms NR 30
Entrance halls, corridors, stairwells, atria and circulation spaces NR 40
Halls and rooms for music drama and other live performances NR 30
Large lecture theatres and flagship conference rooms NR 30
Lecture theatres up to 100 seats NR 30
Library circulation and media storage areas NR 35
Library study areas NR 30
Recording studios NR 30
Rooms intended for clinical examination and treatment, confidential interviews, psychotherapy, speech therapy etc.
NR 35
Science laboratories, art and design studios, graphics workshops NR 30
Sports halls and gymnasia NR 35
Swimming pools NR 50
Workshops NR 35
6.9 Metering
Metering and sub metering of utilities shall be installed as per CIBSE guide TM39, Heat Network
Regulations (2014) and BREEAM requirements. For the sub-metering of mechanical systems (HVAC
and Mains Water Services), the following principles should be followed:
Major plant that consumes more than 10% of the building energy should be sub metered.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 10
Sub metered per floor (particularly for water services).
Sub metering any lettable spaces e.g. leased spaces to shops or businesses within UWE.
Any cooling loads shall be metered separately.
Sub-metering shall be provided in accordance with the requirements of the Building Regulations
specifically “The Building Regulations 2000 part L Conservation of Fuel and Power”.
Metering of electricity supplying mechanical plant shall be installed to all distribution boards either
in the main switchboard or integrally in each distribution board.
Volumetric flow metering (i.e. for water, gas and heat services) should be specified to meet average
flows as there is risk that oversized meters do not provide useful profile data.
All new meters should have an output that is connected to the University Energy Team’s
Elcomponent metering system (see below for further clarification). All necessary equipment
required to ensure that each metering unit can be connected onto the Elcomponent system,
including data points, power supplies, pulse loggers etc. shall be provided as part of the project.
Allowance shall be made for modifying and/or extending the existing data collection system as
required ensuring that it is sufficiently sized to accommodate the additional metering units within
the building. All meters must be fully installed, commissioned and operational at handover.
6.9.1 Heat Meters
Elcomponent communicates with three types of heat meter via MODBUS, these are:
Kamstrup
Micronics
Sharkey
6.9.2 Electric meters
Use either:
Elcomponent’s own AEM33 meters (click ‘AEM33 meters’ to be directed to the Elcomponent
website). These are either multi-parameter or 3 channel meters.
Schneider meters with pulse output as a minimum.
The UWE engineer providing technical assurance, in conjunction with the UWE energy team, will
determine if a multi-parameter meter is necessary or whether pulse output is sufficient.
6.9.3 Gas and Water meters
Gas and water meters must have a pulse output.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 11
6.10 Disposal Systems
All drainage pipework must not be routed in locations (distribution boards, MCC’s etc.) where it is
possible a leak could cause a health and safety hazard.
HDPE or Stainless Steel shall be used for drainage.
6.11 Laboratory/Industrial Waste Drainage
Vulcathene pipework shall be used for chemical drainage including laboratories etc
In engineering/science all drain runs which will carry hazardous or radioactive substances, must be
labelled accordingly.
Waste traps/catch pots are to be labelled with appropriate warning signage and contained in locked
and labelled cupboards.
Please find a list of ‘prescribed substances’ as given by the UWE sewerage provider. These
substances cannot be put down the drain without notifying the sewerage provider, who then needs
to notify the Environment Agency:
Mercury and its compounds
Cadmium and its compounds
Gamma-hexachlorocyclohexane
Pentachlorophenol and its
compounds
DDT
Hexachlorobenzene
Hexachlorobutadiene
Aldrin
Dieldrin
Endrin
Carbon tetrachloride
Polychlorinated biphenyls
Dichlorvos
1,2-dichloroethane
Trichlorobenzene
Atrazine
Simazine
Tributyltin compounds
Triphenyltin compounds
Trifluralin
Fenitrothion
Azinphos-methyl
Malathion
Endosulfan
Trichloroethylene (above 30kg/year)
Perchloroethylene (above 30kg/year)
The use of prescribed substances shall be avoided where possible, where the use of a prescribed
product is proposed by a faculty the designer shall inform and review the full implications with the
design team and UWE faculties.
6.12 Pumping of Drainage
UWE only wishes to use gravity drainage. Sewage pumping, including of condensate, must be
avoided. If a pumped solution is deemed unavoidable then approval for its use must be obtained
from the UWE Estates Team (see management of derogations elsewhere). UWE will need detailed
justification and assurances that the system offers adequate reliability and resiliency (e.g. through
provision of back up pumps).
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 12
6.13 Piped Supply Systems
Distribution pipework should generally be to match the existing installation.
The use of plastic pipework is generally not accepted (excluding overflows and warning pipes etc.).
All water services pipework must not be routed in locations (close to distribution boards, MCC’s etc.)
where it is possible a leak could cause a health and safety hazard.
Low level copper pipework to radiators is prohibited without prior agreement with Estates
Adequate allowance for system expansion should be made in pipework design rather than use of
expansion bellows.
Services for open plan accommodations should be designed on a grid basis.
ALL new plant and pipework/ductwork jointing gaskets in existing buildings must be asbestos-free
with confirmation plastic tags (which extend beyond adjacent joints for ease of future
identification).
Unless identified as indicated above, ALL existing gaskets should be assumed to contain asbestos
until known otherwise. Therefore, if they are to be exposed or removed during the contract works
they must be treated as hazardous and dealt with in the appropriate manner.
6.14 Heating Pipework
All heating pipework up to and including 125mm shall be installed using mild steel pipes to BS1387,
heavy grade, black varnished finish.
All heating pipework 150mm and over shall be installed using carbon steel grade 430 pipes to
BS3601 ERW, dimensions to BS3600 table 1, standard mill protective coating finish.
All heating cold feed and open vent pipework, and safety valve or vent cock discharge pipes, shall
be installed using mild steel pipes to BS1387, heavy grade galvanised finish.
All pipework off air bottles or AAV's shall be copper to BS2871, part 1, table X or Y.
All black steel pipework up to and including 50mm shall have screwed joints to BS21 taper thread,
using hemp and jointing compound to BS5292.
All black steel pipework 65mm and over shall have welded joints or flanged joints throughout.
Joints shall not be permitted within any part of the building fabric.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 13
Screwed fittings on black mild steel pipework, other than sockets, shall be malleable cast iron to
BS6681, having ends to BS143 or BS1256, black finish manufactured by Crane Ltd.
Screwed fittings on galvanised steel pipework, other than sockets, shall be as for black mild steel
pipework, but galvanised finish.
Fittings on welded pipework shall be carbon steel grade 430 seamless, to BS1965, part 1, heavy,
having bevelled ends, varnished finish.
Joints shall be provided as necessary to enable all pipework to be dismantled without cutting.
6.15 Hot & Cold Water Services
6.15.1 General
The designer is responsible for checking the suitability of all existing supplies at project inception. If
record information is not availability the designer shall either survey or request and provide a brief
for any surveys required. The designer if required shall contact the relevant statutory supplier to
establish suitability of supply capacity.
All water services shall be in accordance with the UWE Legionella Policy (specifically the UWE
Procedure on the Management and Control of Legionella).
A mains water service with no tanked supplies should be utilised wherever possible
If CWS storage is required it should have a minimum of two independent tanks (inter-connected in
a ‘fill’ and ‘draw’ configuration) to minimise down time during times of maintenance. However,
their capacity should be minimised.
Cold water outlets in kitchens, tea bays and vending areas should be mains fed.
Communal drinking water should be dispensed via proprietary refrigerated units with carbon filters,
bottle filling as a well as drinking facilities and gravity drains (see approved mechanical suppliers).
To minimise the risk of water stagnation or bacteriological growth, storage capacity should be
commensurate with minimum storage rates.
Labs and workshops where applicable should gave fluid cat 5 supplies to non-domestic appliances.
Back flow protection devices should be provided to Bristol Water Regulations.
To prevent future cross-connection of Cat 5 and domestic pipework, Cat 5 pipework should be
insulated with a different surface finish to domestic (preferred method ISOGENOPAK).
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 14
Domestic washing machines and dishwashers to have appropriate back flow protection to current
water regulations (normally Cat 3).
External bib taps for irrigation and window reach and wash cleaning operations should be avoided
where possible. Where unavoidable, appropriate back flow protection to current water regulations
should be provided (normally Cat 5).
RPZ non-return valves should not be used without the approval of UWE Estates PM/Engineer.
6.15.2 Hot Water Service
All methods of hot water production should be evaluated including Combined-Heat and Power
(CHP), solar, heat pumps etc. Biomass/bio-fuel will be considered under particular circumstances.
An assessment should be made of the most efficient method of hot water production, including the
separation of heating and hot water.
Hot water storage calorifiers or Heat Interface Units shall be assessed for buildings with the
potential to connect to the district heating system, elsewhere gas fired water heaters should be
used for hot water service generation.
Two pipe (Recirculatory) type systems are preferred, approval should be sought from the Facilities
CA\Engineer before installation of any other type. Where hot water use is expected to be low, the
use of electric instantaneous heaters, or low volume electric storage heaters for localised supply
should be considered.
Central water generators should have a minimum of two generators to minimise down time during
times of maintenance.
Storage calorifiers should be selected and designed to be capable of raising cold water from 10oC to
65°C, with a two hour recovery period.
Calorifiers should have anti-stratification pump circuits, controlled to the dictates of document L8.
All HWS should be stored at 60°C and warning labels provided at all outlets where there is a risk of
scalding.
Outlets within Disabled toilets and other areas with vulnerable occupants must have reduced
temperature flow via thermostatic mixing valves, specified as being suitable for this application,
outlets elsewhere should be conventional mixing valves with time flow and/or equalising pressure.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 15
Where Thermostatic Mixing Valves are used the TMV shall be integral to the tap. No remote
thermostatic mixing valves shall be used on the water systems unless a special case is made to and
approved by the Estates Team.
Surface (i.e. non-intrusive) scale-prevention plant should be provided when performing extensive
works to existing central HWS generators. New plant should have probes mounted within the
pipework (see approved mechanical suppliers). Expansion vessels used on potable water supplies
should be of a flow-through type.
All above ground Water Services pipework up to and including 133mm shall be installed using
copper tubes Table X, uncoated or current equivalent. Flexible connections to sanitary appliances
are prohibited.
Above ground Water Services pipework 159mm to 219mm shall be installed using copper tubes to
temper annealed, Table 5 up to 7 bar working pressure, and Table 6 up to 17 bar working pressure.
6.15.3 Sustainable designs
An assessment should be made of the use of rain water and grey water harvesting systems. UWE
Sustainability Plan 2013-2020 has a target to increase rainwater and greywater systems at all
campuses. The aim of this target is to improve the University’s water resilience in the event of
water scarcity in the future.
Low flow water fittings and IR-controls should be considered for all appliances particularly wash
hand basins, urinals, WC’s and showers. Using the BREEAM criteria as values to be achieved.
6.16 Natural Gas
The designer is responsible for checking the suitability of all existing supplies at project inception. If
record information is not availability the designer shall survey or request and provide a brief for any
surveys required. The designer if required shall contact the relevant statutory supplier to establish
suitability of supply capacity.
Gas installation line diagrams for new installations or amendments to existing must be provided.
They should be mounted on site plus a copy given to the Facilities CA at handover.
Gas detection systems, linked to solenoid valves, should be provided within all new remote boiler
houses or those integral within the building and over 300KW.
Where Gas solenoid valves are provided the system must be designed to ensure they do not auto-
open upon power re-instatement, plus control provision should be made such that its power supply
is not interrupted during the university’s regular fire alarm testing regime.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 16
Emergency Isolation Points and gas proving systems shall be provided in all laboratories and
kitchens.
Interlock of gas supply with supply air for all main kitchens is essential.
6.17 Medical/laboratory gas
Designers of faculty gas installations or specialist services (e.g. laboratory gases) must co-ordinate
their designs with the rest of the design team, the faculty and vice versa, even if this installation is
being procured as a separate package.
6.18 Refrigerant Pipework
The entire refrigerant pipe work installation shall be installed using copper tube to BS 2871, Part 2,
Table 2 designation C106 or equivalent, suitable for the type of oil and refrigerant used.
Refrigerant Pipe work up to and including 3/8" (12mm), shall be installed using tube to specification
standard ASTM280, DIN 1754/8905 or equivalent, annealed, having plain ends, finished uncoated,
tested by Eddy Current method, all fully de-greased, dehydrated and capped, all internal surfaces
being absolutely free from scale and dirt.
Refrigerant Pipework for sizes ½" (15mm) and over, shall be installed using tube to BS 2871, Part
2, half hard condition or specification standard ASTM280, DIN 1754/8905, half hard temper or
equivalent, having plain ends, uncoated finish, tested by Eddy Current method, all fully de-greased,
dehydrated and capped, all internal surface being absolutely free from scale and dirt.
Where there is a likelihood of mechanical damage it shall be protected by inverted cable tray
including all external refrigerant pipework.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 17
6.19 Mechanical Heating/Cooling/ Refrigeration Systems
6.19.1 General Temperature Performance Requirements
6.19.1.1 Heating Season (air temperature)
Winter ambient: - 5.5°C db/100% RH
Room temp (general): 22°C db
(See CIBSE guides for specific areas)
100% outside air ventilation ambient: -7.0°C db/100% RH
Allowances for intermittent heating: (See CIBSE guides).
6.19.1.2 Cooling Season (air temperature)
Summer ambient: 28°C db/20°C wb
Summer ambient (heat-rejection plant): 30°C db/21°C wb
Room temp (general): 22°C db (only used for mechanical cooling)
(See CIBSE guide for specific areas)
Note, these temperatures are only applicable where the case for mechanical cooling has been
accepted by the Estates team otherwise the temperature should meet the constraints of the
Summertime Overheating Criteria.
6.19.2 Heating
Heat source: An assessment of low/zero carbon heating sources should be conducted before
specifying fossil fuel boilers. This assessment should include consideration of connecting to the
proposed district heating network at Frenchay Campus, and any other known, existing or, proposed
district heating systems in the proximity to the specific site whether UWE-owned or by another.
Where gas boilers are used, atmospheric gas fired boilers should be used in preference to forced
draft boilers.
Spare capacity: Except in individually served housing units, a minimum of two heat sources must
be installed: 150% total nominal capacity.
Three or more heat sources: 120% total nominal capacity
Heat source control: As HM Government: Non-domestic Building Services Compliance Guide
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 18
Pumped circuits: Each pumped circuit must have dual pumps (i.e. run and standby). Pumps
should be specified with variable speed drives.
Design Margin: A minimum of +10% of heat out-put should be added to all terminal/(heat
emitting) devices. Adequate allowance for heat loss from distribution pipework should be made.
Electrical Heater Batteries: Must be agreed in advance with UWE Estates.
Use of storage tanks: If storage tanks are to be used for providing heating fuel (e.g. bio-fuel),
tanks should be fitted with a fill indicator which is to be clearly visible at the filling point and the
tank should also be fitted with an overfill alarm, linked to the BMS. Secure filling point to be located
on accessible external wall. Tanks are to be double bunded. Handover documentation must contain
details of the refilling strategy (including required traffic management controls etc.).
Zoning: Appropriate heat zoning and controls should be defined to maximise system efficiency,
and to accommodate differences in end user needs.
6.19.3 Cooling
6.19.3.1 General
The emphasis of good design must always be on minimising internal summertime temperatures.
This should be approached in two stages. Stage 1 should evaluate the suitability of natural or
mechanical ventilation. If during this preliminary period it becomes apparent that suitable conditions
will not be achieved with natural ventilation, then Stage 2 should be to investigate the use of
mechanical cooling (see General Principles of this design guide).
The use of Mechanical Cooling is to be avoided, where it cannot be avoided, approval for its use
should be sought from UWE Estates. Passive rather than active systems should always be
prioritised e.g. the use of chilled beams in preference to fan coil units. The system/s shall also
comply with the following:
6.19.3.2 Large-scale
Cooling towers or other spray units will not be accepted.
Number of chillers: A minimum of 2 chillers should normally be installed: nominal System
total nominal capacity: 125%.
Chillers must have dual safety valve configuration to minimise loss of refrigerant during
maintenance procedures.
Larger computer rooms which require comfort cooling will require sensible coolers selected
with minimal latent cooling capacity, N+1 cooling provision shall be provided, consideration
shall also be given to future expansion of the cooling requirement, a report shall be
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 19
submitted to Estates for approval, detailing the level of cooling to be provided and method
of calculation.
6.19.3.3 Small-scale
Local DX Cooling
Heat pump – The use of reverse cycle heat pump shall be evaluated.
Ducted Fresh Air via Fresh Air spigot to external
BMS / controls Requirement: Remote Start/stop
o Common alarm
o Room temp sensor
o Auto-restart upon power reinstatement
The mechanical designer should ensure the details of the amount of refrigerant used and source of
power supply is provided on a trafolyte label screwed to the condensing unit.
6.19.3.4 Design Margin
A minimum of +10% of cooling out-put should be added to all terminal devices.
Adequate allowance for heat gain from distribution pipework should be made.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 20
6.20 Ventilation/Air Conditioning Systems
The fresh air supply rate, calculated in litres/second/person, should comply with CIBSE guides A
and B, and Part F of the Building Regulations. The chapter of this design guide dealing with space
standards provides minimum space allowances for some spaces. This will allow maximum
occupancy (and therefore air supply rate) to be calculated. This should be used for initial
assumptions about HVAC strategies and plant sizing (at RIBA Stage 2). However, the Space
Planning team should be consulted, especially where specialist spaces are concerned, about
anticipated occupancy. The project team must establish the exact processes to be undertaken in
the space (e.g. use of LEV systems) which will influence design.
6.20.1 Mechanical Ventilation
Ducted supply ventilation: Major supply AHU’s (above 0.5m3/s) should have the following:
Pre filter: panel to EU3
Main filter: Bar to EU6
(With Magnahelic and BMS pressure sensors across both filters)
Facility for recirculation of air where possible via motorised dampers. Where full fresh air is
essential, other methods of heat recovery shall be evaluated.
Automated windows and Ventilators: Where installed, they should be complete with position
indication or contacts.
Variable speed drives: Use of these drives to be assessed to maximise efficiency of the system.
Direct drives: Fan power should be of the direct drive type as opposed to belt drive.
Fire damper type: To be specified and installed for ease of annual testing, external resettable fire
dampers shall be used wherever possible. The mechanical designer should make provision to
witness the operation of all fire dampers as part of their witnessing of the commissioning process.
Displacement Ventilation: Use of this principle is preferred where practical and cost effective.
Intake and discharge locations: These should be considered at an early stage in the project
whilst applying good design principles and CIBSE guide B recommendations. Consideration of
discharge and intake pollution must also be considered. External weather louvers should be selected
and specified by the mechanical services designer.
Where cost effective, ground coupled fresh air supply system shall be used.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 21
In all cases, the legionella risk of passing intake air over water should be considered and low level
air intakes should be sited to avoid any accumulation of floor washing or rain water.
Ducted supply & extract fans: Differential Pressure Switches to be mounted across all fans.
VAV supply & extract fans: These should have differential pressure sensors rather than switches.
Humidification: Use of humidifiers is not generally accepted and approval should be sought from
the Estates Team for the use of central plant for dehumidification with reheat.
6.20.2 Fire Strategy
As detailed in Chapter 3 an updated fire strategy is required for any major changes to the building.
This must include the ventilation provision.
The fire strategy should identify the requirements for smoke ventilation, dry risers, hydrants etc.
The Design team and the Mechanical Consultant shall design the systems to meet current
regulations and good practice, where any ambiguity exists between the requirements the design
team should contact Estates for advice.
6.21 Central control/building management system
The UWE Building Management System to be used at Frenchay and Bower Ashton should be
Schneider StruxureWare.
A Trend 963 system is installed in several buildings and the entirety of the Glenside campus, all new
controllers to be BACNet compatible.
BMS monitoring and control shall be provided to all significant items of Mechanical Plant items,
unless agreed with the Estates Team.
Provision should be made within the construction programme for client witnessing of the BMS
controls prior to handover.
Graphics and software shall be created in accordance with associated UWE standard documents:
BMS Graphics Standards
BMS Software Standards
A copy of all BMS graphics, control philosophy and bespoke software programming should be issued
to the Facilities CA\Engineer for approval, with sufficient time period (two weeks) for comment.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 22
All safety interlocks must be hardwired (i.e. temperature, pressure, airflow etc.) with indication only
to be provided via the BMS where applicable.
All plant’s MCCs must be linked to the sites fire alarm system, with a provision to over-ride this link
for regular fire alarm testing.
As a rule of thumb, room sensors should be located 1.5M AFFL, 0.5M from corners and vertical
protrusions, away from draughts e.g. doorways, avoiding heat emissions and other thermal hot-
spots. They must be representative of the space being controlled.
Fridges/freezers that are considered business or research-critical must be monitored by the BMS.
All motorised dampers and valves should have their ‘open’ and ‘closed’ positions clearly marked on
the side of their respective actuators and/or damper linkage prior to handover.
As discussed elsewhere, it is critical that actuators, sensors etc. can be accessed from a position of
safety (avoiding the need to work at height if practicable) and without the need for dismantling.
Schneider Building Analytic software to be installed during the BMS commissioning stage (covering
all plant provided under the contract) with the objective of providing a ‘defect-free’ installation at
handover. Furthermore the contractor shall include for the monitoring, analysis and defect
rectification of all BMS components, and software engineering of said equipment through-out the
entire defects liability period, culminating in a totally defect-free BMS system at end of DLP.
Critical alarms shall be agreed at handover and included in the Bureau remote monitoring system.
Email alerts shall also be configured.
UWE Design Guide for Buildings
C h a p t e r 6 | M e c h a n i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 23
6.22 Approved Mechanical Suppliers
Heating Plant Cooling Plant
Boilers up to
70 kw
Caradon/Ideal
Baxi
Potterton
Vaillant
Chillers Daikin
Carrier
Trane
Boilers over
100 kw
Hamworthy
Hoval
Clyde Combustion
Wellman Robey
DX/VRV Daikin
Mitsubish
Ventilation Plant
Burners Riello
Nuway
AHU ABB Flatk
Dalair
Senior Moducel
Radiators Stelrad (or to match existing)
Runtal / Hudevad in specifically
agreed locations
Fans ABB Flatk
Nuaire
Howden Group
Elta
TRV’s Oventrop TRV’s. Model Series
AV6 (TRV Body). Uni LGH
(Sensing Head), Combi 4 (LSV).
Building Management System
BMS Schneider
Water Generators
Pumps/Pressurisation Units Instantaneous
electric
Heatrae Sadia
Santon
Pumps Armstrong
Grundfos
Smedegaard
Direct gas
fired
Lochinvar
Water Conditioning Drinking Water Dispensers
Water
Conditioning
Hydrotec (UK) Ltd
Enigma - Environmental
Treatment Concepts Ltd
Drinking
Water
Dispensers
Cooleraid
MIW
6.23 Approved Mechanical Contractors
The designer should advise and/or recommend to the Estates Project Manager of suitable
contractors. Estates Project Manager will make the final selection.
UWE Estates and Facilities Design Guide
Chapter 7: Electrical Engineering Design
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 1
Table of Contents 7.1 Introduction ................................................................................................................ 3
7.2 Management of Electrical Design .................................................................................. 3
7.2.1 Initial Survey ........................................................................................................ 3
7.2.2 Design Co-ordination ............................................................................................. 3
7.2.3 Initial Load Assessment ......................................................................................... 3
7.2.4 Plant, System Selection and Location ...................................................................... 4
7.2.5 Electrical Design Standards .................................................................................... 4
7.2.6 Stage Gate Approvals (RIBA Stages 2-6 2013) ........................................................ 4
7.3 Electrical Systems ........................................................................................................ 5
7.3.1 Utilities ................................................................................................................ 5
7.3.2 HV Switchgear and Transformers ........................................................................... 5
7.3.3 LV Modular Switchboards ...................................................................................... 6
7.3.4 LV Panel Boards ................................................................................................... 8
7.3.5 LV Distribution Boards ........................................................................................... 8
7.3.6 Labelling System ................................................................................................... 9
7.3.7 Metering ............................................................................................................ 10
7.3.8 Transient over Voltage Protection ......................................................................... 11
7.3.9 Power Factor Correction ...................................................................................... 11
7.3.10 Harmonic Filters ................................................................................................. 11
7.3.11 Small Power Services .......................................................................................... 12
7.3.12 Under Floor Bus-Bar System ................................................................................ 13
7.3.13 Dado Trunking System ........................................................................................ 13
7.3.14 Special Small Power Areas ................................................................................... 14
7.3.15 Electrical Supplies to Mechanical Plant .................................................................. 15
7.3.16 UPS Systems ...................................................................................................... 15
7.3.17 Generator Systems ............................................................................................. 16
7.3.18 Lighting ............................................................................................................. 17
7.3.19 Lighting Control .................................................................................................. 19
7.3.20 Lighting Control by Area Type .............................................................................. 20
7.3.21 Emergency Lighting ............................................................................................ 23
7.3.22 External Lighting ................................................................................................. 24
7.4 Fire Alarm System ..................................................................................................... 25
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 2
7.4.1 General requirements for the Fire Alarm System .................................................... 25
7.4.2 Fire Alarm System / Mechanical Systems Interface ................................................ 25
7.4.3 Fire Alarm System / Access Control Systems Interface ........................................... 26
7.4.4 Fire Alarm System / General Passenger Lifts Interface ........................................... 26
7.5 Containment and Wiring ............................................................................................ 27
7.5.1 Individual Wiring Methodology ............................................................................. 27
7.5.2 Individual Containment Methodology .................................................................... 29
7.6 Ancillary Services ...................................................................................................... 29
7.6.1 Lightning Protection System and Surge Protection ................................................. 30
7.6.2 Assistance Call Systems ....................................................................................... 30
7.6.3 Wall Clocks......................................................................................................... 31
7.6.4 Electrical hand and hair dryers ............................................................................. 31
7.6.5 Hearing Assistance Systems ................................................................................. 31
7.6.6 Lifts ................................................................................................................... 31
7.6.7 CCTV, Security Alarm, Access Control and Car Park Barrier Systems ........................ 32
7.6.8 Disabled Refuges ................................................................................................ 33
7.7 Energy ..................................................................................................................... 34
7.7.1 Photovoltaics (Where Required) ........................................................................... 34
7.7.2 Inverters ............................................................................................................ 34
7.7.3 Online monitoring ............................................................................................... 34
7.7.4 Considerations .................................................................................................... 34
7.7.5 Demand Side Response ....................................................................................... 34
7.8 Commissioning .......................................................................................................... 35
7.9 Management of Isolation ........................................................................................... 35
7.10 Lessons Learned ....................................................................................................... 36
7.10.1 Tracing / Identification ........................................................................................ 36
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 3
7.1 Introduction
All designers must be familiar with Chapters 1, 2 and 3 of the UWE Design Guides before
commencing any design work.
This current Chapter of the design guide relates to electrical engineering design.
7.2 Management of Electrical Design
Chapters 1, 2 and 3 of this guide states that all designers must consult with a range of stakeholders
including end-users and the Facilities department, during design development. This may be in the
form of structured liaison meetings organised by the internal or external project manager.
Electrical designers, depending on their exact discipline and the nature of the project, will need to
take the following actions:
7.2.1 Initial Survey
Survey existing services and ascertain the implications of any new works. A condition survey
may be required for works within existing areas. The designer is responsible for checking the
suitability of all existing water supplies, drainage capacity etc. at project inception.
Consideration and review of case studies and technical papers of similar applications.
Consider budgetary and energy conservation requirements.
7.2.2 Design Co-ordination
Liaise with all members of the design team including the building designer and structural
engineer to provide an integrated building/ structural / services installation. This must include
coordination of electrical contractors’ work requirements, plant space and significant apertures
within the structure.
Particular attention must be paid to the end-users small power requirements.
Coordination is required with the mechanical services designer regarding the power and control
requirements for the mechanical services.
Likewise, IT infrastructure has specific power, and energy consumptions, requirements which
are discussed in this Chapter (but also see Chapter 8). There must be close co-ordination
between the electrical services designer and UWE IT Engineers.
7.2.3 Initial Load Assessment
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 4
This supports early assessment of plant space requirements for co-ordination with the building
designer.
BSRIA documents and Institutes/CIBSE rules of thumb can be used as a check.
7.2.4 Plant, System Selection and Location
Selected to maximize operational efficiency and availability.
7.2.5 Electrical Design Standards
All electrical specifications and designs shall comply with the current version of BS7671 at the time
the design is prepared including all amendments.
This shall be as a minimum standard to be achieved and / or as supplementary requirements to
detailed technical clauses which relate to a specific aspect of an installation.
If there are any doubts or questions relating to electrical systems or standards required, the
designer shall discuss these with UWE Estates department.
7.2.6 Stage Gate Approvals (RIBA Stages 2-6 2013)
On major capital projects (nominally any project over £2.5m), UWE will adopt BSRIA BG6 Design
Framework for Building Services to manage the allocation of design responsibilities. At the
discretion of the UWE Project Manager, BG6 shall be applied to projects of lower value (especially
where there is a heavy emphasis on building services).
BG6 contains a number of pro-forma templates to be used at different RIBA stages. Due to the
fact that UWE is an informed client, most of the pro-forma 1 activities have been or will be carried
out in-house by UWE (e.g. obtaining and providing existing building information) and other project
processes are in place to ensure this is done.
Therefore, design teams will only be required to use pro-forma 2 onwards contained in BG6.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 5
7.3 Electrical Systems
7.3.1 Utilities
The designer shall ensure that, where there is an existing supply to an existing building, it is of a
suitable type and capacity for the new anticipated load. Consideration shall be given to the load
growth of the installation and time/season of the year. Measurements over a period of 1 month
shall be taken to ascertain the existing electrical load profile. Where programme allows, the month
of monitoring shall apply to the month most anticipated to have the greatest electrical demand.
Where a new supply is required, the designer shall be responsible for liaising with UWE estates
engineers to confirm a suitable connection point for a new supply of adequate rating and capacity.
Marker tape shall be installed above all buried cables. The tape shall be yellow PVC or polyethylene
ribbon at least 150 mm wide and shall be printed with the words “ELECTRIC CABLE” in bold capital
letters throughout its length and at intervals not exceeding 700 mm.
When producing external design drawings please refer to ‘NJUG guidelines on the positioning and
colour coding of underground utilities apparatus’.
7.3.2 HV Switchgear and Transformers
Any new substation shall be connected to the site wide network, connection details shall be agreed
with UWE Estates.
HV switchgear panels shall be built to IEC 60694 and appropriate sections of IEC 62271 -200 2012
or 62271-202:2014 for prefabricated Sub stations.
Switchgear shall be a minimum of IP44 and selected according to site conditions.
Switch Panels shall be equipped with intelligent microprocessor protection relays and trip units
offering data measuring and appropriate communication facilities.
All Ring Main Units (RMU) shall be of the Non Extensible Type, unless specified otherwise.
Ring Main units to be provided with VIP protection relays to ensure that discrimination can be
achieved. Time fused link may also be considered once full calculations have been carried out at
detailed design stage. RMU’s shall also be provided with a voltage presence indicating system and
also have a Pfisterer facility to enable phase comparisons to be carried out at the RMU.
Phase rotation shall be verified when replacing equipment to ensure that cross phasing does not
occur and supplies are not connected to cross phases.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 6
Each new RMU shall be provided with Earth Fault Passage Indication units.
All new equipment shall be of the same manufacture, the preferred UWE supplier being Schneider
Electric utilising ‘Ringmaster’ units, the outline design is based on these units.
It should also be noted that as of the 1st July 2015 Directive No 548/2014 came into force and is
aimed at reducing the amount of energy unnecessarily wasted through transformer losses.
All new transformers shall be, super / ultra low loss, hermetically sealed. Insulating fluid shall be
Model 7131. Low loss cast resin transformers may be proposed where circumstances necessitate
their use, but cast resin transformers are not the preferred transformers.
Transformers shall be sized to ensure their most optimum performance. Each substation shall
require a specialist earthing and bonding design to provide a safe environment and allow the HV
and LV earth terminals to be interlinked. New main earth bars shall be required at each substation
location. The design will firstly require specialist on-site measurements and survey, as well as the
existing fault characteristics and HV supply substation ‘hot’ or ‘cold’ designation to be known.
The consultant shall engage with a HV an earthing specialist to produce a HV earthing design for
each/ all substations. The design shall show details such as the main earth bar and all sized
connections and recommendations for all bonding within each substation.
All electrical switchboards shall be provided with a 1m wide carbon free rubber mat or mats having
a ribbed upper surface and being of such continuous length to suit the full operating extent of each
switchboard.
Where a design entails work on electrical plant within an existing substation, the designer shall
include for a HV earthing specialist to produce a report on the existing HV earthing arrangements
and provisions. The report and any recommendations shall be discussed with UWE Estates on how
these may be implemented in a project.
Approved Equipment and Companies - Schneider Electric, Square D, Siemens, Reyrolle, or
Hawker Siddeley Switchgear.
7.3.3 LV Modular Switchboards
Switchboards shall be a minimum of Form 4b Type 6 construction.
Air Circuit Breakers shall be installed (ACB’s) on all incoming and bus-section switches. The ACB’s
shall be equipped with intelligent microprocessor protection relays and trip units offering data
measuring and communication facilities.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 7
Switchgear shall have pulsed output, kWh and kVArh digital meters with serial output for A, V, kW,
kVAr and power factor. Metering to be provided for each outgoing circuit and be linked to the UWE
campus Elcomponent system.
A separate cubicle shall be provided for the termination of all metering outputs and external control
circuits. Access shall be possible with the switchboard remaining live.
Outgoing switches up to and including 630A shall be Moulded Case Circuit Breakers however fuse-
switch types may be considered where necessary to overcome discrimination issues.
Outgoing switches rated at 630A to 1000A or over, shall be ACB type.
Switchboards shall incorporate transient voltage surge suppression protective devices.
Allowances of at least 25% spare capacity shall be made for future expansion.
Spare cubicles shall be incorporated into the design of LV modular switchboards for future
adaptations.
An assessment of the harmonics content and power factor correction requirement for the connected
loads shall be made at the design stage. Appropriate measures shall be incorporated into the design
of the LV modular switchboards.
Devices for locking-off switches for future maintenance and isolation purposes shall be provided
within the specification and final switchboard installations. The padlocks and keys shall be suitably
engraved for identification purposes.
Switchboards shall incorporate transient voltage surge suppression protective devices.
Access space to be allowed to the rear of the panels to enable maintenance. Resistive rubber mats
to BS 921:1976 to be provided for all accessible sides of LV switchboards (in addition to HV).
7.3.3.1 Discrimination/ grading study
The electrical contractor shall allow for carrying out a complete discrimination and protection
grading study of the complete electrical distribution system, including all connected equipment.
Provide fault (short circuit) calculations for the distribution system as indicated on the
drawings and a protective device co-ordination study to ensure that all protective devices
are co-ordinated. Base the study on the actual devices and cable lengths installed.
Prepare the fault calculations and protective device study with a network analyser, digital
computer or by written calculations, include complete fault calculations for each proposed
source and combinations thereof including motor and generator contributions.
Carry out the protective device co-ordination study including the following:
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 8
Time-current co-ordination curves graphically indicating the proposed co-ordination for the
system on log-log graph transparencies. Include on each sheet, a complete title and one line
diagram identifying the specific portion of the system covered.
A detailed description of each protective device identifying its type, function, manufacturer
and time current characteristics and tabulation of recommended settings.
Include on the curve sheets, system HV equipment relay characteristics, pertinent
transformer, motor and generator characteristics including up to the largest outgoing LV
circuit breaker/fuse for each distribution board. Indicate manufacturing tolerances clearly
showing the final grading margin.
Carry out adjustments of the protection settings to conform with the requirements of the study.
Ensure that discrimination is achieved throughout the network and select protective devices and
settings accordingly.
Approved Equipment and Companies - Schneider Electric or Square D.
7.3.4 LV Panel Boards
Modular Panel boards shall be built to relevant sections of BS EN 60439.
Form 3b type 2 as standard, however use of outgoing neutral or 4 pole breakers can increase the
form rating to form 4b types 2 and 6.
LV panel boards are ideally suited to installations where space is restricted or few outgoing circuits
are required.
Ratings from 250A up to 1600A.
May be used as a main switchboard or sub distribution board.
Approved Equipment and Companies - Schneider Electric or Square D.
7.3.5 LV Distribution Boards
Allowance to be made for future expansion. Distribution boards shall have at least 25% spare
capacity.
Separate or split distribution boards shall be provided to segregate the following services: lighting
services and small power services.
MCB’s and RCBO’s to have a minimum rated breaking capacity of 10kA
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 9
3No. MCB lock out kits to be provided with each distribution board.
RCBO’s to be single module units.
Distribution boards to be provided with door locks.
Distribution boards to incorporate a main switch disconnector. Devices for locking-off MCB and
RCBO for future maintenance and isolation purposes shall be provided within the specification. The
padlocks and keys shall be suitably engraved for identification purposes. All keys to be handed over
to UWE estates electrical engineers.
This small be a minimum of Form 3, Type 2 (as detailed in BS EN 60439). The designer shall,
however, assess the use/application and use a higher rated board if considered necessary.
Approved Equipment and Companies - Schneider Electric or Square D.
7.3.6 Labelling System
All electrical switch rooms or electrical cupboards shall be identified with appropriate signage as
agreed with UWE estates.
All accessories shall be labelled with the distribution board room number, distribution board number
and circuit reference.
Details of cable sizes and type, protection device ratings, and point of origin shall be labelled on all
LV switchboards, panel boards and distribution boards.
Details of Ze readings with the date of test shall be displayed at each switch board/panel
board/distribution board.
All distribution boards shall have engraved labels fixed to the front of the distribution board.
Dyno labels shall be used to identify all circuit descriptions within each distribution board (adjacent
to MCB’s).
All cabling shall be identified by ferrule type cable markers on all phases, neutrals and cpc’s.
All new distribution board and circuitry shall adopt UWE standard methodology for labelling.
Labelling standards to be obtained from estates team.
UWE have an asset tagging system in place, the consultant shall familiarise themselves with UWE
requirements and ensure this is captured within the design.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 10
Warning labels showing voltage affixed to all switchboards, panel boards and distribution boards.
7.3.6.1 Circuit Charts
An accurate circuit chart is to be provided for all new distribution boards or boards which have been
altered. An electronic copy is to be provided to the UWE Electrical Engineer. A hard copy is to be
laminated and positioned adjacent or within the distribution board.
7.3.7 Metering
Metering and sub metering of the electrical distribution shall be installed as per CIBSE guide TM39
and BREEAM requirements. For the electricity metering the following principles should be followed:
Any major plant that consumes more than 10% of the building energy should be sub
metered.
Sub metered per floor.
Sub metering of lighting and small power separately.
Sub metering any lettable spaces e.g. leased spaces to shops or businesses within UWE.
Any cooling loads shall be metered separately.
Sub-metering of electrical supplies shall be provided in accordance with the requirements of the
Building Regulations specifically “The Building Regulations 2000 part L Conservation of Fuel and
Power”.
Metering units shall be installed to all distribution boards either in the main switchboard or
integrally in each distribution board. All meters shall have pulsed outputs.
Metering units shall be linked to the Facilities – Estates Elcomponent Energy Monitoring Package
and the ‘Power Logic’ monitoring and diagnostic system. An analysis study shall be completed for
the buildings to ensure that radio signals can reach the existing transmitter/receiver of the Facilities
– Estates Elcomponent Energy Monitoring Package and that there is spare capacity on the
Elcomponent system. Where the signal strength is weak or not present then number of additional
transmitter/receiver units shall be installed as required.
All necessary equipment required to ensure that each metering unit can be connected onto the
Facilities – Estates Elcomponent Energy Monitoring Package including data points and power
supplies shall be provided. Where required, allowance shall be made for modifying and/or extending
the existing system as required ensuring that it is sufficiently sized to accommodate the additional
metering units within the buildings and an additional 25% spare capacity.
Where the system needs to be augmented then a complete system shall be installed.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 11
7.3.8 Transient over Voltage Protection
The main switchboard shall have an integral three phase and neutral transient over voltage
protection unit to protect the system from the effects of lightning strikes and harmonic spikes.
The transient over voltage protection unit shall be sized and rated to suit the application.
Other protection may be required for outgoing supplies, but this shall be determined by the
lightning protection and surge protection assessment.
Designed to BS6651: 1999 Code of practice for protection of structures against lightning.
Approved Equipment and Companies - Furse or Dehn
7.3.9 Power Factor Correction
If any switchboard has a permanently connected standby generator that supports part or the entire
switchboard upon loss of normal mains, the design and installation shall ensure the power factor
correction is not active on the bus bar sections of the generator.
A suitably sized spare way on the main switchboard shall be provided for the installation of power
factor correction. Power factor correction shall be provided with detuned capacitors to serve the
whole building. The switchboard shall have integral power factor correction equipment comprising
multiple 25kVA capacitor banks to correct the reactive load and automatic switching control of each
bank to apply the necessary capacitance.
The power factor shall be installed to maintain a power factor between 0.95 lagging and unity at
any given time.
7.3.10 Harmonic Filters
A suitably sized spare way on the main switchboard shall be provided for the installation of
harmonic filters. The harmonic content of the system shall be monitored following the completion of
the installation forth first three months and the results shall be made available to the Facilities –
Estates Department, UWE University. Should the harmonic content be above the limit as detailed in
G5/4 ‘Limits for Harmonics in UK Electricity Supply System’ then harmonic filters shall be installed to
reduce the levels to an acceptable level.
The harmonic content metering capability shall be incorporated in the main incoming supply meters
for each LV switchboards.
For particular items of equipment that are known to produce high levels or harmonics, dedicated
filtering should be considered at the design stage.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 12
7.3.11 Small Power Services
The number of socket outlets and dedicated supplies shall be derived from client briefing and
project specific room data sheets.
Small power systems shall be designed to comply with the requirements of the latest edition of the
IET Wiring Regulations BS7671 and current amendments and other applicable British and European
Standards and Codes of Practice.
Room data sheets detail the minimum requirements for small power outlets in each area. However
where PC’s are to be utilised in the space, circuits shall be limited to accommodate a maximum of 8
no. PC’s per circuit. Allowance shall be made for future expansion on each other sub circuit.
The installation layout drawings for small power shall include all small power outlet locations, circuit
references and outlet types. Within all spaces where PCs are likely to be used all twin switched
13A, 230V socket outlets shall have dual earths and outboard switches. The circuit cables shall be
4mm2and arranged as dual earth circuits.
Dedicated single small power outlets shall be provided for cleaners use, with the cleaners sockets
being single gang colour RED. These shall be equipped with 30mA RCD protection. The designer
shall ensure there is a red cleaners socket on all stairwell landings, in each normally occupied room,
of 10m spacing intervals in corridors and in large rooms/ areas.
All teaching rooms, lecture rooms and meeting rooms shall be provided with 13A socket outlets,
audiovisual outlets, RJ45 outlets for data points and a telephone point for the Audio visual and IT
installations, and containment for future Audio visual and IT installations. The requirements are
contained in a separate Audio visual and IT specification.
Many people with disabilities use equipment that needs to be recharged regularly. Multiple power
points with contrasting colour cover plates shall be available at waist height around rooms.
IT server racks or wall mounted server racks shall be supplied via a dedicated circuit. The protective
device will be a 32A type C MCB and supplied via a 32A commando socket.
Where new mains comms rooms are being installed that contain more than one cabinet, the room
shall be provided with a dedicated distribution board that in turn supplies the dedicated circuits for
commando sockets.
UWE are currently implementing the installation of ‘Lecture capture facilities’ on all campuses. Final
details on the requirements are to be obtained from UWE Estates.
Approved Equipment and Companies – MK or Crabtree.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 13
7.3.12 Under Floor Bus-Bar System
In areas with raised access floors an under-floor bus-bar system shall be provided to serve 13A
socket outlets.
The bus-bar shall comply with the requirements of the latest edition IET Wiring Regulations. Wiring
to the under-floor bus-bar shall be in XLPE/SWA/LSF cabling installed directly on the slab floor (the
armour shall not be used as the sole method of CPC or earth reference). All under-floor bus-bar
system shall be rated at 63A and shall be supplied cables sized for the full load of the bus-bar. Bus-
bar shall be provided under certain teaching spaces, IT suites, meeting rooms, offices and studios
where raised floors are available and the diversity of sockets and floor boxes dictates. This shall be
considered on a project by project basis.
The under-floor bus-bar system shall enable the connection of the four compartment floor boxes.
The bus-bar track shall be located in the floor with the maximum spacing of 5.5 metres between
bus-bars and 2.5 metres from walls. The floor boxes shall be fed via prewired 3 metre un-fused tap
offs, the use of fused type tap offs to served floor boxes shall not be permitted.
Under-floor bus-bar systems in IT suites and office areas shall be used to enable connection to desk
mounted socket outlet modules. The desk mounted 13amp socket outlet modules are to have USB
charge facilities and shall be fed via prewired 5 metre fused tap offs which shall exit the floor void
via grommets mounted in the floor. The desk mounted socket outlet modules shall be provided as
part of the electrical installations work. Each tap off unit identified in the room data sheets shall
consist of an electrical supply to the desk mounted socket outlet modules and an RJ45 data outlet.
Floor Boxes shall be of the MK, Crabtree or Legrand type and shall be selected to suit the
installation requirements.
Approved Equipment and Companies – MK, Legrand, Crabtree or Office Electrics.
7.3.13 Dado Trunking System
Dado Trunking can be installed in areas where raised floors are not installed. The extent of use of
dado trunking shall be discussed with UWE Estates and the architect for each project.
Dado trunking shall be 3 compartment, as per Marco Elite shall be installed around the perimeter of
rooms and columns. The dado trunking shall be installed above desk height. The dado trunking
shall accommodate a single or twin switched 13 amp socket outlets and CAT 6 data/voice outlets.
The 13amp socket outlets mounted on the dado trunking shall be wired in Ring configuration and
NO spurs shall be permitted.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 14
The central compartment covers of the dado trunking shall be grey in order to comply with Part M
and provide a 30% visual contrast to the colour of white socket outlets.
Desk mounted socket outlet modules, complete with USB charging points, shall be provided and
installed to connect the desk to the dado trunking.
Approved Equipment and Companies – Marco Elite, Office Electrics.
7.3.14 Special Small Power Areas
7.3.14.1 Studios and Workshops
The electrical distribution system in studios and workshops shall be configured such that all of the
small power outlets (except cleaner’s outlets) can be isolated through one removable key switch
located within the studios and workshops. A ‘Firewatch’ panel shall be installed for this purpose.
Emergency stop buttons shall be installed throughout the studios and workshops to isolate power if
activated. Stop buttons shall be ‘non-latching’ type buttons and isolate all power to machinery and
open sockets and where applicable Gas shut off interlocking installed.
Socket outlets shall generally have RCD protection except where they have been
installed specifically for data equipment. If RCD protection is to be omitted. Then the designer
shall produce a documented risk assessment to explain their decision.
Sockets for cleaners shall be installed on a separate circuit and shall not be affected by the
emergency stop system.
Machinery socket outlets shall be MK Commando type outlets to prevent students from plugging in
unauthorised power tools and the requirement shall be project specific.
7.3.14.2 Laboratories
The electrical distribution system in laboratories shall be configured such that all of the small
power outlets (except cleaner’s outlets) can be isolated through one removable key switch located
within the staff office area.
Emergency Isolation Points, inter-linked to gas supply shall be installed throughout the laboratory to
isolate power and gas supply if activated. Stop buttons shall be ‘non -latching’ type buttons and
isolate all power to machinery and open sockets.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 15
Socket outlets shall generally have RCD protection except where they have been installed
specifically for computers, etc. If RCD protection is to be omitted. Then the designer shall produce
a documented risk assessment to explain their decision.
Red sockets for cleaners shall be installed on a separate circuit and shall not be affected by the
emergency stop system.
7.3.15 Electrical Supplies to Mechanical Plant
Installations in connection with mechanical engineering services power supplies and control circuits
shall be supplied using information from the mechanical services design.
Power supplies and control cabling shall be provided, as required, to all items of mechanical plant
and equipment.
Plant power supplies shall be wired in XLPE/SWA/ LSF cable run on suspended cable tray from
mechanical control panels located in the plant rooms.
Equipment power supplies, such as for extract fans, shall be wired in 6491B (XLSF) cable run in
trunking and conduit.
The controls wiring shall be installed in cabling and containment systems as required to match the
requirements of the Mechanical services design and the requirements of the controls/BMS supplier.
7.3.16 UPS Systems
UPS systems shall be selected to protect ‘critical loads’ from loss of mains power supply. Typical
critical loads to be considered are data storage and processing systems, telecommunications
network equipment and point of sales terminals.
Consideration must be given to:
The size of the load
The load type
The load process requirements
The configuration type i.e. 1N, 2N, N+1 etc.
The installation of a fully safety interlocked, full wrap around maintenance By-pass
Separate LV supplies, one to the rectifier and the other to the static by-pass
The space available to house the equipment
The suitability of the proposed location (size and weight)
Access to the proposed locations
Future expansion of the system
The additional requirement for mechanical cooling
Period of autonomy required for each application
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 16
Provision of wrap-around by-pass facility
Separate supply for static by-pass
Any provision of UPS shall be considered on a project by project basis, and technical
proposals discussed with UWE Estates during the design stage
Approved Equipment and Companies - Chloride or UPS Systems
7.3.17 Generator Systems
Generator systems shall be selected to provide a secondary power supply to various systems in the
event of mains power failure.
Typical loads to be considered but not limited to are fire evacuation lifts, evacuation lifts,
mechanical smoke ventilation systems and essential supplies.
Consideration must be given to:
The size of the load
The load type
The load process requirements
The configuration type i.e. 1N, 2N, N+1 etc.
The space available to house the generator
The suitability of the proposed location (size and weight)
Access to the proposed locations
The additional requirement for mechanical cooling
Period of autonomy required for each application
Fuel storage with fuel polishing facility, double-bunded tank and fully alarmed
BMS interface
Any provision of generator shall be considered on a project by project basis, and technical
proposals discussed with UWE Estates during the design stage
Approved Equipment and Companies - Broadcrownor F.G Wilson or Dale Erskine
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 17
7.3.18 Lighting
7.3.18.1 Lighting Levels and Limiting Glare Indexes.
All lighting is to be designed in line with the relevant standards, including the CIBSE Lighting Guides
and Code for Lighting.
7.3.18.2 Electrical Load and Lighting Calculations
The appropriate load calculations shall be included for all design presented to the UWE Estates
Department for comment and/or information. Designers are required to enter the appropriate
values into a spreadsheet format. Appropriate Dialux lighting design submissions will also be
acceptable.
Lighting levels in lux, uniformity, glare indexes along with energy targets and W/m2 values to be
submitted for each room/space.
The artificial lighting design shall meet the most current and appropriate requirements of Building
Regulations Part L2. Areas that fall outside these parameters shall be highlighted to UWE Estates.
7.3.18.3 General Design Requirements for Lighting
The lighting system shall be designed so that it complies with the most recent edition of Building
Regulation Approved Document Part L.
Our preferred means of lighting distribution is by the use of modular, plug-in systems (such as Flex
7). This system, however, must not be used on central battery systems where fire-rated cables are
required out to each luminaire.
Low energy light sources shall primarily be LED and any deviation from LED technology shall be
approved by UWE Estates prior to detailed design.
All luminaires shall have light output ratios (LOR’s) of >0.8 and incorporate high efficiency DALI
control gear.
Generally, the colour temperature of lamps shall be 4000K (Intermediate).
Provide adequate switching arrangements where applicable to permit ‘good housekeeping’ by staff
and students. The switching facility should provide flexible local control for changing patterns of use
and occupation and also permit considerable reductions in lighting load for out-of-hours security
patrols.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 18
Careful consideration shall be made for future maintenance tasks in relation to the positioning of
luminaires and mounting height. Consider the use of uplighters and suspended lighting systems for
rooms with high ceilings. Attempt to eliminate from the design, the requirement for the use of
access equipment for future maintenance tasks.
Architectural and interior design requirements should be closely co-ordinated in respect of colour
rendering and display effect without compromising energy cost.
Where applicable, a minimum of 10% of each lamp type shall be provided as spares within the
specification and be supplied to the Estates project manager at Handover stage.
All indoor lighting shall comply with BS EN 12464 Part 1, in teaching rooms and lecture rooms the
consultant shall follow the recommendations of CIBSE Lighting Guide LG5.
For all offices the consultant shall follow the recommendations of CIBSE Lighting Guide LG7.
The design documentation shall be produced, and submitted for examination at the request of UWE
estates engineers. This documentation shall include detailed calculation sheets for each sub and
final circuit, showing connected load, circuit protection type and rating, load current, voltage drop
and derivation of protective conductor sizes.
A luminaire schedule shall be presented to UWE estates during the design stages. This will allow
UWE estates to review the selected luminaires and request product samples of any luminaire the
university is unfamiliar with. This exercise will need to be completed in sufficient time prior to final
order placement with the luminaire suppliers to avoid contract delays being incurred during the
installation period.
Where it is practicable to utilise suspended multitrack lighting trunking; Zumtobel Tecton shall be
used. Circuit header wiring to be selected as appropriate.
Accessibility Guidelines (If applicable)
All teaching spaces are to be naturally lit as far as possible.
Flexible lighting options shall be provided with a view to light spectrum, light intensity, and
window blinds.
Lighting levels must be sufficient and not create glare.
Bare bulbs are to be avoided. Translucent covers to diffuse lights are recommended.
Harsh strip lighting is not appropriate.
Flexible lighting to focus on the face of the presenter (so lip-reading is enhanced) and on a
sign language interpreter in a lecture theatre or seminar settings.
Approved Equipment and Companies – Zumtobel, iGuzzini, Riddi, Trilux, Reggiani or Fagerhult
(Luminaire manufacturers to be review annually).
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 19
7.3.18.4 Daylighting
In accordance with the energy section of the BREEAM assessment, and to help to achieve the
required BREEAM rating there is a requirement to incorporate good day lighting into the design.
Consideration shall be given to all spaces where enhanced daylighting can be utilised. The
positioning of daylight sensors shall ensure maximum energy savings from utilising natural daylight
can be achieved.
7.3.18.5 Task Lighting
If required, due to visual impairment or specific activities, this will be included in the client brief and
will be assessed on a case-by-case basis.
7.3.19 Lighting Control
General: The lighting controls within the building shall comply with the most recent edition of
Building Regulation Approved Document Part L and LG14: Control of Electric Lighting.
The lighting control system in open space offices shall have the following:
Absence/ presence detection (PIR’s shall have the ability to be programmed as either)
incorporating local switching to all office spaces. Absence/ presence detection shall be
provided in line with manufacturers specific guidelines so as to detect any personnel in any
area and at any workstation.
In general daylight dimming shall be utilised in areas where natural daylight makes it
appropriate to do so.
Presence detection is used in toilets and corridors. Absence detection is used in other
spaces, with a rocker switch by the room entrances to enable users to switch lights on / off
when required.
Store rooms/cupboards which require lighting shall have PIR or manual switch.
Manual switches where used shall be provided in accordance with the most recent edition of
“The Building Regulations Part L2 Section ‘Controls for general lighting in all types of
spaces’” which stipulates that ‘the distance on plan from any local switch to any luminaire it
controls should generally be not more than 6 metres or twice the height of the luminaire
above the floor if this is greater’.
Lighting Control Modules shall be used where practicable.
For smaller installation a Zumtobel Dimlite control system is preferable.
For larger installations a Zumtobel Litenet control system is preferable.
Zumtobel Tecton Track shall be utilised where practicable.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 20
All luminaires specified shall have a Dali ballast as larger and smaller installations will need a Dali
Approved Equipment and Companies –Zumtobel or (Philips Occuswitch for very small applications)
7.3.20 Lighting Control by Area Type
7.3.20.1 Reception Areas
Lighting control shall be provided to allow for the ease of operation of individual circuits and operation of
a number of pre-set scenes via a DALI touch screen control panel with graphical display.
Lighting to be controllable as individual effects and areas for scene setting by the lighting control system
7.3.20.2 Café Areas
DALI lighting control shall be provided to allow for the ease of operation of individual circuits and
operation of a number of pre-set scenes via a touch screen control panel with graphical display.
Lighting to be controllable as individual effects and areas for scene setting by the lighting control system
7.3.20.3 Exhibition Space
DALI lighting control shall be provided to allow for the ease of operation of individual circuits and
operation of a number of pre-set scenes via a touch screen control panel with graphical display.
Lighting to be controllable as individual effects and areas for scene setting by the lighting control system
7.3.20.4 Teaching Spaces
DALI lighting controls shall be provided by absence/ presence detection and retractive switching. The
lighting will generally be provided by rows of luminaires running parallel to the teaching surface.
Local switches shall be provided to allow the occupant to switch ‘off’ lighting when not required.
Lighting shall be manually switched in rows of luminaires running parallel to the teaching surface so as
to turn off lighting adjacent to the interactive whiteboard/projector screen.
Two rows of fittings running parallel to the building perimeter façade shall be provided with daylight
linking dimming control to maximise the use of the available natural light.
In general, teaching spaces shall have a Zumtobel Circles Switch providing 3 scenes as detailed below:
Scene Function provided
1 Lights full on
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 21
2 Projection mode (turning lights off adjacent to the screen)
3 All lights dimmed (60%)
In the event that spotlights are required in larger teaching areas to illuminate the speaker’s lectern
(which can assist with lip-reading etc.), the spotlights shall be selected, positioned and angled to prevent
glare on presentation screens or otherwise diminish the visual acuity of presentations.
7.3.20.5 Workshop and Laboratory Rooms
Lighting controls shall be provided by manual switching only.
7.3.20.6 Breakout/Social Learning Areas
Lighting shall be DALI controlled by absence/presence detection and retractive switching for DALI
control.
Additional ceiling recessed detectors shall be used to ensure sufficient presence detection coverage
is provided to prevent nuisance automatic switching of the lighting.
7.3.20.7 Open Plan and Cellular Offices
Lighting shall be DALI controlled by absence/presence detection and retractive switching for DALI
control.
Two rows of fittings running parallel to the building perimeter façade shall be provided with daylight
linking dimming control to maximise the use of the available natural light.
Local switching shall also be provided in rows to allow the occupants to switch ‘off’ or dim lighting
when not required.
7.3.20.8 Meeting and Interview Rooms
Generally lighting controls shall be provided by DALI with absence/ presence detection and
retractive switching.
Where the meeting room or interview room has an external window then the lighting shall
also be daylight linked.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 22
7.3.20.9 Corridors
Lighting controls shall be provided by presence detection. Where appropriate the lighting within
corridors shall be linked with photocells such that if there is sufficient natural light, within corridors
then the artificial lighting will switch ‘off’.
Consideration should be made to corridor illumination when the building is still in use to ensure that
people do not step in to unlit corridors.
7.3.20.10 Staircases
Lighting controls shall be provided by presence detection. Where appropriate the lighting within
staircases shall be linked into photocells such that if there is sufficient natural light within a
staircase then the artificial lighting will switch ‘off’.
In a building with a networked lighting control system, the lighting on staircases shall remain
illuminated when the building is occupied and shall not switch off, except where photocells sense
that there is sufficient natural light, until the lighting control system senses the building is empty.
7.3.20.11 Library
The lighting control shall be by manual retractive switching and presence detection.
7.3.20.12 PIR Settings (General)
Type or Area Duration (Mins)
Corridor 20
Stairwells 20
WC’s 20
Shower Rooms 20
Changing Rooms 20
Offices (controlled on presence) 20
Classrooms (controlled on presence) 20
Cleaners Cupboard/ Store 10
Kitchenette 20
Equipment Cupboards/ Stores 10
Meeting Rooms 20
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 23
7.3.20.13 PIR Settings (Student Accommodation)
Type or Area Duration (Mins)
Corridor 20
Stairwells 20
WC’s 20
Ensuite Bathroom 20
Communal Kitchen 20
Amenity Area 20
Laundry 10
Store 10
7.3.20.14 Other Areas
Areas not covered above shall be discussed with UWE Estates.
7.3.21 Emergency Lighting
System to be designed to comply with all relevant parts of the most current edition of BS5266.
Escape routes shall have a system of emergency lighting throughout the route to the final exit from
the building.
The emergency lighting system shall be a fully automatic, centralised self-testing addressable
system. Where the scope of the project includes the provision of a new addressable system, a
data point shall be installed adjacent for future connection to a central monitoring system.
The emergency light fittings shall be LED, self-contained, self-testing and addressable, 3hr duration,
appropriately selected for the specific location and fully compatible with Zumtobel SB 128
Emergency Light test modules.
All emergency luminaires shall be wired with DALI cabling to local SB 128 Modules and central
battery system. If there is no SB128, a unit shall be provided if specified within the project scope.
The escape routes shall be indicated by maintained illuminated signage.
In buildings where sufficient quantities of emergency luminaires are to be installed and
maintenance and access to the fittings may be difficult to change batteries and the like, due
consideration shall be given to the use of a Central Battery system.
In buildings where there are large amounts of emergency lighting (up to 30KW) or increased loads
as higher lux levels of emergency lighting required i.e. High risk areas, workshops, laboratories or
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 24
kitchens, due consideration shall be given to the use of a Zumtobel Onlite central power supply
emergency lighting system.
All emergency lighting shall be labelled and identified on the SB 128 or central battery system in
line with UWE Estates emergency lighting labelling requirements.
The wiring from central battery systems shall be fully fire-rated up to and including connection.
Please see the separate section on containment and wiring.
Emergency luminaires shall have identification numbers affixed to the visible part of the luminaire.
Please remember that emergency lighting must be provided inside and in the vicinity of technical
areas that need to be accessed in an emergency (to assist staff performing isolations etc.).
Approved Equipment and Companies – Zumtobel
7.3.22 External Lighting
Where colour rendering is not critical, consideration should be given to the use of more efficient
LED sources.
External lighting shall be controlled via the combination of a building mounted photocell,
astronomical time clock and 3 position on/off and auto over-ride switch. The time clock and switch
shall be accessible to authorised persons only and shall be linked to the BMS system to give an
alarm condition on operation.
Any external lighting shall avoid upward light pollution and minimise overspill onto neighbouring
buildings, as in accordance with the ILP guidance notes for the reduction of obtrusive light.
Careful consideration shall be given for future maintenance tasks in relation to the positioning of
luminaires and mounting height.
Raise and lower or hinged columns shall be specified and approved maintenance equipment shall be
free issued to estates to carry out future maintenance works on all external column mounted
luminaires.
Due consideration shall be given to the maintainability on the selection of columns or fittings that
can be folded or lowered to limit the need for work at height
Consider the use of LED bollard lights and street lights to illuminate external walkways as opposed
to floodlighting an area.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 25
Approved Equipment and Companies – Thorlux, Simes or Philips Speedstar range or equal and
approved.
7.4 Fire Alarm System
7.4.1 General requirements for the Fire Alarm System
All new fire alarm panels shall be connected to the existing site wide Gent network. Exact
requirements of connections shall be on a project by project basis.
The UWE standard for detection is Type L3 for Non-Residential and L1 for Residential.
The fire alarm system shall be designed to comply with all relevant parts of BS5839.
The fire alarm system shall be fully addressable with clear device descriptions down to room detail.
Spare capacity shall be made available for future expansion of the system.
The category of fire alarm system to be applied will be project specific and will be advised by the
fire officer.
All devices and accessories shall be selected from the same product range as the main fire alarm
panel.
Remote indicators will be required for all concealed detection devices and interface units.
Flashing beacons shall have a red lens and be EN54-23 compliant. They shall be positioned at
various locations which will include corridors and communal areas, bars and café areas, lecture
theatres, classrooms, plantrooms, toilets etc. or other locations where deaf and hard of hearing
users may be alone, including bedrooms, ensuites, kitchens and common rooms in selected campus
residential accommodation.
Plant override test switches shall be a key operated type.
In areas where entertainment equipment will be used, fire alarm interface units shall be installed to
disconnect the power to the equipment in the event of fire alarm activation.
7.4.2 Fire Alarm System / Mechanical Systems Interface
A fire alarm system interface unit shall be installed adjacent to each mechanical plant control panel.
This shall include the ventilation system and boiler plant control panels.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 26
In addition interfaces for but not limited to systems such as smoke dampers, gas solenoid valves,
CHP’s etc. shall be included.
7.4.3 Fire Alarm System / Access Control Systems Interface
All doors with electro-magnetic locking systems shall include a provision to allow the door to be
opened in the event of a fire alarm or other emergency situation. Normally this means that the
locks will automatically disengage upon activation of the fire alarm.
A fire alarm system interface unit shall be installed adjacent to each secure door with an additional
manual break glass override – coloured green – mounted local to the door.
Careful co-ordination is to be ensured between the lock installer and fire alarm system specialist.
7.4.3.1 High risk areas
If the UWE Security Services Department, in consultation with end-users, determines that an area
represents a high security risk they can require that electro-magnetic locks on vulnerable doors do
not release automatically upon activation of the fire alarm. The University Health and Safety team
will be notified of this decision and this decision will need to be recorded (e.g. in the fire strategy
and/or fire risk assessment).
7.4.4 Fire Alarm System / General Passenger Lifts Interface
The interface for the lifts shall bring the lift to the ground floor and park with doors open on
operation of the fire alarm system.
Careful co-ordination is to be ensured between the lift installer and fire alarm system specialist.
Approved Equipment and Companies - Gent Vigilon Analogue Addressable System, GENT S-
Quad components.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 27
7.5 Containment and Wiring
The designer shall utilise a factor +50% when sizing containment systems to allow spare capacity
for future adaptations.
Particular attention must be given to the selection of cable containment used to ensure the integrity
of the containment if subjected to fire.
7.5.1 Individual Wiring Methodology
7.5.1.1 Small Power
Final circuit wiring shall be wired in 6491B singles. Each final circuit cable in the distribution board
shall be fitted with a propriety cable ferrule system identifying the final circuit cable reference. The
cabling shall be sized in accordance with the latest edition of the IET Wiring Regulations.
Final circuits shall be installed in galvanised steel trunking and conduit within ceiling voids and
enclosed in galvanised steel conduit in walls.
Where it has been agreed with the UWE Electrical Engineer that final circuits may be wired utilizing
6242B LSF cables they shall be contained within steel wire basket and in all instances secured with
metallic cable ties.
In the plant and switch rooms final circuits shall be wired in 6491B LSF single core cables in
exposed galvanised steel trunking and conduit.
Within teaching spaces and the like Marco Elite 3 compartment White dado trunking must
accommodate CAT 6 data cables. Contrast inserts or contrasting dado lids are to be provided
behind accessories for DDA Compliance.
All ring final circuits shall be a minimum of 4mm2 conductor CSA.
7.5.1.2 Lighting
Internal lighting circuit cables shall not be less than 1.5 mm² or more than 2.5mm2 conductor CSA.
Final circuit wiring shall be LS0H single core cable, reference 6491B, enclosed in galvanised steel
trunking and conduit. The installation shall be concealed in the fabric of the building, flush down
walls and recessed in ceiling voids.
Lighting circuits containing high wattage luminaries (above 150W) shall be individually designed.
Cable sizes, protective devices shall be carefully calculated to suit the particular installation in these
cases.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 28
MCBs and RCBOs shall be 10A Type C with the load on each MCB limited to 5A maximum.
Luminaires are to be installed and wiring following the manufactures recommends methodology.
Above suspended ceilings, lighting control modules shall be utilised and associated flexible leads.
Emergency luminaries shall be connected varied connectors to distinguish between lighting and
emergency lighting luminaires. Lighting control modules shall be located in the ceiling void, adjacent
to the luminaire fixed to the building structure/trunking, behind an accessible ceiling tile.
Where luminaries are fixed directly to the building soffit they shall be connected direct to the final
circuit wiring with the final connections using heat resistant single core wiring from terminations in
accessible conduit boxes or adaptable boxes.
7.5.1.3 Emergency Lighting
All wiring shall comply with BS5266-1.
Central battery emergency luminaire cabling shall have a minimum conductor CSA of 2.5mm2.
Wiring shall be FP200 enhanced or an equivalent approved standard and sized in accordance with
respective circuit loading.
Central battery emergency luminaire cabling shall be installed on separate or segregated
containment exclusive for the use of emergency lighting cabling.
The use of proven metal cable fixings shall be utilised throughout. Plastic will not be acceptable.
Approved Equipment and Companies – Prysmian
7.5.1.4 Fire Alarm
All wiring to comply with BS5839-1. Cabling must meet the FP200 enhanced standard or equivalent.
Fire alarm cabling shall be installed on separate or segregated containment exclusive for the use of
fire alarm cabling.
The use of proven metal cable fixings shall be utilised throughout. Plastic will not be acceptable.
Approved Equipment and Companies – Prysmian
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 29
7.5.2 Individual Containment Methodology
7.5.2.1 General
Standard galvanised steel trunking or conduit and accessories is to be used throughout the site with
heavy gauge trunking or conduit in boiler and plantrooms.
7.5.2.2 Dado Trunking
3 compartment Marco Elite 3 white PVC dado trunking, with grey lids.
7.5.2.3 SWA Cables
Heavy duty galvanized steel cable tray and cable ladders/racks.
7.5.2.4 Data and Voice
Dedicated, medium/ heavy duty galvanized steel cable basket.
7.5.2.5 Fire Alarm
Dedicated, medium/ heavy duty galvanized steel cable tray with metallic cable ties.
7.5.2.6 Security
Dedicated, medium/ heavy duty galvanized steel cable basket.
Approved Equipment and Companies –
Dado trunking - Marco Elite 3
Accessories - Honeywell MK or Crabtree
LS0H Cables - Delta Crompton, Prysmian or Draka UK
7.6 Ancillary Services
The electrical services consultant shall ensure they interface with UWE specialists for particular
ancillary systems to ensure they have fully understood UWE requirements and have made suitable
allowances within the design to capture requirements.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 30
7.6.1 Lightning Protection System and Surge Protection
The electrical consultant shall engage a lightning protection specialist and provide them with all
required information to carry out a complete lightning protection risk assessment to ascertain the
requirements for the particular project.
The contractor shall be responsible for employing a lightning protection specialist, the lightning
protection specialist shall identify the category of lightning protection system and be responsible for
carrying out a compliant design and full installation.
Consideration shall be given by the lightning protection specialist to hide and conceal all down
conductors wherever possible.
The electrical contractor shall ensure that the cost of the lightning protection system is identified at
tender return.
Within BS EN62305, surge protection is a fundamental part of a lightning protection system. The
purpose of lightning current surge protection is to protect against dangerous sparking to minimise
the risk of loss of life and damage to the structure.
Additional co-ordinated surge protection may be required to protect sensitive electrical and
electronic equipment within the building or structure. The purpose of co-ordinated transient over-
voltage surge protection is to protect electrical and electronic systems and equipment from the
secondary effects of indirect lightning and switching transients, generated downstream of the
lightning current surge protection.
Designed to All relevant British Standards, specifically BS EN62305 and BS 7430.
Approved Equipment and Companies – Furse
7.6.2 Assistance Call Systems
Assistance call systems shall be installed in all accessible WC’s. Alarms, both audible and visual,
shall be given local to the accessible WC and also be signed to show the need to contact the main
reception within the building (if manned and applicable) or the campus gate house. This will need
to read: “When Light Flashes and Alarm Sounds, Contact East Reception on 0117 3289999 for
assistance.”
The reset button shall be located within the accessible WC.
Approved Equipment and Companies – Wandsworth
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 31
7.6.3 Wall Clocks
Unless a central system has been requested, where wall mounted clocks are required, they will be
radio controlled (MSF), with integral batteries and securely fixed in the required locations.
Approved Equipment and Companies – None specified at present
7.6.4 Electrical hand and hair dryers
Hand dryers to be installed against tiled walls.
Hand dryers shall incorporate an overheat protection device and where appropriate installed in
accordance with DDA and part M requirements.
Approved Equipment and Companies – Dyson Airblade V or Xcelerator or Airforce or Xcel Thin
Air Electrical Hair Dryers
Hair dryers shall be installed as required within RDS where appropriate installed in accordance with
DDA and part M requirements.
7.6.5 Hearing Assistance Systems
Analogue infrared transmission equipment shall be installed within each teaching room/space. The
system shall be compatible with other units installed throughout UWE.
All equipment to be housed in a locked cabinet secured to the building fabric.
All systems are to be supplied with radio microphones.
Approved Equipment and Companies – Details to follow
7.6.6 Lifts
Lifts are to be designed to comply with the Lift Regulations 1997, Part M of the Building
Regulations and all relevant parts of BSEN 81.
UWE has a legal duty to ensure the evacuation of all building occupants. In all buildings with
multiple levels, the provision of ‘evacuation lifts’ should form part of the design considerations.
Where the provision of such a lift(s) is discounted the arrangements for the evacuation of
people with a disability that would prevent them from evacuating the building unaided must be
stated.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 32
The lift shall be large enough to allow wheelchairs to turn around and/or have space for a carer
to share the lift.
Buttons and panels should be designed and positioned to be usable from a wheelchair and by
persons with reduced manual dexterity and impaired vision (e.g. large buttons, with a good
visual contrast between the number and the button).
Lifts must have trip counters fitted.
Signage in lifts shall be large clear and contrasting.
Auditory messages and visual indication must be provided to inform users of floor levels and
door opening and closing.
Lighting levels shall be compliant with levels stated within BSEN 81.
Remote communication shall be installed in all lifts.
A lift’s location in the building shall be clearly signed.
Consideration shall be given to the provision of more than one lift in a building to allow for
repairs, maintenance and break downs.
Lifts shall be installed as full evacuation lifts to BS 9999 and useable in the event of a fire.
Lighting and power sockets within the lift shaft must be designed and installed by the lift
specialist installer.
Approved Equipment and Companies – Kone Lifts or Otis Lifts
7.6.7 CCTV, Security Alarm, Access Control and Car Park Barrier Systems
The electrical services designer shall liaise with the UWE Security Services Department and building
designer to determine the requirement for CCTV, security alarm, access control and car park barrier
systems. The designer shall incorporate these requirements into his design to be provided by the
electrical services contractor and allow for all necessary power, fire alarm interfaces, data points
etc. The designer shall further include all containment and ducting requirements.
As explained in Chapter 2, it is essential that designers consider maintenance/replacement access to
cameras.
The designer shall collate all the necessary commissioning certificates for these services for
submission to the Estates PM. Projects must allow for installation of CCTV signage which is
required in law. Security Services will advise on wording.
Approved Equipment and Companies –
CCTV/Access Control, Equipment – Pelco CCTV & Continuum Access Control
CCTV/Access Control, Installer – Schneider
Security Alarm Equipment – Galaxy
Security Alarm Equipment/Installer – Shield Fire & Security
Car Park barriers – Bebarmatic
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 33
7.6.7.1 Lessons learned
Unfortunately, there are numerous examples of the wrong type of CCTV cameras being installed
and/or being installed in the wrong location. Some of these are shown in the image below but
illustrates the need to discuss the brief with security and for CCTV provision to be shown on co-
ordinated drawings:
In addition, it is all-too-common for the legally required CCTV signage to be omitted: This signage
must be provided by the project. The wording is to be agreed with UWE Security.
7.6.8 Disabled Refuges
Disabled refuges shall comply with BS5839-9:2011, BS9999:2009 and BS8300:2009.
The electrical services designer shall liaise with the UWE Safety Unit and building designer to
determine suitable locations for disabled safe refuges. A purpose made system shall be installed
and linked to the East reception gate house. The system shall incorporate an intercom system to
allow direct conversation between the person requiring assistance and the security personnel. The
main control panel shall indicate the location of the alarm by means of an electronic mimic board.
UWE requires refuges to be on stairwells (even though British Standards do not insist on this). If
deviations are required due to other constraints, they must be managed in the same way as any
other derogation.
Approved Equipment and Companies – Baldwin Boxall
Placing a CCTV camera on the side of a building,
rather than on the corner, creates a blind spot.
Blind
Spot
There is little point installing an expensive camera
with Pan, Tilt, Zoom capability in a situation where
only a cheaper, fixed camera is required
External Wall
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 34
7.7 Energy
7.7.1 Photovoltaics (Where Required)
Refer to the requirements of BS7671, including section 712.
7.7.2 Inverters
Consultant to ensure that a voltage optimiser system, or micro inverter system i.e. an inverter
system that offers individual module control visibility on the PV array is specified.
7.7.3 Online monitoring
As a minimum, the online system must have the capability for .csv data exports of hourly
generation data.
7.7.4 Considerations
Lightning protection, earthing and protective equipotential bonding.
Data point to be located next to inverter panels.
Access for maintenance and replacement.
Battery storage where appropriate (co-ordinate with architect to ensure that suitable battery
storage is included if required).
Ensure volt drop of a.c. connection is minimised to prevent the nuisance tripping of the inverter.
7.7.5 Demand Side Response
During the design stages the MEP consultants shall consider ways of reducing non-essential energy
without affecting business operations, comfort or product quality.
This may apply during the operational hours (occupied hours) of the building or out of hours.
Items that should be considered are:
Reduce HVAC to minimum levels.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 35
Reduce lighting to minimum levels.
Shut down select buildings or areas of buildings.
Raise set points on chillers a few degrees
Shut down laundry washers and dryers
Transfer load to back-up generator.
7.8 Commissioning
The designer shall ensure that the systems proposed are fully commissionable.
Commissioning shall be carried out to manufacturers’ recommendations.
CIBSE commissioning codes and BSRIA guides shall be adhered to.
100% of electrical installation test results shall be checked by the electrical designer. They shall also
witness the electrical installation testing to verify their accuracy.
The electrical designer shall attend and witness fire alarm commissioning work and verify sound
level tests.
The electrical designer shall attend and witness emergency lighting commissioning work and
lighting level tests to verify their accuracy.
The contractor shall present a schedule of all commissioning and dates available for inspections for
the electrical designer and UWE estates engineers.
Chapter 2 of this design guide provides an overview of the softlanding and handover processes and
drawing standards.
7.9 Management of Isolation
All works, method and procedures shall be in accordance with separate UWE procedures and
guidance. As a general procedure, the UWE term contractor will be engaged to manage isolations.
UWE Design Guide for Buildings
C h a p t e r 7 | E l e c t r i c a l E n g i n e e r i n g D e s i g n I s s u e 1 . 3 P a g e | 36
7.10 Lessons Learned
7.10.1 Tracing / Identification
The contractor shall allow for advance tracing, identification and recording of all existing LV and ELV
circuits that are identified during refurbishment works.
Any circuits that cannot be identified by the electrical contractor shall not be connected back into a
new distribution board.
Once these circuits have been left disconnected, if it can be confirmed that they are obsolete the
electrical contractor shall remove the circuits in their entirety.
UWE Estates and Facilities Design Guide
Chapter 8: IT Infrastructure
UWE Design Guide for Buildings
C h a p t e r 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1
Table of Contents
8.1 Introduction .................................................................................................... 2
8.2 Architectural Design ......................................................................................... 2
8.3 Design co-ordination & sequencing .................................................................... 3
8.4 Sequence ........................................................................................................ 4
8.4.1 Architectural Design................................................................................... 4
8.4.2 Build ........................................................................................................ 4
8.5 UWE Comms Room Specification ....................................................................... 4
8.5.1 UWE Comms Room Spec Diagram .............................................................. 6
8.5.2 Comms Rooms Ready Condition ................................................................. 7
8.6 IT Cabling Infrastructure .................................................................................. 8
8.6.1 Standards ................................................................................................. 8
8.6.2 UTP Termination and Containment.............................................................. 8
8.6.3 Short Patching .......................................................................................... 8
8.6.4 Fibre Termination and Containment ............................................................ 9
8.6.5 UTP Outlet Labelling Convention ................................................................. 9
8.6.6 Trace and Test ......................................................................................... 11
8.6.7 Fixed IP Addresses ................................................................................... 11
8.7 Wi-Fi Infrastructure ......................................................................................... 14
8.7.1 Overview ................................................................................................. 14
8.7.2 Wi-Fi Design and Installation ..................................................................... 14
8.7.3 Steps to plan, deploy & verify a Wi-Fi installation: ....................................... 14
8.7.4 Refurbishment Works ............................................................................... 16
8.7.5 Wi-Fi Access Point Placement (in order of preference) ................................. 16
8.7.6 Building Fabric ......................................................................................... 20
8.8 Construction Sites ........................................................................................... 21
8.8.1 Training and Certification .......................................................................... 21
8.8.2 Personal Protection Equipment .................................................................. 21
8.9 Security Infrastructure ..................................................................................... 22
8.9.1 Access Control and Door Monitoring ........................................................... 22
8.9.2 CCTV ....................................................................................................... 23
8.9.3 ANPR (Automatic Number Plate Recognition) .............................................. 24
8.9.4 Intruder Detection Systems (IDS) .............................................................. 24
8.9.5 Panic Alarms ............................................................................................ 24
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 2
8.1 Introduction
The purpose of this document is to specify the requirements for IT Infrastructure to be
included in the design of new buildings or refurbishment works done to existing buildings
within the University of the West of England.
IT infrastructure should be considered at the same time as other services (M&E, water, etc)
to avoid considerable delays and added cost due to the rework required.
IT requirements should start to be established as early as RIBA stage 1 (i.e. when
developing the client’s brief) and requirements discussed with UWE’s IT Services from RIBA
stage 2 (when UWE stakeholders should be consulted).
UWE has a large IT estate and a wide area network consisting of both fibre and copper (CAT
6) cabling. The infrastructure is routed through a series of ducts and in-building
containment. Consideration needs to be given to breaking out of new buildings and into
existing ducts in order to run fibre back to the Core network switches. Consideration must
also be given to the positioning of Comms Rooms and containment routes so as not to
exceed the maximum cable lengths. UWE’s incumbent data cabling contractor should be
involved during the development of detailed design.
IT Infrastructure is as important as power, lighting and water, and needs to come online
early in the build cycle in order to commission BMS services, door access controls and other
building related systems. Installing building services relies on Comms Rooms being in a
ready condition, dust free, with power, lighting, fibre connections and if required provision
for cooling. The details of what constitute a ready condition, the design of comes room, and
other requirements are outlined in the following sections.
8.2 Architectural Design
Design is key to the successful implementation of IT Services and to the smooth running of
the project.
The Architects for a new build or UWE Surveyor involved in refurbishments should consider
the following:
How will Fibre Optic cables come into the building? Most buildings will require
two cables to enter the building from diverse routes.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 3
What duct routes are required and how will these connect to existing UWE
duct routes? Diverse duct routes will usually be required to provide resilience.
Where will the Comms Rooms be positioned? Comms Rooms need to comply
with the minimum specification outlined later in this document. Cable lengths need to
comply with the industry standards, meaning there may be a requirement for
multiple Comms Rooms.
Where will the network outlets go and what are the cable containment
routes required to get to them? The containment routes from Comms Room to
network outlets can be considerably longer than the physical distance.
What will the network outlets be used for? What an outlet is used for will
determine how the network switch port is configured.
8.3 Design co-ordination & sequencing
The sequence of the build or refurbishment works is agreed between the principal contractor
and the University but these discussions begin in the pre-construction phase while the
programme and construction phase plan are prepared. UWE IT Services need to be engaged
as early as possible in the process in order to explain the pre-requisites and dependencies
for getting the building online at the earliest opportunity.
Before foundations are laid, the duct routes should be known and accessible. Past
experience has shown that the location of the contractor compounds and placement of plant
equipment sometimes fails to take into account the building of and access to duct routes
(e.g. positioning site cabins on top of manhole covers). This can introduce delays and
additional costs when fibres need to be run into the building.
UWE IT Engineers are the only personnel permitted to install network switches and only
once Fibre cables have been installed and connected back to appropriate Core Network
switches. Comms Rooms must meet the minimum specification required before equipment is
installed.
The installation of BMS devices, sensors, cameras, access control, etc. can only be installed
once the Network switches have been installed and when any fixed IP addresses required
have been allocated.
UWE IT Services will install Wi-Fi and Audio Visual equipment following the installation of
the network switches. The installation of further equipment, PCs, Printers, etc. is usually
done following handover of the building from the principal contractor to the University.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 4
8.4 Sequence
8.4.1 Architectural Design
1. Building duct routes specified, including break out of building and break into existing ducts.
2. Comms Room placement agreed, taking account of cable lengths and containment routes.
3. Comms Rooms specified, taking account of UWE requirements, see Section 4.
8.4.2 Build
4. Contractor compound and plant equipment placements not restricting access to existing cable and other service ducts.
5. Comms Rooms in ready state (with power, lighting, secure door, cooling if required) to enable commissioning of building management systems, etc.
6. Fibre Optic cables installed and connected to the UWE core network switches. 7. Structured Copper (Cat 6) cables installed and terminated at the patch panel (see
note below) 8. Network switches configured and installed. 9. BMS, Access Control, CCTV, etc. devices installed and commissioned 10. Wi-Fi and AV equipment installed
Note: The installation and configuration of network switches must be done at least one
week (5 working days) prior to use by end users. The cabling contractor should therefore be
working to a completion date at least two weeks prior to the end date. Failure to allow
enough time for the installation, configuration and testing of the network may result in
delays to the project.
8.5 UWE Comms Room Specification
Room
Configuration
Specific
element
Implementation to be defined by the project, but must
meet the minimum requirements as per diagram below
Electrical Distribution
Boards New Comms Rooms must have dedicated electrical circuits for
Racks
Lighting
Cooling
Each circuit should be individually protected to avoid problems
affecting other circuits.
Small Power 2x 32amp Commando Sockets located as per diagram below
Rack mounted sequencing PDU strips with the network
connection patched into the patch panel.
Lighting Lighting must ensure illumination of both the front and the rear
of the cabinets. It may be necessary to place lighting off centre.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 5
Containment Determined on a project by project basis. Cable entry from above the cabinet is preferable. . See details regarding ceilings
below.
Fire Detection As specified by UWE building specifications
Environment Temperatures in the Comms Rooms must never exceed 26°C.
Mechanical Cooling Cooling is required and must be N+1;
Wall mounted split units should be installed on the wall facing the front of the cabinet. UWE is investigating the possibility/
technical solutions for reducing the temperature to 22°C if an
operative is working in the room.
Monitoring of the AC, room temperatures and the ability to
control the units remotely by the UWE Facilities Department
should be incorporated into the design.
Pipework Pipework containing liquid of any kind or drains should not be
above or below Comms Rooms.
Fabric Room
Placement
Direct access to the Comms Rooms is a basic requirement. It
must be possible to access the Comms Room without going
through or via another room.
The comms room should not be an access route to any other
room or space, including riser cupboards, since any doors other than the entrance would restrict usable space and cabinet
positioning.
Security Comms Rooms should be fitted with the UWE standard door
access control, but also have a bypass key override facility in
the event of power failure.
Ceiling
False Ceilings should not be fitted to Comms rooms. The fitting
of a ceiling impedes the installation of network cables, and the
use of cable trays and other containment.
Cabinet Sizes Standard 42U full size cabinets 800x1000mm should be used
Switches Access layer switches to be specified, sourced and installed by
UWE IT Services.
Cabinet
Placement
First cabinet must be placed against the wall as per diagram
(Figure 1.)
Technical
Information
Cabling Comms Rooms should be positioned so that cables between the
Comms Room and data outlets do not exceed 90m.
Cabling must comply with Cat 6 industry standards
Single Mode Fibre to cabinets must originate from two of the core network nodes. The rooms which contain core network
nodes must be confirmed by UWE IT Services.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 6
The two fibre cables must travel along diverse routes and enter the building at different locations. This reduces the risk of a
single cut impacting services.
UPS
Requirements
Where UPS is required for Business continuity, the UPS should
be specified by IT Services.
Patching All outlets must be patched into network switches using 20cm
patch leads.
Good Practice E22 IT and Comms Room Energy Consumption -
Dedicated IT and communication rooms have a calculated DCIE (data centre infrastructure efficiency) of 70% or greater.
8.5.1 UWE Comms Room Spec Diagram
The UWE Comms Room Diagram is available as a separate document. Note the 3000mm
size is clear space. Pillars, containment for other services, ladders for roof access, and any
encroachment is not permitted.
3000
30
00
800
10
00
1000
400
Commando Sockets
Cabinet 1 Cabinet 2
Wal
l Sp
ace
for
Elec
tric
al D
istr
ibu
tio
n
Bo
ard
s an
d/o
r A
cces
s C
on
tro
l Un
its
3000
1000
View A
View A
1000
Plan View
1000
Commando Sockets
Lighting Lighting
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 7
1000mm
1000mm
1000mm
3000mm3000mm
800mm800mm
Figure 1.
8.5.2 Comms Rooms Ready Condition
Network equipment will only be installed once the Comms Room is in a ready condition. Due to the security risks associated with IT networks, only authorized UWE IT staff can install network equipment, and only when the following conditions are met:
The comms room door must be secure using a UWE standard plant room Kaba lock. (Please note that use of a Kaba lock is as an interim before the access control system is commissioned)
Power to the comms room is constant, there are no fluctuations or outages beyond what constitutes everyday tolerances. If contractors are aware that further planned power outages will be necessary in a given Comms Room after switch installation, this must be declared in advance to UWE IT Services.
The specified comms cabinet/s are installed and fibres are terminated and labelled at
both the cabinet end and the Core network ends.
Lighting is installed and provides illumination of both the front and back of the cabinet.
Cooling, if required, is installed, tested and shown to provide the specified temperatures.
The level of dust in the room is minimal and there are no further works that will generate significant levels of dust.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 8
8.6 IT Cabling Infrastructure
8.6.1 Standards
The three standards are formally titled ANSI/TIA/EIA-568-B.1-2001, -B.2-2001, and -B.3-
2001.
Copper cabling in new buildings to be CAT 6 and cabling installation will be provided with a
manufacturer warranty for 25 years. New buildings shall be provided with blanket Wi-Fi
coverage. Responsibility for the Wi-Fi design and specification is with UWE IT Services.
UWE Facilities must make contractors aware of fibre duct routes and access panels across
the UWE campuses, where the contractor work may interfere with these services. Where the
contractor is not aware, they must seek instruction from UWE Facilities.
8.6.2 UTP Termination and Containment
Requirements for any UTP cabling are as follows:
Cables to be terminated in the communications room on 24 port RJ-45 patch panels. Cables to be terminated at the outlet on an RJ-45 outlet with spring loaded shutters. Outlets to be white plastic, installed in either flush mounted wall outlets or within
dado trunking. The containment to be pervasive, continuous and allow for 50% more cables than
originally installed. The containment paths must follow routes in accessible areas, such as corridors. A blue 3m patch cord is to be provided for each outlet.
8.6.3 Short Patching
A Short Patching policy has been adopted for access layer network switches in all UWE ITS
comms rooms. Short patching is a one patch panel port to one switch port arrangement that
enables quick indentification of port numbers and reduces the time to configure and make
ports available for users. A one to one arrangement means for the number of outlets
installed, there needs to be a corresponding number of network switch ports available. The
installation of fifty network outlets into a building will necessitate the installation of two 48
port switches.
Patch Panel
Network Switch
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 9
8.6.4 Fibre Termination and Containment
Any fibre optic cable installation will:
Only single mode optical fibre (OS2) to be used. Quantities and end points to be confirmed as this is project specific. All to be advised by UWE IT Services.
Fibre optic cables will be terminated as follows into connectors to be specified by ITS dependent on application.
Fibre optic cables are to be installed in 24-way patch panels at the first easily accessible and visible top slot of communication cabinets.
The containment will be pervasive, continuous and allow for 50% more cables than originally installed. (Containment can be shared between the UTP and fibre installations)
All fibre optic cable installations are to be tested using OTDR and the results supplied to UWE IT Services after commissioning.
8.6.5 UTP Outlet Labelling Convention
Each network outlet must be labelled (black text on yellow label) with a unique reference, as
illustrated in Figure 3.
At the Comms Room end, the unique reference should be the name of the room containing the outlet, and the increment number. The increment number is a three-digit number with leading zeroes, assigned by the cable installer and identifying the actual outlet within the room.
At the outlet end, the unique reference should be the name of the Comms Room where the cable to the outlet is patched, and the same increment.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 0
Room (e.g. 2D053) Outlet
Comms Room (e.g. 2B060)
2B060/001 2B060/006
2D053/001 2D053/002 2D053/003 2D053/004 2D054/005 2D054/006
Comms Room Ref. Increment
Room Ref. Increment
Room (e.g. 2D054) Outlet
IncrementComms Room Ref.
Room Ref. Increment
Thus for the 6th network connection in Comms Room 2B060, where the outlet is positioned
in room 2D054, at the outlet end the label will read 2B060/006 and at the Comms Room end
the label will read 2D054/006.
Note: there is no difference between the labelling of data outlets and telephone outlets.
Data and telephone cables are patched to different locations within the Comms Room, but
labels should still fit in with, and remain unique to, the data outlet labelling. For example, if
an outlet in room 2D054 designated for telephone use is the 71st outlet in comms room
2D060 it will still be labelled 2D060/071 at the outlet end and 2D054/071 at the comms
room end.
It should also be noted that, for each comms room within a building, the labelling can start
with other end/001 since the uniqueness comes at the outlet end where the comms room is
specified as part of the label.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 1
8.6.6 Trace and Test
All switch ports must be configured with description information and the VLAN appropriate
for the equipment being connected to that port, i.e. a BMS device is connected to the BMS
VLAN, a Staff PC is connected to the staff VLAN and a student PC is connected to the
student VLAN.
In order to configure the switch port, it is necessary to know which network outlet is
connected to which switch port, and in turn what will be plugged into the network outlet.
The standard Trace and Test should contain the information in the following format
Note: The Trace and Test Spreadsheet must only be sent to UWE IT Services following the
successful testing of outlet to switch port.
8.6.7 Fixed IP Addresses
The majority of equipment connected to the UWE network is allocated an IP address
automatically. However, equipment to control building systems, CCTV, access control, etc.
must be allocated a fixed IP address.
The building contractor will liaise with the building systems supplier to configure and install
their equipment, usually before the building is handed over. In order to configure the
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 2
devices prior to install, a fixed IP address will need to be allocated by UWE IT Services.
Information about the device needs to be recorded in the IP addressing tool.
The following information is required before an IP address can be allocated:
System Type (e.g. CCTV, Access Control, BMS). Room Location (e.g. 2E007, 1E023).
Device Name (e.g. FR_X_2XC200_NORTH_ENTRANCE, FR_E_1E009_ACX1). The naming convention must be agreed in advance, see para Error! Reference source not found.
Network Outlet ID (e.g. 2B087/026) – see note below
Note: It may not be possible to provide the network Outlet ID until the device is physically installed on site. It is critical to provide the Outlet ID as without it UWE IT Services will not be able to configure the outlet for the VLAN appropriate for the device, i.e. the outlet for a CCTV needs to be configured to connect to the CCTV network.
8.6.7.1 Fixed IP Allocation Spreadsheet
The following spreadsheet has been created to enable the building systems devices to be
recorded by the supplier before being sent to UWE IT Services for IP addresses to be
allocated.
8.6.7.2 Device Naming Conventions
The building system devices need to be allocated a Device Name that meets UWE’s building
device naming conventions.
References for UWE sites are as follows
Frenchay – FR
Bower Ashton – BA
Glenside – GL
8.6.7.3 Close Circuit Television - CCTV
The name is made up of three elements separated by underscores:
<Site> <Block> <Viewing Info>
Here, <Viewing Info> is a text description which must be agreed in advance for each
camera with the UWE Facilities Technical Team Manager and UWE Security.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 3
Example 1 - FR_Block_U_Bar_Main_Entrance
Refers to CCTV in U block that focuses on the bar main entrance
Example 2 - FR_S_Block_Near_Rear_Bike_Park
Refers to CCTV in S block focusing at rear bike park
8.6.7.4 Access Control
The name is made up of four elements separated by underscores:
<Site> <Block> <Room Number> <Access Control Number>
Example 1 - FR_A_2A026_ACX1
Refers to a single access controller in room 2A026
Example 2 - FR_B_4B015_ACX1
FR_B_4B015_ACX2
FR_B_4B015_ACX3
Refers to three access controllers in 4B015
8.6.7.5 Building Management System – BMS
The contractor must confirm with the UWE Facilities BMS Manager
8.6.7.6 Monitoring & Targeting (M&T)
The contractor must confirm with the UWE Facilities Technical Team Manager
8.6.7.7 Intruder Alarm System
The contractor must confirm with the UWE Facilities Technical Team Manager
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 4
8.7 Wi-Fi Infrastructure
8.7.1 Overview
UWE provides ubiquitous Wi-Fi across the campuses. This service is expected to be fast,
reliable and provide seamless access to teaching and learning resources regardless of the
devices in use.
Wi-Fi Access Points (APs) are strategically placed in buildings to maximise coverage and
minimise interference caused by other APs and building materials. Correct placement of
these APs within a building fabric is key to providing a high quality and reliable service.
This section outlines best practice for the location of Wi-Fi APs. These requirements must be
fed into the design for both new buildings as well as refurbishment projects.
8.7.2 Wi-Fi Design and Installation
To provide the quality of Wi-Fi coverage demanded by students and staff at the University,
UWE IT Services will complete a detailed Wi-Fi design. It is important that UWE ITS are
involved at the initial building design stage to ensure that Wi-Fi design is an integral element
of new buildings and refurbishments. Wi-Fi designs that occur after the building works are
complete increase cost and time and often compromise on coverage and aesthetics.
It is important the note that any changes to the building design must be
communicated to UWE IT Services.
8.7.3 Steps to plan, deploy & verify a Wi-Fi installation:
1. The UWE Estates Surveyor / Project Manager should provide UWE IT Services with each
iteration of building drawings in .dwg format as soon as they are available. The .dwg
drawings should include occupancy numbers for each room and the room number
designations (if known).
2. UWE IT Services staff need to meet with the UWE Estates Surveyor, Architect and UWE’s
incumbent cabling contractor to further understand the design. In particular…
Planned usage of each room – Social, GPT (General Purpose Teaching), etc.
Footfall figures in each area
Materials used in building fabric – walls, floors, windows
Type of ceiling – suspended, raft, open/industrial
Any other potential interference sources, i.e. microwave ovens, PIR Sensors
Any design anomalies or aspirations
3. UWE IT Services will create a predictive Wi-Fi coverage survey (see figure below) using
Ekahau modelling software, based on the building drawings and requirements. The
predictive survey determines the type of Wi-Fi access points required and their optimum
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 5
location. UWE IT Services will always install Wi-Fi Access point that meet the latest IEEE
ratified standard.
Figure 4.
4. UWE IT Services will provide a building drawing marked with the Wi-Fi access point
locations to the UWE Estates Surveyor. It is then the responsibility of the building project
team to determine the most appropriate containment routes, cable runs, etc. to the
Access Point locations, ensuring that cable lengths are within specifications.
5. The number of locations to provide coverage will in turn determine the number of Wi-Fi
Access Points units required. Building projects fund the purchase of Wi-Fi APs, therefore
UWE ITS will require a project cost code before the APs can be procured.
6. Following a successful trace and test by the cabling contractor of the network outlets
designated for the Access Points, UWE IT Services will configure the outlets, and prepare
the Access Points. Each Access Point is labelled with a location and outlet identifier. It is
imperative that the correct Access Point is installed in its associated location.
7. The cabling contractor will install the Access Points once the building is dust free and
network outlets / Access Points are configured and labelled. Following successful
installation, the cabling contractor must inform UWE IT Services, who will bring the units
into service.
8. UWE IT Services will then carry out a post installation survey using Ekahau modelling
software. This survey verifies that the Wi-Fi installation delivers the required service and
coverage detailed in the predictive survey. To perform the survey UWE IT Services will
require access to all rooms within the new building/refurbishment project. Therefore
the post installation survey should take place after building handover from the principal
contractor but before occupation.
9. If all Wi-Fi coverage is as required, the coverage maps are published internally. If there
are areas of limited or no coverage, UWE IT Services will work with the Estate Surveyor
to retro fit additional Access Points.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 6
8.7.4 Refurbishment Works
Where refurbishment works are planned in an area that already contains Wi-Fi Access
Points, the units must be removed by UWE’s incumbent cabling contractor and given to UWE
ITS for safe keeping before any building works start. Following completion of works, the
process steps 6 and onwards apply.
For more extensive refurbishment works, removals of walls, changes to materials (glass
partitions) it may be necessary to carry out all the steps above.
8.7.5 Wi-Fi Access Point Placement (in order of preference)
Access Points require a single network outlet. For ceiling mounted units, the outlet should be
within 300mm of Access Point to negate the use of surface mounted containment (Figure 8).
For wall mounted units, the outlet should be within 200mm of the Access Point.
8.7.5.1 Option 1 – Ceiling Mount
Access Points should be placed beneath suspended ceiling tiles (Figure 5) on the structural
beams of a building (Figure 6) or directly to the ceiling fabric (Figure 7). They must be
mounted using manufacturer designed brackets. These are the most preferred options and
should be encouraged in all design specifications as they provide opportunity for the best
Wi-Fi coverage.
Figure 5.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 7
Figure 6.
Figure 7.
Figure 8. Ceiling Mounted 2B060/006
300mm
8.7.5.2 Option 2 – Semi-exposed Ceiling
If a semi-exposed ceiling is specified then APs should be mounted on ceiling tile “rafters” or
“Islands” (Figure 9.)
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 8
Figure 9.
8.7.5.3 Option 3 – Mount to Containment
Another option is to be mount AP’s to wire basket trunking using manufacturer designed
mounting brackets (Figure 10).
Figure 10.
8.7.5.4 Option 4 – Wall Mounting
Wall mounting should only be considered if the first three options are not possible. The
vertical surface holding the AP will absorb a high proportion of the RF Signal and reduce the
effective coverage. APs can be mounted to a vertical surface with the use of third party
brackets (Figure 11).
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1 9
Figure 11.
The network outlet for wall mounted Access Points should be within 200mm, where the
outlet is also being mounted to the wall. Access Points and network outlets should be at a
miniumum height of 2.4m (2400mm) (Figure 12).
Figure 12. Wall Mounted
2400mm
200mm
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 2 0
8.7.6 Building Fabric
The building fabric and materials used can severely hamper the effectiveness of Wi-Fi
Access Points.
Large internal features made of metal or glass should be avoided, as they cause major RF
reflections which degrade Wi-Fi performance significantly.
Suspended ceilings provide the best options for mounting Wi-Fi Access Points, but
consideration must be given to servicing and replacing the units. Placement on very high
ceilings and atriums requiring specialist height access equipment is not permissible.
Wi-Fi is most definitely a service that users expect to have available regardless of where
they are on campus. APs need to be in ‘line of sight’ of the users device to maximise
connectivity and reliability. With this in mind aesthetics must be considered secondary to the
placement of APs in all circumstances. Access Points cannot be hidden to satisfy aesthetic
aspirations.
As of September 2017, the Access Points used to provide UWE Wi-Fi are only manufactured
in White.
Where possible the following should not be used or Wi-Fi Access Points should not be
located within 2 metres of them.
Metal sheeting of any kind
Chain Link fencing or wire sheeting
Glass partitions
Metal laced safety glass
Microwave Ovens
DECT phone transmitters
PIR Security Sensors
Radio Microphone Systems
Bluetooth enabled devices of any kind
Computer/Display monitors and projectors
Surfaces containing a large body of water, i.e. fountains etc
Plant (Air Conditioning, Electrical)
Other Wi-Fi Access Points not part of the same Enterprise
Concrete or Metal Pillars or structures containing rebar
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 2 1
8.8 Construction Sites
The majority of buildings constructed on the UWE campuses have a requirement for building
management systems, access control and CCTV requiring connections to the site network.
These systems are usually installed by the contractor prior to the building being handed over
to UWE. In order to commission the systems, UWE IT Services network engineers need to
install network equipment into the designated comms room whilst the site is still a
construction site managed by the contractor.
8.8.1 Training and Certification
Access to construction sites is controlled by the contractor and therefore UWE IT engineers
must adhere to the Health and Safety requirements specified by the Contractor. All UWE IT
engineers that require access to a live construction site have CSCS site visitor cards (or the
previous CSCS Computer Systems Installer cards), have attended the CITB Health and
Safety Awareness course within the last 5 years and will undertake a site induction.
If for any reason further conditions are required in order to allow access, the Contractor
must make these known to UWE IT Services at the beginning of the build. Failure to do this
may result in delays to the Project.
8.8.2 Personal Protection Equipment
UWE IT Services carry out installations of network equipment into designated construction
sites on a regular basis. It is expected that Personal Protection Equipment (PPE) is required
to be worn. In general, the following is used within UWE:
Hi Vis vest Safety shoes or boots with steel toe cap
Helmet Goggles Gloves appropriate to the task
Where the PPE requirements are above and beyond that specified above, the Contractor
must make these requirements known to UWE IT Services at the beginning of the build.
Failure to do this may result in delays to the Project.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 2 2
8.9 Security Infrastructure
The overarching security strategy is set out in part 3 of the design guide. This section
explains specific elements of the strategy in more depth where it impacts on the IT
infrastructure. The design guide chapter which deals with Electrical Engineering Design
provides details about suppliers to be used and, of course, electrical system design.
8.9.1 Access Control and Door Monitoring
This system enables UWE to employ a degree of security whilst maintaining access for staff
and students – 24/7 if required.
The access control system can be set-up to enable different groups access at different times
- for example a certain group, say staff, can be granted access 6am to midnight whilst
undergraduates given 8am to 7pm and postgraduates a different time schedule again. The
occupying client is responsible for ensuring the necessary risk assessments are carried out
for access outside of core UWE working hours.
Each door can be set up individually and this is carried out in agreement with the occupying
client. On going amendments to this can be implemented by the Security Systems Team in
liaison with the occupying client, ideally via a few key client contacts.
In addition to the access control doors the access control system can be used to monitor
doors, such as fire exits, and trigger an alarm in the 24/7 control room at Frenchay if the
door security is breached. The alarms will be set-up to trigger on high risk doors (e.g.
Nuclear Suite) and on all perimeter doors outside of core hours.
Access control should come on-line on all perimeter doors at an agreed time and UWE Cards
used by staff and students to gain access after that time. This is to maintain a suitable level
of security outside of core UWE hours whilst enabling staff and students to continue to use
the space. In general when a building is relatively quiet those using the building feel safer if
they know the building is secure.
Access control to be installed on the following doors:
All perimeter entrances Where practical on all internal doors which mark the perimeter of a Faculty/Service
area, e.g. HAS internal perimeter doors Rooms that require restricted access but to a significant number of people (where a
key lock is not suitable), e.g. BPTC, Postgraduate spaces etc. Plant rooms Comms rooms Where specialist, high value or desirable equipment is installed Central postrooms Central stores accessed by large numbers of people, e.g. stationery stores
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 2 3
Door Monitoring to be installed on the following doors:
All external doors other than entrances to be monitored via the access control system, e.g. all fire exits
High risk areas with access control are to be identified in liaison with the occupying client
and alarms set-up in the 24/7 control room.
Access control will NOT be installed on the following as a matter of course:
Lecture theatres 24/7 PC labs (unless they contain specialist, high value or desirable equipment is
installed) Teaching rooms Meeting rooms Offices Cleaners’ cupboards
8.9.2 CCTV
Although CCTV acts as a good deterrent, increases the feeling of safety and security, and
can on occasion be useful in providing images for identification and evidential purposes it is
neither practical nor cost effective to cover all areas of a campus.
Where practically possible CCTV will be installed and deployed in the following areas:
To meet licensing requirements Bike parks and racks Site perimeter vehicular access and egress
General perimeter coverage for pedestrian access to site Main entrances to buildings 24 hour IT labs Areas with expensive/desirable equipment, e.g. iMacs Bus stops Taxi rank Main walkways and thoroughfares e.g. from campus to Village (Frenchay), FBL new
build atrium Key vehicle barriers East Reception (24 hour) Cash Office ‘Hotspots’ based on incidents/crime/use of campus Internal spaces as discussed and agreed with occupying clients and dependant on
site specific use .e.g. FBL Trading Room
Please note it is not the intention of the CCTV system to cover car parks across campuses.
There are some existing bicycle racks which cannot be covered by CCTV as there is no data
to these areas, the Travel Team have been made aware of this.
For technical details of the CCTV installation please see the Electrical Engineering chapter.
P a r t 8 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 2 4
8.9.3 ANPR (Automatic Number Plate Recognition)
Not currently deployed across UWE, to be explored as a security addition.
8.9.4 Intruder Detection Systems (IDS)
Door monitoring on all external doors via the access control system will be used to monitor
any out-of-hours breach. This can be used to monitor a security breach on a fire exit whilst
the building is still in use, making it more effective than blanket intruder detection cover
which can only be deployed once the building is unoccupied and locked down.
Intruder detection systems will not be deployed in buildings that are likely to operate 24/7.
Intruder detection will only be installed in the following areas:
Buildings that are remote and stand alone and which are being locked down each night, e.g. historically this applied to Bristol Business Park
Ground floor areas and any areas on upper floors that may be vulnerable such as accessable from a canopy/flat roof.
Rooms that may be a particular target, e.g. alcohol stores, cash office, high value/desirable equipment stores etc.
8.9.5 Panic Alarms
These are to be installed and linked back to the Control Room at Frenchay in the following
areas:
Receptions Information Points Cash Office SPS Interview Rooms
UWE Estates and Facilities Design Guide
Chapter 9: Landscaping, Biodiversity & Infrastructure
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 1
Table of Contents
9.1 Scope ..................................................................................................... 2
9.1.1 General notes on landscape design and aesthetics ....................................... 3
9.2 Soft landscaping ...................................................................................... 4
9.2.1 Biodiversity ............................................................................................... 4
9.2.2 Examples of poor practice .......................................................................... 5
9.2.3 Temporary works impacting on soft landscaping .......................................... 6
9.2.4 Memorials ................................................................................................. 6
9.3 Hard Landscaping .................................................................................... 7
9.3.1 Pavements/Footways/Cycleways ................................................................. 7
9.3.2 Specifications for ‘private streets’ ................................................................ 9
9.3.3 Car Parking .............................................................................................. 10
9.3.4 Motorcycle Parking ................................................................................... 10
9.3.5 Cycle Parking ........................................................................................... 10
9.3.6 Barrier Controls ........................................................................................ 11
9.3.7 Designing for deliveries, maintenance & emergencies .................................. 11
9.3.8 Pollution prevention .................................................................................. 11
9.3.9 Underground Services ............................................................................... 11
9.3.10 Fire hydrants............................................................................................ 13
9.3.11 Fire hydrant and drain covers .................................................................... 13
9.4 Street Furniture ..................................................................................... 14
9.4.1 External seating ....................................................................................... 14
9.5 External Events...................................................................................... 14
9.6 Waste Handling & Storage Facilities ........................................................ 15
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 2
9.1 Scope
The purpose of this Chapter is to inform designers (internal and external to UWE) of UWE’s
approach to Landscaping and Biodiversity, taking into account;
The requirements of UWE’s Environment management system (ISO14001:2015);
UWE’s Sustainability plan 2020 goals (which includes a Biodiversity action plan and
Resource management plan) and;
The need for climate change adaption as a forethought.
The UWE sustainability team has responsibility for; Sustainability; Biodiversity, soft
landscaping, hard landscaping and tree planting; Waste and recycling facilities.
This team is a key stakeholder in the design and planning of any project which alters or
impacts on external spaces and should be consulted from RIBA stage 2.
The need for Climate Change adaptation is becoming a pressing issue. Effective design will
increase UWE’s resilience for coping with resource security (such as fresh water and fuel)
and the impact of changing, and more severe, weather events.
As UWE is adhering to requirements of the ISO14001:2015, project teams must adopt
sustainable procurement practices and evaluate the life cycle costs of a project (discussed
elsewhere in the design guide). Sustainability measures contribute to life cycle savings.
Early consideration should be given to the possibility of creating external teaching or event
spaces. There is an emphasis on the unification of the street furniture with the hard/soft
landscaping, harmonising the built environment and natural environment. This also
contributes to a ‘UWE Bristol’ feel and recognition of the Campus Environment.
Frenchay campus is under biodiversity pressure as a result of increased development on and
around the campus since 2012. Biodiversity is of utmost importance for social, economic
and environmental reasons, but also in terms of wellbeing, understanding the value of
nature, and providing a positive learning and working space for our staff and students.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 3
9.1.1 General notes on landscape design and aesthetics
The designer’s approach to the public realm and the external spaces in general should be to
create sustainable as well as useful spaces which accommodate the necessary functions of
urban life and living. The external areas should provide safe linkages to existing
areas/features, safe areas for teaching and leisure activities. All spaces should be designed
to be welcoming and of high sustainable quality that encourage their use.
Pre-existing external spaces should be enhanced through the use of variations in the visual
character, orientation, scale, dimensions utilized through to the choice of materials for both
hard and soft landscaping (with a view to increase biodiversity where possible).
The design team must consider future management of the external spaces and formulate an
external spaces management plan for future maintenance within UWE’s ability and
resources. This may form part of an access and maintenance strategy.
At the early design stages historic and original environmental features should be taken in to
account such as fresh water habitats to either incorporate them in the design or relocate
them to a suitable location.
While landscape designers should be aware of CEEQUAL (http://www.ceequal.com/) UWE
does not currently require formal CEEQUAL assessments of hard/soft landscape design. By
consulting with UWE from the early stages of design (RIBA stage 2 onwards or equivalent),
we can ensure designs are sustainable and meets UWE’s own standards.
Design teams should be aware that external spaces are often forgotten about, especially
during refurbishments, or spaces may be missed in between two new buildings. It is
essential that projects carefully consider where their boundaries start and stop. Where
appropriate, these boundaries may need to be extended to include a wider, external area,
ensuring that it is accessible and aesthetically in keeping with the project.
Planting schemes must maintain good lines of visibility through the campus, in order to
maintain the safety of drivers and pedestrians.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 4
9.2 Soft landscaping
The university requires the principal designer/contractor to adhere to the National Plant
Specification guidelines when design and implementing soft landscaping.
Tree planting should be adopted in future developments where appropriate to soften the
outline of the built form. Tree selection should be on the basis of appropriate form and
growing habit, but all to be clear stem to allow visual sightlines to be maintained.
Indigenous tree species should always be considered first if appropriate, deciduous
woodland is the type of woodland across the Bristol/South Gloucester region.
Tree selection should be done in consultation with the grounds manager to ensure that any
trees or flora planted is in keeping with the campus as well as in line with grounds team
maintenance ability and UWE’s ambition to increase and enhance biodiversity.
The grounds team will support the design team to comply with ISO14001:2015 standard
clause ‘emergency, preparedness and response’. This requires use of planting of indigenous
trees and flora to decrease soil erosion and interception of precipitation to reduce land
saturation/flooding events. Considerate landscape design will reduce the potential impact of
changing severity of weather events.
Tree planting benefits through solar shading, wind screening, water processing and
retention within the area. Designers should consider to where possible enhance or included
green spaces and trees to increase air quality through ‘carbon sinks’.
The access and maintenance strategy (see Chapter 2) needs to consider how watering and
general ground maintenance will be done efficiently and safely.
9.2.1 Biodiversity
UWE campuses are increasingly becoming urban environments and being encompassed in
surrounding residential/commercial developments. Because of this, biodiversity has to be
carefully considered to ensure that the maximum social, environmental and economic
benefits will be achieved in the design stage through to the build.
At the design stage the designers should consult the universities’ Biodiversity Action Plan for
planting schemes that are appropriate to the campus.
Flower planting schemes should seek to plant ‘nectar rich’ native species. 10% of planting
must be ‘edible’ (improving environmental interaction and wellbeing).
The precise layout and location will be determined in consultation with the grounds manager
to ensure there is no potential for inedible berries/plants to be mistaken for edible varieties.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 5
9.2.2 Examples of poor practice
Poor care of grassed areas
used to store materials or
as a traffic route. Grass
re-seeding has not taken.
The original turf could
have been taken up and
stored for re-laying.
A trench was dug
but not properly
reinstated
causing a ‘scar’.
Tree roots were
suffocated by excavated
soil. These trees
ultimately had to be
removed at a cost to
the University.
While these examples may appear
to be predominantly the fault of
contractors, they can be traced
back to poor specifications, lack of
involvement of the sustainability
team and poor planning (in terms
of agreeing traffic management
routes or storage locations).
Trees were poorly stored
(kept in sacks in the open for
6 weeks during the summer)
and planted. Combined with
poor aftercare, this led to a
total of 5 trees being
removed & replaced.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 6
9.2.3 Temporary works impacting on soft landscaping
The grounds manager must be consulted on:
Operations or temporary works which impact on soft landscaping must be done in
consultation with the Grounds Manager (e.g. use of heavy equipment or creation of
temporary footpaths or compound space on grassed areas).
Proposed locations for stockpiling of soil
The Grounds Manager will offer guidance to ensure the least environment impact, including
advising on Root Protection Areas (RPA) and the health and condition of existing trees. It is
important that all surrounding trees are considered within the scope of the project, not just
those that fall immediately within the boundary of specific works. The University expects
that BS 5837:2012 ‘Trees in relation to design, demolition and construction –
Recommendations’ are followed in their entirety throughout the whole project.
The grounds team will assist in developing the project specification, physically marking out
RPA’s and will ensure the planning includes actions for the protection (e.g. temporary
reinforcement of grassed areas) and remediation of the campus to the original (or better)
state. This consultation should take place prior to ground works starting. Project teams will
be encouraged to look at improvements surrounding their project boundary.
9.2.4 Memorials
UWE does not promote or encourage the use of ‘lasting memorials’ such as plaques, tree
plantings or benches in memory of individuals who have passed away.
The University Chaplain has identified that such measures can feel outdated or ‘tokenistic’,
especially to young adults. In an age of technology and mass communication, students
often use social media to perform a similar function.
There are practical challenges to maintaining and tracking lasting memorials, and
inadvertent loss or damage can be distressing and disrespectful to families and friends.
Instead, UWE encourages the use of memorial events and there are no specific design
considerations that are needed to support these.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 7
9.3 Hard Landscaping
The proposed layout of roads, footpaths and other hard landscaping must be agreed with
the UWE transport team. They will help assess the impact on traffic movement around the
campus, the impact on crossing points etc. and the potential consequences for disabled
people.
In general, designers should comply with the Department for Transport’s Manual for Streets
(Parts 1 and 2). However, these are largely goal setting and this section offers more UWE-
specific guidelines.
9.3.1 Pavements/Footways/Cycleways
2m wide on all side (which will enable two wheelchairs to pass at the same time). Routes
should be made as inclusive as possible by:
Avoiding circuitous routes for wheelchair users.
Placing dropped kerbs with tactile paving at convenient and appropriate locations (which
will also assist porters, catering staff etc. using trolleys etc.).
Achieving gradients that comply with BS 8300.
A strong tonal difference should be achieved between pavement and roadway and
between street furniture and the surrounding paving.
Careful consideration must be given to the use of ‘stripes’ (e.g. different coloured
modules creating striped bands running across pavements, courtyards etc.) and they
should be avoided. For example, for someone with a visual impairment, a dark strip
could create the false perception of shadows and a kerb line.
Resin bonded paths are prohibited at UWE.
UWE does not currently desire shared spaces (where vehicles and pedestrians share the
same space), although this is a decision that could be revisited.
9.3.1.1 What UWE means by a ‘flush’, dropped kerb
For the avoidance of any doubt, a flush, dropped kerb means a 0mm upstand.
9.3.1.2 Pavement Specification
All the following specifications are taken from Gloucestershire County Council manual for
Gloucestershire Streets (4th edition), 01/04/16. They are purely indicative.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 8
If paviours are to be used they should meet the relevant council standard (this is indicative):
9.3.1.3 Designing out trip hazards
The images in the centre and to the left, below, show low-level trip hazards created by lips
which could have been avoided. One example is shown in the image to the right, below.
9.3.1.4 Lighting
It should be self-evident that effective external lighting reduces the likelihood of trips and
promotes a sense of personal safety. Technical aspects of external lighting are addressed in
the electrical chapter. All vehicular and designated pedestrian routes will be lit along with
‘plazas’, pedestrian bridge tunnels, external stairs etc. Designated external escape routes or
assembly points will also have emergency lighting.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 9
9.3.1.5 Considering ‘adjacencies’ in hard landscaping design
Our ambition is to create a harmonious blend of surfaces and designs. Project teams must
consider the hard landscaping outside their own project boundaries to create a sympathetic
solution. This involves considering and accounting for the new ‘desire lines’ that buildings
will create through the campus.
9.3.2 Specifications for ‘private streets’
All main arterial roads through campuses should be designed as a high street as set out by
the local authority. This is purely an indicative standard:
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 10
This standard would need reviewing depending on the specific demands a road is exposed
to (e.g. if the access and maintenance strategy indicated that heavy items of plant (such as
cranes) would need to be deployed on the road).
9.3.2.1 Swept Path Analysis
Depending on the nature of the project, tracking (or ‘swept path’) analysis may be needed.
A 3 axle refuse vehicle should be used for this study and the swept path should be no closer
than 500mm from any kerb, vertical structure, tree, or formal parking space.
9.3.3 Car Parking
All buildings are to have an allocation of disabled parking spaces in line with Part M of the
building regulations. When providing Blue Badge parking bays, locate these within a short,
level distance of the building. In a row of disabled parking spaces, wherever possible, one
will be sized to accommodate a large vehicle allowing for a side or rear access hoist.
9.3.3.1 Recharging Points for Electric Vehicles (EV)
UWE seeks to support and encourage the use of electric vehicles. During any projects that
will be introducing or extending car parking provision, the sustainability team will assess the
need for electric charging points based on number of spaces, proximity to other charging
points and the anticipated usage of the space (e.g. a ‘drop off’ point would not be a sensible
location for a charging point as it will encourage drivers to linger).
Generally these will be ‘fast chargers’ aiming to provide a full charge in 1hr 30minutes. This
requires a 22kW supply (approximately). The charging points are to have Ingress Protection
rated at 55. Charging points are to be individually metered (as detailed elsewhere in this
design guide).
9.3.4 Motorcycle Parking
Provide space for at least one 3 wheel tricycle in any parking designed for motorcycles.
9.3.5 Cycle Parking
UWE has used a range of options to provide comfortable, aesthetically pleasing, well lit and
reasonably secure cycle parking facilities. The requirement for or size of this provision will
be influenced by the number of building users, the proximity to existing facilities etc. as well
as constraints such as space.
Designers should consider wind loading/direction when selecting and positioning bike
shelters, especially open faced shelters.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 11
Shelters should not be positioned in infrequently used or obscured locations, as this could
encourage theft. The transport team will advise on security requirements, but it should be
anticipated that cycle hubs will need swipe access with attendant power/data supplies.
The sustainability team should be consulted during RIBA stage 2 of any major refurbishment
or new build (£2.5m or more exc. VAT) so that they can assess existing provision and advise
on how cycle provision could be enhanced.
In any cycle parking provision, there must be at least one cycle space that is wide enough to
accommodate a recumbent trike which may be used by a disabled person. There will also
need to be space for storage of a wheelchair.
9.3.6 Barrier Controls
Barrier controls should be operated by swipe cards or key codes (the transport team will
advise) and without the need for users to leave their vehicle. Intercom is only a ‘back up’
method of operating barriers: Not all users will have hearing or speech. Barriers must be
designed to prevent harm or damage to people or property.
9.3.7 Designing for deliveries, maintenance & emergencies
The access and maintenance and fire strategies will help establish the demands that will be
placed on hard landscaping. UWE wishes to avoid the need to repair brand new footpaths
etc. damaged by the weight of vehicular traffic which was foreseeable from the outset.
Designers must ensure that there is at least one vehicular route and parking area for each
building, capable of taking the weight of a 3 axle refuse vehicle.
9.3.8 Pollution prevention
Hard infrastructure should include appropriate pollution prevention measures. The
sustainability team can provide advice on, for example, the requirement for interceptors or
the risk to existing drainage (e.g. surface water drains in proximity to a new delivery bay).
Any external spaces that the sustainability team deem to be high risk such as loading bays
or near hydrocarbon storage tanks may need storage for a UWE spill kit (depending on the
distance to an existing kit). This will need to be allowed for in the design process
9.3.9 Underground Services
A range of services and cables are routed through the ground. This makes them vulnerable
to inadvertent damage, especially during future construction projects.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 12
Designs, specifications and installation must conform to the current version of NJUG National
Joint Utilities Group’s guidelines and BS 1710 on the positioning and colour coding of
underground utilities’ apparatus.
Where possible, all utility apparatus should be laid in ‘corridors’ throughout the site. This will
facilitate the installation of the services and any future connections as the development
proceeds. Consideration should be given to the use of trenches and ducts to facilitate this.
Due to the ever evolving nature of the estate, depths must conform to ‘carriageway’
standards and not footways or verges: Within a matter of years road surfaces could be
extended or re-routed.
If for any reason, minimum depths or separation distances cannot be achieved, the situation
must be discussed with the relevant UWE engineer.
The location of access to inspection chambers should be carefully considered in order to:
Facilitate permanent but safe access
Limit the impact on traffic/pedestrians while in use
Prevent damage to the manhole cover from vehicular traffic
9.3.9.1 Marker and identification tape
Identification tape (which must be PVC or polyethylene ribbon at least 150 mm wide) is to
be applied continuously along the whole length of underground services. The relevant
descriptive text should not be more than 700mm apart. The tape should incorporate a
corrosion resistant tracing system.
The tape should be installed directly over the crown of the pipe for its entire length. This
tape should be extended and then terminated within suitable accessible points at either end
of the pipe run (valve chambers & building entry points etc.) to facilitate future tracing via
signal generation method.
Regardless of the service being installed, the trace wire shall be designed and attached in
accordance with the Bristol Water Addendum to Code of Practice for the Self-Laying of
Mains and Services (version 4.0, November 2014). “Trace wire shall be attached to the
service pipe using plastic cable ties at not more than 1 metre intervals. The wire is to be
minimum 1.5 square millimetres blue plastic coated wire to BS 6491X standard. The wire
shall be taken into the property.”
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 13
The final termination point will need to be determined by the exact service. In the case of
water pipes, the Bristol water addendum states “they should be clamped to the service pipe
above the stop tap, and shall terminate above the main to which the service is connected.”
9.3.9.2 Entry of services to buildings
To maximise resilience to cope with damage, planned outage etc., diverse routes are requ-
ired for service distribution. Typically, risers are provided at opposite ends of the building.
9.3.10 Fire hydrants
The requirement and position of fire hydrants will be determined by the fire strategy for the
new building. UWE has a full suite of drawings showing the existing hydrant circuit and can
provide water pressure data. As usual, the design must conform to current versions of
relevant British and Industry Standards (BS 750 and BS EN 14339, in this instance).
9.3.11 Fire hydrant and drain covers
9.3.11.1 Fire Hydrants
In line with recommendations from UMAL, the UWE insurers, all fire hydrant covers must be
highlighted by yellow paint. This is in addition to the marking requirements in BS 750
(“surface box covers shall be clearly marked by having the words “FIRE HYDRANT” in letters
not less than 30 mm high, or the initials “F.H.” in letters not less than 75 mm high, cast into
the cover.”). UWE requires the use of “FIRE HYDRANT”, rather than “F.H.” unless space
constraints prevent this.
9.3.11.2 Drain covers
In line with Pollution Prevention Guidelines (PPG) 1 and 22, UWE requires that: “gullies,
grids and manhole covers are colour coded to aid identification, using blue for surface water
and red for foul and arrows to indicate the direction of flow.”
It will hopefully be self-evident that colour-coding will hugely assist in the management of
the Estates. For example, in the case of a spill, it will help a response team to rapidly
determine which grids to prioritise for protection.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 14
9.4 Street Furniture
The DfT Manual for Streets establishes how detrimental ‘clutter’ can be to the public realm.
Chapter 3 of this design guide addresses wayfinding and the strategy for ensuring that
signage is used in a coherent manner and presents a visually consistent theme.
Any other street furniture should be robust with a design that is sympathetic to the
surrounding built and natural environment (e.g. the requirements of central Frenchay
campus will be different from Glenside).
Where possible any proposed street furniture should be integrated into designed elements,
such as paving bands.
9.4.1 External seating
There should be a mixture of external seating, offering opportunities for individuals to rest
as well as collaborating together on course work etc. Seating should include some with
backs and arm rests, providing a selection that people can pick to suit their health and
physical condition. The design and material will need to match the environment. If there is
space for only one external seat, it should be fitted with arm and back rests. An example
(found at another University) is shown below.
9.5 External Events
UWE’s desire for flexibility extends to external spaces. Any large area of soft or hard
landscaping should be considered as a potential events space (e.g. talks, performances,
street catering etc.). This should be discussed with the end user(s) and sustainability team.
If external events are desirable, provision should be made for power, lighting etc.
UWE Design Guide for Buildings
Chapter 9 | Landscaping, Biodiversity and Infrastructure Issue 1.3 Page | 15
9.6 Waste Handling & Storage Facilities
External Waste and recycling facilities should be designed with consultation of sustainability
team to ensure the appropriate facilities are designed to meet the needs of the users and
waste contractors.
Facilities will obviously take into account the size and quantity of containers for waste.
Where possible bin stores will be enclosed or, if that is not practicable, sheltered to aid with
secure waste containment in line with legal obligations.
As an overarching principle the design team should follow the guidance for waste
handling/storage provision as given in a BREEAM assessment: The space recommended by
this assessment is in direct proportion to the square meterage of the building.
The design team should note that UWE have a priority on recycling. Hence, the wider
design should include space for bins and recycling points across all areas of the building i.e.
offices, kitchens, eating areas, study areas etc. The design team will additionally need to
consider ease of access for cleaners, both storage of materials and access whilst
undertaking the cleaning of the buildings.
Any bin stores provided should have enough space for 1100 litre recycling and general
waste bins to be moved in and out of the bin store and have good access/space/head height
for cleaners to empty smaller bins into them. The exact number of wheelie bins requiring
housing will depend on the occupancy and use of the building; exact specifications for this
should be determined in consultation with the relevant UWE personnel.
Bins stores will need to be positioned 10m or more from a building. If this is not possible,
advice should be sought from the UWE Fire Officer and Insurance Manager.
Access to the bin stores will be required by refuse and recycling contractors’ vehicles.
Any design should include the facilities to store hazardous waste. This will range from
fridges, to chemicals/contaminated cleaning containers to TV's through to chemicals storage
requirements. The design team must ensure adequate Health & Safety precautions are in
place including eye washes etc.
Hazardous waste storage and collection is not included in BREEAM calculations, the exact
requirements will depend on overall size/use of the building. In specific situations,
depending upon the faculty in question, there may be a need to provide external space to
accommodate lockable skips.
UWE Estates and Facilities Design Guide
Chapter 10: Audio-Visual (AV) Infrastructure
UWE Design Guide for Buildings
C h a p t e r 1 0 | A V I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 1
Table of Contents
10.1 Introduction .................................................................................................... 2
10.2 Design Process ................................................................................................ 2
10.3 Cable Routes ................................................................................................... 3
10.4 Containment .................................................................................................... 3
10.4.1 Underfloor ................................................................................................ 3
10.4.2 Riser ........................................................................................................ 3
10.4.3 In ceiling .................................................................................................. 3
10.5 Room Type: .................................................................................................... 4
10.5.1 Signage Screen ......................................................................................... 4
10.5.2 Meeting Room ........................................................................................... 4
10.5.3 Standard General Practice Teaching (GPT) Room. ....................................... 5
10.5.4 Lecture Theatre ......................................................................................... 6
10.5.5 Technology Enhanced Active Learning (TEAL) Room. ................................... 8
10.5.6 PC Lab ..................................................................................................... 8
10.5.7 Open Access Learning ................................................................................ 8
10.5.8 Specialist Spaces ....................................................................................... 8
10.5.9 Other ....................................................................................................... 8
C h a p t e r 1 0 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 2
10.1 Introduction
This document is to assist the design and preparation of the specific mechanical and
electrical infrastructure to enable the IT/AV fit out to take place. We would expect that the
items discussed below will be installed by the construction contract and not as part of fit out
works procured/managed directly by UWE. It is current practice that ITS will appoint the AV
contractor.
All AV cabling is to be supplied and fitted by the AV contractor. The only exceptions are for
Network Data and Power for IT and AV installations.
The fit out works may occur concurrently with the main building works. Contract clauses
will allow for access by UWE contractors. ITS will follow their own processes for appointing
and managing their contractors. While on any Principal Contractor’s site, the AV contractor
will undergo induction and obey site rules.
If ITS staff go onto construction sites, please refer to general health and safety
requirements set out in the IT Infrastructure Chapter.
This chapter should be considered in tandem with the IT infrastructure chapter.
10.2 Design Process
Design is key to the successful implementation of IT/AV Services and to the smooth running
of the project, regardless of whether it is a new build or refibushment. In all circumstances,
ITS should be represented at all design meetings where IT or AV systems are required.
It is critical that design teams ensure that the design accounts for the cable routes and
containment detailed in this chapter and ensure that the overall design is properly co-
ordinated. For example, UWE has had to contend with designs where, after a lectern was
installed, it was no longer possible for a wheelchair to pass along the front row of seats.
It is also incumbent on the wider design team to identify the specific needs of users of the
room/space so that assistive technologies can be incorporated as required. Chapter 3 of the
design guide deals with issues of equality and diversity in more depth.
After discussing generic requirements for cable routes and containment, this chapter will
detail the requirements for different room types.
C h a p t e r 1 0 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 3
10.3 Cable Routes
Direct cable routes, taking in consideration for design and construction, will run from point
of control to point of display/s. For example, projector to teaching position (lectern),
monitor to hard wired control point. Signal cables will follow the same route as control
cables.
Cables should not be run through fire breaks.
10.4 Containment
10.4.1 Underfloor
Perforated cable tray is to run from the lectern floor box to the riser.
10.4.2 Riser
Containment should be in the presentation wall wherever practicable.
External dado will be considered, especially in rooms where cabling is being delivered via dado (i.e. not underfloor).
If use of dado has been agreed by UWE, it is preferable that the riser is not on the teaching wall but is as close to the lectern as is practicable.
Containment should not be less than 50mm x 50mm (or 50mm diameter) but may be
larger depending on room type and use.
Rigid containment will be used (such as Copex but alternative, comparable systems may
be used with ITS approval).
Where containment is hidden or inaccessible, draw cords will be required.
Exposed containment should complement the design of the room.
Containment will be Cat 6E compliant.
10.4.3 In ceiling
A cable basket of suitable capacity must run from the top of the riser to the projector/speakers/camera/microphones etc.
Where it is exposed, the basket must be in keeping with the design of the room. The basket should follow the most practicable, shortest route. AV cables can be mounted in baskets supplying other services.
Ceilings must be capable of holding a mounting plate for the projector and the weight of the
projector.
C h a p t e r 1 0 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 4
10.5 Room Type:
10.5.1 Signage Screen
1. Teaching Position – N/A
2. Cable Routes – High level power and data directly behind the display that does not
conflict with the fixing positions (see Appendix drawing for an example).
3. Containment – Only small power and data both terminated behind the display. Surface
trunking should be avoided. Where inaccessible containment is used then draw cords are
required.
4. Projection Screens/Monitors
a. Suitable wall construction and patrissing will be required for large screen
monitors.
i. Approx. weights:
ii. 42” – 16.9 Kg
iii. 55” - 26.5 Kg
iv. 80” – 61 Kg
5. Projectors – N/A
6. Speakers – N/A
7. Microphones – N/A
8. Hearing Loops – N/A
9. Lecture/Events capture – N/A
10. Small Power and data – 1 x double power, 1 x single data.
11. Exceptions will be by agreement with UWE IT Services.
10.5.2 Meeting Room
1. Teaching Position – N/A
2. Cable Routes
Behind the display will be 1 x double power, 1 x double data. In the dado there should
be a switched fused spur to the double socket behind the display, two single back boxes
(one for control one for input plate).
3. Containment
a. For cable route will run from empty back boxes in mid level dado to single brush
plate back box behind the display (with draw cords)
b. For the construction stage rigid containment will be used although Copex or
comparable will be considered with our agreement.
c. Containment should be in the presentation wall or under floor wherever
practicable and not less than 50mm x 50mm (or 50mm diameter) but may be
larger depending on room type and use.
d. Where containment is hidden or inaccessible draw cords will be required.
e. Containment should complement the design of the room.
f. Containment – Only small power and data both terminated behind the display.
Surface trunking should be avoided.
4. Projection Screens/Monitors
a. Suitable wall construction and patrissing will be required for large screen
monitors. The approximate weights are:
C h a p t e r 1 0 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 5
i. 42” – 16.9 Kg
ii. 55” - 26.5 Kg
iii. 80” – 61 Kg
5. Projectors – N/A
6. Speakers – N/A
7. Microphones – N/A
8. Hearing Loops – N/A
9. Lecture/Events capture – N/A
12. Small Power and data – 1 x double power, 1 x single data.
13. Exceptions will be by agreement with UWE IT Services.
10.5.3 Standard General Practice Teaching (GPT) Room.
1. Teaching Position
All standard teaching rooms and lecture theatres will follow the pattern noted below.
a. Non standard or specialist spaces will need to be agreed with ITS at the earliest
possible design stage.
b. Teaching spaces and theatres are primarily equipped with a lectern, one or two
ceiling mounted projector, two program sound speakers, a large projection
screen and event capture solutions. Spaces seating over 50 will also have voice
reinforcement speakers and a hearing loop system.
c. ITS will advise if the space is to be single or dual projection.
i. For single projection the teaching position will be:
1. off to one side furthest from the door with sufficient space
between the teaching wall and the lectern for wheelchair access.
ii. For Dual projection the teaching position will be:
1. Centred between the projection screens with sufficient space
between the teaching wall and the lectern for wheelchair access.
d. Services should not foul projection screens.
e. The presentation wall will typically have projection screen/s and two passive
speakers for program sound.
2. Cable Routes
a. Cable Routes – From control to ceiling mounted projector/s via floor box and
riser.
b. Floor box will contain 1 x double power, 3 x single data, empty double back box
(for AV cables)
c. Floor box must be a minimum 125mm deep with total void (box plus below) to
be not less than 225mm (to allow for cabling turn radius).
d. Floor box will be positioned under the teaching position.
e. Speakers will require direct cable routes from each speaker to point of control.
3. Containment
a. for cable route will run from empty back boxes in mid level dado to single brush
plate back box behind the display (with draw cords)
b. For the construction stage rigid containment will be used although Copex or
comparable will be considered with our agreement.
C h a p t e r 1 0 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 6
c. Containment should be in the presentation wall or under floor wherever
practicable and not less than 50mm x 50mm (or 50mm diameter) but may be
larger depending on room type and use.
d. Where containment is hidden or inaccessible draw cords will be required.
e. Containment should complement the design of the room.
f. Containment – Only small power and data both terminated behind the display.
g. Surface trunking should be avoided.
4. Projection Screens
a. Suitable wall construction and patrissing will be required for projection screens.
Screen monitors.
i. Approx. weight:2.4m x 1.8m – 30kg
b. Projection screen will be TK Team wet wipe board or equivalent.
5. Projectors
a. To be 1.8-2.2m from the presentation wall.
b. To be central to the screen/s
c. Securely mounted to the ceiling
d. Ceiling should be capable of holding approx. 18kgs held vertically
e. Services will not foul projection sight lines or mounting.
6. Speakers
a. Program sound at either side of the presentation wall only.
b. Speakers will be wall mounted usually under 10 kg
c. Where voice reinforcement is required these will be ceiling mounted unless
agreed as an exception.
7. Microphones
a. Should consist of a teaching position goose neck mic, a lapel mic and a hand held
for voice reinforcement where room capacity of 50 or more.
8. Hearing Loops/Assistive Technology
To be agreed on a project-by-project basis.
9. Lecture/Events capture
a. Current standard specs can be supplied when required but consists of a camera
and single microphone – note cable route to point of control will be required.
10. Small Power and data
a. 1 x double power, 3 x single data at the lectern position.
b. 1 x double power and 1 x single data at mounting position of the projector.
11. Exceptions will be by agreement with UWE IT Services.
10.5.4 Lecture Theatre
1. Teaching Position
All standard teaching rooms and lecture theatres will follow the pattern noted below.
a. Non standard or specialist spaces will need to be agreed with ITS at the earliest
possible design stage.
b. Teaching spaces and theatres are primarily equipped with a lectern, one or two
ceiling mounted projector, two program sound speakers, a large projection
screen and event capture solutions. Spaces seating over 50 will also have voice
reinforcement speakers and a hearing loop system.
C h a p t e r 1 0 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 7
c. ITS will advise if the space is to be single or dual projection.
i. For single projection the teaching position will be:
1. off to one side furthest from the door with sufficient space
between the teaching wall and the lectern for wheelchair access.
ii. For Dual projection the teaching position will be:
1. Centred between the projection screens with sufficient space
between the teaching wall and the lectern for wheelchair access.
d. Services should not foul projection screens.
e. The presentation wall will typically have projection screen/s and two passive
speakers for program sound.
2. Cable Routes
a. Cable Routes – From control to ceiling mounted projector/s via floor box and
riser.
b. Floor box will contain 1 x double power, 3 x single data, empty double back box
(for AV cables)
c. Floor box must be a minimum 125mm deep with total void (box plus below) to
be not less than 225mm (to allow for cabling turn radius).
d. Floor box will be positioned under the teaching position.
e. Speakers will require direct cable routes from each speaker to point of control.
3. Containment
a. For the construction stage rigid containment will be used although Copex or
comparable will be considered with our agreement.
b. Containment should be in the presentation wall or under floor wherever
practicable and not less than 50mm x 50mm (or 50mm diameter) but may be
larger depending on room type and use.
c. Where containment is hidden or inaccessible draw cords will be required.
d. Containment should complement the design of the room.
e. Surface trunking should be avoided.
4. Projection Screens
a. Suitable wall construction and patrissing will be required for projection screens.
i. Approx. weight: 3.5m wide – 30kg
b. Projection screen will be fixed frame stretched skin or equivalent.
5. Projectors
a. To be confirmed distance from the presentation wall, depending on model.
b. To be central to the screen/s
c. Securely mounted to the ceiling
d. Ceiling should be capable of holding approx. 35kgs held vertically
e. Services will not foul projection sight lines or mounting.
6. Speakers
a. Program sound at either side of the presentation wall only.
b. Speakers will be wall mounted usually under 10 kg
c. Where voice reinforcement is required these will be ceiling mounted unless
agreed as an exception.
7. Microphones
a. Should consist of a teaching position goose neck mic, a lapel mic and a hand held
for voice reinforcement where room capacity of 50 or more.
8. Hearing Loops/Assistive Technology
To be agreed on a project-by-project basis.
C h a p t e r 1 0 | I T I n f r a s t u c t u r e I s s u e 1 . 3 P a g e | 8
9. Lecture/Events capture
a. Current standard specs can be supplied when required but consists of a camera
and single microphone – note cable route to point of control will be required.
10. Small Power and data
a. 1 x double power, 3 x single data at the lectern position.
b. 1 x double power and 1 x single data at mounting position of the projector.
c. 1 x single power at camera location
11. Exceptions will be by agreement with UWE IT Services.
10.5.5 Technology Enhanced Active Learning (TEAL) Room.
Two Standard Types - A and B.
TEAL A is a wireless solution, and containment is restricted to small power and data for each
workstation.
TEAL B is a wired solution and containment is required to run a series of cables between
each workstation and point of control.
These spaces are considered an exception to the standard teaching model, and
requirements must be confirmed with ITS before commencing work.
10.5.6 PC Lab
PC labs will normally consist of a standard teaching installation in addition to a number of
workstations set out on desking.
Containment is restricted to small power and data for each workstation, and the Estates
Design Guide should be consulted for load and distribution throughout the room.
Consideration of how cable management, layout and integration with furniture will be
managed will need to be agreed with ITS.
10.5.7 Open Access Learning
Would not normally consist of AV teaching installations, but will require small power and
data for each workstation. Requirement to be agreed with ITS.
10.5.8 Specialist Spaces
Requirement to be agreed with ITS.
10.5.9 Other
Requirement to be agreed with ITS.
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 1
Procedural Document For the management and control of Legionella including
“safe” hot water, cold water and drinking water
Chapter 2: Design and Handover of Water Systems
Revision 4, Issued June 2018
Prepared by Nick Bell, UWE
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 2
Contents
1 System/plant design, installation and maintenance .......................................................... 3
General design and installation considerations .......................................................... 3
Cold water storage tanks ........................................................................................ 3
Hot water calorifiers .............................................................................................. 4
Hot water and cold water distribution systems .......................................................... 7
Showers baths and thermostatic mixing valves/taps (TMV/TMT)................................. 8
Expansion/pressurisation vessels ............................................................................. 8
Usage evaluation ................................................................................................... 9
Prohibited features ................................................................................................ 9
Greywater systems ................................................................................................ 9
Temporary water supplies ...................................................................................... 9
Irrigation systems .................................................................................................. 9
Ice making machines ............................................................................................. 9
Outdoor ornamental fountains and water features .................................................. 10
Humidified food cabinets ...................................................................................... 10
Ion exchange water softeners ............................................................................... 10
Portable humidifiers ............................................................................................. 10
2 Training at handover .................................................................................................. 10
3 Handover documentation ............................................................................................ 11
Domestic water services ...................................................................................... 11
Process water systems ......................................................................................... 13
Closed heating and cooling circuits ....................................................................... 14
REVISIONS
Title Notes Initial Date
Draft v2 June 2010
Final Issue Rev A Oct 2014
Final Issue v2 Apr 2017
Final Issue v3 Clarified author is UWE. Removed references to
maintenance activities/frequencies
NB June 2018
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 3
1 System/plant design, installation and maintenance
General design and installation considerations
Designers must refer to the UWE Design Guides before commencing any design work.
Systems which utilise or contain water and can affect the water supply, the atmosphere and
the user shall be monitored regularly and be subjected to the following regime:
All designs must be carried out and presented in accordance with all relevant and current
Guidelines, European and British Standards and “best-practices”.
The systems shall be carefully designed to eliminate or minimise aerosol production and
excessive water retention. They must also be designed to be readily drained and cleaned.
No materials used in construction shall include those that are known to harbour or provide
nutrient for bacteria.
Any materials that come into contact with the water in a hot or cold water installation shall
comply with the requirements of the Water Supply (Water Fittings) Regulations 1999. The
list of products/materials that have been assessed for compliance with the Water Supply
(Water Fittings) Regulations 1999 requirements are listed in the current edition of Water
Fittings and Materials Directory that is updated every six months. Further information on
the selection of materials can be found in BS8558 and BS6920.
Some flexible hoses are unsuitable for use with domestic potable water, because they
support extensive microbial growth, give the water a very strong, unpleasant, taste and
odour or release toxic substances into it. Hose materials may also encourage the growth of
Legionella bacteria. It is, therefore, UWE’s policy that in new buildings or refurbishments
commissioned by or on behalf of UWE, flexible hoses shall be avoided where possible. Any
flexible hoses fitted shall be WRAS approved. Enquiries regarding specific types of flexible
hose shall be directed to the manufacturer/supplier.
All systems must be easily and safely accessible for maintenance.
All systems/outlets shall be designed, wherever possible, to be frequently used to avoid
stagnant water which will increase the potential of bacterial growth and proliferation.
All plant and distribution pipe-work (where accessible) shall be clearly labelled.
Cold water storage tanks
Cold water storage tanks shall be constructed from non-deleterious materials which
must be WRAS approved.
Cold water storage tanks shall be designed and installed in accordance with the current
Water Supply (Water Fittings) Regulations 1999) and installed in appropriate and
suitable locations to allow easy and safe access to facilitate inspection and maintenance.
Sectional Cold Water Storage tanks shall be designed with external assembly flanges
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 4
and self-draining profiles, to facilitate easy cleaning of internal surfaces.
Externally located cold water storage tanks shall be suitably protected from
environmental conditions for all new buildings and, where practicable, for existing
installations if elevated temperature is found to be due to high ambient temperatures.
Cold water storage tanks shall be protected from the ingress of light, insects and birds.
Cold water storage tanks shall be sized and arranged to minimise retention time of stored
water (24hrs maximum), and therefore to increase the rate of stored water exchange.
Projects should question the presence of any existing tank and consider its removal if
the services it supplies can be, equally well, supplied by converting the systems to
domestic Mains fed only.
When water temperatures are found to be persistently outside recommended parameters,
each unit shall be subjected to a “drop-test” designed to ascertain the capacity and
demand requirements of each system, in order to ensure that excessive volumes of
water are not unnecessarily stored. Eliminating storage within a system would also allow
the negation of the necessary PPM Programme tasks and their replacement with much
less onerous, more infrequent and less costly tasks to be carried out.
All associated pipework and valves shall be adequately insulated and clearly labelled
to identify their purpose.
Delayed-action ball valves shall be fitted (where practicable) in order to help avoid
stagnation of water.
In new buildings where cold water storage tanks are linked “in parallel”, the feed to each
tank shall be fitted with a water meter in order to allow for confirmation of equal and
uniform usage from all tanks in the configuration.
Various arrangements of pumping systems are indicated in BS8558. Where booster pumps
are to be installed, a break cistern will be required between the mains supply pipe
and the pumps. This is required in order to comply with the Water Supply (Water
Fittings) Regulations 1999 with regard to prevention of backflow. Control of the pump(s)
should be fully automatic in operation and controlled by pressure sensors. Where two
or more pumps are installed, the design flow should be achieved with one pump
stationary (or out of service). Automatic control should be provided to cyclically and
sequentially control all pumps to ensure that each is regularly brought into service. If this
is not possible, documented procedures shall be in place to ensure equal usage is achieved.
Designs should maintain stored water at a temperature of <20oC (or no more than 2oC
greater than the inlet supply temperature to the building).
Where indicated and when it is deemed necessary and practicable, Cold Water Storage
Tanks shall be upgraded, refurbished, modified or replaced so that they may comply with
current Water Supply (Water Fittings) Regulations 1999. Following these works, each tank
shall be cleaned and disinfected in accordance with BS 8558:2011and L8 prior to it being
allowed back into service.
Hot water calorifiers
Calorifiers shall be installed in appropriate and suitable locations to allow easy and safe
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 5
access to facilitate inspection and maintenance.
Where more than one Calorifier or heating device is used, they shall be connected in
parallel, taking care to ensure that the flow can be balanced so that the water temperature
from all the Calorifiers exceeds 60°C at all times.
In all new installations, the combined storage capacity and heater output must be sufficient
to ensure that the outflow temperature, at continuous design flow (at least 20 minutes)
from calorifiers or other heaters, shall not be less than 60°C. This applies to both circulating
and non-circulating hot water systems.
The positioning of the control and high limit thermostats, cold feed and return water
connections must ensure that these temperatures are achieved.
Warm water must be prevented from entering the cold-feed. A check valve shall be
provided in the cold feed, as close to the calorifier as practicable, to prevent this. However,
the installation of such a check valve shall not be carried out in systems that use the cold
feed for expansion. In these cases, U-bend or S-bend shall be installed in the cold-feed,
sufficient distance from the connection to the calorifier, so that water which is warm is not
displaced (on heating up) beyond the bend and the vertical pipe rise.
Where practicable, all pressurisation/expansion vessels shall be of the flow- through type.
Where pressurisation vessels are of the single entry type they must be fitted with
appropriate flow-through valves or drain valves to facilitate flushing of the unit.
The practice of terminating the air vent over the Water Storage Tank shall be outlawed.
The vent shall be arranged to discharge over a separate tun-dish arrangement, with visible
Type A air gap, sited at a level that takes account of the hydrostatic head of the system.
The calorifier or water heater shall be provided with a suitable safety valve of appropriate
size and vacuum release arrangement.
Where water quality indicates the need, cathodic protection from galvanic action by means
of sacrificial anodes shall be provided.
Calorifiers shall be fitted with a de-stratification pump, where deemed necessary by
monitoring and/or risk assessment, in order to avoid temperature stratification of the
stored water. Some semi-storage/high-efficiency Calorifiers are supplied with an integral
pump that circulates water in the Calorifier. De-stratification pumps shall not be fitted to
this type of unit.
A single circulating pump shall normally be installed in the return. If, for reasons of
reliability, two pumps are installed in parallel they shall be arranged to have individual non-
return and service valves and be controlled such that each one is brought into operation
twice a day.
When Calorifiers are isolated from the system (for whatever reason), the associated
distribution system shall be subjected to DAILY flushing. However, this is only necessary
when the Calorifier isolated is the sole supply of Hot Water Services (HWS) to that
distribution system. Where more than one Calorifier supplies the distribution services, the
isolated calorifier shall be drained down and remain drained whilst off line.
A suitably sized drain shall be connected to the base of each calorifier (where practicable).
Calorifiers shall be maintained at the following temperature profiles at all times:
o “Stored” and “Flow” at ≥60.0oC
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 6
o “Return” at ≥50oC - “Return” temperatures must be measured from each
“Return” leg
o “Distribution” at ≥50oC
o “Drain” at ≥50oC
In order to ensure that the temperatures required to achieve thermal disinfection (>60ºC
for the “Flow” and >50ºC for “Distribution”) are maintained, it is important to ensure that
the Calorifiers should be allowed to operate continuously ensuring that the heat source is
available constantly. Where the Primary Heating Source is not set by a timer, the heating
source shall be left ‘on’ at all times.
Where Calorifiers are to be operated on a timed basis, the cylinder and recirculating
system (where fitted) shall be held at >60ºC for one hour per day. Shunt pumps may
require fitting to ensure the cylinder can comply with this temperature. The reduction
in overnight temperature shall also be considered in the risk assessment and any
recommendations for increased monitoring shall be instituted. Proof of system compliance
will be required to be provided which shall include monitoring for Legionella 6 monthly
on each system and an annual verification of the pasteurisation regime. If Legionella levels
cannot be controlled to within expected levels by this regime, an additional control regime
(such as chlorine dioxide) will be required to enable timer use.
Calorifiers shall be subjected to regular manual check for “Flow” and “Return”
temperature to each vessel and return temperature from each return leg. BMS may only
be used as the monitoring device where all points required to be taken are fitted with BMS
sensors and the sensor has been calibrated within the last 12 months, otherwise manual
monitoring will be required.
Where practicable Calorifiers shall have water softening devices fitted where water is
stored over 60oC to prevent scaling and degradation of the calorifiers. Softening systems
shall only be allowed to be fitted with the approval of the Compliance Manager.
Cleaning, flushing and pasteurisation shall be carried out in the event of major
modifications or after a period out of service, before a Calorifier is returned to service.
Where temperatures in the calorifier and/or recirculating system are reduced to below
48ºC due to temporary shutdowns (including holiday shutdowns) or system failure for a
duration of more than 30 days, the calorifier shall be drained and refilled, then system shall
be pasteurised for one hour before being allowed back “on-line”. All outlets, drains and
dead legs shall be flushed during the pasteurisation period for at least 5 minutes achieving
a temperature of >60ºC.
Where temperatures in the recirculating system are reduced to below 48ºC due to
temporary shutdowns (including holiday shutdowns) or system failure for a duration of
less than 30 days, the system shall be pasteurised for one hour before being allowed
back “on-line”. All outlets, drains and dead legs shall be flushed during the pasteurisation
period for at least 5 minutes achieving a temperature of >60ºC.
Return and shunt pumps shall be overhauled on an annual basis (where this is a stated
requirement) or shall be serviced and maintained to manufacturers specifications.
Cistern-type water heaters shall be maintained such that the cold tank part of the heater is
kept clean and at the correct temperature, and the hot tank part maintained at a
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 7
temperature of >60.0oC allowing for distribution temperatures of >50.0oC. A screened
vent and an insect/rodent overflow screen shall be fitted to the tank part of the units.
Instant water heaters (<5litres), including combination boilers, usually store small water
volumes, and because of this they do not usually need to be operated within the
temperature profile and limits prescribed for larger systems (≥60oC for the ‘flow’ and
(≥50oC for the ‘return’ and ‘outlet’) which are necessary for thermal disinfection. It is UWE
policy to operate these units to achieve an outlet temperature of ≥50oC. They should
however be switched on at all times to ensure and encourage adequate use.
Hot water and cold water distribution systems
The design and installation of the hot and cold water distribution system shall comply
with the Water Supply (Water Fittings) Regulations 1999 and BS 8558:2011.
The design of the pipework shall ensure that there is no possibility of a cross- connection
between installations conveying potable water and an installation containing non-
potable water or water supplied from a private source (untreated). There shall be no
possibility of backflow towards the source of supply from any tank, cistern or
appliance, whether by back siphonage or otherwise.
All cold distribution pipework, mains and tank down feeds shall be located, as far as is
practicable, to minimise heat gains from their environment. Pipework shall not be routed
through hot ducts or run adjacent to heat sources, such as radiators.
All pipework shall be insulated, except for any exposed final connections to facilities,
and shall be arranged to eliminate or minimise dead-legs.
As far as possible, the objective shall be to design the cold water systems to ensure
that the inlet, outlet and surface water temperatures of cold water storage tanks are
not greater than 2°C above that measured at the main water meter. Also, at cold water
draw-off points, a temperature of not greater than 2°C above the temperature measured
in the source Cold water storage tanks shall be reached within one minute.
Stagnation shall be avoided. Hot and cold water services shall be sized to provide
sufficient flow at draw-off points. The aim is to promote turnover of water by means of;
the design of the distribution circuitry, adequate usage and avoidance of “disused” areas.
Where practicable; separate drinking water systems shall be provided directly from the
incoming water supply to each building without storage, with stored cold water (down
service) being used solely for supplies to WCs, wash hand basins, etc. The supply shall
not be chemically softened. Additionally, it shall be established that the usage is sufficient
to avoid deterioration in water quality, for example, that the outlet water temperature does
not exceed 20OC and that the outlet remains in use. Where drinking water is stored, the
tanks shall conform to WRAS and BS8558 guidance for drinking water storage systems.
Wherever drinking water is stored, a “post-flush” TVCC sample will be required to be
taken from a designated drinking water outlet from each system on a 6 monthly basis.
The water supply to vending and ice making equipment shall be taken from a potable
supply up stream of a regularly used outlet with the minimum of intervening pipe run
i.e. less than 3 metres. The supply shall not be Chemically softened. Additionally, it shall
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 8
be established that the usage is sufficient to avoid deterioration in water quality, for
example, that the inlet water temperature does not exceed 20OC and that the outlet does
not remain unused.
The equipment shall be positioned so that the warm air exhaust does not impinge
directly on taps or hoses supplying cold water.
The domestic hot water system shall not be used for heating purposes. This includes
all radiators, towel rails, heated bedpan racks etc, whatever the pipework configuration.
Central “common blending” systems shall not be installed, since the length of distribution
pipework containing water in the temperature range that supports bacterial growth and
proliferation would far exceed the maximum permissible lengths mentioned above. Where
already fitted with a run of more than 2 metres between the mixer and outlet, they shall
be subjected to a weekly flush of all outlets.
Designated drinking water systems and outlets shall be designed to be maintained
within 2oC of incoming mains water temperature.
Projects shall allow for isolating the unused sections from the system and possibly removing
pipe-work and fixtures completely to avoid "dead-legs”
It is UWE’s policy not to fit hose-reels and to decommission existing reels at the earliest
opportunity.
Showers baths and thermostatic mixing valves/taps (TMV/TMT)
At outlets fitted with TMVs/TMTs, the temperature shall be designed to achieve:
o 41oC for showers
o 41oC for basins
o 38oC for bidets
o 44oC for baths
The pipe-work length from TMV to the outlet shall be restricted to a maximum of 2m.
All TMVs/TMTs shall be fitted with strainers, isolation valves and non-return valves.
All TMVs shall be accessible.
Central “common blending” shower-block systems shall not be installed and all pipe-work
length from the TMV to the shower-head shall be restricted to a maximum of 2m.
Where “common blending” shower-block systems are already in place, each system
shall be fitted with a solenoid valve (at the furthest point from the mixer valve),
programmed to automatically purge water for a three minute period each day. Additional
monitoring of these systems may be required as deemed necessary by risk assessment.
Expansion/pressurisation vessels
All new and replacement expansion/pressurisation vessels fitted shall be of the “flow-
through” type.
Expansion vessels shall be located on the cold feed rather than on the hot water side of
the system. The length of pipework between the expansion vessel and cold feed shall be
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 9
as short as practicable, e.g. less than 1 metre.
All existing expansion vessels of the single entry type must be fitted with appropriate
flow-through valves or drain valves to facilitate flushing of the unit. If fitted with a drain,
this drain must be flushed on a weekly basis.
Usage evaluation
Designers shall undertake 'usage evaluation' of the following and shall specify weekly flushing
(or manual or automatic flushing of the supply pipes using bleed valves) if the usage is found
to be infrequent:
De-ionisers
Dishwashers/washing machines.
Injection moulding machines (total water loss).
Indoor, ornamental water features
Prohibited features
Lathes or CNC machines using organic cutting oils
Portable “wet” evaporative cooling point-of-use units
Greywater systems
Greywater systems shall comply with BS 8525-1:2010 - Greywater systems – Part 1: Code of
practice and BS 8525-2:2011 - Greywater systems –Part 2: Domestic greywater treatment
equipment – Requirements and test methods.
Temporary water supplies
UWE, or others on its behalf, when providing and managing temporary water supplies,
shall comply with their duties under the Health and Safety at Work etc. Act and BS
8551:2011 - Provision and management of temporary water supplies (not including
provisions for statutory emergencies).
Irrigation systems
Irrigation systems shall only use treated water (or treated grey water) and water shall
not be dispersed using sprays.
Ice making machines
Ice is defined as food under the Food Safety Act 1990 and must be made, stored and
handled so that it is not contaminated, a requirement of the Food Safety (General Food
Hygiene) Regulations 1995.
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 10
In order to control the potential of microbiological and other contamination, the following
actions shall be considered and implemented:
o Connect the machine directly to the drinking water supply, ensuring that the supply
pipework is as short as possible and insulated from passive heat gain, particularly in
locations where the supply pipework is directly next to the cooling fan.
o Site the machine in a clean room, away from sources of contamination such as human
waste (in sluice rooms) and cleaning chemicals.
Outdoor ornamental fountains and water features
For ornamental features in public settings, designs should prevent public bathing.
Humidified food cabinets
Designs to comply with established best practice.
Ion exchange water softeners
Designs to comply with established best practice.
Portable humidifiers
Portable humidifiers shall not be used without the written permission of the Compliance
Manager who would need to ascertain suitability of use following an adequate risk assessment.
2 Training at handover
Where necessary, training shall be provided at handover. This should be extended beyond
Estates to facilities colleagues and will include staff involved in using ice making machines,
humidified food cabinets etc.
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 11
3 Handover documentation
Domestic water services
Process No. 2.1
Task Building handover protocol from build contractor to UWE for new buildings
and major refurbishments
System Domestic water services
Requirements Prior to Handover (action by main contractor)
Cleaning and Disinfection:
BS 8558.
The system once totally complete is to be cleaned and disinfected. This process is to include:
Mains cold water services
Stored cold water services
Hot water services
Only spray devices – showers, spray taps etc
Devices that may trap debris – TMV/TMT, Filters etc
All individual outlets - taps
Microbiological
Sampling:
BS 7592. BS 8558.
Following the cleaning and disinfection microbiological samples are to be
taken across the system to give a representation of the potable water quality within the building. Samples are to be submitted to a UKAS laboratory for
analysis. Samples are to be taken from the following points:
Mains cold water services (entry point and furthest extremity) - TVCC
Stored cold water services (closest to storage and furthest point from
storage) - TVCC
Hot water services (each hot water generator and furthest point from
generator) – TVCC and Legionella TVCC:
Total viable count at 22oC
Total viable count at 37oC
Coliforms
E.Coli
Temperature
Profile :
L8. HSG274 Part
2.
Water temperatures a r e to be recorded 3 times equally spaced over 24
hours following the commissioning of the system. Temperatures to be achieved:
Stored cold water - <20 oC after 2 minutes of running
Cold water distribution (furthest point) - <20 oC after 2 minutes of
running
Hot water generator – min 60 oC
Return to hot water generator - > 50 oC
Hot water distribution (nearest and furthest points from hot water generator) - > 50 oC after 1 minute of running)
Flushing:
L8.
HSG274 Part 2.
Where a time period of longer than 1 week occurs between the cleaning and
disinfection process and handover to UWE a programme of weekly flushing is to be undertaken.
A sequential process of flushing each outlet is to be carried out. Flush the outlets until the temperature at the outlet stabilises and is comparable
to supply water and purge to drain.
Requirements Post Handover – within 2 weeks (action by UWE legionella consultant)
Legionella risk
assessment:
L8
A legionella risk assessment is to be carried out to assess the risk from the
legionella organism.
The assessment is to be carried out once building occupancy levels have reached “normal” operating conditions.
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 12
Handover documentation record
Building Name
Handover date
Documents Yes No N/A
Schematics
Cleaning and disinfection certificate
UKAS microbiological certificates
Temperature profile
Flushing records
WRAS certification
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 13
Process water systems
Process Number 2.2
Task Building handover protocol from build contractor to UWE for new buildings and major refurbishments
System Process water systems
Requirements Prior to Handover (action by main contractor)
Cleaning and
Disinfection:
Design guide for specific system
HSG274 Part 3
The system once totally complete is to be cleaned and disinfected. This
process is to include:
Storage device within system
Cold water distribution
Hot water distribution
Spray devices
Devices that may trap debris – Filters etc
All individual outlets
Microbiological Sampling:
BS 7592.
BS 8558.
Following the cleaning and disinfection microbiological samples are to be taken across the system to give a representation of the water quality.
Samples are to be submitted to a UKAS laboratory for analysis. Samples are to be taken from the following points:
Mains cold water services feeding the system - TVCC
Stored cold water services (closest to storage and furthest
point from storage) - TVCC
Hot water services (each hot water generator and furthest
point from generator) – TVCC and Legionella
Spray outlet - Legionella TVCC:
Total viable count at 22oC
Total viable count at 37oC
Coliforms
E.Coli
Flushing:
L8.
HSG274 Part 3.
Where a time period of longer than 1 week occurs between the cleaning and disinfection process and handover to UWE a programme of weekly
flushing is to be undertaken.
A sequential process of flushing each outlet is to be carried out. Flush the outlets until the temperature at the outlet stabilises and is
comparable to supply water and purge to drain.
Post Handover – within 2 weeks (action by UWE legionella consultant)
Legionella risk
assessment
L8
A legionella risk assessment is to be carried out to assess the risk from
the legionella organism. The assessment is to be carried out once building occupancy levels have
reached “normal” operating conditions.
Handover documentation record
Building
Handover date
Documents Yes No N/A
Schematics
Cleaning and disinfection certificate
UKAS microbiological certificates
Flushing records
WRAS certification
Chapter 2 | Design and Handover of Water Systems Issue 1 Page | 14
Closed heating and cooling circuits
Process Number 2.3
Task Building handover protocol from build contractor to UWE for new buildings and major
refurbishments
System Heating and cooling closed circuit systems
Requirements Prior to Handover (action by main contractor)
Pre-Commission cleaning:
BSRIA Pre-Commission Cleaning of Pipework Systems BG29
BG50 Water Treatment for Closed Heating
and Cooling Systems
The system once totally complete is to be pre-
commission cleaned in accordance with BSRIA standards.
Microbiological and chemical sampling:
BSRIA Pre-Commission Cleaning of
Pipework Systems BG29
BG50 Water Treatment for Closed Heating and Cooling Systems
On completion of the pre-commission cleaned
the system is to be sampled in accordance with
BSRIA standards. The samples are to be submitted to a UKAS accredited laboratory.
Handover documentation record
Name of Building
Handover date
Documents Yes No N/A
Schematics
Pre-commission cleaning certificate
UKAS microbiological and chemical certificates
BACK | HOME | FORWARD 1
UWE signage design guidelines
Version 1.0
September 2017 CONTENTS
BACK | HOME | FORWARD 2
Contents Introduction 3
Basic elements 4UWE Logo 5
Colour 6
Typeface 7
Pictograms 8
Campus map 9
Sign reference protocol 10
Materials and finishes 11
External signage 12Overview 13-14
Primary entrance signs (Type 1) 15
Direction signs (Type 2) 16-18
Fingerpost signs (Type 3) 19
Map signs (Type 4) 20
Building signs (Type 5) 21-22
Car park and info signs (Type 6) 23
Internal signage 24Overview 25-26
Sign construction principle 27
Block identification signs (Type 1) 28
Destination signs (Type 2) 29
Direction signs (Type 3) 30
Map signs (Type 4) 31
Directory signs (Type 5) 32
Toilet/lift/shower signs (Type 6) 33
Room information signs (Type 7) 34
Gallery 35External signs 36
Internal signs 37-38
Contact and resources 39
BACK | HOME | FORWARD 3
Introduction In the Spring of 2016 a new brand was created and implemented for The Univervisity of the West of England (UWE).
With the emergence of the new UWE brand, there was a need and opportunity to unify and clarify an integrated signage system that incorporates and is inline with the new brand ethos.
The following pages give an overview for the design and specification of the new UWE signage scheme.
This document gives details for interior and exterior signage in their respective sections, with a gallery of already produced signage examples at the back of this guideline.
When creating new signage, always check (see contact reference page) to see if there is an existing template available. This will help to achieve consistency of delivery across all of our signage.
New signage (interior or exterior) should not be commissioned without the approval from the UWE facilities department (see contact page for details).
BACK | HOME | FORWARD 4
UWE Logo 5
Colour 6
Typeface 7
Pictograms 8
Campus map 9
Sign reference protocol 10
Materials and finishes 11
Basic elements
BACK | HOME | FORWARD 5
Basic elements
UWE LogoIn almost all instances of signage (external and internal) the UWE logo appears at the top, either centred or ranged right and set onto a grey background.
To ensure that you use the correct version of the UWE logo, refer to the UWE brand guidelines.
For specific sizes and placement, please see the relevant pages that follow for further information. Frenchay
Campus
North Entrance
All visitors must report to reception
Car parks 1-11 P
Glenside Campus
BACK | HOME | FORWARD 6
Basic elements
ColourThe 2 key colours for all UWE signage is Grey and White. This has been implemented to help avoid a confusion of colour, improve legibility and imply a sense of consistency across all signage.
Colour finishes
Statutory palette
Material finish
UWE Red (satin)
to match PMS 185c
C:0 M:100 Y:100 K:0
Parking Blue (satin)
to match PMS 185c
C:100 M:20 Y:100 K:0
Metallic silver (satin)
Stainless Steel / aluminium
Metallic silver (satin)
Powder coating or spray finish
Signage Grey (satin)
to match PMS 431c
C:10 M:0 Y:0 K:65 or
RAL 7005
Traffic White (satin)
RAL 9016
Display panel colour
CautionPMS Process Yellow
PMS Process Black
FirePMS 340 Green
High white
ProhibitionPMS 485
High white
InformationPMS Process Blue
High white
Signage panel construction finish (excluding display panel faces)
UWE brand mark when used on signage panels
Parking symbol and blue elements on car park signs
Lettering, arrows, pictograms and graphic information. Also background colour for destination panels
BACK | HOME | FORWARD 7
Basic elements
TypefaceSignage at UWE is to be set exclusively in Parisine Pro (Regular/Bold)
As a general rule, information/direction text should be set in Parisine Pro Regular and Building names/titles/headings etc ... in Parisine Pro Bold.
Parisine Pro Bold
ABCDEFGHijkLmnoPqRstuVwxyzabcdefghijklmnopqrstuvwxyz1234567890
Parisine Pro Regular
ABCDEFGHIjKLMNOPqRSTUvWxYzabcdefghijklmnopqrstuvwxyz1234567890
BACK | HOME | FORWARD 8
Cashpoint Wifi
Basic elements
PictogramsHere is a selection of pictograms that are appropriate for use on UWE signage. As further pictograms are required, always consult with the originators of the pictogram family (see contact page for details).
Male toilet Baby feeding facilities
First aid
Bus Motorcycles
Female toilet Accessible toiletGender neutral toilet
Shop
Showers
Parking
Cloakroom
Information
No vaping/smoking
Café
Cycle rack
Stairs
Braille
No photography
Car
Lift
No eating/drinking
Cycles
Accessible liftMulti Faith room
No mobile phones
Baby change
Pedestrians
Data points
BACK | HOME | FORWARD 9
Basic elements
Campus mapSubheading textBody text
Campus map project to be agreed / advised by UWE team
BACK | HOME | FORWARD 10
Basic elements
Sign reference protocol and id stickers (asset tags)Every sign throughout each campus will have it’s own unique reference and asset tag.Shown here is the protocol that was used for generating signage references.
This should also be used when adding new signage for any part of a campus.
Asset tags are self adhesive stickers 50mm x 20mm and applied to a discreet edge or reverse of sign, whichever is more appropriate.
Asset tags will enable easy cross referencing when any changes/amends are required.
Layout details
1 Parisine Regular 25pt. Centred
Example sign referencesUWE Campuses:
Frenchay (including Bristol Business Park)
Glenside
Internal signs
External signs
UWE City Campuses:
Arnolfini
Bower Ashton
Spike Island
Watershed
UWE Floor levels:
*1 – Lower Ground Floor
2 – Ground Floor
3 – First Floor
4 – Second Floor
5 – Third Floor
6 – Fourth Floor
7 – Fifth Floor
* Buildings without a Lower Ground Floor will start at 1 – Ground Floor
Campus reference (this instance refers to ‘Frenchay’)
Floor reference (this instance refers to Floor 2)
Sign number (an allowance of up to 999 signs per floor)
Building reference (this instance refers to building ‘N’)
FN2 001
Campus reference (this instance refers to ‘Glenside’)
This refers to ‘External’)
Sign number (an allowance of up to 999 signs)
GE- 001FN2001
1
50mm
20mm
BACK | HOME | FORWARD 11
Basic elements
Materials and finishesShown here are a selection of typical materials and finishes that have already been adopted for new UWE signage.See ‘Gallery’ section for more examples of new signage.
Resin display panels Perspex/acrylic panels with white opaque backing
Aluminium for large graphic and information display panels
Stainless steel/aluminium for sign background panels
Detail of toilet sign edgeToilet signs with chamfered edge
Stainless steel floor numbers applied to walls
White acrylic floor number signs Brushed stainless steel posts
BACK | HOME | FORWARD 12
External signageOverview 13-14
Primary entrance signs (Type 1) 15
Direction signs (Type 2) 16-18
Fingerpost signs (Type 3) 19
Map signs (Type 4) 20
Building signs (Type 5) 21-22
Car park and info signs (Type 6) 23
= 100 mm square
BACK | HOME | FORWARD 13
Glenside Campus
Main reception
Library
Student Union
Blackberry Centre
The Riverside Unit
Medical Records
Education Centre
A B
D E
All visitors must report to reception
Car parks 1-11 P
Glenside Campus
Cycle path
Pedestrians
Information point
Car Parks 1–3P
P
P q
A-n
Centre for Performing Arts
Mallard House
visitor Car Park 19 iFrenchay Campus
North Entrance
Type 1Primary entrance signs
Type 2Direction signs
Type 3Fingerpost signs
External signage
Overview 1 of 2This page shows a general layout and size proportions for the following sign types:
Type 1 Primary entrance signs
Type 2 Direction signs
Type 3 Fingerpost signs
Type 4-6 signs (see next page)
See relevant sign pages for details of each sign type.
Building signs (occupancy)
Type 4Campus map signs
Type 5Building signs (letter identification)
Type 6Car park and information signs
BACK | HOME | FORWARD 14
Private land
uwE Bristol sande volupta tiasin et aut es eaquatem. Ris dusam in
Restricted Access (Parking charges apply)See notes in car park for detail. vehicles parked entirely at owners risk
For authorised users only
ACar Park
uwE Bristol sande volupta tiasin et aut es eaquatem. Ris dusam in
3
k
A B C D E F G H i j k
Glenside CampusMap
KeyAccum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archict
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archictv
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
you are here
Occupation information
Occupation information
Occupation information
Occupation information
Occupation information
Frenchay Campus D
Title of this Building
Glenside Campus
Catherine Hawkins Building
Glenside Campus k
Glenside Library
External signage
Overview 2 of 2This page shows a general layout and size proportions for:
Type 4 Campus map signs
Type 5 Building (identification and occupancy) signs
Type 6 Car park and information signs
See relevant sign pages for details of each sign type.
= 100 mm square
= 100 mm square
BACK | HOME | FORWARD 15
External signage
Primary entrance signs (Type 1)
Materials and features• Monolithfreestandingconstruction
• Internalilluminationoption
• Powdercoatedorsprayedsatinsilveraluminium side returns/border
• Acyclic,white/greyfrontfacepanels
• Steel,boxconstructionplinthsetintoconcrete foundation
• 50mmcornerradius
Layout details
1 Centred 750mm wide UWE logo
2 Parisine Bold 600/720pt. 200mm left margin
3 Parisine Regular 450pt. 200mm left margin
Frenchay Campus
North Entrance
Type 1aFull height version
Side profile
Type 1bLow level version
1
1
2
2
3
3 North Entrance
Frenchay Campus
Edge detail
Signage Grey (satin)
RAL 7005
Signage Grey (satin)
RAL 7005
UWE Red (satin) to match
Pms 185c
White acrylic panel
Metallic silver (satin)
sprayed or powdercoat
Metallic silver (satin)
sprayed or powdercoat
= 100 mm square BACK | HOME | FORWARD 16
External signage
Large direction signs (Type 2a)
Materials and features• 2000mmwide,aluminiumdisplaypanels
• 90mm,satinstainlesssteelposts
• UWEbrandingongreysurface
• Wayfindinginformationonwhitesurface
• Upper/lowercornersonpanelsareradiused(interior corners of slats are square)
• Multipleslat,singlepanelanddual panel options
• Thisversionshows9slats200mmhighandset 30mm apart
• 50mmcornerradius(whereapplicable)
Layout details
1 500mm wide UWE logo set 210mm from right edge
2 Parisine Bold 450/550pt. 110mm left margin
3 Parisine Regular 450/550pt. 110mm left margin
4 160mm high arrow set 110mm from right edge
5 130mm high arrow set 110mm from left/right edge
6 100mm ‘block’ letters set 350mm from left edge and spaced 20mm apart
7 Parisine Regular 240pt. 350mm left margin
Bower Ashton Campus
Department of Creative Industries
Main Entrance
Glenside Campus
Main reception
Library
Student Union
Blackberry Centre
The Riverside Unit
Medical Records
Education Centre
A B C
D GE HF j k
Multiple slat version (1200 x 2750 approx)
Single panel example (1200 x 2000)
1
2
5
6
7
3 4
5
Signage Grey (satin)
RAL 7005
UWE Red (satin) to match
Pms 185c
Traffic White (satin)
RAL 9016
Metallic silver (satin)
stainless steel
200mm slats set 30mm apart
Panel fixing detail
Lower panel/post detail
Post cap fixing detail
Signage Grey (satin)
RAL 7005
= 100 mm square
BACK | HOME | FORWARD 17
External signage
Medium direction signs (Type 2b)
Materials and features• 1200mmwidedisplaypanels
• Satinstainlesssteel90mmposts
• UWEbrandingongreysurface
• Wayfindinginformationonwhitesurface
• Upper/lowercornersonpanelsareradiused(interior corners of slats are square)
• Multipleslat,singlepanelanddual panel options
• 35mmcornerradiustopanels
Layout details
1 320mm wide UWE logo set 100mm from right edge
2 Parisine Bold 300/360pt. 100mm left margin
3 80mm symbol set 100mm from left edge
4 Parisine Regular 200pt. 100mm left margin
5 65mm high arrow set 100mm from right edge
6 Parisine Regular 300/380pt. 100mm left margin
7 100mm high arrow set 100mm from left edge
Glenside Campus
Museum
All visitors must report to reception
Car Park 6 Cycle Park
Retail Deliveries
Car Parks 16, 17
Loading Bayn
UWE Exhibition and Conference Centre
Campus destination example (1200 x 1000)
Direction only example (1200 x 800)
Single message example (1200 x 700)
4 7
2 53
6
1
Signage Grey (satin)
RAL 7005
Signage Grey (satin)
RAL 7005
UWE Red (satin) to match
Pms 185c
Traffic White (satin)
RAL 9016
Metallic silver (satin)
stainless steel
Panel fixing detailPost cap fixing detail
Lower panel/post detail
= 100 mm square
BACK | HOME | FORWARD 18
External signage
Small direction signs (Type 2c)
Materials and features• 1000mmwidedisplaypanels
• Satinstainlesssteel75mmposts
• UWEwelcomemessageongreysurface
• Wayfindinginformationonwhitesurface
• Upper/lowercornersonpanelsareradiused(interior corners of slats are square)
• Multipleslat,singlepanelanddual panel options
• Individualslatsare185mmhighandset 20mm apart)
• 25mmcornerradius(whereapplicable)
Layout details
1 Parisine Bold 200pt. 60mm left margin
2 60mm symbol set 60mm from left edge
3 65mm high arrow set 60mm from right edge
4 Parisine Regular 300/380pt. 100mm left margin
5 100mm wide (as shown) arrow set 60mm from right edge
6 Parisine Regular 200pt. 60mm left margin
GlensideTRADERSdeliveries
welcome to uwE Bristol
4 slat example (1000 x 800)
3 slat example (1000 x 600)
Single panel example (1000 x 600)
Single slat example (1000 x 185)
Double slat example (1000 x 380)
1 2 3 4 5 6
Car Parks 16, 17
n
Car Parks 16, 17
Car Parks 16, 17
Retail DeliveriesReception
Loading bay
Cycle path
Cycle path
Pedestrians
Signage Grey (satin)
RAL 7005
Signage Grey (satin)
RAL 7005
Traffic White (satin)
RAL 9016
Metallic silver (satin)
stainless steel
Panel fixing detailPost cap fixing detail
Lower panel/post detail
Lower panel/post detail
= 100 mm square= 100 mm square
BACK | HOME | FORWARD 19
External signage
Fingerpost signs (Type 3)
Materials and features• Satinstainlesssteel90mmposts
• Wayfindinginformationonwhite acrylic slats (800mm x 90mm)
• Upper/lowercornersonslatsareradiused(interior corners are square)
• Slatsarealignedverticallywithhiddenlocating pins
• Maximum6slatsperelevation.Ifmorearerequired, group information on 1 slat to save space
• 25mmcornerradius(whereapplicable)
Layout details
1 Parisine Regular 120pt. Ranged left 40mm left edge. 1 character space away from symbol (where applicable)
2 53mm symbol. 40mm left/right margin. Multiples set 10mm apart.
3 Parisine Regular 120pt. Ranged right 40mm from right edge. 1 character space away from symbol (where applicable)
Information point
Car Parks 1–3P
P
P q
A-n
Centre for Performing Arts
Mallard House
visitor Car Park 19 i
Centre for Performing Arts
visitor Car Park 19
Car Parks 1–3P
P
1
Information point
P q
A-n
i
3 2
2
Signage Grey (satin)
RAL 7005
White acrylic panel
Metallic silver (satin)
stainless steel
Slat profile detail
= 100 mm square
BACK | HOME | FORWARD 20
External signage
Map signs (Type 4)
Materials and features• Monolithfreestandingconstruction
(Type 4a)
• Powdercoatedorsprayedsatinsilversidereturns/border
• UWEbrandingongreysurface
• Wayfindinginformationonwhitesurface
• Mappaneltoberemovableforupdates
• 50mmcornerradius
Layout details
1 260mm wide UWE logo set 90mm from right edge
2 Parisine Bold/Regular 170/200pt. 90mm left margin
3 Map design TBC
4 Key layout/design TBC
A B C D E F G H i j k
KeyAccum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archict
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archictv
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
you are here
you are here
A B C D E F G H i j k
KeyAccum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archict
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archictv
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
you are here
Type 4aMonolith version
Type 4bWall mounted version
Glenside CampusMap
Glenside CampusMap
1
2
3
4
Edge detail
Signage Grey (satin)
RAL 7005
Signage Grey (satin)
RAL 7005
UWE Red (satin) to match
Pms 185c
White acrylic panel
Metallic silver (satin)
sprayed or powdercoat
= 100 mm square
BACK | HOME | FORWARD 21
External signage
Building occupancy signs (Type 5a/b/c)Materials and features• Powdercoatedorsprayedsatinsilverside
returns/border
• UWEGreytitlepanels
• Whiteacrylicinformationpanels
• Letteringexternalgradevinyl
• Occupancyinformationonwhitesurface
• Wallorpostmounted
• 35mmcornerradiustopanels
Layout details
1 140mm wide UWE logo set 50mm from right edge
2 Parisine Bold 250/280pt. 50mm left margin
3 Parisine Regular 75pt. 50mm left margin
4 Parisine Regular 100/120pt. 50mm left margin
5 1.5mm grey separator line. 50mm left margin
6 Parisine Bold 150/180pt. 50mm left margin
7 315mm wide UWE logo set 80mm from right edge
8 Parisine Regular 180pt. 60mm left margin
9 Parisine Bold 380/450pt. 60mm left margin
1 7
Type 5aSmall/medium version (building name only)
600/900mm x 400mm
Type 5aSmall version (building name and single occupation information)
600mm x 400mm
Type 5bSmall version (building name and multiple occupation information)
600mm x 900mm
Type 5cLarge version (building name and multiple or single occupation information)
900mm x 600/1200mm
Glenside Campus k
Glenside Library
Frenchay Campus
Occupation information
D
title of this Building
Occupation information
Occupation information
Occupation information
Occupation information
Occupation information
Frenchay Campus D
title of this Building
Occupation information
Occupation information
Occupation information
Occupation information
Occupation information
Frenchay Campus D
title of this Building
Pervasive Media Studio
Cultural Studio
Café and Bar
Conference Centre
uwE Bristol
Frenchay Campus D
Frenchay Campus A
Coursework Hub
Glenside Campus
Catherine Hawkins Building
Glenside Campus
Catherine Hawkins Building 2
3
4
58
9
6Edge detail
Signage Grey (satin)
RAL 7005
Signage Grey (satin)
RAL 7005
UWE Red (satin) to match
Pms 185c
White acrylic panel
Metallic silver (satin)
sprayed or powdercoat
= 100 mm square
BACK | HOME | FORWARD 22
External signage
Building letter identity signs (Type 5d/e)Materials and features• Highvisibilitybuildinglettersigns
• Mountedatprominentlocationsonbuilding exteriors for clear orientation
• TrafficWhite(RAL9016)letteronUWEgrey aluminium, box constructed panels
Layout details
1 600mm high Parisine Bold letterform. Centred
2 50mm corner radius
3 370mm high Parisine Bold letterform. Centred
4 35mm corner radius
Type 5dLarge version (for identifying buildings at a further distance)
1000mm x 1000mm x100mm
Type 5eSmall version (for closer distance identification)
600mm x 600mm x 70mm
kA1 2 43
Signage Grey (satin)
RAL 7005
Traffic White (satin)
RAL 9016
= 100 mm square
BACK | HOME | FORWARD 23
External signage
Car park and info signs (Type 6a/b/c)Materials and features• Satinstainlesssteel90/75mmposts
• 3-sidedoptionforType5asigns
• Aluminium(dibond)displaypanels
• Panelstohaveradiusedcorners
Panel sizes
1 Medium information, orientation signs 600mm x 900mm (90mm posts) 35mm radius corners
2 Dual message symbol signs 300mm x 600mm (75mm posts) 25mm radius corners
3 Single message symbol signs 300mm x 300mm (75mm posts) 25mm corners
Pay here
uwE Bristol sande volupta tiasin et aut es eaquatem. Ris dusam in
Car Park
uwE Bristol sande volupta tiasin et aut es eaquatem. Ris dusam in
3Private land
uwE Bristol sande volupta tiasin et aut es eaquatem. Ris dusam in
Restricted Access (Parking charges apply)See notes in car park for detail. vehicles parked entirely at owners risk
For authorised users only
Sid
e p
rofi
le
Type 6a
3-sided high-level orientation signs
Type 6b
Dual message low-level sign
Type 6b
Single message low-level sign (variable height)
Type 6c
Medium size car park information panel sign
1
3
3
12
Signage Grey (satin)
RAL 7005
Parking Blue (satin)
c100 m20 y0 k0
Parking Blue (satin)
c100 m20 y0 k0
Parking Blue (satin)
c100 m20 y0 k0
Traffic White (satin)
RAL 9016
Metallic silver (satin)
stainless steel
Signage Grey (satin)
RAL 7005
BACK | HOME | FORWARD 24
Internal signageOverview 25-26
Sign construction principle 27
Block identification signs (Type 1) 28
Destination signs (Type 2) 29
Direction signs (Type 3) 30
Map signs (Type 4) 31
Directory signs (Type 5) 32
Toilet/lift/shower signs (Type 6) 33
Room information signs (Type 7) 34
= 100 mm square
BACK | HOME | FORWARD 25
F L2
G H k jE m
1N1-31
1N41-95
Toilets
Lift
n 1L2
information
Coursework HubE
n
Information Point
Students’ Union
Library
Octagon
E L2 The Hub
Student village
Centre for Sport
Exhibition & Conference centre
P q R
Type 2 Destination signs (suspended, wall mounted and vinyl)
Type 3 Direction signs
Student Services
Waiting Area
Type 1 Block ID signs
F
school of Life sciencesDepartment of Applied SciencesDepartment of Psychology
Internal signage
Overview 1 of 2This page shows a general layout and size proportions for:
Type 1 Block ID signs
Type 2 Destination signs
Type 3 Direction signs
(see next page for Type 4-6 signs)
= 100 mm square
BACK | HOME | FORWARD 26
Internal signage
Overview 2 of 2This page shows a general layout and size proportions for:
Type 4 Campus map signs
Type 5 Directory / floor plan signs
Type 6 Toilet/lift/shower signs
Type 7 Room information signs
Note: all signs shown are for example only and not actual signs
you are here
A B C D E F G H i j k
Glenside CampusMap
KeyAccum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archict
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archictv
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
you are here
n 62
Not every disability is visible
name of staff member Position held
1k4 Room Title
name of staff member Position held
name of staff member Position held
name of staff member Position held
1A07 Room Title
Type 4 Campus map signs
Type 5 Directory / floor plan signs
Type 6 Toilet/lift/shower signs
Type 7 Room information signs
Future Students
Strategic Communications and Engagement
Toilets
2
-1
Human Resources
Commercial Services
Research, Business and Innovation
Toilets
Showers
0
Estates and Facilities
Finance
Toilets
1
n 62
A B C D E F G H i j k
KeyAccum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archict
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archictv
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
you are here
Glenside CampusMap
BACK | HOME | FORWARD 27
Sign construction principleShown opposite is a suggested principle of construction that minimises use of materials, keeping weight of signs to a minimum. Details of fixing/bonding etc ... to be specified by manufacturer.
Graphic information is applied as a single vinyl element and can be removed/updated as required.
All signs to have an identification number (sign reference) sticker applied to the top or bottom edge, depending on the hanging height of sign and applied to the most discreet edge.
This method of construction would apply to the following types of sign:
• Type 2 Destination signs
• Type 3 Direction signs
• Type 4 Campus map signs
• Type 5 Directory / floor plan signs
Frame material
Machined and finished, aluminium or sprayed silver resin frame sections.
35mm radiused upper and lower corners.
Butted construction as advised by manufacturer.
Addition of brace/support bar to support display panels on larger signs
Display panel
White opalescent acrylic panel (material to be confirmed) with opaque white backing and vinyl sign graphics affixed to front face.
Option for making display panel removable/replaceable with clip fixing to rear of panel.
vinyl graphic
Single sheet vinyl graphic applied over display panel. Can be removed/updated when required.
Display method
Signs to be fixed to walls/doors/glazing (where appropriate). Also option of suspending double/single sided versions from ceiling.
Constructed sign
20mm frame sections
6mm frame edge to front elevation
Frame dimensions
Standard width of frame is 600mm. This can vary dependant on sign requirements
Height of frame dependant on sign requirements
50mm
3mm display panels
50mm
Edge detail Sign id sticker
Metallic silver (satin)
sprayed or powdercoat
= 100 mm square
BACK | HOME | FORWARD 28
Internal signage
Block identification signs (Type 1)
Materials and features• Clearandconsistentblockwayfinding
• 35mmradiusedcorners
• 400mmx400mmx60mm
• Optionsforsuspending,wallmounting and projecting signs
• 20mmdeep,silver/aluminiummounting block for projecting version
Layout details
1 215mm high Parisine Bold letterform. Centred
2 35mm corner radius
Suspended version
Wall mounted version
Side profile
Side profile
Projecting version
nn
1 2
Signage Grey (satin)
RAL 7005
n
= 100 mm square
BACK | HOME | FORWARD 29
Internal signage
Destination signs (Type 2a/b/c)
Materials and features• Suspended(type2a)orwallmounted(type2b)
• Powdercoatedorsprayedsatinsilversidereturns/border
• Currentlocation/destinationinformationongrey surface
• Forspecificationandfinishsee‘signconstruction principle’ page
• 35mmcornerradiustosigns
Layout details
1 Parisine Regular 400pt. Centred vertically and horizontally
2 Parisine Bold 270pt. Heading centred, margin dependant on message
3 Parisine Regular 170/230pt. Ranged left with heading, margin dependant on message
4 Parisine Regular 300pt. Centred vertically and horizontally
5 110mm symbol
6 Size of message dependant on space available
Note: all signs shown are for example only and not actual signs
Coursework Hub
information
Type 2a (1.6m)
Large suspended version
(1600mm x 400mm)
Type 2a (1.2m)
Large suspended version
(1200mm x 400mm)
Type 2b
Smaller, suspended or wall mounted version
(1000mm x 300mm)
Type 2 c (vinyl)
vinyl decal versions for glazed and facia areas. White lettering applied to tinted background for enhanced legibility. Can also have solid grey background on unglazed areas where appropriate.
Edge detail
school of Life sciencesDepartment of Applied SciencesDepartment of Psychology
1
5
2
3
4
6
Signage Grey (satin)
RAL 7005
Metallic silver (satin)
sprayed or powdercoat
= 100 mm square= 100 mm square
BACK | HOME | FORWARD 30
Internal signage
Direction signs (Type 3)
Materials and features• Suspended(type3a)orwallmounted(type3b)
• Powdercoatedorsprayedsatinsilversidereturns/border
• Currentlocation/destinationinformationongrey surface
• Wayfindinginformationonwhitesurface
• Forspecificationandfinishsee‘signconstruction principle’ page
• 35mmcornerradiustosigns
Layout details
1 70mm ‘box’ graphic, Parisine Bold 170pt characters. 50mm from left edge and spaced 30mm apart
2 45mm ‘box’ graphic, Parisine Bold 110pt characters. 50mm from left edge and spaced 30mm apart
3 Parisine Regular 90/105pt. 50mm left margin
4 1.5mm grey separator line. 50mm left margin
5 30mm high arrow set 50mm from right edge
Note: all signs shown are for example only and not actual signs
Current block location
Current floor level
Current stairwell (if applicable)
Wayfinding information (on white area)
Chamfered or radiused edges to display panel
F G
1N1-31
1N41-95
L 15F 2
G H k jE m
1N1-31
1N41-95
Toilets
Lift
n 12
j H
G m
G H j k
Room 1k4
Rooms 1k5-11
Way out
Toilets
k 1
Information Point
Students’ Union
Library
Octagon
E 2 The Hub
Student village
Centre for Sport
Exhibition & Conference centre
P q R
Type 3a
Large double aspect, suspended version. variable height options to suit requirements
Type 3b
Medium and small signs. variable height options to suit requirements. Wall mounted or suspended as required.
F G
1N1-31
1N41-95
L 15
Edge detail
1
2 3 54
Signage Grey (satin)
RAL 7005
Signage Grey (satin)
RAL 7005
Metallic silver (satin)
sprayed or powdercoat
= 100 mm square
BACK | HOME | FORWARD 31
Internal signage
Map signs (Type 4)
Materials and features• Monolithfreestandingconstruction
(Type 4a)
• Powdercoatedorsprayedsatinsilversidereturns/border
• UWEbrandingongreysurface
• Wayfindinginformationonwhitesurface
• Mappaneltoberemovableforupdates
• 50mmcornerradiustosigns
Layout details
1 260mm wide UWE logo set 90mm from right edge
2 Parisine Bold/Regular 170/200pt. 90mm left margin
3 Map design TBC
4 Key layout/design TBC
Note: all signs shown are for example only and not actual signs A B C D E F G H i j k
KeyAccum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archict
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archictv
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
you are here
you are here
A B C D E F G H i j k
KeyAccum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archict
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
Archictv
Accum volorerovid
Ugat venet parum
ventiae nient
Ut occuptur
quo eos comnis
you are here
Type 4aMonolith version
Type 4bWall mounted version
Glenside CampusMap
Glenside CampusMap
1
2
3
4
Edge detail
Signage Grey (satin)
RAL 7005
UWE Red (satin) to match
Pms 185c
Metallic silver (satin)
stainless steel
= 100 mm square= 100 mm square
BACK | HOME | FORWARD 32
Internal signage
Directory signs (Type 5)
Materials and features For specification and finish see ‘sign construction principle’ page
• 35mmcornerradiustosigns
• Wallmountedwithconcealedfixings
• Currentfloorlevelhighlightedingrey
• 35mmcornerradiustosigns
Layout details
1 70mm ‘box’ graphic, Parisine Bold 170pt characters. 50mm from left edge and spaced 30mm apart
2 Parisine Regular 140pt. 50mm left margin
3 30mm high toilet symbols (male/female). Set 2 character spaces from text
4 Parisine Regular 90/105pt with 12mm paragraph spacing. 120mm left margin
5 1.5mm grey separator line. 50mm left margin
6 Floor plan illustrations to be created as required and in the set style already in place.
Note: all signs shown are for example only and not actual signs
Current block location
Current floor level
Current stairwell (if applicable)
Chamfered or radiused edges to display panel
Future Students
Strategic Communications and Engagement
Toilets
2
1
n 62
Human Resources
Commercial Services
n 62
Future Students
Strategic Communications and Engagement
Toilets
2
-1
Human Resources
Commercial Services
Research, Business and Innovation
Toilets
Showers
0
Estates and Facilities
Finance
Toilets
1
n 62
Wall mounted directory and floor plan signs. Consistent in size and positioned at key stairwell/entrance areas.
Detail of floor plan example (not an actual sign)
1
2 3 4 5
Estates and Facilities
Finance
Toilets
0 Signage Grey (satin)
RAL 7005
Signage Grey (satin)
RAL 7005
Metallic silver (satin)
sprayed or powdercoat
6
6
= 100 mm square= 100 mm square
BACK | HOME | FORWARD 33
Internal signage
Toilet/lift/shower signs (Type 6a/b)
Materials and features• Type6a–projectingsigns200mmhigh
• Type6b–door/wallmountedsigns150mmhigh
• Opalacrylicdisplaypanelswithopaquewhite backing and surface applied grey (PMS 431) vinyl graphics
• Projectingversionconstructedfromx2 5mm panels
• 60mmdeepx90mmwide/highmachined,aluminium mounting block for projecting signs
• Concealingfixingsforallsigns
• 25mmcornerradiustopanels
• ‘Lift’messagecanhavedesignatednumberif appropriate
Layout details
1 Symbols to be set centrally between outer edge and edge of mounting bracket
2 100mm symbol box centred between outer edge and edge of mounting bracket
3 Parisine Bold 80pt. Centred
4 110mm high symbol, centred on panel
Not every disability is visible
Lift
Side elevation
(x2 5mm panels)
Side elevation
(5mm panel)
Type 6a – Projecting signs250mm x 200mm for multi symbol signs
200mm x 200mm for single symbol signs
Type 6b – Door/wall signs
Not every disability is visible
Double-sided projecting version
Door mounted version
1 2 3
4
Signage Grey (satin)
RAL 7005
White acrylic panel
Metallic silver (satin)
stainless steel
Type 6a signs
= 100 mm square= 100 mm square
BACK | HOME | FORWARD 34
Internal signage
Room information signs (Type 7)
Materials and features• Papyrusoff-the-shelfdoorplatesystem
• Singleormulti-occupancyoptions
• Removableinformationpaperpanelfor easy updating.
• WordtemplatesareavailablefromUWEestates (see contact page) for generating new signs
• Signsshouldbescrewedtodoorwherepossible. For fully glazed doors, self adhesive system is available. Grey vinyl is applied to opposite side of glazing to obscure fixing tape on back of signs.
Layout details
1 Small room sign (297mm x 105mm). Use available word template for generating new signs (see contact page for UWE estates details)
2 Large room sign (297mm x 210mm). Use available word template for generating new signs (see contact page for UWE estates details)
3 UWE asset tag reference vinyl sticker for doors and reverse of signs (see page 10 for further detail on asset tags)
4 Parisine Regular 25pt. Centred
Type 7a Size 1
Single occupancy door sign
Signs to be aligned with top of glazed panel for consistency
unique door identification sticker (asset tag)
Type 7b Size 2
Multiple occupancy door sign (suggest x5 as the recommended maximum)
name of staff member Position held
1k4 Room Title
name of staff member Position held
name of staff member Position held
name of staff member Position held
1A07 Room Title
name of staff member Position held
1A07 Room Title
name of staff member Position held
1k4 Room Title
name of staff member Position held
name of staff member Position held
1
2
3FN2001
4
BACK | HOME | FORWARD 35
GalleryExternal signs 36
Internal signs 37
Type 2a – large direction sign
Type 2c – small direction sign
Type 3 – fingerpost sign
Type 2c – small direction sign
Architectural lettering
Facia sign
BACK | HOME | FORWARD 36
External signs
BACK | HOME | FORWARD 37
Internal signs
Type 5 – directory / floor plan signs
Type 6a – projecting lift sign
Type 4 – Campus map sign structure with directory content
Type 6a – projecting toilet sign
Type 3a – suspended direction signs
Door asset tag sticker
BACK | HOME | FORWARD 38
Internal signs
Type 7 – papyrus door sign (small)
Reception desk – illuminated sign
Type 7 – papyrus door sign (large) Large floor id number sign
Type 3a – suspended direction sign detail
BACK | HOME | FORWARD 39
UWE Facilities
Pete Sutherland
Head of Space Management and Design
T: 0117 32 86 284E: [email protected]
Signage design consultants
Howard Miles – Managing DirectorABG Design
T: 01872 248 355E: [email protected]
Contacts and resourcesFor advice on new signage or templates for papyrus door signs, please contact UWE facilities in the first instance.
Note for sign contractors:To be compliant with risk assesment protocol, prior agreement to be on any UWE campus site must be obtained from UWE facilities department before any work or audit is undertaken.
UWE Facilities
Design Guide
Appendix: Acoustic Standards
UWE Design Guide for Buildings
A p p e n d i x | A c o u s t i c S t a n d a r d s I s s u e 1 . 3 P a g e | 1
Contents
1. Introduction ........................................................................................................ 2
2. Sound Insulation between Rooms - Airborne Sound between Rooms ....................... 2
3. Airborne Sound Insulation between Rooms and Circulation Spaces .......................... 3
4. Impact and Air Borne Sound Insulation of Floors .................................................... 4
5. Noise from Outside .............................................................................................. 4
6. Room Acoustics ................................................................................................... 5
7. Noise from Building Services ................................................................................ 6
8. Acoustic Design of Residential Accommodation ...................................................... 7
UWE Design Guide for Buildings
A p p e n d i x | A c o u s t i c S t a n d a r d s I s s u e 1 . 3 P a g e | 2
1. Introduction
This section deals with acoustic standards within new and re-furbished UWE buildings. The
overarching objective is to provide acoustic conditions within each room which are
compatible with its intended purpose.
The acoustic requirements are dealt with under the following headings; • Sound insulation between rooms • Noise entering the building from outside • Room acoustics • Noise from building services • Acoustic Design of Residential Accommodation
Many of the standards are derived from those contained in the DfES publication BB93
Acoustic Design of Schools. The standards described in that publication are, under the
Building Regulations, mandatory for new and refurbished school buildings. For universities
they are not mandatory. While they form a useful starting point, some spaces within a
university fall outside the requirements of most schools, and in some cases higher acoustic
standards may be justified even when rooms are being put to similar uses.
2. Sound Insulation between Rooms - Airborne Sound between Rooms
The table below lists various types of room according to their function, along with the
required level of airborne sound insulation.
Where a wall separates two rooms with different functions, the standard of sound insulation
to be applied will be the higher of the two.
The quantity used to specify sound insulation here is DnT(Tmfmax),w as defined in BB93.
This is the standardized level difference between the two rooms, measured according to the
requirements of ISO 140 part 4 and standardised to the highest recommended mid
frequency reverberation time in either of the two rooms. It is then frequency weighted as
described in ISO 717 part 2. It is not the same as the weighted sound reduction index,
abbreviated to Rw and commonly used by suppliers of building materials to characterise
their products.
UWE Design Guide for Buildings
A p p e n d i x | A c o u s t i c S t a n d a r d s I s s u e 1 . 3 P a g e | 3
Type(s) of Room Min Value of
DnT(Tmfmax),w
Academic staff and admin offices, meeting rooms 45dB
Cafeterias, coffee bars etc. 45dB
Class rooms, lecture rooms, seminar rooms and tutorial rooms.
Audio Visual and video conference rooms and language laboratories
45dB
Drama studios, music practice rooms. 55dB
Halls and rooms for music drama and other live performances 55dB
Large lecture theatres and flagship conference rooms 50dB
Lecture theatres up to 100 seats 45dB
Library circulation and media storage areas 40dB
Library study areas 45dB
Recording studios 60dB*
Rooms intended for clinical examination and treatment,
Confidential interviews, psychotherapy, speech therapy etc.
50dB*
Science laboratories, art and design studios, graphics workshops 40dB
Sports halls and gymnasia 50dB
Swimming pools 45dB
Workshops 45dB*
* Denotes that requirements can vary considerably and specialist design input may be required.
3. Airborne Sound Insulation between Rooms and Circulation Spaces
It is difficult to measure sound insulation values between a room and an odd shaped space
such as a corridor. As a result it is normal to specify minimum values of the weighted sound
reduction index Rw required of partition systems and doors separating a room from a
circulation space. Two levels of sound insulation are specified here for these situations.
Structure Minimum
value of Rw
Partition separating a teaching space or office from a circulation area 40dB
Door within the above partition, rated as a complete door set 30dB
Partition separating a teaching space for specialised purposes (such as
music or drama) from a circulation area
45dB
Door within the above partition, rated as a complete door set 35dB
Specialist acoustic design input will be required if a teaching room or other noise sensitive
room opens into a busy atrium or through corridor, or in the case of large lecture theatres
and conference rooms with a waiting/ social area immediately outside their doors.
UWE Design Guide for Buildings
A p p e n d i x | A c o u s t i c S t a n d a r d s I s s u e 1 . 3 P a g e | 4
4. Impact and Air Borne Sound Insulation of Floors
Impact sound insulation deals with the transmission of noise to the rooms below from noise
sources in contact with the floor. Typical noise sources include footsteps, moving furniture
and machinery. Because the internal layout of a building may be changed many times
during its lifetime, a single set of standards is applied here for the airborne and impact
sound insulation of floors. In the case of airborne sound insulation, the quantity specified is,
as before, DnT(Tmfmax),w. For impact sound insulation the quantity specified is L'nT,w, as
defined in ISO 140 part 7 and ISO 717 part 2.
Minimum value of DnT(Tmfmax),w 55 dB
Maximum value of L'nT,w 55 dB
5. Noise from Outside
The maximum sound pressure levels due to external noise intrusion are listed in the table
below. These values include noise contributions from transport – including road and rail
traffic and civil aviation – from the weather, and from industrial and human activity both on
and off University’s premises. Building and civil engineering work are not included since they
are temporary in nature.
The values listed should be considered in conjunction with the specification for building
services noise which appears later. Control of external noise involves consideration of the
ambient noise levels at the specific site involved, the sound insulation properties of the
building shell (including the roof structure in the case of aircraft noise) and the impact on
sound insulation of any ventilation requirements such as the need for opening windows.
Type(s) of room Maximum value
of LAeq,30 minutes
Academic staff and admin offices 40dB
Cafeterias, coffee bars etc. 45dB
Class rooms, lecture rooms, seminar rooms and tutorial Rooms
Audio visual and video conference rooms Language laboratories
35dB
Drama studios, music practice rooms 30dB
Entrance halls, corridors, stairwells, atria and circulation spaces 45dB
Halls and rooms for music drama & other live performances 30dB
Large lecture theatres and flagship conference rooms 30dB
Lecture theatres up to 100 seats 35dB
Library circulation and media storage areas 40dB
Library study areas 35dB
UWE Design Guide for Buildings
A p p e n d i x | A c o u s t i c S t a n d a r d s I s s u e 1 . 3 P a g e | 5
Type(s) of room Maximum value
of LAeq,30 minutes
Recording studios 25dB
Rooms intended for clinical examination and treatment,
confidential interviews, psychotherapy, speech therapy etc.
35dB
Science laboratories, art & design studios, graphics workshops 35dB
Sports halls and gymnasia 40dB
Swimming pools 50dB
Workshops 40dB
Rain falling on lightweight roofs can cause disturbing noise inside the building, for example
in a sports hall used for examinations. This subject is still developing and there is as yet no
standard for measuring noise from rain within buildings. The variability of the weather is an
added difficulty when setting standards for this since very exceptional rainfalls will occur
occasionally. Building designers are expected to supply information about expected rain
noise levels in the light of up to date knowledge and experience on other similar projects.
6. Room Acoustics
Control of reverberation within buildings is important in creating good learning and working
conditions within the building. The quantity listed in the table below is the mid frequency
reverberation time, Tmf, as defined in BB93 (and based on measurements made according
to ISO 3382:2000. This is obtained by calculating the arithmetic average of the
reverberation times in the octave bands centred on 500 Hz, 1,000 Hz and 2,000 Hz. As well
as being important in its own right, the reverberation time enters into the calculation of
standardised sound insulation parameters.
Type(s) of room Max. value of Tmf
Academic staff and admin offices 1.0 s
Cafeterias, coffee bars etc. 1.0 s
Class rooms, lecture rooms, seminar rooms and tutorial Rooms
Audio visual and video conference rooms Language laboratories
0.8 s
Drama studios, music practice rooms 1.2 s
Entrance halls, corridors, stairwells, atria and circulation spaces 1.0 s
Halls and rooms for music drama and other live performances 1.2 s
Large lecture theatres and flagship conference rooms 1.0 s
Lecture theatres up to 100 seats 0.8 s
Library circulation and media storage areas 1.0 s
Library study areas 0.8 s
Recording studios 0.6 s
Rooms intended for clinical examination and treatment, confidential
interviews, psychotherapy and speech therapy
0.6 s
UWE Design Guide for Buildings
A p p e n d i x | A c o u s t i c S t a n d a r d s I s s u e 1 . 3 P a g e | 6
Type(s) of room Max. value of Tmf
Science laboratories, art and design studios, graphics workshops 0.8 s
Sports halls and gymnasia 1.5 s
Swimming pools 2.0 s
Workshops 1.0 s
The reverberation time at lower frequencies tends to be greater than at the midrange
frequencies dealt with in the above table. Reverberation times at 250 Hz and 125 Hz should
not exceed the above figures by more than 30%.
Reverberation times in awkward shaped spaces such as corridors and stair wells are difficult
to predict and measure. In these spaces, complying with the guidance in Approved
Document E should result in satisfactory reverberation conditions.
7. Noise from Building Services
Noise from building services should not exceed the noise rating (NR) values listed below.
This includes noise from the normal operation of heating, ventilation and air conditioning
plant. Higher levels may be permissible during purge ventilation. When planning ventilation
duct runs, they should as far as possible avoid crossing partition walls, and where this is
inevitable a crosstalk silencer must be incorporated so that the sound insulation
requirements listed earlier are met.
Type (s) of room Maximum
value of Tmf
Academic staff and admin offices NR 35
Cafeterias, coffee bars etc. NR 40
Class rooms, lecture rooms, seminar rooms and tutorial Rooms
Audio visual and video conference rooms Language laboratories
NR 30
Drama studios, music practice rooms NR 30
Entrance halls, corridors, stairwells, atria and circulation spaces NR 40
Halls and rooms for music drama and other live performances NR 30
Large lecture theatres and flagship conference rooms NR 30
Lecture theatres up to 100 seats NR 30
Library circulation and media storage areas NR 35
Library study areas and Recording studios NR 30
Rooms intended for clinical examination and treatment,
confidential interviews, psychotherapy, speech therapy etc.
NR 35
Science laboratories, art and design studios, graphics workshops NR 30
Sports halls and gymnasia NR 35
Swimming pools NR 50
Workshops NR 35
UWE Design Guide for Buildings
A p p e n d i x | A c o u s t i c S t a n d a r d s I s s u e 1 . 3 P a g e | 7
8. Acoustic Design of Residential Accommodation
The Building Regulations Approved Document E – Resistance to the passage of sound,
provides guidance and sets the requirements for the acoustic design of residential
accommodation