Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC V-GISC Project Office
An Introduction
by
Dieter Schröder (ECMWF)
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
V-GISC PO: What is V-GISC?
V-GISC – The West European Approach to a GISC
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
What is V-GISC and the Project Office?
V-GISC = SIMDAT Software
+ additional Software for integration of local systems
+ organisational concept (the so-called VO)
V-GISC Project Office: Develops concepts / guidelines to reach an operational V-GISC (no software development) System Integration Architecture Organisational Concept of V-GISC
V-GISC Project Office: A VO with 2 staff members (Météo France and ECMWF)
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
System Integration Approach
Collaboration DMZ
Catalogue Node
Data Repository
SIMDAT Components
Local Intranet
Local Databases
Reverse Proxy I
Reverse Proxy 2
GTS - Switch
Decoding SW
Customer DMZ
Push Mode Umbrella
Serving GISC Customers via PUSH
Mirror DB
User Access Management
Data Dissemination System
Serving Site Customers
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
What is a Virtual Organisation?
Definition: VO, inside view Co-operating independent organisations VO, outside view One comprehensive organisation
Layer Model:1. Organisation Layer : Cooperation of people and org. unit2. Product Layer: Meteorological Data, Data Policy3. Operational Layer: Basic IT Infrastructure (Grid Technology)4. Application Layer: Interoperability of the V-GISC components
PO deals with concepts of the Organisation Layer
Counterparts: Organisation Layer IT-LayersStructural VO Model IT-Architecture
Organisation Chart UML Class Diagram
Process Organisation Use Cases
Organisation Flow Chart UML Use Case Diagram
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
Structural Organisation for V-GISC
Central Support Office (at one partner site)
Central Reference Installation / Central Test System / Central SW Documentation / Bugzilla Repository / SW Asset Management / Office Duties
Implementation Team D
EUMETSAT
ECMWF
Implementation Team F
Implementation Team UK
Implementation BoardSyst. Engineers from all sitesQM-Supervision/Change Manag./Escalation/Implem. Governance
Steering Committee / Management BoardExecutive Representatives from all sitesSupervision/Escalation/Strategic Decisions
Project Manager(Ideally: Head of Central Support Office)
Leading the Project,/ Keep Things Going
VGISC Operational Team
System Operation/Monitoring/Backup/
Change Management.
GTS-Teamleader DGTS/VGISC-Op Team D
GTS-Teamleader UKGTS/VGISC-Op Team UK
GTS-Teamleader FGTS/VGISC-Op Team F
EUMETSATECMWF
Operational Board“GTS-Teamleaders”
QM-Supervision/Change Management/Escalation/Functional Operative Decisions
V-GISC “Op-Teamleader”“Round-robin” from GTS-TeamleadersOperational Decisions/Delegation of tasks SW-Dev. Team D
EUMETSAT
ECMWF
SW-Dev. Team F
SW-Dev. Team UKExternal Development
Team(Contractor)
DevelopsCentral
SW-Modules
Design&Architecture Team“Chief Designer”
Representative of Each Local TeamMajor Design & Arch. Decisions/Supervision
Local “User-Group” D
EUMETSAT
ECMWF
Local “User-Group” F
Loc. “User-Group” UK
Evaluation BoardRepresentatives from Local User-GroupsEvaluation of Design,
Architecture and Software
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
Management & Central Service
Central Support Office (at one partner site)
Central Reference Installation / Central Test System / Central SW Documentation / Bugzilla Repository / SW Asset Management / Office Duties
Steering Committee / Management BoardExecutive Representatives from all sitesSupervision/Escalation/Strategic Decisions
Project Manager(Ideally: Head of Central Support Office)
Leading the Project,/ Keep Things Going
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
Structural Organisation for OperationSteering Committee / Management Board
Executive Representatives from all sitesSupervision/Escalation/Strategic Decisions
Project Manager(Ideally: Head of Central Support Office)
Leading the Project,/ Keep Things Going
VGISC Operational Team
System Operation/Monitoring/Backup/
Change Management.
GTS-Teamleader DGTS/VGISC-Op Team D
GTS-Teamleader UKGTS/VGISC-Op Team UK
GTS-Teamleader FGTS/VGISC-Op Team F
EUMETSATECMWF
Operational Board“GTS-Teamleaders”
QM-Supervision/Change Management/Escalation/Functional Operative Decisions
V-GISC “Op-Teamleader”“Round-robin” from GTS-TeamleadersOperational Decisions/Delegation of tasks
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
Structural Organisation for SW Development in V-GISC
Central Support Office (at one partner site)
Central Reference Installation / Central Test System / Central SW Doc. / Bugzilla Repository / SW Asset Management / Office Duties
External Development
Team(Contractor)
DevelopsCentral
SW-Modules
SW-Dev. Team D
EUMETSAT
ECMWF
SW-Dev. Team F
SW-Dev. Team UK
Design & Architecture Team
“Chief Designer”Responsible for an homogeneous SW Design
Representative of Each Local TeamMajor Design & Arch. Decisions/Supervision
Evaluation Board
Representatives from Local User-Groups
Evaluation of Design, Architecture and Software / Change Management / Coordination of the Integration Tasks
EUMETSAT
ECMWF
Local “User-Group” D
Operational TeamData Management Team…
Local “User-Group” F
Operational TeamData Management Team…
Local “User-Group” UK
Operational TeamData Management Team…
Steering Committee / Management BoardExecutive Representatives from all sitesSupervision/Escalation/Strategic Decisions
Project Manager(Ideally: Head of Central Support Office)
Leading the Project,/ Keep Things Going
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
Structural Organisation: Implementation
Central Support Office (at one partner site)
Central Reference Installation / Central Test System / Central SW Documentation / Bugzilla Repository / SW Asset Management / Office Duties
Implementation Team D
EUMETSAT
ECMWF
Implementation Team F
Implementation Team UK
Implementation BoardSyst. Engineers from all sitesQM-Supervision/Change Manag./Escalation/Implem. Governance
Steering Committee / Management BoardExecutive Representatives from all sitesSupervision/Escalation/Strategic Decisions
Project Manager(Ideally: Head of Central Support Office)
Leading the Project,/ Keep Things Going
Project Office: ICG-WIS meeting at ECMWF 04 – 07/09/2007
V-
GISC
Process Organisation
Operational Process:
SW Development & Implementation
Day-to-day operation
Backup Process
Trouble Ticket Process
Missing Data Investigation
Change Management Process