Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
PERT/CPM
Variability in the Project Completion Date
• In doing Critical Path calculations, estimated activity times are not certain.
• What is the effect of these uncertainties on calculated project completion date?
Critical Path determines this date
Critical Path is a sequence of activities
Variation in Critical Path activities can cause variation in the completion date
Variation in non-Critical Path activities will not usually cause variation in the completion date
But… if variation along a non-Critical Path uses all of the slack time, this path may become Critical
But if… if variation along the Critical Path results in an earlier completion date, a non-Critical Path may become Critical.
3 Estimates for each Activity
Optimistic time ( a )
Everything progresses in an ideal manner
Most probable time ( m )
Most likely under normal conditions
Pessimistic time ( b )
Encounter breakdowns and/or delays
Expected time
4
6
t
a m bt
( a ) ( m ) ( b ) Expected
Most Time
Activity Optimistic Probable Pessimistic (Weeks)
A 4 5 12 6
B 1 1.5 5 2
C 2 3 4 3
D 3 4 11 5
E 2 3 4 3
F 1.5 2 2.5 2
G 1.5 3 4.5 3
H 2.5 3.5 7.5 4
I 1.5 2 2.5 2
J 1 2 3 2
Expected time
4
6
t
a m bt
Case Study (1) (2) (3) (4)
Earliest Latest Earliest Latest
Activity Start Start Finish Finish
A 0 0 6 6
B 0 7 2 9
C 6 10 9 13
D 6 7 11 12
E 6 6 9 9
F 9 13 11 15
G 11 12 14 15
H 9 9 13 13
I 13 13 15 15
J 15 15 17 17
C F
A D G
J
E
B H I
(1) (2) (3) (4) (2) - (1) (4) - (3)
Earliest Latest Earliest Latest SLACK SLACK
Activity Start Start Finish Finish (LS - ES) (LF - EF)
A 0 0 6 6 0 0
B 0 7 2 9 7 7
C 6 10 9 13 4 4
D 6 7 11 12 1 1
E 6 6 9 9 0 0
F 9 13 11 15 4 4
G 11 12 14 15 1 1
H 9 9 13 13 0 0
I 13 13 15 15 0 0
J 15 15 17 17 0 0
C F
A D G
J
E
B H I
Project Duration
T stands for the project duration
The activities along the Critical Path are A – E – H – I – J
E H IA Jt t t t tT
Expected
Time
Activity (Weeks)
A 6
B 2
C 3
D 5
E 3
F 2
G 3
H 4
I 2
J 2
6 3 4 2 2 17T
Variance in Project Activities 2
Variance of an activity time = 6
b a
( a ) ( m ) ( b ) Expected
Most Time Variance
Activity Optimistic Probable Pessimistic (Weeks) σ2
A 4 5 12 6 1.78
B 1 1.5 5 2 0.44
C 2 3 4 3 0.11
D 3 4 11 5 1.78
E 2 3 4 3 0.11
F 1.5 2 2.5 2 0.03
G 1.5 3 4.5 3 0.25
H 2.5 3.5 7.5 4 0.69
I 1.5 2 2.5 2 0.03
J 1 2 3 2 0.11
Variance in Project Duration 2 2 2 2 22
E H IA J
2 1.78 0.11 0.69 0.03 0.11 2.72E H IA J
Variance
Activity σ2
A 1.78
B 0.44
C 0.11
D 1.78
E 0.11
F 0.03
G 0.25
H 0.69
I 0.03
J 0.11
Standard Deviation in Project Duration
2.72 1.65
Final Assumption
The distribution of project completion time T is
Normally distributed.
The next step:
• Given the Expected Completion time (mean of the Normal)
• Given the Expected Standard Deviation in the Expected
Completion time (standard deviation of the Normal)
• Convert this Normal Curve to an equivalent Z-Normal Curve
17
1.65
xz
This “says” that any time you want to know the
“what if” probability that another completion
time (x) might actually occur, it represents a
random variable associated with this normal
distribution … and can be converted to an
equivalent z normal value…
What if… example
What is the probability that the project would be
completed in 20 weeks or less?
This would be an x = 20 from this normal distribution.
Convert the x to a z
17
1.65
171.82
1.65
xz
xz
This “says” that a completion time
of 20 is 1.82 standard deviations
above the mean (17).
Here is where we use the Table Handout
Z = 0 Z = 1.82 µ = 17 x = 20
Z table gives the area to the left, but only to the mean line. You need to add in the 0.50 to get the probability.
171.82
1.65
xz
xz
Steps
1. Develop list of activities
2. Draw the network
3. Estimate expected activity time and variance for each
activity
4. Use expected activity time estimates to determine
earliest start & finish and latest finish and start for each
activity
5. Use the project completion time as the finishing time
6. Compute the slack for each activity & identify the
Critical Path
7. Use the variability in the project completion date to
compute probabilities of meeting a specified date