Damien VUILLET Technical and sales meeting – April 2012
Technical and sales meeting
Vaux le Vicomte Castle
Damien VUILLET Technical and sales meeting – April 2012
Main specifications :-Renovation of the main dome with no support on it
-Castle opened to the visitors
-Access of the working site above the river
-Scaffold with canopy on each face
-Keder roof at the top
Damien VUILLET Technical and sales meeting – April 2012
3D view
Damien VUILLET Technical and sales meeting – April 2012
3D view with only steel deck
Damien VUILLET Technical and sales meeting – April 2012
The footbridge access
-Length of 19m
-Assembled on ground then put in by crane
-7T500 of ballast for the stability
Damien VUILLET Technical and sales meeting – April 2012
Principle of the scaffold
Creation of 4 scaffolds beams
Top view
Damien VUILLET Technical and sales meeting – April 2012
Front view Middle view
No support on the dome
Damien VUILLET Technical and sales meeting – April 2012
Rear view
Fixation on the wooden skeleton
Damien VUILLET Technical and sales meeting – April 2012
Section in the middle of the dome
Fixation on the wooden skeleton Last level of anchoring (3 plugs)
Damien VUILLET Technical and sales meeting – April 2012
Damien VUILLET Technical and sales meeting – April 2012
Damien VUILLET Technical and sales meeting – April 2012
Damien VUILLET Technical and sales meeting – April 2012
Damien VUILLET Technical and sales meeting – April 2012
-150t of LAYHER scaffold system
-760kg of wind force by plug
-1160kg on each wooden fixation
-Maximum load per standard : 3580kg