Environmental Monitoring Report
Quarterly Report (April - June 2014) July 2014
VIE: Greater Mekong Subregion Kunming–Hai
Phong Transport Corridor Noi Bai– Lao Cai
Highway Project
Prepared by Getinsa for the Vietnam Expressway Corporation, the Ministry of Transport, the Government of Viet Nam, and the Asian Development Bank
CURRENCY EQUIVALENTS (as of 1 July 2014)
Currency unit – dong (D)D1.00 = $0.0000469$1.00 = D21,328
NOTE
In this report, "$" refers to US dollars unless otherwise stated.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
Hanoi office : 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da District Vinh Phuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Dist, Vinh Phuc Province Madrid Spain head office: C/ Ramón de Aguinaga No 8, 28028 Madrid, Spain/ Web Page: www.getinsa.com
ENVIRONMENTAL, HEALTH AND SAFETY QUARTERLY REPORT
APRIL – JUNE 2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
1
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
INDEX
0. SUMMARY 3
1. INTRODUCTION. FRAMEWORK OF THE REPORT 6
1.1 FRAMEWORK OF THE REPORT ...................................................................................... 6
1.2 DESCRIPTION OF THE PROJECT. DIVISION IN PACKAGES ........................................ 6
2. CONSTRUCTION WORKS PROGRESS DURING THE PERIOD 10
2.1 PACKAGE A1 ................................................................................................................... 10
2.2 PACKAGE A2 ................................................................................................................... 10
2.3 PACKAGE A3 ................................................................................................................... 10
2.4 PACKAGE A4 ................................................................................................................... 11
2.5 PACKAGE A5 ................................................................................................................... 12
2.6 PACKAGE A6 ................................................................................................................... 13
2.7 PACKAGE A7 ................................................................................................................... 14
2.8 PACKAGE A8 ................................................................................................................... 14
3. CARRIED OUT TASKS DURING THE PERIOD 15
4. ENVIRONMENTAL MONITORING RESULTS. COMPLEMENTARY MEASURES
TO BE APPLIED 17
4.1 IMPACT ON AIR QUALITY .............................................................................................. 17
4.2 IMPACT ON WATER RESOURCES ................................................................................ 22
4.3 IMPACT ON SOILS QUALITY .......................................................................................... 26
4.4 NOISE AND VIBRATION LEVELS ................................................................................... 34
4.5 STREAMS AND RIVERSIDES MAINTENANCE .............................................................. 35
4.6 EROSION RISKS AND STABILITY IN SLOPES .............................................................. 43
4.7 HAZARDOUS SUBSTANCES MANAGEMENT ............................................................... 51
4.8 UNSUITABLE MATERIAL DISPOSALS AND BORROW PITS ....................................... 56
4.9 WASTE AND CLEANLINESS ON SITE ........................................................................... 63
4.10 BIODIVERSITY PRESERVATION ................................................................................... 66
4.11 WORKERS’ CAMPS CONDITIONS ................................................................................. 66
4.12 LABOUR SAFETY EQUIPMENT ..................................................................................... 69
4.13 TRAFFIC CONDITIONS AND SIGNPOSTING IN ROADS .............................................. 76
4.14 SIGNPOSTING IN DANGEROUS SURFACES ............................................................... 81
4.15 RESTORATION AND LANDSCAPING WORKS .............................................................. 84
4.16 ACCIDENTS DUE TO THE LACK OF SAFETY MEASURES. RESPONSIBLES ............ 85
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.17 CONTRACTORS’ ENVIRONMENTAL AND SAFETY SPECIALISTS MOBILIZATION .. 86
5. REFERENCE DOCUMENTS RELATIVE TO ENVIRONMENT, HEALTH AND
SAFETY ISSUES 88
5.1 PACKAGE A1 .................................................................................................................. 88
5.2 PACKAGE A2 .................................................................................................................. 88
5.3 PACKAGE A3 .................................................................................................................. 88
5.4 PACKAGE A4 .................................................................................................................. 89
5.5 PACKAGE A5 .................................................................................................................. 90
5.6 PACKAGE A6 .................................................................................................................. 91
5.7 PACKAGE A7 .................................................................................................................. 92
5.8 PACKAGE A8 .................................................................................................................. 93
6. GRIEVANCE INTAKES. PUBLIC CONSULTATION 95
7. ANNEX 1: COMPLAINTS OF LOCAL PEOPLE. SUMMARY TABLE 97
8. ANNEX 2: DATA OF ENVIRONMENTAL QUALITY PARAMETERS ANALYSIS 105
8.1 ANNEX 2.1: AIR QUALITY PARAMETERS .................................................................. 107
8.2 ANNEX 2.2: WATER QUALITY PARAMETERS ........................................................... 113
8.3 ANNEX 2.3: NOISE LEVELS ......................................................................................... 119
9. ANNEX 3: DOCUMENTATION RECEIVED FROM CONTRACTORS DURING THE
PERIOD 125
10. ANNEX 4: STATUS OF THE DOCUMENTATION RELATED TO BORROW PITS,
QUARRIES, SOIL DISPOSALS AND CONCRETE BATCHING PLANTS 129
11. ANNEX 5: SUMMARY TABLE OF IMPOSED PENALTIES 189
12. ANNEX 9: DOCUMENTATION RELATED TO COMPLAINTS AND
COMPENSATION ACTIVITIES DUE TO SOCIAL IMPACTS 195
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 1
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
ABBREVIATIONS
ADB Asian Development Bank
EIA Environmental Impact Assessment
EPMU Expressway Project Management Unit
EHSMR Environmental, Health and Safety Monthly Report
EHSQR Environmental, Health and Safety Quarterly Report
EHSWIR Environmental, Health and Safety Weekly Inspection Report
MONRE Ministry of Natural Resources and Environment
MOT Ministry of Transport
NB-LC Noi Bai - Lao Cai
NS National Specialist (environmental)
PPE Personal Protection Equipment
PSC Project Supervision Consultant
SMR Safety Monitoring Report
TOR Terms Of Reference
VEC Vietnam Expressway Corporation
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 2
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 3
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
0. SUMMARY
Environmental, Health and Safety Control and Protection: Environmental, Health and
Safety inspections continued being regularly carried out in weekly basis to monitor impacts due
to works and the implementation of mitigation measures. Specific monthly reports, which are
submitted to EPMU, and a quarterly report, which is submitted to the Client and to ADB, were
prepared for all packages concerning the supervision and control of the above mentioned
issues, as regular reporting procedure established by the PSC, increasing the duties specified
in our Contract in order to improve the monitoring and control processes. Also, short weekly
check lists are prepared after each inspection on site in order to maintain the information
constantly updated.
The general main problems and impacts on site along the entire Project in this second quarter
2014 have been very similar to the previous periods, and may be summarized as below:
Cleanliness, healthy conditions
Up to the date, six packages including packages A1, A2, A3, A6, A7 and A8 have been
completed and come into operation and exploitation. All the main construction works of
these packages have been finished and there are some miscellaneous works under
construction such as fencing, slope protection with grass/concrete. During the site
inspection, it’s noted that the construction sites are keep in cleanliness and tidiness
condition, in general; however, at some locations of package A4 and A5 we still
detected the dirtiness status due to lack of housekeeping activity of the Contractor such
as worker’s camps, CBPs or at fueling areas.
Noise & Air Pollution
The dustiness status was noted at some locations of package A4 during carrying out
construction works or transporting material. The Engineer has requested the Contractor
to mobilize the water trucks/wagons to water the surface of transportation roads and at
affected areas in order to minimize the spread of dust. The compliance of the
Contractor with this instruction was recorded during the site inspections.
Soil pollution and erosive processes. Hazardous substances management
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 4
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
The status of soil being eroded into cropland or polluted by oil was noted in package
A2, A3, A4 and A5. For the agricultural land which was impacted by erosion, almost all
the land owners have been compensated for damage assets, including restoration cost.
In package A2, the Contractor has prepared the money and made a schedule to
compensate impacted households from July 14th till August 04, 2014.
At the present, for the completed packages, the slope protection work with grass or
concrete is being promptly implemented in order to prevent erosion happening.
Package A1 has finished grassing work; package A2 has reached about 80%; package
A3 has reached 95%; sodding work of package A6 has been completed; package A7
achieved 91% and it’s already finished in package A8.
Bad management in fueling was noted during inspections package A4 and A5 such as
at Km 105+280 and Km 135+000. The Engineer has requested the Contractor to
comply with fuel control regulations; however, the improvement is inadequate.
Rivers protection, water quality
The serious problem was detected in package A1 from 2011 when the Contractor
carried out the construction work at sections Km 7+660 (Xuan Phuong Bridge) and Km
10+695 (Tan Loi Bridge). Because there was no riverside protection measure applied
during carrying out construction work so the riversides in these areas in downstream
have been seriously undermined and collapsed. Despite the strong penalty of the
Engineer (VND ten billion has been retained), restoration work is being carrying out
very slow at Km 7+660 and there is no action at Km 10+695.
At other locations, in general, the water quality is not seriously impacted. At Km
145+000, the cement laden water from CBP was leaked into small existing drainage;
however, the Contractor has solved this problem already.
Safety conditions
At the sections where is under construction, the lack of PPE status is usually detected.
It is partly unawareness of the worker because of lack the training of the Contractors
and also the Contractor didn’t provide them with enough PPE. The Engineer has many
times requested the Contractor to provide the workers with enough PPE at work as well
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 5
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
as implement training for newcomer to ensure the safety onsite; however, the
improvement is unremarkable.
Traffic Protection and Maintenance
It’s noted that almost all the underpass box culverts of package A7 and A7 have not
been completed while the highway has been exploited. This leaded the status of using
the highway for travel by rudimentary vehicles or motorbike, even livestock… of local
people. This is very dangerous. The Engineer has checked and requested the
Contractor to accelerate the progress of frontage roads construction work then
immediately finish the fencing work to ensure the traffic safety.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 6
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
1. INTRODUCTION. FRAMEWORK OF THE REPORT
1.1 FRAMEWORK OF THE REPORT
Within the framework of the Environmental Control Plans proposed by the contractors and the
duties of the Consultant (PSC) in this matter contained in the Consulting Services Contract, the
environmental team of national specialists (NS) in charge of inspecting the environmental
conditions of the works for the new highway, have done weekly inspections along the sites and
surroundings of all the Packages which nowadays are all with construction activities, checking
the environmental measures applied by the constructors and detecting any impacts that could
be generated by the building works during the period of reference of this quarterly report, that
means, April, May and June 2014.
The results were already included in the environmental, health and safety weekly inspection
reports (EHSWIR) and the corresponding monthly reports for each package (EHSMR). The
Weekly Reports have been included in the corresponding Monthly Reports. So, it’s considered
not necessary or useful to include again that information in this document.
As the environmental team, therefore under its responsibility, is also in charge of monitoring
the healthy and safety conditions in site, specialists in site offices also have made weekly
inspections in all packages. Their results have been being included in the mentioned monthly
reports, as nowadays all these issues have been joined in only one report. Therefore these
issues are also included in this quarterly report.
So, this document is defined as Environmental, Health and Safety Monitoring Quarterly Report
(hereinafter called EHSQR). It will be submitted to the Client, Vietnam Expressway Corporation
(VEC), through the Expressway Project Management Unit (EPMU) and following the Terms of
Reference (ToR) of the Consultant’s Contract, also to Asian Development Bank (ADB).
1.2 DESCRIPTION OF THE PROJECT. DIVISION IN PACKAGES
Noi Bai - Lao Cai (NB-LC) Highway is a part of Kunming - Hai Phong Transport Corridor, which
has been studied with a total length of 865 Km passing Yunnan province of China and Lao Cai,
Yen Bai, Phu Tho, Vinh Phuc, Ha Noi, Bac Ninh, Hai Duong, Quang Ninh and Hai Phong
provinces of Vietnam.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 7VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Vietnam Expressway Corporation, which is a state owner company, is the proposer of this
project. Its executing agency is the Ministry of Transport (MOT), and it’s being financed by
Asian Development Bank (ADB) and the Government of Vietnam.
According to original design, NB - LC Highway has a total length of about 262.4 km, passing
through 72 communes and 18 districts of provinces and cities as Ha Noi, Vinh Phuc, Phu Tho,
Yen Bai and Lao Cai.
The construction of project is divided into two phases, in which the first phase will construct
244 km with 4 lanes from Ha Noi to Yen Bai and 2 lanes from Yen Bai to Lao Cai. The second
phase will be the widen section of the former with 6 lanes from Ha Noi to Yen Bai and 4 lanes
from Yen Bai to Lao Cai (Chinese border, 262 km).
Construction of the whole project, first phase, is divided into 8 packages including A1, A2, A3,
A4, A5, A6, A7 and A8. All of them have already begun their construction activities. The length,
location and the status of works in each package at the end of the period are described in the
following paragraphs and tables.
- Package A1 is about 26.630 km of length with start point at station Km 0+070 and
finishes at station Km 26+700. Package A1 goes through the Soc Son district of
Hanoi City and Vinh Phuc province.
- Package A2 is about 22.120 km of length and goes through the Vinh Phuc province
and a little of Phu Tho province. Package A2 has start point at station Km 26+700
and finishes at station Km 48+820. It must cross over Lo River, with a long bridge.
- Package A3 is about 32.240 km of length with start point at station Km48+360 and
ending point at station Km 80+00. Package A3 goes through the Phu Tho province.
The most significant structure is the bridge to cross over Red River.
- Package A4 has start point at Km 80+000 in Cam Khe district, Phu Tho province
and ending point at Km109+750 in Tran Yen district, Yen Bai province. Its total
length is 29.750 km.
- Package A5 has start point at Km109+750 in Tran Yen district, Yen Bai province
and ending point at Km150+900 in Van Yen district, Yen Bai province. Its total
length is 41.150 km.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 8
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
- Package A6 lengthens from start point Km150+900 of Van Yen district, Yen Bai
province to Km190+420 in Van Ban district, Lao Cai province. Its total length is
39.520 km. Almost alignment goes through high mountains in Yen Bai and Lao Cai
province and crosses over natural streams by 18 bridges. This section also
includes 1 tunnel under range of mountain at Km186+500.
- Package A7 lengthens from start point Km190+420 in Van Ban district to Km
218+040 in Bao Thang district, Lao Cai province. Almost alignment also goes
through high mountains and 18 bridges are needed. Its total length is 27,620 m.
Khe Sang bridge with a length of 287m is the biggest one.
- Package A8 begins at station Km 218+040 in Bao Thang district and finishes at Km
244+155 in Bao Thang district, Lao Cai province. Its total length is 26,115 m. Suoi
Trat bridge with a length of 374.8 m is the biggest one.
Table 1.1: Current status of the works at the end of this quarter (%)
Activity A1 A2 A3 A4
Site clearing 100 100 100 93,41
Earthworks 100 99,19 100 84,56
Drainage 88,99 50,88 62,55 58,40
Structures (1) 100 100 100 91,96
Steel works 100 89,89 53,42 --
Asphalt 99,99 92,94 27,58 --
Grassing 97,28 64,67 94,81 6,32
Overall progress 99,72 93,22 83,54 58,53
Activity A5 A6 A7 A8
Site clearing 100 93,09 100 100
Earthworks 76,34 98,37 99,49 99,27
Drainage 65,91 53,95 90,84 81,60
Structures (1) 84,66 98,80 100 100
Steel works -- 25,53 62,43 100
Asphalt 1,19 22,76 100 90,91
Grassing Unknown 19,39 (2) 91,81 100 (2)
Tunnel Construction 20,2 82,76 -- --
Overall progress 56,63 83,62 97,66 96,13 (1) Concrete works
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 9
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
(2) Data provided by the Contractor
(data expressed in percentage of the total planned in the project, related to the contract quantities).
Currently, 2 packages, Package A1 and Package A8, were already opened to traffic, although
some works are still pending. Also, it’s foreseen that on April 1st 2014, Package A7 will be
open to public use. Finally, on April 6th, a forth stretch will be open, Package A2 and first part of
A3 until interchange IC8 to connect with national road.
The environmental monitoring program is carried out in compliance with regulations of Vietnam
Government and ADB safeguard policy in order to control environmental impacts and to
ensure that the environment in the surroundings of the project area is well preserved. The VEC
proponent should perform environmental protection measures stated in the EIA report as well
as requirements written in the approval decision made by MONRE. In accordance with article
23 of the Environmental Protection Law and article 15 of Decree 80/2006/ND-CP, MONRE will
organize, direct, and monitor the environmental protection measures performed by VEC as
stated in the EIA report approved.
At present, this environmental monitoring program is being undertaken by Environmental
specialists of Getinsa hired by Vietnam Expressway Corporation. EPMU, the Project Manager,
with the Consultant’s support, monitors the environmental protection measures applied by the
contractors during the development of their works, incompliance with the environmental control
and protection plans proposed by contractors and already approved by the PSC. Consultant
reports to EPMU-VEC as the main involved authority in the project.
In addition to that, during the monitoring process, the environmental specialists and contractors
will try to find out and mitigate unanticipated environmental impacts arising from the project
construction process.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 10
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
2. CONSTRUCTION WORKS PROGRESS DURING THE PERIOD
In this chapter, they are included all the works already done or in process during the period, in
each package and detailing the section where the works are developed.
2.1 PACKAGE A1
Package A1 has been finished.
2.2 PACKAGE A2
Package A2 has been finished.
2.3 PACKAGE A3
April May June
Sec 1: Km 48+360-Km 54+000 Asphalt Finished Finished
Sec 2: Km 54+000-Km 59+600 Asphalt Asphalt Finished
Sec 3: Km 59+600-Km 65+390 Base works;
Asphalt Base works;
Asphalt Finished
Sec 4: Km 65+390-Km 69+070 Base works;
Asphalt Base works;
Asphalt Finished
Sec 5: Km 69+070-Km 73+070 Base works;
Asphalt Base works;
Asphalt Finished
Sec 6: Km 73+070-Km 77+620 Base works;
Asphalt Base works;
Asphalt Finished
Sec 7: Km 77+620-Km 80+000 base works;
Asphalt base works;
Asphalt Finished
TL 325 B Bored piles Structure work Finished
Bai Bang Finished Finished Finished
Cam Phu Finished Finished Finished
Lung Thuong Finished Finished Finished
TL 320 B Finished Finished Finished
HCM IC Finished Finished Finished
XuanThanh Finished Finished Finished
TL 315B Finished Finished Finished
TL 323B Finished Finished Finished
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 11
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Phai Din Finished Finished Finished
TL 320C Finished Finished Finished
RW Flyover Casting pier
column;casting pier head
Structure work Finished
Red River Finished Finished Finished
IC8 Finished Finished Finished
IC10 Finished Finished Finished
CV QL2 Finished Finished Finished
Phong Chau Finished Finished Finished
New Bai Bang (pipe flyover) Finished Finished Finished
2.4 PACKAGE A4
April May June
Sec 1: Km 80+000 – Km 85+000 Earth work;
Subbase Earth work;
Subbase
Earth work; Subbase; base;
asphalt
Sec 2: Km 85+000 – Km 89+600 Earth work;
Subbase Subbase, base Subbase, base
Sec 3: Km 89+600 – Km 96+200 Earth work;
Subbase Earth work;
Subbase; base
Earth work; Subbase; base;
asphalt
Sec 4: Km 96+200 – Km 100+000Earth work;
Subbase Earth work;
Subbase; base Earth work;
Subbase; base
Sec 5: Km 100+000 – Km 105+000
Earth work; Subbase
Earth work; Subbase
Earth work; Subbase
Sec 6: Km 105+000 – Km 109+750
Earth work; Subbase
Earth work; Subbase
Subbase; base; asphalt
Ngoi Lao bridge - Km97+100 Pier Cap working Structure Structure
QL32C bypass bridge - Km107+533
Prepair for Launching PC slab
grider
Finished Finished
Ngoi Van bridge – Km 108+960 Pier Cap working Structure Finished
Dam Nang bridge – Km 108+287 Foundation,
stemwall working Structure Structure
TL321C bridge – Km 84+400 Foundation
working Structure Structure
Ngoi Gianh bridge – Km 88+760 Pier cap, stemwall Structure Structure
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 12
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
working
2.5 PACKAGE A5
April May June
Van Phu bridge – Km114+100.05 Structure work Structure work Structure work
Hop Minh My bridge – Km118+920.05
Structure work Structure work Structure work
Ngoi Lau bridge – Km120+615.85 Structure work Structure work Structure work
QL 37 bridge – Km121+433.05 Structure work Structure work Structure work
Ngoi Gua bridge – Km128+665.46 Structure work Structure work Structure work
Ngoi Rao bridge – Km130+916.30 Structure work Structure work Structure work
Ngoi Thu bridge – Km136+108.35 Structure work Structure work Structure work
Ngoi Thap bridge – Km138+447.15
Structure work Structure work Structure work
Ngoi Vien bridge – Km140+788.50
Structure work Structure work Structure work
Xuan Thu bridge – Km141+483.55
Structure work Structure work Structure work
Ngoi Thia bridge – Km145+434.05
Structure work Structure work Structure work
Ngoi Buc bridge – Km 150+704.65
Structure work Structure work Structure work
Sec 1: Km109+750 - Km115+800 Sub base & base work
Sub base & base work
Sub base & base work
Sec 2: Km115+800 - Km120+000 Filling work & sub-base work
Sub base & base work
Sub base & base work
Sec 3: Km120+000 - Km125+000 Filling work & sub-base work
Filling work & sub-base work
Filling work & sub-base work
Sec 4: Km125+000 - Km130+000 Filling work & sub-base work
Filling work & sub-base work
Filling work & sub-base work
Sec 5: Km130+000 - Km136+400 Filling work & sub-base work
Sub base & base work
Sub base & base work
Sec6: Km136+400 - Km142+000 Filling work & sub-base work
Filling work & sub-base work
Filling work & sub-base work
Sec 7: Km142+000 - Km148+000 Sub base & base work
Sub base & base work
Sub base & base work
Sec 8: Km148+000 - Km150+900 Sub base & base work
Sub base & base work
Sub base & base work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 13
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
2.6 PACKAGE A6
April May June
Khe Chuong Bridge - Km153+355 Structure work Structure work Finished
Ngoi That bridge – Km155+971.55
Structure work Structure work Finished
Ngoi Rom bridge- Km157+517.05 Structure work Structure work Finished
Ngoi Cong bridge – Km159+207.85
Structure work Structure work Finished
NgoiGiam I bridge – Km162+896.35
Structure work Structure work Finished
NgoiGiam II bridge – Km163+126.00
Structure work Structure work Finished
Ngoi Hut bridge – Km165+110.50 Structure work Structure work Finished
NgoiChac bridge – Km169+412.00
Structure work Structure work Finished
NgoiPha bridge – Km170+312.50 Structure work Structure work Finished
SuoiQuan bridge – Km173+434.00
Structure work Structure work Finished
NgoiNhuoc bridge – Km176+661.85
Structure work Structure work Finished
Lang Nhay bridge – Km182+164.00
Structure work Structure work Finished
Lang Lau bridge – Km184+057.95 Structure work Structure work Finished
Ngoi Don bridge – Km185+077.75 Structure work Structure work Finished
Dai Viet bridge – Km186+902.05 Structure work Structure work Finished
Van Xuan bridge – Km187+141.55
Structure work Structure work Finished
SuoiNau bridge – Km188+766.00 Structure work Structure work Finished
Lang Nheo flyover – Km173+929 Structure work Structure work Finished
Section 1: Km150+900 - Km156+000
Sub base & base work
Sub base & base work Finished
Section 2: Km156+000 - Km162+000
Sub base & base work
Sub base & base work Finished
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 14
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Section 3: Km162+000 - Km165+000
Sub base & base work
Sub base & base work Finished
Section 4: Km165+000 - Km168+000
Sub base & base work
Sub base & base work Finished
Section 5: Km168+000 - Km172+000
Sub base & base work
Sub base & base work Finished
Section 6: Km172+000 - Km176+713
Sub base & base work
Sub base & base work Finished
Section 7: Km176+713 - Km182+214
Sub base & base work
Sub base & base work Finished
Section 8: Km182+214 - Km186+200
Sub base & base work
Sub base & base work Finished
Section 9: Km186+730 - Km190+420
Sub base & base work
Sub base & base work Finished
Tunnel (Km 186+200 – Km 186+730)
Based and Electric system works
Based and Electric system
works Finished
2.7 PACKAGE A7
Package A7 has been finished.
2.8 PACKAGE A8
Package A8 has been finished.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 15
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
3. CARRIED OUT TASKS DURING THE PERIOD
During the period of reference for this quarterly report, the environmental tasks carried out by the specialists in their site offices and for each
package were the following (see table below).
In some cases, weather conditions difficulted so much the movement along the alignment, therefore may be any week it was not possible the
access to site. In other cases, the progress and distribution of the works in the packages, have conditioned especialists to carry out punctual
inspections instead of general ones.
Package General Inspection1 Punctual Inspection2 Weekly Report Submission
Letter/Notification Submission
Weekly, Monthly and Specific Meeting
Apr May June Apr May June Apr May June Apr May June Apr May June
A1 01 10, 30 25
A2 2, 14,
29 10, 30 27
A3 3; 10;
24
7, 9, 16, 20,
29
6, 10, 23
20 6 07; 14; 22; 28
12,19, 26
2 12; 22 13, 21,
30 4, 13 05; 12
4, 11, 18, 25
2, 9, 16, 23
A4 02; 09;
23 8, 16, 20, 29
6, 10, 18, 23
27 07; 14; 21; 28
5, 12, 19, 26
2, 9, 16, 23
08; 22, 30
5, 6, 15, 16
13, 20, 26
19; 26
A5 1, 9, 18 7, 20,
30 9, 18
4, 23, 25
13, 26 4, 13,
24 5, 12, 19, 26
10, 17, 24, 31
7, 14, 21, 28
7, 17, 23, 24,
28
14, 15, 16
10, 20, 24, 25
10, 24 8, 22 12, 26
A6 2, 7, 15 5, 19,
28 11, 20 4, 26 14, 23
5, 16, 23
5, 12, 19, 26
10, 17, 24, 31
7, 14, 21, 28
7,10, 20
14, 17 11, 24 10, 24 8, 22 12, 26
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 16
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Package General Inspection1 Punctual Inspection2 Weekly Report Submission
Letter/Notification Submission
Weekly, Monthly and Specific Meeting
Apr May June Apr May June Apr May June Apr May June Apr May June
A7 10, 24 5, 29 3, 24 14, 25 16 16, 30 12, 19,
26 10, 17,
31 7, 21,
28
2, 22, 25, 29,
30
15, 19, 20, 27
4, 16, 19
3, 10 25, 26
A8 10, 23 16, 29 16, 30 7, 14,
25 5, 20 3, 24
12, 19, 26
17, 31 7, 21,
28
2, 16, 25, 29,
30
5, 6, 14, 27
4, 26 3, 11 24
1: Inspections along the whole package or, at least, most of its main stations
2: Inspections in one or few locations, generally because of any specific matter or problem
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 17
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4. ENVIRONMENTAL MONITORING RESULTS. COMPLEMENTARY MEASURES TO
BE APPLIED
4.1 IMPACT ON AIR QUALITY
As Annex 2.1 there are included the results of the air quality monitoring carried out during the
period of this quarterly report.
4.1.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.1.2 Package A2
At the present, the Contractor has finished the main construction work of package A2. Miscellaneous works don’t affect air quality.
4.1.3 Package A3
May 09, 2014
Location: TL325B bridge
Site visit: Apr 03, 10, 24; May 7, 9, 16, 20, 29;
Jun 6, 10, 23
Date first observed: 03-Apr-2014
Problems description and cause: Soil is
disposed beside the local road and it was swept
onto surface of this road during the rains and
causes high spread or dust in hot windy days
Recommendation and Action taken by
Engineer: The contactor is requested to clean
the surface of the road and water frequently in
order to minimize spread of dust in this area;
erosion control measures must be applied, too.
Responsible Party: POSCO
Deadline: Immediately
Current status: The Contractor has watered
the surface of the road to minimize the spread
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 18
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Jun 23, 2014
of airborne dust. On June 28, 2014, package
A3 was opened to exploit
4.1.4 Package A4
Mar 6, 2014
Apr 9, 2014
Location: QL32C Bridge
Site visit: Apr 02, 09, 23
Date first observed: Dec 11, 2013
Problems description and cause: There is
much dust on the access road
Recommendation and Action taken by
Engineer: The Engineer has orally requested
the Contractor to clean the surface of the road
and to spray water frequently in order to
minimize the spread of dust
Responsible Party: KEANGNAM
Deadline: Immediately
Current status: The Contractor has not yet
cleaned the dirt on the road as well as sprayed
water to minimize the spread of dust in hot
windy day.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 19
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.1.5 Package A5
April 18, 2014
May 07, 2014
Location: Embankment sections
Site visit: Apr 09, 18; May 07, 20; June 04,13
Description: The contractor is spraying water on public roads and access roads in order to minimize dust during material transportation.
May 20, 2014
June 13, 2014
4.1.6 Package A6
Location: whole package
Site visit: Apr 07, 15; May 05, 19
Current Status: The contractor is spraying
water on public roads and access roads in
order to minimize spread of airborne dust
during carrying out construction work. The
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 20
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 7, 2014 (Km 175)
May 19, 2014 (Km 182)
package A6 has been opened to exploit in June
14, 2014
June 16, 2014 (Km18+720)
4.1.7 Package A7
April 25, 2014
Location: Package A7
Site visit: Apr 25; May 05; Jun 23
Current status: At the present, the Contractor has finished the main construction work of package A7. Miscellaneous works don’t affect air quality.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 21
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 05, 2104
June 23, 2014
4.1.8 Package A8
April 20, 2014 (Km 228+000)
April 20, 2014 (Km 241+100)
Location: Package A8
Site visit: Apr 10, 20; May 29; June 04
Current Status: At the present, the main
construction work of package A8 has been
finished, the miscellaneous works don’t pollute
air quality
May 29, 2014 (Km231+800)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 22
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.2 IMPACT ON WATER RESOURCES
As Annex 2.2 there are included the results of the water quality monitoring carried out during
the period of this quarterly report.
4.2.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.2.2 Package A2
Up to now, the main construction work of package A2 has been finished and the miscellaneous
works are not considered as an impact on water quality.
4.2.3 Package A3
Package A3 has come into operation on June 28, 2014. By observation during site inspections
this period, we didn’t detect any serious problem that affects water quality.
4.2.4 Package A4
Apr 23, 2014
Location: Ngoi Van Bridge
Site visit: Apr 02, 09, 23
May 8, 16, 29
Date first observed: Oct 11, 2012
Problems description and cause: The
Contractor dumped soil into riverbed for the
construction works. But the restoration works
has not been implemented. This is affecting the
water quality in this area
Recommendation and Action taken by
Engineer: The Engineer has orally requested
the Contractor to restore the riverbank and
riverbed by removing accumulated soil from
construction works and stabilize the slope of
river bank. Refer to the letter GET-KEA-A4-153
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 23
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 29, 2014
Responsible Party: Keangnam
Deadline: Immediate
Current status: The Contractor has removed
all soil in the riverbed and riverbank to the
approved disposal areas as well as
implemented the restoration works.
May 8, 2014
May 29, 2014
Location: Km 92+600
Site visit: May 8, 20, 29; June 6, 10, 23
Date first observed: 08-May-2014
Problems description and cause:
Construction of frontage road without slope
protection measures resulted leading soil into
the lake due to erosion during the rain
Recommendation and Action taken by
Engineer: The Contractor is requested to
remove the soil that has encroached into the
lake. Implement measures to avoid erosion of
the frontage road into the lake. Refer to the
letter GET-KEA-A4-153
Responsible Party: Keangnam Contractor
Deadline: 15-Jun-2014
Current status: The Contractor has not yet
implemented the requirement of the Engineer
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 24
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 23, 2014
4.2.5 Package A5
May 7, 2014 (CBP km 145)
May 30, 2014 (CBP km 145)
Location: Concrete Batching Plant (km 145)
Site visit: May 07, 20
Date first observed: 07-May-2014
Problems description and cause: The capacity of the settling ponds is not sufficient to handle wastewater from equipment and truck washing. The entire CBP area is muddy due to overflows from the washing area and due to lack of proper drainage for surface run-off. Cement slurry has reached a nearby agricultural lot. This situation may is cause to impact water quality.
Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location, at the same time, the Engineer also provided the instruction for this issues.
Responsible Party: Keangnam Contractor
Deadline: Immediate
Current status: The Contractor still have not provided additional settling ponds to properly treat wastewater from equipment and truck washings; however, the Contractor already cleaned up and rearranged this CBP and surrounding area in order to avoid muddy condition as well as prevent impact on surrounding environmental.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 25
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 30, 2014 (CBP km 145)
4.2.6 Package A6
May 5, 2014
May 28, 2014
Location: Asphalt Concrete Batching Plant
(Km 171)
Site visit: May 5, 28; June 11
Date first observed: 05-May-2014
Problems description and cause: Downpour
caused overlowing of settling pond and surface
runoff leaded the mud containing cement to
adjacent area where is close to irrigation canal
and agricultural land
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to remove all the overflowed mud,
rearrange this area, dredge settling pond and
construct a berm which is made of soil to
prevent this situation happening in the future.
Refer to letter GET-DOO-A6-153
Responsible Party: Doosan Contractor
Deadline: 30-May-2014
Current status: Mitigation measure has been
applied
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 26
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 11, 2014
4.2.7 Package A7
At the present, the main construction work of package A7 has been finished, the
miscellaneous works are not considers as the impact resources affecting water quality.
4.2.8 Package A8
At present, the main construction work of package A8 has been finished; there are only some
miscellaneous works such as fence installation and grassing, these activities don’t impact on
water quality.
4.3 IMPACT ON SOILS QUALITY
4.3.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.3.2 Package A2
Location: Km 42+400 ~ Km 44+900
Site visit: Apr 2, 14, 29; May 30; Jun 27
Date first observed: 05-June-2013
Problems description and cause:
Uncontrolled erosion leaded sediment into
croplands and damaged the crop of local
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 27
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 02, 2014
May 30, 2014
June 27, 2014
people; restoration work is being carried out
slowly
Recommendation and Action taken by
Engineer: Apply erosion and sediment control
measures; contact local people and authority to
negotiate to compensate for the damaged
assets and restore affected areas. Refer to
letter GET1/POS/A2/2090, 2101, 2176, 2315;
GET/MISC/361, 363; The Engineer also warned
the Project Manager of the Contractor of his
negative attitude in cooperation to deal with
problem; refer to letter GET1/POS/A2/2266;
2362, 2450
Responsible Party: POSCO
Deadline: 30-Jun-2014
Current status: The Contractor already contact
local people (Song Lo DPC and its direction
under CPCs) to deal with this matter. Up to
now, there area some unclear problems such
as flooding period, damaged value… that need
to be verified for compensation and the
Contractor is cooperating with local authorities
in order to ascertain this problem.
The compensation is going to be implemented
from July 16 till August 04, 2014. For
unrestorable sections, the EPMU will acquire
that land and hands over to local authorities for
management or change the use purpose of
land.
4.3.3 Package A3
Location: Km 57+300; Km 56+400 – Km
56+800
Site visit: May 07, 09, 16, 20
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 28
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 7, 2014 (Km 57+300)
May 9, 2014 (Km 57+300)
May 7, 2014 (Km 56+400 ~ Km 56+800)
Date first observed:
Problems description and cause: Soil slides
on agricultural lands and irrigation canals. This
can reduce the crop production and quality of
agriculture land
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to restore the ariculture areas
affected and apply the erosion control
measures to prevent this problem happening in
the future. Refer to the letter Ref GET-POS-A3-
264, GET2-POS-A3-2360
Responsible Party: Posco Contractor
Deadline: Immediate
Current status: The compensation has been
paid to some of the affected persons whose
farmlands have been damaged due to erosion
and landslides from road embankment but the
others refuses to receive payment. The
Contractor continues solving this problem.
However, the Contractor still does not
implement the suitable measures (e.g., slope
stabilization, installation of adequate drainage,
etc) to ensure that such impacts will be avoided
in the near future.
4.3.4 Package A4
Location: Km 82+000
Site visit: May 8, 20, 29
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 29
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 20, 2014
May 08, 2014
Date first observed: 26-Apr-2013
Problems description and cause: Agricultural
lands have been damaged due to erosion and
landslides from road embankments.
Recommendation and Action taken by
Engineer: Closely coordinate with affected
households and local authorities to expedite
compensation for damages caused by
construction activities. Dig adequately sized
side drainage/ditch at erosion prone areas to
direct surface run-off away from agricultural
land. Implement slope stabilization measures
to minimize erosion. Provide drainage/ditch
reinforcements (e.g., sandbags and/or other
appropriate measures) to avoid spill-over of
surface run-off onto surrounding agricultural
lands. Refer to the letters GET2-KEA-A4-1283,
GET2-KEA-A4-1293, GET2-KEA-A4-1378;
GET2-KEA-A4-1460, GET2-KEA-A4-1509.
Responsible Party: Keangnam Contractor
Deadline: 05-Apr-2014
Current status: The Engineer has not yet
received any document to confirm that whether
the compensation has been paid to the affected
households. The Contractor also has not
restored these areas or implement
countermeasures (e.g., slope stabilization,
installation of adequate drainage, etc) to
prevent this issue keeping happening.
Location: Km 81+700
Site visit: May 8, 20, 29
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 30
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 8, 2014
May 8, 2014
June 23, 2014
Date first observed:
Problems description and cause: Road
embankment erosion buried portions of rice
fields owned by 4 households. The incident
occurred in December 2012 and compensation
for the affected crops has been paid by the
contractor in 2013. The contractor also
disclosed that the affected HH preferred to
remove the soil by themselves with
corresponding payments from the contractor.
To date, although the households have
received payment, they have not removed the
soil.
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to implement the suitable measures
(e.g., side ditch to direct the discharge of the
culvert away from the rice fields, etc.). Refer to
the letter GET-KEA-A4-153
Responsible Party: Keangnam
Deadline: 15-Jun-2014
Current status: The Contractor has not
implemented the Consultant‘s instructions
4.3.5 Package A5
Location: Ngoi Thu bridge’s construction site
Site visit: Apr 09, 25
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 31
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 9, 2014 (Ngoi Thu bridge)
April 25, 2014 (Ngoi Thu bridge)
Date first observed: 09-Apr-2014
Problems description and cause: Fuel control is not well performed; fuel tanks were put directly on the ground. This situation caused the leak of oil and soil pollution.
Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location (Refer to the letter No. GET3-KEANGNAM-14-A5-117 dated on 17th April, 2014 regarding to require the Contractor to improve fuel control onsite).
Responsible Party: Keangnam Contractor
Deadline: 24-Apr-2014
Current status: Through site checking and supervision, the Engineer dectects that Sub-contractor has already removed all fuel tanks at this location, besides sub-contractor also cleaned this location.
May 7, 2014 (ACBP Km136)
Location: Asphalt Batching Plant (Km 136)
Site visit: May 07, 30
Date first observed: 07-May-2014
Problems description and cause: Leaks and spills from fuel oil tanks and bitumen burning equipment were noted. Puddles of contaminated water were also noted in the said areas. This situation may is cause to impact soils quality. Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location (Referring to the letter No. GET-KEA-A5-145 dated on 15th May, 2014)
Responsible Party: Keangnam Contractor
Deadline: Immediate
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 32
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 30, 2014 (CBP Km136)
Current status: The Contractor cleaned up this location, but he did not apply suitable measures in order to prevent fuel leaking, therefore the Engineer still found that fuel leaks on the ground.
May 07, 2014
May 30, 2014
Location: Km 148+600
Site visit: May 07, 30; Jun 04
Date first observed: 07-May-2014
Problems description and cause: Although a fuel storage area with roof and concrete flooring is provided at the site, toppled drums were left outside and are exposed to the elements. Leaks and spills are also evident. This situation may is cause to impact soils quality.
Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location (Referring to the letter No. GET-KEA-A5-145 dated on 15th May, 2014)
Responsible Party: Keangnam Contractor
Deadline: Immediate
Current status: Mitigation measures have not been implemented
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 33
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 04, 2014
4.3.6 Package A6
May 05, 2014
May 28, 2014
Location: Asphalt Concrete Batching Plant
(Km 171)
Site visit: May 5, 28
Date first observed: 05-May-2014
Problems description and cause: Downpour
caused overlowing of settling pond and surface
runoff leaded the mud containing cement to
adjacent area where is close to irrigation canal
and agricultural land
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to remove all the overflowed mud,
rearrange this area, dredge settling pond and
construct a berm which is made of soil to
prevent this situation happening in the future.
Refer to letter GET-DOO-A6-153
Responsible Party: Doosan Contractor
Deadline: 30-May-2014
Current status: Mitigation measure has been
implemented
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 34
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 11, 2014
June 11, 2014
4.3.7 Package A7
The main construction work of package A7 has been finished at the end of March, 2014; the
Contractor is now carrying out the miscellaneous works such as installing fence, signboard and
sodding. These works don’t impact on soil quality at surrounding areas.
4.3.8 Package A8
Package A8 has come to operation in March 02, 2014; it means the main construction work
has been finished and during the site inspections in this quarter we didn’t detect the problem
that is due to construction work to impact on surrounding soil quality.
4.4 NOISE AND VIBRATION LEVELS
As Annex 2.3 there are included the results of the noise and vibration levels monitored during
the period of this quarterly report.
4.4.1 Package A1
All the construction work of package A1 has been finished by January 2014.
4.4.2 Package A2
The main construction work of package A2 has been finished, and there is no noise or
vibration impacting on the sensitive areas. Up to now, the Contractor is still carrying out the
compensation the local people for the damages which were due to vibration during
implementing construction work.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 35
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.4.3 Package A3
The main works of remaining section of package A3 in this peiod are asphalt concrete
pavement; road marking, fencing and landscaping. These works didn’t cause the vibration that
affects the sensitive areas and the noise didn’t excess the standard.
4.4.4 Package A4
By monitoring onsite, it’s noted that the noise arising from construction work didn’t exceed the
standard.
4.4.5 Package A5
By monitoring onsite, it’s noted that the noise arising from construction work didn’t exceed the
standard.
4.4.6 Package A6
It’s noted that almost all the main construction works of package A6 has been finished and the
Contractor is completing the road marking and landscaping works; these works don’t cause
serious noise and vibration that affect sensitive areas.
4.4.7 Package A7
The main construction work of package A7 has been finished, and there is no noise or
vibration impacting on the sensitive areas.
4.4.8 Package A8
Four months ago, the package A8 has come to operation; therefore, there is no noise or
vibration which is due to construction work impacting on the sensitive areas.
4.5 STREAMS AND RIVERSIDES MAINTENANCE
4.5.1 Package A1
Location: Tan Loi Bridge, Xuan Phuong Bridge
Site visit: Apr 01; May 16, 30; June 25
Date first observed:
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 36
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Apr 01, 2014 (Xuan Phuong Bridge)
May 30, 2014 (Xuan Phuong Bridge)
Jun 25, 2014 (Xuan Phuong Bridge)
Problems description and cause: landslide
happened on riversides because the Contractor
didn’t comply with Engineer’s instructions on
riverside protection during carrying out
construction work in these areas; besides, the
water flows in these sections are being blocked
due to temporary stream crossing. Up to now,
the main construction works in these areas
already finished; however, the Contractor has
not began the restoration work yet
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to submit the detail restoration
schedule as well as the working method
statement basing on the approved restoration
plans. Refer to letter GET1/POS/A1/2269
Due to the Contractor doesn’t comply with
requirements of the Engineer in order to restore
affected areas so the Engineer is going to retain
VND 10,000,000,000 (VND ten billion) until he
finishes restoration work. Refer to letter
GET1/POS/A1/2306, 2314, 2317
Responsible Party: POSCO
Deadline: 30-Jul-2014
Current status: The Contractor begun the
restoration work at Xuan Phuong Bridge (Km
7+660); however, the construction work
progress is slow. At Tan Loi Bridge (Km
10+695), it’s noted that there is no action of the
Contractor to restore affected area.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 37
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Apr 01, 2014 (Tan Loi Bridge)
May 30, 2014 (Tan Loi Bridge)
Jun 25, 2014 (Tan Loi Bridge)
4.5.2 Package A2
The main construction work of package A2 has been finished and the miscellaneous works do
not affect streams and riversides.
4.5.3 Package A3
By observation during this quarter, it’s noted that there is not any serious problems regarding
to stream and riverside maintenance detected.
4.5.4 Package A4
Location: Ngoi Van Bridge
Site visit: Apr 02, 09, 23; May 8, 16, 29
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 38
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Nov 20, 2013
Apr 23, 2014
May 29, 2014
Date first observed: 11-Oct-2012
Problems description and cause: The
Contractor dumped soil into riverbed for the
construction works. But the restoration works
has not been implemented. This problem is
blocking water flow in this area
Recommendation and Action taken by
Engineer: The Engineer has orally requested
the Contractor to restore the riverbank and
riverbed by removing accumulated soil from
construction works and stabilize the slope of
river bank.
Responsible Party: Keangnam
Deadline: Immediate
Current status: Mitigation measures have
been implemented
4.5.5 Package A5
Location: Ngoi Thia Bridge
Site visit: May 07, 30; June 11
Date first observed: 07-May-2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 39
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 7, 2014
May 30, 2014
Problems description and cause: Although
the temporary access road across the river is
no longer needed for the remaining bridge
works, the contractor has yet to remove the
said obstruction causing high velocity flow
downstream. This condition will likely cause
scouring/erosion of the river embankment
Recommendation and Action taken by
Engineer: The Engineer requested the
Contractor to undertake complete removal of
the temporary access road and restoration of
affected riverbed (Referring to the letter No.
GET-KEA-A5-145 dated on 15th May, 2014)
Responsible Party: Keangnam Contractor
Deadline: 30-Jun-2014
Current status: The water flow is being
blocked due to the Contractor has not carried
out the restoration work
June 11, 2014
4.5.6 Package A6
Location: Suoi Quan bridge’s construction site
Site visit: May 05; Jun 05
Date first observed: 05-May-2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 40
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 5, 2014 (Suoi Quan bridge)
June 5, 2014 (Suoi Quan bridge)
Problems description and cause: Spoils have
completely buried a short section of the stream
Recommendation and Action taken by
Engineer: The Engineer requested the
Contractor to clean the stream of spoils and
implements slope stabilization measures to
ensure that the stream will not be blocked even
during heavy downpours
Responsible Party: Doosan Contractor
Deadline: Immediate
Current status: The Contractor cleaned up
stream and applied slope stabilization
measures
May 5, 2014 (Dai Viet bridge)
Location: Dai Viet bridge’s construction site
Site visit: May 05, 28
Date first observed: 05-May-2014
Problems description and cause: The flow of a small stream (which discharges to Red River) at the Dai Viet Bridge site is totally blocked since the pipe culvert under the local road has not been reinstalled yet
Recommendation and Action taken by Engineer: The Engineer requested the Contractor to implement the tasks as follows:
1. Install adequately sized culvert(s) to restore stream flow.
2. Undertake regular clearing of the channel
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 41
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 28, 2014 (Dai Viet bridge)
section affected by construction;
(Ref. GET-DOO-A6-153 dated to on 14th May, 2014)
Responsible Party: Doosan Contractor
Deadline: 30-May-2014
Current status: The Contractor still have not yet installed culvert at this location.
The Contractor is combining with local authorities and Yen Bai province People’s committee in order to install culverts at province road No.166 this month.
May 5, 2014 (Ngoi Rom bridge)
May 28, 2014 (Ngoi Rom bridge)
Location: Ngoi Rom bridge’s construction site
Site visit: May 05, 28
Date first observed: 05-May-2014
Problems description and cause: Although the temporary access roads across the rivers/streams are no longer needed for the remaining bridge works, the contractor has yet to remove the said obstruction
Recommendation and Action taken by Engineer: The Engineer requested the Contractor to undertake complete removal of the temporary access road, restoration of riverbed and river width, as well as stabilization of affected slopes.
(Ref. GET-DOO-A6-153 dated to on 14th May, 2014)
Responsible Party: Doosan Contractor
Deadline: 30-Jun-2014
Current status: The Contractor has alerady removed temporary access road at this bridge to ensure the water flow
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 42
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.5.7 Package A7
April 14, 2014
May 29, 2014
Location: Km 209+329
Site visit: Apr 14; May 29; June 23
Date first observed: 25-Feb-2014
Problems description and cause: The water
flow is being blocked by disposal material
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to restore the natural flow of stream
and apply the slope protection measure to
avoid this problem happening in the future by
letter No: Ref. Get4-GRBCC-1045
Deadline: 15-Mar-2014 (immediate)
Current status: Mitigation measures have not
been implemented
June 23, 2014
4.5.8 Package A8
Location: Son Ha Bridge Km224+369
Site visit: Apr 10, 14, 23; May 16; Jun 04
Date first observed: 22-May-2013
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 43
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 14, 2014
May 16, 2014
Problems description and cause: The canal
was blocked due to soil and stone falling during
carrying out construction works
Recommendation and Action taken by
Engineer: The contractor has been requested
to remove all soil and stone from canal to
ensure the water flow. Refer to letter Get4-
Vinaconex-912
Deadline: 30-Mar-2014
Current status: The Contractor is carrying out
the restoration work but it’s very slow
June 04, 2014
4.6 EROSION RISKS AND STABILITY IN SLOPES
4.6.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.6.2 Package A2
At the present, the main construction work of package A2 has been finished and the
Contractor is preparing the slope at section from Km 39+580 to Km 47+660 to complete the
grassing work.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 44
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.6.3 Package A3
May 7, 2014 (Km 57+300)
May 9, 2014 (Km 57+300)
May 7, 2014 (Km 56+400 ~ Km 56+800)
Location: Km 57+300; Km 56+400 – Km
56+800
Site visit: May 07, 09, 16, 20
Date first observed:
Problems description and cause: Erosion
lead the soil from embankment and slope into
cropland because of unprotected slopes during
the rains
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to restore the ariculture areas
affected and apply the erosion control
measures to prevent this problem happening in
the future. Refer to the letter Ref GET-POS-A3-
264, GET2-POS-A3-2360
Responsible Party: Posco Contractor
Deadline: Immediate
Current status: The compensation has been
paid to some of the affected persons whose
farmlands have been damaged due to erosion
and landslides from road embankment but the
others refuses to receive payment. The
Contractor continues solving this problem.
However, the Contractor still does not
implement the suitable measures (e.g., slope
stabilization, installation of adequate drainage,
etc) to ensure that such impacts will be avoided
in the near future.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 45
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.6.4 Package A4
Apr 20, 2014
May 08, 2014
Location: Km 82+000
Site visit: Apr 02, 09, 23
Date first observed: 26-Apr-2013
May 8, 20, 29
Problems description and cause: Agricultural
lands have been damaged due to erosion and
landslides from road embankments.
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to contact local people and authority
to verify the damaged status, restore the
affected areas and compensate for the
damaged assets. The erosion control measures
are also required to apply in order to prevent
this matter happening in the future. Refer to the
letters GET2-KEA-A4-1283, GET2-KEA-A4-
1293, GET2-KEA-A4-1378; GET2-KEA-A4-
1460, GET2-KEA-A4-1509.
Responsible Party: Keangnam Contractor
Deadline: 05-Apr-2014
Current status: The Contractor has not
reported to the Engineer the compensation
status; the restoration work and
countermeasures have not been implemented
Location: Km 81+700
Site visit: May 8, 20, 29; Jun 6, 10, 23
Date first observed:
Problems description and cause: Road
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 46
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 08, 2014
May 08, 2014
June 23, 2014
embankment erosion buried portions of rice
fields owned by 4 households. The incident
occurred in December 2012 and compensation
for the affected crops has been paid by the
contractor in 2013. The contractor also
disclosed that the affected HH preferred to
remove the soil by themselves with
corresponding payments from the contractor.
To date, although the households have
received payment, they have not removed the
soil.
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to implement the suitable
countermeasures (e.g., side ditch to direct the
discharge of the culvert away from the rice
fields, etc.) to prevent this matter keeping
happening. Refer to the letter GET-KEA-A4-153
Responsible Party: Keangnam
Deadline: 15-Jun-2014
Current status: The Contractor has not
implement the requirement of the Engineer
Location: Km 92+600
Site visit: May 8, 20, 29; Jun 6, 10, 18, 23
Date first observed: 08-May-2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 47
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 8, 2014
May 29, 2014
Problems description and cause:
Construction of frontage road without slope
protection measures resulted leading soil into
the lake due to erosion during the rain
Recommendation and Action taken by
Engineer: The Contractor is requested to
remove the soil that has encroached into the
lake. Implement measures to avoid erosion of
the frontage road into the lake. Refer to the
letter GET-KEA-A4-153
Responsible Party: Keangnam Contractor
Deadline: 15-Jun-2014
Current status: The Contractor has not yet
implemented the requirement of the Engineer
June 23, 2014
4.6.5 Package A5
Location: Package A5
Site visit: Apr 01, 10, 23
May 07, 20, 26, 30
Description: The Contractor is planting grass at cutting slopes and embankment slopes. Besides, the Contractor also built stone wall at cutting slope (material of cutting slope is not good condition), construct top ditch in order to
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 48
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 1, 2014 (Km119)
April 18, 2014 (Km128)
May 26, 2014 (Km124)
minimize erosion risks and protect slope.
May 26, 2014 (Km137)
June 18, 2014 (Km143)
4.6.6 Package A6
Location: whole package
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 49
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 2, 2014 (Km171)
April 7, 2014 (Km179)
May 14, 2014 (Km178)
Site visit: Apr 2, 7, 26
May 14, 23, 28
Description: The Contractor is planting grass
at cutting slopes and embankment slopes.
Besides, the Contractor also is spraying
concrete at cutting slope (material of cutting
slope is not good condition), construct top ditch
in order to minimize erosion risks and protect
slope. Package A6 has been opened for traffic
in June 14, 2014
June 20, 2014 (Km154)
June 16, 2014 (Km174)
4.6.7 Package A7
Location: Excavation slope Km 215+200
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 50
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 14, 2014
May 29, 2014
Site visit: Apr 14; May 29, June 16
Date first observed: 21-May-2013
Problems description and cause: High risk of
erosion and landslide during rainy season due
to unprotected slope
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to apply the slope protection
measure as well as install the warning
signboard to ensure the traffic safety.
Deadline: Immediate
Current status: The Contractor is cutting the
slope to carry out the slope protection measure
June 16, 2013
4.6.8 Package A8
Location: Package A8
Site visit: Apr 10, 14, 23; May 29; June 4, 12,
16, 30
Date first observed:
Problems description and cause: High risk of
landslide happening on slopes due to the
protection measures has not been implemented
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 51
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 14, 2014
May 29, 2014
Recommendation and Action taken by
Engineer: The Engineer has requested the
contractor to settling the safety fence and
signpost around the landside and erosion
areas, after that apply the erosion control
measure to protect the slope
Responsible Party: Vinaconex
Deadline: As soon as possible
Current status: Mitigation measure is being
applied
June 30, 2014 (Km223+000)
4.7 HAZARDOUS SUBSTANCES MANAGEMENT
4.7.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.7.2 Package A2
During the site inspection in this period, we did not detect any serious problem regarding to
hazardous substance management.
4.7.3 Package A3
By observation during this period, there is no serious problem regarding to hazardous
substance management detected in package A3.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 52
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.7.4 Package A4
April 02, 2014
May 29, 2014
June 23, 2014
Location: TL321C bridge
Site visit: Apr 02, 09, 23; May 29, Jun 23
Date first observed: 02-Apr- 2014
Problems description and cause: Haphazard
placement of waste oil and oil drums was
observed at this location. This can cause the
spills/leaks of oil on the ground and affect the
soil quality.
Recommendation and Action taken by
Engineer: The Engineer has orally requested
the Contractor to immediately improve the fuel
storage with roof, concrete floor and bund
surrounding to minimize the risk of spills/leaks
of oil.
Responsible Party: Keangnam
Deadline: 07-Apr-2014 (immediate)
Current status: The Contractor has rearranged
the oil storage; however, he has not complied
with instructions of the Engineer in order to
construct an oil storage that meets
requirements above
Location: Km 105+280
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 53
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 8, 2014
May 29, 2014
June 18, 2014
Site visit: May 8, 20, 29; June 6, 10, 18, 23
Date first observed: 08-May-2014
Problems description and cause: Haphazard
placement of waste oil and oil drums was
observed at this location. This can cause the
spills/leaks of oil on the ground and affect to the
soil quality.
Recommendation and Action taken by
Engineer: The Engineer has orally requested
the Contractor to immediately improve the fuel
storage with roof, concrete floor and
surrounding bund to minimize the risk of
spills/leaks of oil. Refer to the letter GET-KEA-
A4-153
Responsible Party: Keangnam
Deadline: 30-May-2014 (immediate)
Current status: Mitigation measures have not
been implemented
4.7.5 Package A5
Location: Asphalt Batching Plant (km 135)
Site visit: May 07, 30
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 54
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 7, 2014 (ACBP Km136)
May 30, 2014 (ACBP Km136)
Date first observed: 07-May-2014
Problems description and cause: Leaks and
spills from fuel oil tanks and bitumen burning
equipment were noted. Puddles of
contaminated water were also noted in the said
areas.
Recommendation and Action taken by
Engineer: The Engineer required the
Contractor to improve fuel control at this
location (Referring to the letter No. GET-KEA-
A5-145 dated on 15th May, 2014)
Responsible Party: Keangnam Contractor
Deadline: Immediate
Current status: Mitigation measures have not
been implemented
May 7, 2014 (Km 148+600)
Location: Km148+600
Site visit: May 07, 30; June 04
Date first observed: 07-May-2014
Problems description and cause: Although a fuel storage area with roof and concrete flooring is provided at the site, toppled drums were left outside and are exposed to the elements. Leaks and spills are also evident.
Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location (Referring to the letter No. GET-KEA-A5-145 dated on 15th May, 2014)
Responsible Party: Keangnam Contractor
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 55
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 4, 2014
Deadline: Immediate
Current status: Mitigation measure has not been implemented
4.7.6 Package A6
April 27, 2013 (Km172)
June 5, 2014 (Km172)
Location: Km172
Site visit: Apr 27; Jun 05
Date first observed: 27-Apr-2014
Problems description and cause: Fuel control
is not well performed; fuel tanks were put
directly on the ground, lack of safety fence and
signboards at fuel storage area.
Recommendation and Action taken by
Engineer: The Engineer required the
Contractor to improve fuel control at this
location, at the same time, the Engineer also
provided the instruction for this issues.
Responsible Party: Doosan Contractor
Deadline: 05-May-2014
Current status: Most item is finish at this
location, the Contractor have already cleaned at
this location.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 56
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.7.7 Package A7
During the site inspection in this period, we did not detect any serious problem regarding to
hazardous substance management. Package A7 has been opened to exploit.
4.7.8 Package A8
By observation during site inspection this period, we did not find any serious problem regarding
to hazardous substance management.
4.8 UNSUITABLE MATERIAL DISPOSALS AND BORROW PITS
4.8.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.8.2 Package A2
April 02, 2014
May 30, 2014
Location: Km 45+500
Site visit: Apr 2, 14, 29; May 10, 30; June 27
Date first observed: 17-Jan-2014
Problems description and cause: Unsuitable
material is disposed along throughway (this
area is still in right of way)
Recommendation and Action taken by
Engineer: The Contractor is requested to find
out and submit disposal place for this material;
unsuitable material must be removed to
disposal place right after the approval of the
Engineer for disposal area. Refer to letter
GET1/POS/A2/2388
Responsible Party: POSCO
Deadline: 24-Jan-2014 (immediate)
Current status: The Contractor is removing
this material to approved disposal place;
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 57
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Jun 27, 2014
however, the progress of this work is slow
4.8.3 Package A3
Package A3 has been opened on June 28, 2014 and during this quarter there was not any
unauthorized disposal activity detected.
4.8.4 Package A4
June 10, 2014
Location: Km 96+000
Site visit: Jun 10, 18, 23
Date first observed: 10-Jun-2014
Problems description and cause: The
Contractor dumped unsuitable materials beside
express-way without the approval of Engineer
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to remove the unsuitable materials
to the approved disposal. Refer to the letter
GET2-KEA-A4-1580
Responsible Party: Keangnam
Deadline: 25-Jun-2014
Current status: The Contractor has not yet
implemented the Consultant ‘s instructions
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 58
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 18, 2014
4.8.5 Package A5
May 07, 2014
May 30, 2014
Location: Km 136+000
Site visit: May 07, 30; June 09
Date first observed: 07-May-2014
Problems description and cause: It’s noted
that the Contractor disposed unsutable material
on area that is close to a small stream without
permission of local authority and the Consultant
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to remove the spoils to an approved
disposal place and clean the stream of
materials; slope stabilization measures must be
applied to ensure that the stream will not be
blocked even during heavy downpours. Refer to
letter No. GET-KEA-A5-145 dated on 15th May,
2014
Responsible Party: Keangnam Contractor
Deadline: Immediate
Current status: Mitigation measures have not
been implemented
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 59
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 09, 2014
4.8.6 Package A6
By the site inspections during this quarter, the Engineer didn’t dectect the unsuitable material
disposal activity of the Contractor in unauthorized disposal place. Besides, the Contractor also
didn’t submit any new borrow pit.
4.8.7 Package A7
April 25, 2014
Location: Km 190+420
Site visit: Apr 25; May 05, 29; June 7, 16, 30
Date first observed:
Problems description and cause: The
Contractor disposed unsuitable material under
the bridge and close to riverside without
permission of the Engineer
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to remove the unsuitable material as
much as possible to the approved disposal
place and apply the slope protection as well as
restore the water flow in this area as
requirement of ADB during mission in May,
2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 60
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 29, 2014
Responsible Party: Guangxi
Deadline: 30-Jul-2014
Current status: The Contractor is being
mobilized the equipment to carry out the work
June 30, 2014
April 29, 2014
Location: Km 195+500
Site visit: Apr 14; May 05, 29; June 16, 30
Date first observed:
Problems description and cause: The
Contractor disposed unsuitable material under
the bridge and close to riverside without
permission of the Engineer
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to remove the unsuitable material as
much as possible to the approved disposal
place and apply the slope protection in this area
as requirement of ADB during mission in May,
2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 61
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 29, 2014
Responsible Party: Guangxi
Deadline: 30-Jul-2014
Current status: The Contractor is installing the
gabion at the toe of the slope
June 16, 2014
April 14, 2014
Location: Km 208+890
Site visit: Apr 14; May 05, 29; June 12, 16, 30
Date first observed:
Problems description and cause: The
Contractor disposed unsuitable material on
riverside without permission of the Engineer
and the soil encroached riverbed
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to remove the unsuitable material
that encroached riverbed to the approved
disposal place and apply the slope protection in
this area as requirement of ADB during mission
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 62
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 29, 2014
in May, 2014
Responsible Party: Guangxi
Deadline: 30-Jul-2014
Current status: Mitigation measures have not
been implemented
June 12, 2014
April 24, 2014
Location: Km 209+800
Site visit: Apr 14; May 05, 29; Jun 16, 30
Date first observed:
Problems description and cause: The
Contractor disposed unsuitable material on
riverside without permission of the Engineer
and the soil encroached riverbed
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to remove the unsuitable material
that encroached riverbed to the approved
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 63
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 29, 2014
June 16, 2014
disposal place and apply the slope protection in
this area as requirement of ADB during mission
in May, 2014
Responsible Party: Guangxi
Deadline: 30-Jul-2014
Current status: Mitigation measures have not
been implemented
4.8.8 Package A8
Package A8 has come to operation in early of March this year and there was no disposal
activity noted during site inspections in this quarter.
4.9 WASTE AND CLEANLINESS ON SITE
4.9.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.9.2 Package A2
The main construction work of package A2 has been finished and all the sites are clean.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 64
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.9.3 Package A3
During the site inspections during this period, there is no serious problem of waste or dirtiness
on site noted in package A3. This package also has been exploited from June 28, 2014.
4.9.4 Package A4
May 8, 2014
June 23, 2014
Location: Ngoi Van Bridge
Site visit: Jun 10, 18, 23
Date first observed:
Problems description and cause: The
Contractor dumped leftover concrete beside
riverbank
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to remove the this material to the
approved disposal. Refer to the letter GET-
KEA-A4-153; GET2-KEA-A4-1580
Responsible Party: Keangnam
Deadline: Immediate
Current status: The Contractor has not yet
implemented the Consultant ‘s instructions
4.9.5 Package A5
Location: whole package
Site visit: Apr 01, 09, 25; May 13, 26; June 13, 24
Description: Construction site is tidy and clean
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 65
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 1, 2014 (Km135)
May 26, 2014 (Km 136)
June 24, 2014 (Km141)
4.9.6 Package A6
April 4, 2014 (Km154)
Location: whole package
Site visit: Apr 4, 15, 26; May 19; jun 05
Description: Construction site is tidy and
clean. Package A6 has come to operation in
June 14, 2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 66
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 19, 2014 (Km163)
June 5, 2014 (Km182)
4.9.7 Package A7
During the site inspections during this period, there is no serious problem of waste or dirtiness
on site noted in package A7.
4.9.8 Package A8
The main construction work of package A8 has been finished and all the sites are clean.
4.10 BIODIVERSITY PRESERVATION
In this period, during the site inspections, we did not find any serious impacts, which arise from
construction activities of the project, on biodiversity preservation.
4.11 WORKERS’ CAMPS CONDITIONS
4.11.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.11.2 Package A2
Up to now, the main construction work of package A2 has been finished and the Contractor
already demobilized all worker’s camps onsite.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 67
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.11.3 Package A3
In package A3, the Contractor is hiring the local people’s houses for the living of workers with
enough sanitary facilities. Thus, there is not any worker’s camp on site.
4.11.4 Package A4
May 29, 2014
June 23, 2014
Location: Workers’ camps at Ngoi Gianh
Bridge
Site visit: Apr 02, 09, 23; May 8, 16, 29; Jun 6, 10, 23
Current status: The toilet is maintained in
clean and hygienic conditions
Location: Km 105+280
Site visit: May 08, 29; Jun 10, 18, 23
Date first observed: 08-May-2014
Problems description and cause: The
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 68
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 29, 2014
June 18, 2014
rubbish was not collected regularly. The
Contractor does not supply any rubbish bin for
this workers’ camp
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to supply a trash bin and clean the
worker’s camp in regular basic. Refer to the
letter GET-KEA-A4-153
Responsible Party: Keangnam
Deadline: Immediate
Current status: The Contractor has not yet
implemented the Consultant ‘s instructions
June 23, 2014
4.11.5 Package A5
Location: The worker’s camp at Km135
Site visit: May 07, 30
Date first observed: 07-May-2014
Problems description and cause:
Indiscriminate disposal of solid waste was
noted at the camp sites. There is also stagnant
water within the camp’s premises at km 135.
First aid kit and fire extinguishers are also not
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 69
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 07, 2014
May 30, 2014
provided
Recommendation and Action taken by
Engineer: The Engineer requested the
Contractor to improve living and working
condition at this camp (referring to the letter No.
GET-KEA-A5-145 dated on 15th May, 2014)
Responsible Party: Keangnam Contractor
Deadline: 30-May-2014
Current status: The Contractor have already
provided first aid kit and fire-extinguishers for
the worker’s camp
4.11.6 Package A6
In this period, almost all the main construction work of Package A6 was completed and
package A6 has been opened to exploit from June 14, 2014. All the worker’s camps have
been demobilized.
4.11.7 Package A7
Up to now, the Contractor has demobilized all the worker’s camp onsite due to the main
construction work had been finished.
4.11.8 Package A8
Up to now, the Contractor has demobilized all the worker’s camp onsite due to the main
construction work had been finished.
4.12 LABOUR SAFETY EQUIPMENT
4.12.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 70
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.12.2 Package A2
The main construction work of package A2 has been finished and during the site inspections
we didn’t detect the violation of labour safety.
4.12.3 Package A3
April 10, 2014
May 29, 2014
Location: Package A3
Site visit: Apr 03, 10, 24; May 7, 9, 16, 20, 29;
Jun 06
Date first observed: 10-Apr-2014
Problems description and cause: Workers do
not use enough PPEs while working on site
Recommendation and Action taken by
Engineer: The Engineer has orally requested
the Contractor to provide enough PPE for all
the workers and ensure that they use
adequately PPE at work
Responsible Party: Posco
Deadline: Daily
Current status: Workers were provided PPE to
work.
May 7, 2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 71
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.12.4 Package A4
May 08, 2014
May 20, 2014
Location: Ngoi Gianh bridge
Site visit: May 8, 16, 20, 29; Jun 23
Date first observed: 08-May-2014
Problems description and cause: The
workers did not use fully PPEs while working on
site.
Recommendation and Action taken by
Engineer: The Consultant has orally requested
the Contractor to force his workers using fully
PPEs when working on site in order to ensure
safety. Refer to the letters GET-MISC-410,
GET2-KEA-A4-1558, GET-KEA-A4-153, GET-
MISC-412…
Responsible Party: KEANGNAM
Deadline: Immediate
Current status: The Contractor has not yet
implemented the Engineer‘s instructions
June 23, 2014
4.12.5 Package A5
Location: Package A5
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 72
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 1, 2014 (Km136)
April 1, 2014 (Km111)
April 9, 2014 (Km111)
Site visit: Apr 01, 09; May 07, 30; Jun 9, 18
Date first observed: 01-Apr-2014
Problems description and cause: Workers
are not provided enough PPE at work
Recommendation and Action taken by
Engineer: The Contractor must implement the
tasks as follows:
1. Ensure that all workers are provided with
PPE and they use PPE adequately at work,
2. Install scaffoldings that are stable and has
fall prevention provisions
Responsible Party: Keangnam Contractor
Deadline: Immediate
Current status: Mitigation measures have not
been implemented
May 30, 2014 (Km137)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 73
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 18, 2014 (Km138)
4.12.6 Package A6
April 7, 2014 (Km 174)
April 15, 2014 (Km 182)
Location: Km174, Km182, Km156, Km170
Site visit: Apr 4, 15, 25; May 5, 19, 23; Jun 05
Description: The workers use fully PPE during work.
April 26, 2014 (Km 156)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 74
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 23, 2014 (Tunnel’s construction site)
June 05, 2014 (Km 162)
4.12.7 Package A7
April 24, 2014 (Km205+800)
May 16, 2014 (Km195+500)
Location: Package A7
Site visit: Apr 24; May 16; Jun 03, 12, 16, 30
First observed: 24-Apr-2014
Problems description and cause: The
workers are not provided PPE at work
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to immediately provide enough PPE
for workers and ensure that they use
adequately PPE at work
Deadline: Immediate
Current status: The Contractor still has not
provided PPE for workers
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 75
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 03, 2014 (Km195+230)
4.12.8 Package A8
Apr 25, 2014 (Km 222+800)
May 20, 2014 (Km224+369)
Location: Package A8
Site visit: Apr 25; May 20, 29; June 12, 16, 30
Date first observed: 25-Apr-2014
Problems description and cause: Workers
are not provide PPE at work due to
irresponsibility of the Contractor
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to stop the work and provide enough
PPE for workers and ensure that they use
adequately PPE at work
Deadline: Immediate
Current status: The Contractor has not
implemented the requirement of the Engineer
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 76
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
June 30, 2014 (Km231+800)
4.13 TRAFFIC CONDITIONS AND SIGNPOSTING IN ROADS
4.13.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.13.2 Package A2
The main construction work of package A2 has been finished, miscellaneous works which
have been carrying out during this period didn’t affect the traffic.
4.13.3 Package A3
April 03, 2014 (right site)
Location: TL325B bridge
Site visit: Apr 03, 10, 24; May 09, Jun 23
Date first observed: 05-Mar-2014
Problems description and cause: There is
not any sign board.
Recommendation and Action taken by
Engineer: The Contractor is also requested to
install signboard system in this area in order to
ensure safety for public traffic.
Responsible Party: Posco
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 77
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 9, 2014
Deadline: immediately
Current status: The Contractor has finished
the construction work in this area and installed
the signboard to warn the road user about the
height of the bridge; however, the surface of
existing road in this section is destroyed
June 23, 2014
4.13.4 Package A4
During the site inspections in this period, we didn’t detect any serious problem of traffic
maintenance and protection in package A4.
4.13.5 Package A5
Location: Public road Km129
Site visit: Apr 25; Jun 04
Date first observed: 25th April, 2014
Problems description and cause: Quality of
public road was impacted by the Contractor’s
construction activities.
Recommendation and Action taken by
Engineer: The Contractor must implement the
tasks as follows:
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 78
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 25, 2014 (Km129)
June 4, 2014 (Km129)
1. Undertake repair of damaged sections to
ensure that these are in passable condition.
2. Undertake full restoration of damaged road
sections.
Responsible Party: Keangnam Contractor
Deadline: 10-May-2014
Current status: The Contractor is reparing
damaged public road in orde to ensure the
region’s traffic.
May 7, 2014
May 30, 2014
Location: Public road - Km143+000
Site visit: May 07, 30
Date first observed: 07-May-2014
Problems description and cause: Certain
sections of Provincial Road 166 from km 141 to
143 as well as a section of the local road along
km 149, which is used by Project vehicles, are
damaged/in bad condition
Recommendation and Action taken by
Engineer: The Contractor must implement the
tasks as follows:
1. Undertake repair of damaged sections to
ensure that these are in passable condition.
2. Undertake full restoration of damaged road
sections.
(Referring to the letter No. GET-KEA-A5-145
dated on 15th May, 2014)
Responsible Party: Keangnam Contractor
Deadline: Immediate
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 79
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Current status: The Contractor is combining
with Local authorities and Yen Bai province
people’s committee in order to repair damaged
Province road No.166
4.13.6 Package A6
April 2, 2014 (Km180)
April 7, 2014 (Km165)
Location: Package A6
Site visit: Apr 2, 7; May 14, 19
Description: The Contractor installed safety signboard in roads.
May 14, 2014 (Km165)
4.13.7 Package A7
Location: Underpass culvert Km 211+565
Site visit: Apr 24; May 29; Jun 03
Date first observed: 20-Feb-2014
Problems description and cause: The
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 80
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 24, 2014
May 29, 2014
frontage road is dirty and slippery causing
difficulty for road users
Recommendation and Action taken by
Engineer: The Contractor has been requested
to speed up the construciton work here to
ensure the traffic condition for road users as
designed. Refer to letters Get4-GRBCC-1042
and 1056
Deadline: 28-Feb-2014 (Immediate)
Current status: The Contractor is carrying out
the work; surface of frontage road has been
covered with subbase
June 03, 2014
4.13.8 Package A8
Apr 10, 2014
Location: Underpass box culvert Km235+800
Site visit: Apr 10, 23; May 06; June 24
Date first observed: 19-Feb-2014
Problems description and cause: Frontage
road is dirty and slippery causing difficulty for
road users
Recommendation and Action taken by
Engineer: The Engineer has requested the
Contractor to speed up the work in this area to
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 81
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
May 06, 2014
June 24, 2014
ensure the traffic condition for road users. Refer
to letters Get4-Vinaconex-912 and 230 EPMU-
NBLC-A8
Deadline: 28-Feb-2014
Current status: The Contractor is carrying out
the work here to improve the traffic condition as
designed; however, the progress of work is
slow
4.14 SIGNPOSTING IN DANGEROUS SURFACES
4.14.1 Package A1
At the present, at package A1, the Contractor has finished all construction works.
4.14.2 Package A2
Up to now, the main construction work of package A1 has been finished.
4.14.3 Package A3
Location: Box Culvert - Km 60+570
Site visit: Apr 03, 10, 24; May 20
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 82
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
April 10, 2014
May 20, 2014
Current status: Safety fence has installed
surrounding dangerous deep hole. Up to now,
the package A3 has been finished the main
construction work and exploited from June 28,
2014
4.14.4 Package A4
Having inspected the construction sites, there is no serious problem noted during the site
inspections. However, the Engineer also recommended the Contractor to pay attention to this
issue if it happens and the necessary countermeasures must be applied to prevent accident
happening.
4.14.5 Package A5
In the site inspections, we didn’t detect the problem on the sites. However, the Engineer also
recommended the Contractor to pay attention to this issue if it happens and the necessary
countermeasures must be applied to prevent accident happening.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 83
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.14.6 Package A6
April 7, 2014 (Km165)
April 7, 2014 (Ngoi Chac bridge)
April 15, 2014 (Km179)
Location: Package A6
Site visit: Apr 7, 15; May 14, 28; June 5, 16
Description: The Contractor installed
signposting in dangerous surfaces in order to
keep the Project’s safety. Package A6 has been
opened for traffic in June 14, 2014.
May 14, 2014 (Tunnel’s construction site)
June 5, 2014 (Km174)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 84
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.14.7 Package A7
At the present, the main construction work of package A7 has been finished and it has come to
operation.
4.14.8 Package A8
At the present, the main construction work of package A8 has been finished and it has come to
operation.
4.15 RESTORATION AND LANDSCAPING WORKS
4.15.1 Package A1
The Contractor has finished the planting anti-flare and landscaping trees in median and toll
plazas. Planting grass on slopes of embankment to protect slopes from erosion also has been
completed.
4.15.2 Package A2
Up to now, the Contractor has completed planting anti-flare and landscaping trees in median.
Twenty kilometers of embankment slopes has been planted with grass to protect slopes from
erosion. Remaining slope is being prepared in order to carry out sodding work.
4.15.3 Package A3
The Contractor has already planted the anti-flare and landscaping tree in median. It’s about
40% of slope protected with grass and the Contractor is finishing the remaining slope to carry
out the sodding work.
4.15.4 Package A4
The Contractor is preparing to plant the anti-glare trees in median in compliance with the
requirements of the Project‘s Technical Specification.
4.15.5 Package A5
Up to now, the Contractor has grassed about 80% of the slopes and the Contractor is trying to
finish the remaining slope on schedule to complete the sodding work.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 85
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.15.6 Package A6
The Contractor already finshed the sodding work and anti-flare trees in the median of package
A6. Package A6 has come to operation in June 14, 2014.
4.15.7 Package A7
The Contractor has already submitted Restoration plant for Unauthorized disposals at
Km190+420; Km208+890; Km209+800 and Km195+350- Km195+500 on March 28th 2014.
Engineer reviewed and proposed to VEC and ADB to checking and approval. So now the
contractor was waiting opinion of ADB mission and will carry out according to ADB mission
mentions.
Till the present, the Contractor has grassed about 70% of the slopes and all the surfaces that
are prepared for second stage and the Contractor is trying to finish the remaining slope on
schedule to complete the sodding work.
4.15.8 Package A8
Up to the date, the Contractor has grassed about 70% of the slopes and the surface that is
prepared for second stage and the Contractor is carrying out the remaining work.
4.16 ACCIDENTS DUE TO THE LACK OF SAFETY MEASURES. RESPONSIBLES
During this period, the second quarter in 2014, by the site inspection, Consultant did not notice
about any serious accident happened due to lack of safety measures. Also, Consultant did not
receive any report regarding significant accidents in any package.
However, the Consultant has often required the Contractors to comply with the Methods
Statement as well as the project’s Safety Plan and to improve the management and control of
safety issues to ensure the project’s safety during construction process and prevent
unfortunate accidents in the future.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 86
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4.17 CONTRACTORS’ ENVIRONMENTAL AND SAFETY SPECIALISTS MOBILIZATION
As this issue is one of the most important ones for the right implementation of the contractors’ ECP and ECAP, here is presented a summary
table of the currently situation, updated until September 2013, in each package about the mobilization of contractors’ environmental and safety
managers. Some remarks are also considered inside the table.
PACKAGECURRENT STATUS
POSITION PROPOSED APPROVED MOBILIZED NAME REMARKS
A1 Environment Specialist Yes Yes Yes Jeon Young Sub
Safety manager Yes Yes Yes Le Dinh Quyen
A2
Safety manager Yes Yes Yes Le Dinh Quyen
A3 Environmental manager
Safety manager Yes Yes Yes Nguyen Thanh Cong
Demobilzied
A4 Environmental manager Yes No No Phan Manh Ha
Contractor proposed Mr Ha as Environment manager according to the letter KNEA4-GET-2014-192
Safety manager Yes Yes Yes Nguyen Danh Nam
Demobilized
A5 Environmental manager Yes Yes Yes Cho, Han Sun
Safety manager Yes Yes Yes Nguyen Van Phuc
A6 Environmental manager Yes Yes Yes Hee Duk Kim
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 87
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
PACKAGECURRENT STATUS
POSITION PROPOSED APPROVED MOBILIZED NAME REMARKS
Safety manager Yes Yes Yes Kwon, Oh Lin
A7
Environmental manager Yes Yes No Li Sheng Guang EPMU approved by letter No: 1562 /EPMU-NBLC-KH
These managers, after have been approved, were never mobilized,
Safety manager Yes Yes No Lai Jian Hong
A8 Environmental manager Yes Yes Yes Tran Van Dinh Package already opened to traffic
Safety manager Yes Yes Yes Mai Xuan Lap Package already opened to traffic
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 88
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
5. REFERENCE DOCUMENTS RELATIVE TO ENVIRONMENT, HEALTH AND SAFETY
ISSUES
5.1 PACKAGE A1
5.2 PACKAGE A2
5.3 PACKAGE A3
Nº Document reference Date Remark
1 GET2-POS-A3-2330 Apr 12, 2014
Request to ensure safety Km64+100
regarding collapse high voltage power
line).
2 GET2-POS-A3-2341 April 22, 2014
Request the Contractor to provide related
documents of landslide compensation-
Package A3
3 GET2-POS-A3-2342 April 22, 2014
Request the Contractor to solve landslide
in Phu Ninh- Hung Lo-Kim Duc- Viet Tri
City.
4 GET2-POS-A3-2343 April 22, 2014
Request the Contractor to remove spoil
and submit document of disposal area
section Km55+300- Package A3
5 GET2-POS-A3-2360 May 5, 2014 Environment and safety issues at
Package A3.
6 GET-MISC-410 May 6, 2014 Safety issue under NBLC Highway
Project
7 GET2-POS-A3-2360 May 13, 2014 Environment and safety issues at
Package A3.
8 GET-POS-A3-264 May 15, 2014 ADB Inspection Mission, May 2014 -
Package A3
9 GET2-POS-A3-2369 May 21, 2014 Warning the Project Manager about delay
to improve the safety issues at National
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 89
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
Railway Flyover, Package A3.
10 GET2-POS-A3-2375 May 30, 2014 Decorative plants at IC8 bridge.
11 GET2-POS-A3-2378 June 06, 2014
Remind the Contractor POSCO to
cooperate with local authorities to solve
the landslides and vibration issues at
Package A3
12 GET2-POS-A3-2383 June 13, 2014
Approve Environmental monitoring and
Observation services report in April 2014
- Package A3
13 GET-MISC-416 June 20, 2014 To ensure traffic safety on expressway
5.4 PACKAGE A4
Nº Document reference Date Remark
1 GET2-KEA-A4-1539 April 08, 2014 Request the Contractor to ensure safety
at construction area of Ngoi lao bridge
2 GET2-KEA-A4-1545 April 22, 2014
Request the Contractor to provide related
douments of landslide compensation-
package A4
3 GET2-KEA-A4-1546 April 22, 2014
Request the Contractor to solve landslide
in Sai Nga and Son Nga commune – Cam
Khe district, Phu Tho province.
4 GET2-KEA-A4-1547 April 22, 2014
Request the Contractor to submit disposal
area document for soft soil treatment from
Km82+810 - Km83+360 - Package A4.
5 GET-MISC-410 May 6, 2014 Safety issue under NBLC Highway
Project
6 GET2-KEA-A4-1558 May 13, 2014
Request the Contractor KEANGNAM to
ensure the environment & safety issues
and mobilize the environment and safety
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 90
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
managers
8 GET-KEA-A4-153 May 15, 2014 ADB Inspection Mission, May 2014 -
Package A4
9 GET-MISC-412 May 16, 2014
Second Reminder. Ensure traffic safety
for works carried out in open to traffic
areas
10 GET2-KEA-A4-1580 June 13, 2014
Ensure environment and safety issues at
package A4 and submit the document for
unauthorized disposal at Km96
11 GET2-KEA-A4-1581 June 13, 2014
Approve Environmental monitoring and
Observation services report in March
2014 - Package A4.
12 GET2-KEA-A4-1582 June 13, 2014
Approve Environmental monitoring and
Observation services report in April 2014
- Package A4
13 GET-MISC-416 June 20, 2014 To ensure traffic safety on expressway
14 GET2-KEA-A4-1588 June 26, 2014 Ensure safety at package A4
5.5 PACKAGE A5
No Document reference Date Remark
1 GET3-KEANGNAM-14-A5-107
April 7, 2014 Requires the Contractor to submit documents related to compensate local people
2 GET3-KEANGNAM-14-A5-117
April 17, 2014 Requires the Contractor to improve fuel control on the site
3 GET3-KEANGNAM-14-A5-125
April 23, 2014 Approval of Report on Environmental Monitoring for March 2014
4 GET3-KEANGNAM-14-A5-129
April 24, 2014 Comment on the documents of Asphalt Concrete Batching Plant Km126
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 91
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
5 GET3-KEANGNAM-14-A5-132
April 28, 2014 Inspection at Asphalt Concrete Batching Plants at Km117, Km126, Km135
6 GET3-KEANGNAM-14-A5-148
May 14, 2014 Approval of Report on Environmental Monitoring for April 2014
7 GET3-KEANGNAM-14-A5-153
May 15, 2014
Approval with comments on Asphalt Concrete Batching Plant at Dong Quyet Hamlet, Bao Hung commune, Tran Yen district, Yen Bai province
8 GET3-KEANGNAM-14-A5-157
May 16, 2014 Approval with comments on Asphalt Concrete Batching Plant at Km135+700, package A5
9 GET3-KEANGNAM-14-A5-183
June 10, 2014Request the Contractor to apply measures in order to minimize dust
10 GET3-KEANGNAM-14-A5-192
June 20, 2014.Approval of Report on Environmental Monitoring for May 2014
11 GET3-KEANGNAM-14-A5-193
June 20, 2014Comment on Method Statement of tree and shrub planting on package A5
12 GET3-KEANGNAM-14-A5-202
June 24, 2014Requires the Contractor to submit documents
13 GET3-KEANGNAM-14-A5-203
June 25, 2014Approval with comments on Asphalt Concrete Batching Plant
5.6 PACKAGE A6
No Document reference Date Remark
1 GET3-DOOSAN-14-A6-079
April 7, 2014 Require the Contractor to apply measures in order to ensure the Project’s environmental and safety issues
2 GET3-DOOSAN-14-A6-077
April 7, 2014
Approval of Report on Environmental Monitoring for January and February 2014
3 GET3-DOOSAN-14-A6-080
April 7, 2014 Approval of Report on Environmental Monitoring for March 2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 92
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
4 GET3-DOOSAN-14-A6-076
April 7, 2014 Approval with comments on Disposal area
5 GET3-DOOSAN-14-A6-078
April 7, 2014
Requires the Contractor to submit documents related to compensate local people
6 GET3-DOOSAN-14-A6-084
April 10, 2014 Approval with comments on Disposal areas
7 GET3-DOOSAN-14-A6-090
April 20, 2014 Approval of Report on Environmental Monitoring for April 2014
8 GET3-DOOSAN-14-A6-106
May 14, 2014 Approval of Method statement for Landscaping works, package A6
9 GET3-DOOSAN-14-A6-114
May 23, 2014 Require to survey and design additional living road , package A6
10 GET3-DOOSAN-14-A6-130
June 11, 2014Approval of Report on Environmental Monitoring for May 2014
11 GET3-DOOSAN-14-A6-142
June 24, 2014Requires the Contractor to submit documents
5.7 PACKAGE A7
Nº Document reference Date Remark
1 GET4-GRBCC-1103 April 02, 2014 Ensure safety and clean on site after
technical open - Package A7
2 GET4-GRBCC-1115 April 22, 2014
Ensure safety and clean on site after
technical open - Package A7- Second
time
3 GET4-GRBCC-1120 April 25, 2014 Ensure safety and clean on site - Package
A7
4 GET-MIS-406 April 29, 2014 ADB’s fact finding mission in May 2014
5 GET-MIS-407 April 29, 2014 Ensure safety during national holidays
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 93
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
6 GET-MIS-408 April 30, 2014 Ensure safety for works carried out in
areas already opened for traffic
7 GET-GUA-162 May 15, 2014 Actions to be taken regarding the disposal
along Package A7
8 GET4-GRBCC-1128 May 19, 2014 Request to submit the CMS for assuring
traffic safety during construction
9 GET4-GRBCC-1129 May 20, 2014
Retuning the Proposal drawing, addition
items design gabion baskets 151
provincial road (side MSE wall:
Km195+262.65- Km195+411.80)
10 GET4-GRBCC-1133 May 27, 2014 Request to implement the instruction of
ADB mission on May, 2014
11 GET4-GRBCC-1134 June 04, 2104
Require to clearance for under Bridges,
inside box culverts and pile culverts-
Package A7
12 GET4-GRBCC-1137 June 16, 2014Request to remove the bushes have dead
out of Package A7
13 572/EPMUNBLC-KT June 16, 2014
Construction and exploitation of Package
A7 and A8 (Lao Cai province) of Noi Bai-
Lao Cai expressway Project
14 588/EPMUNBLC-KT June 19, 2014To ensure traffic safety on expressway of
Package A7 and A8
5.8 PACKAGE A8
Nº Document reference Date Remark
1 GET4-Vinaconex-982 April 02, 2014 Ensure safety and clean on site after
technical open - Package A8- third time
2 GET4-Vinaconex- 987A April 16, 2104
Returning the Capacity document of Duc
Minh International Joint Stock company-
Grass supplier for slope of cutting section
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 94
VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province
Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain
(Vetiver grass)
3 GET4-Vinaconex-993 April 25, 2104 Ensure safety and clean on site -
Package A8
4 GET-MIS-406 April 29, 2104 ADB’s fact finding mission in May 2014
5 GET-MIS-407 April 29, 2104 Ensure safety during national holidays
6 GET-MIS-408 April 30, 2104 Ensure safety for works carried out in
areas already opened for traffic
7 GET4-Vinaconex-995 May 05, 2014
Approval the Capacity document of Duc
Minh International Joint Stock company-
Grass supplier for slope of cutting section
(Vetiver grass)- version A2
8 GET4-Vinaconex-997 May 06, 2014 Returning the construction methods for
planting grasses of Package A8
9 GET4-Vinaconex-1000 May 14, 2014 Approval the Method statement for
planting grasses for works (Version A2)
10 GET-Vinaconex-155 May 15, 2014 ADB inspection mission, May 2014-
Package A8
11 355/EPMU NBLC A8 June 04, 2014
The contractor is requested to removing
the unsuitable material out of Unauthority
disposal
12 GET4- Vinaconex-1028 June 26, 2014Require to clearance for Drainage box
culverts Km233+506- Package A8
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
95
6. GRIEVANCE INTAKES. PUBLIC CONSULTATION
As Annex 1 we include a summary table with references about complaints which were
expressed by local people affected by the construction works, to the environmental or social
impact specialists.
It’s supposed that these are not the only existing complaints, but the only ones received or
collected by Consultant.
On the other hand, after being implemented in some packages the system to collect
complaints by the contractors, the Consultant has not received any information from
contractors.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
96
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
97
7. ANNEX 1: COMPLAINTS OF LOCAL PEOPLE. SUMMARY TABLE
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
98
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
99
PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT.
A2 Km 42+300 ~ Km 44+180
Erosion leads the soil into croplands and cause the lost for 35 households. Local authority (Song Lo’s DPC) has finished calculating the damaged and requested the Contractor to compensate
15-Mar-2014
The EPMU, together with the Engineer and the Contractor, worked with local authorities and make a schedule for compensation from July 14, 2014 till August 04, 2014
Compensation shall be implemented as scheduled
A2
Tam Duong district,
Lap Thach district,
Song Lo district
There are houses that are near the construction sites affected by vibration during carrying out the embankement work; request the Contractor to verify the quo status of these houses and submit a compensation method basing on the calculation of the independent audit companies, then compensate affected households for the damaged assets
27-Mar-2014
The Contractor has hired the independent audit companies to verify the sphere of influence and impact level to compensate affected households for the damaged assets
The Contractor is carrying out the compensation work. Up to now, there were 90% of affected households already compensated. The remaining households don’t agree with compensation level and the Contractor is cooperating with local authority and these owners to deal with this matter
Consultant’s report
A2 Song Lo district
Request the Contractor to compensate impacted household for damaged assets due to flooding which was caused by construction work of the project
25-Mar-2014
The EPMU, together with the Engineer and the Contractor, worked with local authorities and make a schedule for compensation from July 14, 2014 till August 04, 2014
Compensation shall be implemented as scheduled
A3 IC10, TL325B, National raiway flyover
The Contractor’s construction activities and material transportation were caused dustiness at this location
16/04/2014
The Contractor is spraying water at this location in order to minimize the spread of dust during project implementation
The construction work has been finished
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
100
PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT.
A3 TL325B, National raiway flyover
The Contractor is constructing earth works with high vibration level, this situation is causing impact to structure of local people’s house
14/05/2014
The Contractor is combining with local people and local authorities in order to solve this problem
Construction work has been finished so this area was no longer impacted by construction activity
A4
Ngoi Gianh, Ngoi Lao, TL321C, Ngoi Van
The Contractor’s construction activities and material transportation were caused dustiness at this location
22/04/2014
The Contractor is spraying water at this location in order to minimize the spread of dust during project implementation
The Contractor is maintaining the mitigation measure
A5 Km133+700
After completion of embankment works in this area in January 2014, about 3,000 m2 of rice field, which is on higher elevation than the rest of the surrounding land, has not received irrigation. Prior to construction, water flows from higher fields that are now on the other side of the road. As the road now acts like a dam and the current irrigation system is lower than the affected rice field, the land owner can no longer grow rice in the area and prefers that his land is acquired by the Project. The area is also affected by erosion of the road embankment slope
15/04/2014
The Contractor is planting grass at embankment slope and installing side ditch at this location in order to prevent erosion. Besides, the Contractor also is combining with local authorities and EPMU in order to determine feasible options to resolve the issue on irrigation
The work is being carried out
Consultant´s reports
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
101
PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT. The Contractor must: 1-undertake consultations with the District People’s Committee and the affected HH to determine feasible options to resolve the issue on irrigation; 2-Implement slope stabilization measures and adequate drainage to avoid erosion to the rice field.
A5 Km 141+000 Km 143+000 Km 149+000
Certain sections of provincial road 166 from Km141 to Km143 as well as a section of the local road along Km149, which is used by Project vehicles, are damaged/in bad condition The Contractor must: 1-Undertake repair of damaged section to ensure that these are in passable conditionr; 2-Undertake full restoration of damaged road sections.
02/5/2014
The Contractor is combining with District People’s Committee in order to repair these damaged roads.
The work is being carried out
Consultant´s reports
A6 Km 165+000
The Contractor’s construction activities and transportation material are causing impact to quality of public roads, difficultly to vehicles travel through this location The Contractor must:
04/4/2014
The Contractor is combining with District People’s Committee in order to repair these damaged roads.
The work is under implementation
Consultant´s reports
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
102
PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT. 1-Repair damaged roads in order to ensure the region’s traffic; 2-Implement the Engineer’s requirements and instructionsr; 3-Comply with Traffic Control Plan during construction.
A6 Km 159+000
At Km159, this section of provincial road used to have asphalt pavement but it is now in muddy condition due to damage that is caused by Project vehicles The Contractor must: 1-Undertake repair of damaged section to ensure that these are in passable conditionr; 2-Undertake full restoration of damaged road sections.
02/5/2014
The Contractor is combining with District People’s Committee in order to repair these damaged roads.
The work is under implementation
Consultant's reports
A6
Ngoi Rom bride, Ngoi Cong bridge, Ngoi Hut bridge, Suoi Nau bridge
River obstruction due to temporary access road at bridge sites. Although the temporary access road across the river is no longer needed for the remaining bridge works, the Contrctor has yet to remove the said obstruction causing high velocity flow downstream. This condition will cause scouring/erosion of the river
02/5/2014
The Contractor is combining with District People’s Committee in order to solve this problem
The work is under implementation
Consultant's reports
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
103
PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT. embankment. The Contractor must undertake complete removal of the temporary access road and restoration of affected riverbed
A7 Km 210+200
Erosion leaded the soil from pipe culvert to the cropland; request the Contractor to restore the affected area and compensate land owner for damaged asset; countermeasure must be implemented to avoid this problem happening in the future
09/4/2014
The contractor had coordinate with Local Authorities and EPMU to compensate for household
Consultant´s reports
A7 Km 215+000
Erosion leaded the soil from pipe culvert to the adjacent pond; request the Contractor to restore the affected area and compensate land owner for damaged asset; countermeasure must be implemented to avoid this problem happening in the future
06/5/2014
The Contractor is cooperating with local authority and affected household to deal with this matter
The problem is being resolved
Consultant´s reports
A7 Km199+100 While construction the earth overflow in fields
13/2/2012; 14/8/2012
Request the contractor to dredging or compensation
The contractor had coordinate with Local Authorities and EPMU to compensate for household
Consultant´s reports
A8 Km 237+700 There is a house that was 09/4/2014 Compensation has been Consultant´s reports
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
104
PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT. impacted by vibration during carrying out embankement work and househole owner requested the Contractor to compensate her for damaged asset
implmented on 25/4/2014
A8 Km 220+900
Local people complained for the dirtiness and difficulty during traveling through the underpass box culvert in this area; request the Contractor to repair this section to ensure the traffic condition for the people
06/5/2014
The Contractor has carried out the work to repair the road in this section and ensure the traffic condition here
Consultant´s reports
A8 Km222+000 ~ Km222+500
Local people complained that it’s lack of frontage road to access their fields and forest; request the Contractor to construct a road to connect with production area
13/6/2014 The Contractor is carrying out the work
The work is under construction
Consultant´s reports
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
105
8. ANNEX 2: DATA OF ENVIRONMENTAL QUALITY PARAMETERS ANALYSIS
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
106
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
107
8.1 ANNEX 2.1: AIR QUALITY PARAMETERS
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
108
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
109
PACKAGE A3
Station Sensitive Receptors
Sampling Date & Time,
weather condition
PARAMETERS, µg/m3 SO2 CO NOx TSP PM10
Apr May June Apr May June Apr May June Apr May June Apr May June
Km 48+500 Residential area
14/1/2014 14/2/2014
Km 55+500 Residential area
14/1/2014 14/2/2014
050 3,302 31 128 108
Km 67+700 Residential area
14/1/2014 14/2/2014
65 3,472 29 199 79
Km 78+900 Street 14/1/2014 14/2/2014
58 3,205 62 231 102
QCVN 05:2009/BTNMT 350 (1-hr) 30,000 (1-hr) 200 (1-hr) 300 (1-hr) 150 (24-hr)
PACKAGE A4
Station Sensitive Receptors
Sampling Date & Time,
weather condition
PARAMETERS, µg/m3
SO2 CO NOx TSP PM10
Apr May June Apr May June Apr May June Apr May June Apr May June
Km 91+150 School 20/5/2014 172 3,162 39 235 146
Km 95+100 Residential area
20/5/2014 126 3,264 62 146 112
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
110
CPB TanThanh
Residential area
20/5/2014 215 3,169 85 262 124
Km 88+300 Residential area
21/5/2014 151 3,658 69 243 138
Km 104+900 Residential area
21/5/2014 119 3,056 71 124 88
Km 106+500 Residential area
21/5/2014 127 3,231 42 203 113
Km 106+800 School 21/5/2014 148 3,266 62 168 136
QCVN 05:2009/BTNMT 350 (1-hr) 30,000 (1-hr) 200 (1-hr) 300 (1-hr) 150 (24-hr)
PACKAGE A5
Station Sensitive Receptors
Date
PARAMETERS, µg/m3
SO2 CO NOx TSP HC
Apr May June Apr May June Apr May June Apr May June Apr May June
Km 117+050 A1 174 1620 162 178 - - -
Km 117+050 A1 159 1910 149 172 - - -
Km 117+050 A1 141 1540 157 195 - - -
Km 118+820 A2 292 3830 175 248 - - -
Km 118+820 A2 241 3270 162 231 - - -
Km 118+820 A2 247 3480 179 240 - - -
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
111
Station Sensitive Receptors
Date
PARAMETERS, µg/m3
SO2 CO NOx TSP HC
Apr May June Apr May June Apr May June Apr May June Apr May June
Km 121+433 A3 293 4710 188 257 - - -
Km 121+433 A3 322 4530 182 242 - - -
Km 121+433 A3 278 4490 174 239 - - -
QCVN 05:2009/BTNMT 350 (1-hr) 30,000 (1-hr) 200 (1-hr) 300 (1-hr) 5000 (1-hr)
Notes:
A1, A2, A3: Sampling points are close to Bao Long Church area (Km117+050): (GPS: N 21.40.269; E 104.53.057)
A4, A5, A6: Sampling points are close to Hop Minh My bridge construction site (Km118+820): (GPS: N 21.40.801; E 104.52.259)
A7, A8, A9: Sampling points are close to National Road bridge construction site (Km121+433): (GPS: N 21.41.609; E 104.51.171)
PACKAGE A6
Due to the main construction works of package A6 has been finished in the last quarter and miscellaneous works such as fencing, installing
signboard, cleaning, grassing don’t affect the air quality so the air mornitoring work has been terminated.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
112
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
113
8.2 ANNEX 2.2: WATER QUALITY PARAMETERS
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
114
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
115
PACKAGE A3
May
Sensitive Receptors
Date pH DO TSS COD
BOD5 (20oC)
Surf. Oil and Grease
Fecal Coliform
Total Coliform
- mg/l mg/l mg/l mg/l mg/l mg/l MPN/100mlMPN/100ml
Km 67+000 21/05/2014 6,52 - 22 18 10 - - 20 5.600 Km 78+000 21/05/2014 6,62 - 21 15 09 - - 24 5.720
QCVN08:08 5,5-9 ≥ 4 50 30 15 0,4 0,1 100 7500
Weather condition: Cloudy, average temperature 28.5 C, windy speed 0.33 m/s. South-East windy direction
PACKAGE A4
May
Sensitive Receptors
Date pH DO TSS COD
BOD5 (20oC)
Surf. Oil and Grease
Fecal Coliform
Total Coliform
- mg/l mg/l mg/l mg/l mg/l mg/l MPN/100mlMPN/100ml
Km 88+700 22/05/2014 6,52 - 32 14 7,5 - - 13 4.000 Km 97+500 22/05/2014 6,33 - 36 13,1 6,9 - - 10 4.820
Km 101+000 22/05/2014 6,52 - 30 11,8 6,6 - - 8 3.800 Km 109+000 22/05/2014 6,66 - 32 12,2 7,2 - - 6 3.740 Km 108+227 22/05/2014 6,48 - 33 12,6 7,6 - - 11 4.080
QCVN08:08 5,5-9 ≥ 4 50 30 15 0,4 0,1 100 7500
Weather condition: Cloudy, average temperature 28 C, windy speed 0.38 m/s. South-East windy direction
PACKAGE A5
According to Environmental Monitoring Plan approved by the Engineer through the letter Ref.
GET3-KEANGNAM-11-A5-037 dated 28th March, 2011, the contractor carryied out the
Environment monitoring with frequency: 1 time / 1 month. Include some indications: pH, DO,
TSS, COD, BOD5, Surfactant, Oil and grease, Fecal coliform, total coliform.
May
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
116
Sensitive Receptors
Date pH DO TSS COD
BOD5 (20oC)
Surf. Oil and Grease
Fecal Coliform
Total Coliform
- mg/l mg/l mg/l mg/l mg/l mg/l MPN/100mlMPN/100ml
W1 28/05/2014 7.1 5.7 32 7 < 5 < 0,1 < 0,1 50 960
W2 28/05/2014 6.9 5.5 34 9 < 5 < 0,1 < 0,1 60 930
W3 28/05/2014 7.0 5.4 36 5 < 5 < 0,1 < 0,1 75 880
W4 28/05/2014 6.6 5.9 40 6 < 5 < 0,1 < 0,1 65 780
W5 28/05/2014 7.1 6.4 37 6 < 5 < 0,1 < 0,1 64 690
W6 28/05/2014 7.3 6.1 33 7 < 5 < 0,1 < 0,1 70 710
W7 28/05/2014 7.5 5.6 30 8 < 5 < 0,1 < 0,1 65 680
W8 28/05/2014 6.7 6.2 32 9 < 5 < 0,1 < 0,1 72 610
W9 28/05/2014 6.6 6.0 31 19 11 0.24 0.05 420 4700
W10 28/05/2014 6.5 6.3 36 20 14 0.26 0.03 470 5900
W11 28/05/2014 6.3 5.7 39 18 12 0.30 0.07 510 5700
W12 28/05/2014 6.2 5.6 44 23 15 0.32 0.09 570 6100
QCVN08:08 5,5-9 ≥ 4 50 30 15 0,4 0,1 100 7500
Weather condition: Cloudy, average temperature 29.1 C, windy speed 0.37 m/s. South-East windy direction
Notes:
W1: Ngoi Thia river (Km145+500) – The bridge pier (N21050’961’’; E104042’500’’)
W2: Ngoi Thia river (Km145+500) – 50m from the bridge pier (toward upstream)
(N21050’960’’; E104042’483’’)
W3: Ngoi Thia river (Km145+500 – 200 m from the bridge pier (toward downstream)
(N21050’982’’; E104042’521’’)
W4: Ngoi Thia river (Km145+500 – 400 m from the bridge pier (toward downstream)
(N21050’998’’; E104042’539’’)
W5: Y Can lake (Km126+000) – Surface water sample at position No. 1 (N21044’038’’;
E104049’496’’)
W6: Y Can lake (Km126+000) – Surface water sample at position No. 2 (N21044’046’’;
E104049’503’’)
W7: Y Can lake (Km126+000) – Surface water sample at position No. 3 (N21044’067’’;
E104045’553’’)
W8: Y Can lake (Km126+000) – Surface water sample at position No. 4 (N21044’079’’;
E104045’571’’)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
117
W9: Nuoc Mat lake (Km122+000) – Surface water sample at position No. 1 (N21044’741’’;
E104050’492’’)
W10: Nuoc Mat lake (Km122+000) – Surface water sample at position No. 2
(N21044’711’’; E104050’935’’)
W11: Nuoc Mat lake (Km122+000) – Surface water sample at position No. 3
(N21044’726’’; E104050’955’’)
W12: Nuoc Mat lake (Km122+000) – Surface water sample at position No. 4
(N21044’725’’; E104050’965’’)
* Nuoc Mat lake (W9, W10, W11 and W12) has a small area and locates in the residential area
with dense population density. The area of lake tends to be smaller because of site clearance
as well as encroachment by inhabitants. Because domestic wastewater from residential areas
discharges into Nuoc Mat lake, water quality of the lake in polluted partly although the
measured values are within acceptable limits in QCVN 08:2008 – column B1.
PACKAGE A6
Due to the main construction works of package A6 has been finished in the last quarter and
miscellaneous works such as fencing, installing signboard, cleaning, grassing don’t affect the
water quality so the water quality mornitoring work has been terminated.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
118
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
119
8.3 ANNEX 2.3: NOISE LEVELS
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
120
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
121
PACKAGE A3
Package A3 has been opened for exploitation so there is no construction work that causes the
noise and vibration affecting sensitive areas.
PACKAGE A4
May
Noise measuring
Vibration measuring
MonitoringValue (dBA) Standard Value (dBA)
Station 6h-10h 10h-14h 14h -18h 6h - 21h
Km 91+150 55 53 55
70
Km 95+100 65 59 62
Tan ThanhCBP 67 60 64
Km 88+400 65 60 62
Km 105+100 62 55 61
Km 107+000 65 54 63
Km 106+800 62 53 60
Station Min. Value Max. Value Average
Value Standard Value
(mg/m3)
Km 91+150 0,33 0,29 0,31
0,055
Km 95+100 0,32 0,28 0,30
Tan ThanhCBP 0,34 0,30 0,32
Km88+300 to Km88+500 0,28 0,26 0,28
Km104+900 to Km105+350 0,28 0,24 0,26
Km106+500 to Km107+600 0,29 0,25 0,27
Km106+800 0,33 0,29 0,31
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
122
PACKAGE A5
January
Station Sensitive Receptors
Date
Result (dB) (average)
QCVN 26:2010 Exceeding
value
Working shift
6 h – 21h
21h – 6h
6 h – 21h
21h – 6h
6 h – 21h
21h – 6h
Km 117+050
N 1 23 / 04 / 2014 48.3 38.7 55 45 - -
- The value of noise level referred to standards applied for extremely quiet areas (QCVN 26:2010/BTNMT) - Noise primarily generated from the vehicle the vehicles or motorbike but constructional equipment
Weather condition: Cloudy, average temperature 28.2 C, windy speed 0.26 m/s. South-East windy direction
Station Sensitive Receptors
Date
Result (dB) (average)
QCVN 26:2010 Exceeding
value
Working shift
6 h – 21h
21h – 6h
6 h – 21h
21h – 6h
6 h – 21h
21h – 6h
Km118+820 N 2 23 / 04 / 2014 61.9 49.2 70 55
Km121+433 N 3 23 / 04 / 2014 68.2 51.9 70 55 - -
- The value of noise level referred to standards applied for commerce, office, industry area. - Noise primarily generated
Weather condition: Cloudy, average temperature 28.2 C, windy speed 0.26 m/s. South-East windy direction
Notes:
According to Environmental Monitoring Plan approved by the Engineer through the letter Ref.
GET3-KEANGNAM-11-A5-037 dated 28th March, 2011, the contractor carries out the
Environment monitoring with frequency: 1 time / 1 month.
N1: Sampling points are close to Bao Long Church area (Km117+050): (GPS: N 21.40.269;
E 104.53.057)
N2: Sampling points are close to Hop Minh My bridge construction site (Km118+820):
(GPS: N 21.40.801; E 104.52.259)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
123
N3: Sampling points are close to National Road bridge construction site (Km121+433):
(GPS: N 21.41.609; E 104.51.171)
PACKAGE A6
Package A3 has been opened for exploitation so there is no construction work that causes the
noise and vibration affecting sensitive areas.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
124
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
125
9. ANNEX 3: DOCUMENTATION RECEIVED FROM CONTRACTORS DURING THE
PERIOD
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
126
DOCUMENTS RECEIVED FROM CONTRACTORS DURING THE FOURTH QUARTER 2013
PACKAGE CONTRACTOR REFERENCE DESIGNATION REV APPROVED
A5 KEANGNAM KNE-NBLC5-
VEC&GET-14-142
Submission for approval of Asphalt plant at location Hamlet
4, Minh Tien commune, Tran Yen district, Yen Bai province
1 Yes
A5 KEANGNAM
KNE-NBLC5-
VEC&GET-14-003
Submission for approval of asphalt concrete batching plant
at Dong Quyet Hamlet, Bao Hung commune, Tran Yen
district, Yen Bai province – package A5
1
Yes
A5 KEANGNAM KNE-NBLC5-
VEC&GET-14-163A
Submission for approval of Asphalt Concrete Batching Plant
at Km135+700 - package A5
1 Yes
A5 KEANGNAM KNE-NBLC5-
VEC&GET-14-334
Report on Environmental Monitoring for May 2014 0 Yes
A5 KEANGNAM KNE-NBLC5-
VEC&GET-14-330
Method Statement of tree and shrub planting on package
A5
0 No
A5 KEANGNAM KNE-NBLC5-
VEC&GET-14-277
Submission for approval of Asphalt plant to be used for
section Km143+000 – Km150+900, package A5
1 Yes
A6 DOOSAN DHIC-14-SET-008 Request for approval of new disposal areas (package A6) 0 Yes
A6 DOOSAN DHIC-14-SET-011 Request for approval of new disposal areas (package A6) 0 Yes
A6 DOOSAN DHIC-14-SET-012 Environmental monitoring plan in May 2014 0 Yes
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
127
DOCUMENTS RECEIVED FROM CONTRACTORS DURING THE FOURTH QUARTER 2013
PACKAGE CONTRACTOR REFERENCE DESIGNATION REV APPROVED
A6 DOOSAN DHIC-14-SET-016 Submission of environmental monitoring report in May 2014 0 Yes
A6 DOOSAN DHIC-14-CT-039 Method Statement for landscaping work, package A6 1 Yes
A7 GRBCC
Ref.
GRBCC/GETINSA/
A7/2040
Shop drawing, plan to process and slope protection of
disposal site Km195+500
A1
A7 GRBCC
Ref.
GRBCC/GETINSA/
A7/2054
Proposal drawing, addition items design gabion baskets 151
provincial road (side MSE wall: Km195+262.65-
Km195+411.80)
A1 Returned the
contractor
A8 VINACONEX A8/LC/140411-04
Submit the Capacity document of Duc Minh International
Joint Stock company- Grass supplier for slope of cutting
section (Vetiver grass)
A1 Returned the
contractor
A8 VINACONEX A8/LC/140415-03 Submit the Method statement for planting grasses for works
(Version A2)
A1 Returned the
contractor
A8 VINACONEX A8/LC/140421-01
Submit the Capacity document of Duc Minh International
Joint Stock company- Grass supplier for slope of cutting
section (Vetiver grass)- version A2
A2
Approved
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
128
DOCUMENTS RECEIVED FROM CONTRACTORS DURING THE FOURTH QUARTER 2013
PACKAGE CONTRACTOR REFERENCE DESIGNATION REV APPROVED
A8 VINACONEX A8/LC/140508-09 Submit the Method statement for planting grasses for works
(Version A2)
A2 Approved
A8 VINACONEX A8/LC/140218-04 Submit the Method statement for planting anti-glare tree for
works of package A8
A1 Approved
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
129
10. ANNEX 4: STATUS OF THE DOCUMENTATION RELATED TO BORROW PITS,
QUARRIES, SOIL DISPOSALS AND CONCRETE BATCHING PLANTS
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
130
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
131
Note:
a – For public lands, indicate whether it is the property of the commune, district, province, etc.
b – Indicate the beneficial use of the property before it was acquired for the project (e.g., rice field, acacia plantation, etc.). If none, provide a short description, e.g., grassland, abandoned/idle farm lot, etc.
c – Specify which government agency (e.g., District People’s Committee) issued the approval, including any written agreement between the contractor and the land owner
Package A1
BORROW PITS
Package /Borrow Pit
No. Location
Approved Area (m2)
ApprovedVolume
(m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Local
AuthoritiesPSC Start
Estimated Completion
Actual Completion
A1/BP6
Minh Tri and Minh Phu Commune, Soc Son District,
Hanoi city
832,862 Industrial crop land
31-Aug-09 31-Aug-09 Closed 2013
A1/BP16
La Mai Hill, Huong Son Commune,
Binh Xuyen District, Vinh Phuc Province
606,590 Industrial crop land
27-Apr-10 06-May-10 06-May-10 27-May-13 Closed 2013
A1/BP17
Go De Hill, Huong Son Commune,
Binh Xuyen District, Vinh Phuc Province
263,290 Industrial crop land
27-Apr-10 06-May-10 06-May-10 27-May-13 Closed 2013
A1/BP21
Dong Mo Hill, Nam Son Commune, Soc Son District,
Hanoi City
492,800 Industrial crop land
01-Nov-10 25-Mar-11 25-Mar-11 30-Nov-15 Closed 2013
A1/SG1
Go De Hill, Huong Son Commune,
Binh Xuyen District, Vinh Phuc Province
100,000 Industrial crop land
27-Apr-10 13-Jan-11 13-Jan-11 27-May-13 Closed 2013
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
132
BORROW PITS
Package /Borrow Pit
No. Location
Approved Area (m2)
ApprovedVolume
(m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Local
AuthoritiesPSC Start
Estimated Completion
Actual Completion
A1/SG4
Dong Giang Hill, Trung My
Commune, Binh Xuyen District, Vinh
Phuc Province
90,000 Industrial crop land
27-Apr-10 22-Mar-12 22-Mar-12 27-May-13 Closed 2013
QUARRIES
Package /Quarry No.
Location Approved Area (m2)
ApprovedVolume
(m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Local
Authorities PSC Start
Estimated Completion
Actual Completion
A1/Q1
Quang Son commune, Lap
Thach dist, Vinh Phuc
123,000 2,611,729 Rock-mine
08-Apr-10 13-Dec-11 13-Dec-11 17-Apr-13 Closed 2013
A1/Q2
Trung Mau commune, Binh Xuyen dist, Vinh
Phuc
640,000 75,187,00
0
Rock-mine
21-Jul-04 13-Dec-11 13-Dec-11 30-Jun-14 Closed 2013
BATCHING PLANTS
Package/ CBP No.
Location Appropriate
settling pond
Noise and dust
measures
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Local
AuthoritiesPSC Start Est. End
Actual End
A1/CBP1 Underpass NH2 Yes Yes Evernew Holding.,
JSC
A24-BT4, My Dinh commune,
Tu Liem dist, Hanoi
Unidentified Unidentified 10-May-11 10-May-11 Dec 2013
A1/CBP2 Underpass NH2 Yes Yes Ngoc Mai Construct.
Tho Dan village, Kim No
Unidentified Unidentified 29-Jun-11 29-Jun-11 Dec 2013
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
133
BATCHING PLANTS
Package/ CBP No.
Location Appropriate
settling pond
Noise and dust
measures
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Local
AuthoritiesPSC Start Est. End
Actual End
JSC commune, Dong Anh dist,
Hanoi
A1/CBP3 Km 13+500 Yes Yes POSCO
POSCO E&C – Noi Bai – Lao Cai Highway project – Huu
thu village, Kim Long commune,
Tam Duong dist, Vinh Phuc
Pond 05-May-08 27-Jan-10 27-Jan-10 Dec 2013
A1/CBP4 Km 25+000 Yes Yes POSCO
POSCO E&C – Noi Bai – Lao Cai Highway project – Huu
thu village, Kim Long commune,
Tam Duong dist, Vinh Phuc
Long term cropland
05-May-08 27-Jan-10 27-Jan-10 Dec 2013
SPOILS DISPOSAL AREAS
Package / SD No.
Location Approved
Area (m2)
Approved Capacity
(m3)
Ownershipa Approval Operation
Name Contact Info Local
Authorities PSC
A1/SD1
Trung Mau village, Trung My commune, Binh Xuyen district, Vinh Phuc province
200,000 m2 200,000 m3
Hoang Chi Thanh
Hoang Van Ngoc
Dong Ich Hamlet, Trung My commune,
Binh Xuyen dist, Vinh
Phucs
06-Dec-10 20-Dec-10
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
134
Package A2
BORROW PITS
Package /Borrow Pit No.
Location ApprovedArea (m2)
ApprovedVolume
(m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Local
AuthoritiesPSC Start
Estimated Completion
Actual Completion
A2/BP4
Chay Hill, Vinh Phu village, Hop Hoa
town, Tam Duong District, Vinh Phuc
Province
327,167 Industrial crop land
29-Dec-09 01-Apr-10 01-Apr-10 29-Dec-12 March 2014
A2/BP5
Rung Nen hill, Thanh Van-Dao Tu
Commune, Tam Duong District, Vinh
Phuc Province
508,467 Industrial crop land
23-Mar-10 01-Apr-10 01-Apr-10 30-Apr-13 March 2014
A2/BP7
Nhon Huc & Go Bep Hill, Tu Yen
Commune, Song Lo District, Vinh Phuc
Province
941,590 Industrial crop land
01-Oct-10 15-Nov-10 15-Nov-10 01-Oct-13 March 2014
A2/BP11
Quan Hill, Phu Ninh Commune, Phu Ninh
District, Phu Tho Province
297,000 Industrial crop land
19-May-10 01-Jun-12 01-Jun-12 19-May-12 March 2014
A2/BPSG1
Rung Nen hill, Thanh Van-Dao Tu
Commune, Tam Duong District, Vinh
Phuc Province
508,467 Industrial crop land
23-Mar-10 19-May-12 19-May-
12 30-Apr-13 March 2014
A2/BPSG5
Dinh Chua Hill, Tien Lu Commune, Lap Thach District, Vinh
Phuc Province
623,837 Industrial crop land
18-Oct-10 09-Jul-12 09-Jul-12 18-Oct-12 March 2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
135
QUARRIES
Package /Quarry No.
Location Approved Area (m2)
Approved Volume
(m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact
Info Local
AuthoritiesPSC Start
Estimated Completion
Actual Completion
A2/Q1
Quang Son commune, Lap
Thach dist, Vinh Phuc
123,000 2,611,729 Rock-mine 13-Dec-11 08-Apr-10 13-Dec-11 17-Apr-25 March 2014
A2/Q2
Trung Mau commune, Binh Xuyen dist, Vinh
Phuc
640,000 75,187,000 Rock-mine 13-Dec-11 21-Jul-04 13-Dec-11 30-Jun-14 March 2014
SPOILS DISPOSAL AREAS
Package / SD No.
Location Approved
Area (m2)
Approved Capacity
(m3)
Ownershipa Approval Operation
Name Contact Info Local
AuthoritiesPSC
A2/SD1
Fields 99 and 99(1), map No. 21, Cau hamlet, Hoang Dan commune, Tam Duong district, Vinh Phuc province
9,110 m2 30,000 m3 Hoa Hung Co.,Ltd
Hoang Dan commune, Tam
Duong dist, Vinh Phuc
09-Jul-10 12-Jul-10
A2/SD2 Tu Du commune, Lap Thach district, Vinh Phuc province
60,000 m2 60,000 m3 Tu Du
commune
Tu Du CPC, Lap Thach dist,
Vinh Phuc March-10 04-Jun-10
A2/SD3
Dong Go area, map No. 07, Tien Lu commune, Lap Thach district, Vinh Phuc province
2,000 m2 4,000 m3 Tien Lu
commune
Tien Lu CPC, Lap Thach dist,
Vinh Phuc 28-May-10 04-Jun-10
A2/SD4 Dong Ai area, map No. 19, Tien Lu
12,000 m2 24,000 m3 Tien Lu
commune Tien Lu CPC,
Lap Thach dist, 28-May-10 04-Jun-10
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
136
SPOILS DISPOSAL AREAS
Package / SD No.
Location Approved
Area (m2)
Approved Capacity
(m3)
Ownershipa Approval Operation
Name Contact Info Local
AuthoritiesPSC
commune, Lap Thach district, Vinh Phuc province
Vinh Phuc
A2/SD5
Field No. 155, map No. 12, Phu Thinh village, Tu Yen commune, Song Lo district, Vinh Phuc province
5,566 m2 11,132 m3 Tu Yen
commune
Tu Yen CPC, Song Lo dist,
Vinh Phuc 11-May-10 20-May-10
A2/SD6
Map No. 38, Khan Tat hill, Dao Tu commune, Tam Duong district, Vinh Phuc province
10,300 m2 10,300 m3 Ly Van Hung
Dao Tu commune, Tam
Duong, Vinh Phuc
25-Mar-10 31-Mar-10
A2/SD7
Field No. 1, map No. 3, Bo U hill, Dao Tu commune, Tam Duong district, Vinh Phuc province
9,400 m2 9,400 m3 Nguyen Anh
Chien
Dao Tu commune, Tam
Duong, Vinh Phuc
25-Mar-10 31-Mar-10
A2/SD8
Field No. 185, Dong Ich commune, Lap Thach district, Vinh Phuc province
30,560 m2 30.560 m3 Dong Ich commune
Dong Ich CPC, Lap Thach dist,
Vinh Phuc 08-Mar-10 17-Mar-10
A2/SD9
Field No. 613, Dong Ich commune, Lap Thach district, Vinh Phuc province
10,345 m2 10,345 m3 Dong Ich commune
Dong Ich CPC, Lap Thach dist,
Vinh Phuc 08-Mar-10 17-Mar-10
A2/SD10
Field No. 78, Gian village, Cao Phong commune, Song Lo district, Vinh
3,268 m2 6,536 m3 Nguyen Van
Luu
Cap Phong commune, Song
Lo dist, Vinh Phuc
20-Mar-10 25-Mar-10
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
137
SPOILS DISPOSAL AREAS
Package / SD No.
Location Approved
Area (m2)
Approved Capacity
(m3)
Ownershipa Approval Operation
Name Contact Info Local
AuthoritiesPSC
Phuc province
A2/SD11
Fields No. 337, 475, 481, Dong Hang Phien village, Dong Thinh commune, Song Lo district, Vinh Phuc province
13,863 m2 100,000 m3 Dong Thinh commune
Dong Thich CPC, Dong
Thinh commune, Song
Lo dist, Vinh Phuc
Mar-10 18-Mar-10
A2/SD12
Long Son village, Dao Tu commune, Tam Duong district, Vinh Phuc province
2,250 m2 5,500 m3 Lai Xuan Diem
Long Son village, Dao Tu commune, Tam Duong district,
Vinh Phuc province
07-Mar-13 30-May-13
BATCHING PLANTS
Package/ CBP No.
Location Appropriate
settling pond
Noise and dust
measures
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Local
AuthoritiesPSC Start Est. End
Actual End
A2/CBP1 Km 39+118 Yes Yes Vinh Sinh Co.,Ltd
160 – Dinh Dong – Le Chan dist, Hai Phong
City
Agricultural land
Unidentified 17-Nov-10 17-Nov-10 March 2014
A2/CBP2 Lo River Bridge Yes Yes POSCO
POSCO E&C – Noi Bai – Lao Cai Highway project – Huu
thu village, Kim Long commune,
Tam Duong dist, Vinh Phuc
Agricultural land
05-May-08 15-Jun-11 15-Jun-11 March 2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
138
BATCHING PLANTS
Package/ CBP No.
Location Appropriate
settling pond
Noise and dust
measures
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Local
AuthoritiesPSC Start Est. End
Actual End
A2/CBP3 Lo River Bridge Yes Yes POSCO
POSCO E&C – Noi Bai – Lao Cai Highway project – Huu
thu village, Kim Long commune,
Tam Duong dist, Vinh Phuc
Wild land 05-May-08 25-Jun-11 25-Jun-11 March 2014
Package A3
BORROW PITS
Package / Borrow Pit No.
Location
Approved
Area (m2)
Approved
Volume (m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated
Completion
Actual Completio
n
1 Km 52+500 (Section 1) 90,000m3
/ 1 year TGT Group Hill land
Phu Tho Province
02-Jul-12
30-Aug-13 Not yet
2 Km 53+700 (Section 1) 90,000m3
/ 1 year TGT Group Hill land
Phu Tho Province
02-Jul-12
30-Aug-13 Not yet
3 Km 54+000 (Section 1) 90,000m3
/ 1 year TGT Group Hill land
Phu Tho Province
02-Jul-12
30-Aug-13 Not yet
4 Km 54 + 000 (Section 3)
328,295 Long Vuong Hill land Phu Tho Province
15-Aug-11
14-Jun-13 Not yet
5 Km 76 +400 (Section 6) 264,527 VINASHIN Hill land Phu Tho Province
10-Feb-12
31-Aug-13 Not yet
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
139
BORROW PITS
Package / Borrow Pit No.
Location
Approved
Area (m2)
Approved
Volume (m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated
Completion
Actual Completio
n
6 Km 81 +000 (Section 7) 805,000 Posco E&C Hill land Phu Tho Province
Not yet
QUARRIES
Package / Quarry No.
Location ApprovedArea (m2)
Approved
Volume (m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated
Completion Actual
Completion
1 Phu Man comm.
Quoc Oai dist. Ha Noi Capital
Sunway-
Hataco JSC
2 Phu Man comm.
Quoc Oai dist. Ha Noi Capital
Vimeco
JSC 1-Oct-13 30-Jan-14
3 Ngoc Lap comm. Yen
Lap dist. Phu Tho pro.
Phu Tho forest & mineral product
JSC
4 Phuc Ung comm. Son duong dist.,
Tuyen Quang pro.
Tuyen Quang forest & mineral product
JSC
23-Nov-
12 31-Mar-13
5 Huong Can comm.
Thanh Son dist., Phu Tho pro.
ThanhCong limited Co.,
16-Jan-
13 20-Nov-13
6 Thuong Am comm.,
Son Duong dist. Tuyen Quang pro.
Duy Thinh
Co.,
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
140
QUARRIES
Package / Quarry No.
Location ApprovedArea (m2)
Approved
Volume (m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated
Completion Actual
Completion
7 Nhu Khe comm.
Thanh Liem dist., Ha Nam pro.
Thang Loi
cooperative
8 Dan Ha comm., Ky Son dist., Hoa Binh
pro. N/A
9 Doi Can comm. Yen
Son dist. Tuyen Quang pro.
Ha Nam
lime stone Co., - Mrs
10 Ngoc Lap comm. Yen
Lap dist. Phu Tho pro.
Tu Lap Co.,
11 Ngoc Lap comm. Yen
Lap dist. Phu Tho pro.
Truong An
JSC 6-Feb-13 10-Nov-13
12 Quang Son comm.
Lap Thach dist. Vinh Phuc pro.
Hung Vi
Co.,
13 Cao Duong comm.
Luong Son dist. Hoa Binh pro..
Ngoc Thao
Co., 1-Apr-13 3-Nov-13
14 Cao Duong comm.
Luong Son dist. Hoa Binh pro..
Valine Co.,
(Hung Long)
SPOILS DISPOSAL AREAS
Package SD No.
Location
Approved
Area (m2)
Approved
Capacity
(m3)
Ownershipa
Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
1 Km53+360 3,200 14,400 Nguyen van 3-Jun-10 The
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
141
QUARRIES
Package / Quarry No.
Location ApprovedArea (m2)
Approved
Volume (m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated
Completion Actual
Completion
Hoa, Nguyen Van
Chung
Consultant
2 Km49+500 2,350 46,000 Le Van Ngu Rice field & Vegetable
field
16-Feb-11
The Consultant
3 Km49+600 1,954 37,000 Nguyen
Tien Dung
Rice field & Vegetable
field
16-Feb-11
The Consultant
4 Km50+900 2,146 29,000 Le Dinh
Chat
Rice field & Vegetable
field
16-Feb-11
The Consultant
5 Km51+400 1,940 35,000 Nguyen Thi
Ly
Rice field & Vegetable
field
16-Feb-11
The Consultant
6 Km52+800 5,690 34,000 Nguyen Thi
Tuat
Rice field & Vegetable
field
16-Feb-11
The Consultant
7 Area No. 8 - Hung Lo 53,489 500,000
Nguyen Xuan
Thuong, Nguyen Van Sang, Cao Van Chinh, Cao Van
Duong, Cao Van Minh
22-Mar-
11 The
Consultant
8 Km52+740 4,114 30,000 Nguyen
Xuan Hai
Area No.2 - Phu Ninh Commune
24-Apr-13The
Consultant
9 Km52+840 6,021 60,000 Nguyen Van
The
Area No.2 - Phu Ninh Commune
24-Apr-13The
Consultant
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
142
QUARRIES
Package / Quarry No.
Location ApprovedArea (m2)
Approved
Volume (m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated
Completion Actual
Completion
10 Km54+020 6,084 50,000 Nguyen Van
Bay
Area No.5 - Phu Ninh Commune
11 Hop Quan - Phu Ninh Commune
21,000 378,000 Phu Ninh Commune
Area No. 10 near Nha Xe
hill 13-Oct-10
The Consultant
12 Tien Kien Commune 15,724 283,032 Nguyen
Cong Chuc
Area No. 8 &No.9
4-Nov-11 The
Consultant
13 Km56+100 - Phu Ninh Commune
5,070 40,000 Nguyen Truong Giang
Area No.10 -
Phu Ninh Commune
22-Apr-11The
Consultant
14 Km55+900 - Phu Ninh Commune
2,880 15,500 Nguyen Van
Tai
Area No.10 - Phu Ninh Commune
24-Apr-13The
Consultant
15 Ram A1-2 Km00+100 - Phu Ninh Commune
5,736 50,000 Nguyen Van
Chi
Area No.8 - Phu Ninh Commune
24-Apr-13The
Consultant
16 Ram A1-2 Km00+200 - Phu Ninh Commune
4,072 35,000 Nguyen Thi
Nhuan
Area No.4 - Phu Ninh Commune
24-Apr-13The
Consultant
17 Km53+800 - Phu Ninh Commune
8,172 70,000 Phu Ninh Commune
Area No.7 - Phu Ninh Commune
24-Apr-13The
Consultant
18 Km56+300 - Phu Ninh Commune
6,163 50,000 Phu Ninh Commune
Area No.10 -
Phu Ninh Commune
24-Apr-13The
Consultant
19 Phu Ho Commune 25,000 150,000 Nguyen Van
Thai
Area No.5 - Phu Ho
Commune
25-Feb-11
The Consultant
20 Van Lung Commune 11,508 69,500 Van Lung Commune
Dui forest 13-Oct-10The
Consultant
21 Vo Lao Commune 12,850 89,950 Dinh Tien
Minh
06-Sep-10
The Consultant
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
143
QUARRIES
Package / Quarry No.
Location ApprovedArea (m2)
Approved
Volume (m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated
Completion Actual
Completion
22 Chi Tien & Hoang Cuong Commune
15,170 106,190 Tran Quy
Cuong 19-Oct-10
The Consultant
23 Yen Lap Commune 4,517 90,340
Truong Xuan
Company.,LTD
27-Jul-12 The
Consultant
BATCHING PLANTS
Package / SD No.
Location Appropriate settling
pond
Noise and dust measure
s
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End
1 Section 2 – Concrete batching plant D
Yes Yes HEUNG WOO
VINA CO., LTD
10-Aug-
10 31-Dec-13
2 Section 7 – Concrete batching plan t
Yes Yes Evernew 8-Dec-12 30-Jul-13
3 IC No.10 bridge - Concrete batching plant
Yes Yes
Duong Chau Construction and Trading
company
10-Jan-
13 9-Jul-13
4 Phu Ninh – Phu Tho Yes Yes Song Lo
construction &tradinG, JSC
14-Sep-
11 31-Dec-13
5 Section 3 – Asphalt concrete batching plant
N/A Yes SEAHAN 31-Dec-
12 3-May-13
6 Section 7 – Asphalt concrete batching plant
N/A Yes Cienco 116 12-Jul-13
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
144
Package A4
BORROW PITSPackage /Borrow Pit No.
Location Approved
Area (m2)
Approved
Volume (m3)
Ownershipa Prior Land Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated Completio
n
Actual Completio
n A4/BP1 Hill Thờ, zone 10,
Xuan Ang commune, Ha Hoa district, Phu Tho province.
39,000 473,277.7
Xuan Ang Commune
Mr Tuan. Xuan Ang President
Artificial forest land, farm land…
27 June 2012
Phu Tho Provincial People’s Committee
27 June 2012
4th Quarter 2013
A4/BP2 Hill Sặt, zone 1, Quan Khe commune, Ha Hoa district, Phu Tho province.
34,000 93,180 Quan Khe Commune
Mr Tuoc. Quan Khe president
Artificial forest land, farm land…
26 June 2012
Phu Tho Provincial People’s Committee
26 June 2012
4th Quarter 2013
A4/BP3 Hill Bóng Đa, zone 3, Quan Khe commune, Ha Hoa district, Phu Tho province.
36,000 193,909 Quan Khe Commune
Mr Tuoc. Quan Khe president
Artificial forest land, farm land…
26 June 2012
Phu Tho Provincial People’s Committee
26 June 2012
4th Quarter 2013
A4/BP4 Quyet Tien commune, Ha Hoa district, Phu Tho province.
45,400 292,012 Hien Luong Commune
Mr Nguyen. Hien Luong president.
Artificial forest land, farm land…
26 June 2012
Phu Tho Provincial People’s Committee
26 June 2012
4th Quarter 2013
A4/BP5 Hill Lau, zone 5, Vo Tranh commune, Ha Hoa district, Phu Tho province.
16,800 156,423 Vo Tranh Commune
Mr Thinh. Vo Tranh President
Artificial forest land, farm land…
23 Apr 2012
Phu Tho Provincial People’s Committee
23 Apr 2012
4th Quarter 2013
A4/BP6 Hill Trường, zone 1, Hien Luong commune, Ha Hoa district, Phu Tho province.
55,000 864,270 Hien Luong Commune
Mr Nguyen. Hien Luong president.
Artificial forest land, farm land…
23 Apr 2012
Phu Tho Provincial People’s Committee
23 Apr 2012
4th Quarter 2013
A4/BP7 Km80+000-Km82+500
118.500 805.098 Thanh Nga
Thanh Nga commune, Cam
Hill land of forestry tree
24 Aug 2012
Phu Tho Provincial
Aug 2012
Aug 2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
145
Hills of Ong Duoc, Nuong Phe, Nuong Dieu, Nuong Son, Nha Vam Go Ca
commune, Cam Khe, district.
Khe, district, Phu Tho province
People’s Committee
A4/BP8 Hill Reo, Dong Cam commune, Cam Khe district
239.443 Dong Cam commune, Cam Khe, district.
Dong Cam commune, Cam Khe, district.
Artificial forest land, farm land…
02 Oct 2012
Phu Tho Provincial People’s Committee
02 Oct 2012
02 Oct 2014
A4/BP9 Hill Gieng Chuoi, Tuy Loc commune, Cam Khe district
1.600 195.872 Tuy Loc commune, Cam Khe, district.
Tuy Loc commune, Cam Khe, district.
Artificial forest land, farm land…
02 Oct 2012
Phu Tho Provincial People’s Committee
02 Oct 2012
02 Oct 2014
A4/BP10
Hill Gia Gia and Hill Nuong Trong Phung Xa commune, Cam Khe district
2.500 99.000 Phung Xa commune, Cam Khe, district.
Phung Xa commune, Cam Khe, district.
Artificial forest land, farm land…
05 Oct 2012
Phu Tho Provincial People’s Committee
02 Oct 2012
05 Oct 2014
QUARRIESPackage /Quarry No.
Location Approved
Area (m2)
Approved
Volume (m3)
Ownershipa Prior Land Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated Completio
n
Actual Completio
n Not Applicable
SPOILS DISPOSAL AREAS Package / SD No.
Location Approved
Area (m2)
Approved
Capacity (m3)
Ownershipa Prior Land Useb Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
Xa Minh Coi, Ha Hoa 1 Km 90+080 1266.2 16400 Nguyen Thi
Rang Zone 7, Minh Coi Communce, Ha
Low elevation, flood area, can not
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
146
Hoa cultivation 2 Km 90+220 111.02 2500 Bui Van Nhu Zone 7, Minh Coi
Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
3 Km 90+220 637.6 12250 Nguyen Y Nguyen
Zone 7, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
4 Km 90+280 453.6 8200 Nguyen Viet Hung
Zone 7, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
5 Km 91+200 172.8 12000 Le Quang Thang Zone 5, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
6 Km 92+000 850 16369 Phung Thi Khoa Zone 5, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
7 Km 92+100 702.1 11200 Nguyen Van Giao
Zone 1, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
8 Km 92+510 504.2 6000 Nguyen Van Cuong
Zone 2, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
9 Km 92+600 522.2 6500 Nguyen Van Cuong
Zone 2, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
10 Km 92+850 822.73 14300 Do Thi Nu Zone 2, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
11 Km 93+050 376.2 6100 Nguyen Van Thoa
Zone 2, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
12 Km 93+160 687.6 13400 Nguyen Van Thoa
Zone 2, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
13 Km 93+100 326.3 5800 Le Thi Loan Zone 2, Minh Coi Communce, Ha Hoa
Fish pond, but not efficient
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
14 Km 93+600 1354.8 18200 Ly Minh Tam Zone 2, Minh Coi Low elevation, 20 Oct. Minh Coi 20 Oct. 4th Quarter 4th Quarter
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
147
Communce, Ha Hoa
flood area, can not cultivation
2010 Communce 2010 2013 2013
15 Km 93+700 650 5350 Nguyen Ba Ngoc
Zone 2, Minh Coi Communce, Ha Hoa
Low elevation, flood area, can not cultivation
20 Oct. 2010
Minh Coi Communce
20 Oct. 2010
4th Quarter 2013
4th Quarter 2013
16 Km 93+820 3880 85360 Nguyen Thanh Binh
Zone 2, Minh Coi Communce, Ha Hoa
Steep slope, unable to make farming
05 Oct. 2013
Ha Hoa District
05 Oct. 2013
18th June 2013
17 Km 92+300 900 15300 Nguyen Van Tai Zone 2, Minh Coi Communce, Ha Hoa
Not suitable for farming.
05 Oct. 2013
Ha Hoa District
18 June. 2013
27 June. 2013
18 Km 91+240 2718.7 46218 Minh Coi Commune
Minh Coi Commune
Valley, slopes areas
05 Oct. 2013
Ha Hoa District
18 June. 2013
30 August. 2013
Xa Bang Gia, Ha Hoa 1 Bai ui 3600 28800 Bang Gia
Communce Mr. Thinh Chairman of Bang Gia Communce
Fish pond 12 Dec. 2010
Bang Gia Communce
12 Dec. 2010
4th Quarter 2013
2 Zone 11 3800 11400 Nguyen Van Quan
Zone 11, Bang Gia Communce
Fish pond 19 Nov. 2010
Bang Gia Communce
19 Nov. 2010
4th Quarter 2013
Xa Vo Tranh, Ha Hoa 1 Cap Tien,
Zone 6, Vo Tranh
1200 3600 Tran Thien Le Zone 6, Cap Tien, Vo Tranh Communce
Fish pond 10 January, 2011
Vo Tranh Communce
10 January, 2011
1st Quarter 2014
2 Dong Mai, Zone 5
1500 6000 Vo Tranh Communce
Zone 5, Vo Tranh Communce
Fish pond 10 January, 2011
Vo Tranh Communce
10 January, 2011
4th Quarter 2013
Xa Hien Luong, Ha Hoa 1 Cutural
house 1620 3240 Mr Nguyen,
Chairman of Hien Luong Communce
Hien Luong Communce
Low elevation, flood area need to raise level
17 Dec. 2010
Hien Luong Communce
17 Dec. 2010
4th Quarter 2013
4th Quarter 2013
2 Zone 2 1200 1800 Mr Nguyen, Chairman of Hien Luong Communce
Hien Luong Communce
Low elevation, flood area need to raise level
17 Dec. 2010
Hien Luong Communce
17 Dec. 2010
4th Quarter 2013
4th Quarter 2013
3 Pond of 1200 2400 Mrs Hoan Zone 2, Hien Fish pond 17 Dec. Hien Luong 17 Dec. 4th Quarter 4th Quarter
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
148
Mrs Hoan, Zone 2
Luong Communce 2010 Communce 2010 2013 2013
4 Old brick production area
4000 6000 Dong Trua Au Co Cooperative
Excavated area for brick production needs to be recovered
17 Dec. 2010
Hien Luong Communce
17 Dec. 2010
4th Quarter 2013
4th Quarter 2013
Xa Quan Khe, Ha Hoa
1 Fish pond of Mr. Cuong’s house
690 1244 Nguyen Van Cuong
Zone 1, Quan Khe Communce, Ha Hoa
Fish pond, but not efficient
7 Oct. 2010
Quan Khe Communce
7 Oct. 2010
4th Quarter 2013
4th Quarter 2013
2 Fish pond of Mrs. Oanh’s house, Zone 1
900 2160 Do Thi Oanh Zone 1, Quan Khe Communce, Ha Hoa
Fish pond, but not efficient
7 Oct. 2010
Quan Khe Communce
7 Oct. 2010
4th Quarter 2013
4th Quarter 2013
3 Fish pond of Mr. Chau’s house
624 1560 Do Ngoc Chau Zone 3, Quan Khe Communce, Ha Hoa
Fish pond, but not efficient
7 Oct. 2010
Quan Khe Communce
7 Oct. 2010
4th Quarter 2013
4th Quarter 2013
4 Pond, Zone 1
5788 36000 Mr Doanh, Chairman of Quan Khe Communce
Quan Khe Communce
Fish pond, but not efficient
7 Oct. 2010
Quan Khe Communce
7 Oct. 2010
4th Quarter 2013
4th Quarter 2013
5 Dyke, Zone 1
400 23152 Mr Doanh, Chairman of Quan Khe Communce
Quan Khe Communce
Low elevation, flood area, can not cultivation
7 Oct. 2010
Quan Khe Communce
7 Oct. 2010
4th Quarter 2013
4th Quarter 2013
Xa Son Nga, huyen Cam Khe 1 Km 81+020 800 8000 Nguyen Van
Yen Zone 3, Son Nga Communce
Low elevation, need to raise level for cultivation
29 Dec. 2010
Son Nga Communce
29 Dec. 2010
4th Quarter 2013
4th Quarter 2013
2 Km 81+020 400 2400 Nguyen Minh Duc
Zone 3, Son Nga Communce
Low elevation, need to raise level for cultivation
29 Dec. 2010
Son Nga Communce
29 Dec. 2010
4th Quarter 2013
4th Quarter 2013
3 Km 81+080 240 960 Hoangf Van Ba Zone 3, Son Nga Low elevation, 29 Dec. Son Nga 29 Dec. 4th Quarter 4th Quarter
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
149
Communce need to raise level for cultivation
2010 Communce 2010 2013 2013
4 Km 80+800 2000 20000 Hoa Mai Company
Son Nga Communce
Backfill for brick production area
29 Dec. 2010
Son Nga Communce
29 Dec. 2010
4th Quarter 2013
4th Quarter 2013
Xa Phung Xa, huyen Cam Khe
1 Km 82+080 300 600 Nguyen Thi Thung
Zone 2, Phung Xa Communce
Pond, and low area, need to
28 Dec. 2010
Phung Xa Communce
28 Dec. 2010
4th Quarter 2013
4th Quarter 2013
2 Km 82+100 2200 8800 M. Toa, Vice Chairman of Phung Xa Communce
Phung Xa Communce
Fill for stadium of the communce
28 Dec. 2010
Phung Xa Communce
28 Dec. 2010
4th Quarter 2013
4th Quarter 2013
Xa Tuy Loc, huyen Cam Khe
1 Km 85+500 2,424 9,396 Nguyen Van Hong
Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district
Pond 19 Dec. 2012
Tuy Loc Communce
1 Nov 2012
5 Feb 2013
2 Km 85+600 404
1,568 Nguyen Van Hong
Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district
Houses’s garden 19 Dec. 2012
Tuy Loc Communce
20 Dec 2012
5 Feb 2013
3 Km 85+550 1934
7500 Nguyen Van Hong
Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district
Pond 19 Dec. 2012
Tuy Loc Communce
20 Dec 2012
5 Feb 2013
4 Km 85+480 3112
12064 Nguyen Van Hong
Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district
Pond 19 Dec. 2012
Tuy Loc Communce
1 Nov 2012
5 Feb 2013
5 Km 85+460 851
3300 Nguyen Van Hong
Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district
Houses’s garden 19 Dec. 2012
Tuy Loc Communce
20 Dec 2012
5 Feb 2013
Xa Tuy Loc, huyen Cam Khe
1 Km80+000-Km82+500
4.517 100.000 Truong Xuan Co., Ltd.
Yen Lap commune, Cam
Emty land for storing of brick.
12/04/2013
Cam Khe district
April 2013
Dec 2013 Dec 2013
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
150
Khe district, Phu Tho province
BATCHING PLANTS
Package / SD No.
Location Appropriatesettling pond
Noise and dust measure
s
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A4/CBP1
Ha Hoa Bridge Yes Yes Bang Gia Communce
Mr. Long Chairman of Bang Gia Communce
Pending 1 Jan. 2012
Bang Gia Communce
1 Jan. 2012
1 Jan. 2016
A4/CBP2
Zone 4, Minh Coi commune, Ha Hoa district
Yes Yes Ho Van Thai 01696.643.932 farm land 14 Dec 2012
Minh Coi commune certified
1st Quarter 2012
4th Quarter 2013
4th Quarter 2013
Nguyen Tien Loi
01686.352.890 farm land 14 Dec 2012
Minh Coi commune certified
1st Quarter 2012
4th Quarter 2013
4th Quarter 2013
Nguyen Tuan Hong
0975.247.493 farm land 14 Dec 2012
Minh Coi commune certified
1st Quarter 2012
4th Quarter 2013
4th Quarter 2013
Nguyen Xuan Liem
01689.338.258 farm land 14 Dec 2012
Minh Coi commune certified
1st Quarter 2012
4th Quarter 2013
4th Quarter 2013
Phung Duc Thu
01275.168.096 farm land 14 Dec 2012
Minh Coi commune certified
1st Quarter 2012
4th Quarter 2013
4th Quarter 2013
Tran Van Nhan
0210.6291.937 farm land 14 Dec 2012
Minh Coi commune certified
1st Quarter 2012
4th Quarter 2013
4th Quarter 2013
Nguyen Hong Phuong
01678.814.448 farm land 14 Dec 2012
Minh Coi commune certified
1st Quarter 2012
4th Quarter 2013
4th Quarter 2013
Nguyen Van Sy
01687.147.867 farm land 14 Dec 2012
Minh Coi commune certified
1st Quarter 2012
4th Quarter 2013
4th Quarter 2013
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
151
Package A5
BATCHING PLANTS
Package / SD No.
Location Appropriate
settling pond
Noise and dust
measures
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A5/CBP1 Km 124+000 Yes No Song Hong Concrete JSC
Tran Yen district, Yen Bai province
Side Cut of idled land
31/10/201 Tran Yen GOV
17/9/2011
A5/CBP2 Km 136+000 Yes No Licogi 15 Van Yen
district, Yen Bai province
grass land 31/10/201
1 Van Yen GOV
4/12/2011
A5/CBP3 Km 145+200 Yes No Thanh Thu-Bao Tin
Van Yen district, Yen Bai province
idled grass land
27/6/2011 Van Yen GOV
10/12/2011
A5/CBP dtx KCN Dam Hong Yes No
Dong Tam Xanh Investment and Construction JSC
Van Yen district, Yen Bai province
commercial lot
26/1/2011 Van Yen GOV
30/7/2011
A5/CBP 4 Km145+100 Yes No Trancosin Van Yen
district, Yen Bai province
commercial lot
6/10/2012 Van Yen GOV
12/11/2012
A5/CBP 5 Km122+000 Yes No Licogi 13 Tran Yen
district, Yen Bai province
commercial lot
10/6/2013 Tran Yen GOV
6/5/2013
A5/ACBP1 Km142 Yes No 123 company
Van Yen district, Yen Bai province
Private land 1/10/2013 Van Yen GOV
6/11/2013
A5/ACBP2 Km119 Yes No
Asphalt concrete batching plant Km119
Tran Yen district, Yen Bai province
Private land 11/12/201
3 Tran Yen GOV
14/1/2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
152
BATCHING PLANTS
Package / SD No.
Location Appropriate
settling pond
Noise and dust
measures
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A5/ACBP3 Km135+700 Yes No
Asphalt concrete batching plant Km135
Tran Yen district, Yen Bai province
Disposal areas Km135
3/1/2014 Tran Yen GOV
15/2/2014
A5/ACBP4 Km117 No No
Asphalt concrete batching plant Km117
Tran Yen district, Yen Bai province
Service area Km117
10/1/2014 Tran Yen GOV
2/2/2014
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A5/SD1
Km111+740, Minh Quan commune, Tran Yen district, Yen Bai province
4094 14201 Song Da Co., Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 3-Oct-2012 3-Oct-2012
A5/SD2
Km111+680, Minh Quan commune, Tran Yen district, Yen Bai province
16580 59245 Song Da Co., Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 3-Oct-2012 3-Oct-2012
A5/SD3
Km113+100, Minh Quan commune, Tran Yen district, Yen Bai province
4427 29358 Song Da Co., Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 3-Oct-2012 3-Oct-2012
A5/SD4
Km112+200, Minh Quan commune, Tran Yen district, Yen Bai province
9600 43790 Song Da Co., Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 3-Oct-2012 3-Oct-2012
A5/SD5 Km112+600, Bao 19370 60750 Song Da Bao Hung Wild land 17-Sep-2012 3-Oct-2012 3-Oct-2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
153
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
Hung commune, Tran Yen district, Yen Bai province
Co., Ltd commune, Tran Yen district, Yen
Bai province
A5/SD6
Km116+480, Bao Hung commune, Tran Yen district, Yen Bai province
1940 12731 Song Da Co., Ltd
Bao Hung commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 3-Oct-2012 3-Oct-2012
A5/SD7
Km125+300, Minh Tien commune, Tran Yen district, Yen Bai province
3566 8273 Licogi 15 Co., Ltd
Minh Tien commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 3-Oct-2012 3-Oct-2012
A5/SD8
Km118+755, Bao Hung commune, Tran Yen district, Yen Bai province
560 28528 Licogi 13 Co., Ltd
Bao Hung commune, Tran Yen district, Yen
Bai province
Wild land 9-Oct-2012 27-Oct-2012
27-Oct-2012
A5/SD9
Km119+6800, Hop Minh commune, Tran Yen district, Yen Bai province
1560 43759 Licogi 13 Co., Ltd
Bao Hung commune, Tran Yen district, Yen
Bai province
Wild land 9-Oct-2012 27-Oct-2012
27-Oct-2012
A5/SD10
Km120+180, Hop Minh commune, Tran Yen district, Yen Bai province
64699 Licogi 13 Co., Ltd
Bao Hung commune, Tran Yen district, Yen
Bai province
Wild land 9-Oct-2012 27-Oct-2012
27-Oct-2012
A5/SD11
Km126+620, Y Kan commune, Tran Yen district, Yen Bai province,
4721 Licogi 15 Co. Ltd
Y Kan commune, Tran Yen district, Yen
Bai province,
Private land
17-Sep-2012 15-Oct-2012
15-Oct-2012
A5/SD12
Km126+750, Y Kan commune, Tran Yen district, Yen Bai province
2448 Licogi 15 Co. Ltd
Y Kan commune, Tran Yen district, Yen
Bai province,
Private land
17-Sep-2012 15-Oct-2012
15-Oct-2012
A5/SD13 Km129+300, Y Kan commune, Tran Yen district, Yen Bai
2427 Licogi 15 Co. Ltd
Y Kan commune, Tran Yen district, Yen
Private land
17-Sep-2012 15-Oct-2012
15-Oct-2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
154
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
province Bai province,
A5/SD14
Km130+620, Y Kan commune, Tran Yen district, Yen Bai province
2238 11700 Licogi 15 Co. Ltd
Y Kan commune, Tran Yen district, Yen
Bai province,
Private land
17-Sep-2012 15-Oct-2012
15-Oct-2012
A5/SD15
Km131+840, Quy Mong commune, Tran Yen district, Yen Bai province
2158 28167 Licogi 15 Co. Ltd
Quy Mong commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 24-Oct-2012
24-Oct-2012
A5/SD16
Km132+440, Quy Mong commune, Tran Yen district, Yen Bai province
2465 19720 Licogi 15 Co. Ltd
Quy Mong commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 2-Nov-2012
2-Nov-2012
A5/SD17
Km133+680, Quy Mong commune, Tran Yen district, Yen Bai province
1875 18750 Licogi 15 Co. Ltd
Quy Mong commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 2-Nov-2012
2-Nov-2012
A5/SD18
Km136+320, Quy Mong commune, Tran Yen district, Yen Bai province
2175 32190 Licogi 15 Co. Ltd
Quy Mong commune, Tran Yen district, Yen
Bai province
Wild land 27-Aug-2012 9-Sep-2012
9-Sep-2012
A5/SD19
Km138+000, Hoang Thang commune, Tran Yen district, Yen Bai province
6003 Licogi 15 Co. Ltd
Quy Mong commune, Tran Yen district, Yen
Bai province
Wild land 27-Aug-2012 9-Sep-2012
9-Sep-2012
A5/SD20
Km136+750, Quy Mong commune, Tran Yen district, Yen Bai province
1980 8329 Licogi 15 Co. Ltd
Quy Mong commune, Tran Yen district, Yen
Bai province
Wild land 27-Aug-2012 9-Sep-2012
9-Sep-2012
A5/SD21
Km137+420, Hoang Thang commune, Tran Yen district, Yen Bai province
5437 45891 Licogi 15 Co. Ltd
Hoang Thang commune, Tran Yen district, Yen
Bai province
Private land
27-Aug-2012 9-Sep-2012
9-Sep-2012
A5/SD22 Km137+980, Hoang 1244 5980 Trancosin Hoang Thang Private 27-Aug-2012 9-Sep- 9-Sep-
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
155
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
Thang commune, Tran Yen district, Yen Bai province
Co. Ltd commune, Tran Yen district, Yen
Bai province
land 2012 2012
A5/SD23
Km140+140, Xuan Ai commune, Tran Yen district, Yen Bai province
13940 Trancosin
Co. Ltd
Xuan Ai commune, Tran Yen district, Yen
Bai province
Private land
27-Aug-2012 9-Sep-2012
9-Sep-2012
A5/SD24
Km141+160, Xuan Ai commune, Tran Yen district, Yen Bai province
11681 Trancosin
Co. Ltd
Xuan Ai commune, Tran Yen district, Yen
Bai province
Private land
27-Aug-2012 20-Sep-
2012 20-Sep-
2012
A5/SD25
Km141+240, Xuan Ai commune, Tran Yen district, Yen Bai province
3599 Trancosin
Co. Ltd
Xuan Ai commune, Tran Yen district, Yen
Bai province
Private land
27-Aug-2012 20-Sep-
2012 20-Sep-
2012
A5/SD26
Km140+520, Xuan Ai commune, Tran Yen district, Yen Bai province
6015 Trancosin
Co. Ltd
Xuan Ai commune, Tran Yen district, Yen
Bai province
Private land
27-Aug-2012 20-Sep-
2012 20-Sep-
2012
A5/SD27
Km140+860, Xuan Ai commune, Tran Yen district, Yen Bai province
15826 Trancosin
Co. Ltd
Xuan Ai commune, Tran Yen district, Yen
Bai province
Private land
27-Aug-2012 20-Sep-
2012 20-Sep-
2012
A5/SD28
Km145+000, Yen Hop Commune, Van Yen district, Yen Bai province
4500 26286 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
27-Aug-2012 20-Sep-
2012 20-Sep-
2012
A5/SD29
Km146+250, Yen Hop Commune, Van Yen district, Yen Bai province
3500 11584 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
27-Aug-2012 20-Sep-
2012 20-Sep-
2012
A5/SD30 Km146+720, Yen 1734 6937 Trancosin Yen Hop Private 27-Aug-2012 17-Sep- 17-Sep-
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
156
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
Hop Commune, Van Yen district, Yen Bai province
Co. Ltd Commune, Van Yen district,
Yen Bai province
land 2012 2012
A5/SD31
Km147+200, Yen Hop Commune, Van Yen district, Yen Bai province
1488 11583 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
27-Aug-2012 17-Sep-
2012 17-Sep-
2012
A5/SD32
Km148+300, Yen Hop commune, Tran Yen district, Yen Bai province
1023 15000 Trancosin
Co. Ltd
Yen Hop commune, Tran Yen district, Yen
Bai province
Private land
27-Aug-2012 17-Sep-
2012 17-Sep-
2012
A5/SD33
Km111+740, Minh Quan commune, Tran Yen district, Yen Bai province
2184 6282 Song Da 9 Co. Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
28-Nov-2012 15-Dec-
2012 15-Dec-
2012
A5/SD34
Km111+740, Minh Quan commune, Tran Yen district, Yen Bai province
1280 7919 Song Da 9 Co. Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Wild land 28-Nov-2012 15-Dec-
2012 15-Dec-
2012
A5/SD35
Km111+680, Minh Quan commune, Tran Yen district, Yen Bai province
2677 6150 Song Da 9 Co. Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
28-Nov-2012 15-Dec-
2012 15-Dec-
2012
A5/SD36
Km111+680, Minh Quan commune, Tran Yen district, Yen Bai province
4603 5000 Song Da 9 Co. Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Wild land 28-Nov-2012 15-Dec-
2012 15-Dec-
2012
A5/SD37
Km111+800, Minh Quan commune, Tran Yen district, Yen Bai province
9300 48095 Song Da 9 Co. Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
28-Nov-2012 22-Dec-
2012 22-Dec-
2012
A5/SD38 Km110+100, Minh 9600 43790 Song Da Minh Quan Private 28-Nov-2012 22-Dec- 22-Dec-
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
157
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
Quan commune, Tran Yen district, Yen Bai province
9 Co. Ltd commune, Tran Yen district, Yen
Bai province
land 2012 2012
A5/SD39
Km110+340, Minh Quan commune, Tran Yen district, Yen Bai province
330 1650 Song Da 9 Co. Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
28-Nov-2012 22-Dec-
2012 22-Dec-
2012
A5/SD40
Km110+360, Minh Quan commune, Tran Yen district, Yen Bai province
7070 29100 Song Da 9 Co. Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
28-Nov-2012 22-Dec-
2012 22-Dec-
2012
A5/SD41
Km111+670, Minh Quan commune, Tran Yen district, Yen Bai province
12000 30000 Song Da 9 Co. Ltd
Minh Quan commune, Tran Yen district, Yen
Bai province
Private land
28-Nov-2012 22-Dec-
2012 22-Dec-
2012
A5/SD42
Km148+300, Yen Hop Commune, Van Yen district, Yen Bai province
150000 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
17-Dec-2012 15-Jan-
2013 15-Jan-
2013
A5/SD43
Km146+250, Yen Hop Commune, Van Yen district, Yen Bai province
11584 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
17-Dec-2012 15-Jan-
2013 15-Jan-
2013
A5/SD44
Km145+000, Yen Hop Commune, Van Yen district, Yen Bai province
26286 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
17-Dec-2012 15-Jan-
2013 15-Jan-
2013
A5/SD45
Km126+900, Y Kan commune, Tran Yen district, Yen Bai province
16084 Trancosin
Co. Ltd
Y Kan commune, Tran Yen district, Yen
Bai province
Private land
17-Dec-2012 15-Jan-
2013 15-Jan-
2013
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
158
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A5/SD46
Km127+000, Y Kan commune, Tran Yen district, Yen Bai province
4224
Keangnam
Contractor
Y Kan commune, Tran Yen district, Yen
Bai province
Wild land 4-Feb-2013 28-Mar-
2013 28-Mar-
2013
A5/SD47
Km127+000, Y Kan commune, Tran Yen district, Yen Bai province
5779
Keangnam
Contractor
Y Kan commune, Tran Yen district, Yen
Bai province
Wild land 4-Feb-2013 28-Mar-
2013 28-Mar-
2013
A5/SD48
Km120+200, Hop Minh commune, Tran Yen district, Yen Bai province
7067
Keangnam
Contractor
Hop Minh commune, Tran Yen district, Yen
Bai province
Private land
4-Feb-2013 28-Mar-
2013 28-Mar-
2013
A5/SD49
Km122+100, Hop Minh commune, Tran Yen district, Yen Bai province
37515 Hoang An
Co. Ltd
Hop Minh commune, Tran Yen district, Yen
Bai province
Wild land 4-Feb-2013 28-Mar-
2013 28-Mar-
2013
A5/SD50
Km128+800, Y Kan commune, Tran Yen district, Yen Bai province
2558 Hoang An
Co. Ltd
Y Kan commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 3-Nov-2012
3-Nov-2012
A5/SD51
Km129+590, Y Kan commune, Tran Yen district, Yen Bai province
2784 Hoang An
Co. Ltd
Y Kan commune, Tran Yen district, Yen
Bai province
Private land
17-Sep-2012 3-Nov-2012
3-Nov-2012
A5/SD52
Km126+000, Y Kan commune, Tran Yen district, Yen Bai province
392
Keangnam
Contractor
Y Kan commune, Tran Yen district, Yen
Bai province
Private land
5-Feb-2013 29-Mar-
2013 29-Mar-
2013
A5/SD53
Km125+950, Y Kan commune, Tran Yen district, Yen Bai province
880
Keangnam
Contractor
Y Kan commune, Tran Yen district, Yen
Bai province
Private land
5-Feb-2013 26-Feb-
2013 26-Feb-
2013
A5/SD54 Km125+600, Y Kan commune, Tran Yen
2919 Keangna
m Y Kan
commune, Tran Private
land 5-Feb-2013
26-Feb-2013
26-Feb-2013
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
159
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
district, Yen Bai province
Contractor
Yen district, Yen Bai province
A5/SD55
Km125+500, Y Kan commune, Tran Yen district, Yen Bai province
987
Keangnam
Contractor
Y Kan commune, Tran Yen district, Yen
Bai province
Private land
5-Feb-2013 26-Feb-
2013 26-Feb-
2013
A5/SD56
Km125+780. Y Kan commune, Tran Yen district, Yen Bai province
2095
Keangnam
Contractor
Y Kan commune, Tran Yen district, Yen
Bai province
Private land
5-Feb-2013 26-Feb-
2013 26-Feb-
2013
A5/SD57
Km125+700, Y Kan commune, Tran Yen district, Yen Bai province
378
Keangnam
Contractor
Y Kan commune, Tran Yen district, Yen
Bai province
Private land
5-Feb-2013 26-Feb-
2013 26-Feb-
2013
A5/SD58
Km125+700, Y Kan commune, Tran Yen district, Yen Bai province
622
Keangnam
Contractor
Y Kan commune, Tran Yen district, Yen
Bai province
Private land
5-Feb-2013 26-Feb-
2013 26-Feb-
2013
A5/SD59
Km145+500, Yen Hop Commune, Van Yen district, Yen Bai province
809 2000 Song Da 9 Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
18-Apr-2013 5-May-2013
5-May-2013
A5/SD60
Km147+680, Yen Hop Commune, Van Yen district, Yen Bai province
2000 6000 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
18-Apr-2013 5-May-2013
5-May-2013
A5/SD61
Km148+200, Yen Hop Commune, Van Yen district, Yen Bai province
20000 106000 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Wild land 18-Apr-2013 5-May-2013
5-May-2013
A5/SD62 Km149+030, Yen 1800 4000 Trancosin Yen Hop Private 18-Apr-2013 5-May- 5-May-
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
160
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
Hop Commune, Van Yen district, Yen Bai province
Co. Ltd Commune, Van Yen district,
Yen Bai province
land 2013 2013
A5/SD63
Km146+700, Yen Hop Commune, Van Yen district, Yen Bai province
1992 50000 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Wild land 2-Nov-2013 18-Dec-
2013 18-Dec-
2013
A5/SD64
Km148+000, Yen Hop Commune, Van Yen district, Yen Bai province
2650 105000 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
2-Nov-2013 18-Dec-
2013 18-Dec-
2013
A5/SD65
Km148+500, Yen Hop Commune, Van Yen district, Yen Bai province
2929 45000 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Wild land 2-Nov-2013 18-Dec-
2013 18-Dec-
2013
A5/SD66
Km148+900, Yen Hop Commune, Van Yen district, Yen Bai province
2930 12000 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Wild land 2-Nov-2013 18-Dec-
2013 18-Dec-
2013
A5/SD67
Km149+675, Yen Hop Commune, Van Yen district, Yen Bai province
991 10000 Trancosin
Co. Ltd
Yen Hop Commune, Van
Yen district, Yen Bai province
Private land
2-Nov-2013 18-Dec-
2013 18-Dec-
2013
BORROW PITS
Package / Location Approved Approved Ownershipa Prior Land Approval Operation Schedule
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
161
Borrow Pit No.
Area (m2) Volume(m3)
Name Contact Info Useb
Date Agencyc Start Estimated
Completion Actual
Completion A5/BP1 Km111+170 120,000 Song Da 9
sub-contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP2 Km111+540 130,000 Song Da 9 sub-contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP3 Km116+600 33,000 Song Da 9 sub-contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP4 Km117+120 37,000 Licogi 13 sub-contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP5 Km117+400 15,000 Licogi 13 sub-contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP6 Km118+100 20,000 Licogi 13 sub-contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP7 Km120+340 10,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP8 Km120+860 30,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP9 Km121+180 40,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP10 Km123+760 20,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP11 Km124+600 80,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP12 Km125+460 35,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
162
BORROW PITS
Package / Borrow Pit No.
Location Approved Area (m2)
Approved Volume
(m3)
Ownershipa Prior Land
Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated
Completion Actual
Completion A5/BP13 Km125+700 25,025 Keangnam
Contractor Tran Yen
district, Yen Bai province
Mountain Tran Yen GOV
A5/BP14 Km125+720 30,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP15 Km125+880 100,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP16 Km129+440 130,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP17 Km129+240 70,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
A5/BP18 Km129+160 50,000 Keangnam Contractor
Tran Yen district, Yen Bai province
Mountain Tran Yen GOV
Package A6
BATCHING PLANTS
Package A6 / SD No.
Location Appropriate
settling pond
Noise and dust
measures
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A6/CBP1 Km 163 Yes No Vinasan Van Yen
district, Yen Bai province
idled grass land
10-Jun-2010
Van Yen GOV
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
163
BATCHING PLANTS
Package A6 / SD No.
Location Appropriate
settling pond
Noise and dust
measures
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A6/CBP2 Km 165 Yes No Whitestone Vina
Van Yen district, Yen Bai province
idled grass land
Van Yen GOV
A6/CBP3 Km 180 Yes No Whitestone Vina
Van Yen district, Yen Bai province
idled grass land
29-Sep-2010
Van Yen GOV
A6/CBP4 Km 185 Yes No Whitestone Vina
Van Yen district, Yen Bai province
Side Cut of idled land
26-Aug-2011
Van Yen GOV
A6/ACBP1 Km 171 Yes No
Asphalt Concrete Batching Plant Km171
Van Yen district, Yen Bai province
Service area of Package A6
2-Oct-2011
Van Yen GOV
A6/ACBP2 Km 180 Yes No
Asphalt Concrete Batching Plant Km180
Van Yen district, Yen Bai province
idled grass land 15-Oct-
2011 Van Yen GOV
A6/ACBP3 Km 163 Yes No
Asphalt Concrete Batching Plant Km163
Van Yen district, Yen Bai province
idled grass land 1-Jan-
2014 Van Yen GOV
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End
A6/SD1
Km152+600, Tan Hop commune, Van Yen district, Yen Bai province
2,838 54,528 Quang
Trung., Ltd
Tan Hop commune, Van Yen
district, Yen
Private land 27-Mar-
2012 11-April-
2012 16-April-
2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
164
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End Bai province
A6/SD2
Km152+900, Tan Hop commune, Van Yen district, Yen Bai province
985 17971 Quang Trung., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 27-Mar-
12 11-April-
2012 16-April-
2012
A6/SD3
Km155, Tan Hop commune, Van Yen district, Yen Bai province
1500 6000 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Garden of Mr. Hoa
19-April-2012
26-April-2012
26-April-2012
A6/SD4
Km155, Tan Hop commune, Van Yen district, Yen Bai province
3000 12000 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Garden of Mr. Dung
19-April-2012
26-April-2012
26-April-2012
A6/SD5
Km155, Tan Hop commune, Van Yen district, Yen Bai province
3000 12000 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Garden of Mr. Thang
19-April-2012
26-April-2012
26-April-2012
A6/SD6
Km155+700, Tan Hop commune, Van Yen district, Yen Bai province
1200 4800 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Garden of Mr. Thuc
19-April-2012
26-April-2012
26-April-2012
A6/SD7
Km153+700, Tan Hop commune, Van Yen district, Yen Bai province
3000 12000 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 19-April-
2012 26-April-
2012 26-April-
2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
165
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End
A6/SD8
Km153+300, Tan Hop commune, Van Yen district, Yen Bai province
28766 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 24-May-
2012 12-Jun-
2012 12-Jun-
2012
A6/SD9
Km154+000, Tan Hop commune, Van Yen district, Yen Bai province
3018 15303 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 27-Dec-
2012 18-Jan-
2013 18-Jan-
2013
A6/SD10
Km153+520, Tan Hop commune, Van Yen district, Yen Bai province
3380 20785 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 27-Dec-
2012 18-Jan-
2013 18-Jan-
2013
A6/SD11
Km155+400, Tan Hop commune, Van Yen district, Yen Bai province
480 3638 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 9-Oct-2012
16-Oct-2012
16-Oct-2012
A6/SD12
Km155+600, Tan Hop commune, Van Yen district, Yen Bai province
3161 18644 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Wild land 28-Jan-
2013 5-Feb-2013
5-Feb-2013
A6/SD13
Km155+500, Tan Hop commune, Van Yen district, Yen Bai province
448 1413 Truong Loc.,
Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Wild land 28-Jan-
2013 5-Feb-2013
5-Feb-2013
A6/SD14 Km155+700, Tan 5063 100848 Truong Loc., Tan Hop Private land 28-May- 11-Jun- 11-Jun-
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
166
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End Hop commune, Van Yen district, Yen Bai province
Ltd commune, Van Yen
district, Yen Bai province
2013 2013 2013
A6/SD15
Km155+500, Tan Hop commune, Van Yen district, Yen Bai province
2077 9347 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Garden of Mr. Hieu
19-Apr-2012
26-Apr-2012
26-Apr-2012
A6/SD16 Tan Hop commune, Van Yen district, Yen Bai province
2171 9770 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land of Tan Hop’s
primary school
19-Apr-2012
26-Apr-2012
26-Apr-2012
A6/SD17 Tan Hop commune, Van Yen district, Yen Bai province
6466 29097 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land of Tan Hop’s
children school
19-Apr-2012
26-Apr-2012
26-Apr-2012
A6/SD18 Tan Hop commune, Van Yen district, Yen Bai province
7526 33867 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Garden of Mr. Hien
19-Apr-2012
26-Apr-2012
26-Apr-2012
A6/SD19 Tan Hop commune, Van Yen district, Yen Bai province
3422 15399 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Garden of Mr. Thong
19-Apr-2012
26-Apr-2012
26-Apr-2012
A6/SD20 Tan Hop commune, Van Yen district,
6877 60947 Licogi., Ltd Tan Hop
commune, Van Yen
Garden of Mr. Huong
19-Apr-2012
26-Apr-2012
26-Apr-2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
167
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End Yen Bai province district, Yen
Bai province
A6/SD21 Tan Hop commune, Van Yen district, Yen Bai province
3752 18193 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 5-Jun-2012
16-Jun-2012
16-Jun-2012
A6/SD22 Tan Hop commune, Van Yen district, Yen Bai province
4163 30572 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 5-Jun-2012
16-Jun-2012
16-Jun-2012
A6/SD23 Tan Hop commune, Van Yen district, Yen Bai province
2383 22253 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 11-Jul-2012
16-Jul-2012
16-Jul-2012
A6/SD24 Tan Hop commune, Van Yen district, Yen Bai province
18412 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 24-Aug-
2012 7-Sep-2012
7-Sep-2012
A6/SD25 Tan Hop commune, Van Yen district, Yen Bai province
5502 104470 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 24-Aug-
2012 7-Sep-2012
7-Sep-2012
A6/SD26 Tan Hop commune, Van Yen district, Yen Bai province
23043 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen
Private land 24-May-
2012 21-Jun-
2012 21-Jun-
2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
168
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End Bai province
A6/SD27 Tan Hop commune, Van Yen district, Yen Bai province
22675 Licogi., Ltd
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 24-May-
2012 21-Jun-
2012 21-Jun-
2012
A6/SD28
Km166+600, Dong An commune, Van Yen district, Yen Bai province
3258 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Wild land 13-Aug-
2010 16-Aug-
2010 16-Aug-
2010
A6/SD29
Km167+300, Dong An commune, Van Yen district, Yen Bai province
5380 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Wild land 13-Aug-
2010 16-Aug-
2010 16-Aug-
2010
A6/SD30
Km168+700, Dong An commune, Van Yen district, Yen Bai province
24318 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Private land 13-Aug-
2010 16-Aug-
2010 16-Aug-
2010
A6/SD31
Km168+000, Dong An commune, Van Yen district, Yen Bai province
11882 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Wild land 13-Aug-
2010 16-Aug-
2010 16-Aug-
2010
A6/SD32
Km166+050, Dong An commune, Van Yen district, Yen Bai province
2819 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Wild land 13-Aug-
2010 16-Aug-
2010 16-Aug-
2010
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
169
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End
A6/SD33
Km165+400, Dong An commune, Van Yen district, Yen Bai province
1317 6959 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Private land 1-Jun-2012
12-Jun-2012
12-Jun-2012
A6/SD34
Km165+400, Dong An commune, Van Yen district, Yen Bai province
51127 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Private land 1-Jun-2012
12-Jun-2012
12-Jun-2012
A6/SD35
Km166+487, Dong An commune, Van Yen district, Yen Bai province
20083 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Private land 1-Jun-2012
12-Jun-2012
12-Jun-2012
A6/SD36
Km166+688, Dong An commune, Van Yen district, Yen Bai province
1594 7680 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Private land 1-Jun-2012
12-Jun-2012
12-Jun-2012
A6/SD37
Km166+520, Dong An commune, Van Yen district, Yen Bai province
2571 15058 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Private land 2-Sep-2013
17-Sep-2013
17-Sep-2013
A6/SD38
Km165+360, Dong An commune, Van Yen district, Yen Bai province
2155 3597 An Sinh., Ltd
Dong An commune, Van Yen
district, Yen Bai province
Private land 2-Sep-2013
17-Sep-2013
17-Sep-2013
A6/SD39 Km175+240, Chau 965 3859 Weicovina., Chau Que Ha Private land 13-Aug- 16-Aug- 16-Aug-
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
170
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End Que Ha commune, Van Yen district, Yen Bai province
Ltd commune, Van Yen
district, Yen Bai province
2010 2010 2010
A6/SD40
Km175+460, Chau Que Ha commune, Van Yen district, Yen Bai province
1090 4361 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 13-Aug-
2010 16-Aug-
2010 16-Aug-
2010
A6/SD41
Km175+720, Chau Que Ha commune, Van Yen district, Yen Bai province
2515 10059 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 13-Aug-
2010 16-Aug-
2010 16-Aug-
2010
A6/SD42
Km176+200, Chau Que Ha commune, Van Yen district, Yen Bai province
2383 9534 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 13-Aug-
2010 16-Aug-
2010 16-Aug-
2010
A6/SD43
Km176+560, Chau Que Ha commune, Van Yen district, Yen Bai province
6939 27756 Anh Cuong.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 13-Aug-
2010 16-Aug-
2010 16-Aug-
2010
A6/SD44
Km176+500, Chau Que Ha commune, Van Yen district, Yen Bai province
3333 29105 Anh Cuong.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 19-Mar-
2012 24-Mar-
2012 24-Mar-
2012
A6/SD45 Km177+500, Chau Que Ha commune, Van Yen district,
1054 9329 Anh Cuong.,
Ltd
Chau Que Ha commune, Van Yen
Private land 19-Mar-
2012 24-Mar-
2012 24-Mar-
2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
171
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End Yen Bai province district, Yen
Bai province
A6/SD46
Km177+200, Chau Que Ha commune, Van Yen district, Yen Bai province
2422 44043 Anh Cuong.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 19-Mar-
2012 24-Mar-
2012 24-Mar-
2012
A6/SD47
Km177+210, Chau Que Ha commune, Van Yen district, Yen Bai province
1071 17617 Anh Cuong.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 19-Mar-
2012 24-Mar-
2012 24-Mar-
2012
A6/SD48
Km171+200, Chau Que Ha commune, Van Yen district, Yen Bai province
932 16888 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 19-Mar-
2012 24-Mar-
2012 24-Mar-
2012
A6/SD49
Chau Que Ha commune, Van Yen district, Yen Bai province
1211 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 20-Oct-2012
31-Oct-2012
31-Oct-2012
A6/SD50
Chau Que Ha commune, Van Yen district, Yen Bai province
9781 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 20-Oct-2012
31-Oct-2012
31-Oct-2012
A6/SD51
Chau Que Ha commune, Van Yen district, Yen Bai province
17769 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen
Private land 20-Oct-2012
31-Oct-2012
31-Oct-2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
172
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End Bai province
A6/SD52
Km173+540, Chau Que Ha commune, Van Yen district, Yen Bai province
51276 Doosan
Contractor
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 20-Oct-2012
31-Oct-2012
31-Oct-2012
A6/SD53
Km173+540, Chau Que Ha commune, Van Yen district, Yen Bai province
121442 Doosan
Contractor
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 20-Oct-2012
31-Oct-2012
31-Oct-2012
A6/SD54
Km178+920, Chau Que Ha commune, Van Yen district, Yen Bai province
488 1220 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Garden of Mrs. Vach
20-Apr-2012
5-May-2012
5-May-2012
A6/SD55
Km179+040, Chau Que Ha commune, Van Yen district, Yen Bai province
1980 4950 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Garden of Mr. Khoa
20-Apr-2012
5-May-2012
5-May-2012
A6/SD56
Km179+040, Chau Que Ha commune, Van Yen district, Yen Bai province
2660 6650 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Garden of Mr. Thang
20-Apr-2012
5-May-2012
5-May-2012
A6/SD57
Km179+700, Chau Que Ha commune, Van Yen district, Yen Bai province
380 950 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Garden of Mr. Viet
20-Apr-2012
5-May-2012
5-May-2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
173
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End
A6/SD58
Km179+600, Chau Que Ha commune, Van Yen district, Yen Bai province
1275 3188 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Garden of Mr. Vien
20-Apr-2012
5-May-2012
5-May-2012
A6/SD59
Km181+500, Chau Que Ha commune, Van Yen district, Yen Bai province
7785 19463 Quang
Trung., Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Garden of Mr. Hanh
20-Apr-2012
5-May-2012
5-May-2012
A6/SD60
Km179+520, Chau Que Ha commune, Van Yen district, Yen Bai province
2922 7305 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Garden of Mr. Binh
20-Apr-2012
5-May-2012
5-May-2012
A6/SD61
Km177+200, Chau Que Ha commune, Van Yen district, Yen Bai province
6700 66997 Weicovina.,
Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Wild land 25-Oct-2012
12-Nov-2012
12-Nov-2012
A6/SD62
Chau Que Ha commune, Van Yen district, Yen Bai province
14941 Quang
Trung., Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 27-Feb-
2013 2-Apr-2013
2-Apr-2013
A6/SD63
Chau Que Ha commune, Van Yen district, Yen Bai province
29846 Quang
Trung., Ltd
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 27-Feb-
2013 2-Apr-2013
2-Apr-2013
A6/SD64 Chau Que Ha 42528 Quang Chau Que Ha Private land 27-Feb- 2-Apr-2013 2-Apr-
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
174
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End commune, Van Yen district, Yen Bai province
Trung., Ltd commune, Van Yen
district, Yen Bai province
2013 2013
A6/SD65
Km182+620, Chau Que Thuong commune, Van Yen district, Yen Bai province
3200 4000 Quang
Trung., Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 27-Feb-
2013 2-Apr-2013
2-Apr-2013
A6/SD66
Km184+900, Chau Que Thuong commune, Van Yen district, Yen Bai
27000 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 8-Sep-2010
16-Sep-2010
16-Sep-2010
A6/SD67
Km185+300, Chau Que Thuong commune, Van Yen district, Yen Bai
2700 39286 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 13-Mar-
2013 20-Mar-
2013 20-Mar-
2013
A6/SD68
Km185+300, Chau Que Thuong commune, Van Yen district, Yen Bai
5350 97066 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 24-Mar-
2013 3-May-2013
3-May-2013
A6/SD69
Km188+200, Chau Que Thuong commune, Van Yen district, Yen Bai
46690 162582 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
Private land 29-Dec-
2010 13-Jan-
2011 13-Jan-
2011
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
175
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End district, Yen Bai province
A6/SD70
Km190+110, Chau Que Thuong commune, Van Yen district, Yen Bai province
6910 17032 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Wild land 29-Dec-
2010 13-Jan-
2011 13-Jan-
2011
A6/SD71
Km187+300, Chau Que Thuong commune, Van Yen district, Yen Bai province
1102 15780 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Wild land 29-Dec-
2010 13-Jan-
2011 13-Jan-
2011
A6/SD72
Km187+900, Chau Que Thuong commune, Van Yen district, Yen Bai province
691 5404 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 29-Dec-
2010 13-Jan-
2011 13-Jan-
2011
A6/SD73
Km189+600, Chau Que Thuong commune, Van Yen district, Yen Bai province
1146 19898 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 29-Dec-
2010 13-Jan-
2011 13-Jan-
2011
A6/SD74
Km187+660, Chau Que Thuong commune, Van Yen district, Yen Bai province
2446 13684 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 14-Oct-2011
28-Nov-2011
28-Nov-2011
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
176
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End
A6/SD75
Km188+400, Chau Que Thuong commune, Van Yen district, Yen Bai province
995 5396 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 14-Oct-2011
28-Nov-2011
28-Nov-2011
A6/SD76
Km188+600, Chau Que Thuong commune, Van Yen district, Yen Bai province
1185 4387 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 14-Oct-2011
28-Nov-2011
28-Nov-2011
A6/SD77
Km189+600, Chau Que Thuong commune, Van Yen district, Yen Bai province
3586 14962 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Private land 14-Oct-2011
28-Nov-2011
28-Nov-2011
A6/SD78
Km190+140, Chau Que Thuong commune, Van Yen district, Yen Bai province
1075 18519 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Wild land 14-Oct-2011
28-Nov-2011
28-Nov-2011
A6/SD79
Km188+400, Chau Que Thuong commune, Van Yen district, Yen Bai province
2439 14962 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Wild land 14-Oct-2011
28-Nov-2011
28-Nov-2011
A6/SD80 Km188+500, Chau Que Thuong
1945 12833 Nghe An.,
Ltd Chau Que
Thuong Wild land
14-Oct-2011
28-Nov-2011
28-Nov-2011
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
177
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End commune, Van Yen district, Yen Bai province
commune, Van Yen
district, Yen Bai province
A6/SD81
Km189+200, Chau Que Thuong commune, Van Yen district, Yen Bai province
2148 18714 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Wild land 14-Oct-2011
28-Nov-2011
28-Nov-2011
A6/SD82
Km188+720, Chau Que Thuong commune, Van Yen district, Yen Bai province
58384 Nghe An.,
Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Wild land 11-Jan-
2013 20-Jan-
2013 20-Jan-
2013
A6/SD83
Km186+145, Chau Que Thuong commune, Van Yen district, Yen Bai province
7231 96970 Cavico., Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Wild land 26-Nov-
2010 15-Dec-
2010 15-Dec-
2010
A6/SD84
Km186, Chau Que Thuong commune, Van Yen district, Yen Bai province
19993 Cavico., Ltd
Chau Que Thuong
commune, Van Yen
district, Yen Bai province
Wild land 26-Nov-
2010 15-Dec-
2010 15-Dec-
2010
A6/SD85
Km173+300, Chau Que Ha commune, Van Yen district, Yen Bai province
65350 Doosan Contractor
Chau Que Ha commune, Van Yen
district, Yen
Wild land 25-Sep-2013
10-Oct-2013
25-Sep-2013
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
178
SPOILS DISPOSAL AREAS
Package SD No.
Location Approved
Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land
Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual
End Bai province
A6/SD86
Km156+100 – Km156+300, Tan Hop commune, Van Yen district, Yen Bai province
9506 Doosan Contractor
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 25-Sep-2013
10-Oct-2013
25-Sep-2013
A6/SD87
Km185+060, Chau Que Thuong commune, Van Yen district,
5400 32900 Doosan Contractor
Chau Que Thuong
commune, Van Yen district,
Wild land 22-Oct-13
25-Oct-2013
25-Sep-2013
A6/SD88
Km152+500 – Km152+700, Tan Hop commune, Van Yen district, Yen Bai province
6800 29240 Doosan Contractor
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 29-Oct-13
22-Nov-2013
22-Nov-2013
A6/SD89
Km152+830, Tan Hop commune, Van Yen district, Yen Bai province
15000 Doosan Contractor
Tan Hop commune, Van Yen
district, Yen Bai province
Private land 2-Nov-13 29-Nov-2013
29-Nov-2013
A6/SD90
Km173+540, Chau Que Ha commune, Van Yen district, Yen Bai province
21442 Van Phuc sub-contractor
Chau Que Ha commune, Van Yen
district, Yen Bai province
Private land 29-Oct-13
22-Nov-2013
22-Nov-2013
A6/SD91
Km173+800, Chau Que Ha commune, Van Yen district, Yen Bai province
28043 Doosan Contractor
Chau Que Ha commune, Van Yen
district, Yen Bai province
Wild land 22-Jan-14
14-Mar-2014
14-Mar-2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
179
Packages A7
BORROW PITS
Package /Borrow Pit No.
Location Approved Area (m2)
Approved Volume
(m3)
Ownershipa Prior Land Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated Completion
Actual Completion
A7/BP1 Km207- Km218+040
30.000 300.000m3 Cam4- Cam Con committee- Bao Yen district- Lao Cai Provice
Hill land 11/5/2011 DONRE OF Lao Cai Provice
30/5/2011 11/10/2011 30/10/2011
QUARRIES
Package /Quarry No.
Location Approved Area (m2)
Approved Volume
(m3)
Ownershipa Prior Land Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated Completion
Actual Completion
A7/Q1 No information has been provided
SPOILS DISPOSAL AREAS Package / SD No.
Location Approved Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A7/SD1 Km191+600 106.000 1.060.000 Tan An committee
Tan An- Van Ban- Lao Cai
idle farm lot
19/4/2010 Contact between the contractor and land owner with confirm of commune
30/4/2010 15/12/2010 30/11/2010
A7/SD2 Km195+800 103.000 1.030.000 Tan An committee
Tan An- Van Ban- Lao Cai
idle farm lot
19/4/2010 30/4/2010 15/12/2010 30/11/2010
A7/SD3 Km197+200 65.000 260.000 Tan An committee
Tan An- Van Ban- Lao Cai
idle farm lot
19/4/2010 30/4/2010 15/12/2010 30/11/2010
A7/SD4 Km198+400 8.000 120.000 Tan An Tan An- Van rice field 19/4/2010 30/4/2010 15/12/2010 30/11/2010
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
180
SPOILS DISPOSAL AREAS Package / SD No.
Location Approved Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
committee Ban- Lao Cai people’s committee
A7/SD5 Km203+440 10.000 70.000 Tran Van Bang
Khe U- Tan Thuong- Van Ban- Lao Cai
rice field 7/5/2010 30/5/2010 31/12/2011 20/10/2011
A7/SD6 Km203+440 30.000 210.000 Tran Van Ngoi
Khe U- Tan Thuong- Van Ban- Lao Cai
rice field 7/5/2010 30/5/2010 31/12/2011 25/11/2011
A7/SD7 Km206+500 8.000 40.000 Do Van Hanh
Ban Ly- Cam Con- Bao Yen- Lao Cai
acacia plantation
10/5/2010 25/5/2010 31/12/2011 20/8/2011
A7/SD8 Km205+000 10897.6 54488 Nguyen Van Dong
Ban Ly2- Cam Con- Bao Yen- Lao Cai
idle farm lot
19/5/2010 15/5/2010 31/12/2011 29/9/2011
A7/SD9 Km206+200 3772.3 18861.5 Ly Van Tu Ban Ly1- Cam Con- Bao Yen- Lao Cai
idle farm lot
19/5/2010 15/5/2010 31/12/2011 29/9/2011
A7/SD10 Km209+280 2.848.5 14.242.5 Nguyen Thi Linh
Bong 1- Cam Con- Bao Yen- Lao Cai
rice field 1/2/2012 15/2/2012
A7/SD11 Km210+360 3.044.6 21.312.2 Tran Van Su
Tan Tien- Cam Con- Bao Yen- LC
rice field 1/2/2012 15/2/2012 5/2012
A7/SD12 Km210+360 5.281.9 36.973.3 Hoang Van Chuc
rice field 1/2/2012 15/2/2012 5/2012
A7/SD13 Km210+360 2.703.8 18.926.6 Nguyen Thi Tam
rice field 1/2/2012 15/2/2012 5/2012
A7/SD14 Km210+380 3.735 26.145 Hoang Van Thong
rice field 1/2/2012 15/2/2012 5/2012
A7/SD15 Km210+380 1.592.1 11.144.7 Nguyen Van Hai
rice field 1/2/2012 15/2/2012 5/2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
181
SPOILS DISPOSAL AREAS Package / SD No.
Location Approved Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A7/SD16 Km210+400 1.800 10.800 Tran Van Be
rice field 1/2/2012 15/2/2012 5/2012
A7/SD17 Km216+260 2.010.3 12.061.8 Pham Van Thuy
Hong Cam- Cam Con- Bao Yen- LC
rice field 1/2/2012 15/2/2012 5/2012
A7/SD18 Km216+840 5.760.5 34.563 Vuong Thanh Hung
rice field 1/2/2012 15/2/2012 5/2012
A7/SD19 Km216+980 3.470.7 22.559.55 Pham Van Truong
rice field 1/2/2012 15/2/2012 5/2012
A7/SD20 Km217+960 1.549 10.068.5 Pham Van Minh
rice field 1/2/2012 15/2/2012 5/2012
A7/SD21 Km207+000 5.887.3 41.211.1 Vu Van Khac
Tan Thanh- Cam Con- Bao Yen- LC
rice field 1/2/2012 20/5/2012 6/2012
A7/SD22 Km209+820 2.282.5 15.977.5 Le Van Hung
Tan Tien- Cam Con- Bao Yen- LC
rice field 1/2/2012 20/5/2012 6/2012
A7/SD23 Km210+740 151.5 1.090.8 Trinh Thi Hien
Tan Tien- Cam Con- Bao Yen- LC
rice field 7/5/2012 20/5/2012 6/2012
A7/SD24 Km210+760 1.500 14.250 Cam Con committee
rice field 7/5/2012 20/5/2012 6/2012
A7/SD25 Km210+780 145.3 1.191.46 Dinh Thi Mui
rice field 7/5/2012 20/5/2012 6/2012
A7/SD26 Km210+800 1.390 8.618 Le Nguyen Hong
rice field 7/5/2012 20/5/2012 6/2012
A7/SD27 Km210+820 1.141 8.215.2 Tran Cu rice field 7/5/2012 20/5/2012 6/2012
A7/SD28 Km211+200 1.490 11.026 Lam Xuan Truong
Con2- Cam Con- Bao Yen-
rice field 7/5/2012 20/5/2012 6/2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
182
SPOILS DISPOSAL AREAS Package / SD No.
Location Approved Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
LC
A7/SD29 Km216+520 9.127 86.706.5 Pham Thi Cuong
Hong Cam- Cam Con- Bao Yen- LC
rice field 7/5/2012 20/5/2012 6/2012
A7/SD30 Km216+520 7.385 66.465 Vu Thi Huong
rice field 7/5/2012 20/5/2012 6/2012
A7/SD31 Km216+640 11.075 110.750 Pham Thi Lan
rice field 7/5/2012 20/5/2012 6/2012
A7/SD32 Km217+080 14.655 131.895 Le Van Hien
rice field 7/5/2012 20/5/2012 6/2012
A7/SD33 Km217+280 7.865 86.515 Tran Van Theo
rice field 7/5/2012 20/5/2012 6/2012
A7/SD34 Km189+700 15.555.56 140.000 Tran Van Thanh
Hamlet1- Que Thuong- Van Yen- Yen Bai
idle farm lot
20/10/2011 1/11/2011 25/3/2012
A7/SD35 Km191+350 15.000 120.000 Ta Dinh Hai
Xuan Sang1-Tan An- Van Ban- Lao Cai
idle farm lot
22/10/2011 15/11/2011 3/2012
A7/SD36 Km199+100 10.769.23 70.000 Ly Xuan Hinh
Cau Thin- Tan Thuong- Van Ban- Lao Cai
idle farm lot
21/10/2011 12/11/2011 3/2012
A7/SD37 Km189+700 15,555.56 140,000.00 Tran Van Thanh
Tan An- Van Ban- Lao Cai
abandoned 11/4/2013 These waste disposal have approved by Resource and Environme
15/6/2012 20/12/2012 31/12/2012
A7/SD38 Km191+350 8,000.00 60,000.00 Tran Van Nhi
Tan An- Van Ban- Lao Cai
idle farm lot
11/4/2013 15/6/2012 20/12/2012 31/12/2012
A7/SD39 Km191+350 6,875.00 55,000.00 Pham Van Thong
Tan An- Van Ban- Lao Cai
idle farm lot
11/4/2013 15/6/2012 20/12/2012 31/12/2012
A7/SD40 Km191+350 15,000.00 120,000.00 Ta Dinh Hai
Tan An- Van Ban- Lao Cai
idle farm lot
11/4/2013 15/6/2012 20/12/2012 31/12/2012
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
183
SPOILS DISPOSAL AREAS Package / SD No.
Location Approved Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A7/SD41 Km194+790 9,333.33 70,000.00 Dang Van Thong
Tan An- Van Ban- Lao Cai
abandoned 11/4/2013 nt Bureau of Van Ban district
15/6/2012 20/12/2012 31/12/2012
A7/SD42 Km195+700 70,000.00 490,000.00 Some ownership
Tan An- Van Ban- Lao Cai
abandoned 11/4/2013 15/6/2012 20/12/2012 31/12/2012
A7/SD43 Km199+100 10,769.23 70,000.00 Ly Xuan Hinh
Tan Thuong- Van Ban- Lao Cai
abandoned 11/4/2013 15/6/2012 20/12/2012 31/12/2012
A7/SD44 Km199-Km200 7,500.00 60,000.00 Nguyen Thi Bac
Tan Thuong- Van Ban- Lao Cai
abandoned 11/4/2013 15/6/2012 20/12/2012 31/12/2012
BATCHING PLANTS Package / SD No.
Location Appropriate settling pond
Noise and dust
measures
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A7/CBP1 Km191+353 Settling pond had provided
Noise and dust measures had support with plant
Khe Sang BCP
Xuan Sang2- Tan An commune - Van Ban District- Lao Cai
Abandoned 7/9/2012 Van Ban District people’s committee
18/3/2011 25/3/2013 December 2013
A7/CBP2 Km199+860 Settling pond had provided
Noise and dust measures had support with plant
Tan Thuong BCP
Khe Quat- Tan An commune- Van Ban District- Lao Cai
Abandoned 7/9/2012 Van Ban District people’s committee
14/11/2011 25/3/2013 March 2014
A7/CBP3 Km198+400 Settling pond had provided
Noise and dust measures
Xom Danh BCP
Ngam Thin- Tan Thuong commune - Van
rice field Van Ban District people’s
15/1/2011 25/3/2013 March 2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
184
BATCHING PLANTS Package / SD No.
Location Appropriate settling pond
Noise and dust
measures
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
had support with plant
Ban District- Lao Cai
committee
A7/CBP4 Km209+329 Settling pond had provided
Noise and dust measures had support with plant
Tan Tien BCP
Bong1- Cam Con commune - Bao Yen District- Lao Cai
Hill land Bao Yen District people’s committee
25/3/2011 25/3/2013 July 2013
A7/ABP1 Km195+800 Settling pond had provided
Noise and dust measures had support with plant
Trancosin ABP
Tan Son- Tan An- Van Ban- Lao Cai
Hill land 7/11/2012 Van Ban District people’s committee
15/11/2012 25/3/2013 March 2014
A7/ABP2 Km203+100 Settling pond had provided
Noise and dust measures had support with plant
Trico ABP Tan Thuong- Van Ban- Lao Cai
Hill land 11/10/2012 Van Ban District people’s committee
14/12/2012 25/3/2013 March 2014
Packages A8
BORROW PITSPackage /Borrow Pit No.
Location Approved Area (m2)
ApprovedVolume
(m3)
Ownershipa Prior Land Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated Completion
Actual Completion
A8/BP1 Km234- Km235 10,5ha= 500.000m3/y Hùng Thắng Hill land 10/01/2011 Lao Cai 31/01/2011 31/01/2012 12/2011
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
185
105.000 ear and Dong Cam- Gia Phu Committee- Bao Thang District- Lao Cai Provice
Province people’s committee
QUARRIESPackage /Quarry No.
Location Approved Area (m2)
ApprovedVolume
(m3)
Ownershipa Prior Land Useb
Approval Operation Schedule
Name Contact Info Date Agencyc Start Estimated Completion
Actual Completion
A8/Q1 38800 45.000m3/year Ban Cam quarry
Ban Cam committee- Bao Thang District- Lao Cai Provice
Hill land 7/4/2011 Lao Cai Province people’s committee
April-2011 December- 2015
March-2014
SPOILS DISPOSAL AREAS Package / SD No.
Location Approved Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A8/SD1 Km218+500 2.612 11.754 Tran Van Chac
An Thang- Son Ha- Bao Thang- Lao Cai
rice field 20/7/2010
Contact between the contractor and land owner with confirm of commune people’s committee
8/2010 11/2010
A8/SD2 Km222+500 952 1.904 Tran Hai Cuong
An Hong- Son Ha- Bao Thang- Lao Cai
rice field 20/7/2010 8/2010 11/2010
A8/SD3 Km223+050 1.386 3.465 Nguyen Thi Quy
rice field 20/7/2010 8/2010 11/2010
A8/SD4 Km234+860 10.000 120.000 Nguyen Van Duong
Tien Loi2- Xuan Giao- Bao Thang- Lao Cai
rice field 10/8/2010 8/2010 11/2010
A8/SD5 Km234+860 2.680 8.000 Pham Van Su
rice field 10/8/2010 8/2010 11/2010
A8/SD6 Km234+840 10.000 120.000 Nguyen Van Duong
rice field 10/8/2010 8/2010 11/2010
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
186
SPOILS DISPOSAL AREAS Package / SD No.
Location Approved Area (m2)
ApprovedCapacity
(m3)
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A8/SD7 Km237+580 730 1.900 Nguyen Thanh Luot
Phu Xuan- Gia Phu- Bao Thang- Lao Cai
rice field 20/6/2012 1/7/2010 11/2010
A8/SD8 Km237+195 652 2.000 Do The Huy
Son Ca- Gia Phu- Bao Thang- Lao Cai
rice field 20/6/2012 1/7/2010 11/2010
A8/SD9 Km237+160 360 1.200 Hoang Van Uyen
rice field 3/8/2010 15/8/2010 11/2010
A8/SD10 Km237+060 350 1.255 Pham Van Tho
rice field 20/7/2010 15/8/2010 11/2010
A8/SD11 Km237+060 488 1.200 Nguyen Ngoc Dinh
rice field 28/7/2010 15/8/2010 11/2010
A8/SD12 Km238+500 4.900 7.350 Tran Van Sinh
Ben Den- Gia Phu- Bao Thang- Lao Cai
rice field 10/8/2010 15/8/2010 11/2010
A8/SD13 Km238+500 300 450 Nguyen Thi Vi
rice field 10/8/2010 15/8/2010 11/2010
A8/SD14 Km238+500 2.400 3.600 Dao Van Nghia
rice field 10/8/2010 15/8/2010 11/2010
A8/SD15 Km238+500 3.000 7.500 Nguyen Duc Loi
rice field 10/8/2010 15/8/2010 11/2010
A8/SD16 Km238+500 9.600 19.200 Pham Van Thi
rice field 10/8/2010 15/8/2010 11/2010
A8/SD17 Km238+500 3.000 6.000 Dao Thi Muoi
rice field 10/8/2010 15/8/2010 11/2010
A8/SD18 Km238+500 3.000 6.000 Pham Van Thu
rice field 10/8/2010 15/8/2010 11/2010
A8/SD19 Km238+500 4.00 8.00 Pham Van Vien
rice field 10/8/2010 15/8/2010 11/2010
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
187
BATCHING PLANTSPackage / SD No.
Location Appropriate settling pond
Noise and dust
measures
Ownershipa Prior Land Useb
Approval Operation
Name Contact Info Date Agencyc Start Est. End Actual End
A8/CBP1 Km218+040 Settling pond had provided
Noise and dust measures had support with plant
Suoi Nhu BCp
An Thang hamlet, Son Ha commune, Bao Thang, Lao Cai
Abandoned 16/7/2012 Bao Thang District people’s committee
1/4/2011 1/8/2013 July 2013
A8/CBP2 Km231+889 Settling pond had provided
Noise and dust measures had support with plant
Suoi Trat BCP
Giao Binh hamlet, Xuan Giao commune, Bao Thang, Lao Cai
Hill land 16/7/2012 Bao Thang District people’s committee
11/1/2011
1/8/2013 February 2014
A8/CBP3 Km238+265 Settling pond had provided
Noise and dust measures had support with plant
Ngoi Bo BCP
Ben Pha hamlet, Gia Phu commune, Bao Thang, Lao Cai
Abandoned 16/7/2012 Bao Thang District people’s committee
24/1/2011
1/8/2013 May 2013
A8/ABP1 Km238+265 Settling pond had provided
Noise and dust measures had support with plant
Ngoi Bo ABP
Ben Pha hamlet, Gia Phu commune, Bao Thang, Lao Cai
Abandoned 25/6/2013 Bao Thang District people’s committee
29/3/2013
1/8/2013 March 2014
A8/ABP2 Km230+800 Settling pond had provided
Noise and dust measures had support with plant
Son Hai ABP
Son Hai commune, Bao Thang, Lao Cai
Abandoned Not yet Not yet 20.9.2013
31.12.2013
March 2014
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
188
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
189
11. ANNEX 5: SUMMARY TABLE OF IMPOSED PENALTIES
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
190
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
191
PACKAGE A1
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
22-Nov-2013/GET1-POS-A1-2317
Construction work caused landslide on riversides at Tan Loi (Km 10+695) and Xuan Phuong (Km 7+660) Bridges but restoration works have not been carried out
Due to the Contractor didn’t take any action to implement the requirement of the Engineer in order to restore the affected areas so the Engineer temporarily retained VND ten billion (approximate USD 476,000) from IPC no 38 until the Contractor finishes restoration work
Yes
PACKAGE A2
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
No penaltyimposed
PACKAGE A3
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
No penalty imposed
PACKAGE A4
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
No penalty imposed
PACKAGE A5
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
Ref. GET3-KEANGNAM-14-A5-117 dated on 17th April, 2014
At Km123+860, Km130+800, Asphalt Concrete Batching Plant Km135, Ngoi Thu: incompliance in fuel management
The Engineer required the Contractor to improve fuel control at these locations. If the situation is not improved, we will consider suspending payments of the works
No
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
192
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
which relates to the non compliance item
GET-KEA-A5-154 dated to on 14th May, 2014
Damaged local road (certain sections from km 141 to km 143, km 149), certain sections of Provincial Road 166 from km 141 to 143 as well as a section of the local road along km 149, which is used by Project vehicles, are damaged/in bad condition
The Engineer required the Contractor to apply measures in order to solve this problem. If the situation is not improved, clause 2.1 (h) in the section 01600- Maintenance and protection of traffic (referring to the Project’s technical specification) will be immediately applied, as suspending payments the works related with the non compliance.
No
PACKAGE A6
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
No penalty imposed
PACKAGE A7
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
25/04/2014 - Ref. GET4-GRBCC-1120
Ensure safety and clean on site after technical open - Package A7- Third time
Engineer will not sign next IPC until the contractor completed according to the Engineer’s instructions
No
19/05/2014 - Ref. GET4-GRBCC-1128
Request to submit the CMS for assuring traffic safety during construction
Engineer will not sign next IPC until the contractor completed according to the Engineer’s instructions
No
27/05/2014 - Ref. GET4- GRBCC - 1133
Request to implement the instruction of ADB mission on May, 2014
Engineer will not sign next IPC until the contractor completed according to the Engineer’s instructions
No
04/06/2014 - Ref. GET4- GRBCC - 1134
Request to remove the bushes have dead out of
Engineer will not sign next IPC until the contractor completed
No
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
193
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
Package A7 according to the Engineer’s instructions.
16/6/2014 - Ref. GET4- GRBCC - 1137
Require to clearance for under Bridges, inside box culverts and pile culverts- Package A7
Engineer will not sign as-build and payment for remain items of these Bridges and culverts
No
PACKAGE A8
DATE/ LETTER REFERENCE
ISSUE PENALTY IMPOSED EXECUTION (Y/N)
25/04/2014- Ref. Get4- Vinocanex- 993
Ensure safety and clean on site - Package A8
Engineer will not sign next IPC until the contractor completed according to the Engineer’s instructions.
No
27/05/2014- Ref. Get4- Vinocanex- 1005
Require to clearance An Tien lake at construction place of Son Hai Bridge Km227+065- Package A8
Engineer will retaining payment next IPC for this Bridge
No
26/6/2014- Ref. Get4- Vinocanex- 1028
Require to clearance for Drainage box culverts Km233+506- Package A8
Engineer will not sign as-build and payment for remain items of these Bridges and culverts
No
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
194
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
195
12. ANNEX 9: DOCUMENTATION RELATED TO COMPLAINTS AND
COMPENSATION ACTIVITIES DUE TO SOCIAL IMPACTS
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
196
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor
Noi Bai – Lao Cai Highway Project
197
Package A2: Compensation status for cracking houses which were impacted by construction activity
Location No. of
complained households
Influence Zone Checking Status
Compensated
Amount (VND)
Within influence zone
Ouf of influence zone
Compensated Estimated
Kim Long – Tam Duong 5 2 3 5 58,917,432 58,917,432
Dao Tu – Tam Duong 43 40 3 42 661,834853 814,072308
An Hoa – Tam Duong 8 7 1 7 97,386,487 102,386,487
Hoang Dan – Tam Duong
70 70 0 70 1,036,213,575 1,038,408,386
Tien Lu – Lap Thach 55 47 8 52 195,000,000 380,009,646
Van Quan – Lap Thach 46 44 2 34 254,307,164 295,117,096
Dinh Chu – Lap Thach 7 7 0 1 12,334,891 69,606,578
Dong Ich – Lap Thach 51 49 2 49 515,726,908 539,444,817
Tu Yen – Song Lo 19 16 3 13 65,068,490 105,489,439
Duc Bac – Song Lo 3 3 0 3 55,247,453 55,247,453