31
COMMUNITY MEETING | September 11, 2019 Visitacion Valley Baylands North (Schlage Lock) Development Updates Impact Fee Project Updates

Visitacion Valley - SF Planning

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Visitacion Valley - SF Planning

COMMUNITY MEETING | September 11, 2019

Visitacion Valley Baylands North (Schlage Lock) Development Updates Impact Fee Project Updates

Page 2: Visitacion Valley - SF Planning

Agenda5 min5 min

10 min 10 min5 min

20 min 20 min 5 min

Intros, Agenda & Meeting GoalsImpact Fee OverviewImpact Fee Project UpdatesQ&ABreakBaylands North (Schlage Lock) Development UpdateQ&AWrap Up

6:15 pm

7:45 pm

Page 3: Visitacion Valley - SF Planning

Meeting GoalsImpact Fee

Project Updates• Provide updates on Blanken Tunnel improvements

(lighting & mural)• Provide updates on Visitacion Ave improvements• Provide updates on Herz Playground improvements

• Introduce new staff from UPC• Provide big picture project udpates• Review Phase 1 development status and anticipated timeline

Baylands North Development

Update

Page 4: Visitacion Valley - SF Planning

Part 1 Impact Fee Project Updates

Page 5: Visitacion Valley - SF Planning

VV IMPACT FEES: WHAT ARE THEY?

Executive ParkBaylands North

• Purpose: mitigate impacts brought by new development

• Fees capture value created by development and invest it into the community

• Projected through FY2025 = ~$21.7 million

• Projected through FY2030 = ~$36 million;

• Amount and availability of funds depend on ultimate buildout and timing of development

Page 6: Visitacion Valley - SF Planning

VV IMPACT FEES: HOW CAN THEY BE USED?• Capital improvements only (i.e. not programming/operations)

• Complete Streets & Transportation

• Recreation & Open Space (including community facilities; e.g. library)

• Childcare

ExecutivePark

SchlageLock

Daly City Brisbane

McLarenPark

San Francisco San Francisco

Third

Str

eet

Bays

hore

Blvd

101 Freeway

101 Freeway

Sunnydale Avenue

Blanken Avenue

Mansell Street

Visitacion Avenue

Leland AvenueSunnydale

HOPESFHarney Way

VISITACION VALLEY IMPACT FEE BOUNDARY

Impact Fee Boundary

Impact Fee Boundary 250 Foot Bu�er

City & County Boundary

Page 7: Visitacion Valley - SF Planning

Community

PriorityCity

Priorit

y

Feasibilty Cost

VV IMPACT FEES: PROJECT PRIORITIZATION

Proposed Project

Page 8: Visitacion Valley - SF Planning

IMPACT FEES: WHAT WE’VE HEARD• 5 prioritization workshops to date:

Sept. 2014, May 2015, Sept. 2015, July 2016, May 2017

• 3 community surveys (in person and online); 220 responses

TOP PRIORITIES

Pedestrian Safety Improvements

Bike & Transit Improvements

Park & Playground Improvements

McLaren Park Access Improvements

Page 9: Visitacion Valley - SF Planning

VV IMPACT FEES: WHAT WE’VE HEARD

JULY/AUGUST 2016 SURVEY RESULTS

0 10 20 30 40 60 70

Visitacion Ave Sidewalk Installation & Trail Improvements*

Arleta Bayshore Intersection Improvements

Visitacion Valley Greenway Connections

Blanken Underpass Illumination

Blanken Underpass Art Murals

Transit Stop Improvements*

Visitacion Valley Ballfield Renovation

Elliot Street Staircase

Visitacion Valley Playground Renovation

Herz Playground Renovation

Bike Routes To Bay Trail & Candlestick Point*

Leland & Cora Bulb-Out & Sidewalk Widening

Visitacion Ave/Trailhead Crossing

Proposed Visitacion Valley Projects

60

55

46

42

36

32

32

29

23

21

18

17

35

50 Votes

*For these projects, respondents were asked for their preference on specific sub-options. See graphs below for detail.

selected for initial impact fee allocation

Page 10: Visitacion Valley - SF Planning

VV IMPACT FEES: COMMUNITY INPUT

Community Design ProcessImplementing agencies will host a community design process to take each proposed project from conceptual design through detailed design.

Page 11: Visitacion Valley - SF Planning

VV IMPACT FEES: SELECTED PROJECTS

COMPLETED, SPRING 2019: Blanken Underpass Lighting UpgradeInstall additional lighting in tunnel and repace existing fixtures with LED fixtures. Final cost = $16K ($82K less than original estimate)

Blanken Ave

101 Freeway Exec. Park Blvd

Page 12: Visitacion Valley - SF Planning

VV IMPACT FEES: SELECTED PROJECTS

UPDATE: Blanken Underpass Art MuralArt murals along Blanken Tunnel walls and/or entryway retaining walls; opportunity to create unique neighborhood gateway.

Blanken Ave

101 Freeway Exec. Park Blvd

Project Status• $20,000 from D10 Supervisor for SFAC RFP (no impact fees)• 4 community workshops to select artist and concept designs• Online voting for final design now live through Sept. 24th:

www.surveymonkey.com/r/BlankenMural• Next steps: Caltrans permit and mural installation (fall/winter)

Concept Design A Detail

Concept Design B Detail

Page 13: Visitacion Valley - SF Planning

VV IMPACT FEES: SELECTED PROJECTS

UPDATE: Visitacion Avenue McLaren Park Connector

Proposed NewPedestrian

Crossing

ProposedNew Sidewalk

and/or Trail

Proposed New BikeLanes & Sharrows

ExistingTrailhead

ExistingSidewalk

Conceptual Bike Facility(SF Green Connections Plan)

ExistingBike Path

ProposedNew Sidewalk

VisitacionValleyMiddleSchool

John KingSenior

Community

HerzPlayground &Co�man Pool

Visita

cion A

ve.

Visitacion Ave.

Hahn Street

Manse

ll Stre

et

Leland Ave.

Raymond Ave.

N

>

• New sidewalks on Visitacion Avenue to provide access to McLaren Park

• New bike lanes and/or sharrows for access to McLaren Park

• Narrowed travel lanes for traffic calming

Project Status• Design elements under review• Further community outreach

and detailed design pending availability of impact fee funding

Page 14: Visitacion Valley - SF Planning

IMPACT FEES: SELECTED PROJECTS

UPDATE: Visitacion Avenue Connector Trailhead Crossing• New crosswalk to improve safety & access• Rapid flashing beacons (solar-powered) and new safety signage• New street lighting and school loading improvements

Visitacion Avenue

Visitacion ValleyMiddle SchoolJohn King

Senior Community

McLarenParkExisting Trail

Trailhead

Existing Sidewalk

Proposed New Sidewalk

Existing/Improved Trail

Proposed NewPedestrian

Crossing

Project Status• Fully funded by SF Rec & Park (no impact fees)• Design largely completed• Construction scheduled early 2020

Page 15: Visitacion Valley - SF Planning

IMPACT FEES: SELECTED PROJECTS

Herz Playground Renovation• Redesign • New equipment

VISITACIO

N AVE

NORTH0 4' 8' 16'

1

4

(E) CLUBHOUSE

COLUMBIA CASCADE

EMBANKMENT SLIDE

BERLINER NET CLIMBER

ROLLING SSS

BERLINER DNA TOWER

.02 W/ 9’HIGH TUBE SLIDE

BOULDER SCRAMBLE

CLIMBING WALL

GAME /PICNIC TABLES & SEATING

PLAYHOUSE

PORCH SWINGS

WILLOW TUNNEL

TREES 25’ O.C.

SSS MOUND, TYP,

CLIMBING WALL

(E) WALL

(E) GUARDRAIL

1

2

3

4

5

6

7

2

3

7

5

6

DRAFT DESIGN CONCEPTS26 July 2019Let's Play SF!

CONCEPT A: PLAY PORCH

VISITACIO

N AVE

NORTH0 4' 8' 16'

BENCH, TYP.

BERLINER COSMO S BASE

NEW TREES, TYP.

BERLINER BOWL SWING

SSS MOUNDS,

TYP.

BERLINER DNA

COMBI.01

ARBOR

COLUMBIA CASCADE EMBANKMENT SLIDE

(E) GUARDRAIL

NEW HANDRAILS @ 6.6% RAMP

BOULDERS, 2’-4’ DIAM.

(E) WALL

(E) WALL

1

(E) CLUBHOUSE1

2

3

4

5

6

7

5

2

7

6

4

DRAFT DESIGN CONCEPTS26 July 2019Let's Play SF!

CONCEPT B: DISCOVERY VALLEY

VISITACIO

N AVE

NORTH0 4' 8' 16'

VISITACIO

N AVE

NORTH0 4' 8' 16'

1

2

3

4

5

6

7

BENCH, TYP.

BERLINER BOWL

SWINGS

KOMPAN TODDLER SWINGS

CLIMBING WALL

BERLINER DYNAMO

GALAXY NET CLIMBER & SLIDE

NEW ENTRANCE

CONCRETE LOUNGE FURNITURE

GAME TABLES

SEATWALL/RETAINING WALL 18” HIGH

COLUMBIA CASCADE EMBANKMENT SLIDE

(E) GUARDRAIL

ARBOR

(E) CLUBHOUSE

1

5

7

6

4

2

3

DRAFT DESIGN CONCEPTS26 July 2019Let's Play SF!

CONCEPT C: ADVENTURE LOOP

Project Status• 3 Design concepts developed for August 17 community workshop• Outreach to community groups ongoing• Final design and public meeting later this year

• ADA access upgrades

Page 16: Visitacion Valley - SF Planning

Questions? Feedback?

John M. FrancisSenior Planner/Urban [email protected] 415-575-9147

Brian StoklePlanner [email protected] 415-575-5606Michelle Woo

Construction Manager [email protected] 415-558-5262

Page 17: Visitacion Valley - SF Planning

5 Minute Break

NEXT... Part 2 Baylands North (Schlage Lock) Updates

Page 18: Visitacion Valley - SF Planning

Part 2 Baylands North (Schlage Lock) Development Update

Page 19: Visitacion Valley - SF Planning

September 11th , 2019

The Baylands Development Update

Page 20: Visitacion Valley - SF Planning

Agenda

• Introduction-NewTeam

• TheBaylandsCommunity• OpenSpaceandParkOverview• MobilityPlanOverview• TheBaylandsNorthOverview• OurPartners• CommunityBenefitsOverview• Questions&Answers

6:00 pm

Page 21: Visitacion Valley - SF Planning

The Baylands ‘ One Community ’

The Baylands Community Highlights

• Transit and Sustainability Focused Development• Approx. 4000 Residences • Approx. 140 Acres of Open Space and Parks plus a 132

Acre Lagoon• Over 7 million sf of Retail, Life Science, R&D, Office, Hotel

and Conference Space • Co-Working • Proposed School• Public Art

Page 22: Visitacion Valley - SF Planning

Open Space and Park Highlights

Page 23: Visitacion Valley - SF Planning

Mobility Plan Highlights

The Baylands Mobility

• Commitment to Walkability and Bikeable Streets• Accommodate but not Rely on the use of Cars • Take Advantage of Technology in Mobility • BRT (Bus Rapid Transit)• Cal Train • Existing Muni and Bus Services • Connection To Existing Trails

Page 24: Visitacion Valley - SF Planning

‘ One Community ’

The Baylands Phase 1 Highlights• Approx. 574 Residences• Approx. 40,000 sf of Retail and Co-Working • Leland Park and Bayshore Plaza• Historical Building Rehabilitation

Phase 1 Projected Timeline • 4Q 2019 Restart Infrastructure Improvements • 1Q 2020 Commence Historic Building Rehabilitation • 3Q 2020 Construction Begins

Future Baylands North Phases and Park• Phase 2 (Bldgs. 4, 5, 6) | 2024 (approx.)• Phase 3 (Bldgs. 7, 8, 9) | 2027 (approx.)

The Baylands North

Page 25: Visitacion Valley - SF Planning

The Baylands North ‘ One Community ’

Page 26: Visitacion Valley - SF Planning

The Baylands North ‘ One Community ’

Page 27: Visitacion Valley - SF Planning

Mews Realignment The Baylands North

Page 28: Visitacion Valley - SF Planning

Leland Connectivity The Baylands North

Page 29: Visitacion Valley - SF Planning

1. Approx. 4,000 sqft of community space inside the renovated historic building;2. Demolition, Remediation and Infrastructure for the entire project, approx. $32M;3. Deliver Leland Park and Bayshore Plaza;4. Phase I Impact fee, approx. $10M;5. Grocery Store;6. 15% Inclusionary Housing units;

Phase I Community Benefits Overview

Page 30: Visitacion Valley - SF Planning

Our Partners

Page 31: Visitacion Valley - SF Planning

What’s Next

Questions and Answers