8/2/2019 vsp-works
1/27
ANDHRA PRADESH TOURISM
DEVELOPMENT CORPORATION LTD
VISAKHAPATNAM DIVISION
NOTE ON WORKS
8/2/2019 vsp-works
2/27
VISAKHAPATNAM DISTRICT
Government of India has sanctioned Rs. 571.93 lakhs for development of
Visakhapatnam Beach Circuit under Central Finance Assistance. The components
of the project are as follows:
In Visakhapatnam District eight works are sanctioned and they are
1. Thatiguda water falls 2. Tribal Bazar, Araku
3. Erramattidibbalu 4. Rushikonda
5. Mangamarripeta 6. Thotlakonda
7. Bheemupatnam 8. Etikoppaka
i) Balance works of Thatiguda water falls.
Andhra Pradesh Tourism Development Corporation is taking up the
development of water falls at Thatiguda near Ananthagiri. The VC&MD has
accorded an administrative sanction for Rs.18.00 lakhs for balance works.
I. Feature development:
1. Providing steps from Road to water falls.
2. Construction of Cafeteria.
3. Construction of Toilets.Estimate cost: Rs.18.00 lakhs.
Name of the contractor: Sri P L Ganapathi, VSP
Status: The Contractor not started the work. A letter issued to the contractor to
start the work immediately. The contractor has says that the agreement
period is lapsed 3 months (for 6 months), the work will be started with in
three days if you are agreed EOAT has to be sanctioned for another 3
months with out any finality.
8/2/2019 vsp-works
3/27
ii)Development of water body and Tribal Bazaar at ARAKU :
Estimate cost: Rs.176.00 lakhs.
Name of the contractor: Sri Bonmali Rout
1. Bazaar2. water Body3. Am phi Theatre4. Pathways and Landscaping
Status: The work speed up the contractor, brick work in bazaar blocks 123nearing completion. 4&5 are in progress.
iii) Development of Tourist Centre at Erramatti Dibbalu: with
an amount of Rs 79.00 lakhs out pf which Rs 60.00 lakhs of CFA
grant, Rs 19.00 lakhs APTDC funds.
The following components will be developed at Erramatii Dibbalu.
Tourist Information Center
Parking area
Restaurant
Public amenitie
Estimate cost: Rs.79.00 lakhs.
Name of the contractor: Sri Bonmali Rout
Restaurant blocks column footings casted. The work stopped Due to objection
raised by the INS Kalinga.
8/2/2019 vsp-works
4/27
iv) Development of Tourist Amenities at Rishikonda Beach:
Estimate cost: Rs.107.00 lakhs.
Name of the contractor: Sri Bonmali Rout
Shower Cubicles
View Towers cum Light House and Shacks
Parking Area
Path ways, Sitting Benches and Sunbath decks
Parking area work is in progress. As per the Instructions of VC& MD The work is
stopped.
v) Development of Tourism Amenities at Mangamari Peta
Creek: With an amount of Rs.20.00 lakhs, the following
components will be developed at Mangamaripeta.
Ticketing & Information Center
Public Amenities
Fencing
Status: Earth work is inprogress. As per the Instructions of VC& MDThe work is stopped.
vi) Development of Buddhist Site at Thotlakonda: with an
amount of Rs.126.00 lakhs, the following components will be
developed at Thotlakonda.
a) Security & Ticketing and Lounge cum Public Amenities
b) Open Air Theater, Stupa Replica and Interpretation Center
8/2/2019 vsp-works
5/27
c) Development of roads.
Tenders are invited for the work by the Head office.
vii) Development of Dutch Village at Bheemili :
Andhra Pradesh Tourism Development Corporation is taking up the
development of Bheemili Dutch Village, Visakapatnam District with the Central
Financial Assistance of Rs.224.00 lakhs under Development of Visakapatnam Beach
Circuit. And the proposed components to be developed are as below
I. Feature development:
1. Village centre
2. Interpretation centre
3. Wind mills
4. Theme houses
II. Site Development:
1. Fencing
2. Ticketing and Information centre
An extent of 6.20 acres in Survey No.87 of kummaripalem is handed over to APTDC
for the project. Administrative Sanction approved by the VC and MD and tenders
called for.
viii) Development of ETIKOPPAKA Crafts centre: The work wassanctioned by the Govt. of India for Rs. 45.95 lakhs.
Present status: A letter was addressed by the Executive director duly requesting forallotment of existing DRDA building.
8/2/2019 vsp-works
6/27
8/2/2019 vsp-works
7/27
VIZIANAGARAM DISTRICT
In Vizianagaram District Ten works are sanctioned and they are,
1. Development of Tourist amenities atRamatheertham
2. Development of Tourist amenities atThotapalli
3. Development of Tourist amenities atThatipudi
4. Development of Vizianagaram Fort
5. Development of War memorial Bobbili
6. Development of Tourist amenities atKumili
7. Development of Tourist amenities atPunyagiri
8. Development of Beach resort atChintapalli
9. Development of Beach resort atBhogapuram
8/2/2019 vsp-works
8/27
1 Development of Tourist amenities atRamatheertham
Estimate cost : Rs. 41.50 lakhs.
Name of the contractor : M/s Maruthi Engineering
In this work dormitories for ladies and gents separately and
Keshakhanadana hall and other ancillary works like extension of
steps at koneru and land scaping are taken up.
Stage of work: Work is nearing completion.
8/2/2019 vsp-works
9/27
2 Development of Tourist amenities atThotapalli
Estimate cost : Rs. 41.50 lakhs.
Name of the contractor : M/s Maruthi Engineering
8/2/2019 vsp-works
10/27
In this work dormitories for ladies and gents separately and dress
changed rooms and toilets at river ghat and other ancillary works
and landscaping are taken up.
Stage of work: Dormitory building work is in finishing stage. Derss
changing rooms and toilets plastering are progress.
8/2/2019 vsp-works
11/27
3. Development of Tourist amenities atThatipudi
Estimate cost : Rs. 41.50 lakhs.
Name of the contractor : M/s KCP Projects Ltd.
In this work one restaurant, pathways, landscaping, illumination of
landscaped park and parking area are taken up.
Stage of work: Restaurant work is nearing completion and
pathways work is in progress.
8/2/2019 vsp-works
12/27
8/2/2019 vsp-works
13/27
4. Development of Vizianagaram Fort
Estimate cost : Rs. 41.50 lakhs.
ame of the contractor : Sri K. Balaji
In this work one cafeteria and amphi theatre, land scaping,pathways,
illumination of landscaped park and fort wall are taken up.
Stage of work: Columns raised upto slab and centering work is in
progress. The work stopped due to objection raised by the chairmanof
manasa trust.
8/2/2019 vsp-works
14/27
5. Development of War memorial Bobbili
Estimate cost : Rs. 41.50 lakhs.
Name of the contractor : M/s Lakshmi narasimha Enterprises.
In this work existing land scaped area is being extended, cafeteriaand
toilets and illumination are being taken up.
Stage of work: Basement work for cafeteria and toilets completedand
park area basement work completed and MS grills are fixed.
8/2/2019 vsp-works
15/27
6. Development of Tourist amenities atKumili
Estimate cost : Rs. 41.50 lakhs.
The District Collector has proposed for shifting this work toRamatheertham and the same was accepted by the Vice Chairmanand Managing Director. Concept drawings are accepted by the DistrictCollector Vizianagaram and the consultant preparing the estimate.
7. Development of Tourist amenities atPunyagiri
Estimate cost : Rs. 41.50 lakhs.
Name of the contractor : Sri P.L. Ganapathi
8/2/2019 vsp-works
16/27
In this work dormitories for ladies and gents separately and dress
changed rooms at water falls, keshakhanadana hall and toilets near
temple are taken up.
Stage of work: Dormitory building slab work is completed and
dress change rooms near waterfall footings work is in progress.
8/2/2019 vsp-works
17/27
8. Development of Beach resort atChintapalli and
Bhogapuram
Estimate cost : Rs. 93.00 lakhs.
The District Collector has addressed a letter to the Govt. duly
proposing to take up both the works at Chintapalli at already allotted
site. Concept drawings are accepted by the District Collector
Vizianagaram and the consultant preparing the estimate.
8/2/2019 vsp-works
18/27
SRIKAKULAM DISTRICT
In Srikakulam District Ten works are sanctioned and they are,
1. Development of Koneru (lake) complex atARASAVALLI
2. Development of Tourist amenities atSRI KURMAM
3. Development of Tourist amenities atSRI MUKHALINGAM
4. Development of Tourist amenities centre atSALIHUNDAM
5. Development of Beach Resort atKALINGAPATNAM
6. Development of Tourist amenities centre atSRIKAKULAM
7. Development of Tourist amenities centre atDANTAPURAM
8. Development of Tourist amenities centre atBARUVA
9. Development of Beach destination atBARUVA
10.Budget Hotel atARASAVALLI
8/2/2019 vsp-works
19/27
1. Development of Koneru (lake) complex at ARASAVALLI
Estimate cost : Rs. 41.50 lakhs.
Name of the contractor : Sri K. Anantha rao.
In this work dormitories for ladies and gents separately along with toilets
and two VIP rooms and landscaping are being taken up.
Stage of work: The above items are in one building and the same is
nearing completion.
8/2/2019 vsp-works
20/27
8/2/2019 vsp-works
21/27
2. Development of Tourist Amenities at SRIKURMAM
Estimate cost : Rs. 41.50 lakhs.
Name of the contractor : Sri K. Anantha rao.
In this work two dormitories for ladies and gents separately and extension of
steps at koneru and dress change rooms at koneru is taken up.
Stage of work: Dormitories building is in finishings stage, and dress
change rooms and steps at koneru are to be started.
8/2/2019 vsp-works
22/27
3. Development of Tourist Amenities at SRIMUKHALINGAM
Estimate cost : Rs. 41.50 lakhs.
Name of the contractor : Sri K. Anantha rao.
In this work two dormitories for ladies and gents separately and one
Kesakhandana sala and Dining hall.
Stage of work: Ground and first floor slabs are casted and the contractor
stop the work.
8/2/2019 vsp-works
23/27
8/2/2019 vsp-works
24/27
4.Development of Tourist amenities centre at
SALIHUNDAM
Estimate cost : Rs. 41.50 lakhs.
Name of the contractor : Sri Neha infrastructures.
In this work Restaurant, waiting lounge, Two VIP suits and toilets are
proposed.
Stage of work: Plinth beam are casted, Ground floor columns are
rised,
And further work is in progress.
8/2/2019 vsp-works
25/27
5. Development of Beach Resort atKALINGAPATNAM
Estimate cost : Rs. 51.50 lakhs.
Name of the contractor : Sri GRR constructions.
In this work Restaurant, Public toilets and six guest rooms.
Stage of work: Plinth beam work is completed and further work is in
progress.
8/2/2019 vsp-works
26/27
6. Development of Tourist amenities centre at
SRIKAKULAM
8/2/2019 vsp-works
27/27
Merged with Budget Hotel
7. Development of Tourist amenities centre at
DANTAPURAM
Merged with Budget Hotel
8. Development of Tourist amenities centre atBARUVA
Estimate cost : Rs 41.50 lakhs
AND
9. Development of Beach destination atBARUVA
Estimate cost : Rs 237.61 lakhs
Stage of work : Tenders work is in progress.
10. Budget Hotel atARASAVALLI
Estimate cost : Rs 1372 lakhs