19
Waste-to-Energy Projects at Army Waste to Energy Projects at Army Installations Mr. Franklin H. Holcomb Chief, Energy Branch U.S U.S. Army . Army ERDC ERDC-CERL CERL Champaign IL USA Champaign IL USA 13 JAN 2011 13 JAN 2011 US Army Corps of Engineers BUILDING STRONG ® Distribution Statement A -- Approved for public release; distribution is unlimited.

WasteWaste -toto -Energy Projects at ArmyEnergy Projects … · WasteWaste -toto -Energy Projects at ArmyEnergy Projects at Army Installations Mr. Franklin H. Holcomb Chief, Energy

  • Upload
    vuxuyen

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

Waste-to-Energy Projects at ArmyWaste to Energy Projects at Army Installations

Mr. Franklin H. Holcomb Chief, Energy Branch U.SU.S. Army. Army ERDCERDC--CERLCERL Champaign IL USAChampaign IL USAp gp g 13 JAN 201113 JAN 2011

US Army Corps of Engineers BUILDING STRONG®

Distribution Statement A -- Approved for public release; distribution is unlimited.

Report Documentation Page Form ApprovedOMB No. 0704-0188

Public reporting burden for the collection of information is estimated to average 1 hour per response, including the time for reviewing instructions, searching existing data sources, gathering andmaintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information,including suggestions for reducing this burden, to Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, ArlingtonVA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to a penalty for failing to comply with a collection of information if itdoes not display a currently valid OMB control number.

1. REPORT DATE 13 JAN 2011 2. REPORT TYPE

3. DATES COVERED 00-00-2011 to 00-00-2011

4. TITLE AND SUBTITLE Waste-to-Energy Projects at Army Installations

5a. CONTRACT NUMBER

5b. GRANT NUMBER

5c. PROGRAM ELEMENT NUMBER

6. AUTHOR(S) 5d. PROJECT NUMBER

5e. TASK NUMBER

5f. WORK UNIT NUMBER

7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES) U.S. Army Engineer Research and Development Center,ConstructionEngineering Research Center,Champaign,IL,61826

8. PERFORMING ORGANIZATIONREPORT NUMBER

9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES) 10. SPONSOR/MONITOR’S ACRONYM(S)

11. SPONSOR/MONITOR’S REPORT NUMBER(S)

12. DISTRIBUTION/AVAILABILITY STATEMENT Approved for public release; distribution unlimited

13. SUPPLEMENTARY NOTES presented at the DOE-DOD Waste-to-Energy using Fuel Cells Workshop held Jan. 13, 2011 in Washington DC

14. ABSTRACT

15. SUBJECT TERMS

16. SECURITY CLASSIFICATION OF: 17. LIMITATION OF ABSTRACT Same as

Report (SAR)

18. NUMBEROF PAGES

18

19a. NAME OFRESPONSIBLE PERSON

a. REPORT unclassified

b. ABSTRACT unclassified

c. THIS PAGE unclassified

Standard Form 298 (Rev. 8-98) Prescribed by ANSI Std Z39-18

Outline � Background

► Intro to ERDC ► Army/DoD Energy Requirements & Objectives ► 2008 Installation WTE Workshop ► 2009 Air Force WTE Workshop (Alt Energy Now!)p ( gy ) ► 2009 RDECOM WTE Technology Assessment

� Selected Army WTE Projects ERDC F l C ll D ► ERDC Fuel Cell Demos

► Army Tactical WTE Demos ► Technikron RETC (at Picatinny Arsenal)

� Others � Conclusions

BUILDING STRONG®

� Acknowledgments

,

CRREL Alaska Office

p g y,

3

Engineer Research and Development Center

International Research

Alaska Projects Office Fairbanks, AK

CRREL Alaska Office Development Center Cold Regions ResearchCold Regions Research

OfficeAnchorage, AK

25002500 ERDC Team MembersERDC Team Members

The Dalles Research FacilityDallesport, WA

Eau Galle LaboratorySpring Valley, WI

gand Engineering Laboratory (CRREL) Hanover, NH

g and Engineering Laboratory (CRREL) Hanover, NH

Fisheries Engineering Team Columbia River Basin Bonneville,W A

Construction EngineeringResearch Laboratory(CERL)Champaign, IL

Construction EngineeringResearch Laboratory(CERL)Champaign, IL

Topographic Engineering Center (TEC) Alexandria, VA

Topographic Engineering Center (TEC) Alexandria, VA

Lewisville Aquatic Ecosystems

Research Facility Lewisville, TX

Trotter Shoals LimnologicalResearch Facility

Calhoun, SC

Big Black Test Facility

Field Research Facility, Duck, NC

Laboratories Coastal and Hydraulics Laboratory (CHL)Environmental Laboratory (EL)Geotechnical and Structures Laboratory (GSL)Information Technology Laboratory (ITL)Vicksburg, MS

Coastal and Hydraulics Laboratory (CHL) Environmental Laboratory (EL) Geotechnical and Structures Laboratory (GSL) Information Technology Laboratory (ITL) Vicksburg, MS

Field Offices

Laboratories

BUILDING STRONG®We solve problems to make the world safer and better!

ARMY R&D Organizations ARI

Army Research Institute

Agile Development

Center

AM~ A~ Army Material

Systems Analysis Activity

SMDC Space & Missile

Defense Command

sos~ Systems of Systems

Integration

Natick Solider Center

STC Simulation

Technology Center

ATEC Army Test and

Evaluation Command

RDECOM

Integration

ARL

ARO-W

CERDEO Communications

- Electronics RD&E Center

1ARDEC Tank

Automotive RD&E Center

Armament RD&E Center

AMRDEe Army Aviation

and Missile RD&E Center

Army Research Office - Washington Participants in SBIR

Army SB/R PMO Participants in SBIR and STTR

Key Energy Directives - Challenge and Opportunity ­

The Army has requirements for energy performance established by legislation, Presidential Executive Orders (EO), Office of the Secretary of Defense (OSD)

mandates and Army policies.

5

BUILDING STRONG®

Federal Energy Mandates

Mandate Topic Energy Performance Target [Source]

Energy use in Federal buildingsgy g • Reduce 3% per year to total by 30% by 2015 (2003 baseline) [EO 13423, EISA 2007]p y y y ( ) [ , ]

GHG emission reduction • Identify GHG emission reduction targets to be met by 2020 from 2008 baseline [EO 13514] • Army target – 34% [SA Memo to OSD]

Energy metering for improved energy management

• Meter electricity by Oct 2012 [EPACT 2005] • Meter natural gas and steam by Oct 2016 [EISA 2007]

Electricity use for federal government from renewable sources

• At least 3% of total electricity consumption (FY07-09), 5% (Fy10-12), 7.5% (FY13 +) [EPACT 2005, NDAA 2007]

Total consumption from renewable sources

• At least 50% of required annual renewable energy consumed from “new” renewable sources [EO 13423] • 25% by 2025 -”Sense of Congress” [ EISA 2007]

Hot water in new / renovated federal buildings from solar power • 30% by 2015 if life cycle cost-effective [EISA 2007]

Fossil fuel use in new / renovated Federal buildings • Reduce 55% by 2010; 100% by 2030 [EISA 2007]

Net zero buildings • All new buildings that enter design in 2020 and after achieve net zero energy by 2030 [EOAll new buildings that enter design in 2020 and after achieve net zero energy by 2030 [EO 13514] • New federal buildings achieve net zero by 2030 [EISA 2007]

Fleet vehicle petroleum consumption • Reduce 20% by 2015 (Base 2005) [EISA 2007] • Reduce by 2% per year thru FY2020 (Base 2005) [EO 13423, EO 13514]

Fleet vehicle alternative fuel use • Increase 10% by 2015 (Base 2005) [EISA 2007] Increase 10% by 2015 (Base 2005) [EISA 2007] • Increase by 10% annually to reach 100% (Base 2005) [EO 13423]

Water consumption • Reduce consumption intensity by 2% annually FY 08-FY 15 (2007 baseline ) [EO 13423] • Reduce consumption by 2% annually for 26% total by FY 2020 (2007 baseline ) [EO 13514]

6

� 1st Workshop held at Army Research Office in MAY 2008

� Goals were to share information, spread visibility on current efforts, and explore the potential of wasteand explore the potential of waste to energy technologies for Army (and DoD) installations, and to potentially launch working groups to further advance implementing installation waste to energy technologies.

� Identified a Need to Determine the “Burdened” Cost of Waste at Installations

� 2nd Workshop Sponsored by Air Force on 22-23 JAN 2009 (Alt E (Alt Energy NNow!)!)

http://dodfuelcell.cecer.army.mil/library_items/ERDC-CERL_TR-08-11.pdf

BUILDING STRONG®

Solid Waste Composition Example Army Installation

Glass, 3% Metal, 9% Plastic 16%

Paper, 26%

Plastic, 16%

Organics 19% Construction &

Demolition Special, 3%Organics, 19% Demolition (C&D), 25%

2009 RDECOM WTE Technology A tAssessment

� Sponsored by RDECOM Power & Energy Technology Focus Team (TFT)Focus Team (TFT)

� Hosted by Army Research Lab (ARL)y y ( )

� Goal was to evaluate the current status and potential di ti f t t t h l i i idirection of waste-to-energy technologies vis-a-vis tactical applications and operations.

� Focus on the requirements that drive the WTE efforts and to evaluate technologies that are appropriate to battlefield operations

BUILDING STRONG®

battlefield operations.

FY93-FY94 Phosphoric Acid Fuel Cell (PAFC) Project Sites

PC25B SITE PC25A SITE

PC25C SITE31 fuel cells – United Technologies Corporation (UTC) Manufacturer

BUILDING STRONG®

Corporation (UTC) Manufacturer

http://dodfuelcell.cecer.army.mil)

FY01-FY04 Residential PEM Fuel Cell Project Sites

91 Fuel Cells 56 Sites 5 Manufacturers

BUILDING STRONG®

5 Manufacturers

http://dodfuelcell.cecer.army.mil)

Tactical WTE Efforts & Demos* � Defense Advanced Research Projects Agency (DARPA) and

Army Research Lab (ARL) ► Basic research and fundamental technology development (MISER, etc)

� Natick Soldier RDEC (NSRDEC) ► Combination of SBIR and mission funded projects for Waste to Energy Converter

(WEC) since 2000 Contractors include Community Power Corp (CPC)(WEC) since 2000 Contractors include Community Power Corp (CPC), Infoscitex, General Atomics, and Green Liquid and Gas Technologies

► Targeting PM Force Provider for technology transition / deployment ► Mobile Encampment Waste to Electrical Power System (MEWEPS) project with

CPC, second field demonstration scheduled at Ft. Irwin, CA in Feb 2011

� Edgewood Chemical / Biological Center (ECBC) ► Tactical Garbage to Energy Refinery (TGER) AIDE project with DLS, Purdue

U i it d CPC fi ld d t ti t d i th tUniversity, and CPC, field demonstration executed in theater

� Communications-Electronics RDEC (CERDEC) ► Biofuel / Tactical Quiet Generator Hybrid Waste to Energy project with CPC,

contract on-going

BUILDING STRONG®

contract on going

* Information provided by Daniela Caughron, APG

Slide courtesy of Don Pickard, Natick Soldier RD&E Center

w::::==... Commun.iry Power ~corporation] Littleton , co

•· Appr~o·ach : BioMax® Stratifjed Downdraft ~Gas ilfi er

- ~ n novative ~des~ g n w~th electron~ c ins tru rn entation and active a1k controls to optDn~tize the process

•· Reduces dry feedstock to fuel ~gas and char/ash

- The clean producer gas can be used ~n an internal combllstion engine

•· P' re-c~ommercia l system desi ~gned to conv~ert

w~oody biomass into ellectriic ity and he,at

- r\~arkets include small industrial] agro-processing~ and rural ele~ctrirfiication

•· ''OFWEC" SBIR Phase Ill tech demo in 2008

• "MEWEP'S" demo in 2009 at ~camp Graylling

• "OFWEC Il l" demo pl,anned f1or Net Zer'o' P'lus JCTD

•· " HEDWEC'' c~ontract awarded 2009 f,o,r 2 TPD s·ystem in 2011

~te: 23 Nov 2010 UNCLASSIFIED

MEWEPS Gas Production !Module ~t C~rnp' Gm.yfing

  s ng ers ng er      

tt          

Renewable EnergyRenewable Energy Te ti Cent (RETC)Te ti Cent (RETC)Testing Center (RETC)Testing Center (RETC)

US A C tUS A C tUS Army ContractUS Army Contract W15QKNW15QKN‐‐0505‐‐D300D300

GeorgeGeorge CrandellCrandell Mike WrazenMike Wrazengg [email protected]

916- 929 -8001 [email protected]

Picatinny Arsenal

t t

RETC Example: InternationalpEnvironmental Solutions

� 8 ton/day Gasifier system8 ton/day Gasifier system designed for MSW, tires, food wastes, green biomass

W t d� Waste to steam and power

� 2nd Generation Design

� Have 40 ton/day system permitted in Southern California on MSW-to-power (1 of 4 candidate MSW to energy technologies selected in LA)

� 8 ton/day system will also be8 ton/day system will also be integrated with microturbine steam generator

Others � Fort Stewart 94,000 lbs/hr steam Wood Chip Plant (off line). � Aberdeen Proving Ground - Offsite plant supplies approx

70,000 lbs/hr (peak) and approx 452,000 Mlbs total 350 psi steam/year.

� The Eielson Air Force Base system processed over 560 tons of paper products in the base’s central heat and power plant which provided 7.82 mmBtu of energy (program currently suspended because the pellet plant is inoperable).

� Hill Air Force Base, which generated 2.1 MW of electricity from landfill gas and has plans to expand to 3.2 MW.

� Dyess Air Force Base which is pursuing a 5.5 MW municipal solid waste energy plant.

� SUNY – Cobleskill Bioenergy Center

BUILDING STRONG®

t t

t t t t

Conclusions – WTE Projects at A I ll iArmy Installations

N d D i h “B d d” f � Need to Determine the “Burdened” cost of Waste 3rd P t Fi i R i d i M t C � 3rd Party Financing Required in Most Cases � Privatization of Utilities is an Issue � SitiSiting & P & Permitting can bbe an Issueitti I

*WTE S t f T ti l O ti h� *WTE Systems for Tactical Operations have different requirements!

BUILDING STRONG®

Acknowledgmentsg� René Parker, Select Engineering Services (SES)

rene parker@sesincusa [email protected] � Mike Warwick, DOE-PNNL

[email protected] � Don Pickard, Natick Soldier RD&E Center

[email protected] � Daniela Caughron Aberdeen Proving Ground (APG) � Daniela Caughron, Aberdeen Proving Ground (APG)

[email protected] � Phil Darcy, Benét Labs (Watervliet Arsenal)y, ( )

[email protected] � Mike Wrazen (Picatinny Arsenal)

i h l @ il BUILDING STRONG®