Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
WASTEWATER MASTER PLAN
Prepared for:
Rincon Del Diablo Municipal Water District 1920 North Iris Lane
Escondido, California 92026
Contact: Greg Thomas, General Manager
Prepared by:
605 Third Street
Encinitas, California 92024
Contact: D. Michael Metts, PE
NOVEMBER 2016
Printed on 30% post-consumer recycled material.
INTENTIONALLY LEFT BLANK
WASTEWATER MASTER PLAN
Prepared for:
Rincon Del Diablo Municipal Water District 1920 North Iris Lane
Escondido, California 92026
Contact: Greg Thomas, General Manager
Prepared by:
605 Third Street
Encinitas, California 92024
Contact: D. Michael Metts, P.E.
November 2016
Printed on 30% post-consumer recycled material.
Sewer Master Plan and EIR Project
9552
i November 2016
TABLE OF CONTENTS
Section Page No.
ACRONYMS AND ABBREVIATIONS ......................................................................... IV
ACKNOWLEDGEMENTS ................................................................................................V
ES EXECUTIVE SUMMARY ....................................................................................... 1
ES.1 Background ............................................................................................................................. 1
ES.2 Onsite Wastewater Treatment Systems.......................................................................... 2
ES.3 Water Reclamation Facility ................................................................................................. 3
ES.4 Wastewater Collection System ......................................................................................... 4
ES.5 Project Cost Opinions ......................................................................................................... 4
INTRODUCTION .................................................................................................. 5 1
1.1 Background ............................................................................................................................. 5
1.2 Service Area Overview ........................................................................................................ 9
1.3 Land Use .................................................................................................................................. 9
1.4 Onsite Wastewater Treatment Systems....................................................................... 10
1.5 Sewer Master Plan Scope ................................................................................................. 10
EXISTING FACILITIES AND FLOW PROJECTIONS .................................... 13 2
2.1 HGV Wastewater Collection System ............................................................................ 13
2.2 HGV Water Reclamation Facility (HGVWRF) ............................................................ 16
WATER RECLAMATION EVALUATION ........................................................ 19 3
3.1 HGVWRF Design Criteria ............................................................................................... 19
3.2 HGVWRF Capacity ............................................................................................................ 21
3.2.1 Influent Screen ....................................................................................................... 22
3.2.2 Equalization Basins ................................................................................................ 22
3.2.3 Aero-Mod System (Biological Treatment System) ........................................ 23
3.2.4 Tertiary Filtration ................................................................................................. 24
3.2.5 Chlorine Contact Tanks ...................................................................................... 24
3.2.6 Effluent Pump Station ........................................................................................... 25
3.2.7 Off-Quality Storage Basins .................................................................................. 25
3.2.8 Sludge Dewatering Centrifuge Pumps .............................................................. 26
3.2.9 Wet Weather Storage ......................................................................................... 26
COLLECTION SYSTEM CAPACITY EVALUATION ..................................... 29 4
4.1 Design Criteria .................................................................................................................... 29
4.2 HGV Conveyance System ................................................................................................ 30
4.3 HGV Lift Station ................................................................................................................. 31
Sewer Master Plan and EIR Project
TABLE OF CONTENTS (CONTINUED)
Page No.
9552
ii November 2016
PRELIMINARY OPINION OF PROBABLE COST ........................................... 33 5
5.1 Cost Opinion Methodology and Assumptions ............................................................ 33
5.2 Wastewater Treatment Cost Opinion .......................................................................... 34
5.3 Collection System Cost Opinion .................................................................................... 34
5.4 Opinion of Probable Annual Costs ................................................................................ 34
5.5 Capital Cost Per Equivalent Dwelling Unit ................................................................... 35
CONCLUSIONS ................................................................................................... 37 6
APPENDIX
Appendix A ....................................................................................................HGV Master Sewer Summary
FIGURES
Table ES-1. Existing HGVWRF Process Flow Diagram .......................................................................... 3
Figure 1-1. Vicinity Map and District Water Service Boundary ............................................................. 6
Figure 1-2. Harmony Grove Service Area Communities ........................................................................ 8
Figure 2-1. HGV Wastewater Collection System ...................................................................................14
Figure 2-2. HGV Sewer Lift Station ............................................................................................................15
Figure 2-3. Existing HGVWRF Site Layout ...............................................................................................17
Table 3-4. Existing HGVWRF Process Flow Diagram ............................................................................21
TABLES
Table 2-1. HGV Sewer Design Criteria .....................................................................................................16
Table 2-2. HGV Projected Wastewater Volumes ...................................................................................16
Table 3-1. Influent Wastewater Flow Rate Design Criteria .................................................................19
Table 3-2. Influent Wastewater Quality ....................................................................................................20
Table 3-3. Projected WRF Effluent Limits .................................................................................................20
Table 3-5. Existing Influent Screen Capacity Analysis .............................................................................22
Table 3-6. Equalization Basins Capacity Analysis ....................................................................................22
Table 3-7. Existing Aeration Basins Capacity Analysis ...........................................................................23
Table 3-8. Existing Secondary Clarifier Capacity Analysis .....................................................................23
Table 3-9. Existing Aerobic Digester Capacity Analysis ........................................................................23
Table 3-10. Existing Tertiary Filtration Capacity Analysis .....................................................................24
Table 3-11. Existing Chlorine Contact Tank Capacity Analysis ...........................................................24
Table 3-12. Existing Effluent Pump Station Capacity Analysis ..............................................................25
Sewer Master Plan and EIR Project
TABLE OF CONTENTS (CONTINUED)
Page No.
9552
iii November 2016
Table 3-13. Existing Off-Quality Storage Capacity Analysis ..................................................................25
Table 3-14. Existing Sludge Dewatering Centrifuge Capacity Analysis ...............................................26
Table 3-15. Existing Wet Weather Storage Capacity Analysis ............................................................26
Table 4-1. Sewer Design Criteria Comparison........................................................................................29
Table 4-2. Proposed District Design Criteria ..........................................................................................30
Table 5-1. Summary of Construction Cost Classes ..............................................................................33
Table 5-2. HGV Wastewater System Cost Summary ...........................................................................35
Sewer Master Plan and EIR Project
9552
iv November 2016
ACRONYMS AND ABBREVIATIONS
af/yr acre-feet per year
BOD Biological Oxygen Demand
CEQA California Environmental Quality Act
County San Diego County
EDU equivalent dwelling unit
EIR Environmental Impact Report
EQ equalization
d/D Depth to Diameter ratio
District Rincon Del Diablo Municipal Water District
gpd gallons per day
HGV Harmony Grove Village
HGVS Harmony Grove Village South
HGVWRF Harmony Grove Village Water Reclamation Facility
Hp horsepower
LAFCO Local Agency Formation Commission
LF Lineal feet
MLSS Mixed liquor suspended solids
MPN maximum potential number
N/A not applicable
NTU nephelometric turbidity units
O&M operation and maintenance
OWTS Onsite wastewater treatment system
PDWF Peak Dry Weather Flow
PWWF Peak Wet Weather Flow
RW Recycled Water
RWQCB Regional Water Quality Control Board
SWRCB State Water Resources Control Board
TDH total dynamic head
TSS Total Suspended Solids
VFD variable frequency drives
WRF Water Reclamation Facility
Sewer Master Plan and EIR Project
9552
v November 2016
ACKNOWLEDGEMENTS
We appreciate the combined efforts of the entire project team in the development and
preparation of the sewer master plan. Our project team includes staff from the District and
Dudek. The efforts of the following individuals are gratefully acknowledged for their
contributions to the completion of the evaluations presented in this report:
Rincon del Diablo Municipal Water District
Greg Thomas, General Manager
Clint Baze, Director of Engineering and Operations
Julia Escamilla, Public Service and Information Officer
Dudek
Michael Metts, PE, Principal/Project Manager
Kate Palmer, PE, Senior Engineer
Michael Hill, PE, Senior Engineer
Sarah Lozano, Principal Environmental Manager
Curtis Battle, GIS Analyst
Andrew Talbert, Environmental Analyst
Spencer Hardy, Environmental Analyst
Sewer Master Plan and EIR Project
9552
vi November 2016
Sewer Master Plan and EIR Project
9552
vii November 2016
INTENTIONALLY LEFT BLANK
Sewer Master Plan and EIR Project
9552
1 November 2016
ES EXECUTIVE SUMMARY
The primary purpose of the Rincon Del Diablo Municipal Water District (District) Sewer
Master Plan is to evaluate the feasibility of the District providing wastewater collection,
treatment and disposal service to residential customers located within the Harmony Grove
Village service area in northern San Diego County. Prior to provision of such wastewater
service, the District is required to petition the Local Agency Formation Commission (LAFCO)
for activation of its latent wastewater powers and definition of the District’s wastewater service
boundary. This master plan, and the accompanying Environmental Impact Report (EIR), provide
the information required by LAFCO to evaluate the District’s application and subsequently
establish the District’s wastewater service jurisdiction.
Wastewater service within the Harmony Grove Village (HGV) service areas currently includes
previously constructed collection and treatment facilities for the HGV community. Wastewater
generated within the community is conveyed to a local treatment facility, where it is treated to Title
22 recycled water standards. Recycled water is used for irrigation purposes within the community,
as well as in the greater District recycled water service area. As promulgated by the State of
California, recycled water provides for greater beneficial use in non-potable situations as it reduces
demand on potable water resources and costly imported water supplies. The District has been
providing recycled water within its service area for several years, acquiring recycled water from the
City of Escondido.
The District, with the intent of minimizing community effect and lowering overall cost, is
pursuing activation of its latent wastewater powers. The County of San Diego currently
provides wastewater service to the HGV service area. By taking over operation of the HGV
service area, the District would provide more local management and operation of wastewater
collection, treatment and disposal functions. As a part of its comprehensive approach to
effective wastewater management, LAFCO will also establish the wastewater planning area to
match the boundaries of the District’s current water service area. No wastewater service is
currently proposed or planned within the identified wastewater planning area, with the
exception of the existing HGV services. As such, the District wastewater service boundary will
be congruent with the existing HGV boundary.
ES.1 Background
The HGV development was previously approved by the County and is currently under
construction. The HGV community was approved to provide wastewater service through
construction of local wastewater conveyance and treatment facilities, to be owned and
operated by the County. The HGV Water Reclamation Facility (HGVWRF) is currently
constructed, and is proposed to begin processing tributary wastewater flows in approximately
Sewer Master Plan and EIR Project
9552
2 November 2016
the spring of 2017. Wastewater generation within the HGV community is currently collected
and hauled to a regional treatment facility, until the HGVWRF has sufficient flow to sustain
continuous operation.
Under current discussions, the County will divest itself of the HGVWRF and its associated
collection and conveyance facilities. The District, through LAFCO action, will become the
wastewater service provider for the HGV service area. As such, the District will be obligated
to provide safe, cost-effective wastewater service within its service area in accordance with
State and local regulations. This document defines projected wastewater generation within the
HGV service area, as well as existing and/or proposed facilities required for HGV wastewater
service. The overall goal is to reduce the overall cost of service to local customers within the
HGV wastewater service area.
The HGV community is the only community with County-approved sewer facilities within the
District’s proposed wastewater service area. The County has sole discretion with regard to
land use planning and decision making for the planning area. The District is not a land use
authority, and as such, will rely on and monitor County approval of any new development
within the planning area. Should the County identify future development within the District
planning area, it will be the County’s responsibility to determine available service options
relative to any new development, including wastewater service. LAFCO defines a planning area
as an area that identifies future boundaries, thereby alleviating potential unrepresented land
areas that do not have a designated service provider and facilitating future planning of efficient
and effective services. Preparation of this planning document assures that the District is
fulfilling its regulatory mandate of providing cost-effective and reliable water, recycled water
and wastewater service to its constituents, as required by appropriate government codes.
ES.2 Onsite Wastewater Treatment Systems
In evaluation of the HGVWRF, this study incorporates the requirements of the OWTS Policy
with respect to providing future sewer service to the HGV community. These evaluations
quantify the potential wastewater generation that are hydraulically tributary to the existing
wastewater collection system for the purposes of assuring that treatment capacity is available,
as required by current regulations. The planning study does not establish wastewater collection
and treatment criteria for properties outside the HGV service area, within the District planning
area. The housing densities of the HGV development requires construction of local treatment
facilities, as OWTSs are not permissible under current regulations.
Sewer Master Plan and EIR Project
9552
3 November 2016
ES.3 Water Reclamation Facility
As discussed, future development within the District planning area is not evaluated by this
study. Future County action is required for additional wastewater service, and the County will
evaluate any such options for collection, treatment and disposal.
The existing HGVWRF is designed to accommodate an average daily flow rate of 180,000
gallons per day (gpd). Based on evaluation of the HGVWRF, the following treatment processes
comprise the existing wastewater treatment train:
Influent Screen
Equalization Basin
Aero-Mod Treatment System (Aeration Basins, Secondary Clarifiers, Digesters)
Tertiary Filtration System
Chlorine Contact Tank
Off-Quality Storage Tank
Effluent Pumping
The existing process flow diagram for the HGVWRF facility is illustrated on Table ES-1.
Table ES-1. Existing HGVWRF Process Flow Diagram
Sewer Master Plan and EIR Project
9552
4 November 2016
ES.4 Wastewater Collection System
Evaluations for this analysis were confined to the existing wastewater conveyance plans for the
HGV community. Collected wastewater is conveyed to an existing pump station along
Harmony Grove Road, where it is pumped to the HGVWRF. These wastewater collection and
conveyance facilities are defined in the HGV planning and environmental documentation.
ES.5 Project Cost Opinions
Cost opinions are developed for the HGV collection and treatment systems, as well as
annual operation and maintenance costs.
Sewer Master Plan and EIR Project
9552
5 November 2016
INTRODUCTION 1
Discussions in this section provide an understanding of the previous planning within the HGV
service area, including activation of the District’s latent wastewater powers and formation of a
District wastewater service area.
1.1 Background
The District is located within northern San Diego County, within the greater Escondido Valley,
and formed in 1954. The District provides potable and recycled water service, structural fire
protection and advanced life support-level emergency medical service to its defined service area
(See Figure 1-1). The District currently serves water and recycled water to customers located
within the cities of Escondido, San Marcos, and San Diego, and within various unincorporated
areas of San Diego County. The District delivers potable and recycled water to a population of
approximately 30,000 through approximate 8,000 service connections, representing residential,
agricultural, landscape, and commercial/industrial water customers.
The District does not currently provide wastewater service within its water service boundary. It is
the District’s desire to petition LAFCO for activation of its latent wastewater powers, thereby
expanding its service offerings within its existing service boundary. Upon activation of these latent
powers, the District proposes to acquire the HGV community, currently located within
unincorporated portions of the County, areas to which the District currently provides potable and
recycled water service.
The HGV community is approved by the County, including wastewater conveyance and treatment
facilities. The HGVWRF construction is complete, and processing of tributary wastewater flows from
the HGV community will begin in approximately mid-2017. When placed into service, the County
Sanitation District will own and operate the HFVWRF. Wastewater generation within the HGV
community is currently collected and hauled to a regional treatment facility for disposal, until the
HGVWRF has sufficient flow to sustain continuous operation. Figure 1-2 illustrates the location of
HGV community and the HGVWRF, as well as the LAFCO-proposed wastewater-planning boundary.
The County and District are in negotiations for the District to take responsibility for operation
and maintenance of the HGVWRF. Ongoing County operation and maintenance of the HGV
wastewater system is projected to increase the cost of service, and result in complicated
contractual arrangements between the County and the District. The District is favorable to
acquiring the HGV collection and treatment facilities. As the new wastewater service provider,
the District is obligated to provide viable and cost-effective wastewater service within its
service area. As the HGVWRF is currently designed to accommodate the wastewater
generation of the HGV community, no additional treatment facilities are currently required.
Sewer Master Plan and EIR Project
9552
6 November 2016
Figure 1-1. Vicinity Map and District Water Service Boundary
Sewer Master Plan and EIR Project
9552
7 November 2016
Sewer Master Plan and EIR Project
9552
8 November 2016
Figure 1-2. Harmony Grove Service Area Communities
Sewer Master Plan and EIR Project
9552
9 November 2016
There are existing residential properties included within the proposed wastewater-planning
area, which are currently serviced by on-site septic systems. Any future development or
wastewater service within the wastewater planning boundary will require land use action by the
County. As such, the County will be ultimately responsible for identification and evaluation of
any such future development, including wastewater services. Furthermore, any properties
interested in shifting from septic to municipal wastewater service, as a result of potential septic
system failures or other reasons, will be required to submit such requests in the future and
appropriate planning evaluation will be conducted at that time. No wastewater service outside
the HGV community boundary is planned at this time.
The District’s intention is to increase responsiveness, service reliability and lower cost to HGV
residents by acquiring the HGV wastewater collection and treatment facilities. Through local
management, the District may reduce overall cost, increase operation and maintenance
efficiency, improve local water quality and controls, and maintain compliance with the San
Diego Regional Water Quality Control Board’s (RWQCB) Basin Plan. Furthermore, the local
community benefits when one local agency provide multiple services, as all customers are
assure to receive simultaneous service, while the community benefits from more sustainable
and resilient services.
1.2 Service Area Overview
The proposed wastewater service area encompasses only the HGV community, within
unincorporated areas of northern San Diego County, located west of the City of Escondido,
and south of the City of San Marcos. The District’s wastewater service area would be
congruent with the existing HGV community boundary. The proposed wastewater service area
is located within the District’s current water and recycled water service area. Through LAFCO
activation of the District’s latent wastewater powers, the District will provide water, recycled
water and wastewater service within its existing service area boundary, excluding any areas
currently served by the City of Escondido.
1.3 Land Use
Land use within the proposed service area is primarily rural residential. The HGV community is
comprised of residential and commercial land uses. Other land uses include a former rock
quarry, commercial, school, and institutional land uses. The planning and environmental reports
of the HGV community were approved by the County in 2007 and document the
environmental impact of this community (Final Environmental Impact Report for Harmony Grove
Village, February 2007).
The HGV community is the only community currently approved for construction within the
proposed wastewater planning area. The County has sole discretion with regard to land use
planning and decision-making. The District is not a land use authority, and as such, will rely on
Sewer Master Plan and EIR Project
9552
10 November 2016
County decisions related to any potential approval of new communities. Should any new
developments be identified, the County will define and evaluate future wastewater service
alternatives.
1.4 Onsite Wastewater Treatment Systems
The District is obligated to acknowledge the requirements of the current OWTS Policy with
respect to providing future sewer service. As required by current regulation, the District may
be required, in the future, to evaluate additional wastewater service. This study does not
quantify or evaluate potential future service requirements. As with the HGV community,
where housing densities exceed those allowed, local collection and treatment facilities may be
required. As discussed, these evaluations will be the responsibility of the County within the
identified wastewater planning area.
1.5 Sewer Master Plan Scope
The primary purpose of the District Sewer Master Plan is to provide the analyses required by
LAFCO in evaluating the District petition for wastewater powers activation. These
requirements include evaluating facilities needed for the District to provide wastewater
collection, treatment and disposal service to customers located within the HGV service area.
An Environmental Impact Report (EIR) is required to be prepared simultaneously with this
Sewer Master Plan, evaluating the potential impacts of the District’s Sewer Master Plan. The
District will be submitting its petition to LAFCO for activation of its latent wastewater powers
and establishment of its wastewater service area boundary (congruent with the HGV
community boundary).
Sewer Master Plan and EIR Project
9552
11 November 2016
Sewer Master Plan and EIR Project
9552
12 November 2016
INTENTIONALLY LEFT BLANK
Sewer Master Plan and EIR Project
9552
13 November 2016
EXISTING FACILITIES AND FLOW PROJECTIONS 2
The HGV community’s wastewater collection and treatment facilities are identified and a
portion have been constructed. The following discussions identify the existing facilities within
the HGV community.
2.1 HGV Wastewater Collection System
Approximately 50 percent of the HGV wastewater collection system is installed. As illustrated
by Figure 2-1, the wastewater collection system shown north of the red line is not currently
installed. South of the red line, the collection system is installed and homes are being
constructed. The existing and proposed collection system is comprised of 8- to 12-inch
diameter PVC gravity sewer pipelines, installed within paved roadways. Wastewater generated
within the HGV community is conveyed by gravity to the HGV sewer lift station (Figure 2-2),
located near Harmony Grove Road and Harmony Village Drive. The lift station includes three
pumps (two duty and one standby), with required standby power and wastewater emergency
storage to meet County and RWQCB standards. From the lift station, wastewater is pumped
through one of two 6-inch diameter PVC force mains to the HGVWRF. The HGVWRF is
designed to treat wastewater to Title 22 recycled water standards, which is subsequently
conveyed to recycled water users within the HGV community and into the larger District
recycled water distribution system for disposal.
The HGV community covers an area of approximately 468 acres, and includes 745 single-family
residential homes, live/work homes including retail space on the first floor, two designated
commercial sites, two-acre fire station site, two-acre institutional site, park areas, village hall
and the HGVWRF. The HGV community also includes recreational and open space areas,
including equestrian facilities, public parks and a local trail system.
Wastewater generation from the HGV community is defined in the previously prepared “Sewer
Study for Harmony Grove Village”, dated July 2014. The sewer study adheres to design criteria
promulgated by the San Diego County Sanitation District. County design criteria is included in
Table 2-1.
Based on the County criteria, the projected wastewater flow (Table 2-2) for the HGV
community is approximately 180,000 gpd, with a peak wastewater flow of approximately
380,000 gpd. The HGV wastewater collection system is sized based on the identified County
design criteria, and use of an Excel-based hydraulic model.
Sewer Master Plan and EIR Project
9552
14 November 2016
Figure 2-1. HGV Wastewater Collection System
1 – Figure from Sewer Study for Harmony Grove Village (VTM 5365), July 2014, Rick Engineering Company
Sewer Master Plan and EIR Project
9552
15 November 2016
Figure 2-2. HGV Sewer Lift Station
Sewer Master Plan and EIR Project
9552
16 November 2016
Table 2-1. HGV Sewer Design Criteria
Criteria
Single Family Home Wastewater Flow 240 Gallons/day/EDU
Minimum Sewer Diameter 8 Inches
Minimum Pipe Slope for 8-inch Diameter
Pipeline 0.4 Feet per 100 feet
Depth to Diameter ratio (d/D) for pipelines less
than or equal to 15-inch diameter 0.5 -
d/D for pipelines greater than 15-inch diameter 0.75 -
Manning Coefficient (n) 0.013 -
Commercial Flow rates 500 Gallons/day/acre
Institutional/Fire Station Flow Rates 1,500 Gallons/day/acre
Table 2-2. HGV Projected Wastewater Volumes
Site
Unit/Acres
Unit
(gpd/unit)
Average
Flow (gpd)
PDWF2
(gpd)
PWWF2
(gpd) HGV Development1
Single Family Residential 745 units 215 160,000 192,000 337,600
Commercial, Parks,
Institutional, Etc. N/A Various 20,000 24,000 42,200
Total 180,000 216,000 379,800
1 Data from Rick Engineering Sewer Study for Harmony Grove Village (July 2014) 2 PDWF = Peak Dry Weather Flow, PWWF = Peak Wet Weather Flow
2.2 HGV Water Reclamation Facility (HGVWRF)
The HGVWRF is located on an eight-acre site, located on the northeast corner of Harmony
Grove Road and Country Club Drive. Flows from the HGV collection system are conveyed to
the HGVWRF through the HGVWRF influent lift station. The HGVWRF has an average annual
capacity of 180,000 gpd, and treats wastewater to Title 22 disinfected tertiary recycled water
for distribution in the District’s recycled water distribution system.
Existing structures and processes at the HGVWRF include the operations building, headworks,
equalization basins, Aero-Mod biological treatment system, gravity sand filters, aerobic digesters,
process control/sludge dewatering building, chlorine contact tanks, effluent pump station, off-quality
storage, and wet weather storage. The wet weather storage basin is constructed within an existing
depression from a previous rock quarry. The HGVWRF site plan is illustrated on Figure 2-3.
Sewer Master Plan and EIR Project
9552
17 November 2016
Figure 2-3. Existing HGVWRF Site Layout
Sewer Master Plan and EIR Project
9552
18 November 2016
The effluent pump station discharges to the existing District recycled water system in Country
Club Drive, which includes a 16-inch recycled water distribution. The flow velocity (16-inch
pipeline) will be approximately 4.0 fps for ultimate maximum day conditions and approximately
4.7 fps under peak hour flow conditions. Therefore, the existing recycled water system has
sufficient capacity to convey the recycled water flows to the District’s R1 Reservoir.
Sewer Master Plan and EIR Project
9552
19 November 2016
WATER RECLAMATION EVALUATION 3
Wastewater service within the HGV service area currently include the collection and treatment
facilities required for the HGV community. Wastewater generated within the community is
conveyed to the local treatment facility (HGVWRF), where it is treated to Title 22 recycled
water standards. Recycled water is then used for irrigation purposes within the community, as
well as in the greater District recycled water service area. As promulgated by the State of
California, recycled water is preferable for non-potable water uses as it reduces demand on
potable water resources and reduces the demand on costly imported water supplies. The
District has been providing recycled water within its service area for several years, acquiring
recycled water from the City of Escondido.
3.1 HGVWRF Design Criteria
The HGVWRF is designed to treat an average daily flow of 180,000 gpd. As discussed in
Section 2, annual average wastewater generation within the local HGV service area is identified
to be approximately 180,000 gpd.
Wastewater systems experience fluctuations in flow on both a daily and seasonal basis. In
addition, wastewater volumes fluctuate during storm events, as rainwater may enter the
collection system and be conveyed to the treatment facility. To accommodate these known
fluctuations in tributary wastewater volume, treatment facilities are designed using a variety of
peaking factors, each being attributable to the various components of the treatment plant
depending on the impact these flow have on the treatment facilities. The HGVWRF design
incorporates such peaking factors to maintain required treatment process integrity, as
presented in Table 3-1.
Table 3-1. Influent Wastewater Flow Rate Design Criteria
Flow Scenario
Peaking
Factor
Flow Rate
(mgd) Applicable Process Components
Annual Average Day Flow 1.00 0.387 Storage Tanks
Maximum Month (Dry Weather) Flow 1.20 0.464 Biological treatment, Chlorine contact
tanks
Maximum Day (Wet Weather) Flow 2.11 0.817 Pumps, clarifiers, and filters
Maximum Peak-Hour (Wet Weather)
Flow 4.00 1.548 Influent screen
Note: mgd = million gallons per day
Within most treatment facilities, return flows are generated from various processes and move
water from one process to another. These return flows increase the flow to specific process
Sewer Master Plan and EIR Project
9552
20 November 2016
components, beyond those identified in Table 3-1, changing the required tankage and equipment
sizing. For the HGVWRF, return flows from on-site wet weather storage is returned to the
filtration and chlorination processes prior to distribution. These return flows, combined with
plant influent flow, are designed not to exceed the identified maximum day design capacity of the
affected facility. Similarly, backwash water from filters increases plant process flow, increasing the
required treatment capacity of downstream process components. Underflow from sludge
dewatering facilities similarly increase process flow for the treatment facilities. The HGVWRF
design accommodates necessary return flows for the defined treatment plant capacity, and these
flows are accounted for in analysis of the existing treatment capacity.
Equally important to the flow capacity of the HGVWRF is the quality of the tributary
wastewater. Higher strength wastewater, as measured by Biological Oxygen Demand (BOD),
Total Suspended Solids (TSS), and Total Ammonia as Nitrogen, increases the required size of
the treatment facilities. The HGVWRF accommodates existing influent wastewater strength
criteria as presented in Table 3-2
Table 3-2. Influent Wastewater Quality
Parameter Units Design
Biochemical Oxygen Demand (BOD), average mg/L 364
Total Suspended Solids (TSS), average mg/L 414
Ammonia as Nitrogen mg/L 53
Note: mg/L = milligrams per liter
As discussed, the HGV service area is an inland wastewater service area. As such, the
treatment plant does not have access to a land outfall to convey treated effluent to the Pacific
Ocean for ultimate disposal, as coastal treatment facilities may have. For this reason, the
HGVWRF recycles water for ultimate disposal by irrigation of local and regional non-potable
water demands. On a daily and annual basis, wastewater production is treated and distributed
to completely dispose of wastewater generated within the service area.
The HGVWRF, as an inland treatment facility, is required to treat tributary wastewater volumes to
Title 22 tertiary standards suitable for unrestricted reuse. Protection of groundwater resources is
promulgated in the Water Quality Control Plan for the San Diego Basin (Region 9, hereinafter
referred to as the Basin Plan). Based on the HGVWRF discharge permits and the local Basin Plan,
effluent requirements for the HGVWRF are presented in Table 3-3.
Table 3-3. Projected WRF Effluent Limits
Constituent Units Effluents Limits
Sewer Master Plan and EIR Project
9552
21 November 2016
Daily Maximum Monthly Average 12-Month Average
BOD5 mg/L 45 30 -
Suspended Solids mg/L 45 30 -
Total Nitrogen (as
nitrogen)
mg/L - - 15
Total Dissolved Solids mg/L - - 1,000
pH - 6.5 – 8.5 at all times
Total Coliform MPN/100
ml
23 2.2 (7-day average) -
Turbidity NTU 2 (Max for up to 5% of time/24 hours)
5 (Max at any time)
Note: MPN = maximum potential number, NTU = nephelometric turbidity units
3.2 HGVWRF Capacity
Design criteria, discussed above, establish the capabilities of each process in the HGVWRF
treatment train. Accurately defining the existing capacity of individual HGVWRF treatment process
is critical. Table 3-4 illustrates the process flow diagram of the HGVWRF.
In the following discussions, the capacity of each process unit in the HGVWRF is analyzed to
identify the available treatment.
Table 3-4. Existing HGVWRF Process Flow Diagram
Sewer Master Plan and EIR Project
9552
22 November 2016
3.2.1 Influent Screen
The influent lift station and force mains convey wastewater from the collection systems to the
HGVWRF for treatment. The influent force mains discharge into the headworks channels,
where the wastewater flows into a single rotating drum screen. A bypass channel is provided
with a manual bar rack, to accommodate maintenance of the rotating drum screen. The
computed capacity of these facilities is presented in Table 3-5.
Table 3-5. Existing Influent Screen Capacity Analysis
Parameter Units Design Criteria / Notes
Number of existing units - 1 With bypass manual bar rack
Design capacity per unit gpm 900 Manufacturer specification
Total existing capacity gpm 900 -
3.2.2 Equalization Basins
The screened wastewater flows by gravity to a splitter box, where influent is diverted to the
equalization (EQ) basins. The equalization basins limit flow rate fluctuations by pumping from
the basins at a constant flow rate, allowing water level in the basins to fluctuate throughout the
day. Two EQ basins are constructed, in a duty/standby configuration, to allow for inspection,
maintenance, and rehabilitation of each basin independently. These basins are aerated to keep
the influent wastewater mixed and to avoid odor production. The capacity of these facilities is
presented in Table 3-6.
Table 3-6. Equalization Basins Capacity Analysis
Parameter Units Design Criteria / Notes
Number of existing units - 2 1 duty / 1 standby
Volume per unit gal 49,000 -
Design detention time hrs 6 Existing criteria
Existing capacity per unit gpd 196,000 -
Total existing capacity gpd 196,000 -
Sewer Master Plan and EIR Project
9552
23 November 2016
3.2.3 Aero-Mod System (Biological Treatment System)
Wastewater treatment is a biological process, by which microorganisms are used to eliminate
waste products in the water. For the HGVWRF, influent wastewater is pumped from the EQ
basins, at a constant rate, into the Aero-Mod system splitter box. Biological treatment is
provided within the Aero-Mod SEQUOX BNR, a proprietary aerobic extended aeration
process combined with contiguous anoxic denitrification, clarifiers, and aerobic digesters. These
unit processes are constructed within multiple common-wall concrete tanks. Based on
evaluation of HGVWRF capacity, the capacity analysis for the Aeration Basins, Secondary
Clarifiers, and Digesters is presented in Table 3-7, 3-8 and 3-9, respectively.
Table 3-7. Existing Aeration Basins Capacity Analysis
Parameter Units Design Criteria / Notes
Number of trains - 4 4 duty / 0 standby
Volume per train gal 62,000 -
Total existing volume gal 248,000 -
Design organic loading BOD lb/103cf-
d
20 Existing manufacturer criteria
Total existing treatment
capacity
gpd 223,000 -
Table 3-8. Existing Secondary Clarifier Capacity Analysis
Parameter Units Design Criteria / Notes
Number of units - 4 4 duty / 0 standby
Surface area per units sf 192 -
Design overflow rate gpd/sf 600 Existing manufacturer criteria
Design solids loading lb/d/sf 27.9 Existing manufacturer criteria
Design MLSS mg/L 3,500 Existing manufacturer criteria
Total existing capacity gpd 507,000 (Overflow rate governs)
Table 3-9. Existing Aerobic Digester Capacity Analysis
Parameter Units Design Criteria / Notes
Number of existing units - 4 4 duty / 0 standby
Volume per unit gal 24,000 -
Total existing volume gal 96,000 -
Sewer Master Plan and EIR Project
9552
24 November 2016
Table 3-9. Existing Aerobic Digester Capacity Analysis
Parameter Units Design Criteria / Notes
Required wasting rate gpd 7,893 Based on manufacturer
calculations
Sludge age Days 25 Existing criteria
3.2.4 Tertiary Filtration
Secondary clarifier effluent is conveyed by gravity to the tertiary filtration structure. The
packaged tertiary filtration systems include flash mixing basins, flocculation basins, gravity sand
filter cells, underdrains, mud well, clear well, backwash pumps, and air scour blowers. Similarly,
the capacity of these facilities, with the associated mixers, pumps, and blowers, is presented in
Table 3-10.
Table 3-10. Existing Tertiary Filtration Capacity Analysis
Parameter Units Design Criteria / Notes
Number of existing cells - 5 3 duty / 1 in backwash / 1 standby
Surface area per unit sf 21 -
Filter rate gpm/sf 5 Title 22 Limit
Existing capacity per unit gpd 151,000 -
Total existing capacity gpd 453,000 -
3.2.5 Chlorine Contact Tanks
Effluent from the filtration system is conveyed by gravity to the chlorine rapid mix vault and
subsequently to the Chlorine Contact Tanks. Based on review of the HGVWRF design, the
capacity of these facilities is presented in Table 3-11.
Table 3-11. Existing Chlorine Contact Tank Capacity Analysis
Parameter Units Design Criteria / Notes
Number of existing passes - 2 2 duty
Volume per pass gal 16,000 -
Detention time min 90 HGVWRF Waste Discharge
Requirements
Estimated Baffling Factor - 0.65 Based on geometry and
configuration
Sewer Master Plan and EIR Project
9552
25 November 2016
Existing capacity per unit gpd 166,000 -
Total existing capacity gpd 332,000 -
3.2.6 Effluent Pump Station
Disinfected tertiary effluent (recycled water) is conveyed from the Chlorine Contact Tank to
the Tertiary Effluent Clear Well / Pump Station Wet Well. The recycled water is then pumped
into the District’s recycled water system for delivery to end users. The capacity of these
facilities is presented in Table 3-12.
Table 3-12. Existing Effluent Pump Station Capacity Analysis
Parameter Units Design Criteria / Notes
Number of existing units - 3 2 duty / 1 standby
Capacity of each unit gpm 188 Manufacturer specification
Total existing capacity gpm 376 -
The effluent pump station discharges to the District recycled water system in Country Club
Drive. The District recent constructed the 16-inch recycled water distribution main as a part
of its R1 Reservoir Conversion Project. The flow velocity in the 16-inch pipeline will be
approximately 4.0 fps for ultimate maximum day conditions. Under peak hour flow conditions,
the maximum flow velocity would be 4.7 fps. Therefore, the recycled water system has
sufficient capacity to convey recycled water flow to the R1 Reservoir.
3.2.7 Off-Quality Storage Basins
As protection during emergency situations, recycled water treatment facilities include storage
to which effluent not meeting the required discharge standards can be discharged. The “off-
quality” water is stored while the process anomaly is corrected, and then pumped back into the
treatment process. The off-quality tank is typically sized to provide 24 hours of storage, as
required by California Title 22 redundancy requirements. The capacity of these facilities is
shown in Table 3-13.
Table 3-13. Existing Off-Quality Storage Capacity Analysis
Parameter Units Design Criteria / Notes
Number of existing units - 1 -
Volume per unit gal 182,000 -
Design detention time hr 24 Title 22 redundancy requirements
Sewer Master Plan and EIR Project
9552
26 November 2016
Table 3-13. Existing Off-Quality Storage Capacity Analysis
Parameter Units Design Criteria / Notes
Existing capacity per unit gpd 182,000 -
Total existing capacity gpd 182,000 -
3.2.8 Sludge Dewatering Centrifuge Pumps
Sludge, or biosolids, is the resulting materials following the wastewater treatment process.
These solids are aerated in digesters to make the materials suitable for landfill disposal. The
digested sludge is pumped from the aerobic digesters to the Sludge Dewatering Centrifuge.
The capacity of these facilities is presented in Table 3-14.
Table 3-14. Existing Sludge Dewatering Centrifuge Capacity Analysis
Parameter Units Design Criteria / Notes
Number of existing units - 1 -
Capacity of each unit gpm 80 Manufacturer specification
Total existing capacity gpm 80 -
3.2.9 Wet Weather Storage
During the wet weather events, recycled water facilities operate under normal conditions,
while recycled water irrigation demand decreases. The Regional Water Quality Control Board
requires that excess treated effluent be discharged either to storage facilities or to a fail-safe
land outfall connection to an ocean outfall. If neither exist, the Regional Board requires storage
facilities to maintain 84 days of wet weather storage, unless water balance calculations
demonstrate that less volume is adequate based on available year-round recycled water
demand. The Wet Weather Storage capacity is presented in Table 3-15.
Table 3-15. Existing Wet Weather Storage Capacity Analysis
Parameter Units Design Criteria / Notes
Number of existing
basins
- 1 -
Days of storage days 84 Regional Board Requirement
Volume of basin gal 16,000,000 -
Sewer Master Plan and EIR Project
9552
27 November 2016
Based on review of the District’s recycled water system and associated demands, the HGVWRF
will be able to safely discharge treated recycled water into the District’s existing recycled water
distribution system on an annual basis. Recycled water will be conveyed to the 3,000,000-gallon
R-1A recycled water storage tank, which will be connected to the District’s ID-1 South
recycled water service area. The District’s current annual average recycled water demand is
approximately 3,030 acre-feet per year (af/yr) or 2.7 mgd. The District’s largest recycled water
demand is related to cooling water for the 550-megawatt Sempra Energy plant, having an
annual average demand of 2.4 mgd, which accounts for approximately 90 percent of the
District’s total annual recycled water production. Other recycled water demands are primarily
irrigation and account for an annual average demand of approximately 0.30 mgd. These demand
values do not include new irrigation demand for the HGV community.
Recycled water demand during the winter for customers other than the Energy Plant equates
to 0.09 mgd, assuming a minimum-month factor of 30 percent. The Energy Plant’s recycled
water demand is typically operational year-round, except for scheduled maintenance and shut
down for a two-week period each year, typically in the spring. A two week shut down in the
winter months requires approximately 4-million gallons of wet weather storage, which is
accommodated by the HGVWRF wet weather storage basin. As such, the existing wet weather
storage has sufficient capacity to accommodate the required off-quality storage volumes for the
entire plant.
Sewer Master Plan and EIR Project
9552
28 November 2016
INTENTIONALLY LEFT BLANK
Sewer Master Plan and EIR Project
9552
29 November 2016
COLLECTION SYSTEM CAPACITY EVALUATION 4
Assuming LAFCO grants the District’s petition for activation of its latent wastewater, the
District will be required to own and operate the HGV conveyance and treatment facilities. As
such, it is necessary to understand the existing conveyance system capabilities. To date,
approximately half of the HGV collection system is constructed, as identified in Section 3.
4.1 Design Criteria
As a water and recycled water agency, the District does not currently promulgate wastewater
standard specifications and details. For this reason, Dudek compared commonly implemented
wastewater design criteria from five similar public agencies to establish design criteria for this
evaluation. Criteria used by other local agencies is shown in Table 4-1.
Table 4-1. Sewer Design Criteria Comparison
Design
Criteria
San Diego
County
City of
Escondido
Leucadia
Wastewater
District
Vallecitos
Municipal
Water
District
Rainbow
Municipal
Water
District
Minimum Size 8-inches 8-inches 8-inches 8-inches 8-inches
Minimum Slope
(8”)
Designed to
provide
desired
velocities
0.50% 0.40% 0.40% 0.40%
Minimum Slope
(12” and larger)
Designed to
provide
desired
velocities
0.30% 0.25%2 0.22%2 0.24%
Mannings “n” 0.013 N/A 0.013 0.013 0.013
Minimum
Velocity (ft/s) 2 2 2 2 2
Maximum d/D
(
Sewer Master Plan and EIR Project
9552
30 November 2016
From the identified neighboring agency design criteria, the design criteria used for this
evaluation is shown in Table 4-2. These criteria are used throughout this report to evaluate
conveyance capacity for the collection system.
Table 4-2. Proposed District Design Criteria
Design Criteria
Rincon del Diablo
Municipal Water District
Minimum Size 8-inches
Minimum Slope (8”) 0.4%
Minimum Slope (12” and larger) 0.25%
Manning “n” 0.013
Minimum Velocity (ft/s) 2
Maximum d/D (
Sewer Master Plan and EIR Project
9552
31 November 2016
one-quarter full. Appendix A provides the master sewer summary for the HGV collection
system from the original analysis.
4.3 HGV Lift Station
The existing HGV lift station is designed to accommodate 180,000 gpd average flow and a
378,000-gpd maximum day flow, based on serving the HGV community. To accommodate
these flows, the existing HGV lift station has three vertical centrifugal sewer pumps rated at
250 gpm, with 20 horsepower (Hp) motors, at 86 feet total dynamic head (TDH). The HGV lift
station pumps are constant speed pumps. It may be reasonable to consider variable frequency
drives (VFDs) I the future when the existing pumps are replaced. The HGV lift station has two
6-inch diameter, 1,800 LF force mains connecting the lift station to the HGVWRF. Based on
HGV flow projections, the 6-inch force mains will flow at velocity of approximately 6.0 ft/s
through a single force main.
Sewer Master Plan and EIR Project
9552
32 November 2016
INTENTIONALLY LEFT BLANK
Sewer Master Plan and EIR Project
9552
33 November 2016
PRELIMINARY OPINION OF PROBABLE COST 5
The following opinion of probable cost (cost opinion) serves to establish an order of magnitude
cost for the HGV wastewater facilities. The cost opinion is based on the quantities and unit
price estimates developed from the planning level concepts, quotations from general
contractors, vendor quotes, and existing site conditions. The cost opinion is also based on
actual costs, where known, for the HGVWRF and associated facilities.
5.1 Cost Opinion Methodology and Assumptions
For the purposes of this analysis, the cost opinion is considered a Class 4 Construction Cost
Opinion, based on the feasibility level analysis completed. The cost opinion makes use of
quantity takeoffs, vendor/supplier/manufacturer quotations, actual HGV construction costs, and
recent contract bid award data in the development of projected costs. Table 5-1, below,
provides definition of the various Cost Opinion Classes.
Table 5-1. Summary of Construction Cost Classes
COST
OPINION
Class
Primary
Characteristic Secondary Characteristic
Level of Project
Definition Expressed as % of
Complete Definition
End Usage Typical Purpose of
Cost Opinion
Methodology Typical
estimating method
Expected
Accuracy Range Typical Variation In
Low And High
ranges (a)
Preparation
Effort Typical Degree of
effort relative To Least Cost Index of
1(b)
Class 5 0% to 2% Concept
Screening
Capacity
Factored.
Parametric
Models.
Judgment or
Analogy
L: -20% to -50%
H: +30% to +100%
1
Class 4 1% to 15% Study or
Feasibility
Equipment
Factored or
Parametric
Model
L: -15% to -30%
H: +20% to +50%
2 to 4
Class 3 10% to 40% Budget
Authorization, or
Control
Semi-Detailed
Unit Costs with
Assembly Level
Line Items
L: -10% to -20%
H: +10% to +30%
3 to 10
Sewer Master Plan and EIR Project
9552
34 November 2016
COST
OPINION
Class
Primary
Characteristic Secondary Characteristic
Level of Project
Definition Expressed as % of
Complete Definition
End Usage Typical Purpose of
Cost Opinion
Methodology Typical
estimating method
Expected
Accuracy Range Typical Variation In
Low And High
ranges (a)
Preparation
Effort Typical Degree of
effort relative To Least Cost Index of
1(b)
Class 2 30% to 70% Control or Bid/
Tender
Detailed Unit
Cost with
Forced
Detailed Take-
Off
L: -5% to -15%
H: +5% to +20%
4 to 20
Class 1 50% to 100% Check Estimate
or Bid/Tender
Detailed Unit
Cost with
Detailed
Take-Off
L: -3% to -10%
H: +3% to +15%
5 to 100
Notes: (a) The state of process technology and availability of applicable reference cost data affect the range markedly. The +/- value represents
typical percentage variation of actual costs from the cost estimate after application of contingency (typically at a 50% level of confidence) for given scope.
(b) If the range index value of "1" represents 0.005% of project costs, then an index value of 100 represents 0.5%. Estimate preparation effort is highly dependent upon the size of the Project and the quality of estimating data and tools.
5.2 Wastewater Treatment Cost Opinion
The costs presented in Table 5-2 represent an order of magnitude cost of the proposed
wastewater treatment facilities, as defined in Section 4. Unit costs are based on recent similar
project bid results, vendor quotes and bid results from the existing HGVWRF construction.
5.3 Collection System Cost Opinion
The costs presented in Table 5-2 represent the order of magnitude cost of the proposed
wastewater conveyance facilities as defined in Section 4. Unit costs for pipeline installation are
assumed conservatively at a cost of $15 per inch-diameter per lineal foot.
5.4 Opinion of Probable Annual Costs
The District is petitioning LAFCO for activation of its latent wastewater powers and
establishment of its wastewater planning area. Upon LAFCO approval, the District will acquire
the HGVWRF from the County and take over ongoing operation and maintenance of that
facility. No additional wastewater facilities are planned to be constructed and annual operation
and maintenance (O&M) costs are based on the existing plant and the HGV collection system.
Sewer Master Plan and EIR Project
9552
35 November 2016
As the HGVWRF has not currently begun full operations, it is not possible to definitively
identify the annual O&M costs for the facility. Based on analysis of the HGVWRF and County
Sanitation District data, the projected annual cost is $594,000.
Annual costs include energy and O&M costs for conveyance and pumping, as well as for annual
treatment costs. O&M costs are based on typical cost metrics from literature and previous
projects. Energy costs are estimated using a unit price of $0.15 per kWh. Labor costs are
based on a total compensation of $150,000 per year, including salary, benefits, and insurance.
5.5 Capital Cost Per Equivalent Dwelling Unit
The cost opinion provided in Table 5-2 addresses the financial impacts of constructing and
operating the identified facilities, based on the projected wastewater service and the
assumptions contained therein. Construction of the identified facilities was the responsibility of
the developer building the HGV community. Ongoing annual O&M costs are the responsibility
of the County, until LAFCO takes action to grant the District’s petition for activation of its
latent wastewater powers. At that time, the District will become responsible for annual O&M
of the facilities. The District will then evaluate current costs and acquire the initial O&M costs
established by the County rate structure, such that wastewater customers pay the cost of the
ongoing O&M cost. Table 5-2 provides a calculation of the wastewater service costs, including
the total capital and annual costs of each option.
Table 5-2. HGV Wastewater System Cost Summary
Description Cost
Community served HGV
Total EDUs 745
Water Reclamation Facility
Construction Costs $12,400,000
Soft Costs $3,100,000
Total Capital $15,500,000
O&M (Annual) Costs $451,000
Collection System
Construction Costs $13,859,000
Soft Costs $1,663,000
Total Capital $15,522,000
O&M (Annual) Costs $143,000
Total Combined Facilities
Construction Costs $26,259,000
Sewer Master Plan and EIR Project
9552
36 November 2016
Description Cost
Soft Costs $4,763,000
Total Capital $31,022,000
O&M (Annual) Costs $594,000
Present Worth & Equivalent Annual Cost
Present Worth of O&M Cost $15,011,000
Total Present Worth Cost $46,033,000
Equivalent Annual Cost $2,503,000
Cost Per Equivalent Dwelling Unit (EDU)
Total Present Worth per EDU $61,400
Equivalent Annual Cost per EDU $3,340
1. Identified costs represent the total invested cost of the HGVWRF facilities construction 2. Recycled water is assumed distributed through the District recycled water system
The HGV community has constructed a wastewater collection system and the HGVWRF for its
wastewater disposal requirements. Based on available records, the HGVWRF and associated
collection system construction cost was approximately $26,259,000, with annual costs of
approximately $594,000 per year. Based on an assumed 30-year return period and an interest
rate of 3.5 percent, the equivalent annual cost is approximately $2,500,000. As the HGV serves
a total constituency of approximately 750 equivalent dwelling units (EDUs), the equivalent
annual cost per EDU is approximately $3,340 per EDU. This value represents the equivalent
annual cost to each household over a 30-year period.
Sewer Master Plan and EIR Project
9552
37 November 2016
CONCLUSIONS 6
Based on the evaluation in this report, it is recommended that the District continue
forward with completion of its environmental documentation efforts, and petition to
LAFCO for activation of its latent wastewater powers and definition of its wastewater
service boundary. Following LAFCO action, the District should continue its discussion with
the County with regard to acquiring the HGVWRF and associated collection system.
Sewer Master Plan and EIR Project
9552
38 November 2016
INTENTIONALLY LEFT BLANK
APPENDIX A HGV Master Sewer Summary
JOB NO. J-17008
MASTER SEWER SUMMARYHARMONY GROVE VILLAGE
PREPARED BY RICK ENGINEERING COMPANY 7/20/2016
LINE FROM TO POPULATION CUM. EDU CUMULATIVE PEAK/AVG LINE DESIGN dn(FT) VELOCITYNO. M.H. M.H. PER D.U. UPSTREAM IN LINE CUMULATIVE POP RATIO SIZE SLOPE n= dn/D Rh (fps) Comments
MANHOLE D.U.'S DU's SERVED M.G.D. CFS (INCHES) (%) 0.013 (ft)100 Series
131A 131 3.0 0 5 5 15 4.00 0.005 0.007 8 1.00 0.03 0.05 0.02 0.9131 130 3.0 5 2 7 21 4.00 0.007 0.010 8 1.00 0.04 0.06 0.03 1.0133 132 3.0 0 6 6 18 4.00 0.006 0.009 8 2.00 0.03 0.05 0.02 1.3132 130 3.0 6 3 9 27 4.00 0.009 0.013 8 1.22 0.05 0.07 0.03 1.2130 127 3.0 16 1 17 51 4.00 0.016 0.025 8 5.38 0.04 0.06 0.03 2.3129 128 3.0 0 6 6 18 4.00 0.006 0.009 8 1.99 0.03 0.05 0.02 1.3128 127 3.0 6 8 14 42 4.00 0.013 0.021 8 1.89 0.05 0.07 0.03 1.5127 117 3.0 31 0 31 93 4.00 0.030 0.046 8 5.43 0.05 0.08 0.03 2.8120 119 3.0 0 5 5 15 4.00 0.005 0.007 8 4.57 0.02 0.03 0.01 1.4119 117 3.0 5 2 7 21 4.00 0.007 0.010 8 1.32 0.04 0.06 0.03 1.1126 124 3.0 0 1 1 3 4.00 0.001 0.001 8 6.31 0.01 0.01 0.00 0.8125 124 3.0 0 6 6 18 4.00 0.006 0.009 8 2.75 0.03 0.04 0.02 1.3124 122 3.0 7 0 7 21 4.00 0.007 0.010 8 3.61 0.03 0.04 0.02 1.5123 122 3.0 0 4 4 12 4.00 0.004 0.006 8 4.75 0.02 0.03 0.01 1.4122 121 3.0 11 7 18 54 4.00 0.017 0.027 8 3.07 0.05 0.07 0.03 1.9121 117 3.0 18 7 25 75 4.00 0.024 0.037 8 1.38 0.07 0.11 0.05 1.7117 115a 3.0 63 0 63 189 4.00 0.060 0.094 8 1.00 0.12 0.18 0.07 2.0115a 115 3.0 63 0 63 189 4.00 0.060 0.094 8 10.41 0.07 0.10 0.04 4.5116 115 3.0 0 3 3 9 4.00 0.003 0.004 8 3.36 0.02 0.03 0.01 1.2 Vertical Curve115 114 3.0 66 0 66 198 4.00 0.063 0.098 8 8.46 0.07 0.11 0.05 4.3114 113 3.0 66 0 66 198 4.00 0.063 0.098 8 8.08 0.07 0.11 0.05 4.2136 134 3.0 0 1 1 3 4.00 0.001 0.001 8 1.44 0.01 0.02 0.01 0.6135 134 3.0 0 8 8 24 4.00 0.008 0.012 8 2.00 0.03 0.05 0.02 1.3134 113 3.0 9 0 9 27 4.00 0.009 0.013 8 2.07 0.04 0.06 0.03 1.4113 112 3.0 75 0 75 225 3.92 0.071 0.109 8 3.64 0.09 0.14 0.06 3.3112 111 3.0 75 0 75 225 3.92 0.071 0.109 8 3.73 0.09 0.14 0.06 3.3111 110 3.0 75 0 75 225 3.92 0.071 0.109 8 5.01 0.09 0.13 0.05 3.7110 109 3.0 75 0 75 225 3.92 0.071 0.109 8 1.48 0.12 0.18 0.07 2.4109 108 3.0 75 1 76 228 3.91 0.071 0.110 8 3.07 0.10 0.15 0.06 3.1108 107 3.0 76 2 78 234 3.89 0.073 0.113 8 0.83 0.14 0.21 0.08 2.0
107 106 3.0 78 5 83 249 3.84 0.076 0.118 8 2.00 0.11 0.17 0.07 2.7 Connect to exist. plug, see Unit 6, Sheet 6
POPULATION SERVED PEAK DESIGN FLOW
1
JOB NO. J-17008
MASTER SEWER SUMMARYHARMONY GROVE VILLAGE
PREPARED BY RICK ENGINEERING COMPANY 7/20/2016
LINE FROM TO POPULATION CUM. EDU CUMULATIVE PEAK/AVG LINE DESIGN dn(FT) VELOCITYNO. M.H. M.H. PER D.U. UPSTREAM IN LINE CUMULATIVE POP RATIO SIZE SLOPE n= dn/D Rh (fps) Comments
MANHOLE D.U.'S DU's SERVED M.G.D. CFS (INCHES) (%) 0.013 (ft)
POPULATION SERVED PEAK DESIGN FLOW
145 140 3.0 0 2 2 6 4.00 0.002 0.003 8 1.00 0.02 0.03 0.01 0.6140 138 3.0 2 1 3 9 4.00 0.003 0.004 8 1.00 0.03 0.04 0.02 0.8139 138 3.0 0 8 8 24 4.00 0.008 0.012 8 7.00 0.03 0.04 0.02 2.0138 137 3.0 11 0 11 33 4.00 0.011 0.016 8 1.00 0.05 0.08 0.03 1.2137 147 3.0 11 1 12 36 4.00 0.012 0.018 8 8.18 0.03 0.05 0.02 2.5147 106 3.0 12 0 12 36 4.00 0.012 0.018 8 3.09 0.04 0.06 0.03 1.8106 105 3.0 95 3 98 294 3.69 0.087 0.134 8 4.09 0.10 0.15 0.06 3.6105 104 3.0 98 3 101 303 3.66 0.089 0.137 8 1.00 0.15 0.22 0.09 2.3104 103 3.0 101 0 101 303 3.66 0.089 0.137 8 1.00 0.15 0.22 0.09 2.3103 102 3.0 101 0 101 303 3.66 0.089 0.137 8 6.63 0.09 0.14 0.06 4.4144 143 3.0 0 8 8 24 4.00 0.008 0.012 8 2.00 0.03 0.05 0.02 1.3143 141 3.0 8 0 8 24 4.00 0.008 0.012 8 3.94 0.03 0.05 0.02 1.8142 141 3.0 0 8 8 24 4.00 0.008 0.012 8 2.00 0.03 0.05 0.02 1.3141 102 3.0 16 0 16 48 4.00 0.015 0.024 8 4.61 0.04 0.06 0.03 2.1102 101 3.0 117 0 117 351 3.50 0.098 0.152 8 8.96 0.09 0.13 0.05 4.9101 100 3.0 117 3 120 360 3.47 0.100 0.154 8 0.75 0.17 0.25 0.10 2.1100 99 3.0 120 1 121 363 3.46 0.100 0.155 8 0.75 0.17 0.26 0.10 2.199 9 3.0 121 3 124 372 3.43 0.102 0.158 8 0.88 0.17 0.25 0.10 2.3
2
JOB NO. J-17008
MASTER SEWER SUMMARYHARMONY GROVE VILLAGE
PREPARED BY RICK ENGINEERING COMPANY 7/20/2016
LINE FROM TO POPULATION CUM. EDU CUMULATIVE PEAK/AVG LINE DESIGN dn(FT) VELOCITYNO. M.H. M.H. PER D.U. UPSTREAM IN LINE CUMULATIVE POP RATIO SIZE SLOPE n= dn/D Rh (fps) Comments
MANHOLE D.U.'S DU's SERVED M.G.D. CFS (INCHES) (%) 0.013 (ft)
POPULATION SERVED PEAK DESIGN FLOW
200 Series224 223 3.0 0 4 4 12.0 4.00 0.004 0.006 8 1.00 0.03 0.05 0.02 0.9223 222c 3.0 4 0 4 12.0 4.00 0.004 0.006 8 1.00 0.03 0.05 0.02 0.9222c 222b 3.0 4 0 4 12.0 4.00 0.004 0.006 8 1.00 0.03 0.05 0.02 0.9222b 222a 3.0 4 0 4 12.0 4.00 0.004 0.006 8 1.00 0.03 0.05 0.02 0.9222a 222 3.0 4 0 4 12.0 4.00 0.004 0.006 8 2.21 0.03 0.04 0.02 1.1222 220 3.0 4 0 4 12.0 4.00 0.004 0.006 8 1.00 0.03 0.05 0.02 0.9221 220 3.0 0 3 3 9.0 4.00 0.003 0.004 8 8.98 0.01 0.02 0.01 1.5220 218 3.0 7 0 7 21.0 4.00 0.007 0.010 8 2.43 0.03 0.05 0.02 1.4219 218 3.0 0 8 8 24.0 4.00 0.008 0.012 8 2.00 0.03 0.05 0.02 1.3218 217 3.0 15 0 15 45.0 4.00 0.014 0.022 8 1.00 0.06 0.09 0.04 1.3213 217 3.0 0 1 1 3.0 4.00 0.001 0.001 8 9.10 0.01 0.01 0.00 0.9217 216 3.0 16 0 16 48.0 4.00 0.015 0.024 8 6.25 0.04 0.06 0.03 2.5216 215 3.0 16 0 16 48.0 4.00 0.015 0.024 8 5.22 0.04 0.06 0.03 2.3215 214 3.0 16 5 21 63.0 4.00 0.020 0.031 8 2.36 0.06 0.09 0.04 2.0212 211 3.0 0 8 8 24.0 4.00 0.008 0.012 8 2.00 0.03 0.05 0.02 1.3211 210 3.0 8 0 8 24.0 4.00 0.008 0.012 8 4.50 0.03 0.04 0.02 1.6210 207 3.0 8 3 11 33.0 4.00 0.011 0.016 8 5.08 0.03 0.05 0.02 2.0209 208 3.0 0 8 8 24.0 4.00 0.008 0.012 8 2.00 0.03 0.05 0.02 1.3208 207 3.0 8 0 8 24.0 4.00 0.008 0.012 8 4.07 0.03 0.05 0.02 1.8207 206 3.0 19 3 22 66.0 4.00 0.021 0.033 8 4.34 0.05 0.07 0.03 2.3206 205 3.0 22 4 26 78.0 4.00 0.025 0.039 8 2.10 0.07 0.10 0.04 2.0205 214 3.0 26 5 31 93.0 4.00 0.030 0.046 8 5.22 0.05 0.08 0.03 2.8214 204 3.0 52 0 52 156.0 4.00 0.050 0.077 8 1.15 0.11 0.16 0.07 2.0204 203a 3.0 52 1 53 159.0 4.00 0.051 0.079 8 1.16 0.11 0.16 0.07 2.0203a 203 3.0 53 1 54 162.0 4.00 0.052 0.080 8 16.51 0.05 0.08 0.03 4.9
203 202 3.0 54 0 54 162.0 4.00 0.052 0.080 8 3.85 0.08 0.12 0.05 3.1 Connect to exist. plug, see Unit 5, Sheet 16202 201 3.0 54 0 54 162.0 4.00 0.052 0.080 8 4.79 0.07 0.11 0.05 3.2201 200 3.0 54 0 54 162.0 4.00 0.052 0.080 8 13.07 0.06 0.09 0.04 4.7
3
JOB NO. J-17008
MASTER SEWER SUMMARYHARMONY GROVE VILLAGE
PREPARED BY RICK ENGINEERING COMPANY 7/20/2016
LINE FROM TO POPULATION CUM. EDU CUMULATIVE PEAK/AVG LINE DESIGN dn(FT) VELOCITYNO. M.H. M.H. PER D.U. UPSTREAM IN LINE CUMULATIVE POP RATIO SIZE SLOPE n= dn/D Rh (fps) Comments
MANHOLE D.U.'S DU's SERVED M.G.D. CFS (INCHES) (%) 0.013 (ft)
POPULATION SERVED PEAK DESIGN FLOW
300 Series318 317 3.0 0 6 6 18.0 4.00 0.006 0.009 8 5.51 0.03 0.04 0.02 1.8317 316 3.0 6 10 16 48.0 4.00 0.015 0.024 8 5.00 0.04 0.06 0.03 2.2316 315 3.0 16 3 19 57.0 4.00 0.018 0.028 8 6.54 0.04 0.06 0.03 2.6315 314B 3.0 19 10 29 87.0 4.00 0.028 0.043 8 8.50 0.05 0.07 0.03 3.2
314B 314A 3.0 29 0 29 87.0 4.00 0.028 0.043 8 8.84 0.05 0.07 0.03 3.3314A 313 3.0 29 0 29 87.0 4.00 0.028 0.043 8 9.45 0.05 0.07 0.03 3.4
313 312 3.0 29 0 29 87.0 4.00 0.028 0.043 8 6.00 0.05 0.08 0.03 3.0 Connect to exist. plug, see Unit 5, Sheet 6343 342 3.0 0 5 5 15.0 4.00 0.005 0.007 8 10.88 0.02 0.03 0.01 2.1
342 312 3.0 5 2 7 21.0 4.00 0.007 0.010 8 1.00 0.04 0.06 0.03 1.0 Connect to exist. plug, see Unit 5, Sheet 6312 311 3.0 36 0 36 108.0 4.00 0.035 0.053 8 5.40 0.06 0.09 0.04 3.0341 340 3.0 0 11 11 33.0 4.00 0.011 0.016 8 11.73 0.03 0.04 0.02 2.6340 340A 3.0 11 3 14 42.0 4.00 0.013 0.021 8 7.42 0.03 0.05 0.02 2.4
340A 311 3.0 14 0 14 42.0 4.00 0.013 0.021 8 4.00 0.04 0.06 0.03 2.0Vertical Curve -
Connect to exist. plug, see Unit 5, Sheet 7
311 310 3.0 50 0 50 150.0 4.00 0.048 0.074 8 1.27 0.10 0.15 0.06 2.0310 309 3.0 50 4 54 162.0 4.00 0.052 0.080 8 1.52 0.10 0.15 0.06 2.2308 309 3.0 0 4 4 12.0 4.00 0.004 0.006 8 1.00 0.03 0.05 0.02 0.9309 307 3.0 58 0 58 174.0 4.00 0.056 0.086 8 1.15 0.11 0.17 0.07 2.1307 306 3.0 58 4 62 186.0 4.00 0.060 0.092 8 1.00 0.12 0.18 0.07 2.0306 304 3.0 62 4 66 198.0 4.00 0.063 0.098 8 6.57 0.08 0.12 0.05 4.0305 304 3.0 0 4 4 12.0 4.00 0.004 0.006 8 0.70 0.03 0.05 0.02 0.7304 324 3.0 70 0 70 210.0 3.97 0.067 0.103 8 1.06 0.13 0.19 0.08 2.1324 323 3.0 70 18 88 264.0 3.79 0.080 0.124 8 0.80 0.15 0.22 0.09 2.0330 329 3.0 0 8 8 24.0 4.00 0.008 0.012 8 1.00 0.05 0.07 0.03 1.1329 328 3.0 96 8 104 312.0 3.63 0.091 0.140 8 0.70 0.17 0.25 0.10 2.0328 327 3.0 104 0 104 312.0 3.63 0.091 0.140 8 0.70 0.17 0.25 0.10 2.0327 325 3.0 104 2 106 318.0 3.61 0.092 0.142 8 0.60 0.17 0.26 0.10 1.9326 325 3.0 0 17 17 51.0 4.00 0.016 0.025 8 1.55 0.06 0.09 0.04 1.6325 323 3.0 123 9 132 396.0 3.35 0.106 0.164 8 1.00 0.16 0.24 0.09 2.4323 321 3.0 220 9 229 687.0 2.84 0.156 0.242 8 0.45 0.25 0.37 0.13 2.0322 321 3.0 0 10 10 30.0 4.00 0.010 0.015 8 2.49 0.04 0.06 0.03 1.6321 320 3.0 239 8 247 741.0 2.80 0.166 0.257 8 0.42 0.26 0.39 0.14 2.0331 320 3.0 0 7 7 21.0 4.00 0.007 0.010 8 3.50 0.03 0.04 0.02 1.4320 319 3.0 254 2 256 768.0 2.78 0.171 0.264 8 0.43 0.26 0.39 0.14 2.0319 332 3.0 256 18 274 822.0 2.72 0.179 0.276 8 0.45 0.27 0.40 0.14 2.1332 333 3.0 274 0 274 822.0 2.72 0.179 0.276 8 6.04 0.13 0.20 0.08 5.2303 301 3.0 0 4 4 12.0 4.00 0.004 0.006 8 0.70 0.03 0.05 0.02 0.7302 301 3.0 0 10 10 30.0 4.00 0.010 0.015 8 0.70 0.05 0.08 0.03 1.0301 300 3.0 14 2 16 48.0 4.00 0.015 0.024 8 0.70 0.07 0.10 0.04 1.2300 200 3.0 16 8 24 72.0 4.00 0.023 0.036 8 0.60 0.09 0.13 0.05 1.3200 333 3.0 24 0 24 72.0 4.00 0.023 0.036 8 4.59 0.05 0.08 0.03 2.6334 333 3.0 0 9 9 27.0 4.00 0.009 0.013 8 5.65 0.03 0.04 0.02 1.8333 405 3.0 307 0 307 921.0 2.58 0.190 0.294 8 0.41 0.28 0.42 0.15 2.1
4
JOB NO. J-17008
MASTER SEWER SUMMARYHARMONY GROVE VILLAGE
PREPARED BY RICK ENGINEERING COMPANY 7/20/2016
LINE FROM TO POPULATION CUM. EDU CUMULATIVE PEAK/AVG LINE DESIGN dn(FT) VELOCITYNO. M.H. M.H. PER D.U. UPSTREAM IN LINE CUMULATIVE POP RATIO SIZE SLOPE n= dn/D Rh (fps) Comments
MANHOLE D.U.'S DU's SERVED M.G.D. CFS (INCHES) (%) 0.013 (ft)
POPULATION SERVED PEAK DESIGN FLOW
400 Series415 414 3.0 0 2 2 6.0 4.00 0.002 0.003 8 2.59 0.01 0.02 0.01 0.8414 413 3.0 2 0 2 6.0 4.00 0.002 0.003 8 11.35 0.01 0.02 0.01 1.6413 411 3.0 2 0 2 6.0 4.00 0.002 0.003 8 18.32 0.01 0.01 0.00 1.3412 146 3.0 0 4 4 12.0 4.00 0.004 0.006 8 0.70 0.03 0.05 0.02 0.7146 411 3.0 4 4 8 24.0 4.00 0.008 0.012 8 0.71 0.05 0.07 0.03 0.9411 410 3.0 10 0 10 30.0 4.00 0.010 0.015 8 0.77 0.05 0.08 0.03 1.1409 410 3.0 0 17 17 51.0 4.00 0.016 0.025 8 0.97 0.07 0.10 0.04 1.4410 405 3.0 27 0 27 81.0 4.00 0.026 0.040 8 4.63 0.05 0.08 0.03 2.6405 404 3.0 334 0 334 1002.0 2.50 0.200 0.310 8 0.43 0.29 0.43 0.15 2.1404 403 3.0 334 11 345 1035.0 2.49 0.206 0.319 8 1.81 0.20 0.30 0.11 3.6403 402 3.0 345 13 358 1074.0 2.48 0.213 0.329 8 0.43 0.29 0.44 0.15 2.2402 401 3.0 358 16 374 1122.0 2.47 0.221 0.342 8 0.40 0.31 0.46 0.16 2.1401 400 3.0 374 0 374 1122.0 2.47 0.221 0.342 8 0.71 0.27 0.40 0.14 2.6408 407 3.0 0 8 8 24.0 4.00 0.008 0.012 8 1.17 0.04 0.06 0.03 1.1407 406 3.0 8 7 15 45.0 4.00 0.014 0.022 8 2.38 0.05 0.07 0.03 1.7406 400 3.0 15 0 15 45.0 4.00 0.014 0.022 8 6.32 0.04 0.06 0.03 2.5400 9 3.0 389 0 389 1167.0 2.46 0.229 0.355 8 0.51 0.29 0.44 0.15 2.39 8 3.0 513 5 518 1554.0 2.37 0.295 0.456 12 0.42 0.30 0.30 0.17 2.38 7 3.0 518 0 518 1554.0 2.37 0.295 0.456 12 1.00 0.24 0.24 0.14 3.17 6 3.0 518 0 518 1554.0 2.37 0.295 0.456 12 5.14 0.16 0.16 0.10 5.56 3 3.0 518 0 518 1554.0 2.37 0.295 0.456 12 2.69 0.18 0.18 0.11 4.3
5
JOB NO. J-17008
MASTER SEWER SUMMARYHARMONY GROVE VILLAGE
PREPARED BY RICK ENGINEERING COMPANY 7/20/2016
LINE FROM TO POPULATION CUM. EDU CUMULATIVE PEAK/AVG LINE DESIGN dn(FT) VELOCITYNO. M.H. M.H. PER D.U. UPSTREAM IN LINE CUMULATIVE POP RATIO SIZE SLOPE n= dn/D Rh (fps) Comments
MANHOLE D.U.'S DU's SERVED M.G.D. CFS (INCHES) (%) 0.013 (ft)
POPULATION SERVED PEAK DESIGN FLOW
500 & 600 Series514 513 3.0 0 2 2 6.0 4.00 0.002 0.003 8 1.25 0.02 0.03 0.01 0.7513 512 3.0 2 7 9 27.0 4.00 0.009 0.013 8 0.74 0.05 0.07 0.03 1.0512 511 3.0 9 15 24 72.0 4.00 0.023 0.036 8 1.08 0.07 0.11 0.05 1.5511 510 3.0 24 6 30 90.0 4.00 0.029 0.045 8 1.11 0.08 0.12 0.05 1.6510 509 3.0 30 13 43 129.0 4.00 0.041 0.064 8 0.70 0.11 0.17 0.07 1.6519 515 3.0 0 10 10 30.0 4.00 0.010 0.015 8 1.06 0.05 0.07 0.03 1.1515 509 3.0 10 0 10 30.0 4.00 0.010 0.015 8 6.89 0.03 0.04 0.02 2.0509 508 3.0 53 9 62 186.0 4.00 0.060 0.092 8 1.02 0.12 0.18 0.07 2.0520 516 3.0 0 11 11 33.0 4.00 0.011 0.016 8 1.01 0.05 0.08 0.03 1.2516 508 3.0 11 0 11 33.0 4.00 0.011 0.016 8 17.11 0.03 0.04 0.02 3.2508 507 3.0 73 7 80 240.0 3.87 0.074 0.115 8 0.86 0.14 0.21 0.08 2.0537 536 3.0 0 2 2 6.0 4.00 0.002 0.003 8 3.80 0.01 0.02 0.01 1.0536 535 3.0 2 4 6 18.0 4.00 0.006 0.009 8 2.13 0.03 0.05 0.02 1.3517 518 3.0 0 8 8 24.0 4.00 0.008 0.012 8 1.65 0.04 0.06 0.03 1.3518 535 3.0 8 2 10 30.0 4.00 0.010 0.015 8 2.20 0.04 0.06 0.03 1.5535 534 3.0 16 0 16 48.0 4.00 0.015 0.024 8 0.70 0.07 0.10 0.04 1.2534 533 3.0 16 4 20 60.0 4.00 0.019 0.030 8 0.71 0.07 0.11 0.05 1.2533 532 3.0 20 4 24 72.0 4.00 0.023 0.036 8 0.71 0.08 0.12 0.05 1.3532 531 3.0 24 4 28 84.0 4.00 0.027 0.042 8 2.11 0.07 0.10 0.04 2.0603 602 3.0 0 13 13 39.0 4.00 0.012 0.019 8 3.60 0.04 0.06 0.03 1.9 * - Institutional (13du)721 720 3.0 0 17 17 51.0 4.00 0.016 0.025 8 0.74 0.07 0.10 0.04 1.2 * - Fire Station (13du)720 719 3.0 17 4 21 63.0 4.00 0.020 0.031 8 0.70 0.08 0.12 0.05 1.3719 718 3.0 21 7 28 84.0 4.00 0.027 0.042 8 0.70 0.09 0.13 0.05 1.4718 717 3.0 28 4 32 96.0 4.00 0.031 0.048 8 7.67 0.05 0.08 0.03 3.3717 716 3.0 32 4 36 108.0 4.00 0.035 0.053 8 3.15 0.07 0.10 0.04 2.5716 715 3.0 36 4 40 120.0 4.00 0.038 0.059 8 3.83 0.07 0.10 0.04 2.7715 714 3.0 40 4 44 132.0 4.00 0.042 0.065 8 6.71 0.07 0.10 0.04 3.6714 712 3.0 44 4 48 144.0 4.00 0.046 0.071 8 7.01 0.07 0.10 0.04 3.7708 709 3.0 0 5 5 15.0 4.00 0.005 0.007 8 2.57 0.03 0.04 0.02 1.2709 710 3.0 5 6 11 33.0 4.00 0.011 0.016 8 2.52 0.04 0.06 0.03 1.6710 713 3.0 11 4 15 45.0 4.00 0.014 0.022 8 0.70 0.07 0.10 0.04 1.2713 712 3.0 15 4 19 57.0 4.00 0.018 0.028 8 1.50 0.06 0.09 0.04 1.6712 602 3.0 67 0 67 201.0 4.00 0.064 0.099 8 4.84 0.09 0.13 0.05 3.6602 601 3.0 80 0 80 240.0 3.87 0.074 0.115 8 4.58 0.09 0.14 0.06 3.7601 600 3.0 80 0 80 240.0 3.87 0.074 0.115 8 3.91 0.09 0.14 0.06 3.4600 531 3.0 80 7 87 261.0 3.80 0.079 0.123 8 1.55 0.13 0.19 0.08 2.6531 530 3.0 115 4 119 357.0 3.48 0.099 0.154 8 0.75 0.17 0.25 0.10 2.1530 507 3.0 119 0 119 357.0 3.48 0.099 0.154 8 0.84 0.17 0.25 0.10 2.2507 506 3.0 199 7 206 618.0 2.90 0.143 0.222 8 0.67 0.21 0.32 0.12 2.3506 505 3.0 206 0 206 618.0 2.90 0.143 0.222 8 2.47 0.15 0.23 0.09 3.6505 504 3.0 206 31 237 711.0 2.82 0.161 0.249 8 0.98 0.20 0.30 0.11 2.7 ** - Commercial (30du)504 503 3.0 237 5 242 726.0 2.81 0.163 0.253 8 0.83 0.21 0.32 0.12 2.5503 502 3.0 242 0 242 726.0 2.81 0.163 0.253 8 3.93 0.14 0.21 0.08 4.3
* - Fire Station and Institutional flows each estimated to be 3,000 GPD. Based upon 1,500 gpd/acre and a total of 2 acres each. 3,000 gpd / 240 gpd/DU = 13 DU** - Commercial flows estimated to be 7,200 GPD. Based upon 500 gpd/acre and a total of 14 acres. 7,200 gpd / 240 gpd/DU = 30 DU
6
JOB NO. J-17008
MASTER SEWER SUMMARYHARMONY GROVE VILLAGE
PREPARED BY RICK ENGINEERING COMPANY 7/20/2016
LINE FROM TO POPULATION CUM. EDU CUMULATIVE PEAK/AVG LINE DESIGN dn(FT) VELOCITYNO. M.H. M.H. PER D.U. UPSTREAM IN LINE CUMULATIVE POP RATIO SIZE SLOPE n= dn/D Rh (fps) Comments
MANHOLE D.U.'S DU's SERVED M.G.D. CFS (INCHES) (%) 0.013 (ft)
POPULATION SERVED PEAK DESIGN FLOW
700 Series707 706 3.0 0 4 4 12.0 4.00 0.004 0.006 8 0.87 0.03 0.05 0.02 0.8706 705 3.0 4 4 8 24.0 4.00 0.008 0.012 8 2.07 0.03 0.05 0.02 1.3705 704 3.0 8 4 12 36.0 4.00 0.012 0.018 8 1.27 0.05 0.08 0.03 1.4704 702 3.0 12 4 16 48.0 4.00 0.015 0.024 8 1.18 0.06 0.09 0.04 1.4702 701 3.0 16 4 20 60.0 4.00 0.019 0.030 8 0.71 0.07 0.11 0.05 1.2701 700 3.0 20 0 20 60.0 4.00 0.019 0.030 8 0.76 0.07 0.11 0.05 1.3700 699 3.0 20 0 20 60.0 4.00 0.019 0.030 8 4.00 0.05 0.07 0.03 2.2 200' vertical curve699 523 3.0 20 0 20 60.0 4.00 0.019 0.030 8 0.95 0.07 0.10 0.04 1.4523 502 3.0 20 10 30 90.0 4.00 0.029 0.045 8 0.71 0.09 0.14 0.06 1.4502 501 3.0 272 0 272 816.0 2.73 0.178 0.275 8 0.43 0.27 0.40 0.14 2.1521 522 3.0 0 28 28 84.0 4.00 0.027 0.042 8 2.48 0.07 0.10 0.04 2.2522 501 3.0 28 0 28 84.0 4.00 0.027 0.042 8 4.38 0.05 0.08 0.03 2.5501 500 3.0 300 0 300 900.0 2.60 0.187 0.290 8 0.42 0.28 0.42 0.15 2.1524 500 3.0 0 6 6 18.0 4.00 0.006 0.009 8 1.92 0.03 0.05 0.02 1.2500 5 3.0 306 5 311 933.0 2.57 0.192 0.296 8 1.07 0.22 0.33 0.12 2.95 4 3.0 311 0 311 933.0 2.57 0.192 0.296 8 2.54 0.17 0.26 0.10 4.04 3 3.0 311 0 311 933.0 2.57 0.192 0.296 8 0.91 0.23 0.34 0.13 2.73 11 3.0 829 0 829 2487.0 2.21 0.440 0.681 12 7.04 0.18 0.18 0.11 7.011 2 3.0 829 0 829 2487.0 2.21 0.440 0.681 12 5.31 0.19 0.19 0.12 6.22 1 3.0 829 0 829 2487.0 2.21 0.440 0.681 12 2.00 0.24 0.24 0.14 4.41 10 3.0 829 0 829 2487.0 2.21 0.440 0.681 12 1.00 0.29 0.29 0.17 3.510 Lift Station 3.0 829 0 829 2487.0 2.21 0.440 0.681 12 1.00 0.29 0.29 0.17 3.5
7