1
e Duration Start Finish W 27 W 28 W 29 W 30 W 31 W 32 W 33 W 34 W 35 W 36 W 37 W 38 W 39 W 40 W 41 W 42 W 43 W 44 W 45 W 46 W 47 W 48 W 49 W 50 W 51 W 52 W 1 W 2 15 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January dministrative work 77 d 07-09-2015 at 8:0… 10-23-2015 at 5:0… Concrete Bids 25 d 07-09-2015 at 8:0… 08-12-2015 at 5:0… Obtain bids for installation of pump bases, structure foundation and hole coring 5 w 07-09-2015 at 8:0… 08-12-2015 at 5:0… Structure 27 d 07-13-2015 at 8:0… 08-18-2015 at 5:0… Review tower design for optimization 2 w 07-13-2015 at 8:0… 07-25-2015 at 5:0… Obtain bids for supply and install of tower steel 3.6 w 07-20-2015 at 8:0… 08-12-2015 at 5:0… Issue PO to contractor 1 d 08-18-2015 at 8:0… 08-18-2015 at 5:0… Piping 77 d 07-09-2015 at 8:0… 10-23-2015 at 5:0… Obtain bids for installation of pipng 8 w 07-13-2015 at 8:0… 09-04-2015 at 5:0… Issue PO to contractor 1 w 10-19-2015 at 8:0… 10-23-2015 at 5:0… Obtain pipe and piping component pricing 1 w 07-09-2015 at 8:0… 07-15-2015 at 5:0… oncrete Work 16 d 08-17-2015 at 8:0… 09-07-2015 at 5:0… Issue PO to contractor 1 d 08-17-2015 at 8:0… 08-17-2015 at 5:0… Install pump bases and structure foundation 1 w 09-01-2015 at 8:0… 09-07-2015 at 5:0… teel Work 33 d 08-14-2015 at 8:0… 09-29-2015 at 5:0… Detailing and shop drawings 0.8 w 08-14-2015 at 8:0… 08-19-2015 at 5:0… Steel procurement 1 w 08-19-2015 at 8:0… 08-25-2015 at 5:0… Steel shop work 3 w 08-26-2015 at 8:0… 09-15-2015 at 5:0… Steel erection 1 w 09-22-2015 at 8:0… 09-28-2015 at 5:0… Tower installation 1 d 09-29-2015 at 8:0… 09-29-2015 at 5:0… iping / Mechanical Work 111 d 07-09-2015 at 8:0… 12-10-2015 at 5:0… Piping procurement 1 w 10-26-2015 at 8:0… 10-30-2015 at 5:0… Valve and component procurement 2 w 10-26-2015 at 8:0… 11-06-2015 at 5:0… Shop fabrication (headers etc.) 2 w 11-02-2015 at 8:0… 11-13-2015 at 5:0… Install pre-shutdown pipng 2 w 11-16-2015 at 8:0… 11-27-2015 at 5:0… Install process pumps 3 d 09-30-2015 at 8:0… 10-02-2015 at 5:0… Shutdown 3 d 12-08-2015 at 8:0… 12-10-2015 at 5:0… August Shutdown Work 1 d 08-04-2015 at 8:0… 08-04-2015 at 5:0… Hotwell Coring 1 d 08-04-2015 at 8:0… 08-04-2015 at 5:0… Other Work 4 d 07-09-2015 at 8:0… 07-14-2015 at 5:0… Sprinkler Relocate 1 d 07-09-2015 at 8:0… 07-09-2015 at 5:0… Ceiling conduit relocate 1 d 07-10-2015 at 8:0… 07-10-2015 at 5:0… Light relocate 1 d 07-13-2015 at 8:0… 07-13-2015 at 5:0… Process pump wiring 1 d 07-14-2015 at 8:0… 07-14-2015 at 5:0… Chemical addition relocate 3 d 07-09-2015 at 8:0… 07-13-2015 at 5:0… ecember Shutdown 1 d? 07-09-2015 at 8:0… 07-09-2015 at 5:0… Temp.: 70.0 deg F Rated Pump Efficiency: 72.5 % Min. Hydraulic Flow: 161.5 gpm S.G./Visc.: 1.000/1.000 cp Rated Total Power: 34.5 hp Min. Thermal Flow: N/A Flow: 600.0 gpm Non-Overloading Power: 41.8 hp TDH: 162.0 ft Imp. Dia. First 1 Stg(s): 12.5000 in NPSHa: 0.0 ft NPSHr: 8.6 ft Solid size: Shut off Head: 179.0 ft % Susp. Solids (by wtg): Vapor Press: Max. Solids Size: 0.6250 in Notes: 1.The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown in the appropriate field above. 2. Magnetic drive eddy current and viscous effect on power and efficiency is not included. 3. Elevated temperature effects on performance are not included. 4. Non Overloading power does not reflect v-belt/gear losses. 36 39 38 41 49 39 97 162 104 8 2 14 15 16 572 215 83 41 49 52 12 9 4 11 10 84 97 259 130 5 7 93 124 6 7 30 44 20 12 24 24 12 36 155 15 6 29 25 26 32 40 22 21 27 33 28 34 35 24 20 289 10 4 108 12 18 36 60 37 Return Pipe Header Scale 1:50 ITEM NO. PART NUMBER DESCRIPT 1 Slip On Flange 150- NPS6 2 Slip On Flange 150- NPS8 3 Gsk. CNAF Sheet, NPS 6in, CLASS ANSI 150, For ASME 16.5 RF Flg. 4 90L LR Inch 6 Sch40 5 90L LR Inch 8 Sch40 Frame 6 06" Butterfly Valve 6" Butterfly Valv 7 Swing Check Valve (ASME B16.34) Flanged End, Class 150, NPS 6, RF 8 Tee Inch 6 Sch40 9 Tee Inch 8 Sch40 10 Reducer 8x6 Sch 40 11 6 in, Schedule 40 12 8 in, Schedule 40 13 Hot Well Pump Plate 14 8 in, Schedule 40 Existin 15 90L LR Inch 8 Sch40 Existin 16 ELL-LR, NSP 8in Class ASME 150 90 deg, RF 17 Doorway Existin 18 Column Existin 19 Hot Well Pit Existin 20 Return Pipe Header Existin 21 90L LR Inch 8 Sch40 Existin 22 90L LR Inch 4 Sch40 Existin 23 90L SR Inch 6 Sch40 Existin 24 90L LR Inch 3 Sch40 Existin 25 3 in, Schedule 40 Existin 26 4 in, Schedule 40 Existin 27 8 in, Schedule 20 Existin 28 2 in, Schedule 40 Existin 29 0.75 in, Schedule 40 Existin 30 Slip On Flange 150- NPS2 ANSI B16..5 Existin 31 Slip On Flange 150- NPS3 ANSI B16.5 Existin 32 Slip On Flange 150- NPS4 ANSI B16..5 Existin 33 Slip On Flange 150- NPS8 ANSI B16.5 Existin 34 CLASS 2000 THREADED ELBOW, 2.00 IN Existin 35 CLASS 3000 THREADED UNION, 2.00 Existin 36 CLASS 3000 THREADED ELBOW, 2.00 IN Existin 37 NPS8 Blind Flange. ANSI B16.5 Class 150# Existin 38 HHBOLT 0.7500- 10x3.25x1.375-N Existin 39 HHNUT 0.7500-10-D-N Existin 40 HHBOLT 0.6250- 11x2.75x1.25-N Existin 41 HHNUT 0.6250-11-D-N Existin 2 3 4 5 6 7 5 3 6 2 4 7 H D BACKGROUND Induspec was invited into a large local manufacturing facility in order to perform an overview energy audit. Induspec observed some specific conditions, quantified them and put together business cases for correcting the observed inefficiencies. INITIAL CONDITION One of the biggest observed inefficiencies was a plant wide cooling water system. The system was significantly oversized for current needs and the excessive water flow overcapacity resulted in throttling valves operating at near closed positions. It was soon clear that the oversized pumps not only consumed a lot of energy, but were operating at such a poor efficiency point that they actually contributed significantly to the water warming. ANALYSIS Induspec proposed changes to four pumps and a drastic change to the 6” and 8” piping system. In addition, the client identified that the existing water cooling tower was well past its useful life so that a new cooling tower and storage tank were added to the project scope. SCOPE Induspec performed the initial energy quantification and performed design calculations for new pumps, complete with variable speed drives. Induspec designed a significant structure, complete with foundations and a jib mount, to hold the new water cooling tower and water storage tank. Finally, Induspec supervised all construction, commissioned the system with the client, procured energy savings rebates with the energy provided, and provided as built drawings. RESULTS Not only did Induspec install a robust new cooling system, but the client saved tens of thousands of dollars in annual energy costs making for a quick ROI on this project. The system was tuned and was fully commissioned within only a few hours. Gallery Water Cooling System 1

Water Cooling System A3 - induspec.ca · 16ELL-LR, NSP 8in Class ASME 150 90 deg, RF 1 17Doorway Existing 1 18Column Existing 1 19Hot Well Pit Existing 1 20Return Pipe HeaderExisting

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Water Cooling System A3 - induspec.ca · 16ELL-LR, NSP 8in Class ASME 150 90 deg, RF 1 17Doorway Existing 1 18Column Existing 1 19Hot Well Pit Existing 1 20Return Pipe HeaderExisting

Name Duration Start Finish

W 27 W 28 W 29 W 30 W 31 W 32 W 33 W 34 W 35 W 36 W 37 W 38 W 39 W 40 W 41 W 42 W 43 W 44 W 45 W 46 W 47 W 48 W 49 W 50 W 51 W 52 W 1 W 2 W 3 W 4

June 2015 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January 2016

1 Administrative work 77 d 07-09-2015 at 8:0… 10-23-2015 at 5:0…2 Concrete Bids 25 d 07-09-2015 at 8:0… 08-12-2015 at 5:0…3 Obtain bids for installation of

pump bases, structure foundation and hole coring

5 w 07-09-2015 at 8:0… 08-12-2015 at 5:0…

4 Structure 27 d 07-13-2015 at 8:0… 08-18-2015 at 5:0…5 Review tower design for

optimization2 w 07-13-2015 at 8:0… 07-25-2015 at 5:0…

6 Obtain bids for supply and install of tower steel

3.6 w 07-20-2015 at 8:0… 08-12-2015 at 5:0…

7 Issue PO to contractor 1 d 08-18-2015 at 8:0… 08-18-2015 at 5:0…8 Piping 77 d 07-09-2015 at 8:0… 10-23-2015 at 5:0…9 Obtain bids for installation of

pipng8 w 07-13-2015 at 8:0… 09-04-2015 at 5:0…

10 Issue PO to contractor 1 w 10-19-2015 at 8:0… 10-23-2015 at 5:0…11 Obtain pipe and piping

component pricing1 w 07-09-2015 at 8:0… 07-15-2015 at 5:0…

12 Concrete Work 16 d 08-17-2015 at 8:0… 09-07-2015 at 5:0…13 Issue PO to contractor 1 d 08-17-2015 at 8:0… 08-17-2015 at 5:0…14 Install pump bases and structure

foundation1 w 09-01-2015 at 8:0… 09-07-2015 at 5:0…

15 Steel Work 33 d 08-14-2015 at 8:0… 09-29-2015 at 5:0…16 Detailing and shop drawings 0.8 w 08-14-2015 at 8:0… 08-19-2015 at 5:0…17 Steel procurement 1 w 08-19-2015 at 8:0… 08-25-2015 at 5:0…18 Steel shop work 3 w 08-26-2015 at 8:0… 09-15-2015 at 5:0…19 Steel erection 1 w 09-22-2015 at 8:0… 09-28-2015 at 5:0…20 Tower installation 1 d 09-29-2015 at 8:0… 09-29-2015 at 5:0…21 Piping / Mechanical Work 111 d 07-09-2015 at 8:0… 12-10-2015 at 5:0…22 Piping procurement 1 w 10-26-2015 at 8:0… 10-30-2015 at 5:0…23 Valve and component

procurement2 w 10-26-2015 at 8:0… 11-06-2015 at 5:0…

24 Shop fabrication (headers etc.) 2 w 11-02-2015 at 8:0… 11-13-2015 at 5:0…25 Install pre-shutdown pipng 2 w 11-16-2015 at 8:0… 11-27-2015 at 5:0…26 Install process pumps 3 d 09-30-2015 at 8:0… 10-02-2015 at 5:0…27 Shutdown 3 d 12-08-2015 at 8:0… 12-10-2015 at 5:0…28 August Shutdown Work 1 d 08-04-2015 at 8:0… 08-04-2015 at 5:0…29 Hotwell Coring 1 d 08-04-2015 at 8:0… 08-04-2015 at 5:0…30 Other Work 4 d 07-09-2015 at 8:0… 07-14-2015 at 5:0…31 Sprinkler Relocate 1 d 07-09-2015 at 8:0… 07-09-2015 at 5:0…32 Ceiling conduit relocate 1 d 07-10-2015 at 8:0… 07-10-2015 at 5:0…33 Light relocate 1 d 07-13-2015 at 8:0… 07-13-2015 at 5:0…34 Process pump wiring 1 d 07-14-2015 at 8:0… 07-14-2015 at 5:0…35 Chemical addition relocate 3 d 07-09-2015 at 8:0… 07-13-2015 at 5:0…36 December Shutdown 1 d? 07-09-2015 at 8:0… 07-09-2015 at 5:0…37

Model: 3196 Size: 3X4-13 Group: MTi 60Hz RPM: 1775 Stages: 1

Job/Inq.No. :Purchaser : UNDEFINEDEnd User: Issued by :Item/Equip.No. : ITEM 001 Quotation No. : Date : 10/13/2015Service :Order No. : Rev. : 0Operating Conditions Pump PerformanceLiquid: Water Published Efficiency: 72.5 % Suction Specific Speed: 9,478 gpm(US) ftTemp.: 70.0 deg F Rated Pump Efficiency: 72.5 % Min. Hydraulic Flow: 161.5 gpmS.G./Visc.: 1.000/1.000 cp Rated Total Power: 34.5 hp Min. Thermal Flow: N/AFlow: 600.0 gpm Non-Overloading Power: 41.8 hpTDH: 162.0 ft Imp. Dia. First 1 Stg(s): 12.5000 inNPSHa: 0.0 ft NPSHr: 8.6 ftSolid size: Shut off Head: 179.0 ft% Susp. Solids(by wtg):

Vapor Press: Max. Solids Size: 0.6250 in

Notes: 1.The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown inthe appropriate field above. 2. Magnetic drive eddy current and viscous effect on power and efficiency is not included. 3.Elevated temperature effects on performance are not included. 4. Non Overloading power does not reflect v-belt/gearlosses.

36

39 38

41

49 39

97

162

104 8

2

14

15

16

572

215

83

41 49

52

12

5

9

4

11

10

84

97

259

130

5 7

93 124

6

7

30

44 20

12 24

24

12

36

155

15

6

29

25

26 32 4022

21

27

33

28

34

35

24

20

67 289

10

4 2

17

108

12

18 36 60

37

Return Pipe HeaderScale 1:50

ITEM NO. PART NUMBER DESCRIPTION QTY.

1 Slip On Flange 150-NPS6 12

2 Slip On Flange 150-NPS8 6

3Gsk. CNAF Sheet, NPS 6in, CLASS ANSI 150, For ASME 16.5 RF Flg.

10

4 90L LR Inch 6 Sch40 85 90L LR Inch 8 Sch40 Frame 16 06" Butterfly Valve 6" Butterfly Valve Class 150 2

7Swing Check Valve (ASME B16.34) Flanged End, Class 150, NPS 6, RF

2

8 Tee Inch 6 Sch40 19 Tee Inch 8 Sch40 110 Reducer 8x6 Sch 40 111 6 in, Schedule 40 1712 8 in, Schedule 40 313 Hot Well Pump Plate 214 8 in, Schedule 40 Existing 615 90L LR Inch 8 Sch40 Existing 3

16 ELL-LR, NSP 8in Class ASME 150 90 deg, RF 1

17 Doorway Existing 118 Column Existing 119 Hot Well Pit Existing 120 Return Pipe Header Existing 121 90L LR Inch 8 Sch40 Existing 322 90L LR Inch 4 Sch40 Existing 323 90L SR Inch 6 Sch40 Existing 524 90L LR Inch 3 Sch40 Existing 225 3 in, Schedule 40 Existing 126 4 in, Schedule 40 Existing 127 8 in, Schedule 20 Existing 128 2 in, Schedule 40 Existing 129 0.75 in, Schedule 40 Existing 1

30 Slip On Flange 150-NPS2 ANSI B16..5 Existing 4

31 Slip On Flange 150-NPS3 ANSI B16.5 Existing 2

32 Slip On Flange 150-NPS4 ANSI B16..5 Existing 3

33 Slip On Flange 150-NPS8 ANSI B16.5 Existing 3

34 CLASS 2000 THREADED ELBOW, 2.00 IN Existing 3

35 CLASS 3000 THREADED UNION, 2.00 Existing 1

36 CLASS 3000 THREADED ELBOW, 2.00 IN Existing 3

37 NPS8 Blind Flange. ANSI B16.5 Class 150# Existing 1

38 HHBOLT 0.7500-10x3.25x1.375-N Existing 16

39 HHNUT 0.7500-10-D-N Existing 8

40 HHBOLT 0.6250-11x2.75x1.25-N Existing 36

41 HHNUT 0.6250-11-D-N Existing 28

8

A

1234567

D

C

B

C

A

D

B

5 3 16 248 7

Material <not specified>

Hot Water System

3DO NOT SCALE DRAWING

M201 403SHEET 1 OF 2

22/06/15

22/06/15T. Brost

B. Martel

UNLESS OTHERWISE SPECIFIED:

SCALE: 1:100 WEIGHT:

REVDWG. NO.

DSIZE

TITLE:

NAME DATE

COMMENTS:

Q.A.

MFG APPR.

ENG APPR.

CHECKED

DRAWN

FINISH

MATERIAL

INTERPRET GEOMETRICTOLERANCING PER:

DIMENSIONS ARE IN INCHESTOLERANCES:FRACTIONALANGULAR: MACH BEND TWO PLACE DECIMAL THREE PLACE DECIMAL

APPLICATION

USED ONNEXT ASSY

PROPRIETARY AND CONFIDENTIALTHE INFORMATION CONTAINED IN THISDRAWING IS THE SOLE PROPERTY OFINDUSPEC. ANY REPRODUCTION INPART OR AS A WHOLE WITHOUT THEWRITTEN PERMISSION OF INDUSPEC IS PROHIBITED.

Induspec

BACKGROUND

Induspec was invited into a large local manufacturing facility in order to perform an overview energy audit. Induspec observed some specific conditions, quantified them and put together business cases for correcting the observed inefficiencies.

INITIAL CONDITION

One of the biggest observed inefficiencies was a plant wide cooling water system. The system was significantly oversized for current needs and the excessive water flow overcapacity resulted in throttling valves operating at near closed positions. It was soon clear that the oversized pumps not only consumed a lot of energy, but were operating at such a poor efficiency point that they actually contributed significantly to the water warming.

ANALYSIS

Induspec proposed changes to four pumps and a drastic change to the 6” and 8” piping system. In addition, the client identified that the existing water cooling tower was well past its useful life so that a new cooling tower and storage tank were added to the project scope.

SCOPE

Induspec performed the initial energy quantification and performed design calculations for new pumps, complete with variable speed drives. Induspec designed a significant structure, complete with foundations and a jib mount, to hold the new water cooling tower and water storage tank. Finally, Induspec supervised all construction, commissioned the system with the client, procured energy savings rebates with the energy provided, and provided as built drawings.

RESULTS

Not only did Induspec install a robust new cooling system, but the client saved tens of thousands of dollars in annual energy costs making for a quick ROI on this project. The system was tuned and was fully commissioned within only a few hours.

Gallery

Water Cooling System

�1