WATER MASTER REPORT
GALLINAS RIVER
2009
Luis Pedro Aguirre
Gallinas River Water Master
Contents CONTENTS Page 1 SUMMARY Page 2 INTRODUCTION Page 2 MEETINGS Page 3 HYDROLOGY Page 4 Installation and Measurement of Flow Measuring Devices Page 4 Precipitation, Stream flows and Weather Page 5 Observations from 2009 Diversions and Enforcement Activities Page 6 PENDING MATTERS AND OUTLOOK FOR 2010 Page 7 Attachments A-01 Gallinas River basin location map A-02 January 20, 2009 Response to Additional Questions about the Metering or
Measurement Agreement Letter A-03 January 20, 2009 Review of the RGAA Ditch Metering Subcommittee Revisions
to the Metering or Measurement Agreement Letter A-04 April 15, 2009 on the April 23, 2009 Meeting on Managing Low Flows in the
Middle Section (Las Vegas area) during the 2009 Irrigation Season Letter A-05 April 30, 2009 on the May 12, 2009 Meeting on Managing Low Flows in the
Middle Section (Las Vegas area) during the 2009 Irrigation Season Letter. A-06 2009 Pictures of flume and river gate construction A-07 2009 Summary of Gallinas River Diversions and Flows A-08 2009 Las Vegas Municipal Airport Daily Precipitation Records A-09 2009 Las Vegas Monthly Rainfall and Effective Precipitation Records A-10 2009 USGS Montezuma Gage Report of Gallinas River flows A-11 2009 USGS Montezuma Gage Daily Mean Discharge A-12 2009 City of Las Vegas Days on/off Gallinas River A-13 Middle Gallinas diversions in days in August, October A-14 2010 SNOTEL Report of Wesner Springs in a table A-15 2009 SNOTEL Report of Wesner Springs – snow water equivalent A-16 2009 & 2010 SNOTEL Report of Wesner Springs in graphs “This report does not suggest or establish the existence, nature or extent of a water right and is not binding on the State of New Mexico or State Engineer in any adjudication or administrative proceeding."
Page 1 of 7
SUMMARY The 2008 Watermaster Report was posted to the Office of the State Engineer (OSE) website in mid-March. We held a public forum on Water Use on March 31, 2009 that was very well attended. There were many accomplishments in 2009. The OSE dedicated much time and resources to the following activities which showed our commitment to the Gallinas River basin: the continuing adjudication process, involvement in the City of Las Vegas (COLV) Remand negotiations, signing of the remaining ditch metering agreements, installing flow measuring devices, building a State-funded weir at the Storrie Project point of diversion with the reconstruction of the attached river gate and the monitoring of flows and diversions (see Attachment A-6A & A-6B). The snow melt did not increase the Gallinas River stream flows during the 2009 Spring very much due to a less than average snowpack (see Attachments A-15 & A-16). The 2009 rains did not generate much storm run-off upstream of the USGS Montezuma gage (see Attachments A-10 & A-11) keeping the Gallinas River stream flows (at the USGS Montezuma gage) low in the later months of the irrigation season. The slightly below average rains did provide effective precipitation for agriculture and COLV residents’ outdoor uses (see Attachments A-8 & A-9). The Rio Gallinas Acequia Association (RGAA) requested that the irrigation season start in mid-March to take advantage of the snow melt runoff in the early spring. The RGAA also requested that the OSE not implement a rotation during low flows in the irrigation season as it might conflict with their negotiations on the “river-sharing” agreement with the COLV in the ongoing adjudication Remand negotiations. The COLV and the RGAA acequias implemented a “river-sharing” agreement during the year, which set stream flow and City storage triggers and when the City would come on/off the river.
INTRODUCTION
The State Engineer has the broad authority to administer water rights and it is specifically provided for the Gallinas River by NMSA 1978, Section 72-3-1 (1919) and in Section 72-3-2 (1907). Administration in the Gallinas River was established by declaration of the Gallinas River Water Sub-district of the Pecos River Stream System filed as New Mexico Administrative Code (NMAC) Order 19.26.11, which became effective August 29, 2003. The Gallinas River basin is located in north-central New Mexico (see Attachment A-1). The Gallinas River headwaters are located on the eastern slopes of the Sangre de Cristo Mountains, at an elevation of approximately 11,660 feet. From its headwaters, the river traverses southeasterly approximately 85 miles and enters the Pecos River six miles upstream of the Village of Colonias. The COLV is located in the north-central part of the drainage basin.
Page 2 of 7
The Gallinas River has no major perennial tributaries. The larger tributaries are Porvenir Canyon, Trout Springs, Cañon Bonito, Pecos Arroyo, and Aguilar Creek. The drainage basin of the Gallinas River and its tributaries contains approximately 610 square miles. The OSE Gallinas River Water Master has the responsibility of managing the Gallinas River. For management purposes, the Gallinas River is divided into three separate areas. The following diverters arecurrently recognized in the three separate areas: Upper Gallinas Area From the headwaters to the USGS Montezuma gage
Middle Gallinas Area From USGS Montezuma gage to the USGS Lourdes gage
Lower Gallinas Area From the USGS Lourdes gage to the Pecos River
Judge Long Ditch Placita Arriba Ditch
Upper Maestes Ditch
El Porvenir Ditch
Gallegos Ditch
Max Nordhaus Ditch Trout Springs Ranch
City of Las Vegas United World College
Gallinas Canal
Agapito Vigil Ditch
Storrie Project WUA
Acequia Madre de Los Vigiles
Grzelachowski Ditch
Acequia Md. de Los Romeros
Cleo Fresquez
Los Dolores Ditch
Acequia Madre de Las Vegas
Roundhouse Ditch
Pappen Ditch
San Augustine Comm. Ditch
Stacey Montaňo
Archie Allemand
La Concepcion Ditch
Ancon del Gato Ditch
Acequia Arriba de La Liendre
West Chaperito Ditch
There is an ongoing adjudication process in the Gallinas River basin; therefore, this listing of diversions is subject to changes as the court recognizes water rights.
MEETINGS
The OSE held a public meeting at the Luna Community College on March 31, 2009, a Forum on Water Use that was very well attended. The Memorial Middle School Ag Program, the San Miguel County Ag Extension Service, and the Las Vegas Wildlife Refuge made presentations at the Forum. Talks continued between the OSE and the RGAA on the language in the ditch metering agreement with the assistance of OSE Community Liaison Richard Trujillo. After the RGAA and OSE agreed to the language (see Attachments A-2 & A-3), the remaining major acequias signed off on their ditch metering agreements. The OSE held a meeting on April 23, 2009 with some acequias to determine the alternating groups and the intervals on/off the river for the rotation among the Acequias during low flows for this irrigation season (see Attachments A-4 & A-5). The RGAA
Page 3 of 7
later requested that the OSE not implement a rotation so that it would not conflict with their negotiations on the river-sharing agreement with the COLV. The RGAA and the COLV decided on a “river-sharing” agreement in 2009 amongst themselves to resolve the remand litigation which would define the priority of the City’s water rights. The intent was that the agreement would be tested for three years beginning in 2009 to fine-tune the details. It was anticipated that after each irrigation season, changes could be made to the agreement conditions for the next irrigation season. The COLV and the RGAA followed the diversion schedule defined in the agreement in 2009. At the request of Storrie Project WUA, the Acequias and the OSE, the NRCS prepared a design to modify the Storrie diversion structure that would allow the high flows to be diverted to Storrie Lake and the low flows to continue downstream to the senior acequias. The OSE agreed to fund the project and construction began in November 2009. (See Attachment A-6A).
HYDROLOGY
Installation and Measurement of Flow Measuring Devices The ditch diverters were consulted on the size of the flume and its placement location at each ditch or canal. OSE staff: Vince Chavez and Brian Gallegos coordinated with Sutron, the contractor, and the acequias, on the installation of the flumes and the bubbler. The following locations had flow measuring devices installed in 2009 (see Attachment A-6B): DIVERTER MEASURING DEVICE MONTH 2009
Storrie Project WUA Acequia Mdre de Los Romeros
Roundhouse Ditch
Gallinas Canal
Acequia Mdre de Los Vigiles
Acequia Mdre de Las Vegas
Grzelachowski Ditch
Los Dolores Ditch
La Concepcion Ditch
West Chaperito Ditch
Gallinas River below Storrie
San Augustine Comm. Ditch
Bubbler Flume
Flume
Flume
Flume
Flume
Flume
Flume
Flume
Flume
Weir
Pipe Meter
February April
May
June
July
July
July
July
September
October
Pending 2010
Pending 2010
The data recorders for the water measuring devices were installed in November 2009.
Page 4 of 7
The United World College and Cleo Fresquez installed pipe meters in 2009 to measure their river pump diversions. The Trout Springs Ranch, Archie Allemand and Marc May should be installing pipe meters before the next irrigation season. The weir construction at the Storrie Project WUA point of diversion and the reconstruction of the attached river gate began in November 2009. This project included a flow measurement device on the Gallinas River immediately downstream of the above-mentioned river gate. Staff gages will be or have been installed in the following locations: Placita Arriba Ditch Upper Maestes Ditch El Porvenir Ditch Max Nordhaus Ditch (pending staff gage installation) Agapito Vigil Ditch (pending ditch curve) Pappen Ditch Gallinas River below Pappen Ditch Point of Diversion (to measure stream flows) Pecos Arroyo (to measure stream flows) Ancon del Gato (pending ditch curve)
In 2009, the OSE Water Master was not assisted by Acequia Majordomos nor Highlands University students in monitoring diversions and flows in the Gallinas River. Ditch curves were not developed for some of the staff gauges that had to be replaced or moved to a better location. Due to many reasons, the Gallinas River flows and diversions were not monitored as often as in the two prior years. The monitoring of flows and diversions at least once a week began in late May, therefore there was no data collected in March, April and part of May (see Attachment A-7). Precipitation, Stream flows and Weather. The 2009 precipitation for the Las Vegas area was 12.24 inches (see Attachment A-8). For the irrigation season, there were 11.40 inches of precipitation and 10.10 inches of effective precipitation (see Attachment A-9). For the irrigation season from April 1 – October 31, 2009, the Gallinas River flows measured at the USGS Montezuma gage totaled 6,818.99 acre-feet (see Attachment A-10). The spring runoff provided average daily flows above 15 cfs, measured at the USGS Montezuma gage, from April 14 – May 30 and rains provided them for a week in June, a few days in July, and two weeks in September. The average daily flows were at 15 cfs or below for 144 days of the 214 days (⅔ of the time) of the irrigation season (see Attachment A-11). The rains did little to increase the Gallinas River stream flows (as measured at the USGS Montezuma gage) during the monsoon months of the irrigation season, but they did help reduce the demand on the river in June, July and September. The average daily flows were above 50 cfs only twice this year: once in July and once in October.
Page 5 of 7
For 2009 the last freeze of winter occurred on March 27, 2009 when temperatures rose above 32º F and the first freeze of winter occurred on December 2, 2009 when the temperatures fell below 32º F. Observations from 2009 Diversions and Enforcement Activities. The COLV operated in accordance with a “river-sharing” agreement which was signed by the City and the acequia members of the RGAA. The agreement defined when the COLV would be on/off the river, stream flow and City storage triggers, and its diversion rate in 2009. The COLV was off the river for two weeks in June and two weeks in July through the first part of August for a total of 34 days (see Attachment A-12). While off the river the City used their water storage until they hit the storage trigger that put them back on the river. The COLV supplemented their surface water with water from the Taylor Well Field to help them keep up with their demand. The diversions and flows of the Gallinas River for four separate dates in 2009: August 13, August 21, August 28 and October 8 were placed on an attached table (see Attachment A-13). The table shows that the diversions and flows in the Middle Gallinas River section (downstream of the Storrie Project POD and upstream of the COLV WWTP) were approximately 350%, 450%, 350% and 150% of the flows estimated at the Gallinas River gate at the Storrie Project POD, indicating that return flows and/or natural gains provide a substantial water supply in the Middle Gallinas River Area. The diversions and flows of the Gallinas River on the above-mentioned dates show that without an agreed rotation among the acequias, that either they were all diverting, with insufficient flow going to each ditch; or that one or two acequias were taking all the stream flow. Without a formal rotation what normally happens is that, acequias divert water only when the upstream acequias are satisfied, or they have to request the upstream acequias to bypass flows. Enforcement issues were limited to two incidents. In April a parciante was cleaning the river of silt along their property. The investigation revealed that the silt removal was minor and did not appear to modify the flooding patterns. In September a parciante used a river pump to irrigate his land from an illegal/unpermitted Point of Diversion. In both instances, they ceased the activity and no further enforcement actions were pursued.
Page 6 of 7
Page 7 of 7
PENDING MATTERS AND OUTLOOK FOR 2010 The COLV and the acequias in the RGAA will meet early in 2010 to discuss the problems that occurred during the implementation of their 2009 river-sharing agreement and come up with a 2010 river-sharing agreement. In 2010 the OSE will have more accurate measurements of diversions and flows thanks to the installation of the flumes with their corresponding data recorders in 2009. Approximately 95 % of the flows in the river system will be measured continuously (data recorders) and another 3% periodically (staff gages). The Water Master is responsible for maintaining the flumes clear of debris for their proper operation. Majordomos should report any debris or obstructions that they notice in the flow measuring devices. The weir downstream of the river gate at the Storrie Project WUA Point of Diversion and the pipe meter on the San Augustin Community Ditch should be installed prior to the 2010 irrigation season. The accuracy of measuring diversions using staff gauges will depend on the availability of the Water Master to monitor diversions and flows in 2010, the availability of summer help (college students) and the collaboration by majordomos in communicating with the OSE Watermaster when they open and/or close their headgates. OSE staff need to perform additional flow measurements in the acequias to develop or calibrate the ditch curves to continue to use the staff gauges to measure flows and diversions. A rotation is strongly suggested in 2010 for the period of low flows during the irrigation season. As of March 25, 2010, the SNOTEL report showed 59.0 inches of snow and 16.4 inches of snow water equivalent at their Wesner Springs site which is above average for this time of year. The snow accumulation is slightly above average due to late winter storms which should provide much better snow melt runoff in the Spring of 2010 than last year, in 2009 (see Attachments A-14, A-15 & A-16). The installation in 2009 of several flow measuring devices at key stream locations and at diversion points on the Gallinas River shall help improve the management of Gallinas River basin. Talks and cooperation among the diverters should continue toward common solutions to the challenges that arise from the periodic droughts that occur in this area. For the common good of the region, the diverters should make the effort, to minimize waste and limit their diversions for beneficial use and of their water rights per annum.
(
(
(
(
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
!?
!?
"/"
"/"
"/"
"/"
"/"
"/"
"/"
"/"
West Chaperito Ditch
City of Las Vegas Acequia Madre de los Vigiles
Acequia Madre de Los Romeros
Acequia Madre de Las Vegas
Storrie Project WUA Canal
Ancon del Gato Ditch
Placita Arriba Ditch
Porvenir Ranch Ditch
Grzelachowski Ditch
Max Nordhaus Ditch
San Augustine Community Ditch
La Concepcion Ditch
Upper Maestas Ditch
Los Dolores Ditch
El Porvenir Ditch
Round House Ditch
Judge Long Ditch
Acequia Arriba de La Liendre
Gallegos Ditch
Gallinas Canal
USFS Pipeline
Pappen Ditch
Agapito Vigil Ditch
Taylor WellField
Storrie Lake
§̈¦I 25
River Gate Gage
USGS Montezuma Gage
USGS Lourdes Gage
Las Vegas
!? USGS Gaging Stations
N Points of Diversion
( Taylor Well Field
Rio Gallinas Water Master Sub-District
r0 3 61.5 MilesAttachment A-1
Attachment A-2
Attachment A-3
Attachment A-3
Attachment A-4
Attachment A-5
GALLINAS RIVER PICTURES TAKEN IN 2009
Dec. 22, 2009: Watermaster inspecting the ongoing construction by Johnny Manzanares
and crew of the Gallinas River gate improvements, adjacent to the Storrie Project POD.
Attachment A-06A
Construction of the Concepcion Ditch flume by Glenn Todd and crew from Sutron.
Attachment A-06B
Attachment A-06
b O
Cleo Fresquez 00 0 00 00 00 0 00 00
FLOWS AND DIVERSIONS IN 2009 IN THE GALLINAS RIVER BASIN
Attachment AA-7
Diverter Jan. Fe . March April May June July Aug. Sept. ct. Nov. Dec. Totals Acres ACRES?Judge Long** 0.06 0.15 0.33 0.00 0.19 0.73 0.37 4.50Placita Arriba* 36.36 15.56 0.00 0.00 0.00 51.92 15.58 43.80Upper Maestes* 58.99 28.31 0.00 0.00 0.00 87.30 26.19 10.90El Porvenir* 18.86 3.82 1.30 4.76 3.62 32.36 9.71 45.10Frank Davis (Gallegos)** UNKTrout Springs Ranch 0.00 2.50Max Nordhaus DNM 7.50USGS Montezuma**^ Ice 265.09 775.24 1343.80 2077.69 854.88 656.83 307.24 1009.69 568.86 611.11 Ice 8470.43City of Las Vegas** 330.24 243.27 326.25 289.12 274.67 158.08 120.49 152.86 401.78 136.66 120.30 143.56 2697.27 2683.32COLV Wells** 17.58 9.60 0.00 0.00 2.74 22.77 28.70 29.66 41.34 44.06 41.18 41.33 278.95United World College 0.00 0.00 0.00 0.00 0.00 1.51 0.27 0.03 0.00 0.00 0.00 0.00 1.81Gallinas Canal* 57.76 0.00 0.00 59.81 0.00 117.57 835.83Agapito Vigil DNM 7.10Storrie Project** releases 0.00 0.00 590.00 523.00 852.00 853.00 730.00 850.00 1100.00 450.00 0.00 0.00 5948.00 12225.09Storrie Lake Levels 6586.70 6586.70 6586.80 6586.00 6585.00 6584.90 6583.00 6582.00 6579.00 6578.70 6578.00 6578.00Storrie Lake Storage 10900.00 10900.00 11000.00 10300.00 9580.00 9250.00 7850.00 7550.00 5730.00 5530.00 5190.00 5190.00Gallinas below Storrie* 404.68 439.93 535.42 369.10 300.00 177.39 227.29 241.47 0.00 0.00 2695.28A M de Los Vigiles* 33.99 74.46 13.51 68.04 89.38 279.38 83.81 176.85Grzelachowski* 74.27 20.14 0.00 0.00 94.41 28.32 57.10Danny Lopez** 1.23 1.69 1.41 1.05 0.43 5.81 2.91 6.00A M de Los Romeros* 160.52 94.40 133.47 123.04 134.11 645.54 193.66 199.67Cleo Fresquez** 0.000. 0.00.00 0.00 0.00 0.000. 0. 0. 0.00 0.00. 0.A M de Los Dolores* 13.86 52.67 47.57 58.77 172.87 51.86 65.40A M de Las Vegas* 108.48 93.44 138.11 109.93 228.16 678.12 203.44 62.55Roundhouse* 49.41 35.54 52.11 7.96 10.59 53.39 209.00 62.70 92.00Pappen* 175.57 89.00 13.35 31.21 31.65 340.78 102.23 56.00Gallinas below Pappen* 178.54 61.32 36.40 4.73 4.16 13.74 298.89Pecos Arroyo* 120.77 106.13 194.00 148.04 191.43 217.30 977.67COLV WWTP Returns** 122.51 122.54 133.28 103.70 103.21 112.31 129.69 108.57 114.36 154.58 105.44 132.52 1442.69USGS Lourdes** 385.29 844.56 508.96 772.07 247.93 405.82 113.62 3278.25San Augustin* 0.00 64.00Stacey Montano 0.00 0.00 0.00 0.00 0.00Archie Allemand** 1.99 6.36 6.58 3.36 18.29 9.15La Concepcion* 0.00 16.10Ancon del Gato* 0.00 64.80A Arriba de La Liendre** 0.00 0.00 0.33 0.33 0.33 0.50 0.66 0.66 0.66 0.58 0.00 0.00 4.05 2.03 25.00West Chaperito** 16.00 112.00 32.00 18.00 178.00 53.40 84.80*OSE staff gauge estimates DNM = did not measure UNK = unknown**diverter provided estimates Acres? = acres adjudicated according to WR files?^partial month in February and October Acres = water use if 2 ac-ft/ac, 60 % conveyance efficiency. 100% for pumps.
Las Vegas Municipal Airport
2009 Daily Precipitation in Inches
Date Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 0.11 2 0.02 0.13 3 0.16 0.80 0.05 4 0.10 0.32 0.43 5 0.01 6 0.04 0.01 0.08 7 0.19 0.03 8 0.06 0.01 0.16 9 0.05
10 0.19 0.08 11 0.29 0.01 12 0.01 0.63 13 0.14 0.01 0.03 14 0.26 0.01 0.01 15 0.18 16 0.11 0.04 0.30 17 0.25 0.01 0.01 18 0.03 19 0.06 0.09 20 0.40 0.18 0.04 0.23 21 0.09 1.26 0.44 22 0.16 0.05 23 0.20 0.38 24 0.19 25 0.01 0.01 0.02 0.33 26 0.05 0.15 0.10 0.63 0.01 27 0.02 0.19 0.06 0.01 0.10 28 0.28 0.03 0.02 29 0.06 0.01 0.11 30 0.02 0.39 31 0.39 0.11
Total 0.15 0.06 0.21 0.66 1.07 1.34 4.34 0.83 1.91 1.25 0.13 0.29
Count 2 1 3 4 10 6 16 7 11 8 2 4
Days Totals2009 Annual Precipitation 74 12.24 Irrigation Season (April – October) 62 11.40
Attachment A‐8
2009 LAS VEGAS, NM PRECIPITATION (NOAA WEATHER DATA IN INCHES)* All Year Irrigation Season Month Rain Effective Rain Rain Effective RainJanuary 0.15 0.14 February 0.06 0.06 March 0.21 0.20 April 0.66 0.63 0.66 0.63May 1.07 1.01 1.07 1.01June 1.34 1.26 1.34 1.26 July 4.34 3.47 4.34 3.47August 0.83 0.79 0.83 0.79September 1.91 1.77 1.91 1.77 October 1.25 1.17 1.25 1.17November 0.13 0.12 December 0.29 0.28 Totals 12.24 10.90 11.40 10.10*National Weather Service Forecast Office in Albuquerque http://www.weather.gov/climate/xmacis.php?wfo=abq USBR EFFECTIVE RAINFALL (RE) The amount of rainfall available to crops is influenced by the following factors:
• Duration and intensity of rainfall • Antecedent moisture condition of soil • Infiltration capacity of the soil • Presence of surface seals and crusts
• Slope of fields • Root development of the crop • Interception by the plant canopy
The USBR method expresses effective rainfall (Re) as a percentage of the total monthly rainfall. For each one-inch increment in rainfall, there is a corresponding decrease in the percentage of effective rainfall.
USBR EFFECTIVE RAINFALL TABLE
MONTHLY
RAINFALL (R) (INCHES)
EFFECTIVE RAINFALL (RE)
(INCHES) 1 ≤ R RE = 0.95R 1 < R ≤ 2 RE = 0.95+0.90(R-1) 2 < R ≤ 3 RE = 1.85+0.82(R-2) 3 < R ≤4 RE = 2.67+0.65(R-3) 4 < R ≤5 RE = 3.32+0.45(R-4) 5 < R ≤6 RE = 3.77+0.25(R-5) R > 6 RE = 4.02+0.05(R-6)
Attachment A-9
Attachment A-10
USGS Gallinas River near Montezuma, NM
2009 Daily Mean Discharge, cubic feet per second
Date Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Ice Ice 8.9 14.0 48.0 12.0 11.0 6.7 4.4 7.7 12.0 Ice 2 Ice Ice 10.0 11.0 50.0 11.0 9.4 6.3 3.9 7.4 12.0 Ice 3 Ice Ice 11.0 13.0 52.0 12.0 11.0 5.8 4.6 7.2 13.0 Ice 4 Ice Ice 12.0 13.0 46.0 11.0 12.0 5.4 6.1 7.0 13.0 Ice 5 Ice Ice 13.0 12.0 47.0 9.9 25.0 5.8 6.0 6.7 13.0 Ice 6 Ice Ice 13.0 11.0 48.0 8.9 24.0 9.6 9.3 6.5 12.0 Ice 7 Ice Ice 13.0 12.0 49.0 8.0 17.0 6.7 6.3 7.5 13.0 Ice 8 Ice Ice 12.0 12.0 51.0 7.8 13.0 5.6 7.0 10.0 13.0 Ice 9 Ice Ice 13.0 13.0 50.0 6.9 11.0 5.0 7.4 8.0 12.0 Ice 10 Ice Ice 12.0 12.0 48.0 7.8 9.5 4.8 7.8 7.2 12.0 Ice 11 Ice Ice 10.0 14.0 45.0 10.0 8.5 4.9 6.6 6.9 11.0 Ice 12 Ice 7.0 10.0 14.0 42.0 8.0 7.7 5.6 6.4 6.7 11.0 Ice 13 Ice 7.2 12.0 14.0 37.0 7.5 6.9 5.1 29.0 7.1 10.0 Ice 14 Ice 6.9 9.4 16.0 32.0 8.6 4.7 6.4 29.0 7.2 11.0 Ice 15 Ice 7.7 11.0 16.0 29.0 10.0 5.1 6.4 19.0 6.6 10.0 Ice 16 Ice 7.9 11.0 17.0 27.0 7.0 5.7 5.1 34.0 6.4 8.5 Ice 17 Ice 8.1 11.0 19.0 26.0 6.2 5.9 4.5 64.0 6.3 8.9 Ice 18 Ice 6.8 12.0 20.0 24.0 5.9 5.8 4.3 52.0 6.3 9.1 Ice 19 Ice 7.4 13.0 24.0 21.0 5.5 6.1 4.1 33.0 6.3 8.9 Ice 20 Ice 7.6 14.0 24.0 19.0 86.0 6.6 3.8 26.0 6.4 8.1 Ice 21 Ice 7.8 14.0 26.0 18.0 41.0 8.9 3.7 21.0 13.0 8.2 Ice 22 Ice 7.6 16.0 29.0 21.0 25.0 12.0 3.5 18.0 15.0 8.4 Ice 23 Ice 8.6 17.0 35.0 28.0 19.0 11.0 3.5 16.0 12.0 7.9 Ice 24 Ice 9.4 16.0 37.0 29.0 16.0 21.0 3.3 17.0 12.0 6.3 Ice 25 Ice 9.6 16.0 42.0 24.0 15.0 13.0 3.6 17.0 13.0 8.8 Ice 26 Ice 9.9 15.0 46.0 22.0 13.0 12.0 3.9 15.0 14.0 11.0 Ice 27 Ice 9.6 13.0 45.0 24.0 13.0 11.0 4.1 13.0 15.0 10.0 Ice 28 Ice 9.1 13.0 43.0 21.0 12.0 9.7 4.3 12.0 15.0 9.2 Ice 29 Ice 15.0 44.0 20.0 13.0 8.7 3.9 11.0 13.0 7.7 Ice 30 Ice 14.0 47.0 18.0 12.0 8.1 3.6 11.0 12.0 6.2 Ice 31 Ice 12.0 16.0 7.5 3.5 14.0 Ice
Count 31 28 31 30 31 30 31 31 30 31 30 31
Max Ice 9.9 17.0 47.0 52.0 86.0 25.0 9.6 64.0 15.0 13.0 Ice
Min Ice 6.9 8.9 11.0 16.0 5.5 4.7 3.3 3.9 6.5 6.2 Ice
Irrigation Season Apr May Jun Jul Aug Sep Oct Total
Days > 15 cfs 17 31 5 4 0 13 0 70
Days <= 15 cfs 13 0 25 27 31 17 31 144
Attachment A-11
City of Las Vegas – Days On or Off the Gallinas River Date Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 On On On On On On Off Off On On On On2 On On On On On On Off Off On On On On3 On On On On On On Off Off On On On On4 On On On On On On Off Off On On On On5 On On On On On On On On On On On On6 On On On On On On On On On On On On7 On On On On On On On On On On On On8 On On On On On On On On On On On On9 On On On On On On On On On On On On10 On On On On On On On On On On On On11 On On On On On On On On On On On On12 On On On On On On On On On On On On13 On On On On On Off On On On On On On14 On On On On On Off On On On On On On15 On On On On On Off On On On On On On16 On On On On On Off On On On On On On17 On On On On On Off On On On On On On18 On On On On On Off Off On On On On On19 On On On On On Off Off On On On On On20 On On On On On Off Off On On On On On21 On On On On On On Off On On On On On22 On On On On On On Off On On On On On23 On On On On On On Off On On On On On24 On On On On On On Off On On On On On25 On On On On On Off On On On On On On26 On On On On On Off On On On On On On27 On On On On On Off On On On On On On28 On On On On On Off Off On On On On On29 On On On On Off Off On On On On On30 On On On On Off Off On On On On On31 On On On Off On On On
Count 31 28 31 30 31 30 31 31 30 31 30 31
Irrigation Season Apr May Jun Jul Aug Sep Oct TotalDays On 30 31 16 15 27 30 31 180 Days Off 0 0 14 16 4 0 0 34
Attachment A-12
GALLINAS RIVER FLOWS AND DIVERSIONS
August 13, 2009USGS Montezuma gage 4.20 cfs 4.20 cfs
City of Las Vegas 2.90 cfs
United World College 0.00Gallinas Canal 0.00 3.05 cfsStorrie Project 0.00 upstream of river gateAcequia Madre de Los Vigiles 0.15 cfs
Gallinas River below Storrie Project 1.31 cfs 1.31 cfs
Grzelachowski Ditch not divertingAcequia Madre de Los Romeros 1.60 cfsCleo Fresqez not divertingNuestra Senora de los Dolores 0.80 cfs 4.51 cfsAcequia Madre de Las Vegas 2.00 cfs downstream of gateRoundhouse Ditch not divertingPappen Ditch 0.11 cfs
Gallinas River below Pappen Ditch POD 0.09 cfs 0.09 cfs
Pecos Arroyo 2.70 cfs
USGS Lourdes gage 3.45 cfs
August 21, 2009USGS Montezuma gauge 3.70 cfs 3.70 cfs
City of Las Vegas 2.79 cfs
United World College 0.00Gallinas Canal 0.00 2.79 cfsStorrie Project 0.00 upstream of river gateAcequia Madre de Los Vigiles 0.00
Gallinas River below Storrie Project 0.74 cfs 0.74 cfs
Grzelachowski Ditch not divertingAcequia Madre de Los Romeros 0.60 cfsCleo Fresqez not divertingNuestra Senora de los Dolores 0.30 cfs 3.34 cfsAcequia Madre de Las Vegas 1.60 cfs downstream of gateRoundhouse Ditch 0.80 cfsPappen Ditch 0.04 cfs
Gallinas River below Pappen Ditch POD 0.04 cfs 0.04 cfs
Pecos Arroyo 2.28 cfs
USGS Lourdes gauge 2.81 cfs
Attachment A-13
USGS 13 cfs 13 cfs
GALLINAS RIVER FLOWS AND DIVERSIONS
August 28, 2009USGS Montezuma gauge 4.30 cfs 4.30 cfs
City of Las Vegas 2.90 cfs
United World College 0.00Gallinas Canal 0.00 2.90 cfsStorrie Project 0.00 upstream of river gateAcequia Madre de Los Vigiles 0.00
Gallinas River below Storrie Project 0.69 cfs 0.69 cfs
Grzelachowski Ditch not divertingAcequia Madre de Los Romeros 0.40 cfsCleo Fresquez 0.20 cfsNuestra Senora de los Dolores 0.30 cfs 2.40 cfsAcequia Madre de Las Vegas 1.30 cfs downstream of gateRoundhouse Ditch 0.20 cfsPappen Ditch not diverting
Gallinas River below Pappen Ditch POD 0.04 cfs 0.04 cfs
Pecos Arroyo 2.70 cfs
USGS Lourdes gauge 2.96 cfs
October 8, 2009USGS Montezuma gaugeMontezuma gauge 13.00.00 cfs 13.00.00 cfs
City of Las Vegas 2.23 cfs
United World College 0.00Gallinas Canal 0.00 4.73 cfsStorrie Project 0.00 upstream of river gateAcequia Madre de Los Vigiles 2.50
Gallinas River below Storrie Project 5.47 cfs 5.47 cfs
Grzelachowski Ditch not divertingAcequia Madre de Los Romeros 3.80 cfsCleo Fresquez not divertingNuestra Senora de los Dolores 1.20 cfs 8.50 cfsAcequia Madre de Las Vegas 2.40 cfs downstream of gateRoundhouse Ditch 1.10Pappen Ditch not diverting
Gallinas River below Pappen Ditch POD 0.19 cfs
Pecos Arroyo 3.43 cfsUSGS Lourdes gauge 4.91 cfs
Attachment A-13
2010 SNOTEL Report (in inches)Wesner Springs
MonthDay SWE Snow SWE Snow SWE Snow SWE Snow SWE Snow SWE Snow
01 0.0 1.0 2.1 10.0 1.7 7.0 5.3 22.0 9.5 40.0 12.5 49.0
02 0.0 0.0 2.1 8.0 1.7 7.0 5.4 21.0 9.5 39.0 12.7 51.0
03 0.0 0.0 1.9 8.0 1.7 6.0 5.4 21.0 9.5 38.0 12.8 48.0
04 0.0 0.0 1.9 7.0 1.7 8.0 5.4 21.0 10.6 46.0 12.8 46.0
05 0.0 0.0 1.7 6.0 1.9 8.0 5.4 21.0 10.5 46.0 12.8 44.0
06 0.0 0.0 1.6 5.0 1.9 8.0 5.4 21.0 10.5 45.0 12.8 44.0
07 0.0 0.0 1.4 4.0 1.9 8.0 5.4 21.0 10.6 44.0 12.8 44.0
08 0.0 0.0 1.4 4.0 3.3 21.0 5.4 20.0 10.7 45.0 13.5 47.0
09 0.0 0.0 1.3 5.0 4.5 27.0 5.4 20.0 10.9 49.0 13.9 52.0
10 0.0 0.0 1.3 5.0 4.6 25.0 5.4 20.0 11.0 50.0 14.0 50.0
11 0.0 0.0 1.3 4.0 4.7 23.0 5.4 20.0 11.0 48.0 14.1 52.0
12 0.0 0.0 1.2 4.0 4.7 21.0 5.4 20.0 11.0 46.0 14.1 53.0
13 0.0 0.0 1.1 3.0 4.7 21.0 5.4 19.0 11.1 45.0 14.2 51.0
14 0.0 0.0 1.2 2.0 4.9 23.0 5.4 20.0 11.1 44.0 14.2 49.0
15 0.0 0.0 1.3 5.0 4.9 22.0 5.4 19.0 11.1 44.0 15.0 59.0
16 0.0 1.0 1.4 6.0 4.9 20.0 5.4 20.0 11.1 43.0 15.2 61.0
17 0.0 1.0 1.5 6.0 4.9 19.0 5.4 20.0 11.1 42.0 15.2 58.0
18 0.0 0.0 1.5 5.0 4.9 20.0 5.3 20.0 11.1 41.0 15.3 55.0
19 0.0 0.0 1.5 5.0 4.9 20.0 5.4 20.0 11.1 41.0 15.3 53.0
20 0.0 0.0 1.5 5.0 4.9 19.0 6.5 30.0 11.1 40.0 16.3 68.0
21 0.6 0.0 1.5 5.0 4.9 19.0 6.7 32.0 11.2 41.0 16.3 65.0
22 1.6 9.0 1.5 5.0 4.9 18.0 7.6 34.0 11.6 45.0 16.3 60.0
23 1.5 10.0 1.5 5.0 5 16.0 8.4 38.0 12.1 54.0 16.3 58.0
24 1.4 8.0 1.5 6.0 5.2 23.0 8.5 41.0 12.1 51.0 16.5 59.0
25 1.3 7.0 1.5 6.0 5.2 22.0 8.5 39.0 12.2 48.0 16.4 59.0
26 1.6 8.0 1.5 5.0 5.2 22.0 8.6 38.0 12.2 48.0
27 1.8 10.0 1.5 5.0 5.2 22.0 8.7 36.0 12.2 46.0
28 1.8 10.0 1.5 5.0 5.2 21.0 8.9 38.0 12.2 45.0
29 2.0 13.0 1.6 7.0 5.3 21.0 9.5 45.0
30 2.1 12.0 1.7 7.0 5.3 21.0 9.5 44.0
31 2.1 12.0 5.3 23.0 9.5 41.0
March
Atta
ch
men
t A-1
4
October November December January February
2009 Historical Snow Water Equivalent Data for Wesner Springs
Station : NM05P08S, WESNER SPRINGS ------- Unit = inches day oct nov dec jan feb mar apr may jun jul aug sep --- --- --- --- --- --- --- --- --- --- --- --- --- 1 0.00 0.00 1.30 8.60 9.90 10.50 10.20 7.60 0.00 0.00 0.00 0.00 2 0.00 0.00 1.40 8.60 9.90 10.40 10.20 6.30 0.00 0.00 0.00 0.00 3 0.00 0.00 1.40 8.60 9.90 10.30 10.20 6.20 0.00 0.00 0.00 0.00 4 0.00 0.00 1.40 8.60 9.90 10.10 10.20 6.00 0.00 0.00 0.00 0.00 5 0.00 0.00 1.40 9.00 9.90 10.10 10.20 5.50 0.00 0.00 0.00 0.00 6 0.00 0.00 1.40 9.10 9.90 10.10 10.10 4.70 0.00 0.00 0.00 0.00 7 0.00 0.00 1.40 9.10 9.90 10.10 10.00 3.50 0.00 0.00 0.00 0.00 8 0.00 0.10 1.40 9.10 9.90 10.10 9.20 2.50 0.00 0.00 0.00 0.00 9 0.00 0.10 1.50 9.20 10.20 10.10 8.30 1.20 0.00 0.00 0.00 0.00 10 0.00 0.20 1.80 9.50 10.20 10.20 8.10 0.00 0.00 0.00 0.00 0.00 11 0.00 0.50 1.90 9.50 10.20 10.20 8.20 0.00 0.00 0.00 0.00 0.00 12 0.10 0.50 1.90 9.60 10.50 10.20 9.10 0.00 0.00 0.00 0.00 0.00 13 0.00 0.50 2.30 9.60 10.50 10.30 9.60 0.00 0.00 0.00 0.00 0.00 14 0.00 0.60 2.60 9.60 10.50 10.80 9.60 0.00 0.00 0.00 0.00 0.00 15 0.90 0.40 3.00 9.50 10.50 10.90 9.60 0.00 0.00 0.00 0.00 0.00 16 0.90 0.50 4.40 9.50 10.50 10.80 9.60 0.00 0.00 0.00 0.00 0.00 17 0.70 0.40 4.80 9.60 10.50 10.80 9.60 0.00 0.00 0.00 0.00 0.00 18 0.40 0.30 4.90 9.60 10.50 10.70 10.40 0.00 0.00 0.00 0.00 0.00 19 0.10 0.30 5.50 9.50 10.50 10.70 10.50 0.00 0.00 0.00 0.00 0.00 20 0.00 0.20 5.50 9.60 10.60 10.60 10.60 0.00 0.00 0.00 0.00 0.00 21 0.00 0.10 5.50 9.70 10.60 10.60 10.60 0.00 0.00 0.00 0.00 0.00 22 0.00 0.20 5.50 9.70 10.60 10.60 10.60 0.00 0.00 0.00 0.00 0.00 23 0.00 0.20 6.50 9.70 10.50 10.60 10.40 0.00 0.00 0.00 0.00 0.00 24 0.00 0.10 7.70 9.70 10.50 10.60 10.30 0.00 0.00 0.00 0.00 0.50 25 0.00 0.10 7.90 9.70 10.50 10.60 10.00 0.00 0.00 0.00 0.00 0.40 26 0.10 0.10 8.30 9.70 10.50 10.60 9.80 0.00 0.00 0.00 0.00 0.10 27 0.00 0.20 8.50 9.70 10.50 11.10 9.60 0.00 0.00 0.00 0.00 0.00 28 0.00 1.30 8.60 9.70 10.50 10.90 9.40 0.00 0.00 0.00 0.00 0.00 29 0.00 1.30 8.60 9.80 --- 10.80 9.00 0.00 0.00 0.00 0.00 0.00 30 0.00 1.30 8.60 9.80 --- 10.60 8.70 0.00 0.00 0.00 0.00 0.00 31 0.00 --- 8.60 9.90 --- 10.60 --- 0.00 --- 0.00 0.00 --- mean 0.10 0.32 4.37 9.42 10.31 10.50 9.73 1.40 0.00 0.00 0.00 0.03 max 0.90 1.30 8.60 9.90 10.60 11.10 10.60 7.60 0.00 0.00 0.00 0.50 min 0.00 0.00 1.30 8.60 9.90 10.10 8.10 0.00 0.00 0.00 0.00 0.00
Attachment A-15
Attachment A-16