Upload
lindsey-hoffman
View
214
Download
2
Embed Size (px)
DESCRIPTION
a
Citation preview
Work Breakdown Structure Green Roof Project WBS Level 1 Main Task Item 1. Green Roof Project
WBS Level 2 Main Task Project
Number Item
1. 1.1 Contractor Interview Process 1.2 Design of Green Roof 1.3 Flowers, Vegetation and Planting
Materials Selection 1.4 Planting Day
WBS Level 3 Main Task
Project Number and Item Name
Sub-item Number
Task
1.1 Contractor Interview Process
1.1.1 Research Contractors
1.1.2 Contact the contractors to arrange interviews 1.1.3 Request Testimonies/References from Contractors 1.1.4 Contact references and former clients. 1.1.5 Select Contractor 1.1.6 Contact Contractor and sign contract
1.2 Design of Green Roof
1.2.1 Advertise Ideal Week 1.2.2 Collect submissions 1.2.3 Select the five most feasible options 1.2.4 Hold a campus-wide vote 1.2.5 Review the design with contractor 1.2.6 Contractor provide final design
1.3 Flowers, Vegetation, and Planting Materials Selection
1.3.1 Research native plants 1.3.2 Finalize the plant species 1.3.3 Approach greenhouses for potential sponsorships 1.3.4 Approach campus maintenance about borrowing tools 1.3.5 Finalize date and list of required items 1.3.6 Report to the team about the items that will be used
1.4. Planting Day 1.4.1 Contractor give Calley approval 1.4.2 Pick up equipment 1.4.3 Create an inventory and hand out the equipment 1.4.4 Start planting 1.4.5 At the end of the day, collect the tools and store it 1.4.6 Ask people to take breaks 1.4.7 Return all the equipment