Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

Embed Size (px)

Citation preview

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    1/40

    2.0 WEIR INTAKE STRUCTURE

    ITEM 2.1 COFFERDAM

    2.1.1 GENERAL

    2.1.1.1 DESCRIPTION

     To ensure that all areas are free from the disturbance that the water will

    cause to the constructions, this item shall contain but not limited to the

    following works:

    a. Excavation required for the construction of the weir

     b. Disposal of the excavated material

    c. Backfilling around the weir structure to the original ground level or as

    required by the plans

    d. Works to make sure that all areas are free from water at all times during

    construction such as pumping and dewatering

    e. Sheet piling (if necessary)

    f. Construction and removal of temporary structures such as cofferdam,

    pipes, canals and ditches.

    g. Diversion of existing waterways

     The Contractor shall submit to the Engineer a comprehensive plan and

    construction methodology on how he proposes to achieve this task. This

    shall include all the materials, labor, equipment, tools, pumping units, etc.

    2.1.2 EXECUTION

     The Contractor shall have an engineering documentation for every cofferdam

    installation activity and is accessible for review by the Engineer and

    installation personnel. It must also provide a means of being held firmly and

    securely against the hull in the event of a loss of differential pressure. All

    patches must be secured such that they cannot rotate or move out of

    alignment with the hull opening.

    2.1.3 MEASUREMENT/BASIS OF PAYMENT

     Accomplishment shall be expressed in percentage of all accepted work items

    accomplished included of the Bill of Quantities for the period covered.

     The accepted quantities measured and prescribed above shall be paid for at the

    unit price indicated in the Bill of Quantities. This payment shall constitute full

    payment of all work done related to care of water, materials, labor, equipment,

    tools and incidentals necessary to complete this prescribed work item.

    ITEM 2.2 CLEARING AND GRUBBING

    2.2.1 GENERAL

    2.2.1.1 DESCRIPTION

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    2/40

     The Work under this item includes providing all labor, materials, tools and

    equipment necessary for clearing, grubbing, removing and disposing of all

     vegetation and debris (including earthen materials incidentally removed

     with vegetation and debris), and removing structures and obstructions

    located within the limits shown on the plans or designated by the Engineer,

    except such objects as are designated to remain in place or are to be

    removed in accordance with other sections of these Specifications. The

     Work shall also include the preservation from injury or defacement of all

     vegetation and objects designated to remain

    2.2.2 EXECUTION

    2.2.2.1 CLEARING

    Clearing shall consist of removing shrubs, and brush and disposal of all

    debris including rubbish occurring within areas to be cleared. Stumps,

    roots, brush, and other vegetation in the areas to be cleared shall be cut off

     below the original ground surface.

    2.2.2.2 HAND – CLEARING

    In areas where Hand Clearing is indicated on the Plans or designated by the

    Engineer, no equipment on wheels shall be used. Care shall be taken to

    insure that the grass, moss cover, or the natural ground as indicated in the

    plan is not disturbed.

    2.2.2.3 SELECTED TREE REMOVAL

     Trees designated by the Engineer, outside of the normal clearing and

    grubbing and/or hand clearing limits, shall be removed and disposed of in

    accordance with this item. Trees to be removed may be designated by the

    Engineer at any time during the performance of the contract, and may be

    subject to the conditions specified under Hand Clearing. Trees designated

    for selective removal shall be cut off within six inches of the ground.

    2.2.2.4 REMOVE AND RELOCATE BUSH OR TREE

    Bushes or trees shown on the Plans for removal and relocation shall be

    removed and relocated as directed by the Engineer. Bushes and treesdesignated for removal and relocation shall be carefully removed with

    enough of the root wad kept intact to ensure the survival of the bush or tree

    in its new locations. Bushes and trees designated for removal and

    relocation that are damaged, or that do not survive as a result of the

    transplanting, shall be replaced by the Contractor at its expense. The

    relocated bush or tree shall be placed to original depth at a location as

    directed by the Engineer.

    2.2.2.5 GRUBBING

    Grubbing shall consist of removal and disposal of stumps, roots larger than

    seventy five (75) millimeters in diameter and matted roots from designated

    grubbing areas. Logs and other organic or metallic debris and abandoned

    concrete footings shall be removed.

    2.2.2.6 STRIPPING

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    3/40

     Those areas that will be disturbed by excavation, filling, access road

    development, or compaction by equipment will be soil stripped to a depth of

    one hundred fifty (150) meters taking into consideration all planned erosion

    and sediment control practices shall be in place and functioning properly

    prior to soil stripping.

    2.2.3 PRODUCTS

    2.2.3.1 STORAGE PILES

     Topsoil that is suitable for reuse shall be placed in storage piles convenient

    to areas that are to receive application of topsoil. Topsoil shall be kept

    separate from the other excavated materials and shall be free of roots,

    stones larger than five (5) centimeters and other undesirable materials that

     would interfere with the planting.

    2.2.4 MEASUREMENT/BASIS OF PAYMENT

     The area that is to be cleared and grubbed to be paid for will be the number of

    square meter measure on the ground or site of the weir acceptably cleared in

    conformity with the plans or as directed by the Engineer.

     The accepted quantities, measured as prescribed above shall be paid for at the

    contract unit price for each of the particular pay items listed and included in

    the Bill of Quantities. The payment shall constitute full compensation for the

    removal and disposal of cleared and grubbed materials including all labor,

    equipment tools and incidentals necessary to complete the work prescribed in

    this item.

    ITEM 2.3 EARTH EXCAVATION

    2.3.1 GENERAL

     The excavation will generally refer to open excavation of foundation wet or dry

    and in all sorts of soils.

    2.3.1.1 DESCRIPTION

     This item shall consist of the necessary excavation for foundations and

    other structures indicated in the Plans, in accordance to these

    specifications and in conformity with the lines, grades and dimensions

    shown in the Drawings as indicated and established by the Engineer. The

    Contractor shall be aware of obstructions such as pipes, conduits and

    cables in the areas to be excavated. The Contractor shall verify the

    existence and location of such obstructions before the start of excavation.

     All excavated materials shall be disposed properly and deposited at

    locations indicated by the Engineer.

      2.3.1.2 NATURE of EXCAVATION:

    2.3.1.2.1 Unclassified Excavation – Unclassified excavation shall consist of

    the excavation and disposal of all materials regardless of its nature, or

    not classified and included in the Bill of Quantities under other pay

    items.

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    4/40

    2.3.1.2.2 Common Excavation – Common excavation are those not included

    in the Bill of Quantities under “Rock Excavation” or other pay items.

    2.3.1.2.3 Muck Excavation – Muck Excavation shall consist of the removal

    and disposal of deposits of saturated of unsaturated mixtures of soils

    and organic matter not suitable for foundation materials regardless ofmoisture content.

    2.3.2 EXECUTION

    Before commencement of excavation, spot levels on an approved grid covering

    the entire plot shall be taken by the Contractor in consultation with the

    Engineer and a proper record of these levels shall be kept jointly signed by the

    Contractor and the Engineer. A block level plan showing all ground levels of the

    plot shall be prepared by Contractor and shall also be jointly signed by the

    Contractor and the Engineer.

    Excavation shall include removal of all materials of whatever nature at all

    depths and whether wet or dry necessary for the construction of foundation

    exactly in accordance with lines, levels, grades and curves shown in the Plans

    or as directed by the Engineer. The bottoms of excavation shall be leveled both

    longitudinal and transversely or sloped as directed by the Engineer.

    Should the contractor excavate to a greater depth or width than shown on the

    Plans or as directed by the Engineer, he shall at his own expense fill the extra

    depth or width in cement concrete in proportion as to be directed by the

    Engineer. The Contractor shall report to the Engineer when the excavations areready to receive concrete. No concrete shall be placed in foundations until the

    Contractor has obtained the Engineer’s approval. In case, the excavation is

    done through different types of soil and if different rates are applicable as per

    provision in the Bill of Quantities, the Contractor must get the dimensions of

    the strata agreed by the Engineer for payment. If no specific provisions is made

    in the Bill of Quantities it will be presumed that excavation shall be in all types

    of soil and the contractor's rate hall cover for the same.

     When there is evidence of discrepancy between the actual elevations and those

    shown in the plans, a pre-construction survey shall be conducted by the

    Contractor under the control of the Engineer to serve as the basis for the

    computation of the actual volume of excavated materials. All excavation shall

     be finished to a reasonably smooth and even surface. Excavation operation

    shall be carried out with outmost care ensuring that foundations below

    existing parts of structure shall not be disturbed.

    If instructed by the Engineer all foundation pits, and similar excavations shall

     be strongly fenced and marked with red lights at night to avoid accidents.

     Adequate protective measure shall be taken to make sure that the excavation

    does not affect or damage adjoining structures. All measures required for the

    safety of excavations, the people working in and around the foundation

    trenches, property and the people in the vicinity shall be taken by the

    Contractor at his own cost. He shall be entirely responsible for any injury and

    damage to property caused by his negligence or accident due to his

    constructional operations, storage of materials etc. Should there be

    disturbance of foundations below existing structures same shall be repaired

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    5/40

    and restored in a manner acceptable to the Engineer at no additional cost or

    compensation.

    2.3.2.1 SHORING

     The sides of the excavations should be timbered or supported in such a

     way as is necessary to secure these from falling in, and the shoring shall

     be maintained in position as long as necessary. The Contractor shall be

    responsible for the proper design of the shoring to be approved by the

    Engineer to hold the sides of the excavation in position and ensure safety

    of persons and properties. The shoring shall be removed as directed after

    the items for which it is required are completed. Unless otherwise

    mentioned in the Bill of Quantities no extra payment will be made for

    shoring.

    2.3.2.2 STACKING OF EXCAVATED MATERIALS

    Materials suitable and useful for back filling, plinth filling or levelling of

    the plot or other use shall be stacked in convenient places but not in such

    a way as to obstruct free movement of men, animals and vehicles or

    encroach on the area required for constructional purposes.

    2.3.2.3 BACKFILLING

     All shoring and form work shall be removed after their necessity ceases

    and trash of any sorts shall be cleaned out from the excavation. All space

     between foundation masonry or concrete and sides of excavation shall be

    refilled to the original surface with approved excavated materials in layers

    fifteen (15) centimeter in thickness watered and rammed. The filling shall

     be done after concrete or masonry is fully set and done in such a way as

    not to cause undue thrust on any part of the structure. Where suitable

    excavated materials is to be used for refilling it shall be brought from the

    place where it is temporarily stacked and used in refilling.

    No excavation of foundations shall be filled in or covered up until all

    measurements of excavations, masonry concrete and other works below

    ground level are jointly recorded. Black cotton soil shall not be used for

     back filling or in plinth filling.

    2.3.2.4 DEWATERING

    Excavation shall include bailing or pumping out water which may

    accumulate in the excavation during the progress of work either from

    seepage, springs, rain or any other cause and diverting surface flow if any

     by bunds or other means. Pumping out of water shall be done in such

    approved manner as to preclude the possibility of any damage to the

    foundation trench concrete or masonry or any adjacent structure. When

     water is met in foundation trenches or in tank excavations, pumping out

     water shall be carried out from auxiliary pit of adequate size dug slightly

    outside the excavations. The depth of auxiliary pit shall be more than the

     working foundation trench levels. The auxiliary pit shall be refilled with

    approved excavated materials after the dewatering is over. The excavation

    shall be kept free from water:

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    6/40

    a. during inspection and measurement

     b. When concrete / masonry works are in progress and till they come

    above the natural water level and

    c. Till the Engineer consider that the concrete/mortar is sufficiently set

    2.3.2.5 SURPLUS EXCAVATED MATERIALS

     All excavated materials certified as surplus and not useful shall be

    removed by the Contractor from the site in an approved manner with the

    approval of the Local Authority as required to his own dump and shall be

    paid as a separate item as in the Bill of Quantities. No extra claim on any

    account will be paid. The items of removal of surplus excavated materials

    shall only be undertaken by the Contractor when specific instruction in

    this regard has been obtained from the Engineer. The Contractor must also

    secure the approval of the Engineer regarding the quantity of surplusmaterials to be removed prior to commencement of this item of work.

    2.3.3 MEASUREMENT/BASIS OF PAYMENT

     The volume of excavation to be paid for will be the number of cubic meter

    measure in the original position of material acceptably excavated in conformity

     with the plans or as directed by the Engineer.

     The accepted quantities, measured as prescribed above shall be paid for the

    contract unit price for each of the particular pay items listed and included in

    the Bill of Quantities. The payment shall constitute full compensation for theremoval and disposal of excavated materials including all labor, equipment

    tools and incidentals necessary to complete the work prescribed in this item.

    ITEM 2.4 ROCK EXCAVATION

    2.4.1 GENERAL

    2.4.1.1 DESCRIPTION

     This item shall consist of the necessary rock excavation for foundations

    and other structures indicated in the Plans, in accordance to these

    specifications and in conformity with the lines, grades and dimensions

    shown in the plans of as indicated and established by the Engineer. The

    Contractor shall be aware of obstructions such as pipes, conduits andcables in the areas to be excavated. The Contractor shall verify the

    existence and location of such obstructions before the start of excavation.

     All excavated materials shall be disposed properly and deposited at

    locations indicated by the Engineer.

    2.4.1.2 Nature of Excavation:

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    7/40

    Rock excavation shall consist of igneous, sedimentary and metamorphic

    rock which cannot be excavated without blasting or the use of rippers, and

    all boulders or other detached stones each having a volume of 1 cubic

    meter or more as determined by physical measurements or visually by the

    Engineer.

    2.4.2 EXECUTION

    Before commencement of excavation spot levels on an approved grid covering

    the entire plot shall be taken by the Contractor in consultation with the

    Engineer and a proper record of these levels shall be kept jointly signed by the

    Contractor and the Engineer. A block level plan showing all ground levels of the

    plot shall be prepared by Contractor and shall also be jointly signed by the

    Contractor and the Engineer.

     When there is evidence of discrepancy between the actual elevations and those

    shown in the plans, a pre-construction survey shall be conducted by the

    Contractor under the control of the Engineer to serve as the basis for the

    computation of the actual volume of excavated materials. All excavation shall

     be finished to a reasonably smooth and even surface. Excavation operation

    shall be carried out with outmost care ensuring that foundations below

    existing parts of structure shall not be disturbed.

    If instructed by the Engineer all foundation pits, and similar excavations shall

     be strongly fenced and marked with red lights at night to avoid accidents.

     Adequate protective measure shall be taken to make sure that the excavation

    does not affect or damage adjoining structures. All measures required for the

    safety of excavations, the people working in & around the foundation trenches,

    property and the people in the vicinity shall be taken by the Contractor at his

    own cost. He shall be entirely responsible for any injury and damage to

    property caused by his negligence or accident due to his constructional

    operations, storage of materials etc. Should there be disturbance of

    foundations below existing structures same shall be repaired and restored in a

    manner acceptable to the Engineer at no additional cost or compensation.

    2.4.2.1 BLASTING

     The transportation, handling, storage, and use of dynamite and other

    explosives shall be directed and supervised by a personnel of proven

    experience and ability who is authorized and qualified to conduct blasting

    operations.

    Blasting shall be done in a manner as to prevent damage to the work or

    unnecessary fracturing of the underlying rock materials and shall conform

    to any special requirements specified. When specified, the contractor shall

    furnish the Engineer, in writing, a blasting plan before blasting operations

     begin.

    2.4.2.2 USE OF EXCAVATED ROCK MATERIALS

    Suitable material from the specified excavations may be used in the

    construction of required rock fill. The suitability of material for specific

    purposes is determined by the Engineer.

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    8/40

    2.4.2.3 DISPOSAL OF WASTE MATERIALS

     All surplus or unsuitable excavated materials are designated as waste and

    shall be disposed of by the Contractor at sites of his own choosing away

    from the site of the work. The disposal shall be in an environmentally

    acceptable manner that does not violate local and national rules andregulations.

    2.4.2.4 EXCAVATION LIMITS

    Excavations shall comply with Department Order No. 13 – 1998 otherwise

    known as Guidelines Governing Occupational Safety and Health in the

    Construction Industry. All excavations shall be completed and maintained

    in a safe and stable condition throughout the total construction phase.

    Structure and trench excavations shall be completed to the specified

    elevations and to the length and width required to safely install, adjust,

    and remove any forms, bracing, or supports necessary for the installation

    of the work. Excavations outside the lines and limits shown on the Plans

    or specified herein required to meet safety requirements shall be the

    responsibility of the Contractor in constructing and maintaining a safe and

    stable excavation.

    2.4.3 MEASUREMENT/METHOD OF PAYMENT

     The volume of excavation to be paid for will be the number of cubic meter

    measure in the original position of material acceptably excavated in

    conformity with the plans or as directed by the Engineer.

     The accepted quantities, measured as prescribed above shall be paid for

    the contract unit price for each of the particular pay items listed and

    included in the Bill of Quantities. The payment shall constitute full

    compensation for the removal and disposal of excavated materials

    including all labor, equipment tools and incidentals necessary to complete

    the work prescribed in this item.

    ITEM 2.5 HAULING OF MATERIALS

    2.5.1 GENERAL

    2.5.1.1 DESCRIPTION

     This item shall consist of hauling of materials specified in the Bill of

    Materials needed for the project. These are aggregates, cement, reinforcing

     bars, lumbers, formwork sand and other materials needed for the

    completion of the project.

    2.5.2 EXECUTION

     The Contractor shall be responsible for monitoring truck weight regulations or

    the maximum allowable loads for various axle configurations on roadways

    outside the project limits and on roadways within the project limits open to

    general traffic. All hauling units delivering equipment or materials to the

    project shall be of legal weight loads and/or have appropriate hauling permits.

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    9/40

     The volume or amount of materials to be hauled to the project location of the

    project will conform to the amount of materials required for the project as

    specified on the Bill of Materials.

    2.5.3 MEASUREMENT/BASIS OF PAYMENT

     The Contractor will be paid as per accomplishment of the project.

    ITEM 2.6 ANCHORING 20MM Ø RSB

    2.6.1 GENERAL

    2.6.1.1 DESCRIPTION

     This work shall consist of the installation of rock dowels at the locations

    and orientations designated in the Plans or by the Engineer. The

    Contractor shall select and construct the dowels and supply all materials,

    equipment, and labor to test and install the dowels. The Engineer will

    designate the orientation and minimum length of the dowel required.

    2.6.2 SUBMITTALS

    Not less than two weeks prior to commencing the rock doweling, the Contractor

    shall submit in writing to the Engineer for approval:

     The Contractor shall provide written evidence that the foreman and drill

    operator have performed satisfactory work in similar capacities elsewhere. The

    drill operator assisted by the foreman shall have installed rock dowels as

    indicated in the Plan.

     The Contractor shall submit a detailed plan for the rock doweling to include:

    a.The proposed construction sequence and schedule.

     b.The proposed drilling method and equipment.

    c.The proposed drill hole diameter.

    d.The proposed cement grout mix design

    e.The proposed construction method for upwardly inclined anchors.

    f.The proposed corrosion protection for the rock dowel system.

    g.The calibration data for each load cell, test jack, pressure gauge and

    master pressure gauge to be used in the proof testing.

    h.The proposed stressing procedures and stressing equipment to proof test

    the dowels.

     Work shall not begin until the Engineer has approved the appropriate

    submittals in writing.

    2.6.3 MATERIAL REQUIREMENTS

     All rock dowels, including anchorage, bearing plates, couplers, corrosion

    protection, and other appurtenances, shall be products of a manufacturer

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    10/40

    regularly engaged in the manufacturing of materials for the construction of

    rock dowels.

    Dowels shall be fabricated from deformed steel bars in general compliance with

    DPWH Standard Specification. Anchor bar steel shall not be precut at the

    factory to lengths shown in the Plans, but rather be delivered in bulk lengthsand field cut to the appropriate length. Anchor bar steel shall be provided with

    either fusion-bonded epoxy coating or hot dip galvanizing for corrosion

    protection. Epoxy coating shall be applied in accordance with ASTM A.

    Extreme care shall be taken in the handling of epoxy-coated bars to prevent

    coating damage and embrittlement. Field handling procedures for epoxy-

    coated bars shall be in general accordance with ASTM D 3963 including

    providing padding between contact points during storage and lifting and

    covering coated bars to minimize ultraviolet exposure. Hot dip galvanizing

    shall comply with ASTM A 15.

    Each rock dowel shall be fitted with a bearing plate and nut. The plate shall

    have a central hole large enough to fit easily over the dowel while maximizing

    the average bearing surface for the washer and the nut. Spherical seating of

    the nut is not required. Beveled washers shall be used to accommodate non-

    perpendicular installations.

    Cement grout shall be a proven, non-shrink material capable of permanently

    developing the bond and internal strength necessary for the required dowel

    capacity. The use of epoxy or polyester resin as bonding agents is not allowed.

    If requested by the Engineer, a sample of the cement grout shall be provided fortesting.

    2.6.4 EXECUTION

     Work shall proceed according to the plan and schedule submitted by the

    Contractor prior to the commencement of the work.

     The Engineer shall specify the location, orientation, and minimum length of

    each rock dowel. The rock dowel shall be installed within five degrees of the

    specified angle. Unless otherwise specified, the angle of installation shall be

    perpendicular to the rock face and inclined slightly downward. If the axis of

    the rock dowel is not close to perpendicular to the rock face or within the angle

    provided by the beveled washer, or the rock beneath the bearing plate is not

    sound, a bearing pad approved by the Engineer shall be constructed at no

    additional cost, so that the rock dowel is not bent when tensioned. In all

    cases, at least three quarters of the bearing plate shall be in contact with the

    rock face.

     The dowels shall be handled and stored in such a manner as to avoid damage

    or corrosion of the coating and the steel. Damage to the dowel steel as a result

    of abrasion, cuts, nicks, welds, and weld splatter will be cause for rejection.

     The dowels shall be protected from dirt, rust, and harmful substances. If

    heavy corrosion or pitting is noted, the Engineer will reject the rock dowel.

     The entire length of the rock dowel shall be encapsulated in cement grout for a

    second level of corrosion protection. All exposed parts of the dowel, bearing

    plate and nut on the surface shall be painted with approved corrosion

    protection paint or epoxy patching compound.

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    11/40

     The use of hand drills for advancing the anchor hole is not allowed without

     written permission by the Engineer and demonstrated effectiveness by the

    Contractor.

     The drill hole shall be sized to provide a minimum of 50 millimeter of grout

    cover around the bar. The Contractor shall flush the drill hole of all drillcuttings and debris with compressed air prior to the installation of the rock

    dowel. Holes drilled for rock dowels in which dowel installation is considered

     by the Engineer to be impractical shall be re-drilled at the Contractor’s

    expense.

     The grout equipment shall produce a grout free of lumps and undispersed

    cement. The pump shall be equipped with a pressure gauge near the discharge

    end to monitor grout pressures. The grouting equipment shall be sized to

    enable the grout to be pumped in one continuous operation. The grout shall

     be injected from the lowest point of the drill hole. The quantity of the groutand the grout pressures shall be recorded.

     When the cement grout has reached final set, the Contractor shall install the

     bearing plate, washers and nut. The end of the completed rock dowel shall be

    trimmed to within 15 centimeters of the rock face.

     At the discretion of the Engineer, up to 5 percent, but not less than three rock

    dowels, of the installed rock dowels shall be proof tested. The Contractor shall

    conduct the proof test, and the Engineer will interpret the results. The rock

    dowel shall be tensioned to 11, 500 kilograms with a calibrated hollow-ram

    hydraulic jack using a bar extension and coupler attached to the rock dowel

    and held for 10 minutes. If no loss of load occurs over this time period, the

    rock dowel is acceptable. The Engineer may require additional proof of testing

     beyond the 5 percent maximum, if rock dowels fail the proof testing. All failed

    rock dowels shall be replaced with an additional rock dowel installed in a

    separate hole. No payment will be made for rock dowels that fail or for

    additional proof testing.

    2.6.5 MEASUREMENT/BASIS OF PAYMENT

    Rock dowels will be measured per linear meter of rock dowel installed and

    accepted.

     The accepted quantity shall be paid for at the contract unit price and payment

    shall be full compensation for furnishing and placing all materials, including

    all labor, equipment, tools and incidentals necessary to complete the work

    prescribed in this item.

    ITEM 2.7 STONE MASONRY

    2.7.1 GENERAL

    2.7.1.1 DESCRIPTION

     This item shall consist of stone masonry in minor structures, in headwalls,

    for culverts, in retaining walls at the toes of slopes, and other places called

    for on the plans, constructed on the prepared foundation bed in

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    12/40

    accordance with this Specifications and in conformity with the lines,

    grades, sections, and dimensions shown in the plans or as ordered in

     writing by the Engineer. It shall include all management, labor,

    transportation, materials, tools, equipment and services required to

    manufacture, assemble, deliver, and install all items necessary for the

    proper execution and completion of said items of work.

    2.7.2 MATERIAL REQUIREMENTS

    2.7.2.1 STONE

     The stone shall be clean, hard and durable and shall be subjected to the

    Engineer’s approval. Adobe stone shall not be used unless otherwise

    specified.

    Sizes and Shaped. Unless other sizes are shown on the plans, stones shall

    have a thickness of not less than one and one half times their respectivethickness, and lengths of not less than one and one half times their

    respective widths.

    Dressing. The stone shall be dressed to remove any thin or weak portions.

    Face stones shall be dressed to provide bed and joint lines that do not vary

    more than twenty (20) millimeters from corners of the stones in excess

    thirty (30) millimeters in radius. Bed surfaces of the face stones shall be

    approximately normal to the face of the stones for about eighty (80)

    millimeters and from this point may depart from a normal plane not to

    exceed fifty (50) millimeters in three hundred (300) millimeters.

    Finish for exposed Faces – Face stones shall be pitched to line along the

     beds and joints. The maximum projection of rock faces beyond the pitch

    lines shall not be more than fifty (50) meters.

    2.7.2.2 MORTAR

    Cement, fine aggregate, and water shall conform to the respective

    requirements for those materials as specified under structural concrete,

    except to the grading of the aggregate which shall all pass the two and

    thirty six hundredths (2.36) millimeters (No. 8) sieve, not less than fifteen

    (15) percent nor more than forty (40) percent shall pass the three tenths

    (0.3) millimeters (No. 50) sieve, and not more than ten (10) percent shall

    pass the fifteen hundredths (0.15) millimeters (No. 100) sieve.

    2.7.3 EXECUTION

    2.7.3.1 SELECTION AND PLACING

     When the masonry is to be placed on a prepared foundation bed, the bed

    shall be firm and normal to, the face of the wall, and shall have been

    approved by the Engineer before any stone is placed.

     All stones shall be cleaned thoroughly and wetted immediately before being

    set and the bed which is to receive them shall be cleaned and moistened

     before the mortar spread. They shall be laid with their longest faces

    horizontal in full beds of mortar. The stones shall be handled as not jar or

    displace the stones already settled.

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    13/40

    Suitable equipment shall be provided for setting stones larger than those

    that can be handled by two men. The rolling or turning of stones on the

     walls will not be permitted. If a stone is loosened after the mortar has

    taken initial set, it shall be removed, the mortar cleaned off, and the stone

    is loosened after the mortar has taken initial set, it shall be removed, the

    mortar cleaned off, and the stone re – laid with fresh mortar.

    2.7.3.2 CURING

    If hot or dry weather, the masonry shall be satisfactory protected from the

    sun and shall be kept wet for a period of at least three days after

    completion.

    2.7.4 MEASUREMENT/BASIS OF PAYMENT

     The quantity to be paid for shall be the number of cubic meters of stone

    masonry complete in place and accepted. Projections extending beyond thefaces of the walls shall not be included. In computing the quantity for payment,

    the dimension used shall be those shown on the plans or ordered in writing by

    the Engineer. No deductions shall be made for weep holes drain pipes or other

    openings of less than one square meter in area.

     The quantity of masonry, determined as provided, shall be paid for at the

    contract unit price per cubic meter for stone masonry, which price and

    payment shall be full compensation for furnishing and placing all materials,

    including mortar for masonry, for all necessary excavation, and for all labor,

    equipment, tools and incidentals necessary to complete the item.

    ITEM 2.8 REINFORCING BARS GRADE 40

    2.8.1 GENERAL

    2.8.1.1 DESCRIPTION

     This item shall consist of furnishing, bending, fabricating and placing of

    steel reinforcement of the type, size, shape, and grade required in

    accordance with this specification and in conformity with the requirementsshown on the plans or as directed by the Engineer.

    2.8.2 SUBMITTALS

     A copy of list of all reinforcing steel and bending diagrams shall be furnished to

    the Engineer at the site of the work at least one week before the placing of

    reinforcing steel is begun.

     The Contractor shall be responsible for the accuracy of the lists and for

    furnishing and placing all reinforcing steel in accordance with the details

    shown on the plans.

    2.8.3 MATERIAL REQUIREMENTS

    Unless otherwise designated on the plans, or herein, all reinforcing steel shall

    conform to the requirements of the following specifications:

     Table 2.8.3: STEEL SPECIFICATION

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    14/40

    Deformed Billet - Steel Bars for Concrete

    Reinforcement

     ASTM A 615

     AASHTO M 31

    Deformed Steel Wire for Concrete Reinforcement ASTM A 496

     AASHTO M 225

     Welded Steel Wire Fabric for Concrete

    Reinforcement

     ASTM A 185

     AASHTO M 55

    Cold - Drawn Steel Wire for Concrete

    Reinforcement

     ASTM A 82

     AASHTO M 32

    Fabricated Steel Bar of Rod Mats for Concrete

    Reinforcement

     ASTM A 184

     AASHTO M 54

     Welded Deformed Steel Wire Fabric of Concrete

    Reinforcement

     ASTM A 497

     AASHTO M 221

    Plastic Coated Dowel Bars Type A

     AASHTO M 254

    Loy Alloy Steel Deformed Bars for Concrete

    Reinforcement  ASTM A 206

    Bar reinforcement for concrete structures, except No. 2 bars shall be deformed

    in accordance with AASHTO M 42, M31 and M53.

    Dowel and tie bars shall conform to the requirements of AASHTO M31 or

     AASHTO M42 except that rail steel should not be used for tie bars that are to

     be bent and re-straightened during construction. Tie bars shall be free from

     burring of other deformation restricting slippage in the concrete. A minimum of

    one half (

    1

    2 ¿  the length of each dowel bar shall be painted with one coat of

    approved lead of tar paint before delivery to the site of the work.

     The sleeves for dowel bars shall be metal of an approved design to cover fifty

    (50) millimeters (2 inches), plus or minus six and three tenths (6.3) millimeters

    of the dowel, with a closed end, and with suitable stop to hold the end of the

    sleeve at least twenty five (25) millimeters (1 inch) from the end of the dowel

     bar. Sleeves shall be of such design that they do not collapse during

    construction.

    Plastic coated dowel bar conforming to AASHTO M 254 may be used.

    2.8.4 EXECUTION

    2.8.4.1 ORDER LIST

    Before materials are ordered, all order lists and bending diagrams shall be

    furnished by the Contractor, for approval of the Engineer. The approval or

    order lists and bending diagrams by the Engineer shall in no way relieve

    the Contractor of responsibility for the correctness of such lists and

    diagrams. Any expenses incident to the revisions of materials furnished

     with the plans shall be borne by the Contractor.

    Bar lists and bending diagrams for structures, which are included on the

    Plans, do not have to be furnished by Contractor. When bar lists and

     bending diagrams are included on the Plans, they are intended for

    estimating approximate quantities. Contractor shall verify the quantity,

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    15/40

    size, and shape of the bar reinforcement against those shown on the Plans

    and make any necessary corrections before ordering.

    2.8.4.2 PROTECTION OF MATERIALS

    Steel reinforcement shall be stored above the surface of the ground upon

    platforms, skids, or other supports and shall be protected as far as

    practicable from mechanical injury and surface deterioration caused by

    exposure to conditions producing rust. When placed in the work

    reinforcement shall be free from dirt, detrimental rust, loose scale, paint,

    grease, oil or other foreign materials. Reinforcement shall be free from

    injuries effects such as cracks and laminations. Rust, surface scars,

    surface irregularities of mill scale will not be caused for rejection, provided

    the minimum dimensions are demonstrated.

    2.8.4.3 BENDING

     All reinforcing bars shall be bent cold except as shown on the Plans or as

    permitted by the Engineer. Bars shall not be bent or straightened in a

    manner that will cause damage to the bars. Irregularities in the bars shall

     be caused for the rejection. Bars shall be bent around a circular pin having

    the following diameter (d b) in relation to the diameter of the bar (d):

    Nominal Diameter (d), mm Pin Diameter (d b)

    10 to 20 6d

    25 - 28 8d

    32 and greater 10d

     

    Bends and hooks in stirrups or ties may be bent to the diameter of the

    principal bar enclosed therein.

    2.8.4.4 PLACING AND FASTENING

     The reinforcing bars shall be free from dirt, loose mill scale, paint, oil,

    loose rust, or other foreign substance.

    Steel reinforcement shall be accurately placed in the positions shown on

    the plans or as required by the Engineer and firmly held at all intersectionduring the placing and setting of concrete except where spacing is less

    than three hundred (300) millimeters in each direction, in which case,

    alternate intersections shall be tied. Ties shall be fastened on the inside.

    Distance from the forms shall be maintained by means of stays, blocks,

    ties, hangers, or other approved supports, so that it does not vary from the

    position indicated on the plans by more than six (6) millimeters. Blocks for

    holding reinforcement from contact with the forms shall be precast mortar

     blocks of approved shapes and dimensions. Layers of bars shall be

    separated by precast mortar blocks or by other equally suitable devices.

     The use of pebbles, pieces of broken stone or brick, metal pipe and wooden

     blocks shall not be permitted. Unless otherwise shown in the plans or

    required by the Engineer, the minimum distance between bars shall be

    forty (40) millimeters. Reinforcement in any member shall be placed and

    concrete begins. Concrete placed in violation of this provision may be

    rejected and removal may be required. If fabric reinforcement is shipped in

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    16/40

    rolls, it shall be straightened before being placed. Bundled bars shall be

    tied together at not more than one and eight tenths (1.8) meters interval.

    2.8.4.5 SPLICING

     All reinforcement shall be furnished in the full lengths indicated on the

    plans. Splices of reinforcement shall be made only at locations shown on

    the Plans and provided by the steel schedule unless accepted by the

    Engineer. Splices shall be staggered as far as possible. Except otherwise

    indicated, splicing of reinforcement shall be in accordance with American

    Concrete Institute (ACI) – 318M, except that the minimum separation shall

    not be less than forty (40) bar diameter.In cases where permission is

    granted to splice bars, other than those shown on the plans, the additional

    material required for the lap shall be furnished by Contractor at his’ own

    expense. All splices shall be full contact splices.

    Unless otherwise shown on the plans, bars shall be lapped a minimum

    distance of:

    Splice TypeGrade 40 Min.

    Lap

    Grade 60 Min.

    Lap

    But not less

    than

     Tension 24 bar diam. 36 bar diam. 300 mm

    Compression 20 bar diam. 24 bar diam. 300 mm

    In lapped splices, the bars shall be placed in contact and wired together.

    Lapped splices will not be permitted at locations where the concrete

    sections is sufficient to provide minimum clear distance of one and one –

    third the maximum size of coarse aggregate between the splice and the

    nearest adjacent bar. Welding of reinforcing steel shall be done only if

    detailed on the plans or if authorized by the Engineer in writing. Spiral

    reinforcement shall be spliced by lapping at least one and a half turns or

     by butt welding unless otherwise shown on the plans.

    2.8.4.6 WELDING OF SPLICES

     Where shown on the plans or required by the provisions of this item,

     welded bar splices shall be used. All splices whether lap, weld, mechanicalor coupler, shall develop the full strength of the bar. Information on

    mechanical splicing devices and couplers shall be submitted for approval

    prior to use.

    2.8.4.7 LAPPING OF BAR MAT

    Sheets of mesh or bar mat reinforcement shall overlap each other

    sufficiently to maintain a uniform strength and shall be security fastened

    at the ends and edges. The overlap shall not be less than one mesh in

     width.

    2.8.5 MEASUREMENT/BASIS OF PAYMENT

     The quantity of reinforcing steel to be paid for will be the final quantity placed

    and accepted in the completed structure.

    No allowance will be made for tie-wires, separators, wire and other materials

    used in fastening the reinforcing steel in place. If bars are substituted upon the

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    17/40

    Contractor’s request and approved by the Engineer and as a result thereof

    more steel is used than specified shall be measured for payment.

    No measurement or payment will be made of splices added by the Contractor

    for his convenience. When there is no item for reinforcing steel in the Bill of

    Quantities, costs will be considered as incidental to the other item in the Bill ofQuantities.

     The accepted quantity, measured as Bill of Quantities shall be paid for at the

    contract unit price for reinforcing steel which price and payment shall be full

    compensation for furnishing and placing all materials, including all labor,

    equipment, tools and incidentals necessary to complete the work prescribed in

    this item.

    ITEM 2.9 FORMS/ DEFORM WORKS

    2.9.1 GENERAL

     This item specifies the requirements for the design, construction and removal

    of formwork required to produce the finished concrete to the shape, lines and

    dimensions shown on the Plans.

    2.9.1.1 DESCRIPTION

    Formwork shall be meticulously checked of all recognized line and grade

    references so that the final structure is within the limits of the specified

    dimensional tolerances. They shall be designed to withstand the worst

    combination of self-weight, live load, rate of placement, height of drop,

     weight of moving equipment, together with all incidental dynamic effects

    caused by placing, vibrating and compacting the concrete. The Contractor

    shall verify that reinforcement is free of loose scale or rust and

    contaminants and shall be fabricated in accordance with fabrication

    herein specified and/or in the Plans. Reinforcement shall be checked of its

    allowable tolerances and splicing requirements, and shall be kept in its

    proper position during placement of concrete. The Contractor shall also

    check that all samples and certificates are submitted and approved. Allitems to be embedded in concrete shall be complete and in their proper

    position. Partially set concrete shall not be reworked and used. Vibrators

    shall not be used excessively and to transport concrete. Concrete flatwork

    shall be struck level and floated to disappearance of water sheen and shall

     be finished as specified. Concrete shall be cured as indicated and shall be

    protected from flowing water shock or excessive vibration during curing.

    2.9.2 MATERIAL REQUIREMENTS

     The type and condition of formwork sheeting and lining, and the ability of the

    formwork and its supports to withstand distortion caused by the placementand compaction of the concrete, and the standard of workmanship used in the

    formwork construction shall be such that the finished surfaces of the concrete

     will conform to the requirements of the specifications and Plans.

    Form lumber shall be stress graded or merchantable and shall be of non –

    staining species and dressed on concrete forming side if to be used for exposed

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    18/40

    Formwork panels shall be supplied in the maximum practicable width and

    length to minimize the number of joints.

    Plywood panels shall be placed with the grain of the outer plies in the direction

    of the span.

    Form oil, or coating shall be non – staining, compatible with subsequent

    finishing and bonding, and shall be effective in sealing wood from moisture.

    2.9.3 EXECUTION

    2.9.3.1 FORMWORK DESIGN

    Formwork shall be rigid, watertight, braced and tied together so as to

    maintain position and shape during all construction activities, and shall

     be constructed in such a way that it can be removed without damage to

    the concrete. Where formwork is to be re-used, the formwork design shall

    allow for the deterioration of materials through use and handling. Where

    formwork requires design, the Contractor shall submit to the Engineer for

    review of its detailed Plans and specifications of the proposed formwork not

    less than two weeks prior to the commencement of formwork construction.

     The formwork design shall be verified in accordance with the Contract to

    confirm that design satisfies the performance requirements of the

    formwork. Any amendment to the design shall be referred to the Engineer

    for review and final decision. The formwork Plans shall include all details

    of formwork, formwork joints, sealing procedures, ties, size and spacing of

    framing and details of any proprietary fittings or systems proposed to be

    used. Where vibration is to be applied externally, the design of formwork

    shall include details of external vibrators to ensure efficient compaction

    and to avoid surface blemishes.

    2.9.3.2 FORM CONSTRUCTION

    Formwork shall be constructed and shall be of sufficient stiffness to

    tolerate high frequency vibration and shall be of uniform stiffness to avoid

    causing varying vibration amplitudes over the formwork surfaces during

    compaction of the concrete. The constructed formwork shall maintain

    correct position and shape and achieve the specified dimensions, levels

    and geometry of the finished structural component. The use of wires or

     bolts extended to the surface of the concrete will not be permitted except

     where shown on the Plans. Any embedded ties shall remain embedded and

    shall terminate not less than the minimum clear cover specified on the

    Plans. All recesses shall be filled with a shrinkage compensating

    cementitious mortar.

    Errors in line or level of the formwork, or positioning and/or quantity of

    steel reinforcement shall be corrected prior to placing concrete. The

    Contractor will be responsible for any defects to the formwork,

    reinforcement, embedded components, or the formed concrete surface,

     which may become apparent during or after casting the concrete.

    Formwork shall not be placed in locations where steel reinforcement and

    other fixtures cannot be inspected, until such time that the evidence that

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    19/40

    the reinforcement and other fixtures conform to the requirements of the

    specifications and the Plans has been obtained and recorded by the

    Contractor.

    Fillets and chamfers shall be provided at re-entrant angles and corners.

     The interior surface of formwork shall be thoroughly cleaned out andtreated with form oil or lubricant to prevent adhesion of the exposed

    concrete surface. The form oil or lubricant shall be of the non-staining type

    and shall not discolor the surface of the concrete. The oil or lubricant shall

     be applied uniformly in a thin film and any surplus removed prior the

    concrete placement. Reinforcement and other embedment shall not be

    soiled by the form oil or lubricant.

    Prior to commencement of the concreting operations all tie wire ends, wood

    chips and other debris shall be removed from the forms. Formwork shall

     be sufficiently tight at joints to prevent loss of slurry or mortar while theconcrete is in its freshly placed state, consistent with the method of

    placement and compaction. Formwork shall also be mortar tight where

    holes are needed to facilitate projecting reinforcement or fixing devices.

    2.9.3.3 REMOVAL OF FORMS

    Formwork shall be so constructed as to allow for its undisturbed

    dismantling and removal from the cast concrete without shock or damage.

    Shock or damage to the cast concrete shall also be prevented when

    removing formwork in the vicinity of projecting reinforcement or fixing

    devices. Side forms for beams, girders and walls three feet or less may be

    removed as directed by the Engineer earlier than otherwise specified.

     Time of removal of forms shall be as follows:

    a. Joints, beams and girder soffits.

    - Clear span less than three (3) meters – seven (7) days

    - Clear span three (3) meters to six (6) meters – fourteen (14)

    days

    - Clear span over six (6) meters – twenty one (21) days.

     b. Slabs

    - Clear span six (6) meters – seven (7) days

    - Clear span over six (6) meters – fourteen (14) days

    Formwork tolerance for cast – in – place concrete form plumb shall be as

    follows:

    a. Lines and surfaces of columns, piers, walls and arises one (1)

    centimeter per three and five hundredths (3.05) meters but not morethan three (3) centimeters.

     b. Exposed corner columns, control joints, grooves and all

    conspicuous lines:

    - In any bay – one half (½) centimeters

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    20/40

    - Distances up to six (6) meters – one half (½) centimeters

    - Distances up to twelve (12) meters – one (1) centimeters

    Shoring

     All trenches and other excavations shall be properly sheeted and braced, to furnish working conditions acceptable to the Engineer.

    Bracing shall be so arranged as not to place any strains on portions of

    completed work until the general construction has proceeded far

    enough to provide ample strength in the opinion of the Engineer.

    2.9.4 MEASUREMENT/BASIS OF PAYMENT

     The quantities measured as arranged above shall be paid for at the contract

    unit price of the pay item that is contained within the Bill of Quantities.

    Payment shall be the reimbursement for all materials, labor, equipment, tools,

    and incidentals necessary to complete the work prescribed in this item.

    ITEM 2.10 CONCRETING WORKS (3500 PSI)

    2.10.1 GENERAL

    Concrete shall be composed of Portland cement, fine aggregate, coarse

    aggregate, water and admixtures as specified for the work except as otherwise

    authorized in writing by the Engineer. Ready mix concrete shall be permitted,

    provided it can be placed within the time requirements specified and complies with all of the provisions hereinafter specified.

    2.10.1.1 DESCRIPTION

     This item shall consist of furnishing, placing, and finishing concrete in

    concrete/ reinforced concrete structures in accordance with this

    specification and conforming to the lines, grades, and dimension shown on

    the plans.

    a. All reinforced concrete horizontal, vertical construction and expansion

     joints shall be provided with rubber water stop dumbbell type.

     b. Concrete for foundation, beams, columns, weir and desander shall

    have the strength of at least 3500 psi.

    c. Unless indicated all structures not exposed to water shall have a

    comprehensive strength of at least 3000 psi.

    2.10.2 SUBMITTALS

    Samples of constituent materials and of concrete as placed shall be subjected

    to laboratory tests. The Contractor shall submit samples of materials as

    directed by the Engineer for his approval and all materials incorporated shallconform to the approved samples. The Contractor shall design the concrete

    mixes for all classes of concrete as will be define in this specification and

    submit his proposal together with the test results of the strength of all classes

    of the concrete mix design for the approval of the Engineer. The design of the

    concrete mixes and the concrete strength test shall be made in the field

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    21/40

    laboratory in the presence of the Engineer or his representative. The

    Contractor is responsible for all expenses incurred in this process.

     The use of ready-mixed concrete in any part of the work shall require the

    Engineer’s written approval. The Contractor shall satisfy the Engineer’s plan as

    to the sampling, trial mixing, testing and quality of concrete of various gradesshall equally applied to ready-mixed concrete, which shall be made and

    delivered. Every additional facility including transport, which the Engineer or

    persons authorized by him may require for the supervision and inspection of

     batching, mixing and transporting to site of ready-mixed concrete shall be

    provided by the Contractor at no extra cost to the client. Prior to any major

    concreting as instructed by the Engineer, the Contractor shall submit a

    method statement furnishing all the relevant details including the plants he

    intends to use for the approval of the Engineer.

    2.10.3 MATERIAL REQUIREMENTS

    2.10.3.1 PORTLAND CEMENT

     The cement used for any particular mixed shall comply with the following

    cited specification for the type specified or permitted.

     TYPE SPECIFICATION

    Portland Cement AASHTO M 85 (ASTM C 150)

    Blended Hydraulic Cements AASHTO M 240 (ASTM 595)

    Masonry Cement AASHTO M 150 (ASTM C91)

     When types IV and V (AASHTO M 85), P and PA (AASHTO M 150) cements

    are used, proper recognition shall be given to the effects of slower strength

    gain on concrete proportioning and construction practices. Types S and

    SA cements will be permitted only when blended with Portland cement in

    proportions approved only by the Engineer.

    Unless otherwise permitted by the Engineer, the product of only one mill

    of any brand and type of Portland cement shall be used on the project.

     The cement shall be in bags sealed with the manufacturer’s seal. The

    storage shall be maintain in a perfectly dry and well ventilated condition

    above ground level or as per instructions issued by the Engineer. Any

    cement which has been deteriorated or caked or which has been damageddue to any reason whatsoever shall not be used. Should the results of any

    laboratory tests show that any samples does not comply with the specified

    requirement, the whole consignment from which the sample was taken,

    shall be rejected and replaced with cement of satisfactory quality all

    shouldered by the Contractor. Any work carried out with the failed cement

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    22/40

    shall also be dismantled or corrective action taken by the Contractor as

    per instructions of the Engineer.

    2.10.3.2 CONCRETE AGGREGATE

    2.10.3.2.1 FINE AGGREGATES

    Sand or fine aggregate shall be comprise of natural sand, washed

    and sieved to remove particles larger than five (5) millimeters. It can

     be stone screenings or other inert materials with similar

    characteristics, or combination thereof, having hard, strong and

    durable particles approved by the Engineer. Fine aggregate from

    different sources of supply shall not be mixed or stored in the same

    pile nor used alternately in the same class of concrete without the

    approval of the Engineer.

    Fine aggregate shall not contain more than three (3) mass percent ofmaterial passing the seventy five hundredths (0.75) millimeters (No.

    200) sieve by washing nor more than one (1) mass percent each of

    clay lumps or shale. The use of beach sand will not be allowed

     without the approval of the Engineer.

    If the fine aggregate is subjected to five (5) cycles of the sodium

    sulfate soundness test, the weighted loss shall not exceed ten (10)

    mass percent.

     The fine aggregate shall be free from damaging amounts of organic

    impurities. If subjected to colorimetric test for organic impurities

    and a color darker than the standard is produced, it shall be

    rejected. However, when tested for the effect of organic impurities of

    strength of mortar by AASHTO T71, the fine aggregate may be used

    if the relative strength at seven (7) and twenty eight (28) days is not

    less than ninety five (95) mass percent.

    Fine aggregate shall be capable of developing eighty (80) percent of

    the tensile strength of Ottawa sand. It shall be well graded from

    course to fine and not contain more than one (1) percent clay, coal,

    lignite and other deleterious substances such as shale, alkali, mica,coated grains, soft and flaky particles when tested according ASTM

    methods. All fine aggregate shall conform to the following

    requirements:

     TABLE 2.10.3.2.1: PERCENT PASSING OF DIFFERENT

    SIEVE SIZE

    Sieve Size Percent Passing

    9.5 mm (3

    8  in ) 100

    4.75 mm ( No. 4 ) 95 – 100

    1.18 mm ( No. 16 ) 45 – 80

    0.30 mm ( No. 50 ) 5 – 30

    0.15 mm ( No. 100 ) 0 – 10

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    23/40

    2.10.3.2.2 COURSE AGGREGATES

    Coarse Aggregate shall be composed of hard, strong crystalline rock

    free form shale or other soft materials and free from any adherent

    coating or vegetable matter. It can be crushed stones, gravel, blast

    furnace slag, or other approved inert materials of similarcharacteristics, or combination thereof, having hard, strong, durable

    pieces and free from any adherent coatings.

    Coarse aggregates shall not contain more than one (1) mass percent

    of material passing the 0.075 mm (No. 200) sieve, not more than

    0.25 mass percent of clay lumps, nor more than 3.5 mass percent of

    soft fragments.

    If the course aggregate is subjected to five (5) cycles of the sodium

    sulfate soundness test, the weighted loss shall not exceed 12 mass

    percent.

    It shall have a maximum mass percent of forty (40) when tested by

     AASHTO T 96. If slag is used, its density shall not be less than one

    thousand one hundred twenty (1120) kilograms per cubic meter or

    seventy (70) pounds per cubic foot. Only one grading specification

    shall be used and it shall conform to the following required grading

    for coarse aggregate.

     TABLE 2.10.3.2.2: GRADING FOR COARSE AGGREGATE

    SIEVE DESIGNATION MASS PERCENT PASSING

    STANDARD

    mm

     ALTERNATE

    U.S. Standard

    GRADING

     A

    GRADING

    B

    GRADING

    C

    75.0 3 in 100 - -

    63.0 2 ½ in 90 – 100 100 100

    50.0 2 in - 90 – 100 95 – 100

    37.5 1 ½ in 25 – 60 35 – 75 -

    25.0 1 in - 0 – 15 35 – 70

    19.0 ¾ in 0 – 10 - -

    12.5 ½ in 0 – 5 0 – 5 10 – 30

    4.75 No. 4 - - 0 – 5

    2.10.3.2.3 AGGREGATE TESTS

     Testing of aggregates is a way by which the properties of a material

    are routinely evaluated and compared with the appropriate

    specification requirements. Samples of the aggregates to be usedshall be selected by the Engineer for tests at least thirty (30) days

     before the start of actual concreting operations. It shall be the

    responsibility of the Contractor to designate the sources of

    aggregates to give the Engineer ample time to obtain the necessary

    samples and submit them for testing.

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    24/40

    No aggregate shall be used until advice has been received that it has

    satisfactory passed all tests to the satisfaction of the Engineer, at

     which time written approval shall be given for its use.

    In stating requirements for most materials, reference has been made

    to AASHTO and ASTM Standard Specification for material. ThoseSpecifications, in turn, include reference to the respective AASHTO

    and ASTM methods of sampling and testing. In such instances the

    following methods of sampling and testing will govern:

     TEST METHOD SPECIFICATION

     Amount of Material Finer

    than 0.075 mm Sieve in

     Aggregate

     AASHTO T 11

    Unit Weight of Aggregate AASHTO T 19

    Sieve Analysis of Fine and

    Course Aggregates AASHTO T 27

    Resistance to Abrasion of

    Small Size Coarse

     Aggregate by Use of the Los

     Angeles Machine

     AASHTO T 96

    Soundness of Aggregate by

    Use of Sodium Sulfate of

    Magnesium Sulfate

     AASHTO T 104

    2.10.3.2.4 WATER

     Water to be used in concrete works such as mixing, curing, or other

    assigned application shall be sensibly clean and fresh. It shall be

    free from oil, acids, alkali, sewage, and organic or other deleterious

    matter. Water will be tested in accordance with and shall meet the

    requirements of water from DPWH Standard and Specification for

    Public Works and Highways. Drinking water may be used without

    test. Where the source of water is shallow, the intake shall be so

    enclosed as to exclude silt, mud, grass or other foreign materials.

    2.10.3.2.5 METAL REINFORCEMENT

    Reinforcement shall be detailed, fabricated, placed, and supported

    in place in accordance with the following specifications:

    Deformed and Plain Billet Steel (ASTM A 615)

    Bars for Concrete Reinforcement AASHTO M 31

    Deformed Bars – Steel and Plain ASTM A 616

     ASTM A 617

    For reinforcing bars to be welded, the following ASTM specifications

    shall be accompanied by the requirements assuring satisfactory

     weldability.

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    25/40

    Bar and Rod Mats for Concrete

    Reinforcement

     ASTM 187

    (ASTM A 82)

    Cold – Drawn Steel Wire for

    Concrete Reinforcement

     AASHTO M 32

    (ASTM A 185)

     Welded Steel Wire Fabric for

    Concrete Reinforcement

    (ASTM A 185)

     AASHTO M 55

    Except that the weld shear strength requirements of those

    specification shall be extended to include a wire differential up to

    and including six gauges.

    Reinforcement shall be secured in place with concrete or metal

    spacers. Metal spacers extending to the surface of the concrete or

     wooden supports shall not be used. Reinforcement shall be free

    from scale, rust, or coatings that will reduce the bond between

    reinforcement and concrete.

    2.10.3.2.6 RUBBER SEAL

     Water stop shall be used in all vertical, horizontal, construction and

    expansion joint as needed.

    2.10.3.2.7 ADMIXTURES

     When required by the engineer, admixtures shall be approved

    quality. The Contractor shall furnish full details of the admixtures

    prior to use in works. The employment of admixtures for concretemix shall be at the discretion of the Contractor and at no additional

    cost to the Employer. The amounts and types of additives used shall

     be as directed or approved by the Engineer and may be varied by

    him according to the location of the work or for other reasons.

    If air – entraining admixture is used, it shall conform to ASTM C

    260.

    If used, water – reducing, water proofing and water – reducing,

    retarding and accelerating admixtures shall conform to the

    requirements of ASTM C 494.

    2.10.3.3 STORAGE OF MATERIALS

    Immediately upon arrival at the site, cement and aggregates shall be

    stored in storage designed for the purpose or in dry weather-tight and

    properly ventilated structures with floors raised in a reasonable height

    above ground level with adequate provision to prevent absorption of

    moisture. Aggregates shall be stored on clean hard bases that permit free

    drainage. Care must be taken so as to prevent foreign objects from mixing

    and cross contamination between materials will be prevented. All storage

    facilities shall be subject to approval by the Engineer and shall be such as

    to permit each access for inspection and identification.

    2.10.4 EXECUTION

    2.10.4.1 CONCRETE QUALITY

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    26/40

     The quality and method and control of manufacture and transportation of

    all concrete work irrespective of mix, whether reinforced or otherwise,

    shall conform to the applicable portions of this specification. The

    Engineer shall have the right to inspect the source(s) of materials, the

    layout and operation of procurement and storage of materials, the

    concrete batching and mixing equipment, the quality control system. Such

    an inspection shall be arranged and Engineer’s approval obtained, prior to

    starting of concrete works.

     All plans submitted for approval of used for any structure in the project

    shall clearly show the specified strength of concrete, F’c, of the specified

    age for which it was designed.

    Concrete that will be exposed to sulfate containing of other chemically

    aggressive solutions shall be proportioned in accordance with

    “Recommended Practice for Selecting Proportions for Concrete (ACI 613)”and “Recommended Practice for Selecting Proportions for Structural

    Lightweight Concrete (ACI 613A)”.

    2.10.4.2 METHODS OF DETERMINING THE PROPORTIONS OF CONCRETE

     The determination of the proportions of cement, aggregates, and water to

    attain the required strengths shall be made by one of the following

    methods, but lower water – cement ratios may be required for

    conformance with the quality of concrete.

    a.Without Preliminary Test

     Where preliminary test date the materials to be used in the concrete

    have not been obtained the water to cement ratio for a given strength

    of concrete shall not exceed the values shown on the following table.

     When strengths in excess of two hundred eighty one (281) kilograms

    per square centimeter or four thousand (4000) pounds per square inch

    are required of when light weight aggregates of admixtures (other than

    those exclusively for the purpose of entraining air) are used, the

    required water to cement ratio shall be determined in accordance with

    the next method to be mention.

     TABLE 2.10.4.2:MAXIMUM PERMISSIBLE WATER TO CEMENT RATIO

    FOR DIFFERENT CONCRETE’S COMRESSIVE

    STRENGTH

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    27/40

    SPECIFIED

    COMPRESSIVE

    STRENGTH AT

    28 DAYS, F’c

    (PSI)

    MAXIMUM PERMISSIBLE WATER – CEMENT

    RATIO

    Non air – entrained

    concrete

     Air – entrained

    concrete

    U.S. gallon

    per 42.6

    kilograms

     bag of

    cement

     Absolute

    ratio by

     weight

    U.S. gallon

    per 42.6

    kilograms

     bag of

    cement

     Absolute

    ratio by

     weight

    2500 7 ¼ 0.642 6 ¼ 0.554

    3000 6 ½ 0.576 5 ¼ 0.465

    3500 5 ¾ 0.510 4 ½ 0.399

    4000 5 0.443 4 0.354

     b.For combination of materials previously evaluated to be established by

    trial mixtures.

     Water to cement ratios for strength greater than that shown in the

    above table maybe used provided that the relationship between

    strength and water to cement ratio for the materials to be used has

     been previously established by reliable test data and the resulting

    concrete satisfies the requirements of concrete quality.

     Where previous data are not available, concrete trial mixtures having

    proportions and consistency suitable for the work shall be made using

    at least three different water to cement ratios (or cement content in the

    case of lightweight aggregates) which will produce a range of strengths

    encompassing those required for the work. For each water to cement

    ratio (or cement content) at least three specimens for each age to be

    tested shall be made, cured and tested for strength in accordance with

     ASTM C 39 and ASTM C 192.

     The strength test shall be made at seventh(7th), fourteenth (14th) and

    twenty eighth (28th) days at which the concrete is to receive load, as

    indicated on the plans. A curve shall be established showing the

    relationship between water to cement ratio (or cement content) and

    compressive strength. The maximum permissible water to cement ratio

    for the concrete to be used in the structure shall be that shown by the

    curve to produce an average strength to satisfy the requirements of the

    strength test of concrete provided that the water to cement ratio shall

     be no greater than that required by concrete quality when concrete that

    is to be subjected to the freezing temperatures shall have a water –cement ratio not exceeding six (6) gallons per bag and it shall contain

    entrained air.

     Where different materials are to be used for different portions of the

     work, each combination shall be evaluated separately.

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    28/40

    2.10.4.3 CONCRETE PROPORTIONS AND CONSISTENCY

     The Contractor shall design concrete proportion to produce concrete

    required strength. Notwithstanding the acceptance by the Engineer of any

    mix design and series of trial mixes, variations may be made to the

    proportions when considered necessary by the Engineer.

     The proportion of aggregate to cement for any concrete shall be such as to

    produce a mixture which will work readily into the corners and angles of

    the form and around reinforcement with the method of placing employed

    on the work, but without permitting the materials to segregate or excess

    free water to collect on the surface. The methods of measuring concrete

    materials shall be such that the proportion can be accurately checked at

    any time during the work.

    2.10.4.4 SAMPLING AND TESTING OF STRUCTURAL CONCRETE

     The Contractor shall provide the equipment necessary to determine the

    compacting factor of freshly mixed concrete at each place where concrete

    is being made and shall determine the compacting factor of the freshly

    mixed concrete. At least one (1) set of sample consisting of three (3)

    concrete cylinder test specimens, one hundred fifty (150) by three

    hundred (300) millimeter shall be taken from each class of concrete placed

    each day, and each serves to represent not more than seventy five (75)

    cubic meter of concrete.

    2.10.4.5 CONSISTENCY

    Concrete shall have a consistency such that it will be workable in the

    required position. It shall be such that it will flow around reinforcing steel

     but individual particles of the coarse aggregate when isolated shall show a

    coating or mortar containing its proportionate amount of sand. The

    consistency of concrete shall be gauged by the ability of the equipment to

    properly place it and not by the difficulty of mixing water shall be

    determined by the Engineer and shall not be varied without his consent.

    Concrete as dry as it is practical to place with equipment specified shall

     be used.

    2.10.4.6 STRENGTH TEST OF CONCRETE

    Concrete shall be subjected to compressive and flexural strength test as

    specified in ASTM C 31, “Making and Curing Concrete Compressive and

    Flexural Strength Tests Specimens in the Field”. Each class of concrete

    shall be represented by at least five (5) tests having an accumulation of

    ten (10) specimens. Two (2) specimens shall be made for each test at a

    given age, and not less than one (1) test shall be made for each one

    hundred fifteen (115) cubic meter of structural concrete, but there shall

     be at least one (1) test for each day concreting. The Engineer may requirea reasonable number of additional tests during the progress of the work.

    Samples from which compression test specimens are molded shall be

    secured in accordance with ASTM C 172. Specimens made to check the

    adequacy of the proportions for strength of concrete or as a basis for

    acceptance of concrete shall be made and laboratory – cured in

    accordance with ASTM C 31. Additional test specimens cured entirely

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    29/40

    under field conditions may be required by the Engineer to check the

    adequacy of curing and protection of the concrete.

    If it appears that the laboratory cured specimen will fail to conform to the

    requirements for strength, the Engineer shall have the right to order

    changes in the concrete mix sufficient to increase the strength to meetthese requirements. The strengths of any specimen cured on the job are

    intended to indicate the adequacy of protection and curing of the concrete

    and may be used to determine as to when the forms may be stripped,

    shoring removed or the structure placed in service. In the opinion of the

    Engineer, the strength of the job cured specimen are excessively below

    those of the laboratory cured specimen, then the Contractor may be

    required to improve the procedures for protecting and curing concrete.

     The age for strength tests shall be twenty eight (28) days or, where

    specified, the earlier age at which the concrete is to receive its full load ofmaximum stress. Additional test may be made at earlier ages to obtain

    advance information on the adequacy of strength development where age

     – strength relationships have been established for the materials and

    proportions used.

     To conform to the requirements of this item:

    a.For structures designed in accordance with working stress design

    method of this chapter, the average of any five consecutive strength

    tests of the laboratory – cured specimens representing each class of

    concrete shall be equal to or greater than the specified strength, F’c and

    not more than twenty (20) percent of the strength test shall have values

    less than that specified.

     b.For structures designed in accordance with the ultimate strength

    design method of this chapter, and for pre – stressed structures the

    average of any three consecutive strength test of the laboratory cured

    specified representing each class of concrete shall be equal to or greater

    than the specified strength, F’c and not more than ten (10) percent of

    the strength tests shall have values less than the specified strength.

     The Contractor shall provide for all costs in the making of such tests

    including allowing free access to the work for the selection of samples,

    providing moist storage facilities for specimen, affording protection of the

    specimen against injury or loss through his operations, and furnishing

    material and labor required for the purpose of taking and testing of

    samples. The Contractor shall make slump tests in the field and when

    instructed by the Engineer in the presence of the Engineer's

    representatives.

     The Engineer may request that dynamic testing or loading test to be

    executed when the results of the laboratory test are not satisfactory for

    completed works. The Contractor at his own cost shall carry out testing

    and inspection work.

    2.10.4.7 BATCHING

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    30/40

     When batches are hauled to the mixer, bulk cement shall be transported

    either in waterproof compartments or between the fine and course

    aggregates. When cement is placed in contact with moist aggregates,

     batches will be rejected unless mixed within one half (½) hours of such

    contact. Sacked cement may be transported on top of the aggregates.

    Batches shall be delivered to the mixer separate and intact. Each batch

    shall be dumped cleanly into the mixer without loss, and, when more

    than one batch is carried on the truck, without spilling of material from

    one batch into another.

    2.10.4.8 MIXING AND DELIVERY

    Mixing of concrete shall continue until there is a uniform distribution of

    material and the concrete is uniform in color and consistency. Concrete

    may be mixed at the site of construction, at a central point and truck

    mixing or by a combination of central point mixing and truck agitating.

    Mixing the delivery of concrete shall be in accordance with the

    appropriate requirements of AASHTO M 157 except as modified in the

    following paragraphs of this section, for truck mixing or a combination of

    central point and truck mixing or truck agitating.

     The mixer shall be operated at the drum speed as shown on the

    manufacturer’s name plate on the mixer. Any concrete mixed less than

    the specified time shall be discarded and disposed of by the Contractor at

    his own expenses.

     The timing device on the stationary mixers shall be equipped with a bell

    or any suitable warning device adjusted to give a clearly audible signal

    each time the lock is released.

    Mixes and weighs batches shall be maintained in first class condition

    throughout the time period and any mixer or plant which is faulty shall

    not be used. A mixer of any type shall be maintained in a clean

    serviceable condition and their accuracy periodically checked.

    If volumetric measurement is allowed, the weight proportions shall be

    converted to equivalent volumetric proportions. In such cases, suitableallowance shall be made for variations in the moisture condition of the

    aggregate.

    2.10.4.9 CONCRETE SURFACE FINISHES

    2.10.4.9.1 CURING CONCRETE

     All freshly deposited concrete shall be protected from premature

    drying and excessively hot or cold temperatures, and mechanical

    injury and shall be maintained with minimal moisture loss at a

    relatively constant temperature for the period of time necessary forthe hydration of the cement and proper hardening of the concrete.

    Curing of concrete in the field shall conform to the required standard

    of ASTM C31/C31 M, “Standard Practice for Making and Curing

    Concrete Test Specimens in the Field”.

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    31/40

     The Contractor shall protect all concrete work against injury from

    outside elements and defacement of any nature during construction

    operations. All concrete, particularly exposed surfaces shall be treated

    immediately after concreting or cement finishing is completed, and

    shall be provided with continuous moist curing for at least seven (7)

    days regardless of the ambient air temperature. Walls and vertical

    surfaces may be covered with continuously saturated burlap or by

    other approved means. Horizontal surfaces, slabs, and other items

    shall be inundated with pool of water to a depth of one and 2 tenths

    (1.2) centimeter and kept continuously wet with the use of sprinklers.

    Finished surfaces and slabs shall be protected from the direct rays of

    the sunlight to prevent shrinking and cracking.

     The curing method shall be one or more of the following:

    a. Water Method – The concrete shall be kept continuously wet by theapplication of water for a minimum period of seven (7) days after

    the concrete has been placed.

     b.Curing Compound – Surfaces exposed to the air may be cured by

    the application of an impervious membrane approved by the

    Engineer.

    c.Waterproof Membrane Method – The exposed finished surfaces of

    concrete shall be sprayed with water, using a nozzle that so

    atomizes the flow that a mist and not a spray are formed until the

    concrete has set, after which a curing membrane of waterproof

    paper or plastic sheeting shall be placed.

    d.Forms-in-Place Method – Formed surfaces of concrete may be cured

     by retaining the form in place. The forms shall remain in place for a

    minimum period of seven (7) days after the concrete has been

    placed, except that for members over fifty (50) centimeters in least

    dimension, the forms shall remain in place for a minimum period

    of five (5) days.

    e.Curing Cast-in-Site Concrete – All newly placed concrete cast-in

    into the structures shall be cured by the water method, the forms-

    in-place method, or as permitted herein, by the curing compound

    method.

    f.Curing Pre-Cast Concrete Piles – All newly placed concrete for pre-

    cast concrete piles, conventionally reinforced or pre-stressed shall

     be cured by the “Water Method” as described in subsection “Curing

    Concrete”, except that the concrete shall be kept under moisture for

    at least fourteen (14) days. All the option of the Contractor, steam

    curing maybe used in which case the steam curing provisions of

    DPWH SS subsection 407.3.8 (6) curing pre-cast concrete shall

    apply except that the concrete shall be kept wet for at least seven

    (7) days including the holding and steaming period.

    2.10.4.9 ACCEPTANCE OF CONCRETE

    2.10.4.9.1 STRENGTH OF CONCRETE

  • 8/20/2019 Weir Specification (Especificaciones técnicas de construcción de vertedeteros)

    32/40

    Concrete not meeting the requirements of this specification shall be

    considered potentially deficient and may be rejected. The strength of

    concrete shall be deemed acceptable if the average of three (3)

    consecutive strength test results is equal to or exceeds the specified

    s