6/22/2020
1
1
We recommend you join today’s session using your computer audio.
While you wait for our session to begin, please run the Sound Check Feature in the AUDIO section of your GoToWebinar control panel (see the red arrow).
Alternatively, you may join by telephone:
+1 (631) 992-3221
Access Code: 118-593-468, Webinar ID: 847-455-611
Technical problems? Prior to the session, you can call Tracy Arner at (706) 202-8169
Welcome to “Fundamentals of Purchasing”
2
To Submit a written question, find the Question Pane on the control panel (see the red box). Simply type in the lower portion of the pane and click send.
Want to ask a question?
6/22/2020
2
3
Use the “Raise Hand” button (see the green arrow) to give us a wave!
Ready to be recognized?
4
In order to earn CPE credit for this course, you must:• Answer all polling questions,• Be registered with the Georgia Center for Continuing
Education,• Be logged in to the session individually, and • Remain present until the full hour of the webinar.Certificates will be available within 30 days.
Earning CPE
6/22/2020
3
5
Today’s Presenter
Dave LaklyPublic Service Associate
Fundamentals of PurchasingPresented by: Dave Lakly
6/22/2020
4
7
Learning Objectives Recall the functions and goals of purchasing
Recall the steps of the purchasing cycle
Identify the importance of writing solicitations
Define the process of issuing the requisition and purchase order
8
Public Sector Purchasing
6/22/2020
5
9
What makes public sector purchasing different?• Protection of public funds• Competition• Open/transparent• Value• Legality
Public Sector Purchasing
10
Materials Management
Supply Chain Management
Commodity Management
Supplier Management
Contract Administration
Functions
6/22/2020
6
11
Maximize savings by obtaining the best value for each tax dollar spent
Goals
Efficiency
EconomyEffectiveness
12
• Honesty• Integrity• Ability to Multi-Task• Attention to Detail• Assertiveness• Sense of Responsibility
Quality Purchasing Staff
6/22/2020
7
13
Independent entity formed to govern and administer the Certified Public Procurement Officer (CPPO) and Certified Professional Public Buyer (CPPB) certification programs
https://www.uppcc.org/Certification
Universal Public Procurement Certification Council
14
6/22/2020
8
15
To be effective, purchasing must have
Responsibility
Authority
16
• Exemptions• Ethics• Other policies• Authority• Procedures• Purchasing thresholds• Process• Sole purchase• Emergency purchase
Writing a Policy
6/22/2020
9
17
Sample Thresholds:
• Purchases between $0 and $5,000 – authorized staff members will obtain at least two verbal quotes.
• Purchases greater than $5,000 but not greater than $20,000 –authorized staff members will obtain at least three written quotes.
• Purchases greater than $20,000 use sealed, written bids or proposals.
(Additional examples, Cities of Callaway, Edgewater)
Policy Examples
18
Purchasing’s goal to maximize savings by obtaining the best value for each tax dollar spent is accomplished by…A. Ethics, economy and expediting.B. Honesty, integrity, and sense of responsibility.C. Efficiency, effectiveness, economy. D. Responsive bids and responsible bidders.
Knowledge Check
6/22/2020
10
19
Steps in the Purchasing Process
20
Steps in the Purchasing Process
1 • Determining Need
2 • Verifying Availability of Funds
3 • Writing Specifications
4 • The Requisition
5 • Method of Purchase and Solicitations
6/22/2020
11
21
Steps in the Purchasing Process (cont’d)
6 • Evaluation and Award
7 • Preparation of PO or Contract
8 • Monitoring of Delivery
9 • Receipt of Goods or Services
10 • Capital Assets
22
1. Determining need: the user department determines a need and requisition is submitted to purchasing
2. Verifying availability of funds: fund availability is determined according to your:• Operating Budget• Capital Projects Budget
Purchasing Process
6/22/2020
12
23
3. Writing Specifications• Written by the user department• Describe requirements of products or services• Written at the correct quality level
Purchasing Process
24
3. Writing Specifications(cont’d)
Purchasing Process
Before writing them, research
similar solicitations, review the web,
brochures, catalogs, and other materials
Include performance expectations (usually for
RFPs)
Include physical characteristics
Write them clearly and
accurately to describe minimum
requirements
Write them in a way that they do not
restrict competition
6/22/2020
13
25
“It’s unwise to pay too much, but it’s also unwise to pay too little. When you pay too much, you lose a little money, that is all. When you pay too little, you sometimes lose everything because the thing you bought was incapable of doing the thing it was thought to do.”
- John Ruskin Art Critic & Social Commentator
26
4. The requisition should contain• Date the item is needed• Budget coding information and approval• Description of the item• Suggested vendors• Quantity, estimated costs & delivery location
Purchasing Process
6/22/2020
14
27
5. Method of Purchase and Solicitations will depend on• Dollar amount – formal or informal• Is the request for a product, equipment, or service• Requirements of the user department
Purchasing Process
28
After the need for a purchase is determined by a user department which of the following should be confirmed first?A. Requirements of the products or servicesB. Availability of fundsC. The preferred vendorD. Method of purchase
Knowledge Check
6/22/2020
15
29
6. Evaluation and Award• The department usually evaluates the bids and
makes a recommendation• Bids are evaluated for technical compliance and to
ensure that they are recommended for award to a responsive and responsible vendor
• Final approval of award is based on the dollar amount
Purchasing Process
30
"Responsive" simply speaks to a bidder doing as has been requested. If a bidder has to provide three references, did the bidder do so? If the bidder has to submit a notarized affidavit of some sort, did the bidder do so?
"Responsible" means that the bidder is able to accomplish the task(s) being requested. If a bidder says that they can provide green widgets, can they? If the request is to build a bridge, has the bidder adequately done so before? After all, citizens wouldn't want to use that bridge if it weren't constructed by a competent, experienced, and "responsible" builder.
Closer Look
6/22/2020
16
31
7. Preparation of Purchase Order or Contract• Name and address of vendor• Shipping address• Expected delivery date• Quantity and measure of unit• Description of what is to be purchased
Purchasing Process
32
7. Preparation of Purchase Order or Contract (cont’d)
• Unit cost, extended cost and total cost• Transportation and FOB Point• FOB Source – ownership takes place on the
vendor’s dock• FOB Delivery – ownership takes place on the
buyer’s dock
Purchasing Process
6/22/2020
17
33
7. Preparation of Purchase Order or Contract (cont’d)
• Name of person to contact for questions• Accounting information• Authorized signature of issuer• Date purchase order issued
Purchasing Process
34
Purchase Order Example
6/22/2020
18
35
8. Monitoring Delivery• Who receives actual delivery is dependent on
the size of the organization • Ensure items are shipped to correct address• Copy of purchase order forwarded to user
department
Purchasing Process
36
9. Receipt of goods or services• Upon receipt, someone should verify:• Quality• Quantity• Documentation• Verify items are “per specification”• Testing & storage
Purchasing Process
6/22/2020
19
37
10. Capital Assets• Purchases that qualify for capitalization should
be identified during the purchasing process• Must be tracked in the capital asset
management system
Purchasing Process
38
10. Capital Assets (cont’d)
• Disposal:• Declare unusable items as surplus and sell,
donate or destroy• Methods of disposition
• Sale or donations• Public auction• Sealed/spot bids• Trade-ins
Purchasing Process
6/22/2020
20
39
“FOB Delivery” ownership takes place at…A. The buyer’s dock.B. The vendor’s dock.C. The shipping point.D. Time of payment.
Knowledge Check
4040
6/22/2020
21