© 2013 ARCADIS 22 March 2015 1 Welcome to the 2013 EJCDC Construction Documents Welcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie, The Water Division of ARCADIS-US

Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

Embed Size (px)

Citation preview

Page 1: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20151

Welcome to the 2013 EJCDC Construction Documents

Welcome to the 2013 EJCDC Construction Documents

February 27, 2013

James C. Brown II, PE Vice PresidentMalcolm Pirnie, The Water Division of ARCADIS-US

Page 2: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20152

Today’s Agenda

• EJCDC Overview

• EJCDC Construction Series

• 2013 Changes

Page 3: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20153

EJCDC Overview• Three Sponsoring Organizations

• ACEC• ASCE• NSPE

• Numerous Participating Organizations• APWA• USDA/RUS• AGC• NUCA• CSI and others

Page 4: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20154

EJCDC Overview

• Primary Purpose – Publish standard contract documents for engineer-designed construction

• Content Objectives• Logical risk allocation• Clear and thorough• Consistent with current practice and laws• Responsive to user needs

Page 5: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20155

EJCDC Document Families• Engineering (Owner-Engineer, Master

Agreement, Short Form, Engineer-Subconsultant, Teaming Agreement/Joint Venture, others)

• Construction (Owner-Contractor)• Design/Build• Environmental Remediation• Procurement (Buyer-Seller; for major equipment

purchases, etc.)

Page 6: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20156

2013 C-Series Highlights• Revisions, enhancements, and coordination of all 24

C-series documents• Added three new documents:

• C-111, Advertisement for Bids• C-451, Qualifications Statement• C-521, Subcontract

• Focus and substantive changes to:• C-200, Instructions to Bidders• C-410, Bid Form• C-700, General Conditions• C-800, Supplementary Conditions

• More robust Commentary, C-001

Page 7: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20157

EJCDC Construction Series• C-050 Bidding Procedures and Construction Contract

Documents• C-051 Engineer’s Letter re Bonds and Insurance• C-052 Owner’s Instruction re Bonds and Insurance• NEW C-111 Advertisement• C-200 Instructions to Bidders• C-410 Bid Form• C-430 Bid Bond• C-435 Bid Bond Damages• NEW C-451 Qualification Statement• C-510 Notice of Award• C-520 Agreement Owner and Contractor (Stip. Sum)

Page 8: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20158

The Basic Relationships Among the Various Documents

DrawingsProcurement

Requirements:

•Solicitation

•Instructions for Procurement

•Available Information

•Procurement Forms & Supplements

Addenda

(Pre-Contract Revisions)

Contract Forms:

•Agreement

Project Forms:

•Performance Bond

•Payment Bond

•Certificates

Conditions of the Contract:

•General Conditions

•Supplementary Conditions

Specifications:

•Division 01 –General Requirements

•Divisions 02 -49

Contract Modifications

Procurement Documents

Typical Project Manual

Contract Documents

Construction Documents

When Owner-Contractor Agreement is signed, these become:

Contract Requirements

Page 9: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20159

EJCDC Construction Series• NEW C-521 Subcontract• C-525 Agreement Owner and Contractor (Cost-Plus)• C-550 Notice to Proceed• C-610 Performance Bond• C-615 Payment Bond• C-620 Contractor’s Application for Payment• C-625 Certification of Substantial Completion• C-700 Standard General Conditions• C-800 Guide to Prep. Of Supplementary Conditions• C-940 Work Change Directive• C-941 Change Order• C-942 Field Order

Page 10: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201510

EJCDC Construction Series

• C-430 Bid Bond – Penal Sum 2007-2012

• C-435 Bid Bond – Damages Form 2007-2012

• C-610 Performance Bond 2010

• C-615 Payment Bond 2010

• C-620 Application for Payment 2010

Page 11: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201511

EJCDC Preliminary DocumentsC-050 Bidding Procedures and Construction Contract DocumentsC-051 Engineer’s Letter re Bonds and InsuranceC-052 Owner’s Instruction re Bonds and Insurance• Organization and language improvements• Added NTUs• Coordination with related documents• Revised in accordance with insurance provision revisions of C-800• Added provisions for alternative types of insurance (pollution

liability, excess/umbrella liability, installation floater, etc.)

Page 12: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201512

C-111, Advertisement

• New EJCDC document• Includes discussion on use and topics covered

in an advertisement or invitation to bid• Includes template-style model language for

Advertisement for Bids with NTUs, including alternative provisions for printed Bidding Documents and electronic Bidding Documents

Page 13: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201513

C-200, Instructions to Bidders

• Moved time and location of pre-Bid conference to Advertisement, C-111

• New note concerning digital documents• Additional alternative language and notes on

Bidder qualification and reference to C-451, Qualifications Statement

• Expanded language on Site Visit and Testing by Bidders

Page 14: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201514

C-200, Instructions to Bidders

• Added Cost Plus Bids to Basis of Bid• Added specific language and notes on Price-Plus-

Time Bids to Basis of Bid and Evaluation of Bids• Revised language to coordinate with C-700 and/or

Agreement, including:• Technical Data

• Bidder’s Representations

• Substitute and “Or-Equal” items

• Subcontractors and Suppliers

Page 15: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201515

C-410, Bid Form

• Added Price-Plus-Time bidding option

• Addressed bidding procedures for cost-plus

contracts

• Improvements to format and Notes to Users

Page 16: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201516

C-451, Qualification Statement

• New EJCDC document• Compilation of info from several examples of

similar documents provided by users throughout the nation

• Intended to be edited (added to or subtracted from) based upon local needs/requirements/ Laws & Regulations

• Intended for use as a bidder’s qualification statement or for a more general prequalification

Page 17: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201517

NoticesC-510, Notice of AwardC-550, Notice to ProceedC-625, Certificate for Substantial Completion

• General modifications to make editing easier.• Language modifications to match other

documents.• Deleted references to “tentative” and

“definitive” to match General Conditions wording.

Page 18: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201518

C-520 and C-525, Agreement Between Owner and Contractor• Designation of both Designer and Construction

Phase Owner’s Representative in case they are not the same

• Inclusion of Bonus Clause in Liquidated Damages section

• Special Damages Clause in Liquidated Damages section to cover increased construction observation/inspection/construction admin costs

• Provisions for Milestones instead of just Substantial Completion

• Refinement of list of Contract Documents

Page 19: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201519

C-521, Subcontract• First edition of the Subcontract• Coordinated and meant to be used with C-700 and

EJCDC, but not dependent on it for definitions etc.• Combination of “Agreement” and general

terms/conditionsKey terms:• Prime Contract is incorporated by reference• No contractual relationship or privity with Owner• Sub not a third party beneficiary of Prime Contract• Flow down of obligations• Tied to Contractor’s progress schedule

Page 20: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201520

C-521, Subcontract• Payment: due ten days after Contractor’s receipt

of $$ from Owner (“pay when paid”—ultimately if no $$ received from Owner, Contractor would be obligated to pay Sub)

• Contractor has final authority regarding conflicts and coordination problems between Subs

• Safety duties to Sub’s own workforce, and to other persons and property at the Site

• Duty to report accidents and near misses to Contractor

Page 21: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201521

C-521, Subcontract• If change in Sub’s work resulted from change to

Prime Contract, increased compensation is limited to share of proceeds from Owner

• Insurance and Indemnification provisions track C-700

• Bonds—required only if expressly stated• Dispute resolution independent of Prime

Contract, but Contractor can pull Sub into arbitration with Owner

• Sub’s representations track C-series

Page 22: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201522

C-700 Standard General Conditions of the Construction Contract

• General Reorganization

• Improvements to Changes to the Contract and Claims

• Updated Insurance Provisions

• Differing Site Conditions

Page 23: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201523

General Reorganization

• Article 1 – Definitions and Terminology• Article 2 – Preliminary Matters• Article 3 – Contract Documents: Intent, Amending,

Requirements, Reuse• Article 4 - Commencement and Progress of the

Work• Article 5 – Availability of Lands; Subsurface and

Physical Conditions; Hazardous Environmental Conditions; Reference Points

• Article 6 – Bonds and Insurance

Page 24: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201524

General Reorganization

• Article 7 – Contractor’s Responsibilities• Article 8 – Other Work at the Site• Article 9 – Owner’s Responsibilities• Article 10 – Engineer’s Status During Construction• Article 11 – Amending the Contract Document

Documents; Changes in the Work; Claims• Article 12 – Change of Contract Price; Change of

Contract Times, Claims

Page 25: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201525

General Reorganization

• Article 13 – Cost of the Work; Allowances; Unit Price Work

• Article 14 – Tests and Inspections; Correction; Removal or Acceptance of Defective Work

• Article 15 – Payments to Contractor and Completion• Article 16 – Suspension of Work and Termination• Article 17 – Dispute Final Resolution of Disputes• Article 18 - Miscellaneous

Page 26: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201526

Changes to the Contract & Claims

• Historically all issues referred to Engineer for a “Final Decision”• A condition precedent to filing a Claim

• Similar to AIA• Initial Decision Maker

Page 27: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20152713 January 2012 B&V 27

Contractor Submits CP

within 30 days (GC-11.09A1)

Direct Claims Negotiation(GC‐12.01C)

Contractor Submits Claim within 30 days

(GC-12.01B)

Owner Claim(GC 12.01A)

Contractor Claim(GC-12.01A)

No action by Engineer within 30

days (GC-11.09A2)

CRApproved

Contractor’s Change Proposal

(GC-11.06A1)

Engineer Reviews CP(GC‐11.06A2)

CP Rejected. CP Resolution Final

and Binding(GC‐11.06A3)

CPRejected

Engineer Notifies Parties Unable to Resolve

(GC-11.09B)

Owner Agrees

Owner Appeals Engineer’s Decision within 30 days

Contractor Appeals

Engineer’s Decisions within

30 days

Owner submits Claim within 30 days (GC-

12.01B)

Contractor Submits Change 

Proposal(GC-3.04B ,

4.05G, 5.04D4,

5.05E3, 5.06G,7.05F, 7.06F, 7.10C, 8.03A

11.01A2,11.05A,13.03E,

14.04B1-2,14.07A, 15.01.E

Owner Submits Claim (GC‐3.04B,

GC‐3.04.C, GC‐5.04D3,GC‐7.10C, GC‐11.01A2GC‐11.06A3,GC-13.03E,

Engineer declines RFI or Change Proposal review 

because outside E’s scope; Contractor submits Claim. GC‐

3.04.C and GC11.06.B

Mediation (concluded max 60 days from request)

(GC‐12.01D)

Change OrderExecuted

(GC-11.10A4)NegotiatedResolution

MediatedResolution

Partial Mediated Resolution.

Final and Binding(GC‐12.01E)

Claim Issuer Approves Partial

Approval

Final ResolutionOf Disputes (GC‐

17)

Claim Issuer Rejects Partial Approval within

30 days

Claim Recipient Denies Claim or No action for 90

days

Claim Denied.Final and Binding

(GC‐12.01F)Claim Issuer Invokes Dispute Resolution

within 30 days

Change OrderExecuted

(GC-11.10A4)

Owner Disagree

s

Change Resolution

Page 28: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201528

Changes in the Work

• Changes in scope typically initiated by Owner• Contractor free to suggest changes in scope on

an informal basis• Contract could provide for cost-sharing of savings

(not a standard EJCDC provision)• For equipment and materials, Contractor may

suggest a substitution

Page 29: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201529

Amending the Contract

• Change Order• Commonly used change mechanism• Changes in scope, price, time to complete• Signed by both Owner and Contractor• Engineer’s recommendation needed

• Work Change Directive• Proceed with scope change; price/time TBD

• Field Order: minor changes

Page 30: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201530

Amending the Contract

C-940, Change OrderC-941, Work Change DirectiveC-942, Field Order• General modifications to make editing easier.• Modifications to make Work Change Directive,

Change Order, and Field Order more consistent in appearance.

Page 31: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201531

Non-Technical Change Orders

• As before, changes to the Work involving the design (Drawings, Specs) or other technical matters must be supported by the Engineer’s recommendation. This will be accomplished through Engineer’s signature on the Change Order form, as before.

• Owner and Contractor may enter into contract changes that are non-technical (for example, a change to an insurance or indemnification provision) without Engineer’s input, recommendation, or signature.

Page 32: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201532

Claim (2007)

A demand or assertion by Owner or Contractor seeking an adjustment of Contract Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.

Page 33: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201533

Claim (2013)

(a) A demand or assertion by Owner directly to Contractor, ….: seeking an adjustment of Contract Price or Contract Times, or both; contesting an initial decision by Engineer concerning the requirements of the Contract Documents or the acceptability of Work under the Contract Documents; contesting Engineer’s decision regarding a Contractor’s Change Proposal; seeking resolution of a contractual issue that Engineer has declined to address; or seeking other relief with respect to the terms of the Contract,

Page 34: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201534

Claim (2013)

or (b) a demand or assertion by Contractor directly to Owner, …., contesting Engineer’s decision regarding a Contractor’s Change Proposal; or seeking resolution of a contractual issue that Engineer has declined to address. A demand for money or services by a third party is not a Claim.

Page 35: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201535

First-Level Contract Issues

• What do the Drawings and Specs require?• Are actual conditions a DSC?• Is the Work as constructed acceptable?• Is Owner justified in levying a set-off against

payments due?• How much extra compensation owed for extra

work?• What is impact of a delay?

Page 36: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201536

First-Level Contract Issues:New Approach

• 2007 and prior: All first-level issues fed directly into “Claims”• Formal, often hostile process; not well suited to

garden variety issues• 2013: Contractor allowed to make “Change

Proposals” • New mechanism to resolve first-level issues• Engineer makes decision • Process commonly used, under a variety of names

Page 37: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201537

Changes to the Contract and Claims

Engineer will, with reasonable promptness, render a written clarification, interpretation, or decision on the issue submitted, or initiate an amendment or supplement to the Contract Documents. Engineer’s written clarification, interpretation, or decision will be final and binding on Contractor, unless it appeals by submitting a Change Proposal, and on Owner, unless it appeals by filing a Claim.

37

Page 38: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201538

Change Proposal

A written request by Contractor, … seeking an adjustment in Contract Price or Contract Times, or both; contesting an initial decision by Engineer concerning the requirements of the Contract Documents or the acceptability of Work under the Contract Documents; challenging a set-off against payments due; or seeking other relief with respect to the terms of the Contract Documents.

Page 39: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201539

Second-Level Contract Issues

• Classic “Claims”— serious step to take• Currently lumped together with other issues• Historically decided by Engineer• 2013:

• Label these as “Claims”• Direct between Owner and Contractor• Negotiation and mediation encouraged

• Includes appeal of Change Proposal decisions

Page 40: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 20154013 January 2012 B&V 40

Contractor Submits CP

within 30 days (GC-11.09A1)

Direct Claims Negotiation(GC‐12.01C)

Contractor Submits Claim within 30 days

(GC-12.01B)

Owner Claim(GC 12.01A)

Contractor Claim(GC-12.01A)

No action by Engineer within 30

days (GC-11.09A2)

CRApproved

Contractor’s Change Proposal

(GC-11.06A1)

Engineer Reviews CP(GC‐11.06A2)

CP Rejected. CP Resolution Final

and Binding(GC‐11.06A3)

CPRejected

Engineer Notifies Parties Unable to Resolve

(GC-11.09B)

Owner Agrees

Owner Appeals Engineer’s Decision within 30 days

Contractor Appeals

Engineer’s Decisions within

30 days

Owner submits Claim within 30 days (GC-

12.01B)

Contractor Submits Change 

Proposal(GC-3.04B ,

4.05G, 5.04D4,

5.05E3, 5.06G,7.05F, 7.06F, 7.10C, 8.03A

11.01A2,11.05A,13.03E,

14.04B1-2,14.07A, 15.01.E

Owner Submits Claim (GC‐3.04B,

GC‐3.04.C, GC‐5.04D3,GC‐7.10C, GC‐11.01A2GC‐11.06A3,GC-13.03E,

Engineer declines RFI or Change Proposal review 

because outside E’s scope; Contractor submits Claim. GC‐

3.04.C and GC11.06.B

Mediation (concluded max 60 days from request)

(GC‐12.01D)

Change OrderExecuted

(GC-11.10A4)NegotiatedResolution

MediatedResolution

Partial Mediated Resolution.

Final and Binding(GC‐12.01E)

Claim Issuer Approves Partial

Approval

Final ResolutionOf Disputes (GC‐

17)

Claim Issuer Rejects Partial Approval within

30 days

Claim Recipient Denies Claim or No action for 90

days

Claim Denied.Final and Binding

(GC‐12.01F)Claim Issuer Invokes Dispute Resolution

within 30 days

Change OrderExecuted

(GC-11.10A4)

Owner Disagree

s

Change Resolution

Page 41: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201541

Bonds and Insurance

• Core requirements are performance and payment bonds, CGL, Builder’s Risk

• 2011-12: Heavy scrutiny of precise terms and requirements• From insurance and surety professionals on the

Committee (EJCDC)• From national industry experts

• Expanded level of detail, reorganized• Separated bond requirements from insurance

requirements

Page 42: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201542

Performance and Payment Bonds• Continued reliance on Treasury Department list

for surety qualifications• Bonds (EJCDC C-610, C-615) revised

extensively by EJCDC, AIA, other stakeholders in 2010

• Added provision in GCs authorizing Owner to provide copies of payment bond to subs and suppliers who request it• Consistent with Miller Act and Little Miller Acts

• Review and input from SFAA, NASBP

Page 43: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201543

Bonds• Expressly stated: If Contractor fails to provide

bonds, Owner has right to exclude Contractor from Site, and terminate Contract

• New clause: Upon request, Owner shall provide copy of Payment bond to any sub or supplier claiming to have furnished labor or materials

Page 44: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201544

Liability Insurance

• Contractor’s CGL• Important risk management tool• Requirements consolidated and stated with more

specificity

Page 45: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201545

Insurance Highlights• Insurance companies must have AM Best rating

of A-VII or better• Owner and Contractor must provide copies of

required policies and endorsements upon the other’s, or any additional insured’s, request

• Added Contactor’s pollution liability requirement, covering contamination caused or worsened by Contractor

• Added Contractor’s Professional Liability insurance

Page 46: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201546

Insurance Highlights• In general, Contractor’s insurance policies shall:

contain a provision or endorsement that the coverage afforded will not be canceled, materially changed or renewal refused until at least 10 days prior written notice has been given to Contractor. Within three days of receipt of any such written notice, Contractor shall provide a copy of the notice to Owner, Engineer, and each other additional insured…

Page 47: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201547

Insurance HighlightsCommercial General Liability (CGL)• Completed operations remain in effect for 3 years• Specific form endorsements required for Additional

Insureds—Owner, Engineer• Various CGL provisions relocated from

Supplementary Conditions to Insurance section of GCs (Article 6)

• Deleted “eliminate the exclusion for property under Contractor’s care, custody, control” (impossible to get, and no longer needed)

• In SCs, deleted separate coverage limits for Contractual Liability (always is the same as general CGL coverage)

Page 48: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201548

Builder’s Risk Insurance

• Property insurance on the Work under construction

• Notable feature is waiver of insurance company’s subrogation rights

• 2013 edition: revised list of causal events to be covered by the Builder’s Risk insurance

• Changed default from Owner purchase of Builder’s Risk to Contractor purchase (SCs include “flip” of purchase duty)

Page 49: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201549

Insurance HighlightsBuilder’s Risk• Flood coverage required. “If it’s a risk, why not

insure against it?”• Option for providing flood coverage through

separate policy• Specified exception to standard workmanship,

design, materials exclusions: must cover “ensuing losses” from these causes

Page 50: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201550

Insurance HighlightsMore Builder’s Risk• Conformed policy duration—until Work is completed.

Typical BR policies will not extend “until final payment is made” (old wording)

• “loss payees” term replaced with “named insureds”• Owner, Contractor, Subs are named insureds• Engineer, Suppliers, and all “employees, agents,

etc.” are not named insureds• Waiver of subrogation continues to protect Engineer,

Owner, Contractor, and others, from claims by Builder’s Risk insurer

Page 51: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201551

Insurance HighlightsMore Builder’s Risk• Purchaser of BR insurance pays deductibles• Purchaser of BR is fiduciary for settlement of

claims against the policy• BR insurer may pay claims by joint check to

named insureds

Page 52: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201552

Insurance HighlightsMore Builder’s Risk• Installation Floater is presented in the SCs as a

possible alternative to Builder’s Risk insurance• Installation Floater is purchased by Contractor.

Provides insurance against loss while items to be installed are in transit or stored at Site. Intended for projects where the risk of loss is low once a portion of the Work is installed (e.g., a pipe installation project)

• Includes waiver of subrogation

Page 53: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201553

Site Safety

• EJCDC documents draw a “bright line” between Contractor/Subs and Owner/Engineer

• This risk allocation is efficient and protects the workforce and the Work under construction

• New clauseContractor’s duties and responsibilities for safety and protection shall resume whenever Contractor or any Subcontractor or Supplier returns to the Site to fulfill warranty or Correction Period obligations, or to conduct other tasks arising from the Contract Documents.

Page 54: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201554

Differing Site Conditions

Page 55: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201555

Differing Site Conditions

Page 56: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201556

Differing Site Conditions

Page 57: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201557

Differing Site Conditions

• Owner must disclose available site information• Consistent with court rulings

• Bidders (Contractor) may rely on accuracy of “technical data” identified as reliable in Contract Documents

• No reliance on geotechnical information other than identified “technical data”

• No reliance on extrapolations and interpretations

Page 58: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201558

Differing Site Conditions

• Proposed new clause provides default definition of Technical Data• Data contained in boring logs• Water level data• Other factual, objective information in

geotechnical report• Default definition applies only if Owner and Engineer

fail to identify specific Technical Data in the SCs• Default only applies to reports prepared for the

Project

Page 59: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201559

Differing Site Conditions

• Supplementary Condition alternative language gives Owner the option of furnishing bidders a Geotechnical Baseline Report (GBR)• Sets out assumed conditions for pricing purposes

Page 60: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201560

Differing Site Conditions

• Clarifications of Differing Site Condition procedures• Notice of possible DSC by Contractor• Review/recommendations by Engineer• Written statement by Owner

• Resumption of work• Design changes to be made in reaction to conditions• DSC or not

• Appeal rights of Contractor

Page 61: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201561

Hazardous Environmental Conditions at the Site• Responsibility for pre-existing pollution at the

Site has always belonged to Owner• Assumption: Clean-up tasks not in scope of

contract• Contractor responsible for any hazardous

environmental condition it causes• 2013 revision acknowledges that Contractor

may bring potentially hazardous substances to the Site if such are “controlled, contained, removed”

Page 62: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201562

“Or-equals”

• Or-equal provisions assume a Specification that requires name brand(s) “or equal”

• Ideally or-equal status would be determined pre-bid. EJCDC’s Instructions to Bidders allow for that; but often not practical

• Typically, bid prices should assume that Contractor will furnish one of the name brands

• No price change if or-equal product is approved• Contractor takes savings

• Engineer’s decision not appealable

Page 63: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201563

Substitutions

• Proposal by Contractor to substitute a different item to achieve design goal

• Approval of substitution may result in change in Contract Price or Contract Times

• Contractor reimburses Owner for Engineer’s efforts in reviewing

• Engineer’s decision not appealable

Page 64: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201564

Assigned Contracts

• EJCDC documents facilitate purchases of materials and equipment, and assignments of those purchase contracts to the GC

• Owners sometimes initiate purchases• Long lead time equipment orders• Multi-project purchases

• Warranties–Proposed new clause would clarify that the assigned contract’s specific warranties would govern over the General Conditions of the prime contract

Page 65: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201565

Other Work at the Site

• Work by owner’s own employees• Work by other prime contractors• Work by utilities• Owner coordinates other work with “Work”• Owner responsible to Contractor for delays,

damage caused by others• Owner may impose set-off for harm to others

caused by Contractor; and may assign rights to others

Page 66: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201566

Payment Provisions

• Clarified owner’s right to impose set-offs for pending or incurred costs attributable to Contractor• Recognition of common practice

• Owner must explain set-offs, and pay uncontested amounts

• 2013 allows for progress payments during extended punch list completion period

Page 67: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201567

C-800, Guide to the Preparation of Supplementary Conditions• Added “conformed Contract Documents” option• Allows for details and expansion regarding

working hours• Addresses possible use of construction-phase

representative other than Engineer• Provisions limiting mark-ups on Subcontractor

work under cost of work clause (27% limit) moved to General Conditions

• Added optional “prevailing party pays attorneys fees” clause

Page 68: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201568

C-800, Guide to the Preparation of Supplementary Conditions

• Mandatory Supplementary Conditions• Information available – 5.03• HEC information available – 5.06• Insurance limits – Article 6

Page 69: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201569

C-800, Guide to the Preparation of Supplementary Conditions

New SC: Geotechnical Baseline Report• Owner and geotech establish baselines of subsurface

conditions, by interpreting best available data• If actual site conditions vary from baseline, there is a

differing site condition, Contractor entitled to change in price, times

• Intended to induce better bids, simplify DSC administration

• Geotechnical Baseline Report and related data collection are Contract Documents

• Elements of typical EJCDC DSC clause are retained to deal with conditions that are not addressed in GBR

Page 70: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201570

EJCDC Construction Series

Available mid-MarchEJCDC.orgACEC.org

Page 71: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2013 ARCADIS22 March 201571

Questions – Speaker Contact Info

James (Jim) C. Brown II, P.E.Vice [email protected]

T. 914.641.2502

Malcolm Pirnie, the Water Division of ARCADIS 44 S. Broadway, White Plains, NY 10601www.arcadis-us.com

Page 72: Welcome to the 2013 EJCDC Construction Documents · PDF fileWelcome to the 2013 EJCDC Construction Documents February 27, 2013 James C. Brown II, PE Vice President Malcolm Pirnie,

© 2012 ARCADIS22 March 201572

Imagine the result