Activity ID Activity Name Original
Duration
Start Finish Total Float
MilestonesMilestones 359 01-Dec-14 A 01-Mar-16 0
M1000 Contract Award 0 01-Dec-14 A
M1035 Site & Earthwork Start 0 07-Jan-15 A
M1025 Concrete Footings Start 0 06-May-15 22
M1040 Stadium Enclosure Start 0 23-Jun-15 62
M1070 Steel Erection Start 0 20-Jul-15 15
M1055 Steel Erection Complete 0 01-Oct-15 10
M1080 Exterior Cladding Complete 0 25-Nov-15 56
M1050 Permanent Power 0 07-Dec-15 56
M1060 Dry-in up to Suite Level 0 08-Dec-15 61
M1140 Playing Field Start 0 23-Dec-15 53
M1100 Interior Finishes Complete 0 28-Jan-16 20
M1045 TAB & Cx Start 0 29-Jan-16 24
M1110 INT & EXT FF&E Complete 0 02-Feb-16 21
M1090 Playing Field Sod Start 0 08-Feb-16 17
M1120 Contract Completion Date 0 01-Mar-16 0
Design & EngineeringDesign & Engineering 0 08-Dec-14 A 31-Mar-15 A
DE100 Sitework Package 0 08-Dec-14 A
DE110 Final Construction Docs 0 27-Feb-15 A
DE130 Addendum #1 Civ, Struc, Arch, MEP Revisions0 13-Mar-15 A
DE140 Addendum #2 Civ, Struc, Arch, MEP Revisions0 20-Mar-15 A
DE150 Addendum #3 Wall Sections 0 30-Mar-15 A
DE160 Addendum #4 Add window types 0 31-Mar-15 A
ProcurementProcurement 212 08-Dec-14 A 09-Sep-15 122
Bid & AwardBid & Award 102 08-Dec-14 A 22-Apr-15 9
BA1030 Sitework Bid & Award 5 08-Dec-14 A 12-Dec-14 A
BA1050 Concrete & Rebar 26 02-Mar-15 A 07-Apr-15 6
BA1060 Structural Steel & Misc Metals 26 02-Mar-15 A 07-Apr-15 -1
BA1070 Waterproofing & Sealants 26 02-Mar-15 A 13-Apr-15 14
BA1080 Framing 26 02-Mar-15 A 13-Apr-15 14
BA1090 Roofing & Sheet metal 26 02-Mar-15 A 13-Apr-15 14
BA1100 Masonry, Precast, Stone 26 02-Mar-15 A 13-Apr-15 14
BA1110 Mechanical 26 02-Mar-15 A 13-Apr-15 14
BA1120 Electrical 26 02-Mar-15 A 13-Apr-15 11
BA1130 Plumbing 26 02-Mar-15 A 13-Apr-15 11
BA1140 Fire Sprinklers 26 02-Mar-15 A 13-Apr-15 11
BA1150 Doors, Frames, & Hardware 26 02-Mar-15 A 13-Apr-15 14
BA1160 Glass & Storefronts 26 02-Mar-15 A 13-Apr-15 14
BA1170 GWB & Ceilings 26 02-Mar-15 A 13-Apr-15 14
BA1180 Interior Finishes - Walls & Floors 26 02-Mar-15 A 13-Apr-15 14
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
01-Mar-16, Milestones
Contract Award
Site & Earthwork Start
Concrete Footings Start
Stadium Enclosure Start
Steel Erection Start
Steel Erection Complete
Exterior Cladding Complete
Permanent Power
Dry-in up to Suite Level
Playing Field Start
Interior Finishes Complete
TAB & Cx Start
INT & EXT FF&E Complete
Playing Field Sod Start
Contract Completion Date
31-Mar-15 A, Design & Engineering
Sitework Package
Final Construction Docs
Addendum #1 Civ, Struc, Arch, MEP Revisions
Addendum #2 Civ, Struc, Arch, MEP Revisions
Addendum #3 Wall Sections
Addendum #4 Add window types
09-Sep-15, Procurement
22-Apr-15, Bid & Award
Sitework Bid & Award
Concrete & Rebar
Structural Steel & Misc Metals
Waterproofing & Sealants
Framing
Roofing & Sheet metal
Masonry, Precast, Stone
Mechanical
Electrical
Plumbing
Fire Sprinklers
Doors, Frames, & Hardware
Glass & Storefronts
GWB & Ceilings
Interior Finishes - Walls & Floors
Spirit Communications Park
22-Apr-15 15:28
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 1 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Appendix A
Activity ID Activity Name Original
Duration
Start Finish Total Float
BA1190 Millwork 26 02-Mar-15 A 13-Apr-15 14
BA1200 Exterior FF&E 26 02-Mar-15 A 13-Apr-15 14
BA1210 Interior FF&E 26 02-Mar-15 A 13-Apr-15 14
BA1220 Sports Field & Landscape 26 02-Mar-15 A 13-Apr-15 14
BA1230 Sports Equipment 26 02-Mar-15 A 13-Apr-15 14
BA1960 Elevator 26 02-Mar-15 A 13-Apr-15 9
BA1970 Kitchen / Concessions Equipment 26 02-Mar-15 A 13-Apr-15 14
BA1240 Railings 26 02-Mar-15 A 13-Apr-15 14
BA1250 OH Roll up Doors 26 02-Mar-15 A 13-Apr-15 9
BA1520 GMP Approval 2 21-Apr-15* 22-Apr-15 3
Submittal Prep, Review, ApproveSubmittal Prep, Review, Approve 52 06-Apr-15 A 17-Jun-15 122
S1260 Structural Steel & Misc Metals 30 06-Apr-15 A 01-Jun-15 0
S1250 Concrete & Rebar 15 07-Apr-15 A 06-May-15 6
S1270 Site Utilities 10 22-Apr-15 06-May-15 18
S1280 Waterproofing & Sealants 10 22-Apr-15 06-May-15 40
S1290 Framing 15 22-Apr-15 13-May-15 69
S1300 Roofing & Sheet metal 15 22-Apr-15 13-May-15 89
S1310 Masonry, Precast, Stone 15 22-Apr-15 13-May-15 18
S1320 Mechanical 15 22-Apr-15 13-May-15 50
S1330 Electrical 15 22-Apr-15 13-May-15 3
S1340 Plumbing 15 22-Apr-15 13-May-15 3
S1350 Fire Sprinklers 15 22-Apr-15 13-May-15 3
S1360 Doors, Frames, & Hardware 30 22-Apr-15 03-Jun-15 14
S1370 Glass & Storefronts 30 22-Apr-15 03-Jun-15 55
S1380 GWB & Ceiling 30 22-Apr-15 03-Jun-15 43
S1390 Interior Finishes - Walls & Floors 30 22-Apr-15 03-Jun-15 78
S1400 Millwork 30 22-Apr-15 03-Jun-15 91
S1410 Exterior FF&E 30 22-Apr-15 03-Jun-15 89
S1420 Interior FF&E 30 22-Apr-15 03-Jun-15 115
S1430 Sports Field & Landcape 30 22-Apr-15 03-Jun-15 78
S1440 Sports Equipment 30 22-Apr-15 03-Jun-15 106
S1450 Elevator 5 22-Apr-15 29-Apr-15 10
S1460 Kitchen / Concessions Equipment 40 22-Apr-15 17-Jun-15 29
S1470 Railings 40 22-Apr-15 17-Jun-15 96
S1480 OH Roll up Doors 40 22-Apr-15 17-Jun-15 111
S1770 Sports Equipment 40 22-Apr-15 17-Jun-15 96
Fabrication & DeliveryFabrication & Delivery 123 07-Apr-15 09-Sep-15 122
FD1570 Concrete & Rebar 30 07-Apr-15 14-May-15 6
FD1780 Elevator 5 29-Apr-15 06-May-15 10
FD1600 Site Utilities 10 06-May-15 20-May-15 18
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
Millwork
Exterior FF&E
Interior FF&E
Sports Field & Landscape
Sports Equipment
Elevator
Kitchen / Concessions Equipment
Railings
OH Roll up Doors
GMP Approval
17-Jun-15, Submittal Prep, Review, Approve
Structural Steel & Misc Metals
Concrete & Rebar
Site Utilities
Waterproofing & Sealants
Framing
Roofing & Sheet metal
Masonry, Precast, Stone
Mechanical
Electrical
Plumbing
Fire Sprinklers
Doors, Frames, & Hardware
Glass & Storefronts
GWB & Ceiling
Interior Finishes - Walls & Floors
Millwork
Exterior FF&E
Interior FF&E
Sports Field & Landcape
Sports Equipment
Elevator
Kitchen / Concessions Equipment
Railings
OH Roll up Doors
Sports Equipment
09-Sep-15, Fabrication & Delivery
Concrete & Rebar
Elevator
Site Utilities
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 2 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
FD1610 Waterproofing & Sealants 5 06-May-15 13-May-15 40
FD1620 Framing 20 13-May-15 10-Jun-15 69
FD1630 Roofing & Sheet metal 20 13-May-15 10-Jun-15 89
FD1640 Masonry, Precast, Stone 20 13-May-15 10-Jun-15 18
FD1650 Mechanical 20 13-May-15 10-Jun-15 84
FD1660 Electrical 20 13-May-15 10-Jun-15 3
FD1670 Plumbing 20 13-May-15 10-Jun-15 3
FD1680 Fire Sprinklers 20 13-May-15 10-Jun-15 3
FD1820 Structural Steel 38 01-Jun-15 20-Jul-15 0
FD1690 Doors, Frames, & Hardware 60 03-Jun-15 26-Aug-15 14
FD1700 Glass & Storefronts 60 03-Jun-15 26-Aug-15 55
FD1710 GWB & Ceiling 60 03-Jun-15 26-Aug-15 43
FD1720 Interior Finishes - Walls & Floors 60 03-Jun-15 26-Aug-15 78
FD1730 Millwork 60 03-Jun-15 26-Aug-15 91
FD1740 Exterior FF&E 60 03-Jun-15 26-Aug-15 108
FD1750 Interior FF&E 60 03-Jun-15 26-Aug-15 115
FD1760 Sports Field & Landcape 60 03-Jun-15 26-Aug-15 78
FD1770 Sports Equipment 60 17-Jun-15 09-Sep-15 96
FD1790 Kitchen / Concessions Equipment 60 17-Jun-15 09-Sep-15 29
FD1800 Railings 60 17-Jun-15 09-Sep-15 96
FD1810 OH Roll up Doors 60 17-Jun-15 09-Sep-15 111
SiteworkSitework 77 05-Jan-15 A 16-Apr-15 22
A1500 Site Conctractor Mobilization 2 05-Jan-15 A 06-Jan-15 A
A1450 Clearing 9 07-Jan-15 A 16-Jan-15 A
A1460 Abatement 12 07-Jan-15 A 21-Jan-15 A
A1490 Grading 25 19-Jan-15 A 01-Apr-15 A
A1470 Demolition 10 22-Jan-15 A 04-Feb-15 A
A1530 French Drain System 5 26-Jan-15 A 28-Jan-15 A
A1480 Dewatering 30 28-Jan-15 A 27-Mar-15 A
A1510 Field Drainage System 5 26-Mar-15 A 16-Apr-15 22
A1520 Ground Water Drainage System 10 06-Apr-15 A 13-Apr-15 22
Field Level 3B CL17 to CL0Field Level 3B CL17 to CL0 189 06-May-15 01-Jan-16 46
A1550 FTG CL14 - 0 3B field level 15 06-May-15 26-May-15 6
A1560 FND Walls, Columns, & DO Tunnel CL 14 - 0 3B field level20 19-May-15 16-Jun-15 11
A3190 Dugout FTGs & Walls - 3B field level10 02-Jun-15 15-Jun-15 19
A1580 UG MEP / Drainage - 3B field level 10 10-Jun-15 24-Jun-15 30
A1610 Waterproofing FND walls - 3B field level3 23-Jun-15 26-Jun-15 11
A1620 SOG - 3B field level 7 24-Jun-15 03-Jul-15 30
A3090 Backfill FDN walls - 3B field level 3 29-Jun-15 01-Jul-15 12
A1650 Pan Deck Above Field Level - 3B 15 03-Jul-15 24-Jul-15 30
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
Waterproofing & Sealants
Framing
Roofing & Sheet metal
Masonry, Precast, Stone
Mechanical
Electrical
Plumbing
Fire Sprinklers
Structural Steel
Doors, Frames, & Hardware
Glass & Storefronts
GWB & Ceiling
Interior Finishes - Walls & Floors
Millwork
Exterior FF&E
Interior FF&E
Sports Field & Landcape
Sports Equipment
Kitchen / Concessions Equipment
Railings
OH Roll up Doors
16-Apr-15, Sitework
Site Conctractor Mobilization
Clearing
Abatement
Grading
Demolition
French Drain System
Dewatering
Field Drainage System
Ground Water Drainage System
01-Jan-16, Field Level 3B CL17 to CL0
FTG CL14 - 0 3B field level
FND Walls, Columns, & DO Tunnel CL 14 - 0 3B field level
Dugout FTGs & Walls - 3B field level
UG MEP / Drainage - 3B field level
Waterproofing FND walls - 3B field level
SOG - 3B field level
Backfill FDN walls - 3B field level
Pan Deck Above Field Level - 3B
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 3 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
A3230 CMU Stair & Elevator shafts -3B 15 24-Jul-15 13-Aug-15 33
A2450 INT Stud Framing - 3B field level 5 17-Sep-15 24-Sep-15 10
A2460 MEP R/I Walls - 3B field level 5 24-Sep-15 01-Oct-15 10
A3100 MEP R/I Overhead - 3B field level 10 01-Oct-15 14-Oct-15 10
A4540 Elec Rm F/P Eqpmnt pads - 3B field level5 02-Oct-15 09-Oct-15 75
A4550 Elec RM Set switchgear/panels/transfrmers - 3B field level5 09-Oct-15 15-Oct-15 75
A2580 GWB Hang - 3B field level 10 14-Oct-15 27-Oct-15 10
A2600 GWB Finish - 3B field level 10 20-Oct-15 02-Nov-15 46
A4560 Elec Rm Conduit - 3B Field level 10 20-Oct-15 02-Nov-15 72
A1940 Prime & First Coat Paint Walls - 3B field level10 02-Nov-15 13-Nov-15 46
A2010 Ceramic Tile / Epoxy Coat - 3B field level10 02-Nov-15 13-Nov-15 46
A4570 Elec Rms Feeders/Terminations - 3B field level10 02-Nov-15 13-Nov-15 72
A2000 Flooring - 3B field level 15 13-Nov-15 03-Dec-15 46
A2120 Laundry Equipment 10 13-Nov-15 26-Nov-15 74
A2230 Fire Ext. Cabinets - 3B field level 1 13-Nov-15 16-Nov-15 66
A3130 Trash compactor 5 13-Nov-15 20-Nov-15 79
A3110 Batting Tunnel Equipment 10 13-Nov-15 26-Nov-15 74
A4580 Elec Rms Permanent Power Insp - 3B fiield level1 13-Nov-15 16-Nov-15 72
A4590 Elec Rms Permanent Power - 3B field level1 16-Nov-15 17-Nov-15 72
A1910 Ceiling Grid - 3B field level 10 17-Nov-15 30-Nov-15 53
A1990 Millwork & Trim - 3B field level 16 20-Nov-15 10-Dec-15 46
A1920 Ceiling Tiles - 3B field level 14 30-Nov-15 17-Dec-15 53
A1980 A/V Equipment - 3B field level 15 30-Nov-15 18-Dec-15 57
A2690 Install Interior Doors - 3B field level 8 03-Dec-15 14-Dec-15 58
A2530 MEP Trim Out - 3B field level 8 07-Dec-15 16-Dec-15 49
A2350 Countertops - 3B field level 5 10-Dec-15 16-Dec-15 49
A2020 Final coat paint - 3B field level 10 10-Dec-15 24-Dec-15 46
A2200 Toilet Partitions & Accesories - 3B field level5 16-Dec-15 23-Dec-15 49
A2070 Signage & Graphics - 3B field level 2 24-Dec-15 25-Dec-15 46
A2220 Lockers 2 24-Dec-15 25-Dec-15 51
A2240 Wall & Door Protection - 3B field level1 24-Dec-15 24-Dec-15 47
A1860 Final Clean - 3B field level 5 25-Dec-15 01-Jan-16 46
Concourse Level 1B CL17 to CL31Concourse Level 1B CL17 to CL31 181 19-May-15 05-Jan-16 44
A1570 FTG CL14 - 30 1B 15 19-May-15 08-Jun-15 6
A1575 Install Strip Ftgs 1B CL 28 - 30 10 26-May-15 08-Jun-15 6
A2080 Installl Perimeter Block CL 28 - 30 15 08-Jun-15 26-Jun-15 6
A2370 UG MEP R/I 1st Base CL C - D.5 5 10-Jun-15 17-Jun-15 3
A2360 SOG 1B Concourse CL C - D.5 5 17-Jun-15 23-Jun-15 3
A1690 Interior CMU & Stair tower 1B 10 23-Jun-15 06-Jul-15 3
A1630 Erect steel and deck CL 14 - 30 20 20-Jul-15 13-Aug-15 0
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
CMU Stair & Elevator shafts -3B
INT Stud Framing - 3B field level
MEP R/I Walls - 3B field level
MEP R/I Overhead - 3B field level
Elec Rm F/P Eqpmnt pads - 3B field level
Elec RM Set switchgear/panels/transfrmers - 3B field level
GWB Hang - 3B field level
GWB Finish - 3B field level
Elec Rm Conduit - 3B Field level
Prime & First Coat Paint Walls - 3B field level
Ceramic Tile / Epoxy Coat - 3B field level
Elec Rms Feeders/Terminations - 3B field level
Flooring - 3B field level
Laundry Equipment
Fire Ext. Cabinets - 3B field level
Trash compactor
Batting Tunnel Equipment
Elec Rms Permanent Power Insp - 3B fiield level
Elec Rms Permanent Power - 3B field level
Ceiling Grid - 3B field level
Millwork & Trim - 3B field level
Ceiling Tiles - 3B field level
A/V Equipment - 3B field level
Install Interior Doors - 3B field level
MEP Trim Out - 3B field level
Countertops - 3B field level
Final coat paint - 3B field level
Toilet Partitions & Accesories - 3B field level
Signage & Graphics - 3B field level
Lockers
Wall & Door Protection - 3B field level
Final Clean - 3B field level
05-Jan-16, Concourse Level 1B CL17 to CL31
FTG CL14 - 30 1B
Install Strip Ftgs 1B CL 28 - 30
Installl Perimeter Block CL 28 - 30
UG MEP R/I 1st Base CL C - D.5
SOG 1B Concourse CL C - D.5
Interior CMU & Stair tower 1B
Erect steel and deck CL 14 - 30
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 4 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
A1740 Install Stairs - 1B 5 13-Aug-15 20-Aug-15 38
A3760 Roof Curbs Kitchen Equipment - 1B 5 13-Aug-15 20-Aug-15 64
A1880 Install Roofing - 1B 10 18-Aug-15 31-Aug-15 66
A2640 Pour Concrete Pans on Stairs - 1B 3 20-Aug-15 25-Aug-15 87
A1700 EXT studs & sheathing - 1B 15 26-Aug-15 15-Sep-15 16
A2680 Exterior Doors - 1B 5 31-Aug-15 07-Sep-15 82
A4600 Elec Rms F/P Eqpmnt pads - 1B 5 07-Sep-15 11-Sep-15 82
A2510 INT Stud Framing - 1B 10 08-Sep-15 21-Sep-15 37
A1600 Kitchen Hoods install - 1B 5 09-Sep-15 16-Sep-15 48
A4610 Elec Rms Set switchgear/panels/transfrmers - 1B10 11-Sep-15 24-Sep-15 82
A1720 EXT Vapor Barrier - 1B 7 16-Sep-15 24-Sep-15 16
A1820 Walls MEP R/I - 1B 7 22-Sep-15 30-Sep-15 37
A2160 Kitchen Equipment overhead R/I - 1B7 22-Sep-15 30-Sep-15 44
A1810 Install EXT Brick Veneer - 1B 30 22-Sep-15 30-Oct-15 21
A4620 Elec Rms Conduit - 1B 15 24-Sep-15 14-Oct-15 82
A1730 Above ceiling MEP R/I - 1B 10 25-Sep-15 08-Oct-15 37
A1850 Install Windows - 1B 10 12-Oct-15 23-Oct-15 25
A4630 Elec Rms Feeders/Terminations - 1B15 14-Oct-15 02-Nov-15 82
A1890 GWB Hang - 1B 10 23-Oct-15 05-Nov-15 25
A1900 GWB Finish - 1B 15 30-Oct-15 18-Nov-15 25
A2380 Install Stucco - 1B 15 30-Oct-15 18-Nov-15 66
A2660 Storefronts - 1B 5 30-Oct-15 05-Nov-15 86
A4640 Elec Rms Permanent Power Insp - 1B1 02-Nov-15 03-Nov-15 82
A4650 Elec Rms Permanent Power - 1B 1 03-Nov-15 04-Nov-15 82
A2650 Ceramic Tile / Epoxy Coat - 1B 10 05-Nov-15 18-Nov-15 30
A2670 Prime & 1st Coat Paint Walls - 1B 10 12-Nov-15 25-Nov-15 25
A2720 Flooring - 1B 10 25-Nov-15 08-Dec-15 25
A2730 Fire Ext. Cabinets - 1B 1 25-Nov-15 26-Nov-15 45
A2710 Ceiling Grid - 1B 10 27-Nov-15 10-Dec-15 44
A2740 Millwork & Trim - 1B 16 01-Dec-15 22-Dec-15 25
A4520 Kitchen Equipment install - 1B 15 01-Dec-15 21-Dec-15 51
A2060 Install Interior Doors -1B 4 08-Dec-15 14-Dec-15 59
A1950 MEP Trim out - 1B 10 10-Dec-15 23-Dec-15 44
A2760 Ceiling Tiles - 1B 7 10-Dec-15 18-Dec-15 54
A2750 A/V Equipment - 1B 15 10-Dec-15 29-Dec-15 44
A2770 Countertops - 1B 3 15-Dec-15 17-Dec-15 48
A2780 Final coat paint - 1B 5 22-Dec-15 28-Dec-15 25
A2170 Test & Balance HVAC - 1B 3 23-Dec-15 28-Dec-15 51
A2700 Toilet Partitions & Accesories - 1B 5 23-Dec-15 29-Dec-15 44
A2790 Signage & Graphics - 1B 2 29-Dec-15 30-Dec-15 48
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
Install Stairs - 1B
Roof Curbs Kitchen Equipment - 1B
Install Roofing - 1B
Pour Concrete Pans on Stairs - 1B
EXT studs & sheathing - 1B
Exterior Doors - 1B
Elec Rms F/P Eqpmnt pads - 1B
INT Stud Framing - 1B
Kitchen Hoods install - 1B
Elec Rms Set switchgear/panels/transfrmers - 1B
EXT Vapor Barrier - 1B
Walls MEP R/I - 1B
Kitchen Equipment overhead R/I - 1B
Install EXT Brick Veneer - 1B
Elec Rms Conduit - 1B
Above ceiling MEP R/I - 1B
Install Windows - 1B
Elec Rms Feeders/Terminations - 1B
GWB Hang - 1B
GWB Finish - 1B
Install Stucco - 1B
Storefronts - 1B
Elec Rms Permanent Power Insp - 1B
Elec Rms Permanent Power - 1B
Ceramic Tile / Epoxy Coat - 1B
Prime & 1st Coat Paint Walls - 1B
Flooring - 1B
Fire Ext. Cabinets - 1B
Ceiling Grid - 1B
Millwork & Trim - 1B
Kitchen Equipment install - 1B
Install Interior Doors -1B
MEP Trim out - 1B
Ceiling Tiles - 1B
A/V Equipment - 1B
Countertops - 1B
Final coat paint - 1B
Test & Balance HVAC - 1B
Toilet Partitions & Accesories - 1B
Signage & Graphics - 1B
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 5 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
A2810 Wall & Door Protection - 1B 1 29-Dec-15 29-Dec-15 49
A2820 Window Treatments - 1B 2 29-Dec-15 30-Dec-15 25
A1590 Final Clean - 1B 5 29-Dec-15 05-Jan-16 44
Concourse Level 3B CL17 to CL0Concourse Level 3B CL17 to CL0 174 01-Jul-15 08-Feb-16 17
A1670 FTG CL - B at 3B 10 01-Jul-15 15-Jul-15 11
A1640 Erect Steel CL 14 - 0 20 07-Aug-15 03-Sep-15 0
A1710 Erect Steel & Deck CL 1 - 0 / E - B10 04-Sep-15 17-Sep-15 0
A1070 EXT studs & sheathing - 3B concourse level15 17-Sep-15 07-Oct-15 0
A2490 Install Stairs - 3B 10 17-Sep-15 01-Oct-15 10
A4490 Roof Curbs Kitchen Equip. - 3B concourse level3 17-Sep-15 22-Sep-15 18
A4510 Interior CMU 12 17-Sep-15 02-Oct-15 13
A1660 Backfill to Concourse level 2 18-Sep-15 21-Sep-15 46
A2630 Install Roofing - 3B 10 21-Sep-15 02-Oct-15 18
A1930 SOG Concourse 3rd Base & SOD CL 1-0 / E-B10 22-Sep-15 05-Oct-15 46
A1800 INT Stud Framing - 3B concourse level10 01-Oct-15 14-Oct-15 0
A1830 Pour Concrete Pans on Stairs - 3B 2 01-Oct-15 02-Oct-15 85
A2110 Exterior Doors - 3B 7 02-Oct-15 13-Oct-15 60
A4500 Kitchen Hoods install - 3B Concourse level5 02-Oct-15 09-Oct-15 13
A2500 EXT Vapor Barrier - 3B 8 07-Oct-15 16-Oct-15 11
A4660 Elec Rms F/P Eqpmnt pads - 3B concourse level5 13-Oct-15 19-Oct-15 60
A2540 MEP R/I walls - 3B concourse level 10 14-Oct-15 27-Oct-15 0
A2260 Kitchen Equipment overhead R/I - 3B concourse level10 14-Oct-15 27-Oct-15 10
A2390 Install EXT Brick Veener - 3B 30 16-Oct-15 25-Nov-15 11
A4670 Elec Rms Set switchgear/panels/transfrmers - 3B concourse level8 19-Oct-15 29-Oct-15 60
A3140 MEP R/I overhead - 3B concourse level10 27-Oct-15 09-Nov-15 0
A4680 Elec Rms Conduit - 3B concourse level10 29-Oct-15 11-Nov-15 60
A2400 Install Windows - 3B 10 05-Nov-15 18-Nov-15 76
A2610 GWB Hang - 3B concourse level 10 09-Nov-15 20-Nov-15 0
A4690 Elec Rms Feeders/Terminations - 3B concourse level15 11-Nov-15 30-Nov-15 60
A3220 GWB Finish - 3B concourse level 15 13-Nov-15 03-Dec-15 0
A2150 Storefronts - 3B 5 25-Nov-15 01-Dec-15 66
A2410 Install Stucco - 3B 15 25-Nov-15 14-Dec-15 61
A4700 Elec Rms Permanent Power Insp - 3B concourse level1 30-Nov-15 01-Dec-15 60
A4710 Elec Rms Permanent Power - 3B concourse level1 01-Dec-15 02-Dec-15 60
A2190 Elevator equipment 20 03-Dec-15 29-Dec-15 49
A3120 Ceramic tile / epoxy coat - 3B concourse level10 03-Dec-15 16-Dec-15 0
A3180 Prime & First Coat Paint Walls - 3B concourse level7 10-Dec-15 18-Dec-15 0
A3210 Fire Ext. Cabinets - 3B concourse level1 18-Dec-15 21-Dec-15 24
A3240 Ceiling Grid - 3B concourse level 7 23-Dec-15 31-Dec-15 0
A3300 A/V Equipment - 3B concourse level20 31-Dec-15 26-Jan-16 22
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
Wall & Door Protection - 1B
Window Treatments - 1B
Final Clean - 1B
08-Feb-16, Concourse Level 3B CL17 to CL0
FTG CL - B at 3B
Erect Steel CL 14 - 0
Erect Steel & Deck CL 1 - 0 / E - B
EXT studs & sheathing - 3B concourse level
Install Stairs - 3B
Roof Curbs Kitchen Equip. - 3B concourse level
Interior CMU
Backfill to Concourse level
Install Roofing - 3B
SOG Concourse 3rd Base & SOD CL 1-0 / E-B
INT Stud Framing - 3B concourse level
Pour Concrete Pans on Stairs - 3B
Exterior Doors - 3B
Kitchen Hoods install - 3B Concourse level
EXT Vapor Barrier - 3B
Elec Rms F/P Eqpmnt pads - 3B concourse level
MEP R/I walls - 3B concourse level
Kitchen Equipment overhead R/I - 3B concourse level
Install EXT Brick Veener - 3B
Elec Rms Set switchgear/panels/transfrmers - 3B concourse level
MEP R/I overhead - 3B concourse level
Elec Rms Conduit - 3B concourse level
Install Windows - 3B
GWB Hang - 3B concourse level
Elec Rms Feeders/Terminations - 3B concourse level
GWB Finish - 3B concourse level
Storefronts - 3B
Install Stucco - 3B
Elec Rms Permanent Power Insp - 3B concourse level
Elec Rms Permanent Power - 3B concourse level
Elevator equipment
Ceramic tile / epoxy coat - 3B concourse level
Prime & First Coat Paint Walls - 3B concourse level
Fire Ext. Cabinets - 3B concourse level
Ceiling Grid - 3B concourse level
A/V Equipment - 3B concourse level
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 6 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
A3200 Flooring - 3B concourse level 7 31-Dec-15 08-Jan-16 0
A3310 MEP Trim Out - 3B concourse level 8 31-Dec-15 11-Jan-16 29
A3290 Ceiling Tiles - 3B concourse level 7 01-Jan-16 11-Jan-16 36
A3250 Millwork & Trim - 3B concourse level10 07-Jan-16 20-Jan-16 0
A4530 Kitchen Equipment install - 3B concourse level20 07-Jan-16 02-Feb-16 17
A3260 Install Interior Doors - 3B concourse level8 08-Jan-16 20-Jan-16 29
A3320 Toilet Partitions & Accesories - 3B concourse level5 11-Jan-16 18-Jan-16 29
A3280 Final coat paint - 3B concourse level7 20-Jan-16 28-Jan-16 0
A3710 Test & Balance HVAC - 3B concourse level3 20-Jan-16 22-Jan-16 29
A3270 Countertops - 3B concourse level 5 26-Jan-16 02-Feb-16 17
A3330 Signage & Graphics - 3B concourse level2 28-Jan-16 01-Feb-16 23
A3350 Wall & Door Protection - 3B concourse level1 28-Jan-16 29-Jan-16 24
A3360 Window Treatments - 3B concourse level2 28-Jan-16 01-Feb-16 0
A1780 Final Clean - 3B concourse level 5 02-Feb-16 08-Feb-16 17
Suite Level 3B CL17 to CL4Suite Level 3B CL17 to CL4 105 17-Sep-15 28-Jan-16 24
A2090 Precast concrete seating 3B suite level5 17-Sep-15 24-Sep-15 15
A1680 SOD (incl set drains)) 3B suite level 7 01-Oct-15 09-Oct-15 9
A1750 Roofing 3B suite level 10 12-Oct-15 23-Oct-15 9
A1770 EXT studs framing 3B suite level 5 26-Oct-15 30-Oct-15 10
A2870 INT stud framing 3B suite level 5 30-Oct-15 05-Nov-15 17
A3150 EXT sheathing & vapor barrier 3B suite level5 30-Oct-15 05-Nov-15 10
A2420 Install Sliding Glass Doors 3B suite level10 06-Nov-15 19-Nov-15 75
A3030 MEP R/I walls 3B suite level 7 06-Nov-15 16-Nov-15 10
A2620 Install stucco 3B suite level 9 06-Nov-15 18-Nov-15 61
A3020 MEP R/I overhead 3B suite level 10 16-Nov-15 27-Nov-15 10
A2840 Storefronts 3B suite level 10 25-Nov-15 08-Dec-15 61
A3040 GWB hang 3B suite level 10 27-Nov-15 10-Dec-15 10
A3160 GWB finish 3B suite level 10 10-Dec-15 23-Dec-15 10
A2860 Prime & First Coat Paint Walls 3B suite level5 23-Dec-15 30-Dec-15 10
A3170 Ceramic Tile & Epoxy coat 3B suite level5 23-Dec-15 30-Dec-15 24
A2900 Ceiling Grid 3B suite level 5 30-Dec-15 05-Jan-16 19
A2930 Millwork & Trim 3B suite level 8 30-Dec-15 08-Jan-16 10
A2920 Fire Ext. Cabinets 3B suite level 1 30-Dec-15 31-Dec-15 17
A2960 Countertops 3B suite level 5 05-Jan-16 12-Jan-16 19
A2890 MEP Trim Out 3B suite level 5 05-Jan-16 12-Jan-16 19
A2940 A/V Equipment 3B suite level 7 08-Jan-16 18-Jan-16 28
A2970 Final coat paint 3B suite level 4 08-Jan-16 14-Jan-16 10
A2950 Ceiling Tiles 3B suite level 5 12-Jan-16 18-Jan-16 23
A2910 Flooring 3B suite level 5 12-Jan-16 18-Jan-16 19
A2980 Signage & Graphics 3B suite level 1 14-Jan-16 14-Jan-16 35
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
Flooring - 3B concourse level
MEP Trim Out - 3B concourse level
Ceiling Tiles - 3B concourse level
Millwork & Trim - 3B concourse level
Kitchen Equipment install - 3B concourse level
Install Interior Doors - 3B concourse level
Toilet Partitions & Accesories - 3B concourse level
Final coat paint - 3B concourse level
Test & Balance HVAC - 3B concourse level
Countertops - 3B concourse level
Signage & Graphics - 3B concourse level
Wall & Door Protection - 3B concourse level
Window Treatments - 3B concourse level
Final Clean - 3B concourse level
28-Jan-16, Suite Level 3B CL17 to CL4
Precast concrete seating 3B suite level
SOD (incl set drains)) 3B suite level
Roofing 3B suite level
EXT studs framing 3B suite level
INT stud framing 3B suite level
EXT sheathing & vapor barrier 3B suite level
Install Sliding Glass Doors 3B suite level
MEP R/I walls 3B suite level
Install stucco 3B suite level
MEP R/I overhead 3B suite level
Storefronts 3B suite level
GWB hang 3B suite level
GWB finish 3B suite level
Prime & First Coat Paint Walls 3B suite level
Ceramic Tile & Epoxy coat 3B suite level
Ceiling Grid 3B suite level
Millwork & Trim 3B suite level
Fire Ext. Cabinets 3B suite level
Countertops 3B suite level
MEP Trim Out 3B suite level
A/V Equipment 3B suite level
Final coat paint 3B suite level
Ceiling Tiles 3B suite level
Flooring 3B suite level
Signage & Graphics 3B suite level
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 7 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
A3000 Wall & Door Protection 3B suite level1 14-Jan-16 14-Jan-16 35
A3010 Window Treatments 3B suite level 3 14-Jan-16 18-Jan-16 10
A2850 INT doors & hardware 3B suite level 4 18-Jan-16 22-Jan-16 19
A3640 Final Clean - 3B suite level 5 22-Jan-16 28-Jan-16 24
Suite Level 1B CL17 to CL30Suite Level 1B CL17 to CL30 110 17-Sep-15 04-Feb-16 19
A3650 Precast concrete seating 1B suite level5 17-Sep-15 24-Sep-15 7
A3370 Pour SOD (incl set drains) 1B suite level7 24-Sep-15 05-Oct-15 7
A3380 Roofing 1B suite level 7 05-Oct-15 14-Oct-15 20
A3390 EXT stud framing 1B suite level 5 14-Oct-15 21-Oct-15 21
A3400 INT stud framing 1B suite level 5 21-Oct-15 27-Oct-15 28
A3410 EXT sheathing & vapor barrier 1B suite level5 21-Oct-15 27-Oct-15 21
A3420 Install Sliding Glass Doors 1B suite level10 27-Oct-15 09-Nov-15 58
A3500 Storefronts 1B suite level 10 27-Oct-15 09-Nov-15 59
A3430 MEP R/I walls 1B suite level 7 27-Oct-15 04-Nov-15 21
A4720 Elec Rm F/P Eqpmnt pads - 1B suite level5 27-Oct-15 03-Nov-15 56
A4730 Elec Rm Set switchgear/panels/transfrmers - 1B suite level5 03-Nov-15 09-Nov-15 56
A3450 MEP R/I overhead 1B suite level 10 04-Nov-15 18-Nov-15 21
A3440 Install stucco 1B suite level 9 09-Nov-15 19-Nov-15 59
A4740 Elec Rm Conduit - 1B suite level 10 09-Nov-15 20-Nov-15 56
A3460 GWB hang 1B suite level 10 18-Nov-15 01-Dec-15 21
A4750 Elec Rm Feeders/Terminations - 1B suite level10 20-Nov-15 03-Dec-15 56
A3470 GWB finish 1B suite level 10 24-Nov-15 07-Dec-15 21
A4760 Elec Rm Permanent Power Insp - 1B suite level1 03-Dec-15 04-Dec-15 56
A4770 Elec Rm Permanent Power - 1B suite level1 04-Dec-15 07-Dec-15 56
A3480 Prime & First Coat Paint Walls 1B suite level5 07-Dec-15 14-Dec-15 21
A3490 Ceramic Tile & Epoxy coat 1B suite level5 07-Dec-15 14-Dec-15 53
A3510 Ceiling Grid 1B suite level 5 14-Dec-15 18-Dec-15 33
A3520 Millwork & Trim 1B suite level 8 14-Dec-15 23-Dec-15 21
A3530 Toilet Partitions & Accesories 1B suite level3 14-Dec-15 16-Dec-15 53
A3540 Fire Ext. Cabinets 1B suite level 1 14-Dec-15 15-Dec-15 30
A3550 Countertops 1B suite level 5 18-Dec-15 25-Dec-15 21
A3560 MEP Trim Out 1B suite level 5 18-Dec-15 25-Dec-15 33
A3570 A/V Equipment 1B suite level 7 23-Dec-15 31-Dec-15 46
A3590 Ceiling Tiles 1B suite level 5 25-Dec-15 31-Dec-15 36
A3600 Flooring 1B suite level 5 25-Dec-15 31-Dec-15 33
A3580 Final coat paint 1B suite level 4 25-Dec-15 30-Dec-15 21
A3610 Signage & Graphics 1B suite level 1 30-Dec-15 31-Dec-15 46
A3620 Wall & Door Protection 1B suite level1 30-Dec-15 31-Dec-15 46
A3630 Window Treatments 1B suite level 3 30-Dec-15 04-Jan-16 21
A3830 INT Doors & Hardware 1B suite level3 31-Dec-15 05-Jan-16 33
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
Wall & Door Protection 3B suite level
Window Treatments 3B suite level
INT doors & hardware 3B suite level
Final Clean - 3B suite level
04-Feb-16, Suite Level 1B CL17 to CL30
Precast concrete seating 1B suite level
Pour SOD (incl set drains) 1B suite level
Roofing 1B suite level
EXT stud framing 1B suite level
INT stud framing 1B suite level
EXT sheathing & vapor barrier 1B suite level
Install Sliding Glass Doors 1B suite level
Storefronts 1B suite level
MEP R/I walls 1B suite level
Elec Rm F/P Eqpmnt pads - 1B suite level
Elec Rm Set switchgear/panels/transfrmers - 1B suite level
MEP R/I overhead 1B suite level
Install stucco 1B suite level
Elec Rm Conduit - 1B suite level
GWB hang 1B suite level
Elec Rm Feeders/Terminations - 1B suite level
GWB finish 1B suite level
Elec Rm Permanent Power Insp - 1B suite level
Elec Rm Permanent Power - 1B suite level
Prime & First Coat Paint Walls 1B suite level
Ceramic Tile & Epoxy coat 1B suite level
Ceiling Grid 1B suite level
Millwork & Trim 1B suite level
Toilet Partitions & Accesories 1B suite level
Fire Ext. Cabinets 1B suite level
Countertops 1B suite level
MEP Trim Out 1B suite level
A/V Equipment 1B suite level
Ceiling Tiles 1B suite level
Flooring 1B suite level
Final coat paint 1B suite level
Signage & Graphics 1B suite level
Wall & Door Protection 1B suite level
Window Treatments 1B suite level
INT Doors & Hardware 1B suite level
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 8 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
A2180 Test & Balance HVAC 1B & 3B Suite level5 22-Jan-16 28-Jan-16 19
A3840 Final Clean - 1B suite level 5 29-Jan-16 04-Feb-16 19
Seating Bowl Walls & Risers 1B CL17 to CL31Seating Bowl Walls & Risers 1B CL17 to CL31 178 08-Jun-15 20-Jan-16 31
A3340 FTGs Seating Bowl & 1B DO walls 10 08-Jun-15 19-Jun-15 49
A2880 Conc Walls - Seat Bowl & Terraces, & 1B DO15 15-Jun-15 02-Jul-15 49
A2990 UG MEP / Drainage system 1B 5 05-Oct-15 12-Oct-15 10
A3660 Backfill & grading bowl 1B 5 12-Oct-15 16-Oct-15 10
A3670 P / P SOGs DO, Aisles, Platforms, Terraces 1B10 16-Oct-15 29-Oct-15 10
A3720 F / P Stepped Bowl 1B 25 29-Oct-15 01-Dec-15 10
A3680 Stairs - DO, Platforms, & Terraces 1B10 01-Dec-15 14-Dec-15 21
A2590 Railings 1B 15 14-Dec-15 01-Jan-16 31
A2550 Stadium Seating !B 15 01-Jan-16 20-Jan-16 31
Seating Bowl Walls & Risers 3B CL17 to CL0Seating Bowl Walls & Risers 3B CL17 to CL0 182 16-Jun-15 02-Feb-16 21
A3730 FTGs - Seat Bowl 3B 10 16-Jun-15 29-Jun-15 43
A3750 Conc Walls - Seat Bowl, & Terraces 3B15 22-Jun-15 10-Jul-15 43
A3740 UG MEP / Drainage system 3B 5 05-Oct-15 12-Oct-15 7
A3770 Backfill & grading bowl 3B 5 14-Oct-15 21-Oct-15 7
A3780 P / P SOGs DO, Aisles, Platforms, Terraces 3B10 21-Oct-15 03-Nov-15 7
A3790 F / P Stepped Bowl 3B 25 03-Nov-15 04-Dec-15 7
A3800 Stairs - DO, Platforms, & Terraces 3B10 14-Dec-15 25-Dec-15 21
A3820 Railings 3B 15 25-Dec-15 14-Jan-16 21
A3810 Stadium Seating 3B 15 14-Jan-16 02-Feb-16 21
Outfield Walls & Plazas CL0 to CL31Outfield Walls & Plazas CL0 to CL31 160 03-Jul-15 25-Jan-16 28
A1760 FTG OF Walls, Scoreboard, Batters Eye15 10-Jul-15 30-Jul-15 39
A1970 F/P OF Walls 15 23-Jul-15 12-Aug-15 43
A2210 FTG Keystone retaining wall 10 12-Aug-15 25-Aug-15 70
A3870 FTG OF Bar, OF Mast liights, Flag poles10 12-Aug-15 25-Aug-15 76
A3050 Lay Keystone blocks 15 19-Aug-15 07-Sep-15 70
A3860 Keystone wall drainage system 10 25-Aug-15 07-Sep-15 75
A3850 Backfill Keystone wall 5 01-Sep-15 07-Sep-15 70
A1840 Backfill OF walls 10 01-Oct-15 14-Oct-15 21
A2140 UG MEP OF Plaza 10 14-Oct-15 28-Oct-15 30
A1870 P / P SOG OF Concourse 15 04-Nov-15 24-Nov-15 23
A1960 Install Light Poles 15 24-Nov-15 14-Dec-15 23
A2130 Chain Link Fencing 10 14-Dec-15 25-Dec-15 23
A2310 Flag Poles 3 25-Dec-15* 30-Dec-15 23
A2320 Ornamental Fence & Gates 20 30-Dec-15 25-Jan-16 28
ScoreboardScoreboard 90 18-Sep-15 12-Jan-16 23
A2100 Scoreboard Steel Support 5 18-Sep-15 24-Sep-15 13
A3880 Scoreboard UG Electric & Data 5 24-Sep-15 01-Oct-15 93
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
Test & Balance HVAC 1B & 3B Suite level
Final Clean - 1B suite level
20-Jan-16, Seating Bowl Walls & Risers 1B CL17 to CL31
FTGs Seating Bowl & 1B DO walls
Conc Walls - Seat Bowl & Terraces, & 1B DO
UG MEP / Drainage system 1B
Backfill & grading bowl 1B
P / P SOGs DO, Aisles, Platforms, Terraces 1B
F / P Stepped Bowl 1B
Stairs - DO, Platforms, & Terraces 1B
Railings 1B
Stadium Seating !B
02-Feb-16, Seating Bowl Walls & Risers 3B CL17 to CL0
FTGs - Seat Bowl 3B
Conc Walls - Seat Bowl, & Terraces 3B
UG MEP / Drainage system 3B
Backfill & grading bowl 3B
P / P SOGs DO, Aisles, Platforms, Terraces 3B
F / P Stepped Bowl 3B
Stairs - DO, Platforms, & Terraces 3B
Railings 3B
Stadium Seating 3B
25-Jan-16, Outfield Walls & Plazas CL0 to CL31
FTG OF Walls, Scoreboard, Batters Eye
F/P OF Walls
FTG Keystone retaining wall
FTG OF Bar, OF Mast liights, Flag poles
Lay Keystone blocks
Keystone wall drainage system
Backfill Keystone wall
Backfill OF walls
UG MEP OF Plaza
P / P SOG OF Concourse
Install Light Poles
Chain Link Fencing
Flag Poles
Ornamental Fence & Gates
12-Jan-16, Scoreboard
Scoreboard Steel Support
Scoreboard UG Electric & Data
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 9 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
A2470 Install Score Board 10 30-Dec-15 12-Jan-16 23
LF TerraceLF Terrace 19 07-Oct-15 02-Nov-15 77
A3900 Backfill & Grading LF Terrace 3 07-Oct-15 12-Oct-15 23
A3970 FTG LF Terrace 2 12-Oct-15 14-Oct-15 23
A3910 UG MEP / Drainage LF Terrace 2 14-Oct-15 16-Oct-15 23
A3920 F / P LF Terrace 5 16-Oct-15 22-Oct-15 23
A3890 Aisle SOG LF Terrace 2 22-Oct-15 26-Oct-15 77
A3950 F / P Steps LF Terrace 3 26-Oct-15 29-Oct-15 77
A3930 Railings LF Terrace 2 29-Oct-15 02-Nov-15 77
LF BermLF Berm 26 07-Oct-15 10-Nov-15 87
A2520 Backfill & Grading LF Berm 2 07-Oct-15 09-Oct-15 28
A3960 FTG Wallls LF Berm 2 14-Oct-15 16-Oct-15 25
A3990 F / P Walls LF Berm 3 22-Oct-15 27-Oct-15 23
A3940 UG MEP / Drainage LF Berm 3 27-Oct-15 30-Oct-15 90
A4010 Railings LF Berm 2 02-Nov-15 04-Nov-15 77
A4000 Topsoil, irrigation, sod LF berm 5 04-Nov-15 10-Nov-15 87
Batter's EyeBatter's Eye 41 17-Sep-15 10-Nov-15 77
A2440 Structural Steel Batter Eye 5 17-Sep-15 24-Sep-15 15
A4040 CMU Batter Eye 10 24-Sep-15 07-Oct-15 23
A4020 Fencing & Windscreen Batter Eye 5 07-Oct-15 14-Oct-15 94
A4030 Railings Batter Eye 5 04-Nov-15 10-Nov-15 77
Outfield Bar & RestroomsOutfield Bar & Restrooms 72 25-Aug-15 25-Nov-15 76
A2560 CMU walls - OF Bar 5 25-Aug-15 01-Sep-15 76
A4060 Roof structure - OF Bar 5 01-Sep-15 07-Sep-15 76
A4050 UG MEP - OF Bar 4 07-Sep-15 11-Sep-15 76
A4080 SOG - OF Bar 5 11-Sep-15 17-Sep-15 76
A4090 INT Framing - OF Bar 3 17-Sep-15 22-Sep-15 76
A4150 EXT Doors & hardware - OF Bar 3 22-Sep-15 25-Sep-15 76
A4070 Exterior finish - OF Bar 15 25-Sep-15 15-Oct-15 89
A4100 MEP R / I walls & overhead - OF Bar10 25-Sep-15 08-Oct-15 76
A4110 INT wall finishes - OF Bar 5 08-Oct-15 15-Oct-15 76
A4170 Flooring - OF Bar 5 15-Oct-15 21-Oct-15 76
A4120 MEP trim out - OF Bar 5 21-Oct-15 28-Oct-15 76
A4140 Millwork & Casework - OF Bar 5 21-Oct-15 28-Oct-15 76
A4130 Toilet partitions & accessories - OF Bar3 28-Oct-15 30-Oct-15 76
A4160 Painting - OF Bar 4 30-Oct-15 05-Nov-15 76
A4180 Bar FF & E - OF Bar 15 05-Nov-15 25-Nov-15 76
OF Bar TerraceOF Bar Terrace 40 14-Oct-15 03-Dec-15 68
A4320 Backfill & Grading OF BAR Terrace 3 14-Oct-15 19-Oct-15 24
A4190 FTG terrace walls OF BAR Terrace 5 19-Oct-15 26-Oct-15 24
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
Install Score Board
02-Nov-15, LF Terrace
Backfill & Grading LF Terrace
FTG LF Terrace
UG MEP / Drainage LF Terrace
F / P LF Terrace
Aisle SOG LF Terrace
F / P Steps LF Terrace
Railings LF Terrace
10-Nov-15, LF Berm
Backfill & Grading LF Berm
FTG Wallls LF Berm
F / P Walls LF Berm
UG MEP / Drainage LF Berm
Railings LF Berm
Topsoil, irrigation, sod LF berm
10-Nov-15, Batter's Eye
Structural Steel Batter Eye
CMU Batter Eye
Fencing & Windscreen Batter Eye
Railings Batter Eye
25-Nov-15, Outfield Bar & Restrooms
CMU walls - OF Bar
Roof structure - OF Bar
UG MEP - OF Bar
SOG - OF Bar
INT Framing - OF Bar
EXT Doors & hardware - OF Bar
Exterior finish - OF Bar
MEP R / I walls & overhead - OF Bar
INT wall finishes - OF Bar
Flooring - OF Bar
MEP trim out - OF Bar
Millwork & Casework - OF Bar
Toilet partitions & accessories - OF Bar
Painting - OF Bar
Bar FF & E - OF Bar
03-Dec-15, OF Bar Terrace
Backfill & Grading OF BAR Terrace
FTG terrace walls OF BAR Terrace
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 10 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
A4200 F / P terrace walls OF BAR Terrace 7 27-Oct-15 04-Nov-15 23
A4210 UG MEP / Drainage OF BAR Terrace5 04-Nov-15 11-Nov-15 66
A4250 Final Backfill & grading OF BAR Terrace5 11-Nov-15 18-Nov-15 66
A4240 F / P Steps OF BAR Terrace 5 18-Nov-15 24-Nov-15 66
A4220 Railings OF BAR Terrace 3 24-Nov-15 27-Nov-15 66
A4230 Topsoil, irrigation, sod OF BAR Terrace5 27-Nov-15 03-Dec-15 68
RF BermRF Berm 42 14-Oct-15 07-Dec-15 66
A4260 Backfill & Grading RF Berm 3 14-Oct-15 19-Oct-15 95
A4290 UG MEP / Drainage RF Berm 3 19-Oct-15 22-Oct-15 95
A4280 F / P apron next to OF wall RF Berm2 04-Nov-15 06-Nov-15 84
A4300 Railings RF Berm 2 27-Nov-15 01-Dec-15 66
A4310 Topsoil, irrigation, sod RF berm 5 01-Dec-15 07-Dec-15 66
RF PorchRF Porch 40 14-Oct-15 03-Dec-15 68
A3700 Backfill & Grading RF Porch 3 14-Oct-15 19-Oct-15 29
A4330 FTG walls RF Porch 3 26-Oct-15 28-Oct-15 24
A4340 F / P walls RF Porch 5 28-Oct-15 04-Nov-15 24
A4270 UG MEP / Drainage RF Porch 5 04-Nov-15 11-Nov-15 81
A4350 P / P SOG RF Porch 3 11-Nov-15 13-Nov-15 81
A4360 Railings RF Porch 3 01-Dec-15 03-Dec-15 68
Field Maintenance AreaField Maintenance Area 157 03-Jul-15 20-Jan-16 31
A4370 Loading Dock Concrete Steps & Rail5 03-Jul-15 10-Jul-15 178
A4380 UG MEP / Drainage field access ramp15 24-Nov-15 14-Dec-15 31
A2300 P / P SOG Field access ramp 10 14-Dec-15 25-Dec-15 31
A2570 Fencing & Gates 15 25-Dec-15 13-Jan-16 31
A3690 Concrete material bins 5 25-Dec-15 31-Dec-15 43
A4390 Pipe bollards 3 31-Dec-15 05-Jan-16 43
A2250 Loading Dock Equip 5 13-Jan-16 20-Jan-16 31
Playing FieldPlaying Field 61 04-Dec-15 19-Feb-16 7
A2030 Field subsurface 15 04-Dec-15 23-Dec-15 7
A3070 Bowl collector field piping 10 17-Dec-15 30-Dec-15 7
A2270 Install Foul Poles 5 23-Dec-15 30-Dec-15 23
A2430 Field drainage piping 10 23-Dec-15 05-Jan-16 7
A2800 Field irrigation 12 30-Dec-15 14-Jan-16 7
A3060 Field AV equipment / wiring / devices15 12-Jan-16 01-Feb-16 23
A2290 Backstop Netting 5 14-Jan-16 20-Jan-16 31
A2830 Field rootzone 5 14-Jan-16 20-Jan-16 7
A2480 Padding walls & rails 10 20-Jan-16 02-Feb-16 7
A3080 Field clay surfaces 4 02-Feb-16 08-Feb-16 7
A2040 Sod Playing Field 5 08-Feb-16 15-Feb-16 7
A2280 Dugout equipment installation 5 15-Feb-16 19-Feb-16 7
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
F / P terrace walls OF BAR Terrace
UG MEP / Drainage OF BAR Terrace
Final Backfill & grading OF BAR Terrace
F / P Steps OF BAR Terrace
Railings OF BAR Terrace
Topsoil, irrigation, sod OF BAR Terrace
07-Dec-15, RF Berm
Backfill & Grading RF Berm
UG MEP / Drainage RF Berm
F / P apron next to OF wall RF Berm
Railings RF Berm
Topsoil, irrigation, sod RF berm
03-Dec-15, RF Porch
Backfill & Grading RF Porch
FTG walls RF Porch
F / P walls RF Porch
UG MEP / Drainage RF Porch
P / P SOG RF Porch
Railings RF Porch
20-Jan-16, Field Maintenance Area
Loading Dock Concrete Steps & Rail
UG MEP / Drainage field access ramp
P / P SOG Field access ramp
Fencing & Gates
Concrete material bins
Pipe bollards
Loading Dock Equip
19-Feb-16, Playing Field
Field subsurface
Bowl collector field piping
Install Foul Poles
Field drainage piping
Field irrigation
Field AV equipment / wiring / devices
Backstop Netting
Field rootzone
Padding walls & rails
Field clay surfaces
Sod Playing Field
Dugout equipment installation
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 11 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish Total Float
Main Entrance PlazaMain Entrance Plaza 95 16-Oct-15 16-Feb-16 11
A4400 FTGs Main plaza 5 16-Oct-15 23-Oct-15 11
A4410 UG MEP / Drainage Main plaza 7 23-Oct-15 02-Nov-15 11
A4420 F / P Walls Main plaza 10 02-Nov-15 13-Nov-15 11
A4480 Backfill & grading Main plaza 4 13-Nov-15 19-Nov-15 11
A1790 CMU Main plaza 12 19-Nov-15 07-Dec-15 10
A2330 Brick veneer & steps Main plaza 25 01-Dec-15 01-Jan-16 11
A2340 Curb & Gutter, Sidewalks, Aprons Main plaza10 08-Dec-15 21-Dec-15 16
A4450 Railings Main plaza 20 21-Dec-15 14-Jan-16 16
A4430 P / P SOG Main plaza 15 01-Jan-16 20-Jan-16 11
A4440 MEP fixtures & trimout Main plaza 7 20-Jan-16 29-Jan-16 14
A4470 Fencing & Gates 10 20-Jan-16 02-Feb-16 11
A4460 Landscape Plantings Main plaza 10 02-Feb-16 16-Feb-16 11
Close OutClose Out 29 22-Jan-16 01-Mar-16 0
A4790 Fire Inspection 1 22-Jan-16 25-Jan-16 28
A4800 Contractor's Punch List 10 01-Feb-16 12-Feb-16 0
A4820 Systems Training 3 01-Feb-16 04-Feb-16 20
A4810 Architect / Owner's Punch List 12 12-Feb-16 29-Feb-16 0
A4780 Owner Final Inspection 1 29-Feb-16 01-Mar-16 0
0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0
N D J F M A M J J A S O N D J F M A M J J A S O
16-Feb-16, Main Entrance Plaza
FTGs Main plaza
UG MEP / Drainage Main plaza
F / P Walls Main plaza
Backfill & grading Main plaza
CMU Main plaza
Brick veneer & steps Main plaza
Curb & Gutter, Sidewalks, Aprons Main plaza
Railings Main plaza
P / P SOG Main plaza
MEP fixtures & trimout Main plaza
Fencing & Gates
Landscape Plantings Main plaza
01-Mar-16, Close Out
Fire Inspection
Contractor's Punch List
Systems Training
Architect / Owner's Punch List
Owner Final Inspection
Spirit Communications Park
22-Apr-15 15:29
Actual Work
Remaining Work
Critical Rem...
Milestone
Page 12 of 12 Baseline DD 07 April 2015
© Oracle Corporation
Appendix B
Page 1
NON-COLLUSION AFFIDAVIT – ATTACHMENT D
State of __________________________________) County of _________________________________) ________________________________ being first duly sworn, deposes and says that:
(1) He is __________________________ of __________________________, the Respondent that has submitted the attached Proposal:
(2) He is fully informed respecting the preparation and contents of the attached Proposal and of all pertinent circumstances respecting such Proposal: (3) Such Proposal is genuine and is not a collusive or sham Proposal: (4) Neither the said Respondent nor any of its officers, partners, owners, agents, representatives, employees or parties in interest, including this affidavit, has in any way colluded, conspired, connived or agreed, directly or indirectly with any other Respondent, firm or person to submit a collusive or sham in connection with the Contract for which the attached Proposal has been submitted or to retain from proposing in connection with such Contract, or has in any manner, directly or indirectly, sought by agreement or collusion or communication or conference with any other Respondent, or to secure through any collusion, conspiracy, connivance or unlawful agreement any advantage against the City of Columbia, S.C. or any person interested in the proposed Contract; and (Signed)___________________________________
___________________________________ (Title)
Subscribed and sworn to before me this __________day of ______________, 20_____ ___________________________________________________