Page 1: West Seattle and Ballard Link Extensions

West Seattle and BallardLink Extensions

Seattle Planning Commission | 3.08.18

Page 2: West Seattle and Ballard Link Extensions

Representative project

Previous studies

Next steps

Agenda

Page 3: West Seattle and Ballard Link Extensions

• 3 counties: King, Pierce, Snohomish

• More than 3 million residents

• 51 cities

• 800,000 more people by 2040

Sound Transit district

Page 4: West Seattle and Ballard Link Extensions

• Identifies mode, corridor,

station areas

• Informs cost, schedule,

operating needs

Representative project

Page 5: West Seattle and Ballard Link Extensions

• Opening 2030

• Four elevated stations at SODO,

Delridge, Avalon and Alaska

Junction; one at-grade station at

Stadium

• New rail-only fixed span crossing

of the Duwamish River

• Length: 4.7 miles

West Seattle Link Extension

Page 6: West Seattle and Ballard Link Extensions

Ballard Link Extension

• Opening 2035

• Three elevated stations: Ballard,

Interbay, Smith Cove

• Six tunnel stations: Seattle Center,

South Lake Union, Denny, Westlake,

Midtown, International

District/Chinatown

• New rail-only movable bridge over

Salmon Bay

• Length: 7.1 miles

Page 7: West Seattle and Ballard Link Extensions

New Downtown Transit Tunnel EVERETT

EAST

LINK

WEST

SEATTLE

BALLARD

AIRPORT &

TACOMA

Page 8: West Seattle and Ballard Link Extensions

EVERETT

EAST

LINK

WEST

SEATTLE

BALLARD

AIRPORT &

TACOMA

New Downtown Transit Tunnel

Page 10: West Seattle and Ballard Link Extensions

Previous studies

Page 11: West Seattle and Ballard Link Extensions

Previous studies

Forward

Thrust1968, 1970

Seattle Monorail

Project2005

ST2 Long Range

Plan update2005

HCT corridor

studies2013–2014

ST3 Long Range

Plan update2014

ST3

System Plan2015–2016

Page 12: West Seattle and Ballard Link Extensions

Transit Expansion Study Ballard to Downtown

• City and Sound Transit partnership

• Supported Seattle Transit

Master Plan

• Supported ST Long-Range Planning

Page 13: West Seattle and Ballard Link Extensions

Transit Expansion Study Ballard to Downtown

• Studied five representative

alignments

• Included Light Rail and

Rapid Streetcar

Page 14: West Seattle and Ballard Link Extensions

South King CountyHCT Corridor Study

• Studied six alternatives

• Considered options to the

Junction, along Delridge and to

Burien and Renton

• Included light rail and BRT

Page 15: West Seattle and Ballard Link Extensions

Sound TransitLong Range Plan

Regional Transit Long-Range Plan

December 2014

Page 16: West Seattle and Ballard Link Extensions

system

ST3: Ballard to Downtown – Candidate Projects

C-01a C-01b C-01c C-01d

Page 17: West Seattle and Ballard Link Extensions

C-03bC-03a C-03c

ST3: West Seattle to Downtown – Candidate Projects

Page 18: West Seattle and Ballard Link Extensions

ST3 Draft Plan

At-grade on 15th Ave W

Included South Lake

Union Station

Page 19: West Seattle and Ballard Link Extensions

ST3 Final Plan

Elevated on 15th Ave W

Page 20: West Seattle and Ballard Link Extensions

Final plan

Sound Transit 3 (ST3) Plan

June 2016

Page 21: West Seattle and Ballard Link Extensions

Next steps

Page 22: West Seattle and Ballard Link Extensions

West Seattle project timeline

PUBLIC INVOLVEMENT PUBLIC INVOLVEMENT

Conversations withproperty owners

Groundbreaking

Construction updatesand mitigation

Safety education

Testing and pre-operations

PUBLIC INVOLVEMENT

Final route design

Final station designs

Procure and commission station and public art

Obtain land use and construction permits

PLANNING DESIGN CONSTRUCTION2017–2022 2022–2025 2025–2030

START OF

SERVICE

2016Alternatives development

Board identifies preferred alternative

Draft Environmental Impact Statement

Final Environmental Impact Statement

Board selects projectto be built

Federal Record of Decision

2030

Page 23: West Seattle and Ballard Link Extensions

Ballard project timeline

PUBLIC INVOLVEMENT PUBLIC INVOLVEMENT

Conversations withproperty owners

Groundbreaking

Construction updatesand mitigation

Safety education

Testing and pre-operations

PUBLIC INVOLVEMENT

Final route design

Final station designs

Procure and commission station and public art

Obtain land use and construction permits

PLANNING DESIGN CONSTRUCTION2017–2022 2023–2026 2027–2035

START OF

SERVICE

Alternatives development

Board identifies preferred alternative

Draft Environmental Impact Statement

Final Environmental Impact Statement

Board selects projectto be built

Federal Record of Decision

20352016

Page 24: West Seattle and Ballard Link Extensions

PUBLIC INVOLVEMENT

PLANNING DESIGN

20162019–2022

Draft Environmental

Impact Statement

Final Environmental

Impact Statement

Board selects project

to be built

Federal Record of

Decision

2017–2019

Alternatives

development

Board identifies

preferred alternative

Page 25: West Seattle and Ballard Link Extensions

PUBLIC INVOLVEMENT PUBLIC INVOLVEMENTPUBLIC INVOLVEMENT

Alternatives development process

LEVEL 1Alternatives development

LEVEL 2Alternatives development

LEVEL 3Alternatives development

PREFERRED

ALTERNATIVE*

Conduct early scoping

Study ST3 representative

project and alternatives

Screen alternatives

Early-2018 Mid-2018 Late-2018 / Early-2019 Early-2019

Technical analysis

Refine and screen

alternatives

Refine and screen

alternatives

Conduct Environmental

Impact Statement

(EIS) scoping

*The Sound Transit Board identifies preferred alternatives and other alternatives to study.

Page 26: West Seattle and Ballard Link Extensions

PUBLIC INVOLVEMENT PUBLIC INVOLVEMENTPUBLIC INVOLVEMENT

Alternatives development process

LEVEL 1Alternatives development

LEVEL 2Alternatives development

LEVEL 3Alternatives development

PREFERRED

ALTERNATIVE*

Conduct early scoping

Study ST3 representative

project and alternatives

Screen alternatives

Early-2018 Mid-2018 Late-2018 / Early-2019 Early-2019

Technical analysis

Refine and screen

alternatives

Refine and screen

alternatives

Conduct Environmental

Impact Statement

(EIS) scoping

*The Sound Transit Board identifies preferred alternatives and other alternatives to study.

Page 27: West Seattle and Ballard Link Extensions

Community engagement and collaboration

Page 28: West Seattle and Ballard Link Extensions

Community engagement and collaboration

Page 29: West Seattle and Ballard Link Extensions

Community engagement and collaboration

Page 30: West Seattle and Ballard Link Extensions

Community engagement and collaboration

Page 31: West Seattle and Ballard Link Extensions

Next steps

MarchEarly Scoping

• Stakeholder Advisory Group:

3/14 (Early Scoping feedback

summary)

• Early Scoping Summary

Report: late March

AprilLevel 1 screening

• Stakeholder Advisory Group:

4/17 (Level 1 evaluation results)

• Stakeholder Advisory Group:

4/25 (Level 1 recommendation)

• Neighborhood Forums:

beginning 4/21

MayLevel 1 screening

• Elected Leadership Group:

5/17 (Level 1 recommendation)

Page 32: West Seattle and Ballard Link Extensions

soundtransit.org/wsblink

Page 33: West Seattle and Ballard Link Extensions

New approach to project development

Page 34: West Seattle and Ballard Link Extensions

• System-wide investment

New Downtown Transit Tunnel

Page 35: West Seattle and Ballard Link Extensions

Everett to West Seattle

via Downtown Seattle Transit Tunnel

Everett to Downtown Redmond

via Downtown Seattle Transit Tunnel

Ballard to Tacoma via new rail-only tunnel

Operating plan

Page 36: West Seattle and Ballard Link Extensions

Spinesegmentation

• Splits long trip from

Tacoma to Everettvs.E

VE

RE

TT

TA

CO

MA

2 H

OU

RS

Page 37: West Seattle and Ballard Link Extensions

Balancedloads

• Balances passenger loads,

enabling future growth

• All users benefit from core

capacity expansion

vs.

EVERETT

TACOMA

RE

DM

ON

D

WE

ST

SE

AT

TL

E

Page 38: West Seattle and Ballard Link Extensions

Maintenance capacity: 2030

• West Seattle Extension

dependent on new facility

in the south

TACOMA

WESTSEATTLE

Federal Way

Page 39: West Seattle and Ballard Link Extensions

Maintenance capacity: 2041

• Forest Street (104 vehicles)

• Bellevue (96 vehicles)

• New facility in the south

(~ 152 vehicles)

• New facility in the north

(~108 vehicles)