20

What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks Project InitiationJune 2005 Existing ConditionsOct. 2005 Planning

Embed Size (px)

Citation preview

Page 1: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning
Page 2: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

What is the S-48 Corridor?What is the S-48 Corridor?Study Area

Page 3: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

What’s Happened So Far?What’s Happened So Far?Previous Tasks

Project Initiation June 2005

Existing Conditions Oct. 2005

Planning Charrette Nov. 2005

Issues Identification Dec. 2005

Preliminary Alternatives Feb. 2006

Project Initiation June 2005

Existing Conditions Oct. 2005

Planning Charrette Nov. 2005

Issues Identification Dec. 2005

Preliminary Alternatives Feb. 2006

Page 4: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

What Did We Discover?What Did We Discover?Issues Identified

Vehicular Travel Issues• Significant congestion during peak

commuter hours S-48 serves as the primary

connection between Chapinand I-26

• Lack of parallel routes and minimal connectivity

• “Bottleneck” at Chapin High School• Future failure of all intersections• Ninety-degree turn at western end

of Columbia Avenue

Vehicular Travel Issues• Significant congestion during peak

commuter hours S-48 serves as the primary

connection between Chapinand I-26

• Lack of parallel routes and minimal connectivity

• “Bottleneck” at Chapin High School• Future failure of all intersections• Ninety-degree turn at western end

of Columbia Avenue

Page 5: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Vehicular Travel Issues• Through traffic at Chapin

town center• Offset intersection of Peak

and Clark Streets• Significant queuing where

left turns are frequent• Difficult truck

ingress/egress to Ellett Brothers

Vehicular Travel Issues• Through traffic at Chapin

town center• Offset intersection of Peak

and Clark Streets• Significant queuing where

left turns are frequent• Difficult truck

ingress/egress to Ellett Brothers

What Did We Discover?What Did We Discover?Issues Identified

Page 6: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Pedestrian & Bicycle Issues• Excessive travel speeds• Lack of sidewalks and connections

between land uses• Minimal controlled

pedestrian crossings• Vehicular disregard for

pedestrian/bicycle right-of-way and safety

• Lack of elements to designate a bicycle-friendly environment

Pedestrian & Bicycle Issues• Excessive travel speeds• Lack of sidewalks and connections

between land uses• Minimal controlled

pedestrian crossings• Vehicular disregard for

pedestrian/bicycle right-of-way and safety

• Lack of elements to designate a bicycle-friendly environment

What Did We Discover?What Did We Discover?Issues Identified

Page 7: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Transit Issues• SmartRide park-and-ride

lot is limited by size and perceived safety

• Lack of ped/bike connections between SmartRide park-and-ride lot and Town of Chapin

• Absence of transit to majority of corridor

Transit Issues• SmartRide park-and-ride

lot is limited by size and perceived safety

• Lack of ped/bike connections between SmartRide park-and-ride lot and Town of Chapin

• Absence of transit to majority of corridor

What Did We Discover?What Did We Discover?Issues Identified

Page 8: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Railroad Corridor Issues• Perpendicular intersection of

S-48 and railroad• Queuing of westbound traffic

waiting for trains creates difficult left-turn movement and traffic backups across rail line

• Numerous at-grade rail crossings

• Railroad corridor acts as barrier

Railroad Corridor Issues• Perpendicular intersection of

S-48 and railroad• Queuing of westbound traffic

waiting for trains creates difficult left-turn movement and traffic backups across rail line

• Numerous at-grade rail crossings

• Railroad corridor acts as barrier

What Did We Discover?What Did We Discover?Issues Identified

Page 9: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Land Use Issues• Large amount of vacant

land with the potential to build out in a low density pattern

• Grouped incompatible uses• Lack of design standards• Eroding community

character• Existing development

located in close proximity to roadway

Land Use Issues• Large amount of vacant

land with the potential to build out in a low density pattern

• Grouped incompatible uses• Lack of design standards• Eroding community

character• Existing development

located in close proximity to roadway

What Did We Discover?What Did We Discover?Issues Identified

Page 10: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Preliminary Alternatives – Vehicular TravelWhat’s Being Considered?What’s Being Considered?

Dedicated turn lanes, traffic signals, and correction of geometric deficiencies at intersecting streets

New, localized east/west linkages

New circulation and connections within Chapin High School property

Dedicated turn lanes, traffic signals, and correction of geometric deficiencies at intersecting streets

New, localized east/west linkages

New circulation and connections within Chapin High School property

Page 11: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Preliminary Alternatives – Vehicular TravelWhat’s Being Considered?What’s Being Considered?

Potential for Redesigned Circulation and Access at Chapin High School

Page 12: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Preliminary Alternatives – Vehicular Travel

Widen S-48 to three lanes beginning at Chapin Road and transition to five lanes

Construct northern and/or southern connector

New interchange(s) with I-26 with appropriate roadway improvements

Widen S-48 to three lanes beginning at Chapin Road and transition to five lanes

Construct northern and/or southern connector

New interchange(s) with I-26 with appropriate roadway improvements

What’s Being Considered?What’s Being Considered?

Page 13: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Preliminary Alternatives – Vehicular TravelWhat’s Being Considered?What’s Being Considered?

Potential for Connectors and Interchanges

Page 14: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Preliminary Alternatives – Pedestrian & Bicycle Travel

Spot improvement or replacement of sidewalks and addition of ADA ramps

High visibility crosswalks with limited ITS elements

Pedestrian connections between land uses

Sidewalks throughout corridor Bicycle lanes throughout

corridor Streetscape improvements

Spot improvement or replacement of sidewalks and addition of ADA ramps

High visibility crosswalks with limited ITS elements

Pedestrian connections between land uses

Sidewalks throughout corridor Bicycle lanes throughout

corridor Streetscape improvements

What’s Being Considered?What’s Being Considered?

Page 15: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Preliminary Alternatives – Transit

Pedestrian and bicycle connections between park-and-ride, corridor, and town center

Pedestrian and bicycle connections between park-and-ride, corridor, and town center

What’s Being Considered?What’s Being Considered?

Page 16: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Preliminary Alternatives – Railroad Corridor

Extend Columbia Avenue to St. Peter’s Church Road and grade separate crossing of railroad

Extend Columbia Avenue to St. Peter’s Church Road and grade separate crossing of railroad

What’s Being Considered?What’s Being Considered?

Page 17: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Preliminary Alternatives – Vehicular TravelWhat’s Being Considered?What’s Being Considered?

Potential for Railroad Grade Separation

Page 18: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Preliminary Alternatives – Land Use

Increase coordination between approval agencies

Refine regs to encourage denser development with a mix of uses

Street and sidewalk system planand right-of-way dedicationrequirement

Performance standardstargeting improved multimodalaccess and interconnectivityof parcels

Impact fees

Increase coordination between approval agencies

Refine regs to encourage denser development with a mix of uses

Street and sidewalk system planand right-of-way dedicationrequirement

Performance standardstargeting improved multimodalaccess and interconnectivityof parcels

Impact fees

What’s Being Considered?What’s Being Considered?

Page 19: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Further Refine and Develop Alternatives

Develop Recommendations and Implementation Plan

Public Information Meeting #3 (April 2006)

Issue S-48 Columbia Avenue Corridor Study Report (May 2006)

Further Refine and Develop Alternatives

Develop Recommendations and Implementation Plan

Public Information Meeting #3 (April 2006)

Issue S-48 Columbia Avenue Corridor Study Report (May 2006)

ScheduleWhat’s Next?What’s Next?

Page 20: What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct. 2005  Planning

Give Feedback and Ask Questions Tonight• What do think about the Preliminary Alternatives?

Fill Out a Comment Sheet Tonight Mail/Email/Fax Your Comments

• Phone: 376-5390 Fax: 376-5394• Email: [email protected]• Blog: www.centralmidlands.org/blog.asp• Mail: 236 Stoneridge Drive, Columbia, SC 29210

Give Feedback and Ask Questions Tonight• What do think about the Preliminary Alternatives?

Fill Out a Comment Sheet Tonight Mail/Email/Fax Your Comments

• Phone: 376-5390 Fax: 376-5394• Email: [email protected]• Blog: www.centralmidlands.org/blog.asp• Mail: 236 Stoneridge Drive, Columbia, SC 29210

Your Continued ParticipationWhat are We Asking Tonight?What are We Asking Tonight?

Thank You for Your Participationin this Important and Exciting Project!

Thank You for Your Participationin this Important and Exciting Project!