Page 1: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

White Creek Rd over Little White CreekBridge Replacement Project

Public MeetingApril 16, 2013

Page 2: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

2

Project Team

Town of Hoosick• Louis Schmigel – Highway Superintendent• Keith Cipperly – Town Supervisor

Creighton Manning Engineering, LLP• Charles Tutunjian, PE – Project Manager• Tom Barrell, PE – Project Engineer• Alex Brown, IE – Assistant Project Engineer

Page 3: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

3

Meeting Agenda• Introduce the project team• Project Overview Project goals and purpose Project alternatives Existing conditions Recommended alternative

• Next steps• Public Questions and Comments Receive public input about the project Address questions the community has about the project

Page 4: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

4

Project Location

Page 5: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

5

Design Report

• Project Identification, Needs and Objectives

• Preliminary Alternatives ‐ Engineering Geometrics, Traffic, Safety, Drainage, Utilities, Right‐of‐Way, Pedestrians, 

Costs

• Environmental, Social and Economic Considerations Environmental – Historical resources, Air Quality, Noise, Energy

Social ‐ Planning, Community, Emergency Services, Social Groups

Economic – Local Economy, Highway related businesses, Established Business Districts

Indirect and Secondary Impacts

• Evaluation and Comparison of Alternatives

Page 6: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

6

Project Goals

• Increase the structural capacity of the crossing• Provide a structure with a 50‐year (minimum) design life 

• Improve roadway geometry

Page 7: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

7

Alternatives

• Do Nothing (Null Alternative)• Alternative 1 Complete Replacement on Improved Alignment

• Alternative 2 Superstructure Replacement

Page 8: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

8

Existing Conditions• Deteriorated bridge deck• Deteriorated stringers• Load posted structure

Page 9: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

9

Existing Conditions• Deteriorated Substructure • Erosion behind wingwall• Non‐standard pipe bridge rail

• Broken bridge rail (safety hazard)

Page 10: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

10

Existing Conditions

• Uneven, cracked, and patched pavement

• Substructures constrict stream

Page 11: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

11

Which Alternative is Preferred?

Alternative 1 – Complete Replacement Removes kink in road and improves roadway geometry50‐year design lifeNo load posting

Page 12: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

12

Alternative 1 – Complete Replacement

Page 13: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

13

Alternative 1 – Complete Replacement

Page 14: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

14

Alternative 1 – Complete Replacement

• Precast Concrete Con‐Span Arch Elevation

Page 15: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

15

Alternative 1 – Complete Replacement

• Top of roadway view

Source: Google Earth image of Stone Way N in Seattle, WA

Page 16: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

16

Detour

• Project will be built in one stage• If project were built in two stages, construction cost would be approximately 25% more

• Traffic will be detoured along Telford Rd• Telford Rd will be ½ mile longer commute

Page 17: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

17

Right of Way

• Temporary easements will be required to accommodate construction activities

• Permanent easements will be required so the town can have access to maintain the structure

• Easements will extend up to 50 ft from the edge of the existing road

• All disturbed areas will be reconstructed with topsoil and seed

Page 18: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

18

Project Funding

Construction Cost:• Approximately $850,000

Funding Breakdown:• 80% Federal• 20% Local 15% New York State 5% Town of Hoosick

Page 19: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

19

Schedule / Next Steps

• Incorporate public comments into Alternatives• Final Design Report – May 2013• Design Approval – June 2013• ROW Acquisitions Complete – December2013• Detailed Design Complete – December 2013• Advertise for Construction – February 2014• Construction Start – May 2014

Page 20: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

20

Questions?

• General comments or questions?• Specific concerns can be addressed individually.• You are encouraged to take a comment form and submit it tonight, via email, or regular mail.

Page 21: White Creek Rd over Little White Creek - Town of Hoosick ...townofhoosick.org/pdf2013/Public Meeting Presentation 4-16-13.pdfProject Team Town of Hoosick • Louis Schmigel–Highway

21

We appreciate your time.