Upload
eric-romanowski
View
77
Download
0
Embed Size (px)
Citation preview
P a g e |
Wind Turbine Design
Report
Members:Matthew Boles
Caleb Henry
Eric Romanowski
P a g e |
Table of Contents
Introduction......................................................................................................................................1
Abstract........................................................................................................................................1
Customer Needs...........................................................................................................................2
Design Summary.............................................................................................................................3
Prototype One..................................................................................................................................4
Concept Generation and Selection...............................................................................................4
Base Design..............................................................................................................................4
Table 1: Base Design Decision Matrix.....................................................................................5
Blade Design............................................................................................................................7
Table 2: Blade Design Decision Matrix for Prototype One.....................................................7
Selected Design for Prototype One............................................................................................10
Final Assembly..........................................................................................................................11
Figure 1: Full assembled CAD Drawing - Prototype One.....................................................11
Square Base:...............................................................................................................................12
Figure 2: Square Base Drawing..............................................................................................12
Main Shaft..................................................................................................................................13
Figure 3: Shaft Drawing.........................................................................................................13
Motor Holder..............................................................................................................................14
Figure 4: Motor Holder Drawing...........................................................................................14
Motor..........................................................................................................................................15
Figure 5: Motor Drawing.......................................................................................................15
Tri-Force Blade..........................................................................................................................16
Figure 6: Tri-Force Blade Drawing........................................................................................16
Prototype Two...............................................................................................................................17
P a g e |
Concept Generation and Selection.............................................................................................17
Blade Design..........................................................................................................................17
Table 3: Blade Design Decision Matrix for Prototype Two..................................................18
Selected Design for Prototype Two...........................................................................................19
Final Assembly..........................................................................................................................20
Figure 7: Full assembled CAD Drawing – Prototype Two....................................................20
Square Base................................................................................................................................21
Figure 8: Square Base Drawing..............................................................................................21
Main Shaft..................................................................................................................................22
Figure 9: Main Shaft Drawing................................................................................................22
Motor Holder..............................................................................................................................23
Figure 10: Motor Holder Drawing.........................................................................................23
Motor Attachment......................................................................................................................24
Figure 11: Motor Attachment Drawing..................................................................................24
Adapted Water Wheel Blade......................................................................................................25
Figure 12: Adapted Water Wheel Blade Drawing.................................................................25
Prototype Three.............................................................................................................................26
Concept Generation and Selection.............................................................................................26
Base Design............................................................................................................................26
Table 4: Base Design Decision Matrix for Prototype Three..................................................27
Blade Design..........................................................................................................................28
Table 5: Blade Design Decision Matrix for Prototype Three................................................28
Selected Design for Prototype Three.........................................................................................30
Final Assembly..........................................................................................................................31
Figure 13: Full assembled CAD Drawing - Prototype Three.................................................31
P a g e |
Square Base................................................................................................................................32
Figure 14: Square Base Drawing............................................................................................32
Base Supports.............................................................................................................................33
Figure 15: Base Support #1 Drawing.....................................................................................33
Figure 16: Base Support #2 Drawing.....................................................................................33
Support Tail................................................................................................................................34
Figure 17: Support Tail Drawing...........................................................................................34
Main Shaft..................................................................................................................................35
Figure 18: Main Shaft Drawing..............................................................................................35
Torque Support..........................................................................................................................36
Figure 19: Torque Support Drawing......................................................................................36
Motor Mount..............................................................................................................................37
Figure 14: Motor Mount Drawing..........................................................................................37
Swept Tri-blade..........................................................................................................................38
Figure 20: Swept Tri-Blade Drawing.....................................................................................38
Test Performance for Prototype One.........................................................................................39
Test Performance for Prototype Two.........................................................................................40
Test Performance for Prototype Three.......................................................................................41
Conclusion.....................................................................................................................................42
Budgets..........................................................................................................................................43
Budget for Prototype One..........................................................................................................43
Table 6: Budget for Prototype One........................................................................................43
Budget for Prototype Two..........................................................................................................43
Table 7: Budget for Prototype Two........................................................................................43
Budget for Prototype Three........................................................................................................44
P a g e |
Table 8: Budget for Prototype Three......................................................................................44
Mass of Turbine.............................................................................................................................45
Mass of Turbine Prototype One.................................................................................................45
Table 9: Mass of Turbine One................................................................................................45
Mass of Turbine Prototype Two................................................................................................45
Table 10: Mass of Turbine Two.............................................................................................45
Mass of Turbine Prototype Three..............................................................................................46
Table 11: Mass of Turbine Three...........................................................................................46
Appendices....................................................................................................................................47
Appendix A: Generator Specifications......................................................................................47
Appendix B: Measured Wind Speeds........................................................................................48
Works Cited...................................................................................................................................49
P a g e |
IntroductionThis section will introduce the Wind Turbine Project. This includes the abstract and the customer
needs which forms the basis of the project.
Abstract
The problem that must be addressed is the design and construction of a wind turbine that
is light, inexpensive, and effective at producing power. The first prototype has been based on
similar designs used within the industry using a singular tower and the generator mounted at the
top of the structure with the propeller. The goal of the first prototype was to mimic the
effectiveness and strength of the most commonly produced wind turbine. The cost of the first
prototype would cost approximately $8.54. The total mass of the wind turbine was
approximately 284.6 grams. The base of the wind turbine was very effective. This means that it
did not falter throughout the duration of the three minute test. The blades, however, only created
a maximum of .0014 watts, which is very inefficient. The first prototype would not be
recommended due to a lack of power produced and a large cost compared to the poor power
output.
The second prototype was based on a paddle boat paddle system which was thought to be
very productive at utilizing air to turn the generator. While the second prototype succeeded at
reducing the cost, it added both weight and reduced the number of watts produced. The total cost
of the turbine was $3.93 which is much better than the first prototype. The total mass of the
second turbine was approximately 361.0 grams. It produced a lower amount of watts producing
only .00051 watts which is much less than the first prototype. The second prototype would not be
recommended due to a large mass and very low power output.
The third prototype used a swept tri-blade design that was based on the first prototype but
with a way to catch and utilize more wind to its advantage. The third prototype improved every
aspect of the turbine and thus the group recommends this prototype be used. The turbine mass
totaled only 254.4 grams which is lighter than the previous turbines while not compromising
stability. The cost was also much less than the previous turbines, totaling only $3.18 which is
one-third of the second prototypes cost. It also improved upon the power output, outputting .615
P a g e |
watts, which is approximately a 500% increase from the first prototype. It is for the decrease in
cost, weight, and an increase in power output that the group recommends the third prototype.
Customer Needs
The customer requires a wind turbine that is freestanding, functions without issue for
three minutes, and generates power. The customer is also interested in three other aspects that
should be incorporated into the design of the turbine. The turbine should be lightweight which
will help the customer transport and set up the wind turbine. It should also have a low cost which
will allow the customer to purchase more wind turbines or increase profitability of the purchased
turbines. Last but not least, the turbine should have a high efficiency which will allow for fewer
turbines to be required, thus saving the customer money. Part of the turbine should also be built
using either a 3D printer, the Torchmate, or the laser cutter.
P a g e |
Design SummaryThe purpose of the design summary is to address the design of the prototypes and explain
the decisions pertaining to the aspects of the turbine. The design summary contains all possible
solutions that were considered and the reasoning that the designs were chosen and the potential
effectiveness to the overall design. It includes both the entire base design as well as various blade
designs that were considered to be potential contenders to be included in the first design
prototype.
P a g e |
Prototype OneThis section will discuss all aspects pertaining to prototype one.
Concept Generation and Selection
The purpose of the concept generation and selection is to eliminate potentially poor
design ideas before they are attempted as prototypes. Thus, this section will focus on various
ideas, many of which are not incorporated in the prototype.
Base Design
The group has decided to make a decision matrix considering the following elements:
constrains blade possibilities, cost, simple assembly, stability, and weight. The base should allow
for multiple different types of fan blades, but if the base lowers the choices of blades, then it
loses value. Cost is also highly rated because the higher the cost for the producer; the higher the
cost for the consumer. A simple assembly, simple meaning quick and does not require much
effort to build, will allow for us to develop more prototypes in less time if the idea does fail.
Stability is the most valuable element to our decision matrix. The project will fail immediately if
the project topples and falls. This structure and its strength begins at the base. Weight is another
important factor in the group’s decision matrix. The less the structure weights; the easier it will
be to transport the turbine.
P a g e |
Table 1: Base Design Decision Matrix
Decision
Matrix
Idea 1 – Long
quad base
Idea 2 –
Pyramid base
Idea 3 –
Wire
Idea 4 – Big Circle,
Little Square
Constrains Blade
Possibilities/Motor Mount - 15
2 3 4 4
Cost – 20 4 3 3 4
Simple Assembly – 15 4 2 3 4
Stability – 25 2 4 4 3
Weight – 20 4 3 4 4
Total Points 300 295 355 355
Idea one scored 300 points overall. The aesthetics of the base are standard to a wind
turbine and thus scored in the middle of the rubric. In terms of motor mounting capabilities, it
scored below average due to a limited amount of mounting options. This is in contrast to the
cost, which is relatively low, allowing it to score high. It also scored high in simplicity due to the
cross base design and the few pieces required. It did, however, score low for stability because of
the lack of area covered and few supports preventing wobbling, though the weight scored a four
because of the few pieces needed.
Idea two scored 295 points overall. It had acceptable mounting abilities for the motor.
Due to the extra material needed for the pyramid, it has an average cost compared to the others.
Due to the more complicated design of the base, it scores a 2 on the ease of assembly. It is
because of the extra material, however, that it scores well with stability due to it taking less space
to be stable, which also is a downside for the weight, which is at an average projection.
Idea three scored the highest with 355 points overall. It has an above average amount of
motor mounting options. It also features average cost and assembly specifications due to the
P a g e |
amount of parts involved in the structure. The wire design does feature exceptional stability and
a low weight from the hollow base and rectangle design.
Idea four scored the highest as well with an overall score of 355. The number of motor
mounting positions placed it around average adaptability. Because of the large amount of
material used, it had an average low cost though it features a simple assembly, being a base with
a pole, allowing it to score high in that regard. Both the stability and weight were scored as
above average because of the size of the base, though those features contribute to the positive
attributes of the design (Contech Engineered Solutions n.d.).
P a g e |
Blade Design
To determine the best blade, a decision matrix has been created considering the following
elements: adaptability, cost, simple assembly, projected efficiency, and weight. The adaptability
of a blade is important because it can allow for various arrangements as well as allowing the base
to change around it. The cost is also important to consider because it can be a determinant of
whether the customer will choose to purchase the wind turbine. A simple assembly can allow
maintenance to be done fast as well as allow a company to build more turbines in less time. The
efficiency of the system, and thus the blades, are easily the most important aspect of a turbine
because it allows the motor to generate the most power. The weight is also important for all
aspects of the machine because it affects the ability to transport the turbine as well as adds extra
unneeded force to the base.
Table 2: Blade Design Decision Matrix for Prototype One
Decision
Matrix
Idea 1 – Tri
Blade
Idea 2 – River
Wheel
Idea 3 – Flat shovel
blades
Idea 4 – Curved
Shovel
Adaptability - 15 3 1 3 3
Projected Cost - 20 4 1 2 3
Simple Assembly –
15
4 4 3 3
Efficiency - 25 4 3 2 3
Weight – 20 4 1 2 3
Total Points 365 190 220 285
The adaptability of the blades is important because of the implications it can have on the
base and the efficiency of the turbine. Idea one, three, and four scored in the middle of the
possible points for adaptability because while they can be slightly adjusted after being built and
P a g e |
tweaked without much effort, the designs do not have the ability to conform immediately to the
group’s desire. Idea two scored the lowest out of the four designs due to it needing a specific
base and can only have an orientation in relation to the base.
Cost of a machine is also important to consider while building a wind turbine and the cost
of the propeller can be a significant cost that will eventually be passed down to a consumer.
Assuming all ideas were to be produced of the same material, the least costly idea would be idea
one because of the lack of material that would be used in the production. The next least costly
idea would be number four because the propeller's fin density would not be as high as the
remaining two options. Ideas two and three come in a close last and second to last place due to
the extra material that is used with each design, thus exponentially increasing the cost of both
propellers.
A simple assembly of the propeller to the base is very important to the overall design of
turbine because it allows for changes to be made quickly and without money being lost to time.
Both idea one and two’s propellers are relatively easy to assemble due to a simpler design which
is horizontal in nature. Ideas 3 and 4 are somewhat more complicated due to a vertical mounting
system which can complicate the overall base design.
The projected efficiency is possibly the most important aspect of the design because it
determines the power output by the motor. The tri-blade design is regarded as one of the most
efficient designs within the wind turbine industry and thus scored the highest out of the four
ideas (Gurit n.d.). Idea three and four closely follow with idea two being based off of an old
steam boat propeller, it would not face as much opposing wind thus increasing its efficiency over
the remaining two designs. Idea four would also be efficient due to the curve of the blade,
allowing the opposing air flow to pass over it with more ease than a non-curved blade. Idea three
scores very low due to the straight edge of the blade which causes more air disruption and also
catches more opposing air, reducing the effectiveness of the design.
The weight of the propeller is a determinant factor to the design of a propeller because of
the implications it has, not only structurally, but also when the turbine has to be transported. Idea
one scored the highest in the weight category due to the lack of material that is used. Idea four is
similar to idea one but uses slightly more material in comparison, as does idea three in
comparison to idea four. Idea two, however, would be the heaviest because of the extravagant
design that uses much more material than the others.
P a g e |
The first prototype tested used the Tri Blade design due to it having a projected high
effectiveness for producing power.
P a g e |
Selected Design for Prototype One
The purpose of the Selected Design Concept Discussion is to describe the proposed plan
to develop our first prototype. This section will discuss the square base, the shaft, the motor
holder, the motor, and the Tri-Force Blade design.
P a g e |
Final Assembly
Figure 1: Full assembled CAD Drawing - Prototype One
P a g e |
Square Base:
Figure 2: Square Base Drawing
The square base is a simple portion of the design. The shape will allow for equal
balancing in all directions. In the case that the motor needs to be rotated to catch a wind, the
square base will pose no threat to a change in direction. The square will be created out of half
inch cardboard. We expect that the price of a full 30” X 40”cardboard sheet is $1.69 from
Utrecht Art Supplies (Utrecht n.d.). Though the design is simple, the large size of the lofty
material will allow it to prevent tipping in the winds.
P a g e |
Main Shaft
Figure 3: Shaft Drawing
The shaft is a hollow cylinder that is designed to fit directly into the center of the square
base. This piece will be made of 3/4 thick PVC. The piece is 431.8mm to catch the strongest
winds that was recorded in the wind speed table. This part weighs enough to hold the cardboard
square down, but not enough to destabilize the generally low weight turbine. The PVC pipe has
been purchased through PVC Fittings Online for $3.91 (PVC Fittings Online n.d.). The
cylindrical shape of the PVC shaft will allow for winds to bend around the structure unlike a
rectangular face. This will benefit overall stability in the base and will not hamper the wind
speeds on the turbine blades.
P a g e |
Motor Holder
Figure 4: Motor Holder Drawing
The motor holder was designed for the purpose of transitioning a PVC pipe into a
comfortable setting for the motor. The motor holder fits directly into the PVC pipe hole and
snuggly fits the motor directly into the slot. The motor holder will be created out of ABS plastic
using a 3-D printer, which will fufill our machine use requirement. ABS plastic costs
approximately $30 per kilogram. The final product weighs 37.7g which would cost
approximately $1.13.
P a g e |
Motor
Figure 5: Motor Drawing
The motor was measured so that it will have a perfect fit into the motor holder. The Tri-
Force blade used an interference fit to slide onto the motor’s axle. The figure shows a modeled
version of the motor that was provided for testing. Though the technical drawings look bare, two
wires stick out the rear end of the motor, so that they can be connected to a voltometer or another
power measuring utensil. This will remain the design for all remaining prototypes.
P a g e |
Tri-Force Blade
Figure 6: Tri-Force Blade Drawing
The Tri-Force blade is very similar to designs commonly used in industry. The propeller
has been 3D printed out of ABS plastic to ensure a light weight and low cost. It has been
designed to have a curvature that can slice thorugh the air as well as catch the wind to produce
power. The Tri-Force Blade follows the same pricing for the motor holder at approximately $30
per kilogram. The blade’s mass is 13.9 grams so the total cost for the Tri-Force blade is $0.42.
These blades are low cost and low weight; they also are expected to have a generally high power
output due to the frequent usage of these blades.
P a g e |
Prototype TwoThis section will discuss all aspects pertaining to prototype two.
Concept Generation and Selection
The purpose of the concept generation and selection is to eliminate potentially poor
design ideas before they are attempted as prototypes. Thus, this section will focus on various
ideas, many of which are not incorporated in the prototype. The group felt that the base did not
need modified or redesigned from prototype one and will remain the same for the second
prototype.
Blade Design
To determine the best blade, a decision matrix has been created considering the following
elements: adaptability, cost, simple assembly, projected efficiency, and weight. The adaptability
of a blade is important because it can allow for various arrangements as well as allowing the base
to change around it. The cost is also important to consider because it can be a determinant of
whether the customer will choose to purchase the wind turbine. A simple assembly can allow
maintenance to be done fast as well as allow a company to build more turbines in less time. The
efficiency of the system, and thus the blades, are easily the most important aspect of a turbine
because it allows the motor to generate the most power. The weight is also important for all
aspects of the machine because it affects the ability to transport the turbine as well as adds extra
unneeded force to the base.
P a g e |
Table 3: Blade Design Decision Matrix for Prototype Two
Decision
Matrix
Idea 1 – Adapted
River Wheel
Idea 2 – River
Wheel
Idea 3 – Flat
shovel blades
Idea 4 – Curved
Shovel
Adaptability - 15 3 1 3 3
Projected Cost -
20
3 1 2 3
Simple Assembly
– 15
3 4 3 3
Efficiency - 25 4 3 2 3
Weight – 20 3 1 2 3
Total Points 310 190 220 285
Three of the original blade ideas remained from prototype one and a new one was
subsequently created and chosen. The adapted river wheel was scored higher than the original
river wheel design due to the potential for more mounting positions, a lower cost due to using a
material already in the design, as well as a higher efficiency than what was projected compared
to the original river wheel design. This provided average and above average scores for the blade
design allowing it to score a reasonable 310 points.
The adapted river wheel was designed with the intention of mimicking the design of the
original river wheel while adding additional blades and a minimal blade mounting system. This
lead the group to believe that not only will the weight be reduced, but also, cost be reduced, and
efficiency increased. This significantly increased the projected points for that blade design.
P a g e |
Selected Design for Prototype Two
The purpose of this Selected Design Concept Discussion is to describe the proposed plan
to develop the group's second prototype. This section will discuss the square base, the shaft, the
motor holder, the motor, and the adapted water wheel blade design.
P a g e |
Final Assembly
Figure 7: Full assembled CAD Drawing – Prototype Two
P a g e |
Square Base
Figure 8: Square Base Drawing
The square base is a simple portion of the design. The shape will allow for equal
balancing in all directions. In the case that the motor needs to be rotated to catch a wind, the
square base will pose no threat to a change in direction. The square will be created out of half
inch cardboard. We expect that the price of a full 30” X 40”cardboard sheet is $1.69 from
Utrecht Art Supplies (Utrecht n.d.). Though the design is simple, the large size of the lofty
material will allow it to prevent tipping in the winds. Hot glue is also needed for the construction
of the base which can be found at Walmart for $1.04.
ALL DIMENSIONS ARE IN MM.
P a g e |
Main Shaft
Figure 9: Main Shaft Drawing
The shaft in prototype two is very similar to the shaft in prototype one. The main
difference is that its height is 15”. The group used the same 3/4” schedule 40 PVC pipe, because
of its acceptable cost and weight. The length of the PVC was changed to support the new blade
design and allow it to operate in the acceptable air flow region. The lowered height allowed for
the highest speed winds to only hit the top blade. Hot glue was used to fix the shaft into place.
The shaft’s mass is 119 grams. The PVC cost $1.29 for a 5’ 1” schedule 40 PVC pipe at
Menards.
P a g e |
Motor Holder
Figure 10: Motor Holder Drawing
The motor mount in prototype two is also similar to the motor mount in prototype one.
This motor mount design was cut in size. This will help reduce both the cost and the weight of
the turbine as a whole. The motor mount is designed to fit snugly inside the PVC shaft opening.
The top of the mount allowed for the motor to slide into place and stay fixed with hot glue. The
motor mount was created out of ABS plastic and has a mass of nine grams. Using $30.00 per
kilogram, the motor mount cost $0.27.
P a g e |
Motor Attachment
Figure 11: Motor Attachment Drawing
The motor attachment is a crucial component to the blade design. The motor shaft slides
directly onto either side of the hole in the center of the cylinder. The motor shaft attachment
gives the ability to transfer a very small shaft into a much larger, more applicable shaft. The shaft
attachment is made out of ABS plastic and has a total mass of 21 grams. The shaft costs $0.63
according to the pricing of $30.00 per kilogram of ABS.
ALL DIMENSIONS IN MM.
P a g e |
Adapted Water Wheel Blade
Figure 12: Adapted Water Wheel Blade Drawing
The water wheel blade design consists of the shaft attachment and four long blades of
cardboard that would catch high winds one blade at a time. The blades were 12” long to catch the
strongest wind on the top blade, due to a short shaft design. This prevented the blades from
catching winds in two directions that opposed each other. The blades are made of cardboard and
are directly hot glued to the shaft attachment. With the shaft attachment, the blade had a mass of
99 grams.
ALL DIMENSIONS IN MM.
P a g e |
Prototype ThreeThis section will discuss all aspects pertaining to prototype three.
Concept Generation and Selection
The purpose of the concept generation and selection is to eliminate potentially poor
design ideas before they are attempted as prototypes. Thus, this section will focus on various
ideas, many of which are not incorporated in the prototype.
Base Design
The group has decided to make a decision matrix considering the following elements:
constrains blade possibilities, cost, simple assembly, stability, and weight. The base should allow
for multiple different types of fan blades, but if the base lowers the choices of blades, then it
loses value. Cost is also highly rated because the higher the cost for the producer; the higher the
cost for the consumer. A simple assembly, simple meaning quick and does not require much
effort to build, will allow for us to develop more prototypes in less time if the idea does fail.
Stability is the most valuable element to our decision matrix. The project will fail immediately if
the project topples and falls. This structure and its strength begins at the base. Weight is another
important factor in the group’s decision matrix. The less the structure weights; the easier it will
be to transport the turbine.
P a g e |
Table 4: Base Design Decision Matrix for Prototype Three
Decision
Matrix
Idea 1 –
Long quad
base
Idea 2 –
Pyramid base
Idea 3 –
Wire
Idea 4 – Big Square,
Little Circle with a Tail
Constrains Blade
Possibilities/Motor Mount - 15
2 3 4 4
Cost – 20 4 3 3 5
Simple Assembly – 15 4 2 3 5
Stability – 25 2 4 5 4
Weight – 20 4 3 4 5
Total Points 300 295 370 435
Ideas one through three stayed the same due to the possibility of an improvement in the
design factors listed. They retained the same scoring as provided during prototype one because
of the lack of changes made to the base throughout the iterations between the first prototype and
the third.
A square design with a tail scored the highest with an overall score of 435. The number
of motor mounting positions placed it around average adaptability. Because of the large amount
of material used, it had an average low cost though it features a simple assembly, being a base
with a pole, allowing it to score high in that regard. Both the stability and weight were scored as
above average because of the size of the base, though those features contribute to the positive
attributes of the design and the thinner material which cost and weighed less while retaining the
minimum stability needed for the turbine (Contech Engineered Solutions n.d.). A change that
was made to the original design that was determined to be better is adding a stabilizer to the rear
P a g e |
of the board. This enables an increase in stability though it minimally sacrifices some weight.
Cost is not affected due to the size of cardboard purchased.
P a g e |
Blade Design
To determine the best blade, a decision matrix has been created considering the following
elements: adaptability, cost, simple assembly, projected efficiency, and weight. The adaptability
of a blade is important because it can allow for various arrangements as well as allowing the base
to change around it. The cost is also important to consider because it can be a determinant of
whether the customer will choose to purchase the wind turbine. A simple assembly can allow
maintenance to be done fast as well as allow a company to build more turbines in less time. The
efficiency of the system, and thus the blades, are easily the most important aspect of a turbine
because it allows the motor to generate the most power. The weight is also important for all
aspects of the machine because it affects the ability to transport the turbine as well as adds extra
unneeded force to the base.
Table 5: Blade Design Decision Matrix for Prototype Three
Decision
Matrix
Idea 1 – Curved
Tri-Blade
Idea 2 – River
Wheel
Idea 3 – Flat
shovel blades
Idea 4 – Curved
Shovel
Adaptability - 15 3 1 3 3
Projected Cost -
20
4 1 2 3
Simple Assembly
– 15
4 4 3 3
Efficiency – 25 5 3 2 3
Weight – 20 4 1 2 3
Total Points 390 190 220 285
Idea one was the only idea that changed due to the prototype 2’s blade not performing as
expected. A curved tri blade that absorbs more of the air and uses the force to push the blade is
P a g e |
expected to be relatively adaptable to certain situations but is nowhere near excellent. The ABS
printed blade would be relatively cost efficient and would only require payment for the amount
of material necessary. This is in contrast to any other form of blade which may use excess
material which incurs additional costs. A curved ABS Tri-Blade also requires minimum
assembly allowing it to score highly in that category. Due to the swept front of the blade, it is
believed that the blade will provide maximum efficiency which gives it top marks in projected
efficiency. The lightweight nature of ABS gives the blade system a low projected weight
allowing it to do well in that category as well as become a top prospect due to not adding
unnecessary weight to the turbine design.
P a g e |
Selected Design for Prototype Three
The purpose of this Selected Design Concept Discussion is to describe the proposed plan
to develop the group's third prototype. This section will discuss the square base, the shaft, the
torque support, the motor holder, the motor, and the swept tri-blade design.
P a g e |
Final Assembly
Figure 13: Full assembled CAD Drawing - Prototype Three
P a g e |
Square Base
Figure 14: Square Base Drawing
The base design in prototype three has several small changes compared to prototype two.
For instance, the shaft hole is no longer in the center of the base, it has been moved so that the
main shaft was 2” from the front edge. The base is still made of cardboard and had a mass of
48.4 grams. The cardboard used for all cardboard pieces related to the turbine cost $0.62 from
Wal-Mart.
P a g e |
Base Supports
Figure 15: Base Support #1 Drawing
Figure 16: Base Support #2 Drawing
The base potion of prototype three incorporated two different types of base supports. The
base supports uses cardboard and hot glue to attach to the rest of the base. The supports stack up
around the hole in the base to support the PVC pipe. The first support is the 4” by 4“ cardboard
base support. The next two supports uses 2” by 2” card board supports. Without these supports,
the PVC pipe would be less stable and thus could suffer failure. The total mass of the support is
5.6 grams. The hot glue costs totaled $1.04 from Wal-Mart. The cardboard used for the base
supports are of the same cardboard used for the base.
ALL DIMENSIONS IN MM.
ALL DIMENSIONS IN MM.
P a g e |
Support Tail
Figure 17: Support Tail Drawing
The tail attaches to the center of the rear end of the base. The tail pushes up against the
wooden back stop so that the turbine can stand near the red line which also helps to increase the
stability of the turbine. The tail is connected to the base with hot glue and is composed of
cardboard. The mass of the tail is 10.7 grams. The cardboard used for the suport tail is of the
same cardboard used for the base.
P a g e |
Main Shaft
Figure 18: Main Shaft Drawing
The shaft is a ½” schedule 40 PVC pipe. The shaft hot glues into the cardboard base and
base supports. The PVC pipe weighs just enough to keep the whole turbine down, and does not
have much unnecessary mass. The shaft has a mass of 129.2 grams. The cost for 2 feet of ½ inch
schedule 40 PVC is $1.26 which can be found at Menards.
P a g e |
Torque Support
Figure 19: Torque Support Drawing
The torque support is a cardboard rectangle that attaches at approximately a 45º angle
from the base. The torque support resists motion from pushing the shaft backwards. The rotation
of the turbines shaft changed the angle at which the blade accepted wind. With the torque
support attached, the blade to catches more wind at the appropriate angle. The torque support has
a mass of 2.7 grams. The cardboard used for the motor mount is of the same cardboard used for
the base.
P a g e |
Motor Mount
Figure 14: Motor Mount Drawing
The motor mount is simply comprised of cardboard. The center of the cardboard motor
mount hotglues to the top of the PVC shaft. Hot glue sufficiently holds the motor in place on top
of the motor mount. The end of the motor extends past the edge of the motor mount to support
free action of the blade. The mass of the motor mount is 0.6 grams. The cardboard used for the
motor mount is of the same cardboard used for the base.
ALL DIMENSIONS IN MM.
P a g e |
Swept Tri-blade
Figure 20: Swept Tri-Blade Drawing
The Tri-Blade design looks similar to the the Tri-Force blade design in the first
prototype. The main changes in the design mainly has to do with the size of the entire blade and
the size of each blade. The Tri-Blade is a very small blade and low density ABS plastic blade so
that the force of wind will allow for a faster angular velocity. The blades were also designed to
catch wind and rotate clockwise. The Tri-Blade attaches directly to the shaft of the motor. This
part has a mass of 8.8 grams. According to $30.00 per kilogram cost, the Swept Tri-Blade costs
$0.26.
P a g e |
Test Performance for Prototype One
The turbine was ran for a timed interval of three minutes using the testing set up provided
for experimentation and found that the max voltage was 0.2 volts. The turbine was within the
area determined to have the highest air flow and set at the appropriate distance from the air
source (Appendix B). The center of the turbine was at approximately 22.5" tall. This placed the
turbine in what was measured as the optimal position for usage.
The base of the turbine was also tested for stability. This was done by attempting to move
the top of the motor mount and ensuring that it held the motor and would not be affected by
adverse movements as a result of the air flow acting on it. This ensured a constant position of the
propeller and an ample amount of air passing over it as such. The stability test was performed to
ensure that the base of the turbine would be safe and hold up to the effects of the air acting on the
base during usage. This also confirmed that the turbine would be safe for consumer use.
The wind speed test was performed in order to identify the best positioning and placing
of the turbine during testing and to give an exact measurement of the forces of the air acting
upon the blades of the wind turbine. This prevented the turbine from being placed incorrectly and
ensure it was optimally placed and designed to ingest the optimal amount of air.
The voltage test was done to test the effectiveness of the turbine and to see if it would
produce and acceptable output. This test was conducted with the fully assembled prototype to
allow for the most accurate measurement possible.
The motor mount and propeller were weighed to calculate the total mass of each and to
see if there would be the possibility to reduce the weight in the future to allow for a lighter
design of the turbine as a whole. This test showed that the motor mount weighted 37.7 grams and
the blades weighted a total of 13.9 grams. It was determined that the blades could be made both
larger and thinner in order to improve efficiency and reduce weight. The motor holder could also
be lightened by shelling the structure and also making a side of the square tangent to the post to
reduce material used, which would also save on cost.
Using an equation to determine the power of the generator,Watts=Current∗Voltage and
Current= VoltsResistance , it can be determined that the generator produced .00143 watts while the
generator was under 28 ohms of resistance. This shows the need for increased efficiency of the
P a g e |
blade design and the need for improvement for the generator to produce closer to its two watt
capacity in future prototypes (Appendix A).
P a g e |
Test Performance for Prototype Two
The second prototype was ran for three minutes and produced a maximum voltage of
0.12 volts. This is dismal when compared to what the turbine can produce, and in comparison to
the first prototypes maximum voltage.
The blade was set at a height of 15" which was determined to be the optimal height so
that the majority of the blade would utilize the maximum wind velocity in that region, which
would be approximately 20" high (Appendix A).
The base was determined to be stable, however, it suffered from extreme vibration,
potentially lowering the power and maximum voltage produced. It was able to withstand the
minimum requirement of not failing for three minutes which is the primary goal of the base
structure.
The wind speed test, the stability test, and the voltage test were performed in order to
make sure that the prototype would meet the requirements determined by the project, and by the
group. While the prototype met these requirements, it performed poorly in the group’s eyes and
has multiple aspects that can be improved upon.
The weight of the second prototype, in comparison to the first, is extremely heavy. It also
produces less power and has a lower maximum voltage which needs to be increased in order for
a prototype to become a viable option that is worthy of production.
This conclusion was reached by performing wind velocity, stability tests, and also
weighing the structure. This enabled the group to find the optimal height for the turbine to
operate and also horizontal positioning. A stability test was conducted by running the trial for a
three minute period and ensure there were no additional stresses on the turbine. The structure
was also weighed to ensure that the structure would not be obscenely heavy, thus potentially
affecting the efficiency, and structural integrity.
Using an equation to determine the power of the generator,Watts=Current∗Voltage and
Current= VoltsResistance , it can be determined that the generator produced .000514 watts while the
generator was under 28 ohms of resistance. This shows the increased efficiency of the blade
design and the need for improvement for the generator to produce closer to its two watt capacity
(Appendix A).
P a g e |
P a g e |
Test Performance for Prototype Three
The third prototype was ran for three minutes and the maximum voltage produced was
4.01 volts. The voltage was produced at a height of 19.5 inches which was determined to be the
optimal height for this blade design (Appendix B). The turbine was centered in the exact location
where wind speed was determined to be highest. This allowed the blade to utilize the maximum
amount of air and generate the highest voltage possible for this blade design.
The base was also tested for stability by running a full three minute run to ensure the
prototype would be able to meet the minimum requirements. It was found that with the torque
support, the base would enable the shaft to stay straight and thus reduce vibrations that could
cause the blade to be less efficient than predicted. The primarily cardboard base withstood the
test without issue and proved to be durable for the given conditions.
The motor mount weighed a total 0.6 grams which is much lighter than the original motor
mounts. The propeller design was also much lighter than all other designs, weighing only 8.8
grams. The overall weight of the structure became considerably lighter due to a change of
cardboard thickness and other design differences, which enabled the design to only weigh 254.4
grams. This improves the standing for the weight while also increasing the original durability
and power significantly.
Using an equation to determine the power of the generator,Watts=Current∗Voltage and
Current= VoltsResistance , it can be determined that the generator produced .615 watts while the
generator was under 28 ohms of resistance. This shows the increased efficiency of the blade
design and the improvement for the generator to produce closer to its two watt capacity
(Appendix A). These aspects made turbine three the most efficient and effective option of the
three prototypes tested.
P a g e |
ConclusionThe first prototype met all of the design criteria specified. The wind turbine produced
energy and withstood the three minute test period. The base also passed all stability tests
allowing for it to be put into production. Given the amount of power that was produced, it is not
recommended that this iteration be used as a final product and is therefore not ready for
consumer use. There are multiple aspects that could be improved upon. One such aspect would
be the blade. The current propeller is not efficient enough for use or further experimentation. It
would be beneficial to increase the surface area of the individual blades, as well as produce the
blades out of a lighter material. Such materials for the blades could include Styrofoam, balsa
wood, or cardboard. Throughout research, it was shown that three long blades were the most
efficient design, however the first prototype did not utilize this to its advantage, though it may
still be worth developing a new propeller design based on this idea. It would also not drastically
affect the cost of the turbine by exploring the route.
The second prototype made many of the changes suggested after analyzing the
performance of the first prototype. The longer blades that were made to be wider created to much
drag for the additional advantage to be used to its full potential. It was also far heavier than the
first prototype which added to the list of disadvantages that the second prototype incurred. While
the turbine passed all requirements, it did not meet the group’s standards. The group focused on
going forward from the second prototype was improving upon the power output, lowering the
weight, and increasing the stability of the base.
The third prototype remedied the majority of grievances that were had with the previous
prototypes. It drastically increased the power output from 0.2 volts to 4.01 volts. This resulted in
a power increase of 500% in comparison to the first prototype. While this could be further
improved, the group feels that this is satisfactory for the given conditions and the possibilities
presented by the current testing protocol. The turbine also weighs less than either prototype
further increasing its favorability with the group. The cost also decreased which improves the
overall cost effectiveness of the turbine. While, the power and weight could be improved, the
group has does not currently have the means to improve upon the third prototype, and while a
gear train or belt system could be added, the group does not believe it will be entirely beneficial
to the turbine.
P a g e |
BudgetsThe purpose of the budget is to allow the project to be tested with respect to what the total cost of
the prototype would be if it were to be put into production.
Budget for Prototype One
Table 6: Budget for Prototype One
Object Price
Half-Inch Cardboard Sheet 30” X 40” $1.69
¾” PVC Pipe 5' $3.91
Motor Holder ABS Plastic $1.13
Tri-Force Blades ABS Plastic $0.42
*Hot Glue Stick 5/16” X 4”* $1.21
Total $8.36
*Found at (MID Hardware n.d.)*
Budget for Prototype Two
Table 7: Budget for Prototype Two
Component Price
11.75” x 8” x 4.75” Shipping Box $0.62
¾” Schedule 40 PVC Pipe $1.37
Transparent Hot Melt Glue Stick $1.04
Motor Mount $0.27
Motor Attachment $0.63
Total $3.93
P a g e |
Budget for Prototype Three
Table 8: Budget for Prototype Three
Component Price
11.75” x 8” x 4.75” Shipping Box $0.62
1/2” Schedule 40 PVC Pipe 5 feet $1.26
Transparent Hot Melt Glue Stick $1.04
Tri-Blade ABS Plastic $0.26
Total $3.18
P a g e |
Mass of TurbineThe purpose of these tables is to note and sum all masses of the prototypes in the measurement of
grams.
Mass of Turbine Prototype One
Table 9: Mass of Turbine One
Object Mass
¾” PVC Pipe – 19.5” length 154.7g
Cardboard 8” x 8” x .5” 22.2g
Motor Holder - ABS Plastic 37.7g
Tri-Force Propeller 13.9g
Motor 56.1g
Total 284.6g
Mass of Turbine Prototype Two
Table 10: Mass of Turbine Two
Object Mass
3/4” Schedule 40 PVC Pipe – 15” length 118.6g
Base of cardboard 87.7g
Water Wheel Blade 98.6g
Motor 56.1g
Total 361.0g
P a g e |
Mass of Turbine Prototype Three
Table 11: Mass of Turbine Three
Object Mass
1/2” Schedule 40 PVC Pipe – 19” length 129.2g
Cardboard 12” x 12” x 1/8” 48.4g
Support Materials 5.6g
Swept Tri-Blade 8.8g
Generator 56.1g
Torque Support 2.7g
Hot Glue 3.6g
Total 254.4g
P a g e |
Appendices
Appendix A: Generator Specifications
P a g e |
Height in Inches33 0 0 0 0 0 0.8 0 1 1 0.8 0 0 0 0 0 0 031 0 0 0 0 0 0.9 1.8 2.8 2.4 1.1 0.3 0 0 0 0 0 029 0 0 0.7 0.8 1 3.7 3.5 5.2 5.5 3.5 1.8 0.8 0 0 0 0 027 0 0 0.9 1.3 2.9 2.3 5.5 8.2 12.8 5.0 5 2.4 1.1 0.9 0 0 025 0 0 1.4 1.4 5.5 4 5.6 12.5 13.7 8 4.2 3.3 2.4 1.4 0.8 0 023 0 0.9 1.6 2.3 6 7.8 14.7 16.9 17.2 11.1 6.4 3.6 2.6 2.1 1.1 0.7 021 0 1.2 1.8 4.3 6.4 8.4 18.7 23.1 19.5 13.5 8.5 4.8 3.1 1.9 1 0.8 019 0 0.8 1.2 2.9 7.3 10.4 19 21 21 12.5 7 2.6 2.1 1.3 0 0 017 0 0 0.9 2.1 5.8 8.5 14 18.6 14 11.2 4.8 2.7 2 1.1 0 0 015 0 0 0 1.4 3.2 6.3 8.5 12.4 9.5 7 4.8 1.5 1.1 0.9 0 0 013 0 0 0 0 1.5 4.9 6.8 7.3 5.7 3.4 3 0.9 0 0 0 0 011 0 0 0 0 0.8 1 2.3 1.8 2.3 0.8 0 0 0 0 0 0 09 0 0 0 0 0 0 1.8 0.8 1 0 0 0 0 0 0 0 07 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 05 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 03 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 01 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33Width in Inches
Appendix B: Measured Wind Speeds
P a g e |
Works CitedContech Engineered Solutions. n.d. Wind Turbine Foundations. Accessed February 2, 2016.
http://www.conteches.com/Markets/Wind-Turbine-Foundations.
Gurit. n.d. Wind Turbine Blade Structural Engineering. Accessed February 25, 2016. http://www.gurit.com/files/documents/3_blade_structure.pdf.
MID Hardware. n.d. Mintcraft, mini glue sticks for jlgg10. Accessed March 2, 2016. http://midhardware.com/hardware/product_info.php?products_id=6228761&gclid=COC6m5GNpcsCFQyEaQodkY8AcA.
PVC Fittings Online. n.d. 1" Schedule 40 PVC Pipe . Accessed March 1, 2016. http://www.pvcfittingsonline.com/4004-010ab-1-schedule-40-pvc-pipe-5-ft-section.html?gclid=CjwKEAiAmNW2BRDL4KqS3vmqgUESJABiiwDTEueUgrwMlpEPKA4SSUxtxLlttkM1wys4B5EuFFiVCRoCxQzw_wcB.
Utrecht. n.d. Utrecht Corrugated Cardboard 30 x 40 inches. Accessed March 1, 2016. http://www.utrechtart.com/Utrecht-Corrugated-Cardboard-30-x-40-inches-MP-13900-001-i1015872.utrecht?utm_source=google&utm_medium=cse&utm_term=13900-3040&country=US¤cy=USD&gclid=CjwKEAiAmNW2BRDL4KqS3vmqgUESJABiiwDT3Wi2VJV4eOJ7gOT8uUQf6Edg6DGw5CWDtzo9.