Upload
ngongoc
View
225
Download
3
Embed Size (px)
Citation preview
0
The report consists of all the projects
carried out at Biome Environmental
Solutions during the period of 29th May
2014 to 15th July 2014 under the Wipro
Earthian Programme.
Wipro
Earthian
Internship
Project
Report. At Biome Environmental
Solutions.
Prepared by: Soham D’souza, Yousuf Bootwala and Vijay Patil
Acknowledgements
We would like to thank Wipro Earthian for giving us this opportunity to work at Biome
Environmental Solutions as interns. The Earthian Internship is a brilliant initiative and we’re
going back with so much knowledge which wouldn’t have known otherwise. We would also
like to thank Mr. Vishwanath for teaching us many things regarding water treatment and
conservation and for always motivating us to try new things. All the projects we took and
completed in our period of internship wouldn’t have been possible without the help and
guidance of Shubha Ma’am and Rajiv Sir. So a big thanks to them. We would also like to
thank Avinash Sir for spending time, talking to us about how we should go about our job and
widening our way of looking towards the project we were doing.
Finally, we would like to thank everyone at Biome for making our internship period
memorable and informative and one which we would never forget and always cherish the rest
of our lives.
Index
Aquifer Mapping 1
i) What is an aquifer? 1
ii) Aquifer Mapping 2
iii) Aquifer Mapping in and around Wipro Corporate office Sarjapur Road 2
iv) Importance of the Project 2
v) Project Details 4
(a) Phase 1-Finalising the dealers for Chemical Analysis 4
(b) Phase 2- Kits and Chemical Procurement 7
(c) Phase 3- Setting Up Laboratory 7
(d) Phase 4- Collecting the water samples from lakes and borewells 10
(e) Phase 5- Studying the Chemistry behind analysis method 11
(Occurrence, Health Effect, Testing)
(f) Phase 6- Discussion and Results 16
(Experimental, Materials and Methods, Results and Data analysis of
lakes, Results and data analysis of borewells)
Jakkur Lake 29
i) Introduction to Jakkur Lake 29
ii) Project Objective 29
iii) Results and Discussion 29
Rainwater Harvesting Projects 37
i) Assignment 1 37
(a) Stage 1 and Stage 2 37
(b) Background 37
(c) Work Details 38
ii) Assignment 2 41
(a) Groundwater Recharge Solution for Trinity Woods and Acres 42
iii) Assignment 3 66
(a) Work Details 66
Construction of BioSand Filter 69
i) Introduction 69
ii) Water that can be used for filtration 69
iii) Functioning of each part of BioSand Filter 70
iv) Specification of Sand to be Used 73
v) Pathogen and Dirt Removal Mechanism 74
vi) What can BioSand filter remove from filter 74
vii) Biolayer 75
viii) Pause Period 75
ix) How did we develop our BioSand filter 76
(a) Stage 1: Thought Process 76
(b) Stage 2: Implementation 76
(c) Stage 3: Innovation( further studies and maintenance) 78
Construction of Tippy Tap 80
i) Introduction 80
ii) Advantages 80
iii) How did we develop our Tippy tap 80
(a) Stage 1: Thought Process 80
(b) Stage 2: Implementation 80
(c) Stage 3 : Documentation 82
Field Visits 83
i) Visit 1: Rainbow Drive Layout 83
ii) Visit 2: Sumanahalli Nagarbhavi Slum 87
iii) Visit 3: Water Hygiene and Sanitation Awareness at Sumanahalli 91
Presentations and Videos Made 94
Bibliography 95
Earthian Internship at Biome Environmental Solution Page 1
Aquifer Mapping
1) What is an aquifer?
An aquifer is an underground layer of water-bearing rock. Water-bearing rocks are
permeable, meaning that they have openings that liquids and gases can pass through.
Sedimentary rock such as sandstone, as well as sand and gravel, are examples of water-
bearing rock. The top of the water level in an aquifer is called the water table.
(The study of aquifers and the water flows in them is called hydrogeology)
An aquifer fills with water from rain or melted snow that drains into the ground. In some
areas, the water passes through the soil on top of the aquifer; in others, it enters through joints
and cracks in rocks. The water moves downward until it meets less permeable rock.
Aquifers act as reservoirs for groundwater. Water from aquifers sometimes flows out in
springs. Wells drilled into aquifers provide water for drinking, agriculture, and industrial
uses. Aquifers can dry up when people drain them faster than nature can refill them. Because
aquifers fill with water that drains from the surface of the Earth, they can be contaminated by
any chemical or toxic substance found on the surface.
There are two types of aquifers.
Earthian Internship at Biome Environmental Solution Page 2
An unconfined aquifer is covered by permeable rock and can receive water from the
surface. The water table of an unconfined aquifer rises or falls depending on the amount of
water entering and leaving the aquifer. It is only partly filled with water.
In contrast, a confined aquifer lies between two layers of less permeable rocks and is filled
with water. Water trickles down through cracks in the upper layer of less permeable rock, a
nearby water source, such as an underground river or lake, or a nearby unconfined aquifer.
An artesian well is a type of confined aquifer that flows upward to the Earth's surface
without the need for pumping. The artesian well sits below the water table at the bottom of U-
shaped aquifers. Pressure from water in the long sides of the aquifer pushes the water up the
well shaft.
Aquifers and how they behave are determined by:
1) Geology of the place
2) Other ecological characteristics like terrain, topography, watershed and rainfall
3) Land use
4) Use of water from the aquifer and the discharge of our waste water
2) Aquifer Mapping:
Groundwater resides in aquifers. Aquifers do not respect property, political or administrative
boundaries. They are a common property resource. Aquifers can be understood, they can be
mapped, and how water flows in it, how much water it holds can be established. With this
understanding and all our participation and stewardship, aquifers can be managed.
3) Aquifer Mapping in and around WIPRO Corporate Office ,Sarjapur
Road (Covering the entire micro watershed)
Our main project for the WIPRO Earthian Internship with Biome Environmental Solutions
Pvt.Ltd. was to contribute in the aquifer mapping project (To map the entire micro watershed
in and around WIPRO Corporate Office) by providing details of the quality of water from the
various water bodies existing in the aquifer.
We were given the task of doing a detailed chemical analysis study of the water samples
collected from this particular micro watershed and thereby our results would be displayed on
the aquifer map.
4) Importance of this project (Participatory Aquifer Mapping)and how is it
going to impact and help the communities:
Earthian Internship at Biome Environmental Solution Page 3
(i)A lot of bureaucracy exists in the Karnataka State Government as different portfolios
regarding water and water management are being held by different governing bodies which
don't really work in collaboration with each other. The bore well testers by the government
aren't reliable and the data hasn't been updated.
(ii)This project is linking various organisations and institutions with different spheres of
influence and collaborating with each of them so that the citizens receive detailed information
about the water bodies in their vicinity, the depth of aquifers in their locations and in turn the
citizens also help this system developed by providing information through observations in
and around their areas (regarding water bodies ,bore wells, recharge wells and the quality of
water)
Now, why this model is a win-win for everybody involved with this and how can we make
the government accountable ?
A) This being a "PARTICIPATORY MODEL" there shall exist a great sense of
belongingness amongst the citizens and a sort of healthy competition shall develop wherein
citizens from various colonies shall start plugging their observations and data on a common
platform.
B) This can also prove to act as a hawk-eye on the governmental data that might appear to be
Earthian Internship at Biome Environmental Solution Page 4
rather old and outdated. So the government on knowing that the citizens of Bangalore are
taking so many efforts will foster water management projects from the state level.
(iii)This is going to be a very user friendly interface wherein any person can plug in his/ her's
data and check the quality of the water in the aquifers by viewing the maps. Also if people
wish to dig recharge wells/bore wells, they will get better insights about the ground water
level even before digging it.
(iv)We can ascertain the water quality at each micro-watershed .This can help us see how the
water quality changes from one place to another. Also, this data can be used by people to
decide the purification stages needed at each place before using the water.
5) Project Details
Objective: To test the water samples from the lakes ,borewells and other water bodies in
and around WIPRO Corporate office (Sarjapur Road)Bangalore for the following
parameters:
pH
Total Dissolved Solids(TDS)
Electrical Conductivity
Nitrates
Nitrites
Ammonium
Phosphates
Iron
Calcium
Phase 1: Finalising the dealers for chemical analysis tool kits
We did an extensive search about the various dealers and chemical suppliers in the country in
order to procure the best tool kits and chemicals for the water analysis of the samples
collected. We got the quotations from various dealers, collated the entire data in an excel
sheet, showed it to our project head, got it approved and went ahead with the purchasing.
The dealers list are as furnished below:
(Note: Yellow boxes indicate the selected vendors from the given sheet from whom we are
going to purchase the sampling kit)
Earthian Internship at Biome Environmental Solution Page 5
Earthian Internship at Biome Environmental Solution Page 6
(Note: Green boxes indicate that we have zeroed down on that particular vendor
for purchasing the kit/chemicals)
Earthian Internship at Biome Environmental Solution Page 7
Phase 2: Kits and chemicals procurement:
Purchase orders were placed appropriately to the dealers by us. We would meticulously track
the developments and document the conversations with the vendors. Follow up was done
with the vendors. After the kits are procured, we checked whether the kits and chemicals are
in a proper condition as specified in the product specification manuals
Phase 3: Setting up our laboratory at the Biome Office
The next stage was to set up a laboratory for us in the Biome office. All the chemicals and the
kits were arranged in a meticulous fashion and kept safely. All safety measures were ensured
seeing to it that nobody gets injured during the experiments.
Earthian Internship at Biome Environmental Solution Page 8
We then made a detailed inventory of all the instruments, chemicals and apparatus
present in our laboratory. The details are as furnished below:
Sr.
No.
Equipment Quantity
1 Calcium Hardness Kit
Contents: Sample Bottle
Reagent CH-1
Reagent CH-2
Reagent CH-3
Reagent CH-4
1
2 Nitrates, Nitrites and Ammonia Combo Testing Kit
Contents: For Nitrates
Reagent NA-1
Reagent NA-2
For Nitrite
Reagent NI-1
For Ammonia
Reagent NH-1
1
3 Phosphorus and Iron Combo Testing Kit
Contents: For Phosphates
Reagent PR-1
Reagent PR-2
For Iron
Reagent Fe-1
Reagent Fe-2
Reagent Fe-3
1
4 Chloride and Fluoride Testing Kit 1
5 Total dissolved solids (TDS) meter 3
6 Electric Conductivity (EC) meter 1
7 pH meter 3
8 Glass Test tubes 10
9 Glass droppers 2
10 Measuring cylinders (10 mL) 4
11 Measuring cylinder (25 mL) 1
12 Buffer Solution (pH = 6.86, 250 mL) 1
13 Plastic Beakers (100 mL) 2
14 Buffer Solution (pH = 4.01, 250 mL) 1
15 Spirit bottle with spirit lamp 1
16 Test tube holder 2
Earthian Internship at Biome Environmental Solution Page 9
The Laboratory Instructions that we have made are as furnished below:
Do not drink water or solutions from the bottles kept in the workplace.
Use plastic gloves for safety.
Label the samples to be tested, to avoid confusion.
Read carefully about the procedure of testing before experimentation.
Clean the workplace for experimentation before and after using.
Clean and rinse equipments (testubes, beakers, measuring cylinder, droppers, etc.) with
distilled water before experimentation.
Rinse the equipments of experimentation with sample to be tested.
Keep all the equipments back into their respective places after their use.
Calibrate pH meter before using by testing it in buffer solution of pH = 6.89 and pH =
4.01 available in laboratory.
Avoid wasting the solutions and chemicals.
Safely dispose the solutions to the sink after experimentation.
Earthian Internship at Biome Environmental Solution Page 10
Phase 4: Collecting the water samples from the lakes and the borewells.
We then went on a road trip to collect the water samples in the micro watershed. Pictures and
videos were taken for reference purpose. All the water samples were neatly labelled. Some
lakes and borewells were dried or some construction activity was underway on the lakes.
Earthian Internship at Biome Environmental Solution Page 11
Phase 5: Studying the chemistry behind the analysis method:
Nitrates:
Occurrence:
Most nitrogenous materials in natural waters tend to be converted to nitrate, so all sources of
combined nitrogen, particularly organic nitrogen and ammonia, should be considered as
potential nitrate sources. Primary sources of organic nitrates include human sewage and
livestock manure, especially from feedlots.
The primary inorganic nitrates which may contaminate drinking water are potassium nitrate
and ammonium nitrate both of which are widely used as fertilizers.
Nitrate (NO3-) results from a process known as oxidation or nitrification, which is the
stepwise addition of oxygen atoms to a nitrogen atom:
NH4+ -> NH3 ->NO2 NO3-
Nitrate represents nitrogen in its most oxidized form.
Health Effects:
Nitrate in drinking water can be responsible for a temporary blood disorder in infants called
methaemoglobinemia (blue baby syndrome). In infants less than six months old, a condition
exists in their digestive systems which allows for the chemical reduction of nitrate to nitrite.
The nitrite absorbs through the stomach and reacts with haemoglobin to form
methaemoglobin, which does not have the oxygen carrying capacity of haemoglobin. Thus,
the oxygen deficiency in the infant’s blood results in the “blue baby” syndrome. Although
extreme levels of nitrate can be associated with central nervous disorders in adults, it should
be noted that nitrates and nitrites are rarely a problem in drinking water for humans older than
six months of age.
Testing:
10mL of sample was taken in a test tube. Nitrates in the water were first reduced to nitrites by
adding a pinch of cadmium powder to the sample.
Cd(s) + N03-
(aq) + 2 W(aq) Cd2+
(aq) + N02-
(aq) + H2O(l)
The solution is then decanted and about 5mL of the decanted solution was taken for further
analysis. A mixture of solutions containing acidified Sulfanilamide( with concentrated HCl)
and N-(1-naphthyl) ethylene diamine dihydrochloride were added. The hydrochloric acid
present in the solution creates an acidic environment for the reaction to take place in. In such
an environment, the nitrite reacts with the sulfanilamide to form a diazonium compound.
Then this compound reacts with the N-(1-naphthyl) ethylene diamine dihydrochloride
solution. 3 drops of this mixture was added to the decanted solution. This reaction produces a
pink coloured azo-compound. The intensity of the pink colour was directly related to the
amount of nitrate present in the sample.
Earthian Internship at Biome Environmental Solution Page 12
Nitrites:
Occurrence:
Natural water has a low nitrite concentration because bacteria quickly convert Nitrite (NO2-)
to other more stable nitrogen ions. Therefore, nitrate measurements typically represent
nitrate+nitrite concentrations.
Nitrite is:
- An unstable nitrogen ion
- An intermediate ion in nitrification/denitrification process
- A nitrogen source for algae or phytoplankton
- More toxic than nitrate to fish, animals, and humans
Health Effects:
Since nitrites are rarely found in water because it converts to nitrates readily, its health effects
are almost the same as Nitrates.
Testing:
5mL of the sample was taken in a test tube. A mixture of solutions containing acidified
Sulfanilamide( with concentrated HCl) and N-(1-naphthyl) ethylene diamine dihydrochloride
were added. The hydrochloric acid present in the solution creates an acidic environment for
the reaction to take place in. In such an environment, the nitrite reacts with the sulfanilamide
to form a diazonium compound. Then this compound reacts with the N-(1-naphthyl) ethylene
diamine dihydrochloride solution. 3 drops of this mixture was added to the water sample.
This reaction produces a pink coloured azo-compound. The intensity of the pink colour was
directly related to the amount of nitrate present in the sample.
Ammonia:
Occurrence:
Ammonia is rarely found in unpolluted surface water or well water, but water contaminated
with sewage, animal wastes or fertilizer runoff may contain elevated levels. Ammonia is
commonly found in surface water and rainwater. The level of ammonia in surface water
varies regionally and seasonally and can be affected by localized anthropogenic influences,
such as runoff from agricultural fields or industrial or sewage treatment discharges. The
ammonia concentrations in rivers and bays are usually less than 6 mg/L; higher levels may
indicate anthropogenic pollution (Bouwer and Crowe, 1988)
Health Risks:
Earthian Internship at Biome Environmental Solution Page 13
Ammonia has a toxic effect on healthy humans only if the intake becomes higher than the
capacity to detoxify. In humans, most health effects reported as a result of ammonia exposure
are associated with exposure through inhalation, which is not a relevant mode of action in the
consideration of toxicity associated with drinking water. Although ingestion of concentrated
ammonia causes irritation and damage to the mouth, throat and gastrointestinal tract, these
effects are unlikely to occur at the concentrations of ammonia found in drinking water
(Klendshoj and Rejent, 1966; Klein et al., 1985; Lopez et al., 1988). Based on the lack of an
appropriate endpoint from the ingestion of ammonia, the lack of sufficient evidence of
systemic effects in humans, as well as limited relevant studies in experimental animals, no
health-based guideline can be derived for ammonia in drinking water.
Testing:
The ammonia level in mg/L (or ppm), ammonia as nitrogen is determined by a colorimetric
method.
5mL of the sample was taken in a test tube. The Nessler reagent reacts with ammonia, under
strong alkaline conditions, to form a yellow coloured complex (see equation below). An
addition of an EDTA (Ethylenediaminetetraacetic acid) solution inhibits precipitation of
calcium and magnesium ions due to the presence of the alkaline Nessler reagent. 5 drops of
this Nessler’s reagent was added to the sample. The colour intensity of the solution
determines the ammonia concentration
2K2Hgl4 +2NH3 ➝ NH2Hg2I3 + NH4I + 4KI
Phosphates:
Occurrence:
Phosphates enter waterways from human and animal waste, phosphorus rich bedrock,
laundry, cleaning, industrial effluents, and fertilizer runoff. These phosphates become
detrimental when they over fertilize aquatic plants and cause stepped up eutrophication.
Health Effects:
Rainfall can cause varying amounts of phosphates to wash from farm soils into nearby
waterways. Phosphate will stimulate the growth of plankton and aquatic plants which provide
food for fish. This may cause an increase in the fish population and improve the overall water
quality. However, if an excess of phosphate enters the waterway, algae and aquatic plants
will grow wildly, choke up the waterway and use up large amounts of oxygen. This condition
is known as eutrophication or over-fertilization of receiving waters. This rapid growth of
aquatic vegetation eventually dies and as it decays it uses up oxygen. This process in turn
causes the death of aquatic life because of the lowering of dissolved oxygen levels.
Phosphates are not toxic to people or animals unless they are present in very high levels.
Digestive problems could occur from extremely high levels of phosphate.
Earthian Internship at Biome Environmental Solution Page 14
Testing:
Ortho-phosphate reacts with ammonium molybdate and antimony potassium tartrate in an
acidic medium to form an antimony-phospho-molybdate complex which is reduced to an
intensely blue-coloured complex by ascorbic acid. The colour produced is proportional to the
phosphorus concentration present in the sample. Only orthophosphate forms a blue colour in
this test.
5mL of the sample was taken in a test tube. x Drops of a mixture containing ammonium
molybdate and antimony potassium tartrate in an acidic medium of sulphuric acid was added.
It was mixed and then it was reduced by adding y drops of ascorbic acid.
Iron:-
Occurrence:
Iron can be a troublesome chemical in water supplies. Making up at least 5 percent of the
earth’s crust, iron is one of the earth’s most plentiful resources. Rainwater as it infiltrates the
soil and underlying geologic formations dissolves iron, causing it to seep into aquifers that
serve as sources of groundwater for wells. It may also be released to water from natural
deposits, industrial wastes, refining of iron ores, and corrosion of iron containing metals.
Although present in drinking water, iron is seldom found at concentrations greater than 10
milligrams per litre (mg/L) or 10 parts per million. However, as little as 0.3 mg/l can cause
water to turn a reddish brown colour. Iron is mainly present in water in two forms: either the
soluble ferrous iron or the insoluble ferric iron. Water containing ferrous iron is clear and
colourless because the iron is completely dissolved. When exposed to air in the pressure tank
or atmosphere, the water turns cloudy and a reddish brown substance begins to form. This
sediment is the oxidized or ferric form of iron that will not dissolve in water.
Health Effects:
Iron is not hazardous to health, but it is considered a secondary or aesthetic contaminant.
Essential for good health, iron helps transport oxygen in the blood. Dissolved ferrous iron gives water a disagreeable metallic taste. Concentrations of iron as low
as 0.3 mg/L will leave reddish brown stains on fixtures, tableware and laundry that are very
hard to remove. When these deposits break loose from water piping, rusty water will flow
through the faucet. The ingestion of large quantities of iron can damage blood vessels, cause bloody
vomitus/stool, and damage the liver and kidneys, and even cause death. However, because
ingestion is regulated, body tissues are generally not exposed to high-level concentrations.
Earthian Internship at Biome Environmental Solution Page 15
Calcium Hardness:
Occurrence:
Hardness comes from naturally occurring calcium and magnesium mineral salts which are
dissolved from the rocks through which rain water flows. Water is harder in chalk or
limestone areas than those with insoluble rock such as granite.
Health Effects of Hardness:
The presence or absence of the hardness minerals in drinking water is not known to pose a
health risk to users. Hardness is normally considered an aesthetic water quality factor. The
presence of some dissolved mineral material in drinking water is typically what gives the
water its characteristic and pleasant taste. At higher concentrations however, hardness creates
the following consumer problems.
• Produces soap scum most noticeable on tubs and showers.
• Produces white mineral deposits on dishes more noticeable on clear glassware.
• Reduces the efficiency of devices that heat water. As hardness deposits build in
thickness, they act like insulation, reducing the efficiency of heat transfer.
It has also been observed that areas of higher hardness in drinking water maybe associated
with lower incidents of heart disease. This possible relationship is being investigated.
The World Health Organization says that "there does not appear to be any convincing
evidence that water hardness causes adverse health effects in humans". In fact, the United
States National Research Council has found that hard water can actually serve as a dietary
supplement for calcium and magnesium.
Some studies have shown a weak inverse relationship between water hardness
and cardiovascular disease in men, up to a level of 170 mg calcium carbonate per litre of
water. The World Health Organization has reviewed the evidence and concluded the data was
inadequate to allow for a recommendation for a level of hardness.
Other studies have shown weak correlations between cardiovascular health and water
hardness.
Some studies correlate domestic hard water usage with increased eczema in children.
Testing:
Method Overview:
To determine the hardness of a water sample, technologists use the EDTA
(ethylenediaminetetraacetic acid) titration. EDTA disodium salt is a soluble salt that reacts
readily with all +2 ions, namely Ca+2
, Mg+2
, Fe+2
and Ba+2
. The EDTA anion reacts quickly
with any +2 metal to form a soluble metal EDTA complex. EDTA is called a chelating or
Earthian Internship at Biome Environmental Solution Page 16
sequestering agent since it will react with and tie up heavy metal ions and render them
harmless to humans and water systems.
All metal-EDTA salts are colourless and require an indicator to tell us when the reaction is
over. Various hardness indicators have been developed. They all tell the operator when the
titration is complete. Hardness indicators are large complex organic dyes that react with
EDTA to form coloured complexes. EDTA reacts preferentially with highly mobile metal
ions, but once they are all tied up, the EDTA will react with the slow moving, massive dye
molecules to give an endpoint. As a consequence, endpoints are challenging.
We will use Eriochrome Black T for the total hardness endpoint, which includes the sum of
calcium and magnesium ions. Murexide indicator gives us the calcium endpoint.
1) Place 25 mL of sample water in a bottle
2) Add 10drops of Sodium Hydroxide (NaOH, “caustic soda”) solution to sample.
3) Add a few grains of Murexide indicator. This will turn the solution pink.
4) Titrate with EDTA until the solution turns purple. Record the mL of EDTA used.
Phase 6: Discussions and Results
Experimental:
The water samples were collected from 15 lakes at various points in the lakes in the specified
watershed area. Also we tried collecting water samples from 42 borewells in the area. Out of
the 42 borewells, 22 were dried. Therefore we could get samples from only 20 of them. The
samples were collected in plastic water bottles and were stored away from sunlight to prevent
any decomposition which might affect the testing results.
Materials and Method:
The kits for testing for Nitrates, Nitrites, Ammonia, Phosphates, Iron and Calcium Hardness
was bought from Avinash Chemicals . These kits were manufactured by Nice Chemicals. The
instructions were given on each of the testing kits which were followed to give results
Earthian Internship at Biome Environmental Solution Page 17
The results of the parameters tested for the lakes are furnished below:
Name Nitrates Nitrites Ammonia Iron Phosphates Calcium TDS pH EC (uS)
Hosa Lake(boundary) 20 5 3 0 1 220 410 6.1 845
Halanayakalli Lake 0 0.5 0.5 0.3 0.5 40 36 6.7 85
Gatahalli Lake 0 0-0.5 0.5 0.3 0.5 50 118 6.8 264
Hadosidhapura Lake 0 0-0.5 1 0 0.5 30 15 5.9 34
Lake dew 5 5(>5) 1-3 0 2 150 362 6.4 759
Saul Kere Lake 5 2 0.5 0.3 0.5 45 48 7 122
Kudlu Lake 0 0 3 0 1 190 420 6.8 764
Lake opp accenture/Ecospace 0 0 5 0 2 160 690 6.9 1340
Kasavanahalli Lake 0 0.5
1-3(close to 3) 0 0.5 125 824 7.3 1620
Kaikondrahalli Lake(center) 20-30 0
<1(0.5-0.7) 0 0.5 95 979 7.1 1780
Kaikindrahalli Lake(inlet) 0 0 1 0 0.5 30 1000 7.7 1780
Doddakanalli Lake 0 0 0 3 0.5 55 99 6.8 230
Rayasandra Lake 5 5 3 0 2 140 596 7 1190
Adarsh Palm retreat 0 0.5 1 0 2 160 566 7.2 1130
Hosa Lake(Middle) 20-30 5(>5) 1-3(>1) 0 1 205 379 6 801
Acceptable Limits 45 3 0.5 0.3 0 200 500 6.5-8.5 N.A
Permissible Limits No relaxation
No relaxation
No relaxation
No relaxation 5 600 2000
No relaxation N.A
Note: The Black bars in all graphs indicates that the concentration of that component in
water is above acceptable limits,
Earthian Internship at Biome Environmental Solution Page 18
DATA ANALYSIS-LAKES OF THE RESULTS OBTAINED:
5
0.5 0.25 0.25
5
2
0 0 0.5
0 0 0
5
0.5
5
0
1
2
3
4
5
6
Nitrites(ppm)
Hosa Lake(boundary)
Halanayakalli Lake
Gatahalli Lake
Hadosidhapura Lake
Lake dew
Saul Kere Lake
Kudlu Lake
Lake opp accenture/Ecospace
3
0.5 0.5 1
2
0.5
3
5
2.8
0.6 1
0
3
1
2
0
1
2
3
4
5
6
Ammonium(ppm)
Ammonium(ppm)
Earthian Internship at Biome Environmental Solution Page 19
0 0.3 0.3
0 0 0.3
0 0 0 0 0
3
0 0 0 0
0.51
1.52
2.53
3.5
Iron(ppm)
Hosa Lake(boundary)
Halanayakalli Lake
Gatahalli Lake
Hadosidhapura Lake
Lake dew
Saul Kere Lake
Kudlu Lake
1
0.5 0.5 0.5
2
0.5
1
2
0.5 0.5 0.5 0.5
2 2
1
0
0.5
1
1.5
2
2.5
Phosphates(ppm)
Phosphates(ppm)
220
40 50 30
150
45
190 160
125 95
30 55
140 160
205
0
50
100
150
200
250
Calcium(ppm)
Hosa Lake(boundary)
Halanayakalli Lake
Gatahalli Lake
Hadosidhapura Lake
Lake dew
Saul Kere Lake
Earthian Internship at Biome Environmental Solution Page 20
410
36 118
15
362
48
420
690 824
979 1000
99
596 566 379
0
200
400
600
800
1000
1200
TDS(ppm)
Hosa Lake(boundary)
Halanayakalli Lake
Gatahalli Lake
Hadosidhapura Lake
Lake dew
Saul Kere Lake
Kudlu Lake
Lake opp accenture/Ecospace
6.1 6.7 6.8
5.9 6.4 7 6.8 6.9 7.3 7.1
7.7 6.8 7 7.2
6
0123456789
pH
Hosa Lake(boundary)
Halanayakalli Lake
Gatahalli Lake
Hadosidhapura Lake
Lake dew
Saul Kere Lake
Kudlu Lake
Lake opp accenture/Ecospace
Kasavanahalli Lake
Earthian Internship at Biome Environmental Solution Page 21
The results of the parameters tested for the bore wells are furnished below:
845
85
264
34
759
122
764
1340
1620 1780 1780
230
1190 1130
801
0
200
400
600
800
1000
1200
1400
1600
1800
2000
EC (µS)
EC (uS)
Earthian Internship at Biome Environmental Solution Page 22
Note: The Black bars in all graphs indicates that the concentration of that component in
water is above acceptable limits,
Name TDS pH E.C Nitrates Nitrites Ammonia Phosphates Iron Calcium Hardness
Wipro Utility 716 6.8 1400 <5 0 0 0.5 0 125
Wipro bus parking 1090 7.2 1950 <5 0 0 0 0 200
Sobha Carnation-Borewell no.1 766 7 1520 5 0 0 2 0 100
Sobha Carnation Borewell no.3 810 7 1590 10 0 0 2 0 160
Raindrops 741 7 1480 30 0 0 0 0 150
BBMP Opp Raindrops 1130 7.2 2000 20 1 0.5 0 0 125
Sindhu Amazon near A Block 636 7.4 1280 50 0 0 0 0 185
Shubh enclave outside Aashram 706 7.2 1400 10 0 0 <0.5 0 140
Shubh Enclave inside Aashram 683 7.2 1370 10 0 0 0 0 140
Trinity Woods And Acres 1000 6.9 1840 0 0 0 0 0 140
Springfield borewell(behind 'I' block) 500 7.3 1040 <5 0 0 0 0 75
Sobha Jasmine 951 7 1760 5 0 0 0 0 170
SJR Verity Veni Block 543 7 1120 20 0 0 <0.5 0 115
SJR Verity Vega Block 534 6.9 1080 30 0 0 <0.5 0 160
Rainbow drive 401 389 7 818 0 0 0 0 0 125
Rainbow drive 137 587 8 1200 20 0 0 0 0 150
Rainbow drive STP 2 721 6.8 1430 <5 0 0 0 0 185
Manjunath House 740 6.9 1460 20 0 0 0.5/<0.5 0 190
SJR Redwoods near Tulip block 615 7 1220 <5 0 0 0.5/<0.5 0 115
Elan near STP 790 6.9 1550 0 0 0 2 5/>5 145
Acceptable Limits 500 6.5-8.5 N.A 45 3 0.5 0 0.3 200
Permissible Limits 2000
No relaxation N.A
No relaxation
No relaxation
No relaxation 5
No relaxation 600
Earthian Internship at Biome Environmental Solution Page 23
DATA ANALYSIS-BOREWELLS OF THE RESULTS OBTAINED:
(Note: The green bars indicate the nitrate content in that bore well to be < 5ppm. The black
bar indicates that the nitrate content is above Acceptable Limits
5 5 5
10
30
20
50
10 10
0
5 5
20
30
0
20
5
20
5
0 0
10
20
30
40
50
60
Wip
ro U
tilit
y
Wip
ro b
us
par
kin
g
Sob
ha
Car
nat
ion
-Bo
rew
ell
no
.1
Sob
ha
Car
nat
ion
Bo
rew
ell n
o.3
Rai
nd
rop
s
BB
MP
Op
p R
ain
dro
ps
Sin
dh
u A
maz
on
ne
ar A
Blo
ck
Shu
bh
en
clav
e o
uts
ide
Aas
hra
m
Shu
bh
En
clav
e in
sid
e A
ash
ram
Trin
ity
Wo
od
s A
nd
Acr
es
Spri
ngf
ield
bo
rew
ell(
beh
ind
'I' b
lock
)
Sob
ha
Jasm
ine
SJR
Ve
rity
Ven
i Blo
ck
SJR
Ve
rity
Veg
a B
lock
Rai
nb
ow
dri
ve 4
01
Rai
nb
ow
dri
ve 1
37
Rai
nb
ow
dri
ve S
TP 2
Man
jun
ath
Ho
use
SJR
Re
dw
oo
ds
nea
r Tu
lip b
lock
Elan
ne
ar S
TP
Nitrates(ppm)
Wipro Utility
Wipro bus parking
Sobha Carnation-Borewell no.1
Sobha Carnation Borewell no.3
Raindrops
BBMP Opp Raindrops
Sindhu Amazon near A Block
Shubh enclave outside Aashram
Shubh Enclave inside Aashram
Trinity Woods And Acres
Springfield borewell(behind 'I' block)
Sobha Jasmine
SJR Verity Veni Block
SJR Verity Vega Block
Rainbow drive 401
Rainbow drive 137
Rainbow drive STP 2
Manjunath House
SJR Redwoods near Tulip block
Elan near STP
Earthian Internship at Biome Environmental Solution Page 24
(Note: The orange bar indicates that the iron content in that bore well is above 5 ppm)
0 0 0 0 0
1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.2
0.4
0.6
0.8
1
1.2
Nitrites(ppm)
Nitrites(ppm)
0 0 0 0 0
0.5
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.1
0.2
0.3
0.4
0.5
0.6
Ammonium(ppm)
Ammonia
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5
0123456
Wip
ro U
tilit
y
Wip
ro b
us…
Sob
ha…
Sob
ha…
Rai
nd
rop
s
BB
MP
Op
p…
Sin
dh
u A
maz
on
…
Shu
bh
en
clav
e…
Shu
bh
En
clav
e…
Trin
ity
Wo
od
s…
Spri
ngf
ield
…
Sob
ha
Jasm
ine
SJR
Ve
rity
Ven
i…
SJR
Ve
rity
Veg
a…
Rai
nb
ow
dri
ve…
Rai
nb
ow
dri
ve…
Man
jun
ath
Ho
use
SJR
Re
dw
oo
ds…
Elan
ne
ar S
TP
Iron
Wipro Utility
Wipro bus parking
Sobha Carnation-Borewell no.1
Sobha Carnation Borewell no.3
Raindrops
BBMP Opp Raindrops
Sindhu Amazon near A Block
Earthian Internship at Biome Environmental Solution Page 25
(Note: The brown bars indicate that the phosphate content in that bore well is < 0.5 ppm)
0.5
0
2 2
0 0 0
0.5
0 0 0 0
0.5 0.5
0 0 0
0.5 0.5
2
0
0.5
1
1.5
2
2.5W
ipro
Uti
lity
Wip
ro b
us
par
kin
g
Sob
ha
Car
nat
ion
-Bo
rew
ell
no
.1
Sob
ha
Car
nat
ion
Bo
rew
ell n
o.3
Rai
nd
rop
s
BB
MP
Op
p R
ain
dro
ps
Sin
dh
u A
maz
on
ne
ar A
Blo
ck
Shu
bh
en
clav
e o
uts
ide
Aas
hra
m
Shu
bh
En
clav
e in
sid
e A
ash
ram
Trin
ity
Wo
od
s A
nd
Acr
es
Spri
ngf
ield
bo
rew
ell(
beh
ind
'I' b
lock
)
Sob
ha
Jasm
ine
SJR
Ve
rity
Ven
i Blo
ck
SJR
Ve
rity
Veg
a B
lock
Rai
nb
ow
dri
ve 4
01
Rai
nb
ow
dri
ve 1
37
Rai
nb
ow
dri
ve S
TP 2
Man
jun
ath
Ho
use
SJR
Re
dw
oo
ds
nea
r Tu
lip b
lock
Elan
ne
ar S
TP
Phosphates(ppm)
Wipro Utility
Wipro bus parking
Sobha Carnation-Borewell no.1
Sobha Carnation Borewell no.3
Raindrops
BBMP Opp Raindrops
Sindhu Amazon near A Block
Shubh enclave outside Aashram
Shubh Enclave inside Aashram
Trinity Woods And Acres
Springfield borewell(behind 'I' block)
Sobha Jasmine
SJR Verity Veni Block
SJR Verity Vega Block
Rainbow drive 401
Rainbow drive 137
Rainbow drive STP 2
Manjunath House
SJR Redwoods near Tulip block
Elan near STP
Earthian Internship at Biome Environmental Solution Page 26
125
200
100
160 150
125
185
140 140 140
75
170
115
160
125
150
185 190
115
145
0
50
100
150
200
250
Calcium Hardness
Calcium Hardness
716
1090
766 810
741
1130
636 706 683
1000
500
951
543 534
389
587
721 740
615
790
0
200
400
600
800
1000
1200
Wip
ro U
tilit
y
Wip
ro b
us
par
kin
g
Sob
ha
Car
nat
ion
-Bo
rew
ell
no
.1
Sob
ha
Car
nat
ion
Bo
rew
ell n
o.3
Rai
nd
rop
s
BB
MP
Op
p R
ain
dro
ps
Sin
dh
u A
maz
on
ne
ar A
Blo
ck
Shu
bh
en
clav
e o
uts
ide
Aas
hra
m
Shu
bh
En
clav
e in
sid
e A
ash
ram
Trin
ity
Wo
od
s A
nd
Acr
es
Spri
ngf
ield
bo
rew
ell(
beh
ind
'I'…
Sob
ha
Jasm
ine
SJR
Ve
rity
Ven
i Blo
ck
SJR
Ve
rity
Veg
a B
lock
Rai
nb
ow
dri
ve 4
01
Rai
nb
ow
dri
ve 1
37
Rai
nb
ow
dri
ve S
TP 2
Man
jun
ath
Ho
use
SJR
Re
dw
oo
ds
nea
r Tu
lip b
lock
Elan
ne
ar S
TP
TDS(ppm)
Wipro Utility
Wipro bus parking
Sobha Carnation-Borewell no.1
Sobha Carnation Borewell no.3
Raindrops
BBMP Opp Raindrops
Sindhu Amazon near A Block
Shubh enclave outside Aashram
Shubh Enclave inside Aashram
Trinity Woods And Acres
Springfield borewell(behind 'I' block)
Sobha Jasmine
SJR Verity Veni Block
SJR Verity Vega Block
Earthian Internship at Biome Environmental Solution Page 27
6.8
7.2
7 7 7
7.2
7.4
7.2 7.2
6.9
7.3
7 7 6.9
7
8
6.8 6.9
7 6.9
6.2
6.4
6.6
6.8
7
7.2
7.4
7.6
7.8
8
8.2
pH
pH
1400
1950
1520 1590
1480
2000
1280 1400 1370
1840
1040
1760
1120 1080
818
1200
1430 1460
1220
1550
0
500
1000
1500
2000
2500
E.C(µS)
E.C(uS)
Earthian Internship at Biome Environmental Solution Page 28
Through our tests, we found out that ammonia was present in a large amount in lakes, way
more than acceptable limits. Also, in Halanayakalli Lake, Gatahalli Lake and Saul Kere Lake
we have iron 0.3ppm. This is because these lakes were very shallow and there can be possible
mixing of water with soil. Also Hadosidhapura Lake and Hosa Lake are surprisingly very
acidic. All the other parameters are below the acceptable limits for all lakes except Calcium
hardness of Hosa Lake.
In the borewell samples, the borewell at Sindhu Amazon near A block has a high content of
Nitrates, above the acceptable limits. Also the water of the borewell at Rainbow drive 137 is
very basic. And the water from Elan was the only sample in the watershed which had iron
dissolved in it. That is very surprising because it may mean that the aquifer from which they
draw water is different from other borewells. The TDS in these water samples are also above
the Acceptable limits but below the permissible limits.
So by looking at this data we can connect the aquifers.
Earthian Internship at Biome Environmental Solution Page 29
Jakkur Lake
Introduction to Jakkur Lake:
1) The Jakkur Lake is in the north-eastern part of the Bangalore city and is one of the largest
and cleanest water bodies in Bangalore. It is the main lake in the chain of lakes comprising of
the Yelahanka Lake upstream and the Rachenahalli Lake downstream. It is about 140 acres
large and has recently been rejuvenated by the Bangalore Development Authority (BDA).
2) Besides being a freshwater lake that provides water to the city, it is particularly special
because it is a potential model for Integrated Urban Water Management (IUWM). This
unique socio-ecological ecosystem highlights the symbiotic relationship between nature and
humankind
3) By serendipity, a sewage treatment plant (STP) with a capacity to treat 10 million litres a
day was set up north of the lake by the Bangalore Water Supply and Sewerage Board
(BWSSB). This treatment plant receives wastewater from about 12,500 households from
areas around Jakkur like Yelahanka.
4) The plant is currently able to let out 8 million litres of treated water into the man-made
wetland that further purifies the water by a natural process before letting it enter the lake.
Therefore the lake is fed with 8 million litres of treated water everyday, which in turn
recharges the ground, increases the water table and fills up the bore-wells and the beautiful
old open wells — heritage structures that adorn this area and are in need of preservation.
Project Objective: We had to do the chemical analysis of the water samples collected at
various locations at Jakkur lake for the following parameters:
pH
Total Dissolved Solids(TDS)
Electrical Conductivity
Nitrates
Nitrites
Ammonium
Phosphates
Iron
Calcium
Results and Discussions:
Earthian Internship at Biome Environmental Solution Page 30
Earthian Internship at Biome Environmental Solution Page 31
Earthian Internship at Biome Environmental Solution Page 32
The results of the chemical analysis area as follows:
Name Nitrates (ppm)
Nitrites (ppm)
Ammonia (ppm)
Iron (ppm)
Phosphates (ppm) Calcium(ppm) TDS(ppm) pH EC(uS)
Jakkur Lake(Shore) 0 0 1 0 2 165 675 7.7 1370
Jakkur Lake( Centre) <5 3 1 0 2 170 728 7.3 1350
Jakkur Lake(Wetland) 0 0 5 0.3 >5 115 703 6.7 1540
JakkurLake (outlet from stp) 0 0 5 0 >5 215 680 7.3 1330
Jakkur Lake(inlet to stp) 0 0 5 0 >5 190 812 7.4 1620
Well outside jakkur Lake(In private field Near fishing place-Staircase to go down inside the well) 0 0 0.5 0 0 95 489 7.7 960
Well outside Jakkur lake(On MainRoad-One well inside another) <5 <0.5 0 0 0 210 616 7.3 1240
Earthian Internship at Biome Environmental Solution Page 33
Borewell inside the STP in Jakkur Lake 0 0 0 0 0 120 421 6.6 859
Acceptable
Limits 45 3 0.5 0.3 0 200 500 6.5-8.5 N.A
Permissible
Limits
No
relaxation
No
relaxation
No
relaxation
No
relaxation 5 600 2000
No
relaxation N.A
(Note: The blue bars indicate that the nitrates in that given water sample is <5 ppm)
(Note: The green bar indicates that the nitrates in that given water sample is <0.5 ppm)
0123456
Nitrates(ppm)
Nitrates(ppm)
00.5
11.5
22.5
33.5
Nitrites(ppm)
Jakkur Lake(Shore)
Jakkur Lake( Centre)
Jakkur Lake(Wetland)
Earthian Internship at Biome Environmental Solution Page 34
(Note: The Ammonium concentration is way above the acceptable limit of 0.5 ppm)
0123456
Ammonia(ppm)
Jakkur Lake(Shore)
Jakkur Lake( Centre)
Jakkur Lake(Wetland)
00.05
0.10.15
0.20.25
0.30.35
Iron(ppm)
Iron(ppm)
0
1
2
3
4
5
6
Phosphates(ppm)
Phosphates(ppm)
Earthian Internship at Biome Environmental Solution Page 35
0
50
100
150
200
250
Calcium(ppm)
Jakkur Lake(Shore)
Jakkur Lake( Centre)
Jakkur Lake(Wetland)
JakkurLake (outlet from stp)
0100200300400500600700800900
TDS(ppm)
Jakkur Lake(Shore)
Jakkur Lake( Centre)
Jakkur Lake(Wetland)
JakkurLake (outlet from stp)
0200400600800
10001200140016001800
EC(µS)
EC(uS)
Earthian Internship at Biome Environmental Solution Page 36
66.26.46.66.8
77.27.47.67.8
pH
pH
Earthian Internship at Biome Environmental Solution Page 37
Rain Water Harvesting Projects
Assignment 1:
This rain water harvesting project at Sobha Quartz was a two stage process.
Stage 1: Mapping the entire rain water collection piping system in the basement area at
Sobha Quartz.
Stage 2: Doing the level translation of the pipes in the various sections of the apartment to
the sump for the re-plumbing work to be carried out
Background:
The RWH system (for storage and reuse) at SOBHA Quartz currently comprises 3 systems,
namely –
1. the fire room system,
2. swimming pool filtration system
3. lift area system
The rooftop down takes are redirected to HDPE tanks (in each of these locations) and then is
pumped to the raw water sump. Such a system was implemented primarily due to a limitation
enforced by the residents requesting that no hole be made in the existing sump. Hence water
from the 3 systems is pumped through an existing 3” pipe (existing bore well inlet) into the
raw water sump. This results in overflow from the HDPE tanks as the 3” pipe is not always
sufficient to handle the full flow of water.
Hence it has now been decided to route all the pipes to the sump directly. For this core
cutting will be required to make 2 new 10” inlets into the sump. All the 40 downtakes will be
redirected into one of these 10” inlets into the sump.
Currently only 32 of the 40 pipes have been connected to the RWH system as it was observed
that 8 of the pipes carried water other than rooftop runoff water. Hence it will be required that
all the contaminating lines are disconnected from these 8 downtakes so that it can be
connected to the raw water sump
The levels of all pipes do not allow for a continuous gravity flow to the sump. However given
the availability of the overall head (10 floors) it has been assumed to be ok to not always
allow for a positive slope to the sump. This is especially applicable to lift area system where
the pipes will hold water for about 200ft - 300ft due to the negative slope. Provision will be
made to drain this water into the existing HDPE tanks placed at the location. This is a risk
Work Details:
Earthian Internship at Biome Environmental Solution Page 38
1) We first mapped all the pipes which were collecting the rooftop run off water and taking it
to the sumps near the fire room system, the swimming pool filtration system and the lift area
system.
2) A detailed pictorial representation was made by us.
(Mapped Piped System Diagrams are given below)
Piping near the Fire Room Tank
Earthian Internship at Biome Environmental Solution Page 39
Piping near the Lift Room Tank
Piping near the Swimming Pool Area
Earthian Internship at Biome Environmental Solution Page 40
3) Level Translation for Re-plumbing:
The heights were projected using the tubular-water level method .By this we shall come to
know the required heights of the new pipes that need to be installed.
Given below are the measurements of the various projections on the wall (Near the Fire
Room):
Earthian Internship at Biome Environmental Solution Page 41
Assignment 2:
Ground Water Recharge Proposal for Trinity Acres and Woods Society(Sarjapur
Road)
We made an exhaustive proposal report for the groundwater recharge at Trinity Acres
and Woods Society. This report was based on the concept of building recharge wells
in the campus for recharging the aquifers.
The following was provided in the report following :
1)Detailed area calculations of various catchment areas
2)Data of the various catchment areas available for recharge
3)BWSSB Considerations for recharge
4)Positioning of each recharge well
5)Details regarding the collection of water from the various catchment areas to the
recharge wells
6)Diagrammatic representation of the recharge wells with the drains
7)Costing of various recharge wells, drains, cattle traps, RCC slabs, etc and the net
project cost
8) Appendix: Rainfall pattern and Rainwater harvesting strategies for Bangalore
Work Details:
The report is as furnished below:
Earthian Internship at Biome Environmental Solution Page 42
Ground Water Recharge Solutions for Trinity Wood and Acres
1. Customer Details
1.1 Contact Info
Name and Address of Customer Trinity Acres and Woods,
Ambalipura ,Sarjapura Main Road,
Sector 1,HSR Layout,
Bangalore.
Karnataka
Customer Type Apartment
Contact Person name Mr.Basavaraj Deodurg
Contact Phone number – Land line -
Contact Phone number – Mobile 9845039450
Email id [email protected]
Date of Visit 13th
June 2014
Date of Report 23rd
June 2014
1.2 A Brief Overview
Trinity Woods and Acres is a 7.5 acres apartment complex with 284 homes (Trinity Acres:
176 Apartments. East Wing 11 Blocks & West Wing 11 Blocks. Trinity Woods: 108
Apartments East 2 Blocks and West 2 Blocks) on Sarjapura Road. The current water is
supplied by tankers rainwater and groundwater. Water demand for Trinity Woods and Acres
from tankers is 180KL and from bore wells it is 20 KL. It has one working bore well and one
non- working bore well. It is in this context that Biome has been approached to provide an
Earthian Internship at Biome Environmental Solution Page 43
appropriate groundwater recharge solution. The society management wishes Biome to
provide solutions to Ground Water Recharge.
1.3 Water management at Trinity Woods and Acres
Source of water in Trinity Woods and Acres is currently rainwater, tanker water and
bore wells. Trinity Woods and Acres have one sump where all the water collected is
stored.
Water is used for all household consumption of apartments from this sump. There also
exists one septic tank where all the sewage from the household is collected.
There exist storm drains on both the sides of the layout.
Rainwater harvesting system is done in the Trinity Acres and not in Trinity Woods.
The rainwater harvested is put in the common sump which is used by the society.
Also, this sump collects the water from the private tankers.
2. Ground Water Recharge Calculations at Trinity Woods and Acres:
NOTE: Rainfall Calculations:-
Volume of rainfall in the given area(in kL):
= Area (sq.m)*(X mm of rainfall)*0.001*(Runoff Coefficient)
Runoff coefficient for rooftop area=0.9
Runoff coefficient for non- rooftop area=0.5
# Given below is the general schematic map of the entire campus:
NOTE: All distances in schematic diagrams are in metres.
Earthian Internship at Biome Environmental Solution Page 44
Football Ground 30.3
24.5
7.6
7.6
6.5
6.5
Trinity Woods East
Trinity Woods West
Garden
Sarjapuraroad In Gate Out Gate
Area=30.6
*24.5
158.3
6.2
15.3
6.5 5.7
25.5
Clubhouse
Underground
Sump
Tennis Court
Trinity Acres West
Trinity Acres East
Garden
Garden
Underground
Septic Tank
Borewell
LAKE
105.7
105.6
78.5
44.5
34.1
Earthian Internship at Biome Environmental Solution Page 45
A) Various Catchment Areas in Trinity Woods and Acres:
Catchment Description Area(sq.m)
Annual
rainfall
970mm(kL)
30mm
rainfall(kL)
20mm
rainfall(kL)
BWSSB
No.(kL)
Trinity Acres
Rooftop Area(EAST+WEST) 5857 5113 158 105 117
Non-Rooftop Area(EAST+WEST) 4050 1964 61 73 41
Club House 750 654 20 13 15
Garden Area 606 294 9 6 NA
Trinity Woods
Rooftop Area(EAST+WEST) 10354 9039 280 186 207
Non-Rooftop Area(EAST+WEST) 5703 2766 86 103 57
Football Court 1682 816 25 17 NA
TOTAL
BWSSB
Water to
be
Harvested
20646 639 503 437
TOTAL RAINFALL RUNOFF(kL)
NOTE:
1. The daily requirement of Trinity Acres and Woods is 200kL.Hence for
365 days(annual requirement), the requirement is 73000kL.
2. For a 970 mm annual rainfall, the total rainfall runoff on the campus is
20,646kL which is 28.28 % of the annual requirement.
B) Details of catchment areas available for recharge in the campus:
Earthian Internship at Biome Environmental Solution Page 46
i. Rooftop Areas:
ii. Non-Rooftop Areas:
Catchment
Description(NON
ROOFTOP AREA)
Area(sq.m)
Annual
rainfall
970mm(kL)
30mm
rainfall(kL)
60mm
rainfall(kL)
20 mm
rainfall(kL)
Catchment Description Area(sq.m)
Annual
rainfall
970mm(kL)
30mm
rainfall(kL)
20mm
rainfall(kL)
Trinity Woods
0.25 of the Rooftop Area of
Trinity Woods goes to the
lakes
2589(0.25*10354)
2260 70 47
0.75 of the Rooftop Area of
Trinity Woods can be
recharged
7766(0.75*10354) 6779 210 140
Club House
All the rooftop area of the
Club House can be recharged 750 654 20 13
Trinity Acres
0.25 of the Rooftop Area of
Trinity Acres goes to the
drain
1464 1278 40 26
0.50 of the Rooftop area of
Trinity Acres goes to RWH
sump
2929 2557 79 53
0.25 of Rooftop area of
Trinity Acres is available for
recharge
1464 1278 40 26
TOTAL ROOFTOP(For
Harvesting)(Adding the
blocks in blue)
9980 8711 270 179
Earthian Internship at Biome Environmental Solution Page 47
Trinity Acres
Open Area of Trinity
Acres West facing
towards the lake 1060 514 16 32
10.6(Not to be
counted as it is
going to the
lake)
Open area of Trinity
Acres East facing
towards Villa Del
Morte 1060 514 16 32 10.6
In between
pathway(Till Club
House)-Starting from
gate 1407 683 21 42 14
Pathway between
Club House and
Trinity Acres(Left
Side) 87 42 1 3 0.86
Front Path way
horizontal(near
entrance) 437 212 7 13 4.37
Garden Area(Both
the gardens near
EAST and WEST) at
the entrance 606 294 9 18 6
Trinity Woods
Extreme left (Starting
from Club house
end)(EAST) towards
Villa Del Morte 1241 602 19 37 12.4
Pathway between
Club House and
Trinity Woods(EAST
SIDE) 159 77 2 5 1.6
Pathway from the
Circle Between the
two blocks 1416 687 21 42 14.15
Extreme
right(towards the 1205 584 18 36 12
Earthian Internship at Biome Environmental Solution Page 48
lake)(WEST)
Football Ground
(ALL WATER IS
GOING TO THE
LAKE) 1682 816 25 50 16.8
TOTAL NON
ROOF TOP(For
Harvesting)(Adding
the blocks in blue) 6413 3111 96 192 64
Area(sq.m) 20 mm rainfall(kL)
TOTAL ROOFTOP AREA 9980 179
TOTAL NON ROOFTOP
ARE
6413 64
TOTAL AREA TO BE
HARVESTED
16393 243
Hence the total volume of water that is available for recharge is the addition of all the
cells in the above tables which are blue coloured (For 20 mm rainfall assuming the
runoff coefficients) which is equal to 243 kL
NOTE: We are not including football court and tennis court runoffs as it goes to the
lake.
C. BWSSB Recharge Value:
According to BWSSB standard about 20 litres/m2 of the rooftop and 10-litres/ m2 of paved
area rainwater needs to be harvested or groundwater recharge with no runoff coefficient
added.
Referring to Table 2 A: All the rooftop area has been multiplied by 20 and non rooftop
area(paved area) has been multiplied by 10 to obtain the BWSSB recharge value of 437
kL.(Note: We are not including the gardens, football and tennis courts for BSWWB
calculations)
Earthian Internship at Biome Environmental Solution Page 49
D. Proposal:
We are going to recharge roughly about 243kL of rainfall by building recharge wells.
So, for 243kL capacity, we are proposing to build 7 recharge wells of the following capacity:
(i) 5 recharge wells of 32 kL capacity
(ii) 2 recharge wells of 17 kL capacity
(Note: We are assuming 100 % recharge of the water that falls in the recharge
wells)
Given that Trinity Acres has rainwater harvesting with storage facility implemented,
recharge options can be implemented for their bore well. Hence, for the campus the
following strategy is proposed:
We are creating recharge capacity by digging 7 recharge wells and redirecting rainwater to
it. The recharge well description is as follows:
(Please refer to the schematic diagram representation)
Earthian Internship at Biome Environmental Solution Page 50
Football Ground 30.3
24.5
7.6
7.6
211.3
6.5
6.5
Trinity Woods East
Trinity Woods West
R1 6 ft X 40 ft Capacity: 32KL
Garden
R2 6 ft X 40ft Capacity: 32KL
RWH
Sarjapuraroad In Gate Out Gate
30.6
158.3
18.5
6.8
6.2
15.3
6.5 5.7
7.6
25.5
Clubhouse
Underground
Sump
Tennis Court
4.7
Trinity Acres West
Trinity Acres East
Garden
Garden
Underground
Septic Tank
Borewell
R3 6 ft X 40 ft Capacity: 32KL
R4 5 ft X 30 ft Capacity: 17KL
R5 5 ft X 30 ft Capacity: 17KL
R6 6 ft X 40 ft Capacity: 32KL
R7 6 ft X 40 ft Capacity: 32KL
Trinity Acres West
LAKE
Earthian Internship at Biome Environmental Solution Page 51
#The catchment area and recharge wells capacity measurements:
Recharge water in R1 Area(sq.m)
Annual
Rainfall
(970mm
kL)
30mm
Rainfall
(kL)
20mm
Rainfall
(kL)
Total
capacity
(for 20mm)
KL
Well
Dimensions
(ft*ft)
Well
capacity
(kL)
Rooftop before R1 2590 2261 70 47 53 6*40 32
Non Roorftop before R2 645 313 10 6
Recharge for R2 Area(sq.m)
Annual
Rainfall
(970mm)
30mm
Rainfall
(kL)
20mm
Rainfall
(kL)
Total
capacity
(for 20mm)
KL
6*40 32
Rooftop before R2 2590 2261 70 47 53
Non Rooftop before R2 645 313 10 6
Recharge for R3 Area(sq.m)
Annual
Rainfall
970mm
(kL)
30mm
Rainfall
(kL)
20mm
rainfall
(kL)
Total
capacity
(for 20mm)
KL
6*40 32
Rooftop for R3 2588 2260 70 47 60
Non Rooftop for R3 1364 661 20 14
Recharge for R4 Area(sq.m)
Annual
Rainfall
970 mm
(kL)
30mm
Rainfall
(kL)
20mm
rainfall
(kL)
Total
capacity
(for 20mm)
KL
5*30 17
Rooftop for R4 1827 1595 49 33 38
Non Rooftop for R4 510 247 8 5
0
Earthian Internship at Biome Environmental Solution Page 52
Recharge for R5 Area(sq.m)
Annual
Rainfall
(970mm
kL)
30mm
Rainfall
(kL)
20mm
rainfall
(kL)
Total
capacity
(for 20mm)
KL
5*30 17
Rooftop for R5 823 719 22 15 18
Non Rooftop for R5 289 140 4 3
Recharge for R6 Area(sq.m)
Annual
Rainfall
(970mm
kL)
30mm
Rainfall
(kL)
20mm
rainfall
(kL)
6*40 32
Rooftop for R6 1839 1606 28 33 49 kL
(Includes
club house
rooftop
50% also )
Non Rooftop for R6 1600 776 24 16
Recharge for R7 Area(sq.m)
Annual
Rainfall
970mm
( kL)
30mm
Rainfall
(kL)
20mm
Rainfall
(kL)
Total
capacity
(for 20mm)
KL
6*40 32
Rooftop for R7 631 551 17 11 20
Non rooftop for R7 867 421 13 9
The locations and the well description is as follows:
R1(6 ft X 40 ft Capacity: 32KL) : Located near the small passage between the blocks of
Trinity Woods.
Water collection: Will collect water from Trinity Woods West rooftop runoff, runoff from
the passage between Trinity Woods East and Trinity Woods West and the rooftop runoff
from Trinity Woods East(Collection till the middle passage way of Trinity Woods West)
Earthian Internship at Biome Environmental Solution Page 53
R2(6 ft X 40ft Capacity: 32KL): Located at the Garden in Trinity Woods (West) Starting
Point.
Water collection: Will collect water from Trinity Woods West rooftop runoff, runoff from
the passage between Trinity Woods East and Trinity Woods West and the rooftop runoff
from Trinity Woods East (Collection from the entry to Trinity Woods till the first passage
way in Trinity Woods West)
Earthian Internship at Biome Environmental Solution Page 54
R3(6 ft X 40 ft Capacity: 32KL): Located between Trinity Woods (East) and the Club
House
Water collected: Will collect water from the rooftop runoff from Trinity Woods East via the
drains which are located to the left side of Trinity Woods East.
R4(5 ft X 30 ft Capacity: 17KL): Second Open Space Passage in Trinity Acres (West)
Water collected: Will collect water from the rooftop runoff from the Club House, the runoff
from the passage between Trinity Acres East and West, the rooftop runoffs from Trinity
Acres East and West. The overflow from here will go to R5 and R7.
Earthian Internship at Biome Environmental Solution Page 55
R5(5 ft X 30 ft Capacity: 17KL): First Open Space Passage in Trinity Acres (West)
Water collected: Will collect water from the runoff from the passage between Trinity Acres East
and West, the rooftop runoffs from Trinity Acres East and West till the speed breaker and from the
overflow of R4.The overflow from here will go to R5.
Earthian Internship at Biome Environmental Solution Page 56
R6(6 ft X 40 ft Capacity: 32KL): Located at the extreme left of the Trinity Acres East Block (near
entrance-Close to Septic Tank)
Water collected: All water between Trinity Acres East and the Club House and the rooftop runoff
of Trinity Acres East. Also the overflow of the Garden in front of the east wing goes to R6.It also
collects water from the entry drain parallel to Sarjapur Road.
R7(6 ft X 40 ft Capacity: 32KL): Located near the bore well. (Near Trinity Acres West Block)
Water collected: All the water falling post the first open passage space of Trinity Acres West is
collected. It includes, the rooftop runoffs from Trinity Acres East and West (post the first open
passage space and towards the entrance), the runoffs from the passage between Trinity Acres East
and West and the water from the drain at the entrance parallel to Sarjapur Road. Since it is of 32KL
capacity, it can take the overflow of R4 and R5.
4. RWH Strategies
As discussed Trinity Woods and Acres already has rainwater harvesting system
implemented. Hence, only recharge for the bore well is being proposed. In and around
Bangalore it has mostly been observed that the recharge rates at about 20-30ft depth
are extremely good. Recharge wells upstream of the bore well could potentially
recharge the aquifer from where the yielding bore well draws its water.
5. Ground Water Recharge Strategies
Since the campus has only 1 already dug bore well, seven recharge wells of the
following dimensions are proposed for the recharge of this bore well:
6ft Diameter and 40 ft deep (viz.R1,R2,R3,R6,R4)
5ft Diameter and 30ft deep(Viz.R4,R5)
(Please refer to the above schematic diagram for the exact positioning of the recharge wells)
The capacity of these recharge wells are as follows:
6ft Diameter and 40 ft deep:32kL
5ft Diameter and 30 ft deep:17kL
6. Next Steps:
Earthian Internship at Biome Environmental Solution Page 57
The suggestion is to start the work with one 5 feet diameter and 30 feet deep (R5)
well and one 6 feet diameter and 40 feet deep well (R7) and depending on the
recharge capacity, the work can be progressed, either after one rainy season or after
performing a slug test.
Illustration a: Silt trap and In-drain filter Illustration b: A Completed Recharge Well
Illustration c: Indicative drawing for recharge well
Earthian Internship at Biome Environmental Solution Page 58
7. Commercials for implementation
RECHARGE WELL (6 Feet Diameter & 40 Feet Depth) FOR ONE WELL COST
(R1,R2,R3,R6,R7)
S No Description Unit Rate(Rs) Amount
RECHARGE WELL ( 6 Feet
Dia & 40 Feet Depth)
Digging a Ground water
recharge well, arranging
Cement
Rings, packing with
aggregates like stone/
marble/kadapa around,
Shifting Dug up soil.
Dewatering extra if it happens.
The depth
May be 10% difference and it
depends on soil condition and
Weather and can be adjusted
accordingly. No digging
possible if we
Hit the rock. Cement
concrete of 5 to 6 inches thick
is packed around
The ring at the ground level.
40 40*3300 132000
2 6ft diam slab with 2'x2' manhole
cover
1 Nos 1*15000 15000
Earthian Internship at Biome Environmental Solution Page 59
3 Providing 2 Nos Safety grills
with Openable 2’ x 2’Manhole
at the center
2 Nos 2*10000 20000
Total- Rs 167000
RECHARGE WELL (5 Feet Diameter & 30 Feet Depth) FOR ONE WELL COST (R5,R4)
S No Description Unit Rate(Rs) Amount
1 RECHARGE
WELL ( 5 Feet Dia &
30 Feet Depth)
Digging a Ground
water recharge well,
arranging Cement
Rings, packing with
aggregates like stone/
marble/kadapa
around,
Shifting Dug up
soil. Dewatering extra
if it happens. The
depth
May be 10%
difference and it
depends on soil
condition and
Weather and can be
adjusted accordingly.
No digging possible if
we
Hit the rock.
Cement concrete of 5
to 6 inches thick is
packed around
The ring at the
ground level.
30 30*2900 87000
2 6ft diam slab with
2'x2' manhole cover
1 Nos 1*14000 14000
3 Providing 2 Nos
Safety grills with
Openable 2’ x
2’Manhole at the
center
2 Nos 2*10000 20000
Total-Rs 121000
Earthian Internship at Biome Environmental Solution Page 60
Recharge Well Dimensions Location Cost(INR) Remarks
R1 6ft*40ft
Located near the
small passage
between the blocks
of Trinity Woods. 167000
R2 6ft*40ft
Located at the
Garden in Trinity
Woods (West)
Starting Point. 167000
R3 6ft*40ft
Located between
Trinity Woods
(East) and the Club
House 167000
R4 5ft*30ft
Second Open Space
Passage in Trinity
Acres (West) 121000
R5 5ft*30ft
First Open Space
Passage in Trinity
Acres (West) 121000
R6 6ft*40ft
Located at the
extreme left of the
Trinity Acres East
Block (near
entrance-Close to
Septic Tank) 167000
Care should be
taken while
digging the
well as it is
near the septic
tank
R7 6ft*40ft
Located near the
bore well. (Near
Trinity Acres West
Block) 167000
Recharge rate
for the
considered
well should be
accounted first
TOTAL COST 10,77,000
Earthian Internship at Biome Environmental Solution Page 61
# Cost of other utilities involved for installing the recharge system:
COSTS FOR DRAINS AND RCC SLABS REQUIRED FOR EACH
RECHARGE WELL (for water collection) in INR
Utility Cost per
foot(INR) R1 R2 R3 R4 R5 R6 R7
Drain with Cattle
Trap(1.5 ft deep and 1.5
ft broad)
3000 NA NA 90000 NA NA NA NA
Drain with RCC
Slabs(1.5 ft deep and
1.5 ft broad)
2000 42000 42000 NA 44000 44000 NA 44000
Chamber 15000 15000 15000 NA 15000 15000 NA 15000
Connection between
chambers and recharge
wells(2ft x 6inch pipe)
NA 15000 15000 15000 15000 15000 15000 15000
TOTAL 72000 72000 105000 74000 74000 15000 74000
# Net Costing:
(Please note this is cost estimation not a quotation)
Cost(INR) R1 R2 R3 R4 R5 R6 R7
Only recharge well cost
167000
167000
167000 121000 121000 167000 167000
Cost of utilities 72000 72000 105000 74000 74000 15000 74000
Net Cost 239000 239000 272000 195000 195000 182000 241000
NET PROJECT COST 15,63,000
Earthian Internship at Biome Environmental Solution Page 62
#Cattle Trap:
#Drain with RCC Slab:
Earthian Internship at Biome Environmental Solution Page 63
8. Biome’s Commercials for implementation
The given proposal can also be implemented in a phased/partial manner with
modifications. The proposal attempts to list all feasible options of RWH
implementation and is a basis for further discussion.
Biome’s design and supervision fee will be depending upon the scope of project
implementation.
All payments to be made by cheque to the name of “Biome Environmental Solutions
Pvt. Ltd.”, A/c payee crossed. Service Taxes if applicable will be charged extra at
around 12.36 %.
Earthian Internship at Biome Environmental Solution Page 64
9. APPENDIX - Rainfall pattern and Rainwater harvesting strategies for Bangalore
The following are details about the rainfall pattern in Bangalore and drive design:
Parameter Measure
Total Annual average rainfall 970 mm
Total no of rainy days 60 rainy days
Peak hour intensity of rain in Bangalore 60 mm/hr
The rainfall distribution pattern in Bangalore is as follows:
MONTH DAYS QUANTITY (mm)
JAN 0.2 2.70
FEB 0.5 7.20
MAR 0.4 4.40
APR 3.0 46.30
MAY 7.0 119.60
JUN 6.4 80.80
JUL 8.3 110.20
AUG 10.0 137.00
SEP 9.3 194.80
OCT 9.0 180.40
NOV 4.0 64.50
DEC 1.7 22.10
TOTAL 59.8 970.00
It can be observed from the above table that Bangalore is blessed with a relatively well-distributed
rainfall and has a rainfall distribution, which is bi-modal (two peak rainfall seasons in a year). In this
context, and given Bangalore’s geology, rainwater harvesting strategies appropriate for Bangalore has
been found to be the following in their respective order of priority.
a) Storage of rainwater for direct use: Priority is given to capture as much of the run-off
Earthian Internship at Biome Environmental Solution Page 65
rainwater in storages such as sumps, on-ground tanks or tanks on terraces at intermediate
levels (eg: sitouts / balconies). However for such a strategy, the run-off only from clean areas
can be tapped. It is important that these catchment areas are free from any form of chemical
or other toxic contamination and dust content is as low as possible. Typically roof areas
qualify well for such a strategy. The water from this run-off is first rain separated, filtered and
then let into the storage. The water can be used for all household purposes such as bathing,
washing, cleaning, gardening etc directly and can even be used for potable purposes if
subsequently it is passed through filters to deal with bacteriological contamination (Eg: aqua
guard filters, boiling etc). However, this requires that roof areas be kept clean and there is no
junking of material on the roof or movement of pets such as dogs and cats on the roof and
there is no soap water washing of the roof area. In apartments these forms of contamination
are often observed in private terraces. A water testing process prior to use for drinking and
cooking purposes is recommended. Subsequently regular potability tests are also
recommended.
b) Groundwater recharge: Excess run-off from above mentioned clean surfaces, run-off from
other surfaces such as roads, garden area etc can then be redirected for groundwater recharge.
In the context of Bangalore, the most effective recharge structure has been found to be a
recharge well whose depth is a minimum of around 15 - 20 feet. These recharge wells
recharge the shallow aquifer. Water needs to be desilted adequately before allowing the water
into recharge wells. The location of the recharge wells need to be chosen strategically – both
where significant run-off water passes through the recharge well location and which is close
to existing ground water sources of water. Recharge wells, over time will help replenish
groundwater. If the ground water table rises above the bottom of the recharge well, the
recharge well can be used as a withdrawal well. Recharge wells are likely to help recharge
local borewell sources of water though such guarantees cannot be provided. The diagram
below illustrates the principle of recharge.
Earthian Internship at Biome Environmental Solution Page 66
Assignment 3:
1. To measure the capacity of the rainwater harvesting storage tank installed in Sindhu
Amazon Apartments(Outer Ring Road-Bangalore)
2. To do a proportional isometric view of the tank
3. To represent the tank(with compartments) in a three dimensional format for easy
understanding
Work Details:
1. A rain water tank was under construction in the Sindhu Amazon apartment complex
for collecting the rain water, filtering it and then allowing it to go to the society sump.
2. There existed three compartments in the tank installed :
The first compartment collects the roof top water .The overflow of the
first compartment is directed to the second compartment.
The second compartment of the tank comprises of a filtration assembly (gelly and
pebbles-Not yet installed) to filter the impurities. The filtered water from the
second compartment in then channelized to the third compartment.
The water from the third compartment is then directed to the underground sump that
is used by the residents
3. We took the measurements of each compartment and produced it in our engineering
drawing (Isometric View)
RWH Tank
Earthian Internship at Biome Environmental Solution Page 67
4. A three dimensional diagram was also made for easier understanding of the tanks and
stages of water movement.
Isometric View (RWH Tank) With Measurements
Taking the measurements
Earthian Internship at Biome Environmental Solution Page 68
Three Dimensional View of the RWH Tank
Earthian Internship at Biome Environmental Solution Page 69
Construction of a Biosand Filter
1) Introduction:
• The biosand filter is about 1 m tall, 0.3 m wide on each side and adapted from the
traditional slow sand filter so that it does not flow continuously, making it suitable for
use in people’s homes.
• The filter container can be made of concrete or plastic. It is filled with layers of
specially selected and prepared sand and gravel.
• The sand removes pathogens and suspended solids from contaminated drinking water.
• A biological community of bacteria and other micro-organisms grows in the top 2 cm
of sand. This is called the biolayer.
• The micro-organisms in the biolayer eat many of the pathogens in the water,
improving the water treatment.
2) Water that can be used for filtration:
• Water in the biosand filter – well water, borehole water, pond or river water, tap-stand
water, or rainwater.
• The water must not have been chlorinated though, or the chlorine will kill the
biolayer.
Earthian Internship at Biome Environmental Solution Page 70
• The water should also not contain any dangerous chemicals, because the biosand filter
cannot remove most chemicals from water.
3) Functioning of each part of the Biosand Filter:
1) Lid: • Prevents contamination and keeps out unwanted pests
2) Reservoir:
The top of the filter is called as the reservoir and it can hold about 12 litres, or 1 bucket
of water.
3) Diffuser: • It has small holes in it so that water slowly drips through the sand
• It prevents disturbing the filtration sand and protects the biolayer from damage when the
water is poured in the filter
4) Standing Water:
• When the water stops flowing, there should be 5 cm of water on top of the sand. This
layer of water protects the top of the sand and the biolayer from the force of the dripping
water.
Earthian Internship at Biome Environmental Solution Page 71
• The standing water also keeps the biolayer wet.
• The biolayer will die if it dries out.
• The biolayer needs oxygen.
• Some oxygen can still get to the biolayer through 4 to6 cm of water.
• But if there is more than 6 cm of water, the biolayer may die from lack of oxygen.
5) Filter Container:
• Can be concrete/plastic
• Can be square/round
6) Filtration Sand:
• Sand removes almost all the dirt and the pathogens from the water
Earthian Internship at Biome Environmental Solution Page 72
7) Separation Gravel:
• It stops the sand particles from moving down and blocking the outlet tube
8) Biolayer:
• The biolayer is the toplayer of sand (1-2 cm or 0.8” deep), where very small microbes
live.
• You cannot see them - they are too small.
• They eat the pathogens in the water
• This layer also develops in conventional slow sand filters, where it is called the
schmutzdecke
Earthian Internship at Biome Environmental Solution Page 73
9) Drainage Gravel:
• The large gravel stops the small gravel from moving and blocking the outlet tube.
• The large gravel is too big to get inside the outlet tube.
10) Outlet Tube:
• Can be of plastic/copper
4) Specifications of the sand to be used:
Earthian Internship at Biome Environmental Solution Page 74
5) Pathogens and dirt removal mechanism:
Pathogens and suspended solids are removed through biological and physical processes that take
place in the sand. These processes include: mechanical trapping, predation, adsorption, and
natural death
6) What can the biosand filter remove from water:
The biosand filter has been studied in the field and in labs. It has been shown to remove the following from contaminated water:
Up to 100% of helminths (worms)
Up to 100% of protozoa
Earthian Internship at Biome Environmental Solution Page 75
Up to 98.5% of bacteria
70-99% of viruses
The filter can also remove up to 95% of turbidity (dirt and cloudiness), and up to 95% or iron (which people often don’t like because it turns water, laundry and food red!). Like other filters, the biosand filter cannot remove dissolved contaminants or chemicals, such as salt, arsenic or fluoride.
7) Biolayer:
The biolayer is the key component of the filter that removes pathogens. Without it, the filter
removes about 30-70% of the pathogens through mechanical trapping and adsorption. The
ideal biolayer will remove up to 99% of pathogens. It may take up to 30 days for the biolayer
to fully form. During that time, the biolayer gets better at removing pathogens. The biolayer
is NOT visible – it is NOT a green slimy coating on top of the sand. The filtration sand may
turn a darker colour, but this is due to the suspended solids that have become trapped. The
time for the formation of the biolayer varies from filter to filter. The length of time it will
take(for the process) depends on the amount and source of water being used.The water from
the filter can be used during the first few weeks while the biolayer is being established, but
you still need to disinfect the water.
8) Pause Period:
• The biosand filter is most effective and efficient when operated intermittently (not
constantly flowing) and used consistently (every day). There must be a rest period or
pause period between uses.
• The pause period should be a minimum of 1 hour after the water has stopped flowing,
up to a maximum of 48 hours.
• The pause period is important because it allows time for the micro-organisms in the
biolayer to consume the pathogens in the water. This should be a minimum of 1 hour.
Earthian Internship at Biome Environmental Solution Page 76
• If the pause period is extended for too long (over 48 hours), the micro-organisms will
eventually eat all of the nutrients and pathogens in the water and then die from
starvation. If the microbes in the biolayer die, the filter will not work as well or
remove as many pathogens when it is used again.
• A long pause period may also cause the standing water in the filter to evaporate,
causing the biolayer to dry out and die.
9) How did we develop our biosand filter:
Stage 1(Thought Process):
We had the vision of constructing a biosand filter that can be easily made by anyone
with very few and easily available resources. Initially we thought of making it in a
huge plastic barrel. Then we realised that this would require a lot of sand and gravels
.Also, the availability of this barrel can be a problem. Hence we decided to scrap this
idea and we chose a Bisleri 20 L plastic barrel for the filter body.
Stage 2(Implementation ):
The Bisleri water bottle is light in weight, it is easily available and the fabrication also
wasn’t that complicated as compared to the earlier barrel used.The sand and gravel
requirements would also be very less as compared to our earlier design version.
Earthian Internship at Biome Environmental Solution Page 77
Phase 1:
An important task was to collect the sand and gravels and wash it thoroughly. We
collected sand of the required type from a local residential construction site (near our
office) and removed all the impurities present in it by water wash.
The sand washing was a long and tedious task as we had to ensure that all the clay and
impurities had gone away.
After the sand was washed, we kept it to dry to evaporate the water.
Earthian Internship at Biome Environmental Solution Page 78
Phase 2:
The next stage was to do the required layer markings on the Bisleri bottle for the
various sand and gravel layer heights.
Then we drilled the holes in the bottle for the pipe and fitted the pipe at the required
position so that the siphoning action takes place.
We added the gravels and sand without leaving any voids within the marking
territories.
After this we added charcoal (washed) at the topmost layer so that it can adsorb the
impurities and increase the filtration efficiency.
Phase 3:
We then tested the volumetric flow rate of this filter and it came out to be 5ooml/min
which is above the prescribed minimum limit of 400 ml/min and it is not very high
also.
Adhering to the pause period need, we would pour water everyday inside the filter.
Water would be added once every day(Till 15th
July 2014) for the biolayer formation
to occur.
The biolayer would be formed by 30th
July 2014(given that it takes 20-30 days for
formation at the top)
Stage 3(Innovation, Further Studies and Maintenance):
We are hereby suggesting the following innovation and research studies that can be
done on the Biosand Filter:
Current Scenario:
The biolayer is the most important layer in the Biosand Filter and without it the
Biosand Filter would be of no use. The biolayer formation takes about 20-30 days and
Earthian Internship at Biome Environmental Solution Page 79
is formed naturally. The formation of the biolayer also depends on the climatic
conditions and the formation period varies form one filter to another and also is
affected by climatic conditions. So, you have to depend on nature completely for the
formation of the biolayer.
What did we think about?
We thought about developing a man made biolayer.
How can it be achieved?
The following steps can be followed for making the man made biolayer :
Initially you will have to take a portion of the naturally formed biolayer (well
functioning) of a Biosand Filter (that already exists).
Identify which kind of bacteria is present in the biolayer and study it in detail
Culture the bacteria in the laboratory and increase this bacteria culture.
Preserve this bacteria culture and add it to the top layer of the Biosand Filter
How shall it be helpful?
No need of waiting for 20-30 days for the natural biolayer to develop
Can add the biolayer as and when required according to the Biosand Filter
size.
Natural dependence for the formation of the biolayer no longer exists.
Further Maintenance:
Within a time interval of 48 hrs, water should be added to the Biosand
Filter inorder to avoid the biolayer to be dried off.
The water should be put inside the barrel very slowly.
Add a diffuser at the neck if the Biosand Filter to regulate the flow rate of
water in order to avoid any damage to the biolayer.
Earthian Internship at Biome Environmental Solution Page 80
Construction of a Tippy Tap:
Introduction:
•The tippy tap is a hands free way to wash your hands .Appropriate for rural areas where
there is no running water.
•It is a great tool that can help kick start the conversation about hand washing with soap and
help increase this behaviour.
•It does so in a fun and easy manner that is especially appealing to children.
Advantages:
•It is a hygienic –hands free device.
•It is operated by a foot lever and thus reduces the chance for bacteria transmission as the
user touches only the soap.
•It uses only 40 millilitres of water to wash your hands versus 500 millilitres using a mug.
•Additionally, the used “waste” water can go to plants or back into the water table.
•The tippy tap is low cost and can be made from local salvaged materials
How did we develop our Tippy Tap:
Stage 1(Thought Process):
We had done a literature survey of Tippy Taps and we found it a very fascinating and
cost effective water conservation technology. We realised that this can help people
wash their hands more effectively with minimum wastage of water.
Below are some global facts and figures about hand washing released by
UNICEF in 2010. •Over 1.5 million children under five die each year as a result of diarrhoea. It is the
second most common cause of child deaths worldwide.
•Hand washing with soap at critical times – including before eating or preparing food
and after using the toilet – can reduce diarrhoea rates by more than 40 per cent.
•Hand washing with soap can reduce the incidence of acute respiratory infections
(ARI’s) by around 23 per cent.
•Hand washing with soap has been cited as one of the most cost-effective
interventions to prevent diarrhoeal related deaths and disease
We wanted to experiment by making this Tippy Tap with minimum resources in our
Office (Biome Solutions) compound.
Stage 2(Implementation):
We took the distilled water beaker(that we had used for our chemical analysis) as the
Tippy Tap container. We drilled a small hole on the beaker from where the water
would flow outside.
Earthian Internship at Biome Environmental Solution Page 81
We attached a simple rope to it .
Then, we hung it on a tree using its branches support and a rod.
A wooden foot pedal was made and attached to the beaker cap.
The Tippy Tap showed some initial problems with the pedal mechanism not
functioning properly, then we lowered the hole height from the bottom of the barrel
and then it worked as desired.
Earthian Internship at Biome Environmental Solution Page 82
Stage 3(Documentation):
We have made a short video describing the making process of our tippy tap that can
be easily reproduced and replicated by anyone. This video is very concise and is
comprehensible.
Earthian Internship at Biome Environmental Solution Page 83
Field Visits:
Visit to Rainbow Drive Layout and Sumanahalli-Nagar Bhavi
Slum Location on 29th May 2014 In order to get insights on water management we were asked to join a group of students from The University of
Minnesota on a field visit to Rainbow Drive Layout(RBD)in Bangalore which perhaps happens to be an ideal
society unit in Bangalore that has undertaken several water conservation and waste management projects for
environmental sustainability. After the RDB visit, we were scheduled to visit a slum area -a low income group
in Sumanahalli which lies in Bangalore itself to identify the water problems that the communities living there
faced.
Visit 1:Rainbow Drive Layout
We gathered near the club house and were briefed by Shubha Madam about the general water
problems faced by Bangalore .It was startling to know that Bangalore gets its water from the
river Cauvery which happens to be approximately 100km from Bangalore and 0.5kms below
it. So this is a very energy intensive operation of pumping the water from such a far
distance to the city area. Also South Eastern Bangalore has no water available. We were
given a brief overview about the water conservation operations done by the Plot Owner's
Association at Rainbow Drive Layout . In view of sustainability and conservation, the
residents have installed rainwater harvesting set ups in their bungalows. The layout has a few
deep bore wells that pumped water from the aquifers and each household was advised to
build small recharge wells of about 20-30ft.The entire layout depends on rainwater collected
and the water from the aquifers. They do not get the municipal corporation water supply.
Each household had to make an investment of about fifty thousand to set up the recharge
wells and the rainwater collection assembly along with the filtration unit. So instead of each
family digging deep bore wells and competing with each other(which would apparently lead
to the exhaustion of the aquifers), a community sense was built by the entire community
contributing in building only a few bore wells and in turn building recharge wells of their
own to replenish the aquifers.
Earthian Internship at Biome Environmental Solution Page 84
Observing the recharge wells
We were then introduced to Ms.Bharati Swaminathan and Mr.K.P.Singh who were one of the forerunners in
setting up this concept in RBD.
Mrs.Bharati showing us her home where rainwater harvesting is done
Bangalore being blessed by rainfall over a period of 6 months, rainwater harvesting turned
out to be a win-win situation for the residents as they had sufficient water at their disposal
and never depended on the local governing bodies for water supplies.
Recharge well in RBD
Earthian Internship at Biome Environmental Solution Page 85
Also due to the recharge wells, floods had stopped occurring there. Initially the government
gave rebates to those who would build recharge wells but now it doesn't exist. Slowly and
gradually few concerned families started spreading awareness about rooftop harvesting and
recharge wells. Now there are about 300 recharge wells existing in the layout which are set
up by the individual families.
Each family has a limit to use water per month and the tariff rates are so devised that if they
exceed their upper limit of water usage then that particular family would be penalised. So this
penalty on the extra water being used by the households caused the residents to use water
more judiciously. There exists a strict mandate about each household implementing the rain
water harvesting model.
Understand the concept behind the rain water harvesting done at RBD:
1) The rain water falling on the flat roof tops is collected by a pipe ,filtered and send to a tank kept at on the
ground.
Filter assembled for filtering the rooftop water collected
2) Once the tank overflows, a pipe takes the water to the ground where it is bifurcated into
two parts. One part of the water goes to the sump where it is used by the family. And the
other part is send to the recharge well which contributes to the main association water
supply.
3) So, each family gets water from the main association water supply(which is due to the
deep bore wells and individual recharge well) plus it's own roof top harvested water.
Earthian Internship at Biome Environmental Solution Page 86
Piping for Rain Water Harvesting
By doing this activity, the association claimed to save a lot of money and the awareness of
water conservation has increased in each household.
Also, there exists an excellent waste management system adopted by each family. At the
household, waste is segregated according to its category viz. dry waste, organic waste,
sanitary waste and electronic waste.
Mrs.Bharati explaining her household waste management protocol
Then these waste materials are collected separately .We even saw roof sheds made by tetra
pack waste material.
Roof made by waste tetrapacks
We also saw the sewage treatment plant in the layout and one more sewage treatment facility was under
construction. The under construction site shall use organic ways of treating sewage.
Earthian Internship at Biome Environmental Solution Page 87
Seeing a recharge well
The road trip made many things clearer and added more perspective to what we heard in the
briefing. Due to strong contour difference between one part of the layout and the other, there
existed various drains embedded with in-drained filters, check dams and silt sedimentation
units for collecting the storm water and discharging it into the wells. The residents also said
that they regularly check the Biological Oxygen Demand(BOD) and the Chemical Oxygen
Demand (COD).This completed our first visit and indeed we had gained a lot of knowledge
on water conservation and acquainted ourselves with the terminologies in the field of water
management.
Visit 2:Sumanahalli -Nagar Bhavi Slum Location
After lunch we headed to Nagar Bhavi in Sumanahalli to check the water problems faced by
the low income groups that resided there. It was rather appalling to see the pathetic conditions
of the poor slum dwellers.
Earthian Internship at Biome Environmental Solution Page 88
Mr.Nagarajaiah speaking to the slum dwellers
The slums consisted of about 80 families and roughly around 300 people lived over there.
Our guide for this trip was Mr.N Nagarajaiah who is the Executive Director of Pragathi
Charitable Trust-an NGO that works closely with the children of this slums for their
development. The residents were really very excited on seeing us and the kids over there
couldn't resist themselves in posing before our cameras for a click. Nagarajaiah Sir told us
about the water problems faced by this slum in detail.
Slum dwellers eagerly listening to our questions
The slum would get its water from a public tap that is open for a few hours only. So, it was
but natural that all the families would compete with each other in taking water. The burden of
getting the water was on the women and the children of the family. He also told us that these
people are migrant workers from North Karnataka and Andhra Pradesh who have come here
in search of jobs and were living illegally on government land. They lived in a constant fear
of their land being evacuated by the Government on legal grounds.
Earthian Internship at Biome Environmental Solution Page 89
All ears
They lived in shanty homes and didn't receive electricity. They used firewood for cooking
that caused air pollution. The water collected by them would be stored for roughly about 2
days. The water used for bathing and washing were kept outside their homes and the water
for drinking was kept inside their homes covered.
Water storage for bathing and washing stored outside the house
Water storage for drinking and cooking stored inside the home
There were many flies in the location. The only purification done there was by a cloth filter to
remove physical impurities. They didn't even boil water before usage. We then started a
conversation with the local people and started questioning them about various issues faced by
Earthian Internship at Biome Environmental Solution Page 90
them. They were very open in expressing themselves. We learned that every year the
groundwater table goes down by 15-20 ft over there. They would wash their clothes and
defecate in open.
Washing clothes in the open
The main worrying issue was the water borne diseases that inflicted the families like
diarrhoea, cholera, etc. and moreover most of them didn't avail any medical facilities for cure.
Asking them questions
The men over there had gotten into several addictions and they would splurge most of what
they earned. The children there were send to work to earn money but Pragati NGO is doing
an excellent job in emphasising the need to educate these children. They even opened a
school in the locality and are convincing the parents of the slum children to send them there.
The school grooms these kids and moulds them to be ready for a normal city school.
This really opened our eyes and we committed ourselves that we would work on improving
the conditions of this slum during the internship. Visiting both these locations has given us
excellent hindsight into water problems and water conservation. And the innovative mind in
Earthian Internship at Biome Environmental Solution Page 91
us has started in exploring cost effective and feasible conservation methods to be taken to the
grassroots.
Visit to Sumanahalli Slum-Date 11/07/2014
Objective: To educate the slum people about SODIS and Tippy Tap method.
Operation: Mr Nagarajaiah who works for a NGO called Pragathi Charitable Trust which
works closely with the people of this slum was contacted to act as a translator and to give
insight to how to go about do our work in the slum. We went in the morning before the men
left for work.
The men were spoken to first and got them to understand about the SODIS method, how to
do it and its importance in stopping almost all water-borne diseases. The men were very
interested in the method and had many questions which were answered.
Then we proceeded to educate the women about SODIS method and requested every one of
them to implement the method to protect them as well as their kids from water borne
diseases.
Mr. Nagarajan was very helpful in translating everything what was said.
Earthian Internship at Biome Environmental Solution Page 92
Then everyone in the community and especially the children were gathered and an extensive
description of Tippy tap was given along with a demonstration. The kids were rather amazed
by this technology because of which it was decided to visit the school too to educate the
students because they are the most eager to learn.
The students were enthusiastic to learn and were very excited. So the discussion there was
very productive and informative for the students with their teacher helping us out with the
translation among other things. A demonstration of Tippy tap was done there too and the
teacher was asked to make the students construct this as part of Arts and Craft in school. The
students were more than ready to make this and install it in their school.
A Tippy Tap was carried there for demonstration but wasn’t installed there because we
wanted the community to themselves make it so that there is some sense of belonging
towards the tippy tap because of which it’ll be maintained properly.
Earthian Internship at Biome Environmental Solution Page 93
Follow Up: There should at least be one more visit by someone in the next few weeks to
make sure the community has adopted SODIS method to purify their water and constructed a
Tippy Tap.
Earthian Internship at Biome Environmental Solution Page 94
Presentations Made:
1) Solar Water Disinfection(SODIS)
A detailed PowerPoint presentation has been made by us about the SODIS method for
water purification so that it can be easily taught to everybody and the mechanism of
its operation can be understood.
2) Biosand Filter
A detailed PowerPoint presentation has been made by usabout the principle,
mechanism and working of a Biosand Filter for public usage.
3) Tippy Tap
A detailed PowerPoint presentation has been made by us about the principle ,
mechanism and working of a Tippy Tap for public usage.
Videos Made:
1) A comprehensive video explaining the making of a Tippy Tap so that it can be easily
replicated and used by the public.
2) A series of easy to understand videos explaining the chemical testing methods (water
analysis) for the following parameters: Nitrates, Nitrites, Ammonium, Iron,
Phosphate, Calcium, TDS, pH and Electrical Conductivity.
Earthian Internship at Biome Environmental Solution Page 95
Bibliography Research Journal of Pharmaceutical, Biological and Chemical Sciences Evaluation of
physicochemical parameters of ground water of Renigunta, Andhra Pradesh, India
Venkateswarlu P*, Suman M and Narasimha Rao C
Physico-Chemical Characteristics of Selected Ground Water Samples of Ballarpur
City of Chandrapur District, Maharashtra, India, Das N.C.
Mishra A. and Bhatt V., Physico-chemical and microbiological analysis of under
ground water in V.V.Nagar and nearby places of Anand district, Gujrat, India, E. J.
Chem., 5(3), 487-492 (2008)
Physiochemical Analysis of Ground Water of Selected Area of Kaithal City
(Haryana) India , D. P. Guptaa*, Sunitaa & J. P. Saharanb
Quality of Ground Water and its Suitability for drinking purpose R. P. Dhok*,1, A.S.
Patil 2 and V.S. Ghole, Water Research and Development Vol 1 No.1 27-35
Chemical Analysis of Drinking Water of Kashan District, Central Iran,
Mohammad 1 mehdi Heydari and 2Hossein Noori Bidgoli, World Applied Sciences
Journal 16 (6): 799-805, 2012
STUDY OF PHYSICO-CHEMICAL PARAMETERS OF GROUNDWATER
QUALITY OF DUDU TOWN IN RAJASTHAN,Ranjana Agrawal, Rasayan J.Chem,
Vol.2, No.4 (2009), 969-971
Mohamed Hanipha M. and Zahir Hussain A., Study of ground water quality at
Dindigul town, Tamilnadu,India, Int. Res. J. Environment Sci., 2(1), 68-73 (2013)
The use of horizontal planted filters for decentralised wastewater treatment in
Auroville, an overview and description. AUROVILLE CENTRE FOR SCIENTIFIC
RESEARCH Auroshilpam
PHOSPHORUS SPECIATION IN WATER AND SEDIMENTS, B. YA.
SPIVAKOV1, T. A. MARYUTINA1 AND H. MUNTAU, Pure Appl. Chem., Vol.
71, No. 11, pp. 2161±2176, 1999.
Water quality parameters of ground water samples in Tamilnadu, Kerela and
Pondicherry,M. Ramesha and K. Elam Valuthi, Der Chemica Sinica, 2012, 3(5):1272-
1275
Earthian Internship at Biome Environmental Solution Page 96
Extent of Nitrate and Nitrite Pollution in Ground Water of Rural Areas of Lucknow,
U.P., India ANJALI VERMA, AMIT KUMAR RAWAT and NANDKISHOR
MORE, Current World Environment, Vol. 9(1), 114-122 (2014)
Rapid Determination of Iron in Water by Modified Thiocyanate Method,D.C.
Goswami and H. Kalita, DefSci J, Vol38, NO. 2, April 1988, pp 177-182
Monitoring of Fluoride Concentration in Ground Water of Prakasham District in India
: Correlation with Physico-chemical Parameters S.V. RAMANAIAH, S. VENKATA
MOHAN*, B. RAJKUMAR** AND P. N. SARMA, JOURNAL OF
ENVIRONMENTAL SCIENCE AND ENGG. Vol 48 No.2 Page 129-134 April 2006
Hydrochemical characteristics of ground water (well & tube well) in the slum area of
Bhoogaon, Wardha district, Maharashtra,G. S. Gaikwad1, Atul V. Wankhade2 and
Atul V. Maldhure, J. Chem. Pharm. Res., 2010, 2(3):499-503
Determination of nitrate and phosphate in seawater at nanomolar concentrations,
Matthew D. Patey, Micha J.A. Rijkenberg, Peter J. Statham, Mark C. Stinchcombe,
Eric P. Achterberg, Matthew Mowlem, Trends in Analytical Chemistry, Vol. 27, No.
2, 2008
WHO, International standards for drinking water, World Health Organization,
Geneva, 55-79 (2004)
BIS, Indian standards specifications for drinking water,Bureau of Indian Standards,
IS:10500
www.cawst.com
http://education.nationalgeographic.com/education/encyclopedia/aquifer/?ar_a=1