    CE 5806 - Construction Project & Site Control 0

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    Improvement of work

    flow for lifting of

    Insulation Material

    with Tower Crane

    CE5806 Construction Project

    & Site Control

    Presented By

    Allan Tay Eng Mian A010

    Diwakar Velu A0104260X

    Song Zujiang A0103244X

    Suresh Lakshana A0103323B

    Thirunavukkarasu Thayathan A010

    http://www.google.com.sg/imgres?q=nus+logo&um=1&hl=en&sa=N&biw=1920&bih=999&tbm=isch&tbnid=dRIytVAHmwmNqM:&imgrefurl=http://www.siiaonline.org/?q=events/visions-a-region%E2%80%99s-future-south-asia-2060&docid=fUq8DbIPvmvMIM&imgurl=http://www.siiaonline.org/files/u3709/NUS_LOGO_-_blue.jpg&w=500&h=262&ei=RH-9TqDaH4jZrQfC9628AQ&zoom=1
  • 7/27/2019 Work Improvement

    2/14

    CE 5806 - Construction Project & Site Control 1

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    CHAPTER 1: INTRODUCTION

    1.1 Background Information

    The Down Town Line is one of the on-going MRT project that is being constructed in Singapore

    Government to ease the traffic congestion. This line is connecting Bukit Panjang to the Expo for

    40 kms and is one of the important project in terms of completion and the cost considered .Hence

    it is very important that the work is carried out effectively and efficiently.

    Figure 1. The Down Tine LIne

  • 7/27/2019 Work Improvement

    3/14

    CE 5806 - Construction Project & Site Control 2

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    Scope of Work Improvement:

    The scope of the work improvement report is to analyse a particular construction activity and

    show the result of one of cycle of work. This will discuss the problems that are faced such as idle

    labours, resource managing etc.. due to the current condition as seen in the video submitted. This

    work improvement is done in the following steps

    Activity Considered

    Actual Work Analysis

    Thinking over an ideal Solution

    Resolved Problem Analysis

    The recommendation for improving the process of the workflow cycle will be given in this report

    with a detailed analysis and study. This is a concept of Lean construction.

    2.1 Work Description

    The video taken is to monitor a DOWN TOWN LINE MRT Project. This is particularly focussed

    on the lifting of Insulation Materials at the Bukit Batok Depot for the covering of the roof in

    order to reduce the heat affect. This is being shifted with the help of a Tower Crane and Helpers.

    Lean Concept

  • 7/27/2019 Work Improvement

    4/14

    CE 5806 - Construction Project & Site Control 3

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    Objective:

    The objective of the work analysis done for the above mentioned activity is as follows

    Reduce idle time of work men

    Manage the Tower Crane Effectively

    Reduce the manpower if necessary

    Activity Considered:

    The work to be done in the situation taken is to shift a 200 Rolls of Insulation coils to the roof of

    the Bukit Panjang MRT where it is to be spread over. The stock is arrived and has been stored at

    the ground level.

    As in this case it is planned to be shifted with the help of a tower crane. Two workmen are

    bought in along with a supervisor and a signal man .The characters are as shown in the video

    below.

  • 7/27/2019 Work Improvement

    5/14

    CE 5806 - Construction Project & Site Control 4

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    Actual Work Analysis :

    Below shows the snapshot of the actual work sequence that is to be carried out and the time at

    which the particular activity is done and what is the status of the workmen

    Scene 1 :

    Scene 2:

    This scene shows the helpers

    loading the material on the rope

    for lifting

    TIME NOW : 02:10

    This scene shows the materials

    fully loaded and lifted

    TIME NOW : 03:01

  • 7/27/2019 Work Improvement

    6/14

    CE 5806 - Construction Project & Site Control 5

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    Scene 3:

    Thus from the above analysis it is found that

    Manpower gets idle once the load is sent. This is because they do not have an extra

    loading SLING/ROPE.

    Tower Crane gets idle as material needs to be loaded.

    A table showing the cycle time study is given below.

    This scene shows the workmen

    are idle as the crane being at the

    top

    TIME NOW : 04:52

  • 7/27/2019 Work Improvement

    7/14

    CE 5806 - Construction Project & Site Control 0

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    Average Actual Time cycle with 1 hook and 2 helpers

    Total Duration 10:20

    Nos Shifted 14.00

    DescriptionSta

    rt

    En

    d

    Du

    r

    Signal man Lifting Supervisor Helper1 Helper2 Crane

    Working Time

    Working

    contributary Idle Time Working Time Idle Time Working Time Idle Time Working Time Idle Time Working Time Idle Time

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Sta

    rt

    En

    d

    Du

    r

    Arrangement of

    lifting Sling

    00:

    00

    00:

    21

    00:

    21

    00:

    00

    00:

    21

    00:

    21

    00:

    00

    00:

    21

    00:

    21

    00:

    00

    00:

    21

    00:

    21

    00:

    00

    00:

    00

    00:

    21

    00

    21

    Loading of

    materials on to

    Sling

    00:

    21

    02:

    10

    01:

    48

    00:

    21

    02:

    10

    01:

    48

    00:

    21

    01:

    41

    01:

    20

    00:

    21

    01:

    41

    01:

    20

    00:

    00

    02:

    13

    02:

    13

    00:

    21

    02:

    10

    01

    49

    hooking back 02:10 03:01 00:51 02:10 03:01 00:51 01:41 02:32 00:51 01:41 02:20 00:39 02:13 02:32 00:20 02:10 03:01 0051

    Lifting up of Sling

    03:

    01

    04:

    52

    01:

    51

    03:

    01

    04:

    52

    01:

    51

    02:

    32

    04:

    52

    01:

    51

    02:

    20

    04:

    52

    02:

    04

    02:

    32

    04:

    52

    01:

    51

    03:

    01

    04:

    52

    01:

    51

    Unloading

    04:

    52

    09:

    29

    04:

    36

    04:

    52

    09:

    29

    04:

    36

    04:

    52

    09:

    29

    04:

    36

    04:

    52

    09:

    29

    04:

    36

    04:

    52

    09:

    29

    04:

    36

    04:

    52

    09:

    29

    04

    36

    lowering of Sling

    09:

    29

    10:

    20

    00:

    52

    09:

    29

    10:

    20

    00:

    52

    09:

    29

    10:

    20

    00:

    52

    09:

    29

    10:

    20

    00:

    52

    09:

    29

    10:

    20

    00:

    52

    09:

    29

    10:

    20

    00:

    52

    Total

    10:

    20

    00:

    51

    03:

    04

    06:

    25

    01:

    12

    08:

    39

    02:

    20

    07:

    31

    02:

    13

    07:

    39

    02:

    43

    07

    37

  • 7/27/2019 Work Improvement

    8/14

    CE 5806 - Construction Project & Site Control 0

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    Based on the work carried out and the above calculations, a detailed pie chart is prepared and

    plotted as shown below. This gives a detailed report on percentage of idle time and effective

    work done,

    Working Time22%

    Idle Time

    78%

    Helper 2

    Working Time

    Idle Time

    Working Time

    26%

    Idle Time

    74%

    Crane

    Working Time

    Idle Time

  • 7/27/2019 Work Improvement

    9/14

    CE 5806 - Construction Project & Site Control 1

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    IDEAL SOLUTION:

    From the problem analyzed and the cycle time considered the following strategy is used

    Usage of 3 Nos Sling/Rope instead of One.

    Reducing a workmen considering the crane rotation time.

    Usage of 3 Slings:

    The sequence of work done is as follows

    When crane is lowered material are loaded and hooked for lifting with Sling 1.

    Meanwhile the workmen start loading in the Sling 2

    Now as and when the crane is lowered the Sling 2 is hooked and sent without idling the

    crane for loading.

    Repeating the same process

    Reducing the Manpower:

    After implementing this idea it is observed that the helpers remained ideal as the crane rotation

    time is found to be more 2mins 24 secs, the loading time with 2 helpers . In order to reduce this

    time , we replaced 2 workmen by just one 1 Helper. This reduced the ideal time and managed

    the tower crane rotation time.

    Working Time

    25%

    Idle Time

    75%

    Total

    Working Time

    Idle Time

  • 7/27/2019 Work Improvement

    10/14

    CE 5806 - Construction Project & Site Control 0

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    A flowchart showing the above operation is given below:-

    Based on this proposal, A cycle time table that is prepared is attached herewith.

  • 7/27/2019 Work Improvement

    11/14

    CE 5806 - Construction Project & Site Control 0

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    Proposed Time cycle with 3 hooks & 1 helpers

    Total Duration 12:34

    Increase in

    efficiency 60%

    Nos Shifted 42.00

    DescriptionSta

    rtEnd Dur

    Signal man Lifting Supervisor Helper1 Crane

    Working Time

    Working

    contributary Idle Time Working Time Idle Time Working Time Idle Time Working Time Idle Time

    Sta

    rtEnd Dur

    Sta

    rtEnd Dur Start

    En

    d

    D

    ur

    Sta

    rtEnd Dur

    Sta

    rtEnd Dur

    Sta

    rtEnd Dur

    Sta

    rtEnd Dur Start End Dur

    Sta

    rtEnd Du

    Unlocking of Sling 1

    00:

    00

    00:

    21

    00:

    21

    00:

    00

    00:

    21

    00:

    21

    00:

    00

    00:

    21

    00:

    21

    00:

    00

    00:

    24

    00:

    24

    00:

    00

    00:

    21

    00

    21

    hooking & Lifting up of

    Sling 2

    00:

    21

    03:

    03

    02:

    42

    00:

    21

    01:

    12

    00:

    51

    01:

    12

    03:

    03

    01:

    51

    00:

    21

    00:

    51

    00:

    30

    00:

    51

    03:

    03

    02:

    12 00:51

    03:

    03

    02:

    12

    00:

    21

    00:

    51

    00

    30

    unhooking of Sling 2,

    hooking & lowering of

    Sling 3

    03:

    03

    04:

    24

    01:

    21

    03:

    03

    04:

    24

    01:

    21

    04:

    03

    04:

    24

    00:

    21

    03:

    03

    04:

    03

    01:

    00

    04:

    24

    04:

    27

    00:

    03 03:03

    04:

    24

    01:

    21

    Loading of materials on

    to Sling 1

    00:

    24

    04:

    24

    04:

    00

    00:

    24

    04:

    24

    04:

    00

    04:

    24

    04:

    54

    00

    30

    hooking & Lifting up of

    Sling 1

    04:

    28

    07:

    10

    02:

    42

    04:

    28

    05:

    19

    00:

    51

    05:

    19

    07:

    10

    01:

    51

    04:

    24

    04:

    54

    00:

    30

    04:

    54

    07:

    10

    02:

    16 04:54

    07:

    10

    02:

    16

    unhooking of Sling 1,

    hooking & lowering of

    Sling 2

    07:

    10

    08:

    31

    01:

    21

    07:

    10

    08:

    31

    01:

    21

    08:

    10

    08:

    31

    00:

    21

    07:

    10

    08:

    10

    01:

    00

    08:

    27

    08:

    31

    00:

    03 07:10

    08:

    31

    01:

    21

    Loading of materials on

    to Sling 3

    04:

    27

    08:

    27

    04:

    00

    04:

    27

    08:

    27

    04:

    00

    08:

    31

    09:

    01

    00

    30

    hooking & Lifting up of

    Sling 3

    08:

    31

    11:

    13

    02:

    42

    08:

    31

    09:

    22

    00:

    51

    09:

    22

    11:

    13

    01:

    51

    08:

    31

    09:

    01

    00:

    30

    09:

    01

    11:

    13

    02:

    12 09:01

    11:

    13

    02:

    12

    unhooking of Sling 3,

    hooking & lowering of

    Sling 1

    11:

    13

    12:

    34

    01:

    2111:

    13

    12:

    34

    01:

    21

    12:

    13

    12:

    34

    00:

    21

    11:

    13

    12:

    13

    01:

    00

    12:

    31

    12:

    34

    00:

    03 11:13

    12:

    34

    01:

    21

    Loading of materials on

    to Sling 2

    08:

    31

    12:

    31

    04:

    00

    08:

    31

    12:

    31

    04:

    00

    Total

    02:

    33

    09:

    57

    No idle

    time

    02:

    54

    09:

    40

    12:

    00

    00:

    34

    10:

    43

    01

    51

  • 7/27/2019 Work Improvement

    12/14

    CE 5806 - Construction Project & Site Control 0

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    A pie chart showing the effective work time & idle time for the proposed work is given below

    Working Time

    76%

    Idle Time

    24%

    Total

    Working Time

    Idle Time

  • 7/27/2019 Work Improvement

    13/14

    CE 5806 - Construction Project & Site Control 1

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    The Comparison of the actual & proposed work is as shown in the bar chart below.

    Thus from the analysis it is seen that

    S.No Item Actual Proposed

    1 Cycle Time 10 m 20 s 12 m 34 s

    2 No of rolls transferred 14 42

    3 % of working time 25% 76%

    4 % of idle time 75% 24%

    5 % of productivity increase 60%

    62%

    88%

    76%

    78

    %

    74%

    75%

    0%

    77%

    4% 1

    5%

    24%3

    8%

    12% 2

    4%

    22%

    26%

    25%

    100%

    23%

    96%

    85%

    76%

    0%

    20%

    40%

    60%

    80%

    100%

    120%

    Actual Idle Time

    Proposed Idle time

    Actual Working Time

    Proposed Working time

  • 7/27/2019 Work Improvement

    14/14

    CE 5806 - Construction Project & Site Control 2

    Improvement of work flow for lifting of Insulation Material with Tower Crane

    CHAPTER 5: CONCLUSION

    Thus from the work analysis it is see that the small tool has reduce particular cost and

    time in the project.

    Hence all small activity also must be studied prior t and a proper o being carried out and

    analysis is to be done on order to avoid the above.