www.unisdr.org 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller Overstrand Municipality Hermanus, South Africa

Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

1

Working Group 2

Tools and Good Practices

“Forum on Disaster Reduction”

Shanghai, China, 28-31 July, 2010

Stephen Muller

Overstrand Municipality

Hermanus, South Africa

Page 2: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

2

Focus on Checklist points 3, 4 and 8

3. Maintain up-to-date data on hazards and vulnerabilities, prepare risk

assessments and use these as the basis for urban development

plans and decisions. Ensure that this information and the plans for

your city’s resilience are readily available to the public and fully

discussed with them.

4. Invest in and maintain infrastructure that reduces risk, such as flood

drainage, adjusted where needed to cope with climate change.

8. Protect ecosystems and natural buffers to mitigate floods, storm

surges and other hazards to which your city may be vulnerable.

Adapt to climate change by building on good risk reduction practices.

Page 3: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

3

CONTEXT

Page 4: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

4

Page 5: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

5

CONTEXT

Page 6: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

6

CONTEXT

Page 7: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

7

CONTEXT

Page 8: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

8

CONTEXT

• Total population = 73,000 people

• 11 towns spread over 230km of coast line

• Total developed urban properties = 25,000

• Total undeveloped urban properties = 10,000

• Large seasonal variation in population

• Largest industries are tourism and agriculture

• Budget per year: Operational =USD70m, Capital = USD25m

• Main town is Hermanus with a population of 37,000

Page 9: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

9

Greater Hermanus Area

Page 10: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

10

Municipal Risk Management

Municipal

Directorates

Infrastructure

and Planning

Finance

Community

Services

Protection

Services

Local Economic

Development

Management

Services

Risk Manager

RiskCommittee

Top 10 Risks

Integrated

Development

Plan

Budget

Page 11: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

11

Disaster Risk and Vulnerability – PROFILE & TRENDS

• Drought and Water Scarcity

• Flooding

• Fire and wind in dry season (summer)

• Moving sand dunes

Page 12: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

12

Disaster Risk and Vulnerability – PROFILE & TRENDSOverstrand Municipality

Annual rainfall measured at Hermanus Magnetic Observatory

0

100

200

300

400

500

600

700

800

900

1000

1947

1949

1951

1953

1955

1957

1959

1961

1963

1965

1967

1969

1971

1973

1975

1977

1979

1981

1983

1985

1987

1989

1991

1993

1995

1997

1999

2001

2003

2005

2007

Year

Ra

infa

ll (

mm

)

Rainfall Trend

11 years 6 years

Page 13: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

13

Page 14: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

14

Overstrand Municipality

Hermanus Annual Water Demand

-

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

1960

1962

1964

1966

1968

1970

1972

1974

1976

1978

1980

1982

1984

1986

1988

1990

1992

1994

Year

kl

per

year

De Bos Dam Safe Yield Annual Demand Trend

Page 15: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

15

WHAT has been done so far to address the issue?

• Reduce demand (Water Demand Management)

• Additional supply

Page 16: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

16

Water Demand Management

• Clearing Invasive Alien Plants (DWA WfW)

• Water wise gardening

• Public awareness campaign

• Leak detection and leak repair

• Water re-use (treated effluent)

• Pressure management

• Metering (bulk and domestic)

• Water tariffs

• Water restrictions

• Development restrictions

Page 17: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

17

DWA : Working for Water

• Invasive alien plants pose a direct threat to biological diversity, water security, the ecological functioning of natural systems and the productive use of land. They intensify the impact of fires and divert enormous amounts of water from more productive uses.

• Alien plants cover about 10% of the country.

• Since 1995, the programme has cleared more than 1,000,000 hectares of invasive alien plants providing jobs and training to approximately 20,000 people from among the most marginalized sectors of society. Of these, 52% are women.

Page 18: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

18

• The programme is globally recognised as one of the most outstanding environmental conservation initiatives in Africa. It enjoys sustained political support for its job creation efforts and the fight against poverty.

• WfW considers the development of people as an essential element of environmental conservation. The emphasis is on employing:

– women (the target is 60%),

– youth (20%), and – disabled (5%).

• Creating an enabling environment for skills training, it is investing in the development of communities wherever it works. Implementing HIV and Aids projects and other socio- development initiatives are important objectives.

DWA : Working for Water

Page 19: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

19

Working for Water

Alien Clearing

Page 20: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

20

Working for Water - Alien Clearing

Page 21: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

21

Water Demand Management

• Clearing Invasive Alien Plants (DWA WfW)

• Public awareness campaign– Water wise gardening

– Water saving devices

– General information

• Water re-use (treated effluent)

• Leak detection and leak repair

• Pressure management

• Metering (bulk and domestic)

• Water tariffs

• Water restrictions

• Development restrictions

Page 22: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

22

Hermanus annual water demand

-

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

1960

1962

1964

1966

1968

1970

1972

1974

1976

1978

1980

1982

1984

1986

1988

1990

1992

1994

1996

1998

2000

2002

Year

kl

per

year

De Bos Dam Safe Yield Annual Demand Trend

Page 23: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

23

Additional supply and diversify sources

• Raise the De Bos Dam wall

• Build a new dam

• Abstraction of groundwater (boreholes)

• Desalination of sea water

Page 24: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

24

Page 25: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

25

Page 26: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

26

Hermanus ground water investigation

Page 27: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

27

Hermanus ground water investigation

Page 28: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

28

Hermanus ground water investigation

• Reduce demand (Water Demand Management)

• Additional supply

• 5 well fields identified

• 3 well fields established

• 1 well field in production

• Water quality

– Water is rich in Iron and Manganese

– Requires pre-treatment

• Cost

– Ground water = USD 0.12 per kl

– Surface water = USD 0.50 per kl

– Desalination = USD 1.00 per kl

Page 29: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

29

Hermanus annual water demand

-

1,000,000

2,000,000

3,000,000

4,000,000

5,000,000

6,000,000

7,000,000

8,000,000

1960

1962

1964

1966

1968

1970

1972

1974

1976

1978

1980

1982

1984

1986

1988

1990

1992

1994

1996

1998

2000

2002

2004

2006

2008

2010

2012

2014

2016

2018

2020

Year

kl

per

year

De Bos Dam Safe Yield Annual Demand De Bos Dam and Ground water

2% growth 4% growth Trend

Well field 1

Well field 3

Well field 2

Page 30: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

30

What have been the GOOD PRACTICES…

• “Working for Water”

• 1st well field partly established (3 boreholes in production out of a

possible 10 boreholes)

•Good inter-governmental co-operation on all levels

(National, Provincial and Local) and between different

Departments (Water Affairs, Environmental, Social Services)

•Environmental management

• DWA “Working for Water” programme

– Good inter-governmental co-operation on all levels

(National, Provincial and Local) and between Departments.

– Many positive outcomes: less water demand from invasive

alien species, environmental restoration, job creation, skills

training, entrepreneurial development, poverty alleviation,

environmental education, empowerment of woman, the

youth and the disabled, HIV and AIDS awareness.

– National Programme with strong Local support

• Environmental management

– Environmental Impact Assessment

– Ecological monitoring

Page 31: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

31

… and the LESSONS LEARNED

• Our fresh water resources are limited and it must be managed

responsibly,

• Effective inter-governmental co-operation is possible,

• There are no sustainable “quick fixes” - an integrated long term

approach must be followed,

• Public participation and support is important and enough time

must be allowed for it.

Page 32: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

32

What are the CHALLENGES ahead?

• Completing the well fields,

• Manage the well fields responsibly,

• Research to gain an even better understanding of the aquifer,

• Expanding the programme to other towns,

• Implement sea water desalination when appropriate.

Page 33: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

33

… and HOW to address them?

• Ongoing implementation of the Hermanus Water Resource

Development and Management Programme

Page 34: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

34

CONLUSIONS

• The risk of drought/water scarcity has greatly been reduced by

the implementation of the Hermanus Water Resource

Development and Management Programme.

• The Programme yielded many additional benefits such as job

creation, skills training and empowerment of woman and the

youth.

• It is a sustainable Local solution with Provincial and National

support.

Page 35: Working Group 2 Tools and Good Practices · 2011-04-06 · 1 Working Group 2 Tools and Good Practices “Forum on Disaster Reduction” Shanghai, China, 28-31 July, 2010 Stephen Muller

ww

w.u

nis

dr.

org

35

Thank you