Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Ministry of EconomyRepublic of Fiji
Workshop on PPP (Public Private Partnership) for Mini-Grids
12th December 2017
Training Prepared and Conducted by Grue + Hornstrup A/S
Overview of the Sessions
• 09:00 – 09:15 Welcome
• 09:15 – 09:30 Application of PPP models for mini-grids
• 09:30 – 10:00 Identification, screening, and appraisal process for PPP projects
with mini-grids
• 10:00 – 10:15 Tea break
• 10:15 – 10:45 Design of PPP projects and business models in rural communities
• 10:45 – 11:15 PPP Agreement and governance
• 11:15 – 11:45 Implementation and private sector set-up
• 11:45 – 12:30 Monitoring and evaluation of PPP projects with mini-grids
• 12:30 – 13:30 Lunch
Training Prepared and Conducted by Grue + Hornstrup A/S
Ministry of EconomyRepublic of Fiji
Workshop on PPP (Public Private Partnership) for Mini-Grids
Application of PPP models for mini-grids
Contents and Outcomes
The Big Question: What are we trying to aim for and achieve through the Application of PPP
models for mini-grids
Key Questions for PPP Model Framework
1. Scope of the Application:✓ What is the sector / technology,
✓ Type of energy assets,
✓ Geographical aspects,
✓ Scale/ capacity,
✓ Type of service (what gaps are to be filled),
✓ Payment conditions,
✓ Business models that need to be considered…
2. Overview of the Process:✓ How does the overall structure / relationship look like
✓ What are the steps for developing a PPP Framework
Key Questions for PPP Model Framework
3. Identification, Screening and Appraisal✓ How do you identify the initial project / site
✓ What is needed for initial pre-screening
✓ What are the criteria when assessing the project
✓ Are there any tools such as SWOT analysis which can facilitate
the decision making process
4. Design and Business Models:What needs to be considered when defining:
✓ The stakeholder consultation process
✓ The legal and regulatory framework
✓ Proposed roles and responsibilities
✓ Income generating activities
✓ Determing baseline and demand
✓ Tariff setting structure / methodology
✓ Commercial and Financial considerations
Key Questions for PPP Model Framework
5. PPP Agreement and Governance ✓ What goes into developing a PPP Agreement - Understand the
key elements of the PPP Agreement
✓ What does a PPP Governance structure need to consider with a
focus on parties invovled (incl. Government)
6. Implementation and MRV ✓ Understanding risks and mitigating them
✓ What does the PPP implementation plan look like
✓ What are the considerations from the Private Sector
✓ What are the cornerstones of the MRV system
✓ The key parameters and data that needs to be tracked
✓ What additional training and support is needed (follow-up)
7. And finally, Lessons Learned
The Big Picture
Questions and Comments
Ministry of EconomyRepublic of Fiji
Workshop on PPP (Public Private Partnership) for Mini-Grids
Identification, Screening and Appraisal
What is a PPP ?
A Public-Private Partnership (PPP) is a well proven model that is used globally typically for public infrastructure projects such as Renewable Energy Projects
The public partner is represented by the government at a local, state and/or national level. The private partner can be a privately-owned business, public corporation or consortium / JV of businesses with a specific area of expertise.
What is Unique in Fiji ?
The public partner of a PPP in Fiji can be the is represented by the Government of the Republic or the Native & Village government units.
National Government
District Government
Sud-ProvincialTikinaTowns / Cities
Village / Matangali
Provincial GovernmentsYasana
Supported by Ministry of iTaukei Affairs
Advantage PPP
The PPP Framework can support the development of RE power generation projects in Fiji to enable more investment by:
✓ Accessing private finance, ✓ Helping to achieve value for money in the provision of energy services, ✓ Improve accountability and reliability in the provision of the services, ✓ Harnessing private sector innovation and efficiency,✓ Stimulating growth and development, particularly in rural areas.
Scope of Application – with Focus on RE:
Note: The application in this Workshop is limited to the electricity sector in the form of RE power generation and/or distribution in mini-grids.
Pre-conditions for PPP Projects:
✓ PPP can be applied for hydro projects (up to 100 kW), ✓ Wind / hybrid proects and ✓ Solar / hybrid projects
Only mini-grids and fully off-grid projects are eligible.
The PPP model framework is NOT applicable for:
End-user RE systems (like solar home systems); Generation connected to the FEA grid systems.
Scope of Application - Continued
Type of Energy Assets
✓ Existing Energy assets and service areas for RE power generation and distribution
✓ New energy assets and service areas, or ✓ Existing energy assets and service areas which are to be extended,
For privately owned energy assets (e.g. Resorts)
Scale and Capacity:
✓ The service should benefit a minimum of 50 households / end-consumers
Payment Conditions:
✓ Private counterpart is paid mainly through collecting fees from end-users
Identification – The 2 Approaches
Top-down approach
Based on a selection of projects identified through a review of the public or private sectors infrastructure
planning processes or energy development plans.
Bottom-up approach
Potential sites and projects are proposed e.g. from a community, a development agency,
and/or a private sector company
Screening - Aspects to Consider:
Value for Money
Sustainability
Risk Transfer
Commercial Potential
Market Potential
Appraisal - Questions that need Answering:
✓ Who are the key stakeholders involved?
✓ What are most critical aspects/risks involved? (e.g. related to ownership, legal, financial or technical aspects)
✓ Capacities available vs. capacities required?
✓ What does it require in terms of logistics and coordinating for the PPP process?
✓ Is there potential private sector interest in the project/site? Generally, the private sector would consider the following aspects: - Is there sufficient demand for the underlying service (electricity) by the users and in the area?- What is the viability of the project?- What is the potential for revenue creation and future development?
✓ Is there a strong political commitment to support the PPP?
✓ Is a PPP the potentially best method to deliver the required services (power generation or power generation & distribution)?
Appraisal - Criteria for Investment Decision
Feasibility and economic viability of the project:
A project is economically viable if the economic benefits of the project exceed its economic cost.
Commercial Viability:
Would the project be attractive to the market and has good financial returns, or can break even if non-profit?
Would the PPP require the private party to bear only reasonable levels of risk?
Value for Money:
• Generation of additional revenues;• Improved service quality;• Faster implementation; • Reduced or Better allocation of risks; • Reduced life cycle costs.
Fiscal Responsibility:
Would the project’s overall revenue requirements be within the capacity of users, the public authority, or both, to pay for the infrastructure and service.
Ministry of EconomyRepublic of Fiji
Workshop on PPP (Public Private Partnership) for Mini-Grids
Business Models and Design
PPP Models – Components of Project Activity
Construction
Phase
Operation / Main
Phase
Project
Management
Ownership
Rights
Design
Build
Operate
Maintain
Finance
Manage
Transfer
Own
Technical design and
construction
of the project
Make sure that the
project provides
required services
Ensure appropriate
project funding and
oversight
Pertains to project
ownership
PPP Procurement Assessment
Planning & Implementation Post Project Review
Establish OutputSpecifications
Contract Award
Management and Review
Traditional Procurement Process
PPP Process
Project Operation
End of EconomicLife (i.e. ROI achieved)
ConstructionPhase
OwnershipRights
OperationPhase
Various Phases in Project Financeand Project Management
PPP Models – Comparison
In the context of improving access to energy through Renewable Energy in
Fiji via mini-grids, the following models are relevant:
Types of PPP Model relevant to Fiji / EnergyConstruction
Phase
Operation
Phase
Project
Management
Ownership
Rights
Operation and Maintenance (O&M) ✓
Operation, Maintenance and Management (OMM) ✓ ✓
Design Build Operate Maintain (DBOM) ✓ ✓
Design Build Finance Operate Maintain (DBFOM) ✓ ✓ ✓
Build Operate Transfer (BOT) ✓ ✓ ✓ ✓
Build Own Operate (BOO) ✓ ✓ ✓ ✓
• Public agency contracts a private entity to provide and/or maintain a specific service.
• Under the private operation and maintenance option, the public partner retains
ownership and overall management of the public facility or system.
• O&M are one of the most popular form of contracts globally and is even practiced by
private entities to outsource either non-essential or highly technical type of works.
• The private entity is usually a “small player” (e.g. local contractor with limited financial
resources or a specialized company offering a specific type of service) and undertake
repairs/servicing of equipment required to ensure the regular operation of the facility.
• O&M in context of Fiji will provide employment of local population to operate and
maintain decentralized and remote RE power plants.
O&MPPP Models – Operate & Maintain
Public agency contracts with a private partner to operate, maintain, and manage a
facility or system proving a service.
Under this contract option, the public partner retains ownership of the public facility
or system, but the private party may invest its own capital in the facility or system.
Any private investment is carefully calculated in relation to its contributions to
operational efficiencies and savings over the term of the contract.
Generally, the longer the contract term, the greater the opportunity for
increased private investment because there is more time available in which to
recoup any investment and earn a reasonable return.
In context of Fiji, OMM contract maybe awarded with the added responsibility to
collect payments for the services / energy provided.
OMM
PPP Models – Operate, Maintain & Manage
• The design-build-operate-maintain (DBOM) model is an integrated partnership
that combines the design and construction responsibilities of design-build
procurements with operations and maintenance.
• These project components are procured from the private section in a single
contract with financing secured by the public sector.
• The public agency maintains ownership and retains a significant level of
oversight of the operations through terms defined in the contract.
• In the context of Fiji, the DoE can choose to appoint a reputed private entity
(international or national) to design and build the power plant who can then be
made responsible to train local staff to ensure O&M of the facility.
DBOM
PPP Models – Design, Build, Operate & Maintain
• With the DBFOM approach, the responsibilities for designing, building, financing,
operating and maintaining are bundled together and transferred to private partner.
• There is a great deal of variety in DBFOM arrangements especially the degree to
which financial responsibilities are actually transferred to the private sector.
• One commonality that cuts across all DBFOM projects is that they are either partly
or wholly financed by debt leveraging revenue streams dedicated to the project.
• They are also often supplemented by public sector grants in the form of money or
contributions in kind, such as right-of-way. In certain cases, private partners may be
required to make equity investments as well.
DBFOM
PPP Models – Design, Build, Finance Operate & Maintain
• The private partner builds a facility to the specifications agreed to by the public
agency, operates the facility for a specified time period under a contract or
franchise agreement with the agency, and then transfers the facility to the
agency at the end of the specified period of time.
• The private partner will also provide some, or all, of the financing for the
facility, so the length of the contract or franchise must be sufficient to enable the
private partner to realize a reasonable return on its investment through user
charges.
• At the end of the franchise period, the public partner can assume operating
responsibility for the facility, contract the operations to the original franchise
holder, or award a new contract or franchise to a new private partner.
BOT
PPP Models – Build, Operate & Transfer
The contractor constructs and operates a facility without transferring ownership to
the public sector.
Legal title to the facility remains in the private sector, and there is no obligation for
the public sector to purchase the facility or take title.
BOO
PPP Models – Build, Operate & Own
Design Consideration - Stakeholder Consultation
Local Stakeholders:Service Users, local community
The Government:Ministries, FEA, FCC etc.
Land Owners & 3rd parties:e.g. Respective Matangalis
Private Sector:Potential service providers
And/or Suppliers
Community / Stakeholder Consultants (Bukuya)
Mission Key stakeholder engagement activities
1 Technical Assessment of Hydro Power Station;
Introduction of PPP concept (workshop with
stakeholders); Inputs/ concerns from
stakeholders;
2 Present the Bukuya PPP concept to the Bukuya
Cooperative and to gain feedback. Determination
of income generating activities
3 Present final Bukuya PPP concept and land lease /
easement issue.
4 Present SPC company structure, Coop decision on
PPP participation, elect SPC board members,
notification of prepaid meters and tariff.
5 Meet with SPC team and Coop Board to inform on
progresss, review of company operating structure,
and small business accounting training. Mid-
Review of pre-paid meter installation.
6 Meet with SPC team and Coop Board to inform on
progresss, sign employment contracts, and small
business accounting training. Final-Review of pre-
paid meter installation.
DOE held additional consultations and support for the rehabilitation, facilitating the PPP, and supervision of pre-paid meters installation.
Design Consideration – Roles & Responsibilities
Government of Fiji:
Supporting the development and implementation of the PPP relationship.
Oversee the PPP contract (PPP Agreement) over its lifetime. Includes enforcing the PPP contract requirements and managing the relationship between the public and the private party.
Enforcement is via the laws of Fiji, but also as a balanced member of the PPP Governance Board
Private Party:
Legal responsibility to manage, operate and maintain the renewable power plant under the PPP.
Other 3rd Parties:
Roles and Responsibilities are dependent on the type of 3rd party, for e.g. an External service provider may be appointed for installing, operating and maintaining the pre-paid meters, to conduct extraordinary and larger maintenance work and annual overhauls at the power plant or to verify the measured and reported data
Public Party:
Assigns the rights to provide the service, and is legally responsible to support the Private Party during implementation and operation, and in disputes with the community.
Roles & Responsibilities (Bukuya Example)
Design Considerations –Inclusion of Income Generation Activities
• Step 1: Discussions with national stakeholders incl. DOE and local stakeholders (Community, Village);
• Step 2: Identification of most relevant income generating activities; • Step 3: Costs and benefits of income generating activities; • Step 4: Income Generating Investment Plan.
Minimum Information that should be Provided:
• Description of what exactly is planned (incl. technology, amount, space required, location);
• Purpose of the activity;• How will it affect the village, community?; • Expected revenues per annum;• Other co- benefits (e.g. social, environmental, economic); • Expected investment costs and costs for operation and management (incl. salary).
Design Considerations – Tariff Setting
Identify & Quantify Cost Components
Measure or Assess Power Demand
Calculate annual revenue requirement
Calculate the Tariff based on revenue and power demand
Approval of Tariff
Design – Commercial / Financial Considerations
Major Maintenance Fund(Tariff Guarantee)
Income Generating Activity Fund
PPP Specific Funds
Established in form of an ESCROW-Bank Account, to ensure that the costs for major maintenance required can be ensured at any time of the operation of the PPP project
Established in form of a controlled bank account to accumulate the revenues required for investing in the selected and planned income generating activities in the service area of the PPP
Income Generating Activities (Bukuya Example)
Determining Electricity Demand
Services (Health Center, Nurses Quarters, Teacher Quarters)
Items Number Power Rating
(W)
Load hours (Hr) Daily Load (Wh)
CR Tube TV 1 150 4 600
Refrigerator 4 150 7 4200
Mobile charger 2 5 3 30
Iron 3 1000 1 3000
Laptop 3 75 3 675
Flat Screen TV 2 40 6 480
Washing machine 2 500 3.5 3500
Electric oven 1 2000 4 8000
LED/CFL Lights 12 11 9 1188
Small radio 1 30 15 450
Desktop computer 3 300 7 6300
Starlizer 1 1000 4 4000
Blood Pressure Machine 1 50 3 150
Electric Kettle 1 1000 3 3000
Fan 1 30 6 180
Total 35753
Number of households surveyd 23
Households
Items Number in
Households
Power Rating
(W)
Load hours (Hr) Daily Load (Wh)
CR Tube TV 20 150 5 15000
Refrigerator 10 150 7 10500
Stereo 8 300 6 14400
Rice cooker 2 650 1 1300
Mobile charger 23 5 3 345
Iron 16 1000 1 16000
Washing machine 5 500 2 5000
Laptop 1 75 4 300
Toaster 1 800 1 800
Flat Screen TV 2 40 3 240
Electric oven 1 2000 1 2000
LED/CFL Lights 69 11 9 6831
Frying Pan 1 1000 2 2000
Small radio 1 30 15 450
Corrected values
Total 75166
per Household 3268
Past Generation MethodEnd-Use Survey Method
Results = 3.4 kWh per HH Results = 1.9 kWh per HH
Determining Electricity Demand
Compairson Method
Results = 4.2 kWh per HH
✓ Different methods lead to a high level of uncertainly
✓ Direct measurement method is best, but not possible for greenfield projects
✓ Suppressed demand scenarios should be considered.
✓ Demand range between 1.9 – 4.2 kWh per HH
Tariff Setting
Itemized Annual Costs Conservative Demand Estimate
Tariff Components Annual Cost Part of Tariff Part of Tariff
FJD/kWh %
Daily Operational Costs 11,535 0.067 17%
Continual Maintenance Costs 4,500 0.026 7%
Company Management Costs (incl. Staff) 27,000 0.157 39%
Cooperative Costs (incl. easement) 6,000 0.035 9%
Major Maintenance Costs 10,167 0.059 15%
Investment in Income Generating Activities 9,753 0.057 14%
FJD FJD/kWh
TOTAL Annual 68,955
Electricty Generation 191,359
Electricty Supply (Generation - losses) 172,223 0.400
Final Tariff
Items Quantity Frequency Unit Price Annual Cost Total Cost
FJD
Continual Maintenance Costs 4,500
Turbine & Governor 1 1 3,000 3,000
Generator & Operating Panel 1 1 1,500 1,500
Daily Operation (Nominal Replacement Parts) 11,535
Oil to governor (34 l) 1 1 200 200
DC Battery replacement - 48V - 100Ah 1 4 2,500 625
Lighting (2x 200W, 3x 60/11W, 1x 100W 1 2 100 50
Painting of metal surfaces 1 4 1,500 375
Replace trash rack 1x 1 4 2,000 500
Replace panel circuit breakers 1x 60A, 4x 15A 1 4 500 125
O&M of pre-paid meters monthly fee 12 1 735 8,820
Replacement of village level electric meters 3 1 280 840
Private Company Annual Costs 27,000
Monthly Company Manager (full-time) 12 1 560 6,720
Accountant & Secretary (Full-time) 12 1 480 5,760
Daily Operator x1 (Full-time) 24 1 480 11,520
Outsourced electrical repairs 12 1 100 1,200
Additional company cost (materials, audit….etc.) 12 1 100 1,200
Private Company Profits 12 1 - -
Costs of Capital (e.g. for loan repayment, interest) 12 1 - -
Contingancy 12 1 50 600
Cooperative Annual Costs 6,000
Bukuya Cooperative Fee 12 1 400 4,800
Right-of-way / easement cost 4 1 300 1,200
TOTAL Annual Operating and Maintenance Costs FJD 49,035
Monthly breakdown FJD 4,086
Items Quantity Frequency Unit Price Annual Cost Total Cost [FJD]
Major Maintenance Costs 10,167
Overhaul Turbine & Governor & Operating Panel 1 12 72,000 6,000
Overhaul Generator 1 12 20,000 1,667
Repair Penstock, LP Conduit and Forebay 1 12 30,000 2,500
TOTAL Annual Operating and Maintenance Costs FJD 10,167
Monthly breakdown FJD 847
Example of Revenue Distribution Mechanism
Questions and Comments
Ministry of EconomyRepublic of Fiji
Workshop on PPP (Public Private Partnership) for Mini-Grids
Agreement and Governance
The PPP Agreement
The PPP agreement or contract is the central legal document of the PPP. It defines the relationship between the public and private party, their respective rights and responsibilities, risk allocation and providing
mechanisms for dealing with change.
The PPP Agreement should be between the public party and the private sector company.
The PPP Agreement - Contents
Element 1 : Performance Requirements:
Define clear performance targets or output requirements, including:
✓ How performance will be monitored;✓ Consequences for failure to reach the required performance targets;✓ Specifying payment deductions for poor performance (or bonuses);✓ Describe formal performance warning system;✓ Step-in rights for the public party or the PPP Board.
Element 2 : Duration
Define the period of validity
Element 3 : Guarantees on Risk Variables
Procedures should be described to compensate the private party for loss in revenue,
should a particular risk variable deviate from a contractually specified level.
The PPP Agreement - Contents
Element 4 : Dispute Resolution:
Defining dispute resolution processes helps ensure resolving disputes quickly and
efficiently and reducing the risk of disruptions of the PPP process due to disputes.
✓ Mediation – a third Party gets involved to help resolve a dispute. Mediation is used in the hope of not having to enter formal arbitration. Or a special PPP Board is setup as a part of the PPP Agreement.
✓ Recourse to a sector regulator – e.g. for specific disputes on aspects if independent regulator exists (e.g. tariff)
✓ Judicial system – For PPPs in developing countries, it is recommended that the dispute resolutions avoids resorting to the court system as far as possible, as it the court system may be slow and lack technical expertise.
✓ Panel of experts and arbitrators – the PPP contract or law could designate a panel of independent experts for dissolving disputes.
✓ International arbitration – this would be the last option and would be under a permanent arbitration institution or could involve ad-hoc arrangements such as international expert panels.
The PPP Agreement - Contents
Element 5 : Termination Commitments
A fair contract should ensure that the private party would not lose out in case of
the public party to default.
Three possible reasons for early termination: default by the private party,
termination by the public party (whether due to default or for reasons of public
interest), and early termination due to some external reason (force majeure).
✓ Define the contract term, handover provisions, and circumstances and implications of early termination and consequences.
Element 6 : Debt Guarantees and Other Credit Enhancements
Guarantees are used to provide more security to a lender so that a loan will be
repaid and should cover specific risk or event.
The PPP Agreement - Contents
Element 7 : Payment Mechanisms
Define how the private party will be paid, through user charges, government
payments based on usage or availability, or a combination, and how bonuses and
penalties can be built in.
Element 8 : Adjustment Mechanisms
Should be built in to the PPP agreement for handling changes, such
as extraordinary reviews of tariffs, or changing service requirements
Element 9 : Contract Management
Procedures for dealing with change and establishing contract management
institutions , and defining and establishing the responsibilities and communication
mechanisms.
PPP Governance
PPP Unit:
To date there does not exist a special PPP Unit in Fiji that is in charge, oversees
and coordinates PPP projects in Fiji. In other countries, such a PPP unit coordinates
the PPP activities in different sectors (incl. transport, industry, energy). The past
PPP Act was dissolved and a new one may only address large projects.
For the Bukuya project the acting PPP Unit is currently the DOE
The functions of the PPP unit would include:
✓ Policy Guidance and capacity building (incl. providing templates or guidance documents for PPP);
✓ PPP Promotion (inside Government and for private sector/investors);
✓ Technical support (e.g. hand-holding for PPP preparation, design and implementation);
✓ Oversight and coordination.
PPP Governance
PPP Governing Board :
A PPP Governing Board shall be established as a part of the PPP agreement
between the Private Company and the Public Party of the service
area (or Community).
For the Bukuya project the PPP Governing Board shall be composed of four representatives as
follows:
✓ One representative of the DOE;
✓ One representative of another government agency (appointed by DOE), e.g. Cooperative
Department;
✓ One representative of the Private Party the Electricity Cooperative (or local
Community/Village representing the service area of the PPP);
✓ One representative of the Private Party (SPC) operating the renewable power plant and
distribution under PPP project.
PPP Governance
PPP Board of Directors: Roles and Responsibility
✓ Meet twice a year (at minimum)
✓ Selection of the private company based on Competitive process
✓ Agree of the final structure of the PPP framework
✓ Agree upon and prioritize income generating activities
✓ Agree on the tariff structure including price and revenue streams
✓ Review audited annual balance sheet for the PPP (e.g. SPC in the case of Bukuya)
✓ Review, allocate and authorize (or not) the payments for major maintenance activities from
Major Maintenance Fund
✓ Review, allocate and authorize (or not) the payments for unpaid revenue to the Private
Company from Major Maintenance Fund
✓ Act as an arbitrator in disputes between the Private Company and the Electricity
Cooperative of the PPP
Questions and Comments
Ministry of EconomyRepublic of Fiji
Workshop on PPP (Public Private Partnership) for Mini-Grids
Implementation and Set-Up
Private Party Selection
Procurement Process for Private Party:
Not in the case of Bukuya
✓ Preparation of tender and documents, ✓ Execution of bidding process, ✓ Review and evaluation of proposals,✓ Selection of Private Party, and entering into the PPP agreement
OR decision to create a Special Purpose Company (SPC):
In the case of Bukuya
✓ Needs✓ Board of Directors✓ Empolyees✓ Registration✓ Licenses✓ 3rd Party Suppliers
Private Company Set-Up
Needs ASSESSMENT:
✓ Staff and Skills✓ Hardware✓ Legal & accounting services✓ ….
Management and Board:
The Board of the Private Party engaged in the PPP should
consist of at least 3 board members, including one
chairman with an upper limit of 5 members.
✓ Representative of the private sector company / special purpose company
✓ Representative from the Community and/or Cooperative
✓ Representative based on Owner distribution of the SPC (if limited company)
Private Company Set-Up
Registration and Company Licenses:
The registration process of a company in Fiji has to be in full
compliance with the Fiji´s Company Act 2015, and/or the
Cooperative Act.
Steps include:
✓ Inception Phase✓ Company Registration Process✓ Securing local Tax Identification Number
Employment Process:
✓ Job descriptions of SPC staff✓ Job advertisements✓ Job interviews and hiring process✓ Contracts for SPC employees
Private Company Set-Up
Applicable Company Types:
Limited Company✓ Shareholder based company, with limited liability to capital of company✓ 33.3% Advanced Tax (PT) on realised profits✓ Capital gains tax of 10% of individual dividends applies if above FJ$ 16,000✓ Annual accounts required
Company Limited by Guarantee✓ Bounder under a guarantee (like a trust)✓ No taxes on profits✓ No dividends are paid out✓ Requires special Ministerial review✓ Annual accounts required
Cooperative Company✓ Income taxes apply as in the Tax Act✓ Annual accounts required (after grace period)
Other Taxation✓ VAT of 9% is applicable for any business achieving over FJ$ 100,000 per year
in revenues.✓ All companies are subject to the FNPF (gross 18%)
Private Company Set-Up
Electricity Licenses:
The license process under the Electricity Act 2017 (not in effect yet),
✓ Wireman’s license✓ Provider/distributer license
Private Service Providers (not part of PPP)
Selecting Private Service Providers :
Generation and Distribution Technology (installation of rehabilitation) Prepaid Metering System
✓ Preparation of tender and documents, ✓ Execution of bidding process, ✓ Review and evaluation of proposals,✓ Selection of Supplier, and entering into the agreement ✓ Implementation and supervision✓ Hand-over
Banking Services / Bank Accounts✓ Setting up accounts (checking and ESCROW)✓ Setting up automotive payments
Auditor / Accountant✓ Selection and contacting
Land and Access Rights
There must be an agreement with the
community on the use of land plus access to
energy assests (generation and tranmission).
This can be done either by a Lease Agreement
and/or an Easement/Right of Way Agreement.
Lease Agreement:
✓ Right of long term use of defined land✓ May require valuation✓ Approval through iTaukei Affairs✓ Agreed upfront or annual fee
Easement/Right of Way Agreement:
✓ Right of long term use of defined land
✓ Approval by Parties
✓ Agreed upfront or annual fee (or none)
Implementation Schedule
The main purpose of the implementation schedule is to provide information about
the duration that is required to achieve the individual activities.
✓ Baseline determination tariff setting;✓ Procurement (private company, staff, technology);✓ Private company set-up;✓ Service providers;✓ Licenses and official approvals;✓ Setting up Governing Body(ies);✓ PPP Agreement;✓ Measurement, Reporting and Verification (MRV);✓ Training.
Questions and Comments
Ministry of EconomyRepublic of Fiji
Workshop on PPP (Public Private Partnership) for Mini-Grids
Monitoring and Evaluation
MRV - Generation, Consumption & Revenues
Cornerstones of MRV System:
✓ Identification and setting of agreed upon parameters and their data requirements. Noting that the parameters should best align to existing and planned monitoring & accounting at the service area (i.e. villages) where the PPP is developed;
✓ Any calculation methodologies for the transformation of raw data into specific parameters;
✓ Baseline setting of parameters based on latest available data, as a measuring point for improvements and benefits;
✓ Defining the internal monitoring frequency of the parameters and the external reporting frequency to FDOE by responsible parties for the M&E (i.e. private company, service providers, Cooperative).
MRV – Identified Parameters
Typical set of Parameters include:
✓ TSE = Total sold electricity (kWh/a)✓ ER = Emission reductions achieved (tCO2e/a)✓ THC = Total household connections (no.)✓ IGA = Total number of active income generating activities (no.)✓ JCtotal and JCfemale = Reporting of total additional jobs created and total
additional female jobs created (no. and no.)✓ CS = Level of capital saving for investment in income generating activities (FJD)✓ QIP = Reporting qualitative implementation of the project components✓ UP = Unit price of electricity (FJD/kWh)
MRV – Identified Parameters
Template for Data Collection:
Parameter Value (base year) Explanation
TSE XXX kWh Description of base year and source of date
ER XXX tCO2e Emission reduction from generated electricity in
20XX
THC XXX Household connections in 20XX (base year)
IGA XXX Number of new income generating activities
using electricty in 20XX (base year)
JCtotal and
JCfemale
XXX and XXX Reporting only additional jobs created from the
project
CS XXX FJD Total value of capital savings for investment in
income generating activities in 20XX
QIP XXX Reporting implementation annually
UP X.XXX FJD / kWh Value for [date, month, year] and source
Evaluation Procedure
Annual Evaluation by PPP Governance Board:
An annual evaluation of the PPP should be addressed in the annual meeting of the
PPP Governance Board. The steps and content of the evaluation should include:
1. Before the annual meeting the Private Party (SPC) should provide the latest
annual financial statement, the MRV results for the year, a record of actions
taken in maintenance and operation, any new issues to be addressed in the
near future.
2. Before the annual meeting the Public Party should provide feedback from the
community on the quality of services provided and request any elements of
services or the PPP Agreement which may be changed.
3. Members of the PPP Governance Board shall review and appraise these items
in the points above and determine compliance with the PPP Agreement, and
expected results of the PPP.
4. The results of the evalution at the annual meeting shall be recorded in the
official notes the meeting.
Questions and Comments
Ministry of EconomyRepublic of Fiji
Workshop on PPP (Public Private Partnership) for Mini-Grids
Lesson Learned
Capacity Building Needs
Assess Capacity Needs
The following questions need to be answered:
✓ What are the required skills for achieving the objectives of the PPP project and the PPP model framework?
✓ What is the current status of capacities and skills in terms of PPP for renewable power generation in Fiji within the public/private entities involved?
✓ Who (which institution and which persons) holds the skills and know-how-how for the required skills?
✓ What would be required to improve the skills and know-how, so that the current and future PPP activities can be prepared, developed, implemented and managed?
Training Needs
Define Training Programme
The following questions need to be answered:
✓ What should be the training content? ✓ Who requires the training? ✓ Who should conduct the training (e.g. what skills, experience, and national or
international)?✓ What training methods, approaches and tools used? ✓ Extent, duration and frequency of training?✓ Monitoring and Evaluation measures (incl. reporting)✓ What resources (i.e. budget, logistics, skills, tools, time) are required to provide
the training programme?
Training
Conduct the Training
Training aspect Public Entity Private Entity
Introduction to PPP (Modalities, Scope, Purpose,
Benefits)
Case Studies and PPP experience
PPP Model Framework
Fundamentals of PPP identification and appraisal
Policy and legal aspects
PPP Management and Governance
PPP Contracts and PPP Contract Management
Risk Management
Financial Management
Private Sector Modalities
Procurement procedures
Technical training for RE technologies (Operation &
Maintenance)
Measurement, Reporting and Verification
Private company management and administration
Additional Services Required
✓ Legal (Fijian company - Siwatibau and Sloan) for company registration, employment contracts, review of PPP agreement & governance.
✓ Small Business accounting setup and training (done by G+H)
✓ Installation supervision of rehabilitation and pre-paid meters (by DOE)
✓ Banking service (BSP but pending company registration)
✓ Community engagement and translation (by DOE)
✓ Pre-paid meters and annual service contract (by Clay Energy)