Upload
lily-potter
View
214
Download
1
Embed Size (px)
Citation preview
www.bmvbs.de
PPP projects in federal trunk road construction in Germany
byFrank Süsser,
(Head of Division StB 28, Liaison Division) Federal Ministry of Transport, Building and Urban Development
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau2
Objectives of PPP
• High efficiency because of life cycle approach
• Quicker realization of measures, shorter periods of traffic disruptions
• The state should focus on core functions
• Promoting innovations in the sectors of construction, operation and maintenance
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau3
Principles
• Provision of services from one source (tender procedure for construction, maintenance, operation and partly financing)
• No privatization, i.e. the responsibility remains with the state
• Long-term contractual links, life-cycle approach and contractual incentives for high-quality and efficient realization
• Functional provisions, more flexibility for industry
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau
PPP models in federal trunk road construction
A model: = upgrading model
– In the case of existing federal motorways with first priority upgrading requirement, the private investor constructs the fifth and sixth lanes and operates and maintains all the lanes according to defined quality standards.
– He finances his expenses by start-up financing and toll revenue or by availability payments , i.e. no remuneration on the basis of traffic levels from the toll revenue transferred but a total remuneration in monthly payments according to temporal availability.
4
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau
PPP models in federal trunk road construction
5
F model (named after the Private Sector Funding of Trunk Road Construction Act)
- The private investor constructs, maintains and operates bridges, tunnels and mountain passes ormulti-lane federal highways with separate carriageways for the two directions of traffic.
He is entitled to levy a toll (even from passenger cars). Up to now, 2 projects on federal highways have been realized
under local authority control. Further projects at federal level are being planned (e.g.
Weser crossing in the course of the A 281)
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau
PPP in a wider sense
Function contracts in roadconstruction
-Life cycle approach;
-Term of contract 10 – 30 years, currently small-scale projects on the basis of functional requirements;
-At the moment, evaluation of 8 pilot projects, Preparation of a Guide on Value for Money Tests.
6
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau7
Four A model pilot projects (1st generation)
The contracts were awarded for all projects (2007 - 2009):-A 8 in Bavaria: Augsburg – Munich (approx. 52 km, thereof 37 km upgrading)-A 4 in Thuringia: federal state border Hesse/Thuringia – Gotha access point (approx. 45 km, thereof approx. 25 km upgrading) -A 5 in Baden-Württemberg: Malsch – Offenburg access point (approx. 61 km, thereof approx. 41 km upgrading)-A 1 in Lower Saxony: Buchholz motorway junction – Bremen motorway interchange (approx. 72 km, thereof approx. 72 km upgrading)
In total: 230 kilometres (of a total of approx. 12,800 km of federal motorways in Germany), thereof approx. 175 km upgrading, Construction costs approx. 1.1 billion €, Period of the contracts: 30 years
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau8
8 new projects: The second batch (2nd generation)
In total: 450 kilometres (of a total of approx. 12,800 km of federal motorways in Germany),
Construction costs approx. 1.5 billion €,
Further PPPs
A model pilot projects
Second batch
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau9
Second batch PPP*Depending on the level of the process to achieve construction permission (to be provided by the federal state) and on the positive result of the Value for Money Test
Start of the contract award procedure*
1. (Bavaria/Baden-Württemberg) A8, Ulm-Elchingen motorway interchange – Augsburg W motorway junction
28 January 2009, award of contract: 11 April 2011; beginning of the contract: 1 June 2011
2. (Thuringia) A9, Lederhose access point – federal state border Thuringia / Bavaria
18 March 2009, award of contract: 4 August 2011; beginning of the contract: 1 October 2011
3. (Schleswig-Holstein/Hamburg) A7, Neumünster/N motorway junction– Hamburg/N motorway junction
14 December 2011
4. (Baden-Württemberg) A 6, Wiesloch-Rauenberg motorway interchange – Weinsberg motorway interchange
2012 (planned)
5. (Lower Saxony) A7, Salzgitter motorway junction – Göttingen access point
2012 (planned)
6. (Hesse) A 44, Diemelstadt access point – Kassel-Süd motorway junction
2012 (planned)
7. (Rhineland-Palatinate) A 61, Worms access point - federal state border Rhineland-Palatinate/Baden-Wurttemberg & A 650, A 65
2012 (planned)
8. (Northrhine Westphalia) A 1, Lotte/Osnabrück motorway interchange Münster/N access point and A 30, Rheine/N access point – Lotte/Osnabrück motorway interchange
2012 (planned)
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau10
Prerequisites for the start of the contract award procedure for the A
models
Suitability for realization as PPP model (assessment of suitability for realization as PPP)
Construction permission granted or at least to be granted in the foreseeable future
Positive result of the value for
money test
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau
Value for Money Test
Cost of • construction, • maintenance,• operational service,• planning/ management
Controlling
Start-up financing
Non-transferable risks
Transferable risks
Non-transferable risks
Remuneration to be paid (tolls/availiability)
Economic advantage
Total costs
Conventional variant (PSC) PPP variant (PPP)
Remaining structures
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau12
Value for Money Test– taking national economic advantages into account
Monetizable benefit differences are primarily possible inthe following fields:
• Earlier activation of the overall benefit of the measure
• Lower level of disruption due to shorter construction time
• Benefit differences during the operational phase which are relevant to the national economy
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau13
Award of contract for PPP projects in detail
• EU tender notice, information memorandum
• Competition procedure
• Bidding phase (involving only four candidates)
• Negotiation phase (involving only two candidates)
• Best And Final Offer (BAFO)
• Final economic efficiency analysis
• Conclusion of contract with private partner
• Financial Close
Str
uctu
red
neg
otia
tion
proc
edur
e
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau14
Payment system for the A model pilot projects
• Upgrading, maintenance, operation and pro rata funding by the concessionaire
• Remuneration of the concessionaire from
the HGV tolls levied on the respective concession section ("user pays" funding cycle)
if necessary, start-up financing
if necessary, deductible amounts (contractually agreed upon)
Mechanism (remuneration based on traffic volumes) provides incentives for the concessionaire to ensure high-quality construction/maintenance and at least equivalent operational service
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau15
Structure of the toll remuneration
HGV toll
Toll Collect
Public sector
Federal Office for
Goods Transport
Transport Infrastructure
Financing Company
A model operator
Transfer of the tolls
Contr
ol fu
nct
ions
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau16
Remuneration mechanism availability model A 9
Start-up financing
Remuneration according
to availability
Increases/reductions of remuneration
according to availability
+/-Reductions due to
the system of points
- =
Remuneration of the private partner
Availability restrictions
www.bmvbs.de StB 26 30.01.2012 ÖPP im Bundesfernstraßenbau17
Remuneration mechanism Unit toll model A8 Ulm-Augsburg
Remuneration of the concessionaire by Unit toll rate
- amount was subject to competition- transfer of the traffic volume risk to the concessionaire without simultaneous transfer of the fleet mix risk
Start-up financing - pre-determined
- payment in annual instalments to the tune of 25 % each
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau18
Findings/evolution with regard to future PPPs in road
construction
1. Positive market valuation, avoidance of market concentration;
2. Increase in competence (public sector + private sector), standardization;
3. Simplification of central contractual elements/ deepening of the functionality;
4. Integration and evolution of the findings from the function contracts in road construction;
5. Interaction among the procurement variants, e.g. economic efficiency of the project (transparency of the consequential costs, management of the "road"asset).
www.bmvbs.de StB 26 22.03.2012 ÖPP im Bundesfernstraßenbau19
Contact details
Bundesministerium für Verkehr, Bau und Stadtentwicklung (BMVBS)- Abteilung Straßenbau -Robert-Schuman-Platz 1
53175 Bonn, Deutschland
Phone: + 49 (0)228-300-0
Fax: + 49 (0)228-300-3428
Contact:Referat StB 26: ÖPP im Bundesfernstraßenbau
Phone: +49 – (0)228/300-5260Email: [email protected]