Upload
clarence-hamilton
View
218
Download
0
Tags:
Embed Size (px)
Citation preview
www.costengineering.eu
The Key Role of the Cost EngineerAchieving an Integrated Work Process through a Holistic Mindset
by
Ko des BouvrieTechnical Director – Cost Engineering Consultancy
www.costengineering.eu
About Ko des Bouvrie
Degree:Mechanical Engineering
Experience:Technical Director, Cost Engineering Consultancy B.V. More than 40 years of industrial experience in consulting various industries such as oil & gas, petrochemical, power, mining & minerals, chemicals, construction and pharmaceutical.
Professional Field:Co-founder of Cost Engineering ConsultancyMember of NAP/DACE, AACEI, ICEC and AcostETeacher of cost engineering courses
Cost Engineering Consultancy:Cost Engineering LinkedIn Group (> 6000 members)[email protected]
www.costengineering.eu
Agenda
What is Cost Engineering?• Cost Estimating• Cost Control• PlanningChallenges of the Modern Cost EngineerAchieving an Integrated Work Process through a Holistic Mindset
www.costengineering.eu
What is Cost Engineering?
AACEI defines Cost Engineering as:“That area of engineering practice where engineering
judgment and experience are utilized in the application of scientific principles and techniques to the problems of cost estimating, cost control and profitability”.
www.costengineering.eu
What is Cost Engineering?
The Profession of Cost Engineering:Applying methods and techniques for:
Cost EstimatingCost controlPlanningContracting / TenderingQuantity surveyRisk AssessmentValue Engineering
www.costengineering.eu
Is Cost Engineering a Science?
Some advise:Keep it simple, Cost Engineering is not “Rocket Science”In science 1 + 1 = 2, in cost engineering 1 + 1 = 3Keep in mind that cost engineering is a profession!
www.costengineering.eu
Cost is Everything
“It costs time”“It costs resources”
“ It costs money”
Everything invested in assets and projects
is a Cost
www.costengineering.eu
Challenges of the Modern Cost Engineer
A day in the office
Telephone rings…..
A business partner !!!!
Challenges of the Modern Cost Engineer
www.costengineering.eu
Can We Predict the Future Based on the Past?
Past performance is noguarantee for future results
www.costengineering.eu
What is Cost Estimating?
“An evaluation of all the costs of the elements of a project or effort as defined by an agreed-upon scope.” (AACE 10S-90)
Cost Estimate• Involves assumptions and unknowns• Involves probabilities (and therefore ranges of
costs)• Involves a given scope
• Contingency covers variability within the defined scope - not changes in scope
www.costengineering.eu
Project Life Cycle
Projectinitiation
note
± 40%Screeningestimate
Economics
Step 1
Feasibilitystudy
± 25%Study
estimate
Economics
Step 2
Developmentplan
± 25%Budget
estimate
Economics
Step 3
initialexecution
plan
Initialcommit.
plan
Basis fordesign
Projectspecification
± 10%Control
estimate
commit.plan
Economics
Step 4
Operationsreference
plan
Projectexecution
plan
Detaileddesign
Materialsprocurement Construction
Commission.start-up
handover
Approval Approval
Review
Approval
Review
Approval
Identicalto
Executionphase
Abandonproject
Commit. &cost control
Contractcontrol
Purchaseorder control
Reporting
Operationsreference
plan
Close out
Projectdebrief
Changecontrol
± 5%Counterestimate
Step 5
Identification phase Definition phase Execution phaseOperational
phaseAbandon
phase
Step 6 Step 7
Identicalto
Executionphase
www.costengineering.eu
What is Accuracy?
An estimate should not be regarded as a single point number (or cost)
An estimate is a range of potential cost outcomes, and associated probabilities of occurrence
Thus – the accuracy range of an estimate is a probabilistic assessment of how far a project’s final actual cost can be expected to vary from the estimate• The range is driven by risks
www.costengineering.eu
Cost Estimate Classification (AACEI)
Level of Project definition
End Usage Methodology Expected Accuracy Range
PreparationEffort
Primary Characteristics
Secondary Characteristics
5
4
3
2
1
EstimateLevel
0% to 2%
1% to 15%
10% to 40%
30% to 70%
50% to 100%
ConceptScreening
Study or Feasibility
Budget, Authorization or
Control
Control or Bid / Tender
Check Estimate or Bid / Tender
Capacity factoredParametric
Models, Judgment or analogy
Equipment factoredor Parametric
Models
Semi-detailed unit cost with assembly level line
items
Detailed Unit Cost with Forced Detailed take-
off
Detailed Unit Cost with Detailed take-off
L: -20% to -50%H: +30% to +100%
L: -15% to -30%H: +20% to +50%
L: -10% to -20%H: +10% to +30%
L: -5% to -15%H: +5% to +20%
L: -3% to -10%H: +3% to +15%
1
2 to 4
3 to 10
4 to 20
5 to 100
Cost Estimate Classification System
www.costengineering.eu
Accuracy Level of the Estimate
StudyTypeCClass4
90/10
Order ofmagnitudeDClass5
Base
~2-8% ~1-5%
BudgetTypeBClass3/2
ControlEstimateClass1
+40
%
+10
%
-25%
- 10%
Base
50/50 Base
10/90
90/10
Zero baseline
Base
90/10
90/10
50/50 Base
Base
www.costengineering.eu
What Defines the Accuracy?
Influences on the estimateScope definitionToolsDatabaseRisk• Systemic Risk• Project Specific RiskMarket influencesKnowledge of the cost engineer
www.costengineering.eu
Baseline of Cost Control
“Measurements are the key. If you cannot measure it, you cannot control it. If you cannot control it, you cannot manage it. If you cannot manage it, you cannot improve it.” - James H. Harrington
www.costengineering.eu
What Is Cost Control?
There are two processes used for controlling the costs of the project.
1. Change Management – a formal process that identifies any requested (or un-requested) changes to the contract.
2. Forecasting – predictions of the costs at completion for any cost elements in progress or not yet started.
www.costengineering.eu
Change Management
All changes shall be documented, regardless if no net change in schedule
or cost has happened.
Don’t run and hide !!!
www.costengineering.eu
What Is Forecasting?
Forecasts are much like estimates. Whereas an estimate is always for future activities and assets, forecasts are predictions of the costs at completion for cost elements in progress.
www.costengineering.eu
Earned Value, Budget & Schedule Forecasting
0
200
400
600
800
1000
1200
1400
1600
1800
1-apr 7-apr 14-apr 21-apr 28-apr 5-mei 12-mei 19-mei 26-mei 2-jun 9-jun 16-jun 23-jun
Budget Earned Actual
BCWS(Budgeted cost of work scheduled) ACWP
(Actual cost of work performed)
Budget plan
BCWP (Budgeted cost of work performed
www.costengineering.eu
BusinessPlanning
FeasibilityPlanning
ProjectPlanning
Execution Start-up
Inv
olv
em
en
t
Process Engineering
Project ControlEstimating
Project Director ConstructionOperations
/CommissioningBusiness
Feedback/Learning/Knowledge Engineering
Detailed Engineering /Procurement
Involvement Process for Technical Projects
www.costengineering.eu
Money
Business Case
Process Engineers
Engineering
Quality
Time / Schedul
e
Environment
Safety
Cost Engineers
Project Lead
Process
Flow
Data sheets
Sub Contracto
rs
Health
Regulation
Contractors
Permits
Government
Risk Assessmen
t
Discipline Engineers
Involvement Process for Technical Projects
www.costengineering.eu
Common Problem with Current Approach
Potential of Decisions to Influence Value
Potential of Changes to Destroy Value
Project Life Cycle (Better Scope Definition/Time)More involvement results in better scope definition
www.costengineering.eu
Better Scope Definition Drives Better Absolute, Bottom-Line Cost Performance
Front End Loading (FEL)
Per
cen
tag
e A
bo
ve o
r B
elo
w
Ind
ust
ry A
vera
ge
Co
st
-10%
-5%
0%
5%
10%
15%
20%
3 3,5 4 4,5 5 5,5 6 6,5 7 7,5 8 8,5 9FEL Index
From: Hollmann, John K., Best Owner Practices For Project Control, 2002 AACE Transactions
5% Lower Cost = 1% Better ROE
SCREENINGPOORFAIRGOODBEST
www.costengineering.eu
Less than 30% of Projects Achieve All Business Objectives
Per
cen
t T
hat
Ach
ieve
O
bje
ctiv
e
As Reported by IPA, Inc.
www.costengineering.eu
INITIATION THROUGH CLOSE-OUT PHASE
Close-out phase
CounterEstimate
“Close-out”Report
Cost Control
Execution phase
StudyEstimate
BudgetEstimate
ControlEstimate
ScreeningEstimate
Estimating Cycle: The Ideal Scenario
www.costengineering.eu
From Specialist to All-Round Cost Engineer
Mixing all different ideas together
www.costengineering.eu
Continuous Improvement Cycle
A process for collecting, maintaining, and analyzing project historical information so that it is ready for use in an effective form by each functional processEmpirical information is the most fundamental project planning resource availableIt is manifested in the form of quantified and documented historical data and information The purpose is not to repeat history, but to learn from it (continuous improvement)
www.costengineering.eu
Estimating Cycle: The Ideal Scenario
Scoping & Work PlanningTendering
Purchasing & Warehousing
Execution
Scheduling
EstimatingProject
Controls
www.costengineering.eu
Continuous Improvement Cycle
SchedulePlanning andDevelopment
Physical Progressand Performance
Measurement
Cost Accountingand Resource
Tracking
Cost Estimatingand Budgeting
PerformanceAssessment
ResourcePlanning
Project Historical Database Management
EstimatingReferenceInformation
ScheduleReferenceInformation
ResourceReferenceInformation
Forecasting andChange
Management
ProcurementPlanning
Value and RiskManagement
ScopeDevelopment
ActualSchedule
Data
ActualCostData
ActualResource
Data
ProjectLearnings
ProjectSystem
Learnings
Measurement Methods and Tools Planning Methods and Tools
ControlBaseline
Information
Forecast &Change
Information
Benchmarks/Validation
Metrics
Assessment Methods and Tools
Measurements
AssessmentSupport
Information
ReferenceTools
ReferenceTools
Asset Historical Database Management (6.3)
Suddenly, a heated exchange took place
between the King and the project manager
What was objective?
“dig a ditch next to the castle wall”
or“defend the castle from
attack”Good Scope and Communicatio
n is ESSENTIA
L!
www.costengineering.eu
Questions?
Cost Engineering Consultancy
HQ - PO box 25, 3330 AA Zwijndrecht, IJsselmeer 32e, 3332 EX Zwijndrecht
T: +31 78 620 09 10 F: +31 78 620 91 42E-mail: [email protected]
www.costengineering.eu