3
Yograj Infrastructure Ltd v. Ssang Yong Engineering and Construction Co. Ltd Introduction The appellant is a company incorporated under the companies act, 1956 and the respondent company is a company incorporated as per the laws of the Republic of Korea with its registered office at Seoul and project office at New Delhi. Case history leading to this appeal 1. On 12 th April, 2006, NHAI entered into a contract with the respondent company for up gradation to Four laning of Jhansi-Lakhnadon section in Madhya Pradesh. 2. On 13 th August, 2006, the respondent company entered into a sub-contract with the appellant company to carry out the above mentioned work which mentioned the consideration involved 3. The appellant furnished certain bank guarantees to the respondent company along with investing 88.15 Crore in the project. 4. Clauses 27 and 28 of the agreement provided for arbitration wherein the governing law was to be the arbitration and conciliation act, 1996. 5. On 22 nd September, 2009, the respondent company issued a notice of termination, on the ground of delay in performing the work. 6. the Appellant filed an application before the District and Sessions Judge, Narsinghpur, Madhya Pradesh, under Section 9 of the Arbitration and Conciliation Act, 1996, praying for interim relief's. A similar application under Section 9 of the above Act was filed by the Appellant before the same Court on 30th December, 2009, also for interim relief's. Ultimately, on 20th May, 2010, the dispute between the parties was referred to arbitration in

Yograj Infrastructure Ltd V

Embed Size (px)

DESCRIPTION

Yograj infrastructure

Citation preview

Yograj Infrastructure Ltd v. Ssang Yong Engineering and Construction Co. Ltd

Introduction

The appellant is a company incorporated under the companies act, 1956 and the respondent company is a company incorporated as per the laws of the Republic of Korea with its registered office at Seoul and project office at New Delhi.

Case history leading to this appeal

1. On 12th April, 2006, NHAI entered into a contract with the respondent company for up gradation to Four laning of Jhansi-Lakhnadon section in Madhya Pradesh.2. On 13th August, 2006, the respondent company entered into a sub-contract with the appellant company to carry out the above mentioned work which mentioned the consideration involved3. The appellant furnished certain bank guarantees to the respondent company along with investing 88.15 Crore in the project.4. Clauses 27 and 28 of the agreement provided for arbitration wherein the governing law was to be the arbitration and conciliation act, 1996.5. On 22nd September, 2009, the respondent company issued a notice of termination, on the ground of delay in performing the work.6. the Appellant filed an application before the District and Sessions Judge, Narsinghpur, Madhya Pradesh, under Section 9 of the Arbitration and Conciliation Act, 1996, praying for interim relief's. A similar application under Section 9 of the above Act was filed by the Appellant before the same Court on 30th December, 2009, also for interim relief's. Ultimately, on 20th May, 2010, the dispute between the parties was referred to arbitration in terms of the Agreement and a Sole Arbitrator, Mr. G.R. Easton, was appointed by the Singapore International Arbitration Centre on 20th May, 2010.7. Both parties filed an application for interim measures under section 17 of the act. 8. On considering the prayers of both the parties, the sole arbitrator passed an order in favour of the respondent. Due to which, the appellant went in appeal under section 37(2) of the act to set aside the same. The same was set aside as the respondents conteded that the seat of arbitration is Singapore and hence the laws applicable to the proceedings would be that of Singapore.9. On being aggrieved, the appellants filed for a revision in the High Court, which was also dismissed, against which the current Special leave petition has been filed.

Issues

1. Whether the law of arbitration would be the arbitration act of Singapore?2. Whether the curial laws would be the laws of Singapore?

Held:

1. With regard to the second issue, the court held that clause 27.1 of the agreement states that arbitration proceedings are to be conducted in Singapore in accordance with the SIAC rules. Hence the procedural law with regard to the arbitration proceedings has been held to be the SIAC rules as it was explicitly mentioned in the agreement.2. With regard to the first issue, the judge referred to the judgment of Bhatia International wherein, it was held that Part I of the act did not automatically exclude all foreign arbitral proceedings or awards, unless the parties specifically agreed to exclude the same.3. After reference to the case, in the instant case it was held that Bhatia international would have no application once the parties agreed by virtue of Clause 27.1 of the Agreement that the arbitration proceedings would be conducted in Singapore, i.e., the seat of arbitration would be in Singapore, in accordance with the Singapore International Arbitration Centre Rules as in force at the time of signing of the Agreement. As noticed hereinabove, Rule 32 of the SIAC Rules provides that the law of arbitration would be the International Arbitration Act, 2002, where the seat of arbitration is in Singapore. Although, it was pointed out on behalf of the Appellant that in Rule 1.1 it had been stated that if any of the SIAC Rules was in conflict with the mandatory provision of the applicable law of the arbitration, from which the parties could not derogate, the said mandatory provision would prevail, such is not the case as far as the present proceedings are concerned. In the instant case, Section 2(2) of the 1996 Act, in fact, indicates that Part I would apply only in cases where the seat of arbitration is in India.