Background
2004 Needs Assessment Q1. As the renovation of the recreation center is in the planning stages, what
would you identify as your top five program priorities?
After school Programs, Youth Sports, Community Events, Teen Programs, Preschool Programs/Health and Wellness (tie)
Q2. If we could add additional space to the recreation center, how would you like to see that space allocated?
Indoor Pool, Teen Center, Gymnasium/Art Studios (tie)
Q3. A Master Plan for Costello Park will set priorities for future facilities and amenities for the next 25 years. What would you identify as your top five facilities you would like to see in Costello Park?
Playgrounds, Indoor Aquatic Facility, Walking/Jogging Paths, Outdoor Aquatic Facility, Lighted Sports Fields
Early Master Plan process:• Markham and Associates (2003)• VMDO (8/2004 - 5/2006)
PPEA unsolicited process (8/2006)• 9 responses/3 re-submittals to program• HDR services (11/2006)• Design submitted by OWPR; 45 day review period
commenced (5/2007)• Interim Agreement with Howard Shockey and Sons
(11/2007)
• Comprehensive Agreement (5/2008)*
Background
• 50 year construction standard• Emergency Preparedness - Triple redundant IT
infrastructure• Auxiliary Governing Body chambers (live streaming)• Emergency shelter for up to 250 people, generator to
support the entire facility for 5 days • Office space for IT, Community Resource Officer and Social
Services. • Flexible and diverse programming space • Multi-generational programming opportunities• Energy Efficient• Re-incorporate natural species, reforest
Program Requirements
• Senior friendly facility• Therapeutic recreation opportunities• Community partnering• Human service support• Training and conference spaces• Rental Opportunities• Emergency Shelter• Technologically supported to meet current and
future IT demands• Year round aquatics opportunities• Nature/Outdoor/Interpretive environmental
opportunities
Facility Benefits
Project Partners
•Citizens of Manassas Park
•PPEA Consultants
•Development/Construction Group
•Project Architects
• Concept Master Plan• Concept Facility Plan• Needs Assessment (2004)• Capital Improvement Plan (since 2002)• Technical reports
– Geotechnical Survey, Land survey, Boundary survey, Phase I Environmental Survey, Utility Survey
– Basis of Site and Landscape Architecture Design– Program Criteria– Division 1 Specifications– Performance Criteria
Work Completed
Department of Parks and Recreation
Community Center
PPEA Project$ 22,435,287.00
Proposed Master Plan
Proposed Phase One.
• Facility• Demolition of Existing Elementary School• Demolition of Existing Pool and Building• Indoor Pool• Ornamental Interpretive Garden• Outdoor Plaza• Miracle League Baseball Field• Expansion of Parking Facilities
Phase One Inclusions
Proposed Community Center
Exterior Elevation
Proposed Community Center
Floor Plan
79,110 sq. ft.
Public Comment Period
• The public comment period runs from April 4, 2008 through May 6, 2008.
• Copies of the comprehensive agreement can be reviewed at the Manassas Park City Hall, located at 1 Park Center Court, at the Costello Park Recreation Center, located at 99 Adams Street, or viewed online at www.cityofmanassaspark.us.
• Please direct all correspondence to Catherine Morretta, Parks and Recreation Director, at [email protected] or via direct mail at 99 Adams Street, Manassas Park, Virginia, 20111. For project specific information please contact the Director at 703.335.8871.