Transcript
Page 1: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

1

Construction Delays in Florida: An Empirical Study

Final Report

Submitted to:

Mr. Michael Ashworth Planning Consultant

State of Florida Department of Community Affairs

By:

Syed M. Ahmed, Ph.D., M.ASCE

Assistant Professor & Graduate Program Director Department of Construction Management (CEAS2952) Florida International University, Miami, Fl 33174, USA

Phone: 305-348-2730, Fax: 305-348-6255 E-mail: [email protected] URL: www.fiu.edu/~ahmeds

Salman Azhar, M. Engg., M.ASCE

Ph.D. Candidate and Research Assistant Department of Civil and Environmental Engineering

Florida International University, Miami, Fl 33174, USA

and

Mr. Mauricio Castillo Ms. Pragnya Kappagantula

Research Assistants Department of Construction Management (CEAS2952) Florida International University, Miami, Fl 33174, USA

Page 2: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

2

INTRODUCTION General: The Construction industry is large, volatile, and requires tremendous capital outlays. Typically, the work offers low rates of return in relation to the amount of risk involved. A unique element of risk in the industry is the manner in which disputes and claims are woven through the fiber of the construction process. The type of contract used, is often based on an overall attempt to allocate (often shifting) the risks of the work to the parties involved. A certain amount of risk must always be recognized and accepted. Risk can only be mitigated - it cannot be eliminated. Delays on construction projects are a universal phenomenon. They are almost always accompanied by cost and time overruns. Construction project delays have a debilitating effect on parties (owner, contractor, consultant) to a contract in terms of a growth in adversarial relationships, distrust, litigation, arbitration, cash-flow problems, and a general feeling of apprehension towards each other. Delays caused by the client such as late submission of drawings and specifications, frequent change orders, and incorrect/inadequate site information generate claims from both the main contractors and subcontractors which many times entail lengthy court battles with huge financial repercussions. Delays caused by contractors can generally be attributed to poor managerial skills. Lack of planning and a poor understanding of accounting and financial principles have led to many a contractor’s downfall. Empirical studies to determine the causes of delays in construction projects have been carried out in the US. Objectives of the Study: The main objective of this study is to identify the major causes of delays in construction projects in the Florida Construction Industry through a survey. The primary aim is to identify the perceptions of the different parties regarding causes of delays, the allocation of responsibilities and the types of delays. Scope of the Study: The scope of this research project is limited to building projects in the Florida region only. The data for this study has been gathered through detailed literature review and questionnaire survey.

Page 3: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

3

Organization of the Report: The report is logically organized into five (5) chapters and appendices: Chapter one is composed of background and general information, which give an overview of the various types of delays encountered in a project. It includes the overall delays concept along with the causes and further classification of delays, responsibilities that the parties have in a delay, time extensions and liquidated damages. Chapter two comprises of literature review, and quotes the various related works done in this area of study. Chapter three describes in detail the methodology followed in this research study. Chapter four contains the analysis of the information gathered through the questionnaire survey, identifies the critical causes of delay in the Florida Construction Industry, based on the chance of occurrence. Chapter five provides the conclusions and recommendations of the study.

Page 4: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

4

CHAPTER 1:

BACKGROUND 1.1. General Delay is generally acknowledged as the most common, costly, complex and risky problem encountered in construction projects. Because of the overriding importance of time for both the Owner (in terms of performance) and the Contractor (in terms of money), it is the source of frequent disputes and claims leading to lawsuits. To control this situation, a contract is formulated to identify potential delay situations in advance and to define and fix obligations to preclude such controversies. A substantial number of General Conditions clauses address this subject in one way or another. Under some circumstances, a Contractor may be entitled to claim delay damages if he finishes later than an Owner-accepted early completion schedule but is still ahead of the official contract completion date. This may occur if the Contractor establishes a direct cause-and-effect relationship between Owner’s breach of a contractual obligation and the delay. In addition, the Contractor has the burden of establishing its increased costs as a result of the delay. It is found in practice that not everything in the contract can be taken at face value and applied in cookbook fashion. Circumstances play a great deal in determining which clause(s) will be applied to a particular delay claim. Also, contract law encompasses concepts of reasonableness and fair dealing, implied obligations and warranties, constructive acceleration, etc. A good general understanding of the principles involved and the operation of the applicable clauses are essential to help make appropriate decisions and take the proper action in those delay situations. In a large and complex project there will be a certain amount of give and take policy among the parties competing for the same time and space. Time, energy, and money must not be diverted in pursuing claims and disputes over minor delays, disruptions, and interferences. Accordingly, the General Conditions in Owner issued contracts typically contain clauses that the Contractor on notice can plan for certain events. Further delays that occur due to these events can be termed as ‘non-excusable delays’. Often contract clause will require that a delay claim be submitted in writing within a stipulated number of days from the commencement of a delay. Further, within those stipulated number of days, after the termination of any such delay, the Contractor is required to file a written notice specifying the actual duration of the delay. Failure to give either of the above notices shall provide sufficient ground for denial of an extension of time. By giving notice, the Contractor warns the Owner in taking alternate action to avoid or reduce the excess costs.

Page 5: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

5

However, delays do not always result from a single catastrophic event. They frequently develop slowly during the course of work. Minor delays are generally overlooked until their cumulative effect becomes financially apparent. By the time a Contractor recognizes that there is a problem, many different parties and natural forces would have contributed to the situation. Failure to comply with the notice requirements can contribute to the situation which may or may not defeat the claim. To avoid acceleration claims from Contractors in delay situations, it is best to:

� Issue formal (change order) schedule extensions in a timely manner when justified

� Avoid ordering early or inappropriate completion � Respond in a timely manner to any Notice of Claim from the Contractor

1.1 Types of delays: Delays can be grouped in the following four broad categories according to how they operate contractually:

� Non-excusable delays � Excusable non-compensable delays � Excusable compensable delays � Concurrent delays

1.1.1 Non-excusable Delays Non-excusable delays are delays, which the Contractor either causes or assumes the risk for. These delays might be the results of underestimates of productivity, inadequate scheduling or mismanagement, construction mistakes, weather, equipment breakdowns, staffing problems, or mere bad luck. Such delays are inherently the Contractor’s responsibility and no relief is allowed. These delays are within the control of the Contractor or are foreseeable; however, it is not necessary that they be both. 1.1.2 Non-compensable Excusable Delays: When a delay is caused by factors that are not foreseeable, beyond the Contractor’s reasonable control and not attributable to the Contractor’s fault or negligence, it may be “excusable”. This term has the implied meaning that neither party is at fault under the terms of the contract and has agreed to share the risk and consequences when excusable events occur. The Contractor will not receive compensation for the cost of delay, but he will be entitled for an additional time to complete his work and is relieved from any contractually imposed liquidated damages for the period of delay.

Page 6: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

6

1.1.3 Compensable Excusable Delays In addition to the compensable delays that result from contract changes by Change Notice, there are compensable delays that can arise in other ways. Such compensable delays are excusable delays, suspensions, or interruptions to all or part of the work caused by an act or failure to act by the Owner resulting from Owner’s breach of an obligation, stated or implied, in the contract. If the delay is compensable, then the Contractor is entitled not only to an extension of time but also to an adjustment for any increase in costs caused by the delay. Owner-issued contracts specifically address some potential compensable delays and provide equitable adjustments. The usual equitable adjustment clauses in Owner issued contracts that apply to delay are:

� Changes � Differing Site Conditions � Suspension

The changes clause in Owner-issued contracts provides that equitable adjustments may be considered as follows: 1.1.3.1 Changes With the help of a written Change Notice, the Owner may, without any notice to the sureties (if any), unilaterally make any change, at any time in the Work within the general scope of the Contract, including but not limited to changes:

� In the drawings, designs or specifications � In the method, manner or sequence of Contractor’s work � In Customer or Owner furnished facilities, equipments, materials, services or

site(s) � Directing acceleration or deceleration in the performance of the work � Modifying the Contract Schedule or the Contract milestones

If at any time Contractor believes that acts or omissions of Customer or Owner constitute a change to the Work not covered by a Change Notice, Contractor shall within ten (10) calendar days of discovery of such act or omission, submit a written Change Notice Request, explaining in detail the basis for the request. Owner may either issue a Change Notice or deny the request in writing. If any change under this clause causes directly or indirectly an increase or decrease in the cost, or the time required for the performance of any part of the Work, whether or not changed by any order, an equitable adjustment shall be made and the contract will be modified accordingly. The clause recognizes that changes in the work or changes in the method or manner of performance may require changes in the schedule and schedule milestones and this could further necessitate revisions in activity durations, sequence of work items, or

Page 7: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

7

interrelationships of various tasks. These changes may have a direct impact on the schedule, as where a change in method requires a greater or lesser period of performance or its effects may be subtler, as where the change merely rearranges priorities. In addition to a time extension, the contract’s clause provides compensation for any delay resulting from a contract change by allowing an equitable adjustment for the increased cost of the performance of the work caused by the change. 1.1.3.2 Differing Site Conditions The portion of the clause addressing cost or time adjustments for ‘differing site conditions’ provides: If such conditions do differ in material and thus cause an increase/decrease in the Contractor’s cost or time required for performance of the Work, an equitable adjustment will be made pursuant to the General Condition titled “Changes”. No claim of the Contractor under this clause will be allowed unless the Contractor has given the required notice. The main intention is to leave the Contractor neither damaged nor enriched because of the resultant delay. The differing site conditions clause must not be confused with the Site Conditions clause in Owner issued contracts - the so-called “Exculpatory” clause. Its intent is to disallow any claims for delays relating to conditions at the site, which the Contractor should have anticipated. The exceptions are limited to those conditions defined in the Differing Site Conditions clause. 1.1.4 Concurrent Delays Concurrent delays occur when both Owner and the Contractor are responsible for the delay. Generally, if the delays are inextricably intertwined, neither the Contractor can be held responsible for the delay (forced to accelerate, or be liable for liquidated damages) nor can he recover the delay damages from the Owner. Until the development of CPM schedule analysis, there was no reliable method to differentiate the impact of Contractor caused delays from Owner-caused delays. With the sophisticated computerized techniques now available, however, it has become possible to segregate the impacts of apparently concurrent Owner and Contractor delays. In analyzing a delay claim, an analysis based on a comparison of the Contractor’s approved CPM schedule with the as-built CPM schedule should be performed to apportion proper responsibility for delay. Because the critical path may shift as the job progresses, it is updated based upon contractually required input from the Contractor.

Page 8: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

8

1.2 Causes of delays: There are two kinds of causes for delays in construction projects: external and internal causes. Internal causes of delays include the causes, which come from four parties involved in that project. These parties include the Owner, Designers, Contractors, and Consultants. Other delays, which do not come from these four parties, are based on external causes for instance from the government, material suppliers, or weather. The followings are some of the possible causes of delays that the construction industry is facing nowadays:

• Possessive decision-making mechanism • Highly bureaucratic organization • Insufficient data collection and survey before design • Site’s topography is changed after design • Lack of coordination at design phase • Inadequate review • Improper inspection approach • Different attitude between the consultant and contractors • Financial difficulties • Inexperienced personnel • Insufficient number of staffs • Deficiency in project coordination • Spend some time to find sub-contractors company who is appropriate for each

task • Often changing Sub-contractors Company • Inadequate, and old equipment • Lack of high-technology equipment • Harvest time

1.3 Extensions of Time: Time is an integral part of every plan a company develops for performing contract work. There is a relationship between the schedule, the scope of work, and the project conditions. Changes to any one or more of the above three can affect the time of completion and compensation. 1.3.1 Excusable or Non-excusable Delays Delays can quickly consume the time in your schedule, and it is important to understand the net effect of those delays.

• Non-excusable: the construction company gets no time or money

Page 9: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

9

• Excusable: the construction company gets time, but no money • Compensable: the construction company gets both time and money

To be able to evaluate which type of delay you may be experiencing, you first need to read the full Contract. Usually a contract clause dealing with time, schedule, suspension of the work, or default will list the events that will entitle you to an extension of time. A typical clause allows extensions of time for unforeseeable events that are beyond the company’s control and are not caused by the company’s fault or negligence. Clauses often give a “laundry list” of examples, such as:

• Acts of God • Acts of the public enemy • Acts of the Owner or those under his control • Acts of the Owner’s independent Contractors • Fire • Floods • Epidemics • Quarantine restrictions • Strikes • Freight embargoes • Unusually severe weather

This type of clause sometimes called a “force majeure” clause, lists excusable delays. Any other type of delay becomes Non-excusable. A typical Non-excusable delay is one where the company or anyone for whom the company is responsible (subcontractors or suppliers) has caused a delay by failing to:

o Prosecute the work in a timely manner. o Properly staff the job. o Order materials or equipment on time. o Submit shop drawings for approval on schedule. o Coordinate the work of its subcontractors.

Thus, the company must read the Full Contract carefully because occasionally it is found, for example, that weather (not just abnormal or unusually severe weather) might be an excusable delay, while strikes are not. An excusable delay for which a company receives payment in addition to a time extension is called a compensable delay. Typically compensable delays occur when the Owner or one of his representatives, including the engineer, architect and construction manager, has delayed the contract in the prosecution of its work. Examples of compensable delays by the Owner are:

o Failure to provide access to all or part of the worksite when the company needs it. o Failure to review shop drawings in a timely manner.

Page 10: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

10

o Failure to properly coordinate the work of his other Contractors on the site. o Ordering changes in the company’s method or sequence for performing the work.

Other owner acts that stop or disrupt the company’s prosecution of its work. 1.4 Receiving Due Compensation: The clause that lists excusable delays usually will not tell you if the delay is also compensable. It may either say nothing about it or sometimes may even say that the delay is not compensable, which is not necessarily so. The company may have to look at other clauses in the contract to see if the company is entitled to compensation for one or more of the types of excusable delays listed above. There are clauses that may entitle the company for compensation for certain delays. Other clauses to check are the “changes” clause and the “Differing Site Conditions” clause, both of which will say that the company will be compensated for added costs under the circumstances described in those clauses. 1.5 Giving Required Notice: The need to give contractually required notices to the Owner is stressed. Virtually all contract provisions that deal with excusable and compensable delays contain a requirement for prompt written notice of the delay to the Owner. In addition, the next schedule update submitted to the Owner should clearly show any delays the company has experienced and the time extensions the company is entitled to (and has requested from the owner), whether the Owner has approved it or not. The schedule update should be accompanied by a narrative that describes the delay and its impact in the completion of the project to the extent known at that time. If the delay is non-excusable, notice to the Owner is generally not required. However, even a non-excusable delay may have to be shown on the contractually required schedule together with the actions the company will take to make up for the effects of the delay, such as acceleration of the work. 1.5.1 Steps to take when delays occur: With time being the essence in most of the construction contracts and with the project duration clearly defined, it is also important to follow the next outline procedures when delays occur: Whenever the Contractor foresees any delays in the prosecution of the work, and in any event immediately upon the occurrence of any delay which the Contractor regards as unavoidable, the Contractor shall notify the Owner’s representative in writing of the probability of occurrence of such delay and its cause in order that the Owner’s representative may take immediate steps to prevent, if possible, the occurrence or continuance of the delay or, if this cannot be done, may determine whether the delay is to be considered avoidable or unavoidable, how long it continues, and to what extent the prosecution and completion of the work are to be delayed. The Contractor shall make no

Page 11: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

11

claims that any delay not taken to the attention of the Owner at the time of its occurrence has been an unavoidable delay. 1.6 Liquidated Damages and Acceleration: The concepts of “liquidated damages” and “acceleration” are often opposite approaches in solving the delay problem. When does a company have to pay liquidated damages? What if the contract does not have liquidated damages clauses? When does the company have to accelerate the job? When does the owner pay for the acceleration? 1.6.1 Liquidated Damages: The word “liquidated” is a legal concept, which means the amount of money to be paid for late-completion, if fixed. A company seldom (if ever) signs a contract that does not have a specified completion date. The combination of that specific date and time is of essence in the contract, which means that if the company fails to complete the work on time – and that the causes of the delay are due company’s fault the company is liable for all of the Owner’s damages that occur because of that delay. 1.6.2 Acceleration: Events may delay the job and shorten the Contractor’s time to accomplish his work. Or the Owner may require the Contractor to finish his work sooner than initially scheduled. Either of these cases may call for an acceleration of Contractor’s work – that is, Contractor may need to make up time to avoid damages (liquidated or actual) payable to the Owner for the late completion of the project. It is often carried by working overtime and on weekends by adding manpower or even by placing extra shifts and equipment. 1.7 Controlling the project: Project control consists of two components: one, accurate information about the schedule status of a project, and the other, actions taken in response to the status reports. The driving force for keeping a project “on schedule” is money. Typically, contracts include liquidated damages for a project not being completed on time or bonus/penalty clauses that provide an incentive to the Contractors to complete the project as soon as possible. 1.8 Delay responsibility: The issue of delay responsibilities is related to whether the Contractor is awarded, or is liable for costs and additional time to complete the project. The categories of responsibilities are:

Page 12: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

12

� Owner (or Agent) Responsible: Contractor will be granted time extension and additional costs (indirect), where warranted.

� Contractor (or subcontractor) Responsible: Contractor will not be granted time or costs and may have to pay damages/penalties.

� Neither Party (e.g., Act of God) Responsible: Contractor will receive additional time to complete the project but no costs will be granted and no damages/penalties assessed.

� Both Parties Responsible: Contractor will receive additional time to complete the project but no costs will be granted and no damages/penalties assessed.

1.9 CPM in Dispute Resolution and Litigation: In many cases it may only be in the “final analysis”, during the resolution of disputes, that CPM is considered to be worth to use it to its fullest extent. It is at this point that the CPM technique is particularly useful, because it provides a complete model of the project. The model illustrates how the project was originally planned and how it changed as the project progressed. By introducing changes into this model, it would be possible to see how other portions of the model will be affected. It thereby furnishes a basis upon which assessments of time and money awards can be made. 1.10 Going to court: Disputes normally come down in assessing three aspects of delays: (1) whose was the fault or who caused the delay, (2) how much delay occurred (project delay) and, consequently, (3) what monetary awards should be made. The Critical Path Method is primarily useful in addressing the second of these conditions and in some cases can be used to assist in determining at least a portion of the monetary awards. CPM enables anyone to evaluate the impacts of the action of any party (Owner, Contractor, subcontractor, or other). Most importantly, the assessment can be considered as being objective (unbiased) provided the model (network) used is valid. There are numerous court cases in which the project duration has allegedly been compromised by changed orders, differing site conditions, excusable delays, non-excusable delays, suspensions of work, and others causes. Many of these cases concern Contractors who felt that they have been delayed the project as a result of some occurrence for which there was entitlement to additional time and/or money. 1.11 As-built schedules: As-built schedules are similar to as-built drawings. Where as-built drawings are corrections made on the original set of construction drawings to reflect the actual locations of all construction features, as-built schedules reflect the actual time occurrences for all major project activities. As-built schedules are not commonly prepared in most projects. Note that an updated schedule merely shows the correct status of the project activities beginning at a designated point in time. In the updated schedules,

Page 13: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

13

the actual occurrence time of past activities is not of primary interest. It is only when the true representation of the entire project schedule is needed that an as-built schedule is warranted. Since these take time to prepare, a decision must be it the effort is justified. What is the purpose of as-built schedules? The most widely recognized use is in the area of claims, especially delay claims, from a Contractor’s point of view, an as-built schedule might be prepared to demonstrate how a particular Owner-caused delay or unforeseen condition resulted in a significant project delay. This will often be difficult to show without an as-built schedule. To make the impact of delay clear, comparisons must be made against other schedules of the project, namely those that were prepared without the anticipation of a delay. 1.12 Building code-related delays: The following is the list of the most likely causes for delays to happen related to building code-related:

• Building Permits Approval Process • Changes in Laws and Regulations • Safety Rules • OSHA Regulations • Florida Building Code • Building Regulations in Coastal Regions • Coastal Construction Control Line Permit • Florida Administrative Code • National Flood Insurance Program

1.12.1 The United Florida Building Code:

� The United Florida Building Code (FBC) drives the Florida Building System. � A new Florida Building Code started applicable from March 1, 2002. � FBC describes the code of the general organization, its applicability, and major

exemptions, as well as major changes to the code relevant to high wind provisions and means of egress.

1.12.2 OSHA Regulations: The term "Occupational Safety and Health Standard" means a standard which requires conditions, or the adoption or use of one or more practices, means, methods, operations, or processes, reasonably necessary or appropriate to provide safe or healthful employment and places of employment.

Page 14: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

14

1.12.3 Coastal Construction Control Line (CCCL) Program: The purpose of the CCCL program is to preserve and protect Florida's coastal beach-dune system from imprudent construction and still provide reasonable use of private property. Construction can jeopardize the shoreline's stability, accelerate erosion, provide inadequate protection to upland structures, endanger adjacent properties, or interfere with lateral public beach access. Within the boundaries of the CCCL, no person, firm, corporation, or governmental agency may construct any type of facility or building without a CCCL permit, unless it is exempted. Regulated activities include everything from large multifamily developments to dune walkover structures. 1.12.4 National Flood Insurance Program (NFIP) Zones: The NFIP began in 1968 as a nationwide system for obtaining flood insurance. The program first helped in developing maps of all areas that have a 1% chance of serious flooding each year. Local governments were also encouraged to adopt regulations to reduce the impacts of future flooding. In exchange for these regulations property owners within the community can obtain flood insurance. If a community does not adopt regulations to reduce flood impacts, property owners in the community are not eligible for federal flood insurance.

Page 15: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

15

CHAPTER 2.

LITERATURE REVIEW

2.1 General: One of the most important problems in the Construction industry is delay. Delays occur in every construction project and the magnitude of these delays varies considerably from project to project. Some projects are only a few days behind the schedule; some are delayed over a year. So it is essential to define the actual causes of delay in order to minimize and avoid the delays in any construction project. There is a wide range of views for the causes of time delays for engineering and construction projects. Some are attributable to a single party, others can be ascribed to several quarters and many relate more to systemic faults or deficiencies rather than to a group or groups. The successful execution of construction projects and keeping them within estimated cost and prescribed schedules depend on a methodology that requires sound engineering judgment [1]. 2.2 Previous Work Leishman [4] presented the legal consequences of delays in construction. Herbsman et al. [5] studied the effect of delays on cost and quality. Yates [6] developed a decision support system for construction delay analysis called (DAS). The main categories of delays in DAS include engineering, equipment, external delays, labor, management, material, owner, subcontractors, and weather. Ogunlana et al. [7] studied the delays in building project in Thailand, as an example of developing economies. They concluded that the problems of the construction industry in developing economies could be nested in three layers: (1) problem of shortages or inadequacies in industry infrastructure, mainly supply of resources; (2) problems caused by clients and consultants; and (3) problems caused by incompetence of contractors. Kumaraswamy et al. [8] surveyed the causes of construction delays in Hong Kong as seen by clients, contractors and consultants, and examined the factors affecting productivity. The survey revealed differences in perceptions of the relative significance of factors between the three groups, indicative of their experiences, possible prejudices and lack of effective communication. Mansfield et al [9] studied the causes of delay and cost overrun in construction projects in Nigeria. The results showed that the most important factors are financing and payment for completed works, poor contract management, changes in site conditions, shortage of material, and improper planning.

Page 16: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

16

Assaf et al. [10] studied the causes of delay in large building construction projects in Saudi Arabia. The most important causes of delay included approval of shop drawings, delays in payments to contractors and the resulting cash-flow problems during construction, design changes, conflicts in work schedules of subcontractors, slow decision making and executive bureaucracy in the owners' organizations, design errors, labor shortage and inadequate labor skills. Mezher et al. [11] conducted a survey of the causes of delays in the construction industry in Lebanon from the viewpoint of owners, contractors and architectural/engineering firms. It was found that owners had more concerns with regard to financial issues, contractors regarded contractual relationships the most important, while consultants considered project management issues to be the most important causes of delays. Battaineh [2] evaluated the progress reports of 164 building and 28 highway projects constructed during the period 1996¯1999 in Jordan. The results indicate that delays are extensive: the average ratio of actual completion time to the planned contract duration is 160.5% for road projects and 120.3% for building projects. Al-Momani [3] conducted a quantitative analysis of construction delays by examining the records of 130 public building projects constructed in Jordan during the period of 1990¯1997. The researcher presented regression models of the relationship between actual and planned project duration for different types of building facilities. The analysis also included the reported frequencies of time extensions for the different causes of delays. The researcher concluded that the main causes of delay in construction projects relate to designers, user changes, weather, site conditions, late deliveries, economic conditions, and increase in quantities. Hancher and Rowings, [1] for example, provide a concise summary of the methodologies used by transportation agencies to establish the contract duration used for highway construction projects, and also provides a schedule guide for field engineers during construction. Similarly, Chalabi and Camp [13] conducted a review on project delays in developing countries during planning and construction stages. In their study they found that the delay and cost overruns of construction projects are dependent entirely on the very early stages of the project. Fereig and Qaddumi [14] in their study on the construction experience of the Arabian Gulf demonstrate the various components of the planning, controlling and productivity on construction delay. Their primary purpose is to alert the reader to the deviation from the project plans. Wilson [15] examined the role of the owner and architect/engineer's roles in the prevention and resolution of construction claims. Wilson also summarized the causes of construction claims which include: extra work, project delays and acceleration, lack of management, limited site access and change in work schedule. Jonathan Jingsheng Shi [16] presented a paper on method for computing activity delays

and assessing their contributions to project delay. The method consisted of a set of

Page 17: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

17

equations, which could be easily coded into a computer program that would allow speedy access to project delay information and activity contributions. Sabah Alkass, Mark Mazerolle, Frank Harris [17] presented a paper which discusses different delay analysis techniques that are currently used by practitioners in the construction industry. It also discusses a proposed new delay analysis technique called the Isolated Delay Type (IDT). These techniques were tested against a case example and their strengths and weaknesses highlighted. Empirically based time performance research measures either construction time (physical building time) or contract time (performance measured against the date stipulated in contracts). Bromilow [18] headed a CSIRO investigation of contract time performance for 329 projects constructed between 1964 and 1969. One outcome of this study was the development of an empirical relationship between total cost of construction and project duration. The equation describing the average duration as a function of value is T = KCb, where ‘T’ equals the construction period from possession of site to practical completion in days, ‘C’ is the final adjusted project value, ‘K’ is a constant describing how time performance is affected by size, and ‘b’ a constant indicative of the sensitivity of time performance to cost level. This established the parameters of cost/time performance predictability, although the performance of the individual projects varied significantly. The relationship was re-tested by Bromilow [19] in collaboration with the Australian Institute of Quantity Surveyors (AIQS) in two follow-up contract time performance studies, in 1976 and 1988. The former study investigated 408 projects built between 1970 and 1976 and found that despite evidence of greater variation between the time performance of projects of similar value, ‘the relationship between construction duration and project cost uncovered in the 1960s still holds.’ The 1988 study investigated 408 projects built between 1976 and 1986. It found that the average contract time was about 32% for government contracts and 22% for private contracts (Bromilow, Hinds, & Moody 1988). Ireland [20] describes the relationship between time, cost, and quality as in the following terms: • time is a function of cost and quality • cost is a function of time and quality • quality is a function of time and cost He studied the performance on twenty five high rise commercial projects in Sydney, Australia. Amongst his finding is confirmation of the formula derived by Bromilow, though with slightly different constants. A detailed study by the NSW Royal Commission into Productivity in the Building Industry (1992) of 20 commercial high-rise buildings with a total design and construct value of over A$2.0 billion found 22 specific causes of time overrun. Weather, industrial

Page 18: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

18

disputation, client scope changes and variations, and consultant problems were some of the ones occurring with the highest frequency. Comparative time performance research has been conducted by Ireland in several studies; a comparison of Australian contractors (1984), a comparison of US and UK projects with Flanagan, Norman and Orerod (1986) and a comparison of best US and Australian contractors (1987). Ireland’s [21] study compared 14 office and hotel projects by a leading Australian contractor with 22 similar projects by a similar US contractor and later compared them with the performance of a leading UK contractor. One of the major findings of this study was that if the US contractor takes 107 days, the UK takes 118 days and the average Australian best takes 136 days. In sum, Australian projects take up to 20-30% longer than in the US. There has been a considerable and continued interest on the effects of construction delays. The information available is diverse and widespread. Despite the necessity for such research, little work has been described in the literature concerning public projects. The previously proposed factors contributing to construction delay were frequently observed in public projects. The actual frequency and magnitude of these factors is not known, which has proven to be a serious and very expensive problem for the construction industry.

Page 19: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

19

CHAPTER 3.

METHODOLOGY 3.1 General The preliminary data for this research was collected through a literature review and the use of a questionnaire survey targeted at Contractors in the State of Florida.

The literature review was done through books, conference proceedings, the Internet, and leading construction management and engineering journals. In this step, all the causes for delays that may be encountered in a construction project were identified through a detailed review of published technical papers, recent magazines, newspapers and via Internet. The causes of delays are classified into six broad categories depending on their nature and mode of occurrence. Based on the findings, the delays checklist is as follows:

Detailed Literature Review

Questionnaire Survey

Florida’s Construction Contractors

Analysis

Conclusions & Recommendations

Page 20: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

20

ACTS OF GOD Flood

Hurricane Fire Wind Damage

DESIGN - RELATED Design Development Change Order Decision during development stage Changes in Drawings Changes in Specifications Shop Drawings Approval Incomplete Documents

CONSTRUCTION-RELATED Inspections Subsurface Soil Conditions Material/Fabrication Delays Material Procurement Lack of Qualified Craftsmen Poor Subcontractor Performance Defective Work Different Site Conditions Labor Injuries Damage to Structure Construction Mistakes Poor Supervision Equipment Availability

FINANCIAL/ECONOMICAL Financial Process Financial Difficulties Delayed Payments Economic Problems

MANAGEMENT/ADMINISTRATIVE Labor Dispute and Strike Inadequate Planning Inadequate Scheduling Contract Modifications Underestimation of Productivity Staffing Problems Lack of coordination on-site Scheduling Mismanagement Transportation Delays Suspensions Inadequate Review Lack of High-Technology Poor Managerial Skills

Page 21: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

21

CODE-RELATED Building Permits Approval Process

Changes in Laws and Regulations Safety Rules OSHA Regulations Florida Building Code Building Regulations in Coastal Regions Coastal Construction Control Line Permit Florida Administrative Code National Flood Insurance Program

3.2 Questionnaire: The questionnaire survey (Appendix A) was made available on the Internet and was developed to identify:

• The type of delay: A=Non-Excusable B=Excusable Non-Compensable C=Excusable Compensable D=Concurrent

• Chance of occurrence: 1-Unlikely = 20 % probability to happen. 2-As likely as not = 40 % 3-Likely = 60 % 4-Almost certain = 80 % 5-Certain = 100 % probability to happen

• Responsibility Own=Owner Cont=Contractor Cons=Consultant Gov=Government Shared=Shared

3.3 Analysis and Conclusions: Upon the completion of the data analysis, conclusions and recommendations were presented.

Page 22: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

22

CHAPTER 4.

ANALYSIS OF RESULTS

4.1 General: This chapter deals with the analysis of the information gathered (Appendix B) from the questionnaire survey and includes the identification of the critical causes of delays, responsibilities and types of delays based on the delays checklist outlined in the methodology section of the report. 4.2 Questionnaire Response Rate: A detailed questionnaire was prepared (appendix A) and sent to the different companies specially General Contractors in the State of Florida by regular mail and also via Internet. The survey was carried out over the period from October 2001 to March 2002, and the response rate is as shown in the Table 4.1:

Questionnaire Sent

Regular Mail Via Internet Total

No. of Participant

200

180

380

No. of Companies

Responding

23

12

35

Response Rate

11.5%

6.67%

9.21%

Table 4.1 Response Rate

4.3 Identification of the Key Delays: The key causes of delays are presented in tables 4.1 – 4.5. Each table categorizes the different causes of delays (Acts of God, Design-Related Delays, Construction-Related Delays, Financial/Economical Delays, Management/Administrative Delays and Code-Related Delays) based on the chance of occurrence. The chance of occurrence was rated on a scale of 1 to 5 with 1 having the lowest frequency of occurrence and 5 the highest. The number in the filled cells indicates the number of respondents who chose that option. The last cell in each category shows the average of the responses while the far most right column indicates the selection of the key causes of delays, which were selected as those having a value of 2.5 or higher indication at least a 50% chance of occurrence.

Page 23: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

23

1. Acts of God

1 2 3 4 5 Total Key Delay

Flood 20 4 3 0 0 1.37 Hurricane 5 10 9 1 0 2.24 Fire 11 11 3 0 0 1.68 Wind Damage 7 11 7 0 0 2.00 Total of Key Delay 0

Table 4.2 Key Delays – Acts of God

2. Design-Related

Design Development 1 4 12 7 2 3.19 � Change Order 0 3 5 12 6 3.81 � Decision in development stage 0 5 11 6 4 3.35 � Changes in Drawings 0 3 6 10 6 3.76 � Changes in Specifications 2 4 8 8 5 3.37 � Shop Drawings Approval 0 5 10 4 3 3.23 � Incomplete Documents 0 4 8 5 7 3.63 � Total of Key Delay 7

Table 4.3 Key Delays – Design Related

3. Financial/Economical

Financial Process 4 10 8 2 0 2.33 Financial Difficulties 5 10 8 1 0 2.21 Delayed Payments 2 8 8 5 0 2.70 � Economic Problems 4 11 7 2 0 2.29 Total of Key Delay 1

Table 4.4 Key Delays – Financial/Economical

Page 24: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

24

4. Construction Related

1 2 3 4 5 Total Key

Delay Inspections 0 4 12 4 5 3.40 � Subsurface Soil Conditions 4 10 10 3 0 2.44 Material/Fabrication Delays 1 7 14 3 2 2.93 � Material Procurement 1 13 6 5 1 2.69 � Lack of Qualified Craftsmen 4 8 9 3 2 2.65 � Poor Subcontractor Performance 2 9 8 5 2 2.85 � Defective Work 5 11 6 3 1 2.38 Different Site Conditions 5 8 9 4 0 2.46 Labor Injuries 7 9 7 2 1 2.27 Damage to Structure 14 8 3 0 0 1.56 Construction Mistakes 5 9 6 2 3 2.56 � Poor Supervision 5 9 8 2 1 2.40 Equipment Availability 9 8 6 2 0 2.04 Total of Key Delay 6

Table 4.5 Key Delays – Construction Related

5. Management and Administrative 1 2 3 4 5 Total Key Delay

Labor Dispute and Strike 12 6 4 1 0 1.74 Inadequate Planning 5 9 7 3 0 2.33 Inadequate Scheduling 4 9 7 2 0 2.32 Contract Modifications 2 7 5 7 1 2.91 � Underestimation of Productivity 3 13 6 2 0 2.29 Staffing Problems 4 10 7 2 0 2.30 Lack of coordination On-site 5 9 8 1 0 2.22 Scheduling Mismanagement 5 8 7 3 0 2.35 Transportation Delays 3 11 7 1 0 2.27 Suspensions 10 9 3 1 0 1.78 Inadequate Review 5 8 7 2 1 2.39 Lack of High-Technology 7 8 6 0 0 1.95 Poor Managerial Skills 6 8 9 1 0 2.21 Total of Key Delay 1

Table 4.6 Key Delays – Management and Administrative

6. Code Related

Building Permits Approval Process 1 2 6 5 9 3.83 � Changes in Laws and Regulations 1 7 8 4 3 3.04 � Safety Rules 3 8 9 0 3 2.65 � OSHA Regulations 2 11 5 3 2 2.65 � Florida Building Code 1 7 9 3 3 3.00 � Building Regulations in Coastal Regions 0 10 9 1 3 2.87 � Coastal Construction Control Line Permit 3 4 9 3 3 2.95 � Florida Administrative Code 4 6 6 4 2 2.73 � National Flood Insurance Program 5 7 5 3 2 2.55 � Total of Key Delay 9

Page 25: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

25

Table 4.7 Key Delays - Code Related After analyzing tables 4.2 through 4.7, based on their chance of occurrence the main key delays ranked from the highest to the lowest in each category affecting the Florida Construction Industry are shown as follows:

Code Related Delays

3.83

3.04 3 2.95 2.87 2.73 2.65 2.65 2.55

00.5

11.5

22.5

33.5

44.5

Key Delays

Building Permits Approval

Changes Laws-Regulations

Florida Building Code

Coastal Construction ControlLine Permit Building Regulations CoastalRegions Florida Administrative Code

Safety Rules

OSHA Regulations

Fig 4.1 Ranking of Code Related Key Delays

Design Related Delays

3.81 3.763.63

3.37 3.353.23 3.19

2.8

3

3.2

3.4

3.6

3.8

4

Key Delays

Change order

Changes in Drawings

Incomplete Documents

Changes in Specifications

Decision DuringDevelopment Stage Shop Drawings Approval

Design Development

Fig 4.2 Ranking of Design Related Key Delays

Page 26: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

26

Construction Related Delays

3.42.93 2.85 2.69 2.65 2.56

00.5

11.5

22.5

33.5

4

Key Delays

Inspections

Material/Fabrication Delays

Poor SubcontractorPerformance Material Procurement

Lack of Qualified Craftsmen

Construction Mistakes

Fig 4.3 Ranking of Construction Related Key Delays

Management/Administrative Delays

2.91

0

0.5

1

1.5

2

2.5

3

3.5

Key Delays

Contract Modifications

Fig 4.4 Ranking of Management/Administrative Key Delays

Page 27: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

27

Financial/Economical Delays

2.7

0

0.5

1

1.5

2

2.5

3

Key Delays

Delayed payments

Fig 4.5 Ranking of Financial/Economical Key Delays

Acts of God

0

0.2

0.4

0.6

0.8

1

1.2

Key Delays

Fig 4.6 No Key Delays in Acts of God

Page 28: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

28

4.4 Identification of Responsibility and the type of delay: The identification of responsibilities as well as types of delays is shown in tables 4.8 through 4.13. The responsibility was rated among the parties that may be involved on a construction project starting from the Owner, Contractor, Consultant, and Government to Shared (Owner-Contractor, Owner-Consultant, etc). On the other hand, the types of delays, which were already explained in chapter 2 - Literature Review, are classified as:

• Non-excusable: the construction company gets no time or money. • Excusable Non-Compensable: the construction company gets time, but no

money. • Excusable Compensable: the construction company gets both time and money. • Concurrent: the construction company may or may not get either time or money.

The identification was done based on the information gathered (Appendix B) from the questionnaire and selecting the highest percentage in each item.

1. Acts of God

Responsibility Type of Delay

Flood Owner Excusable Compensable Hurricane Owner Excusable Compensable Fire Shared Excusable Compensable Wind Damage Owner Excusable Compensable

Table 4.8 Responsibility & Type of Delay – Acts of God

2. Design-Related

Design Development Consultant Excusable Compensable Change Order Owner Excusable Compensable Decision during development stage Owner Excusable Compensable Changes in Drawings Owner Excusable Compensable Changes in Specifications Owner Excusable Compensable Shop Drawings Approval Consultant Excusable Compensable Incomplete Documents Consultant Excusable Compensable

Table 4.9 Responsibility & Type of Delay – Design Related

3. Financial/Economical

Financial Process Owner Excusable Compensable Financial Difficulties Owner Excusable Compensable Delayed Payments Owner Excusable Compensable Economic Problems Owner Excusable Compensable

Table 4.10 Responsibility & Type of Delay – Financial/Economical

Page 29: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

29

4. Construction Related

Responsibility Type of Delay

Inspections Contractor Non-Excusable Subsurface Soil Conditions Shared Excusable Compensable Material/Fabrication Delays Contractor Non-Excusable Material Procurement Contractor Non-Excusable Lack of Qualified Craftsmen Contractor Non-Excusable Poor Subcontractor Performance Contractor Non-Excusable Defective Work Contractor Non-Excusable Different Site Conditions Shared Excusable Compensable Labor Injuries Contractor Non-Excusable Damage to Structure Contractor Non-Excusable Construction Mistakes Contractor Non-Excusable Poor Supervision Contractor Non-Excusable Equipment Availability Contractor Non-Excusable

Table 4.11 Responsibility & Type of Delay – Construction Related

5. Management and Administrative Labor Dispute and Strike Contractor Excusable Non-Compensable Inadequate Planning Contractor Non-Excusable Inadequate Scheduling Contractor Non-Excusable Contract Modifications Owner Excusable Compensable Underestimation of Productivity Contractor Non-Excusable Staffing Problems Contractor Non-Excusable Lack of coordination On-site Contractor Non-Excusable Scheduling Mismanagement Contractor Non-Excusable Transportation Delays Contractor Excusable Non-Compensable Suspensions Shared Excusable Non-Compensable Inadequate Review Shared Non-Excusable Lack of High-Technology Shared Non-Excusable Poor Managerial Skills Contractor Non-Excusable

Table 4.12 Responsibility & Type of Delay – Management and Administrative

6. Code Related

Building Permits Approval Process Government Excusable Non-Compensable Changes in Laws and Regulations Government Excusable Compensable Safety Rules Contractor Non-Excusable OSHA Regulations Contractor Non-Excusable Florida Building Code Government Excusable Compensable Building Regulations in Coastal Regions Government Excusable Compensable Coastal Construction Control Line Permit Government Excusable Compensable Florida Administrative Code Government Excusable Compensable National Flood Insurance Program Government Excusable Compensable

Table 4.13 Responsibility & Type of Delay – Code Related

Page 30: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

30

Figures 4.1 through 4.6 and Tables 4.8 through 4.13 are briefly explained below: Basic structure of the flow diagram as it relates to delays:

Acts of God: There is no key delay in this category. The most likely to happen is a hurricane with a 44.8% (2.24 from table 4.1) chance of occurrence which is less than 50% to be considered as a key delay. In the event a delay occurs due to Acts of God, the responsibility is borne by the Owner and the type of delay is an excusable compensable.

Design Related: This is one of the most critical categories among the six because all of the causes were identified as key delays, which means that a delay is most likely to happen due to a design related problem. In fact there is a 76.2% chance (3.81 from table 4.2) that a delay occurs due to a change order, which is very high in number. According to the survey, Design-Related Delays are considered as excusable compensable delays.

Acts of God Excusable Compensable

Shared (Owner & Contractor)

Owner

Design-Related

Owner

Consultant

Excusable Compensable

(CAUSE) (RESPONSIBILITY) (TYPE OF DELAY)

One or the other

One or the other

Page 31: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

31

Construction Related: Basically in construction stage, the contractor will always have the responsibility and the construction company will get no time or money if a delay occurs. However, if a delay occurs because of Subsurface Soil Conditions or Different Site Conditions, the responsibility would be shared between the contractor and the owner and the type of delay in this situation would be considered excusable compensable. Delays due to lack of inspections with 68% (3.40 from table 4.3) are the most common in this stage.

Financial/Economical: Delayed payments (2.70) was selected as the only Key Delay. According to the results, it seems that delays rarely occur because of Financial/Economical reasons. The owner of the project will always have the responsibility, which means that the delay will be excusable compensable.

Management/Administrative: Similar to the above category (Financial/Economical), this also has just one key delay; Contract Modifications (2.91). However there are two parties involved (Owner and contractor) that have to carry the responsibility depending on the cause of the delay and the type of delay is also depending on what caused the delay.

Construction Related

Contractor

Shared (Owner & Contractor)

Excusable Compensable

Non-Excusable

Financial and Economical

Owner Excusable Compensable

One or the other

Page 32: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

32

Code Related: This is the category that influences the most in delays, especially on projects built on the coastal areas. Very often (77.7%), the government is responsible for it and in this case they are excusable compensable delays. However, there is a chance of 22.3% that the contractor be responsible for it in which the delays are Non-Compensable.

Management and

Administrative

Contractor

Shared

Owner

Non-Excusable

Excusable Non-

Compensable

Excusable Compensable

Code Related

Government

Contractor

Excusable Compensable

Excusable Non-Compensable

Non-Excusable

One or the

other

One or the other

Page 33: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

33

CHAPER 5

CONCLUSIONS & RECOMMENDATIONS Project delays have been a topic of concern in the construction industry. Delays have become a universal phenomenon and are almost always accompanied by cost and time overruns. Construction project delays have a debilitating effect on parties (owner, contractor, consultant) to a contract in terms of a growth in adversarial relationships, distrust, litigation, arbitration, cash-flow problems, and a general feeling of apprehension towards each other. Delays can be minimized only when their causes are identified. Knowing the cause of any particular delay in a construction project would help avoiding the same. This project was therefore, aimed at identifying the major causes of delays in construction projects in the Florida Construction Industry through a survey, and quantifies the perceptions of different parties relating to causes, responsible party and types of delay. This research project was limited to building projects in the Florida region only. Based on the results of the questionnaire survey and information gathered from the literature review, the following conclusions were drawn. Generally, whether a delay is determined to be excusable or non-excusable, a contractor is not entitled to an extension of time or to an upward adjustment in costs without understanding the full context of the contract. Code-Related Delay is ranked as the most critical category followed by Design-Related Delays, Construction-Related Delays, and so on, as shown below: 1. Code-Related Delays 2. Design-Related Delays 3. Construction-Related Delays 4. Financial/Economical Delays 5. Management/Administrative Delays 6. Acts of God In general, the ten (10) most critical causes (across the six sub-headings given above) of delays are: 1. Building Permits Approval (3.83) 2. Change order (3.81) 3. Changes in Drawings (3.76) 4. Incomplete Documents (3.63) 5. Inspections (3.40) 6. Changes in Specifications (3.37) 7. Decision During Development Stage (3.35) 8. Shop Drawings Approval (3.23)

Page 34: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

34

9. Design Development (3.19) 10.Changes Laws - Regulations (3.04) Based on the overall results, we can conclude that the following is the ranking of responsibilities of the contractual from the most responsible (1) to the least (5): 1. Contractor = 44% 2. Owner = 24% 3. Government = 14% 4. Shared = 12% 5. Consultant = 6% It can be said that the most common type of delay is Excusable Compensable at 48%, followed by Non-Excusable delays with 44% and 8% for Excusable Non-Compensable Delays. In most of the cases, it is found that when the contractor has the responsibility, the type of delay respectively is Non-Excusable; when the responsibility is the owner’s or the consultant’s it is an Excusable Compensable Delay; and when the government is responsible, the delay is considered an Excusable Compensable. The consultants play a very important roll in Design-Related Delays because as they are in charge of the design process in conjunction with the owner of the project. On the other hand, the government plays the most important role in Code-Related Delays. The contractor has the major responsibility for delays in Construction-Related Delays. Delays due to Financial/Economical Causes as well as Management/Administrative Causes share an intermediate position of importance, just presenting one Key Delay – Delayed Payments. These categories do not have the same negative impact on project completion times as other factors considered in this study such as code, design and construction related issues. Based on the findings of this study, the authors would like to recommend that the Buildings Permit Approval Process be streamlined as much as possible and changes in Laws and Regulations be made keeping in mind the negative impact it causes in terms of construction project cost and time. Design related issues such as changes in drawings, incomplete and faulty specifications and change orders have a very damaging effect on project completion times and invariably lead to cost escalations as well. These are issues that can be controlled with proper design process management and timely decision-making. It is a well know fact that decisions made early in the life of a project have the most profound effect on the project’s objectives of delivering a safe, quality project within the time and budget allocated.

Page 35: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

35

REFERENCES 1. D.E. Hancher and I.E. Rowings, Setting highway construction contract duration. Journal of Construction Engineering and Management, ASCE 107 2 (198 1), pp. 169¯179. 2. Battaineh HT. Information system of progress evaluation of public projects in Jordan, MSc thesis, Dept. of Civil Engineering, Jordan Univ. of Science and Technology, Irbid, Jordan, 1999. 3. H.A. Al-Moumani, Construction delay:a quantitative analysis. International Journal of Project Management 18 (2000), pp. 51¯59. 4. D.M. Leishman, Protecting engineer against construction delay claims: NDC. Journal of Management in Engineering 7 3 (1991), pp. 319¯333. 5. Z.J. Herbsman, W.T. Chen and WC. Epstein, Time is money:innovative contracting methods in highway construction. Journal of Construction Engineering and Management, ASCE 121 3 (1995), pp. 273¯281. 6. J. Yates, Construction decision support system for delay analysis. Journal of Construction Engineering and Management, ASCE 119 2 (1993), pp. 226¯244. 7. S.O. Ogunlana and K. Promkuntong, Construction delays in a fast-growing economy: comparing Thailand with other economies. International Journal of Project Management 14 1 (1996), pp. 37¯45. 8. ChanWM. Kumaraswamy MM, Contributors to construction delays. Construction Management and Economics 16 (1998), pp. 17¯29. 9. N.R. Mansfield, O.O. Ugwu and T. Doran, Causes of delay and cost overruns in Nigerian construction projects. International Journal of Project Management 12 4 (1994), pp. 254¯260. 10. S.A. Assaf, M. Al-Khalil and M. Al-Hazmi, Causes of delay in large building construction projects. Journal of Management in Engineering. ASCE 11 2 (1995), pp. 45¯50. 11. TM Mezher and W. Tawil, Causes of delays in the construction industry in Lebanon. Engineering Construction and Architectural Management Journal 5 3 (1998), pp. 251¯260. 12. S. Dowdy and S. Wearden, Statistics for research. (2nd Ed. ed.),, John Wiley & Sons, New York (1985). 13. Chalabi FA, Camp D., “Causes of delay and overruns of construction projects in developing countries”.

Page 36: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

36

14. Fereig S, Qaddumi N. “Construction problems: The Arabian Gulf experience”, CIB Proc, W-65 1984 15. Wilson RL. “Prevention and resolution of construction claims”, Journal of Construction Division 1982 16. Jonathan Jingsheng Shi, “Construction Delay Computation Method”, Journal of Construction Engineering and Management -- January/February 2001 -- Volume 127, Issue 1, pp. 60-65 17. Sabah Alkass, Mark Mazerolle, Frank Harris, “Construction delay analysis techniques”, Construction Management & Economics-- Volume 14, Number 5/September 1, 1996 18. Bromilow, F. J. (1969). “Contract time performance: expectations and the reality.” Building Forum, September, 70-80. 19. Bromilow, F. J., Hinds, M. F. & Moody, N. F. (1988). “The time and cost performance of building contracts 1976-1988: a summary of a report on research carried out by AIQS and CSIRO.” The Building Economist, September, 4-5. 20. Ireland, V. (1985). “The role of Managerial actions in cost, time and quality performance of high-rise commercial building projects.” Construction Management and Economics, Vol. 3, 59-87. 21. Ireland, V. (1987). “A comparison of US, UK and Australian management practices with special reference to lost time.” The Building Economist, December, 4-17.

Page 37: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

37

APPENDIX

Page 38: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

38

STRICTLY CONFIDENTIAL

Construction Delays in Florida: An Empirical Study

DEPARTMENT OF CONSTRUCTION MANAGEMENT

Questionnaire

Page 39: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

39

Introduction

Delays on construction projects are a universal phenomenon. They are almost always accompanied by cost and time overruns. Construction project delays have a debilitating effect on all parties (owner, contractor, consultant) to a contract in terms of a growth in adversarial relationships, distrust, litigation, arbitration, cash-flow problems, and a general feeling of apprehension towards each other.

Objectives

The objectives of this study would be to identify the major causes of delays in construction projects in the Florida Construction Industry through a survey; and find the perception of the different parties towards the problem, what their responsibilities are and how they carry them out. It is expected that this study will provide some good empirical data on the extent and type of delays in construction projects in Florida. The reasons for these delays will also be documented with an overall aim to provide guidelines for future owners, builders, designers, and managers of construction projects on the dos and don’ts for devising effective systems to deliver projects on time, within budget, and to quality standards, which fully satisfy the clients as well as the intended end-users.

Instructions Please take a look at the following questionnaire and try to answer correctly and accurately, as many questions as possible. All the information gathered here will be kept strictly confidential and will be used only for research and analysis without mentioning the person or company names. Thank you very much for your cooperation. Please mail the answered questionnaire as soon as you can, as timely reply is very crucial for our analysis. Upon completion of the study, the final report will be sent to each survey participant. For more details, please contact: Dr. Syed M. Ahmed Assistant Professor, Department of Construction Management, Florida International University 10555 West Flagler Street, EAS #2952, Miami, Florida 33174 Tel: (305)-348-2730 Fax: (305)-348-6255 E-mail: [email protected] THANK YOU VERY MUCH FOR YOUR KIND COOPERATION AND TIME

Page 40: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

40

Question 1: Which of the following are most important delays associated with your

ongoing project(s)? Please rate the Chance of Occurrence, Responsibility and Type of Delay by circling a suitable figure as indicated below:

Scale of Chance of Occurrence: 1-Unlikely, 2-As likely as not, 3-Likely, 4-Almost

certain, 5-Certain Scale of Responsibilities: Own= Owner, Cont= Contractor, Cons= Consultant, Gov=

Government Scale of Type of Delay: A=Non-Excusable, B=Excusable-Non-Compensable, C= Excusable-Compensable, D= Concurrent * Please also provide other delay (s) (if you think it is important in Florida) and give reason why? and rate in column C.

A B C D Delays Causes Responsibility Chance

of Occurren

ce

Type of Delay

Acts of God Flood

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Hurricane

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Fire

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Wind Damage

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Design Related

Page 41: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

41

Design Development

Own Cont Cons Gov Shared

1 2 3 4 5

A B C D

Change Order

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Decision during development stage

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Changes in Drawings

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Changes in Specifications

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Shop Drawings Approval

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Incomplete Documents

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Construction Related Inspections

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Subsurface Soil Conditions

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Material/Fabrication Delays

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Material Procurement

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Lack of Qualified Craftsmen

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Poor Subcontractor Performance

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Defective Work

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Different Site Conditions

Own Cont Cons Gov

1 2 3 4

A B C D

Page 42: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

42

Shared 5

Labor Injuries

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Damage to Structure

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Construction Mistakes

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Poor Supervision

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Equipment Availability

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Financial/Economical Financial Process

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Financial Difficulties

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Delayed Payments

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Economic Problems

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Management-Administrative Labor Dispute and Strike

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Inadequate Planning

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Inadequate Scheduling

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Contract Modifications

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Underestimation of Productivity

Page 43: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

43

Own Cont Cons Gov Shared

1 2 3 4 5

A B C D

Staffing Problems

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Lack of coordination on-site

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Scheduling Mismanagement

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Transportation Delays

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Suspensions

Own Cont Cons Gov Shared

1 2 3 4 5

A B C D

Inadequate Review

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Lack of High-Technology

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Poor Managerial Skills

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Code Related Building Permits Approval Process

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Changes in Laws and Regulations

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Safety Rules

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

OSHA Regulations

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Florida Building Code

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Building Regulations in Coastal Regions

Own Cont Cons Gov

1 2 3 4

A B C D

Page 44: Construction Delays in Florida: An Empirical Study · PDF file1 Construction Delays in Florida: An Empirical Study Final Report Submitted to: Mr. Michael Ashworth Planning Consultant

44

Shared 5 Coastal Construction Control Line Permit

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Florida Administrative Code

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

National Flood Insurance Program

Own Cont Cons Gov Shared

1 2 3 4

5

A B C D

Question 2: Select the project your company has had the worst problem because of a delays cause and answer the following questions. Building Type: __________________________________________ Project Location: __________________________________________ Contract Price and Time Scheduled: _________________________________________ Type of Contract: _________________________________________ Total Floor Area and Number of Floors: _____________________________________ Structural System: _____________________________________ Delay’s Cause: _____________________________________ Delay’s Duration: _____________________________________ Observations (How you handled it) _____________________________________


Recommended