Prosper is a place where everyone matters.
September 2019
Town of Prosper
Engineering
Capital Projects
Development
Stormwater
Physical Address:
250 W First Street
2nd Floor
Prosper, Texas 75078
Mailing Address:
P.O. Box 307
Prosper, Texas 75078
Phone: 972.569-1198
www.prospertx.gov
Statistics at a Glance Engineering Plans Reviewed
15
Water Well Permits Reviewed
0
Plans Approved 1
Engineering Services
Monthly Report
The new Gee Road connection to Fishtrap Road opened to the public on September 20, 2019. Now that the road is open, a traffic signal warrant study at the intersection is underway.
2
September 2019 Pre-Construction Meetings
September 2019 Final Acceptance Approved
DEVELOPMENT
Case Number Project Title
1 D19-0075 Prestonwood, Phase 3 & 3A
Case Number Project Title
1 D18-0127 306 E Broadway
2 D16-0096 Falls of Prosper, Phase 2
3 D17-0084 Gates of Prosper Block E
4 D16-0038 Legacy Garden, Phase 1
3
Case Number Project Title Location
1 D18-0025 Westfork Infrastructure NWC Gee Road and US 380
2 D18-0075 Prosper Commons Infrastructure NWC Coit Road and US 380
3 D18-0048 Chrysler, Dodge, Jeep & Ram 2550 West University Drive
4 D18-0076 La Cima Crossing Infrastructure West of La Cima Boulevard, North of US 380
5 D18-0132 Prosper ISD Middle School #4 3080 Fishtrap Road
6 D18-0100 Prosper Gardens Office SWC of Prosper Trail & Coit Road
7 D18-0114 Brakes Plus 5010 West University Drive
8 D17-0076 Brazos Substation 2600 FM 1385
9 D17-0088 Westfork Crossing, Block A, Lot 2 NWQ Gee Road & US 380
10 INF18-0007 Gates of Prosper, Phase 2 Infrastructure SWQ Lovers Lane & Preston Road
11 D17-0080 Victory at Frontier SWQ Frontier Parkway & Preston Road
12 INF18-0004 SWC DNT and First Grading SEQ First Street & North Dallas Parkway
13 LD18-0026 Prosper North 12 Grading NEC St. Peter and Preston Road
14 D18-0095 Ace Montessori 4770 West University Drive
15 D17-0041 Rock Creek Church 2860 Fishtrap Road
16 D18-0081 Cook Children’s Medical Center 4200 & 4300 West University Drive
Development Continued
Under Construction—Non-Residential Projects
4
Under Construction—Non-Residential Projects - Continued
Development Continued
Case Number Project Title Location
17 D18-0067 Goddard School 1180 La Cima Boulevard
18 D18-0105 Kindercare 1230 South Coit Road
19 D18-0064 7-Eleven SWQ First Street and Preston Road
20 D17-0053 Pinnacle Montessori SEQ Coit Road and Richland Boulevard
21 D18-0042 World Wide Rock SEQ Cook Lane and Prosper Trail
22 D18-0098 Whispering Gables NWC Coit Road and Richland Boulevard
23 D19-0029 Prosper Commons-Panda Express North side of US 380 W of Coit Road
24 D19-0032 Westfork –Valvoline North side of US 380 W of Gee Road
25 D19-0048 Gates of Prosper, Phase 2 SWC Lovers Lane and Preston Road
26 D19-0075 Prestonwood, Phase 3 1001 West Prosper Trail
5
Development Continued
3. Chrysler, Dodge, Jeep & Ram
2550 West University Drive
Pre-Construction Held:
March 29, 2019
2. Prosper Commons
Infrastructure
NWQ US 380 & Coit Road
Pre-Construction Held:
October 4, 2018
1. Westfork Infrastructure
NWQ US 380 & Gee Road
Pre-Construction Held:
October 10, 2018
6
Development Continued
5. Prosper ISD Middle School #4
3080 Fishtrap Road
Pre-Construction Held:
February 21, 2019
4. La Cima Crossing
Infrastructure
NWQ US 380 & Richland Boulevard
Pre-Construction Held:
December 12, 2018
6. Prosper Gardens Office
SWC Prosper Trail & Coit Road
Pre-Construction Held:
February 18, 2019
7
Development Continued
8. Brazos Substation
2600 FM 1385
Pre-Construction Held:
September 13, 2018
7. Brakes Plus
5010 West University Drive
Pre-Construction Held:
March 15, 2019
9. Westfork Crossing,
Block A, Lot 2
NWQ Gee Road & US 380
Pre-Construction Held:
January 16, 2019
8
Development Continued
11. Victory at Frontier
SWQ Frontier Parkway & Preston Road
Pre-Construction Held:
January 11, 2019
10. Gates of Prosper, Phase 2
Infrastructure
SWQ Preston Road & Lovers Lane
Pre-Construction Held:
November 26, 2018 - Utilities
March 25, 2019 - Roads
12. SWC DNT & First Street
Grading
SWC DNT & First Street
Pre-Construction Held:
November 27, 2018
9
Development Continued
14. Ace Montessori
4770 West University Drive
Pre-Construction Held:
December 19, 2018
13. Prosper North 12
Grading
NEC of Street Peter & Preston Road
Pre-Construction Held:
September 26, 2018
15. Rock Creek Church
2860 Fishtrap Road
Pre-Construction Held:
July 9, 2018
10
Development Continued
16. Cook Children’s Medical Center
4200 & 4300 West University Drive
Pre-Construction Held:
February 7, 2019
17. Goddard School
1180 La Cima Boulevard
Pre-Construction Held:
December 4, 2018
18. Kindercare
1230 South Coit Road
Pre-Construction Held:
December 3, 2018
11
Development Continued
21. World Wide Rock
1020 and 1030 Cook Lane
Pre-Construction Held:
April 10, 2019
19. 7-Eleven
390 North Preston Road
Pre-Construction Held:
February 25, 2019
20. Pinnacle Montessori
2770 Richland Boulevard
Pre-Construction Held:
May 1, 2019
12
Development Continued
22. Whispering Gables
SWC Coit Road and Richland Boulevard
Pre-Construction Held:
May 15, 2018
24. Westfork-Valvoline
2251 East University Drive
Pre-Construction Held:
July 11, 2019
23. Prosper Commons-Panda
Express
2251 East University Drive
Pre-Construction Held:
July 25, 2019
13
Development Continued
25. Gates of Prosper, Phase 2
SWC Lovers Lane and Preston Road
Pre-Construction Held:
June 6, 2019
26. Prestonwood, Phase 3
1001 West Prosper Trail
Pre-Construction Held:
September 13, 2019
14
Case Number Project Title Location
1 D18-0073 Legacy Garden, Phase 1C NWQ Prosper Trail & Shawnee Trail
2 D18-0036 Star Trail, Phase 5 SWQ Prosper Trail & Shawnee Trail
3 D17-0083 Lakewood, Phase 1A NWQ Coit Road & Meadowbrook Boulevard
4 D18-0130 Lakewood, Phase 2 NWQ Lakewood Drive & Meadow Dell
5 D19-0022 Lakewood, Phase 3
Grading only NWQ Lakewood Drive & Meadow Dell
6 D18-0107 Windsong Ranch, Phase 5A NWQ Fishtrap Road & Teel Parkway
7 D18-0125 Windsong Ranch, Phase 5B NWQ Fishtrap Road & Teel Parkway
8 D18-0137 Tanners Mill, Phase 1D South and East of Coleman Road
9 D18-0077 Parks at Legacy, Phase 3
*Grading only NWQ Prairie Drive/Legacy Drive
10 D18-0078 Parks at Legacy, Phase 4
*Grading only NWQ Prairie Drive/Legacy Drive
Under Construction—Residential Projects
Development—Continued
15
CAPITAL PROJECTS
Current Construction Activity—Total of $49,627,033
Project Project Title Start Date Finish Date Project Cost Est. Project Agency
S01 1507-ST - West Prosper Road Improvements,
Phase 2 (Segment D) Summer 2018 Fall 2019
$4,500,000
(Town Participation $1.85 Million) Town of Prosper
S04 1511-ST - Prosper Trail (Kroger - Coit Road) Winter 2017-
2018
Winter 2019-2020
(estimated) $4,742,760 Town of Prosper
S05 1513-ST - Old Town Streets 2015 Summer 2018 Summer 2019 $1,800,000 Town of Prosper
S06 1412-ST - Broadway (McKinley - Coleman) Summer 2018 Summer 2019 $2,500,000 Town of Prosper
S10 1836-ST - DNT Southbound Service Road
(US 380 - FM 428) Summer 2018
Winter 2019-2020
(estimated) $ 17,000.000 (County Funded) Collin County
T18 1909-TR - Traffic Signal (First and Coit) Fall 2019 Summer 2020
(estimated) $288,444 Town of Prosper
S20 1708-ST - E-W Collector (Cook Lane - DNT) Spring 2019 Fall 2019 $1,504,091 Town of Prosper
S24 1820-ST - First Street and DNT Intersection Spring 2019 Winter 2019-2020
(estimated) $1,387,000 Town of Prosper
S30 1819-ST Coleman Street (at Prosper High School)
Summer 2019 Spring 2020
(estimated) $650,000 Town of Prosper
W02 1715-WA - Fishtrap Elevated Storage Tank Winter 2018-
2019
Summer 2020
(estimated) $5,979,677 Town of Prosper
W04 1716-WA - LPP Water Line, Phase 1B
(FEST to BNSF and Lovers to Coit) Summer 2019
Summer 2020
(estimated) $9,275,061 Town of Prosper
16
Capital Projects -Continued
S04. Prosper Trail
(Kroger to Coit Road)
Start Date : Winter 2017-2018
Finish Date: Winter 2019-2020 (estimate)
Project Cost: $4,742,760
S01. West Prosper Road
Improvements, Phase 2 (Segment D)
Start Date : Summer 2018
Finish Date: Fall 2019
Project Cost: $4, 500,000
S05. Old Town Streets 2015
Start Date : Summer 2018
Finish Date: Summer 2019
Project Cost: $1,800,000
*Contractor in Final Cleanup of Site
17
Capital Projects -Continued
S06. Broadway Street
(McKinley Street to Coleman Street)
Start Date : Summer 2018
Finish Date: Summer 2019
Project Cost: $2,500,000
*Broadway complete, North Main began in
July 2019.
S10. DNT Southbound Service Road
(US 380 to FM 428)
Start Date : Summer 2018
Finish Date: Winter 2019-2020 (estimate)
Project Cost: $17,000,000
Collin County Funded
T18. Traffic Signal (First and Coit)
Start Date : Fall 2019
Finish Date: Summer 2020 (estimate)
Project Cost: $288,444
18
Capital Projects -Continued
S24. First Street & DNT Intersection
Start Date : Spring 2019
Finish Date: Winter 2019-2020 (estimate)
Project Cost: $1,387,000
S20. E-W Collector
(Cook Lane –DNT)
Start Date : Spring 2019
Finish Date: Fall 2019 (estimate)
Project Cost: $1,504,091
S30. Coleman Street at Prosper High
School
Start Date : Summer 2019
Finish Date: Spring 2020 (estimated)
Project Cost: $650,000
19
Capital Projects -Continued
W02. Fishtrap Elevated Storage Tank
Start Date : Winter 2018-2019
Finish Date: Summer 2020 (estimate)
Project Cost: $5,979,677
*Foundation crews have completed the
installation if foundation piers.
W04. LPP Water Line, Phase 1B.
Start Date : Summer 2019
Finish Date: Summer 2020 (estimate)
Project Cost: $9,275,061
20
Have been submitted to the Town
Notice of Intent (NOI) — 1
Notice of Termination (NOT) — 2
Notice of Change (NOC) — 1
Stormwater Inspections — 58
STORMWATER
The Stormwater program conducts many types of compliance inspections. In any given
month, Stormwater staff will see compliant sites, non-compliant sites and sites that are
just plain awful. September was a pretty good month as far as the number of compliant
job sites. This is primarily due to the lack of precipitation which makes it easier for job
sites to keep sediment on site and out of our local water ways. Below you will find
comparison graphs that show the number of inspections performed or documents
received and the total amount that have been performed or received so far, this year. The
goal is to paint you a picture of a few of our many accomplishments this month.
58
461
SEPTEMBER YTD
Active Site Inspections
21
1
8
SEPTEMBER YTD
Notice of intent (NOI)All construction sites that disturb >5 acres of land, require a NOI
issued by the Texas Commission on Environmental Quality (TCEQ).
Stormwater—Continued
22
Stormwater—Continued
23
At the Community Picnic, Stormwater staff hosted the Prosper Stormwater management
program booth, which helps to satisfy state required education and outreach
requirements for the MS4 permit. The education and outreach booth is starting to come
together; staff was able to reach out to approximately 100 residents, demonstrating the
watershed model, and handing out Stormwater management program SWAG. Staff is
looking forward to the Christmas Festival, where we will be able to reach out to more
residents.
Education is a key component to achieving water quality and construction site
compliance. The Stormwater management program is dedicated to educating Town
residents and site workers to ensure that everybody is doing their best to protect water
quality and stay in compliance with Town Stormwater ordinance, TCEQ permit
requirements, and Federal regulations.
Community Picnic!!