Transcript
Page 1: Environment Construction Method Statement 01 General

Hunter Expressway Alliance

ECMS – General Construction

Attachment B

Overview of Environmental Construction MethodStatements

Page 2: Environment Construction Method Statement 01 General

GENHEA GIS

HUNTER EXPRESSWAY ALLIANCEStatus

Original Size

Coordinate System

Height Datum

Drawn

Designed

Date Printed

A3MGA ZONE 56

AHD

NOT USED FOR CONSTRUCTION

Company Zone Type Figure No. Issue

DescriptionIssue Date Approved

0

1000

200030

00

4000

5000

6000

7000

8000

9000

10000

11000

12000

0001

0010

0005

0006

0007

0008

0009

0003

0002

0004

5

10

6

12

7

3

6

8

8

8

11

8

4

9

8

8

88

8 F3 FRE

EWAY

JOHN RENS

HAW DRIVE

GEORGE BOOTH DRIVE

BLACKHILL ROAD

LENAGH

ANS DR

IVE

WOOD

FORD

STR

EET

BUCHANAN ROAD

MINMI RO

AD

NEWCASTLE LINK ROADC A MER

ON PARK DRIVE

BLACK HILL ROAD

LANG S

TREET

MAITL

AND

ROAD

F3 FREEWAY

9

Scales BERESFIELD

Viaducts

Rest areaBuchanan interchange

Newcastle interchange

Kurri Kurri interchange

Skyline Ridge cut

JOHN RENSHA W DRIVE

GEORGE BOOTH DRIVE

BLA CKHILL ROAD

MINMI ROAD

LEGGE

TTS

DRIVE

SYDN

EY NE

WCAS

TLE F

REEW

AYBUCH

ANAN

RO

AD

NEWCASTLE

LINK ROAD

KURRI KURRI

NEWCASTLE1:40000

0 1,000 m

Map sheetConstruction Method Statement zoneRoad design (DES HEA 007)Construction compound

RoadsMotorwayPrimary roadArterial roadSub-arterial road

EN133 A

ENVIRONMENTAL CONSTRUCTIONMETHOD STATEMENT

A FOR INFORMATION 13 JUL 10

PRELIMINARY

AZDB

Draft date: Thursday, July 15, 2010 9:56:31 AMFile name: \\10.10.25.35\Data\HEA\L-GIS\A_Current\B_Maps\HEA-GEN-GIS-EN133-Construction method statement-General-A.mxd 0000

50 mm on Original

15 JUL 10OVERVIEW

GENERAL ENVIRONMENTAL CONSTRUCTIONMETHOD STATEMENT COVERAGE

1 - GENERAL CONSTRUCTION2 - CLEARING AND TOPSOIL MANAGEMENT13 - SITE STABILISATION AND REHABILITATION WORKS

SITE SPECIFIC CONSTRUCTION METHODSTATEMENTS

3 - CONSTRUCTION SITE COMPOUNDS4 - CONCRETE PRODUCTION AND DELIVERY (BATCH PLANT)5 - ACCESS TRACKS FOR MINE VOID TREATMENT AND VIADUCTS6 - TREATMENT OF MINE VOIDS7 - NEWCASTLE INTERCHANGE AT THE F38 - TEMPORARY WATERWAY CROSSINGS9 - BRIDGE STRUCTURES OVER WALLIS CREEK, MINMI CREEK AND SURVEYORS CREEK10 - BUCHANAN INTERCHANGE11 - VIADUCTS IN THE SUGARLOAF RANGES12 - KURRI SANDS SWAMP WOODLAND

Page 3: Environment Construction Method Statement 01 General

Hunter Expressway Alliance

ECMS – General Construction

Attachment C

Environmental Constraint Maps

Page 4: Environment Construction Method Statement 01 General

GENHEA GIS

HUNTER EXPRESSWAY ALLIANCEStatus

Original Size

Coordinate System

Height Datum

Drawn

Designed

Date Printed

A3MGA ZONE 56

AHD

NOT USED FOR CONSTRUCTION

Company Zone Type Figure No. Issue

DescriptionIssue Date Approved

-800

-700

-600

-500

-400

-300

-200

-100

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500

1600

1700

1800

1900200

0210022

00

230024

00250026

00270028

00290030

003100

3200

3300

3400

3500

3600

3700

3800

3900

4000

4100

4200

4300

4400

4500

4600

4700

4800

4900

5000

5100

5200

5300

5400

5500

5600

5700

5800

5900

6000

6100

6200

6300

6400

6500

6600

6700

6800

6900

7000

7100

7200

7300

7400

7500

7600

7700

7800

7900

8000

8100

8200

8300

8400

8500

8600

8700

8800

8900

9000

9100

9200

9300

9400

9500

9600

9700

9800

9900

10000

10100

10200

10300104

0010500106

0010700108

0010900110

0011100112

0011300114

0011500116

00

11700

11800

11900

12000

12100

12200

12300

12400

12500

12600

12700

12800

12900

NOTE: AHM ZONE 4 - MINMI CREEK EXCLUSION ZONE APPLIES. NO SECTION 90 CONSENT OVER MINMI CREEK. REFER TO IHMSP.

NOTE: SEAHAMPTON 1 AND 2, MINMI CREEK STONE ARRANGEMENTS 1, 2, AND 3 AREA FOR CONSERVATION.

BW004

BW01BW02

BW03

BW06

BW024

BW07

BW07

BW05

SEE CMS 5: ACCESS TRACKS FOR MINE VOID TREATMENT AND VIADUCTSFOR FURTHER INFORMATION

SEE CMS 7: NEWCASTLE INTERCHANGE AT THE F3FOR FURTHER INFORMATION

SEE CMS 6: TREATMENT OF MINE VOIDSFOR FURTHER INFORMATION

SEE CMS 9: BRIDGE STRUCTURES OVER CREEKSFOR FURTHER INFORMATION

SEE CMS 8: TEMPORARY WATERWAY CROSSINGSFOR FURTHER INFORMATION

Isolated Find 5European Brick Weir

Minmi Creek Stone Wall

European Stone and Brick Weir

Sugarloaf 1 Artefact Scatter & PAD

Aboriginal pathway(impact to be minimised)

38-4-0394 Seahampton 1 Grinding Groove Site

38-4-0393 Seahampton 2 Grinding Groove Site

38-4-0392 Seahampton 3 Grinding Groove Site

Minmi Creek Stone Arrangements 1

Minmi Creek Stone Arrangements 2 & 3

Fan Shaft (Mining shaft)Sandstone slab with slots

AHM zone 1

AHM zone 5

AHM zone 2

AHM zone 4

AHM zone 3

F3 FRE

EWAY

NEWCASTLE LINK ROAD

WOODF

ORD ST

REET

CAMERO

N PARK

DRIVE

F3 FRE

EWAY

1 Seahampton

MC-D

MC-U

MINMI C

REEK

Scales BERESFIELD

Viaducts

Rest areaBuchanan interchange

Newcastle interchange

Kurri Kurri interchange

Skyline Ridge cut

JOHN RENSHA W DRIVE

GEORGE BOOTH DRIVE

BLA CKHILL ROAD

MINMI ROAD

LEGGE

TTS

DRIVE

SYDN

EY NE

WCAS

TLE F

REEW

AYBUCH

ANAN

RO

AD

NEWCASTLE

LINK ROAD

KURRI KURRI

NEWCASTLE1:5000

0 200 m

DesignConstruction boundaryRoad design (DES HEA 007)Bridge footprintConstruction compoundFauna fence

Construction accessExisting trackExisting road utilised as isExisting track upgraded without wideningExisting road widened to 8 m for accessNew minor access roadNew 8 m wide access roadNew grouting access track

RoadsMotorwayPrimary roadArterial roadSub-arterial road

Threatened species (Biosis, 2009)Threatened flora locationThreatened fauna location

HeritageEuropean heritage locationIndigenous heritage location

Monitoring locationsAir monitoring locationWater monitoring locationNoise monitoring locationNoise and vibration sensitive receiverVibration sensitive receiver

Acid sulfate soil risk categoriesHigh probability of occurrenceLow probability of occurrenceDisturbed TerrainNo known occurrence

Vegetation (combined CK2009)Vegetation community (EEC)Vegetation community (non-EEC)

EN133 A

ENVIRONMENTAL CONSTRUCTIONMETHOD STATEMENT

A FOR INFORMATION 13 JUL 10

PRELIMINARY

AZDB

Draft date: Thursday, July 15, 2010 9:56:31 AMFile name: \\10.10.25.35\Data\HEA\L-GIS\A_Current\B_Maps\HEA-GEN-GIS-EN133-Construction method statement-General-A.mxd 0001

50 mm on Original

15 JUL 10ENVIRONMENTAL CONSTRAINTS MAP

Aboriginal Heritage Management (AHM) Zones

Conservation/partial conservation

High level of aboriginal cultural heritage and archaeological sensitivity.

Area of site outside road corridor to be protected

Variable levels of aboriginal cultural heritage and archaeological sensitivity.

Significant sites in close proximity to road corridor

Variable levels of aboriginal cultural heritage and archaeological sensitivity.

Impact minimisation

Moderate aboriginal cultural heritage and archaeological sensitivity.

Cleared under s.90 consent

Low aboriginal cultural heritage and archaeological sensitivity.

See the IHMSP for details of management requirements foreach zone.

AREA 1 - NEWCASTLE INTERCHANGE

Page 5: Environment Construction Method Statement 01 General

GENHEA GIS

HUNTER EXPRESSWAY ALLIANCEStatus

Original Size

Coordinate System

Height Datum

Drawn

Designed

Date Printed

A3MGA ZONE 56

AHD

NOT USED FOR CONSTRUCTION

Company Zone Type Figure No. Issue

DescriptionIssue Date Approved

-800

-700

-600

-500

-400

-300

-200

-100

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500

1600

1700

1800

1900200

0210022

00

230024

00250026

00270028

00290030

003100

3200

3300

3400

3500

3600

3700

3800

3900

4000

4100

4200

4300

4400

4500

4600

4700

4800

4900

5000

5100

5200

5300

5400

5500

5600

5700

5800

5900

6000

6100

6200

6300

6400

6500

6600

6700

6800

6900

7000

7100

7200

7300

7400

7500

7600

7700

7800

7900

8000

8100

8200

8300

8400

8500

8600

8700

8800

8900

9000

9100

9200

9300

9400

9500

9600

9700

9800

9900

10000

10100

10200

10300104

0010500106

0010700108

0010900110

0011100112

0011300114

0011500116

00

11700

11800

11900

12000

12100

12200

12300

12400

12500

12600

12700

12800

12900

SEE CMS 8: TEMPORARY WATERWAY CROSSINGSFOR FURTHER INFORMATION

SEE CMS 11: VIADUCTS IN THE SUGARLOAF RANGESFOR FURTHER INFORMATION

NOTE: SEAHAMPTON 1 AND 2, MINMI CREEK STONE ARRANGEMENTS 1, 2, AND 3 AREA FOR CONSERVATION.

Stockrin

gton Roa

d

BLUE G

UM CRE

EK

GROUTING ACCESSTRACKS

BW09BW09

BW10BW10

BW11BW11

BW024

BW08

SEE CMS 6: TREATMENT OF MINE VOIDSFOR FURTHER INFORMATION

SEE CMS 5: ACCESS TRACKS FOR MINE VOID TREATMENT AND VIADUCTSFOR FURTHER INFORMATION

SEE CMS 11: VIADUCTS IN THE SUGARLOAF RANGESFOR FURTHER INFORMATION

SEE CMS 8: TEMPORARY WATERWAY CROSSINGSFOR FURTHER INFORMATION

SEE CMS 9: BRIDGE STRUCTURES OVER CREEKSFOR FURTHER INFORMATION

Isolated Find 5

Blue Gum Creek 1Blue Gum Creek 2

Blue Gum Creek 4 & PAD

Sugarloaf 1 Artefact Scatter & PAD

PAD 10 Rock shelter on Burnt Creek

Aboriginal pathway(impact to be minimised)

Area of High Cultural Heritage Value

38-4-0392 Seahampton 3 Grinding Groove Site

Burrenjim Dam

Jewboy Bushrangers Cave

End of southwest cutting and Rail Tunnel 134

Sandstone slab with slots

AHM zone 7

AHM zone 5

AHM zone 6

AHM zone 8

BLUE GUM

CREEK

Scales BERESFIELD

Viaducts

Rest areaBuchanan interchange

Newcastle interchange

Kurri Kurri interchange

Skyline Ridge cut

JOHN RENSHA W DRIVE

GEORGE BOOTH DRIVE

BLA CKHILL ROAD

MINMI ROAD

LEGGE

TTS

DRIVE

SYDN

EY NE

WCAS

TLE F

REEW

AYBUCH

ANAN

RO

AD

NEWCASTLE

LINK ROAD

KURRI KURRI

NEWCASTLE1:5000

0 200 m

DesignConstruction boundaryRoad design (DES HEA 007)Bridge footprintConstruction compoundFauna fence

Construction accessExisting trackExisting road utilised as isExisting track upgraded without wideningExisting road widened to 8 m for accessNew minor access roadNew 8 m wide access roadNew grouting access track

RoadsMotorwayPrimary roadArterial roadSub-arterial road

Threatened species (Biosis, 2009)Threatened flora locationThreatened fauna location

HeritageEuropean heritage locationIndigenous heritage location

Monitoring locationsAir monitoring locationWater monitoring locationNoise monitoring locationNoise and vibration sensitive receiverVibration sensitive receiver

Acid sulfate soil risk categoriesHigh probability of occurrenceLow probability of occurrenceDisturbed TerrainNo known occurrence

Vegetation (combined CK2009)Vegetation community (EEC)Vegetation community (non-EEC)

EN133 A

ENVIRONMENTAL CONSTRUCTIONMETHOD STATEMENT

A FOR INFORMATION 13 JUL 10

PRELIMINARY

AZDB

Draft date: Thursday, July 15, 2010 9:56:31 AMFile name: \\10.10.25.35\Data\HEA\L-GIS\A_Current\B_Maps\HEA-GEN-GIS-EN133-Construction method statement-General-A.mxd 0002

50 mm on Original

15 JUL 10ENVIRONMENTAL CONSTRAINTS MAP

Aboriginal Heritage Management (AHM) Zones

Conservation/partial conservation

High level of aboriginal cultural heritage and archaeological sensitivity.

Area of site outside road corridor to be protected

Variable levels of aboriginal cultural heritage and archaeological sensitivity.

Significant sites in close proximity to road corridor

Variable levels of aboriginal cultural heritage and archaeological sensitivity.

Impact minimisation

Moderate aboriginal cultural heritage and archaeological sensitivity.

Cleared under s.90 consent

Low aboriginal cultural heritage and archaeological sensitivity.

See the IHMSP for details of management requirements foreach zone.

AREA 1 AND AREA 2

Page 6: Environment Construction Method Statement 01 General

GENHEA GIS

HUNTER EXPRESSWAY ALLIANCEStatus

Original Size

Coordinate System

Height Datum

Drawn

Designed

Date Printed

A3MGA ZONE 56

AHD

NOT USED FOR CONSTRUCTION

Company Zone Type Figure No. Issue

DescriptionIssue Date Approved

-800

-700

-600

-500

-400

-300

-200

-100

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500

1600

1700

1800

1900200

02100220

0230024

00250026

00270028

00290030

003100320

0

3300

3400

3500

3600

3700

3800

3900

4000

4100

4200

4300

4400

4500

4600

4700

4800

4900

5000

5100

5200

5300

5400

5500

5600

5700

5800

5900

6000

6100

6200

6300

6400

6500

6600

6700

6800

6900

7000

7100

7200

7300

7400

7500

7600

7700

7800

7900

8000

8100

8200

8300

8400

8500

8600

8700

8800

8900

9000

9100

9200

9300

9400

9500

9600

9700

9800

9900

10000

10100

10200

10300104

0010500106

0010700108

0010900110

0011100112

0011300114

0011500116

00

11700

11800

11900

12000

12100

12200

12300

12400

12500

12600

12700

12800

12900

SEE CMS 8: TEMPORARY WATERWAY CROSSINGSFOR FURTHER INFORMATION

SEE CMS 11: VIADUCTS IN THE SUGARLOAF RANGESFOR FURTHER INFORMATION

SEE CMS 6: TREATMENT OF MINE VOIDSFOR FURTHER INFORMATION

Daracon Road

BW10BW10

BW11BW11

BW12

SEE CMS 6: TREATMENT OF MINE VOIDSFOR FURTHER INFORMATION

SEE CMS 8: TEMPORARY WATERWAY CROSSINGSFOR FURTHER INFORMATION

PAD 6

Rail Tunnel 139

Blue Gum Creek 1Blue Gum Creek 2

Blue Gum Creek 3

Blue Gum Creek 4 & PAD

PAD 10 Rock shelter on Burnt Creek

Area of High Cultural Heritage Value

Blue Gum Creek 5 Grinding Groove Site

38-4-0236 Blue Gum Creek Grinding Grooves38-4-0235 Blue Gum Creek Grinding Grooves

Burrenjim Dam

Jewboy Bushrangers Cave

End of southwest cutting and Rail Tunnel 134

AHM zone 7

AHM zone 10

AHM zone 9

AHM zone 8

GEORGE BOOTH DRIVE

BGC-D

BGC-UBLUE

GUM CREE

K

BURN

T CRE

EK

SURVEYOR

S CREEK

Scales BERESFIELD

Viaducts

Rest areaBuchanan interchange

Newcastle interchange

Kurri Kurri interchange

Skyline Ridge cut

JOHN RENSHA W DRIVE

GEORGE BOOTH DRIVE

BLA CKHILL ROAD

MINMI ROAD

LEGGE

TTS

DRIVE

SYDN

EY NE

WCAS

TLE F

REEW

AYBUCH

ANAN

RO

AD

NEWCASTLE

LINK ROAD

KURRI KURRI

NEWCASTLE1:5000

0 200 m

DesignConstruction boundaryRoad design (DES HEA 007)Bridge footprintConstruction compoundFauna fence

Construction accessExisting trackExisting road utilised as isExisting track upgraded without wideningExisting road widened to 8 m for accessNew minor access roadNew 8 m wide access roadNew grouting access track

RoadsMotorwayPrimary roadArterial roadSub-arterial road

Threatened species (Biosis, 2009)Threatened flora locationThreatened fauna location

HeritageEuropean heritage locationIndigenous heritage location

Monitoring locationsAir monitoring locationWater monitoring locationNoise monitoring locationNoise and vibration sensitive receiverVibration sensitive receiver

Acid sulfate soil risk categoriesHigh probability of occurrenceLow probability of occurrenceDisturbed TerrainNo known occurrence

Vegetation (combined CK2009)Vegetation community (EEC)Vegetation community (non-EEC)

EN133 A

ENVIRONMENTAL CONSTRUCTIONMETHOD STATEMENT

A FOR INFORMATION 13 JUL 10

PRELIMINARY

AZDB

Draft date: Thursday, July 15, 2010 9:56:31 AMFile name: \\10.10.25.35\Data\HEA\L-GIS\A_Current\B_Maps\HEA-GEN-GIS-EN133-Construction method statement-General-A.mxd 0003

50 mm on Original

15 JUL 10ENVIRONMENTAL CONSTRAINTS MAP

Aboriginal Heritage Management (AHM) Zones

Conservation/partial conservation

High level of aboriginal cultural heritage and archaeological sensitivity.

Area of site outside road corridor to be protected

Variable levels of aboriginal cultural heritage and archaeological sensitivity.

Significant sites in close proximity to road corridor

Variable levels of aboriginal cultural heritage and archaeological sensitivity.

Impact minimisation

Moderate aboriginal cultural heritage and archaeological sensitivity.

Cleared under s.90 consent

Low aboriginal cultural heritage and archaeological sensitivity.

See the IHMSP for details of management requirements foreach zone.

AREA 2

Page 7: Environment Construction Method Statement 01 General

GENHEA GIS

HUNTER EXPRESSWAY ALLIANCEStatus

Original Size

Coordinate System

Height Datum

Drawn

Designed

Date Printed

A3MGA ZONE 56

AHD

NOT USED FOR CONSTRUCTION

Company Zone Type Figure No. Issue

DescriptionIssue Date Approved

-800

-700

-600

-500

-400

-300

-200

-100

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500

1600

1700

1800

1900200

02100220

0230024

00250026

00270028

00290030

003100320

0

3300

3400

3500

3600

3700

3800

3900

4000

4100

4200

4300

4400

4500

4600

4700

4800

4900

5000

5100

5200

5300

5400

5500

5600

5700

5800

5900

6000

6100

6200

6300

6400

6500

6600

6700

6800

6900

7000

7100

7200

7300

7400

7500

7600

7700

7800

7900

8000

8100

8200

8300

8400

8500

8600

8700

8800

8900

9000

9100

9200

9300

9400

9500

9600

9700

9800

9900

10000

10100

10200

10300104

0010500106

0010700108

0010900110

0011100112

0011300114

0011500116

00

11700

11800

11900

12000

12100

12200

12300

12400

12500

12600

12700

12800

12900

Daracon Road

Daracon Road

BW12

BW13BW13

SEE CMS 8: TEMPORARY WATERWAY CROSSINGSFOR FURTHER INFORMATION

SEE CMS 8: TEMPORARY WATERWAY CROSSINGSFOR FURTHER INFORMATION

PAD 6

PAD 5

Rail Tunnel 139

Surveyors Creek RTA 5

Surveyors Creek RTA 4

Surveyors Creek RTA 3 IF

Surveyors Creek RTA 9 IF

GEORGE BOOTH DRIVE

SC2OC-U

SC2OC-D

SC1OC-D

SC1OC-U

SURVEYORS CREEK

SURVEYORS

CREEK

SURVEYORS CREEK

Scales BERESFIELD

Viaducts

Rest areaBuchanan interchange

Newcastle interchange

Kurri Kurri interchange

Skyline Ridge cut

JOHN RENSHA W DRIVE

GEORGE BOOTH DRIVE

BLA CKHILL ROAD

MINMI ROAD

LEGGE

TTS

DRIVE

SYDN

EY NE

WCAS

TLE F

REEW

AYBUCH

ANAN

RO

AD

NEWCASTLE

LINK ROAD

KURRI KURRI

NEWCASTLE1:5000

0 200 m

DesignConstruction boundaryRoad design (DES HEA 007)Bridge footprintConstruction compoundFauna fence

Construction accessExisting trackExisting road utilised as isExisting track upgraded without wideningExisting road widened to 8 m for accessNew minor access roadNew 8 m wide access roadNew grouting access track

RoadsMotorwayPrimary roadArterial roadSub-arterial road

Threatened species (Biosis, 2009)Threatened flora locationThreatened fauna location

HeritageEuropean heritage locationIndigenous heritage location

Monitoring locationsAir monitoring locationWater monitoring locationNoise monitoring locationNoise and vibration sensitive receiverVibration sensitive receiver

Acid sulfate soil risk categoriesHigh probability of occurrenceLow probability of occurrenceDisturbed TerrainNo known occurrence

Vegetation (combined CK2009)Vegetation community (EEC)Vegetation community (non-EEC)

EN133 A

ENVIRONMENTAL CONSTRUCTIONMETHOD STATEMENT

A FOR INFORMATION 13 JUL 10

PRELIMINARY

AZDB

Draft date: Thursday, July 15, 2010 9:56:31 AMFile name: \\10.10.25.35\Data\HEA\L-GIS\A_Current\B_Maps\HEA-GEN-GIS-EN133-Construction method statement-General-A.mxd 0004

50 mm on Original

15 JUL 10ENVIRONMENTAL CONSTRAINTS MAP

Aboriginal Heritage Management (AHM) Zones

Conservation/partial conservation

High level of aboriginal cultural heritage and archaeological sensitivity.

Area of site outside road corridor to be protected

Variable levels of aboriginal cultural heritage and archaeological sensitivity.

Significant sites in close proximity to road corridor

Variable levels of aboriginal cultural heritage and archaeological sensitivity.

Impact minimisation

Moderate aboriginal cultural heritage and archaeological sensitivity.

Cleared under s.90 consent

Low aboriginal cultural heritage and archaeological sensitivity.

See the IHMSP for details of management requirements foreach zone.

AREA 2


Recommended