Harlan High School
Facilities Construction
NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT
Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION
January 2016
2010 BOND SAVINGS
PROJECTS
BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST)
Architect – Noonan Rittimann Project Architect – John Rittimann NISD Project Manager – Chris Parker Contractor – Bartlett Cocke General Contractor Construction Amount - $25,371,707.00 (2010 Bond Savings) Construction Period – April 2015 – June 30, 2016 (53% Complete) Project Scope – New 800 Student Elementary School
Concrete superstructure, MEP rough-in, permanent power installation, masonry, structural steel, decking and drywall framing in progress.
BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST) (Jan. 7, 2015)
BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST)
BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST) (Jan. 11, 2016)
BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST)(Dec. 29, 2015)
BENNIE L. COLE ELEMENTARY SCHOOL (Future Library) (Dec. 29, 2015)
NORTHSIDE SPORTS GYM
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke General Contractor Contract Amount – $26,326,724.00 (2010 Bond Savings) Construction Period – May 2015 – October 2016 (23% Complete) Project Scope – Provide a District-Wide Sports Gymansium at the Farris
Complex. Site work, electrical and plumbing rough-ins in progress. Concrete foundation and columns being placed. Precast concrete seating being installed.
NORTHSIDE SPORTS GYM Aerial View (December 17, 2015)
NORTHSIDE SPORTS GYM – Entry Perspective View
NORTHSIDE SPORTS GYM – Plaza Perspective View
NORTHSIDE SPORTS GYM (January 11, 2016)
NORTHSIDE SPORTS GYM – Seating Perspective View
NORTHSIDE SPORTS GYM (January 11, 2016)
2014 BOND PROJECTS
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL)
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Jim Berg Contractor – Joeris General Contractor GMP - $110,800,000.00 Construction Period – October 2014 – May 2017 (54% Complete) Project Scope – New 2800 Student High School
Notice to Proceed issued October 8, 2014. Site Construction began October 14, 2014. Site grading, 1st,2nd and 3rd Floor framing and columns in progress. Underground utilities and Interior CMU walls, drywall framing, electrical, plumbing, and HVAC rough-in in progress. Roof steel erection, roof deck roofing and window installation in progress. Interior painting in progress. Exterior brick veneer in progress.
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (Dec. 22, 2015)
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (Jan. 11, 2016)
HARLAN HIGH SCHOOL (CONNECTION BETWEEN MAIN BUILDING and GYMS) (Jan. 11, 2016)
RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3)
Architect – O’Neill Conrad Oppelt Project Architect – Mark Oppelt NISD Project Manager – Marilyn Sevedge Contractor – Joeris General Contractor Contract Amount - $24,615,127.00 Construction Period – April 2015 – June 30, 2016 (49% Complete) Project Scope – New 800 Student Elementary School
Steel superstructure and masonry in progress. Plumbing, electrical and mechanical rough-ins in progress, site drainage. Window install in progress. Exterior damp roofing, insulation in progress. Brick starting.
RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) Aerial (Dec. 22, 2015)
RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) Front Entry
RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) (Jan. 11, 2016)
ADDITIONS AND RENOVATIONS
PROJECTS IN PROGRESS
ELEMENTARY SCHOOL ISMS – (Integrated Security Mgmt System)
Consultant – Combs Consulting Group NISD Project Manager – Charles Pereira Contractor – Convergint Technologies Construction Contract Award – $13,422,826.29 Total Change Orders to Date - $661,683.79 Adjusted Construction Contract Amount - $14,084,510.08 Total Construction Contract Completed - $13,787,503.30 Balance to Finish Construction Contract - $297,006.78 Notice to Proceed – January 23, 2013 Original Construction Completion – May 31, 2014 Revised Construction Completion – November 11, 2015 Contract Percentage Completion – 98%
ELEMENTARY SCHOOL ISMS – (Integrated Security Mgmt System)
Project Scope – Furnish and install all new interior and exterior security
surveillance cameras, with access control electrified hardware and security alarm disarm keypads. Connect and integrate the existing intrusion alarm devices, motion sensors and glass break sensors at all existing campuses.
75 Elementary School Campuses have Substantial Completion Certificates. 2 Additional Middle School Campuses have Substantial Completion
Certificates. 75 Elementary School Campuses have ISMS software training completed. 2 Additional Middle School Campuses have ISMS software training
completed. 75 Elementary campuses have Post Warranty Documents completed. 2 Additional Middle school campuses have Post Warranty Documents
completed.
RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – D.L. Bandy Contract Amount - $4,782,000.00 Construction Period – May 15, 2015 – August 1, 2016 (46% Complete) Project Scope – New Science Classroom Addition and Renovation.
Site work and underground site utilities in progress. Exterior and interior CMU walls completed. Plumbing, electrical and HVAC rough-in in progress. Window install in progress. Brick veneer in progress. Interior painting in progress.
RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (Perspective)
RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (Front Entry – Final Scheme)
RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (1st Floor Plan)
RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (2nd Floor Plan)
RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (January 8, 2016)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Thomas Curiel Contractor – Guido Brothers Construction Contract Amount - $3,198,000.00 Construction Period – June 2015 – June 2016 (32% Complete) Project Scope – New Classroom Addition
Pilot holes drilled for addition foundation. Piers are completed. Plumbing rough-in underway. Foundation columns completed.
LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Site Plan)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION (1st Floor Plan)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION (2nd Floor Plan)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Elevation)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION (January 11, 2016)
2014 BOND PROJECTS
IN
BID/DESIGN PHASES
KALLISON RANCH #2 ES (ELLISON ES PROTOTYPE)
Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – Guido Construction Construction Budget - $22,500,000.00 Tentative Construction Period – May 7, 2016 – May 26, 2017 Project Scope – Construction of an 800 Student Elementary School
KALLISON RANCH #2 ES - (Ellison ES Prototype) Front Entrance
CHILD NUTRITION WAREHOUSE - Warehouse Renovation
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $3,000,000.00 Tentative Construction Period – April 4, 2016 – October, 2016 Project Scope – Warehouse Renovation
CHILD NUTRITION WAREHOUSE - Warehouse Renovation (Aerial View)
ALLEN ES CLASSROOM - ADDITION/ADA/WINDOW UPGRADES
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $6,230,000.00 Tentative Construction Period – March 7, 2016 – November 7, 2016 Project Scope – Classroom Addition/ADA/Window Upgrades
Proposals in progress.
ALLEN ES CLASSROOM - (Rendering of Site and Floor Plans)
ALLEN ES CLASSROOM - (Rendering of Floor Plan, Elevation and Perspectives)
HOLMES HS FINE ARTS - UPGRADE
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – James Berg Contractor – TBD Construction Budget - $14,000,000.00 Tentative Construction Period – TBD Project Scope – Fine Arts Building Replacement
THORNTON ES - MUSIC ROOM ADDITION
Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – James Berg Contractor – TBD Construction Budget - $300,000.00 Tentative Construction Period – June 6, 2016 – August 5, 2016 Project Scope – Music Room Addition
THORNTON ES - MUSIC ROOM ADDITION (Rendering of Site Plan)
THORNTON ES - MUSIC ROOM ADDITION (Rendering of Music Room Addition)
ZACHRY MS BUS CANOPY MODIFICATIONS
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – TBD Construction Budget - $1,100,000.00 Tentative Construction Period – February 8, 2016 – July 1, 2016 Project Scope – Proposal Evaluations in Progress
Board approval recommendation scheduled for January.
ALE Upgrades at CLARK HS, JAY HS & PEASE MS & ESPARZA ES – Library Addition
Architect – O’Connell Robertson Project Architect – Chris Narendorf NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $1,125,000.00 and $880,000.00 Tentative Construction Period – March 4, 2016 – August 5, 2016 Project Scope – Upgrades of Existing ALE Classrooms and
Library Addition for Esparza ES Bid Drawings To Be Issued in January.
GLENOAKS ELEMENTARY - Administration Upgrades
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $3,750,000.00 Tentative Construction Period – March 14, 2016 – March 3, 2017 Project Scope – Administration Upgrades
GLENOAKS ELEMENTARY - (Rendering of Front Elevation)
CODY ES & LEON VALLEY ELEMENTARY - (CAFE & KITCHEN RENOVATIONS)
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Tom Curiel Contractor – TBD Construction Budget - $3,500,000.00 Tentative Construction Period – February 15, 2016 – August 8, 2016 Project Scope – Renovations to Cafeteria and Kitchen
Proposals in Progress.
2016 SECURITY LOBBIES - LOCKE HILL ES, THORNTON ES, CARLOS COON ES, LEON VALLEY ES, POWELL ES, MICHAEL ES, MARY HULL ES AND CABLE ES
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $480,000.00 Tentative Construction Period – February 1, 2016 – August 1, 2016 Project Scope – New Security Lobby for (10) Elementary Schools
NORTHSIDE ACTIVITY CENTER RENOVATIONS
Architect – Richard Sanchez Architects, Inc. Project Architect – Richard Sanchez NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - TBD Tentative Construction Period – April 4, 2016 – March 1, 2017 Project Scope – Addition
Program Phase
PAUL TAYLOR FIELD HOUSE RENOVATIONS
Architect – Garza Bomberger Architects Project Architect – Roy Lewis NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - TBD Tentative Construction Period – April 2016 – November 2016 Project Scope – ADA Interior/Exterior Renovations
Schematic Design Phase
2016 GROWTH & IMPROVEMENT
HARDIN SOCCER COMPLEX - UPGRADES
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - TBD Tentative Construction Period – February 1, 2016 – July 5, 2016 Project Scope – Replacement of existing ticket collection, concessions
and officials trailer with a building. Contractor evaluation complete. Board approval recommendation scheduled for January.
2016 ATHLETIC AREA UPGRADES (JAY HS, CLARK HS, JONES MS & ROSS MS)
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - TBD Tentative Construction Period – May 30, 2016 – August 8, 2016 Project Scope – Installation of Athletic Storage Units and Interior
Renovations. Site Verifications in progress. CDs in progress.
2016 CTE RENOVATIONS - (CLARK HS HOLMES HS, & TAFT HS)
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Jim Berg Contractor – TBD Construction Period – TBD Tentative Construction Period – May 2, 2016 – August 12, 2016 Project Scope – Renovations to Cosmetology at Holmes and Taft, Health
Science Technology at Clark, Residential Kitchen at Clark and Engineering Lab at Taft HS.
ROOFING PROJECTS
BOONE ELEMENTARY SCHOOL – ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – TBD Budget – $365,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing
CABLE ELEMENTARY SCHOOL – ROOFING PROJECT
Roofing Consultant – Austech Engineering Contractor – TBD Budget – $160,000.00 Construction Period – June – August 2016 Project Scope – Roof Repairs & Waterproofing
HOWSMAN ELEMENTARY SCHOOL – ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – TBD Budget – $740,000.00 Construction Period – June – August 2016 Project Scope – Roof Replacement & Waterproofing
ANSON JONES MIDDLE SCHOOL – ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $165,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing
65% Review
LEWIS ELEMENTARY SCHOOL - ROOFING PROJECT
Roofing Consultant – Austech Contractor – TBD Budget – $200,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing
LINTON ELEMENTARY SCHOOL - ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – TBD Budget – $180,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing
MARY HULL ELEMENTARY SCHOOL – ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $70,000.00 Construction Period – June – August 2016 Project Scope – Roof Replacement & Waterproofing
65% Review
MAY ELEMENTARY SCHOOL - ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $2,175,000.00 Construction Period – June – October 2016 Project Scope – Roof Replacement & Waterproofing
Board Approval Scheduled for January 19, 2016
TAFT HIGH SCHOOL – ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $1,885,000.00 Construction Period – June – December 2016 Project Scope – Roof Replacement & Waterproofing
Board Approval Scheduled for January 19, 2016
PAUL TAYLOR FIELD HOUSE – ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $525,000.00 Construction Period – June – August 2016 Project Scope – Roof Replacement & Waterproofing
Board Approval Scheduled for January 19, 2016
VILLARREAL ELEMENTARY SCHOOL – ROOFING PROJECT
Roofing Consultant – Austech Contractor – TBD Budget – $110,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing